Status and Installation Plan for the Spectrometer Solenoid Magnets Steve Virostek Lawrence Berkeley National Lab MICE CM17 @ CERN February 24, 2007

Status and Installation Plan for the Spectrometer Solenoid Magnets

Embed Size (px)

DESCRIPTION

Status and Installation Plan for the Spectrometer Solenoid Magnets. Steve Virostek Lawrence Berkeley National Lab. MICE CM17 @ CERN February 24, 2007. MICE Cooling Channel Layout. Spectrometer Solenoid 1. Spectrometer Solenoid 2. Spectrometer Solenoid Overview. - PowerPoint PPT Presentation

Citation preview

Page 1: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status and Installation Plan for the Spectrometer

Solenoid Magnets

Steve VirostekLawrence Berkeley National Lab

MICE CM17 @ CERN February 24, 2007

Page 2: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 2

Steve Virostek - - - Lawrence Berkeley National Laboratory

MICE Cooling Channel Layout

SpectrometerSolenoid 1

SpectrometerSolenoid 2

Page 3: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 3

Steve Virostek - - - Lawrence Berkeley National Laboratory

Spectrometer Solenoid Overview

•Order for two spectrometer solenoid magnets was placed with Wang NMR by LBNL in June ‘06

•Design review was held by Wang on Sept 6, 2006-Complete design package book provided to LBNL

•Detailed magnet design is complete and fabrication is well under way

•First magnet shipment expected by Sep 07

•Second magnet to follow ~6 weeks later

Page 4: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 4

Steve Virostek - - - Lawrence Berkeley National Laboratory

Spectrometer Solenoid Fabrication Update

•First machined coil former delivered to Wang

•Preparation for coil winding is under way

•First two cryocoolers to arrive at Wang on Feb 28th, two additional to follow two weeks later

•Quench protection assemblies are near complete

•Winding of fiberglass cold mass support bands will begin in early March

•50 A HTC procured, 300 A leads coming next week

•Magnet instrumentation is on order

Page 5: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 5

Steve Virostek - - - Lawrence Berkeley National Laboratory

He Filler Neck

Lead Neck

Cold Mass Support

PMT Iron Shield

Space for Radiation Shield Support Stand

Cooler Neck

Page 6: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 6

Steve Virostek - - - Lawrence Berkeley National Laboratory

Lead Neck

He Gas Pipe

4.2 K Coolers

Condenser Tank

Liquid Pipe

Cold Mass

4K End

60K Intercept

300K End

Cold Mass Support

Page 7: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 7

Steve Virostek - - - Lawrence Berkeley National Laboratory

300 K Support End

60 K Support Intercept

Support Band

4 K Support End

Cold Mass Assembly

Cold Mass with 50 Ton Support System

Page 8: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 8

Steve Virostek - - - Lawrence Berkeley National Laboratory

Passive Quench Protection Space

Center Coil

Match Coil 1

End Coil 1

Match Coil 2

Coil Cover

Liquid Helium Space

490 mm

690 mm

2544 mm

Coil Spacer

Spectrometer Solenoid Cold Mass

End Coil 2

Page 9: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 9

Steve Virostek - - - Lawrence Berkeley National Laboratory

•Single piece 6061-T6 aluminum coil former

•Each layer wet wound using Stycast 2850 FT

•2.5 mil thick fiberglass between winding layers

•Passive quench protection will be provided by a system of diodes & resistors

•Aluminum coil banding will provide hoop force support and ensure coils are tight after cooldown

•Conductor joints are to be lapped by at least 24” to minimize the I2R losses

Design Overview (coil construction)

