MCHS Measure BB Campus Improvements Manhattan Beach Unified School District
Status Report – November 2011
table of contents
Executive Summary .................................................... 1.1 Project Overview 1.2 Summary of Progress
2
Project Schedule ......................................................... 2.1 Overview 2.2 Schedule
3
Financials ...................................................................... 3.1 Overview
4
Mira Costa High School Expansion & Modernization STATUS REPORT November 2011
executive summary
1.1 Project Overview The Manhattan Beach Unified School District (MBUSD), through the passage of a local bond measure, has elected to expand and renovate its only existing high school campus, Mira Costa High School. Mira Costa High School opened in 1950 and currently has an enrollment of approximately 2,400 students.
In 2008, the City of Manhattan Beach passed Measure BB which was aimed at attracting and retaining quality teachers, improving instruction and ensuring college and career readiness for local students by replacing deteriorated classrooms with new classrooms and science labs, upgrading technology, replacing deteriorated plumbing/restrooms and improving safety and energy-efficiency.
The expansion and renovation project involves three distinct construction phases: Addition of a Math/Science Building, Modernization of the “Finger Buildings”, and the Modernization of the Performing Arts Buildings and Quad Development.
1.2 Summary of Progress Notice to proceed issued November 7, 2011. Subcontract awards complete. Phase 1 Math/Science building commenced. Temporary facilities: Mobilization, temporary fencing, initial storm water prevention plan, temporary offices, and temporary service activities complete. Initial sitework: Mark removals and protection items complete. Site demolition commenced.
2
Mira Costa High School Expansion & Modernization STATUS REPORT November 2011
project schedule 2.1 Overview
The project began construction in November and on schedule to finish in December 2014. See the attached project schedule.
2.2 Schedule
Below are the critical milestone dates as set forth by the overall schedule.
2011 Nov 7 Contract awards Nov 7 Start Construction Phase I – Math/Science Building 2013 Aug 19 Substantial Completion Construction Phase I – M/S Building Sep 6 Start Construction Phase II – Modernizations Nov 13 Substantial Completion Construction Phase II Nov 18 Start Construction Phase III – New Buildings, Modernizations &
Central Quad
2014 December 31 Completion of Construction Phase III
3
Mira Costa High School Expansion & Modernization STATUS REPORT November 2011
4
financials
3.1 Overview
Initial
LLB Contractor initial committed costs are $45,800,193. These costs are made up as follows (including GC Fee):
Subcontracts $ 41,019,711 General Conditions $ 4,211,477 Contingency $ 569,005 Total $ 45,800,193
Changes
Original Costs $ 45,800,193 Change Orders $ 0 Total $ 45,800,193
Billings
Scheduled Value $ 45,800,193 Billed To Date $ 623,721 Total Balance $ 45,176,481
See the attached costs status summary reports.
TENNANT IMPROVEMENT PAYMENTLINE ITEM BREAKDOWN
Project:Application No.: 1 Period From: 11/1/2011
Application Date: 11/30/2011 Period To: 11/30/2011Bernards Job No.: 1466
PHASE 1 Invoice No.: 15260
Harley Ellis Devereaux Project #2009-0001-000A B C D E F G H I
LINE DESCRIPTION OF WORK SCHEDULED WORK COMPLETED TOTAL % LEASE PAYMENT BALANCENO. VALUE FROM PREVIOUS THIS COMPLETED (F/C) 10% TO FINISH
APPLICATION PERIOD TO DATE(D+E) (C-F+H)
Division 1 - GENERAL REQUIREMENTS1 Bonds 350,852 350,852 350,852 100% 35,085 35,0852 Preconstruction 246,970 246,970 246,970 100% 24,697 24,6973 General Conditions 2,092,117 95,191 95,191 5% 9,519 2,006,445
Division 2 - SITE CONSTRUCTION4 Surveying 45,069 0 0 0% 0 45,0695 Shoring 210,997 0 0 0% 0 210,9976 Demolition & Earthwork 359,975 0 0 0% 0 359,9757 Site Concrete 711,192 0 0 0% 0 711,1928 Asphalt Paving 262,568 0 0 0% 0 262,5689 Site Utilities 415,793 0 0 0% 0 415,793
MCHS Measure BB Campus Improvements
9 Site Utilities 415,793 0 0 0% 0 415,7939 Pavement Joint Sealants 22,430 0 0 0% 0 22,43010 Playground Surface System 4,628 0 0 0% 0 4,62811 Irrigation Systems 82,072 0 0 0% 0 82,07212 Chain Link Fences and Gates 22,149 0 0 0% 0 22,14913 Ornamental Fences and Gates 131,498 0 0 0% 0 131,49814 Landscape Planting 77,795 0 0 0% 0 77,795
Division 3 - CONCRETE15 Concrete Reinforcement 400,811 0 0 0% 0 400,81116 Cast-In-Place Concrete 1,894,239 0 0 0% 0 1,894,23917 Precast Concrete Stair Treads 66,853 0 0 0% 0 66,853
Division 5 - METALS19 Structural Steel 1,933,925 0 0 0% 0 1,933,92520 Metal Decking 286,952 0 0 0% 0 286,95221 Load-Bearing Metal Studs 712,010 0 0 0% 0 712,01022 Metal Fabrications 1,135,428 0 0 0% 0 1,135,428
Division 6 - WOOD AND PLASTICS24 Rough Carpentry 5,143 0 0 0% 0 5,143
25 Architectural Woodwork 142,801 0 0 0% 0 142,801
Division 7 - THERM & MOIST PROTECTION28 Waterproofing Membrane 3,667 0 0 0% 0 3,66729 Sheet Waterproofing 26,856 0 0 0% 0 26,85630 Rubberized Asphalt Waterproofing 167,532 0 0 0% 0 167,53231 Vertical Fluid Applied Coatings 12,342 0 0 0% 0 12,34232 Building Insulation 183,356 0 0 0% 0 183,35633 Exterior Screen Walls 20,152 0 0 0% 0 20,15234 Thermoplastic Membrane Roofing 234,498 0 0 0% 0 234,49835 Sheet Metal 183,396 0 0 0% 0 183,39636 Sprayed Fire Resistive Materials 81,457 0 0 0% 0 81,45737 Intumescent Fireproofing 80,223 0 0 0% 0 80,22338 Through Penetration Firestop Systems 3,600 0 0 0% 0 3,60039 Fire-Resistive Joint Systems 10,285 0 0 0% 0 10,28540 Joint Sealants 38,291 0 0 0% 0 38,291
Division 8 - DOORS AND WINDOWS39 Steel Doors and Frames 87,807 0 0 0% 0 87,80741 Wood Doors 3,501 0 0 0% 0 3,50142 Door & Frame Installation 59,744 0 0 0% 0 59,74443 Elevator Door Smoke Containment 18,557 0 0 0% 0 18,55744 Access Doors & Frames 5,143 0 0 0% 0 5,14345 Horizontal Fire Shuuters 240,864 0 0 0% 0 240,86446 Push Up Fire Doors 190,273 0 0 0% 0 190,27347 Coiling Fire Doors w/ Egress Door 59,628 0 0 0% 0 59,62848 Sectional Overhead Doors 79,184 0 0 0% 0 79,18448 Sectional Overhead Doors 79,184 0 0 0% 0 79,18449 Aluminum Framed Storefront 243,669 0 0 0% 0 243,66950 Awning & Hopper Windows 94,416 0 0 0% 0 94,41651 Casement Windows 92,359 0 0 0% 0 92,35952 Finish Hardware 122,353 0 0 0% 0 122,35353 Glazing 334,091 0 0 0% 0 334,09154 Light Shelves 80,017 0 0 0% 0 80,01755 Sloped Glazing Systems 272,553 0 0 0% 0 272,553