Page 10: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 10

Steve Virostek - - - Lawrence Berkeley National Laboratory

First Completed Coil Winding Form

Page 11: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 11

Steve Virostek - - - Lawrence Berkeley National Laboratory

First Completed Coil Winding Form

Page 12: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 12

Steve Virostek - - - Lawrence Berkeley National Laboratory

First Completed Coil Winding Form

Page 13: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 13

Steve Virostek - - - Lawrence Berkeley National Laboratory

Vacuum Leak Check of Coil Winding Form

Page 14: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 14

Steve Virostek - - - Lawrence Berkeley National Laboratory

Vacuum Leak Check of Coil Winding Form

Page 15: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 15

Steve Virostek - - - Lawrence Berkeley National Laboratory

Vacuum Leak Check of Coil Winding Form

Page 16: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 16

Steve Virostek - - - Lawrence Berkeley National Laboratory

G-10 Material for Coil Side Insulation

Page 17: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 17

Steve Virostek - - - Lawrence Berkeley National Laboratory

Coil Winding Apparatus

Page 18: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 18

Steve Virostek - - - Lawrence Berkeley National Laboratory

Coil Winding Apparatus

Page 19: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 19

Steve Virostek - - - Lawrence Berkeley National Laboratory

PSPower Supply ±10 V, 300 A

PS PS

Power Supply ±5 V, ±50 A

50 Amp Leads

300 Amp Leads

300 Amp Leads

A B C D E FG H

Match 1 Match 2 End 1 Center End 2

PSPS

Quench Diodes

Quench Protection & Power Supply Hookup

Page 20: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 20

Steve Virostek - - - Lawrence Berkeley National Laboratory

Quench Protection Diodes and Resistors

Page 21: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 21

Steve Virostek - - - Lawrence Berkeley National Laboratory

Quench Protection Diodes and Resistors

Page 22: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 22

Steve Virostek - - - Lawrence Berkeley National Laboratory

Quench Protection Diodes

Page 23: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 23

Steve Virostek - - - Lawrence Berkeley National Laboratory

Quench Protection Resistors

Page 24: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 24

Steve Virostek - - - Lawrence Berkeley National Laboratory

Quench Protection Assembly Parts

Page 25: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 25

Steve Virostek - - - Lawrence Berkeley National Laboratory

50 Amp High TC Leads

Page 26: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 26

Steve Virostek - - - Lawrence Berkeley National Laboratory

Winding Form for Cold Mass Support Bands

Page 27: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 27

Steve Virostek - - - Lawrence Berkeley National Laboratory

Example of a Cold Mass Support Band

Page 28: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 28

Steve Virostek - - - Lawrence Berkeley National Laboratory

Example of a Quench Protection Assembly

Page 29: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 29

Steve Virostek - - - Lawrence Berkeley National Laboratory

Example of a Cold Mass Support System

Page 30: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 30

Steve Virostek - - - Lawrence Berkeley National Laboratory

•Two 1.5 W PT415’s will cool magnets to 45 K (1st stage) & 3.8 K (2nd stage)

•~0.05 T field @ cooler rotary valve motors (no iron shielding needed)

•Up to three coolers per magnet can be installed and removed without breaking cryostat vacuum

•Four units ordered by IIT – 1st two to arrive Feb 28th, 2nd two in ~2 weeks

Pulse Tube Cryocoolers

PT415 Pulse Tube

Page 31: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 31

Steve Virostek - - - Lawrence Berkeley National Laboratory

Magnet Power Supplies

•Three power supplies of +300 A at ±10 V for the center and two match coils (shared for 2 magnets)

•Four power supplies of ±50 A (may need 2 @ 60 A) at ±5 V for the two end coils (2 per magnet)

•Power supply specification is nearly complete-Resolve issue of whether quick discharge circuit is needed-Address computer interface question-Settle on quantities (testing, operation @ RAL, spares)

•3 month lead time – place order soon after CM17

Page 32: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 32

Steve Virostek - - - Lawrence Berkeley National Laboratory

Updated Schedule Summary

Page 33: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 33

Steve Virostek - - - Lawrence Berkeley National Laboratory

Installation Plan and Issues

•Integration discussions ongoing with RAL

•Module connection to rail system resolved

•Required lifting features being finalized

•Requirements for transfer through door of MICE hall @ RAL established

•Flange sealing options being discussed

•Vacuum pumping requirements defined

Page 34: Status and Installation Plan for the Spectrometer Solenoid Magnets

Status & Installation of the Spectrometer Solenoids

Page 34

Steve Virostek - - - Lawrence Berkeley National Laboratory

•Detailed magnet design is complete

•1st coil former at Wang & ready for winding

•50 A HTC leads at vendor (300 A to follow)

•Two cryocoolers to arrive on Feb 28

•P.S. spec is nearly complete – order ASAP

•Expect 1st magnet complete by Sep 07

•Second magnet to follow ~6 weeks later

Summary