Division 9 - FINISHES55 Non-Load Bearing Steel Framing 474,673 0 0 0% 0 474,67356 Portland Cement Plaster 454,597 0 0 0% 0 454,59757 Gypsum Board 320,609 0 0 0% 0 320,60958 Ceramic Tile 119,516 0 0 0% 0 119,51659 Acoustical Ceilings 244,783 0 0 0% 0 244,78360 Resilient Flooring 164,853 0 0 0% 0 164,85361 Carpet Tiles 53,955 0 0 0% 0 53,95562 Tackable Wallcovering 20,570 0 0 0% 0 20,57063 Fiberglass Reinforced Panels 2,571 0 0 0% 0 2,57164 Slip Resistant Epoxy Coatings 4,114 0 0 0% 0 4,11465 Exterior Painting 43,197 0 0 0% 0 43,197
66 Interior Painting 88,451 0 0 0% 0 88,45167 High-Performance Coatings 28,798 0 0 0% 0 28,79868 Intumescent Paints 14,399 0 0 0% 0 14,39969 Graffiti Resistant Coatings 16,456 0 0 0% 0 16,456
Division 10 - SPECIALTIES70 Visual Display Surfaces 128,563 0 0 0% 0 128,56371 Interactive Whiteboards 72,427 0 0 0% 0 72,42772 Toilet Compartments 29,621 0 0 0% 0 29,62173 Signage 21,431 0 0 0% 0 21,43174 Fire Extinguishers and Cabinets 6,843 0 0 0% 0 6,84375 Operable Panel Partitions 14,080 0 0 0% 0 14,08076 Exterior Sun Control Devices 129,180 0 0 0% 0 129,18077 Toilet and Janitorial Accessories 16,970 0 0 0% 0 16,970
Division 11 - EQUIPMENT78 Audio Visual Equipment 317,016 0 0 0% 0 317,01679 Miscellaneous Laboratory Equipment 55,333 0 0 0% 0 55,33380 Laboratory Fume Hoods 87,511 0 0 0% 0 87,511
Division 12 - FURNISHINGS81 Laboratory Casework 821,219 0 0 0% 0 821,21982 Casework Countertops 27,096 0 0 0% 0 27,096
Division 13 - SPECIAL CONSTRUCTION83 Fire Sprinkler System 121,877 0 0 0% 0 121,87783 Fire Sprinkler System 121,877 0 0 0% 0 121,877
Division 14 - CONVEYING SYSTEMS84 Hydraulic Elevators 119,306 0 0 0% 0 119,306
Division 15 - MECHANICAL85 Basic Mechanical Materials 39,597 0 0 0% 0 39,59786 Basic Mechanical Supports 35,998 0 0 0% 0 35,99887 Basic Mechanical Vibration and Seismic 32,912 0 0 0% 0 32,91288 Basic Mechanical Identification 2,571 0 0 0% 0 2,57189 Basic Mechanical Insulation 77,138 0 0 0% 0 77,13890 Basic Mechanical General Duty Valves 24,170 0 0 0% 0 24,17091 Basic Mechanical Expansion Compensation 3,600 0 0 0% 0 3,60092 Plumbing Systems 1,019,244 0 0 0% 0 1,019,24493 Hydronic Piping 123,420 0 0 0% 0 123,42094 Refrigerant Piping 12,856 0 0 0% 0 12,85695 Natural Gas 138,848 0 0 0% 0 138,84896 Hydronic Pumps 35,998 0 0 0% 0 35,99897 Sewage Pumps 41,140 0 0 0% 0 41,14098 Plumbing Fixtures 113,135 0 0 0% 0 113,13599 Domestic Water Heaters 35,998 0 0 0% 0 35,998
100 Condensing Boilers 30,855 0 0 0% 0 30,855101 Water Treatment System 3,600 0 0 0% 0 3,600102 Custom Packaged DX Units 462,825 0 0 0% 0 462,825103 Split System AC Units 18,513 0 0 0% 0 18,513104 Metal Ducts 493,680 0 0 0% 0 493,680105 Laboratory Exhaust Ductwork 267,410 0 0 0% 0 267,410106 Duct Accessories 35,998 0 0 0% 0 35,998107 Laboratory Exhaust Fans 87,423 0 0 0% 0 87,423108 Power & Gravity Ventilators 4,628 0 0 0% 0 4,628109 Air Terminal Units 25,713 0 0 0% 0 25,713110 Air Inlets & Outlets 102,850 0 0 0% 0 102,850111 Air Duct Cleaning 5,657 0 0 0% 0 5,657112 Building Management System 334,263 0 0 0% 0 334,263113 Laboratory Control Systems 205,700 0 0 0% 0 205,700114 Testing, Adjusting, & Balancing 17,999 0 0 0% 0 17,999115 HVAC Commisioning 25,713 0 0 0% 0 25,713
Division 16 - ELECTRICAL116 Short Circuit & Protective Device Study 6,171 0 0 0% 0 6,171117 Grounding and Bonding 37,026 0 0 0% 0 37,026118 Electrical Hangers & Supports 87,423 0 0 0% 0 87,423119 Electrical Identification 12,342 0 0 0% 0 12,342120 Surface Metal Raceway 56,568 0 0 0% 0 56,568121 Electrical Wire & Cable 262,268 0 0 0% 0 262,268122 Raceways & Boxes 866,083 0 0 0% 0 866,083123 Cabinets & Enclosures 66,853 0 0 0% 0 66,853124 Wiring Devices 46,283 0 0 0% 0 46,283124 Wiring Devices 46,283 0 0 0% 0 46,283125 Transient Voltage Surge Suppression 30,855 0 0 0% 0 30,855126 Enclosed Switches 32,912 0 0 0% 0 32,912127 Enclosed Contactors 32,912 0 0 0% 0 32,912128 Switchboards 32,912 0 0 0% 0 32,912129 Panelboards 32,912 0 0 0% 0 32,912130 Transformers 32,912 0 0 0% 0 32,912131 Fuses 5,143 0 0 0% 0 5,143132 Interior Luminaires 594,473 0 0 0% 0 594,473133 Exterior Luminaires 63,767 0 0 0% 0 63,767134 Fire Alarm System 164,560 0 0 0% 0 164,560135 Master Clock System 18,513 0 0 0% 0 18,513136 Premise Wiring 154,275 0 0 0% 0 154,275137 Intrusion Detection System 19,542 0 0 0% 0 19,542138 Public Address System 54,511 0 0 0% 0 54,511139 Assistive Listening System 6,480 0 0 0% 0 6,480
Contingency140 Contingency Funds Available 569,005 0 0 0% 0 569,005
Subtotals 25,810,236 0 693,013 693,013 3% 69,301 25,186,524
0 0 0 0% 0 0
0 0 0 0 0 0
PHASE 1 - TOTALS 25,810,236 0 693,013 693,013 3% 69,301 25,186,524
TENNANT IMPROVEMENT PAYMENTLINE ITEM BREAKDOWN
Project:Application No.: 1 Period From: 11/1/2011
Application Date: 11/30/2011 Period To: 11/30/2011Bernards Job No.: 1466
PHASE 2 Invoice No.: 15260
Harley Ellis Devereaux Project #2009-0001-000A B C D E F G H I
LINE DESCRIPTION OF WORK SCHEDULED WORK COMPLETED TOTAL % LEASE PAYMENT BALANCE
NO. VALUE FROM PREVIOUS THIS COMPLETED (F/C) 10% TO FINISHAPPLICATION PERIOD TO DATE
(D+E) (C-F+H)Division 1 - GENERAL REQUIREMENTS
1 General Conditions 380,385 0 0 0% 0 380,385
Division 2 - SITE CONSTRUCTION2 Surveying 11,267 0 0 0% 0 11,2673 Demolition & Earthwork 359,975 0 0 0% 0 359,9754 Site Concrte 132,472 0 0 0% 0 132,4725 Asphalt Paving 10,285 0 0 0% 0 10,2855 Site Utilities 44,115 0 0 0% 0 44,1157 Pavement Joint Sealants 10,636 0 0 0% 0 10,6368 Porous Unit Paving 23,141 0 0 0% 0 23,1419 Irrigation Systems 15,795 0 0 0% 0 15,79510 O t l F d G t 9 205 0 0 0% 0 9 205
MCHS Measure BB Campus Improvements
10 Ornamental Fences and Gates 9,205 0 0 0% 0 9,20511 Landscape Planting 35,979 0 0 0% 0 35,979
Division 3 - CONCRETE12 Concrete Reinforcement 2,859 0 0 0% 0 2,85913 Cast-In-Place Concrete 13,583 0 0 0% 0 13,583
Division 4 - MASONRY14 Concrete Unit Masonry 34,969 0 0 0% 0 34,969
Division 5 - METALS15 Structural Steel 28,798 0 0 0% 0 28,79816 Metal Fabrications 15,428 0 0 0% 0 15,428
Division 6 - WOOD AND PLASTICS17 Architectural Woodwork 356,478 0 0 0% 0 356,478
Division 7 - THERM & MOIST PROTECTION18 Building Insulation 61,437 0 0 0% 0 61,43719 Exterior Screen Walls 6,718 0 0 0% 0 6,718
20 Fluid Applied Roofing 24,684 0 0 0% 0 24,68421 Thermoplastic Membrane Roofing 426,828 0 0 0% 0 426,82822 Through Penetration Firestop Systems 3,600 0 0 0% 0 3,60023 Sheet Metal 10,760 0 0 0% 0 10,76024 Joint Sealants 4,865 0 0 0% 0 4,865
Division 8 - DOORS AND WINDOWS26 Steel Doors and Frames 9,469 0 0 0% 0 9,46927 Wood Doors 9,507 0 0 0% 0 9,50728 Door & Frame Installation 18,036 0 0 0% 0 18,03629 Access Doors & Frames 5,143 0 0 0% 0 5,14330 Awning & Hopper Windows 855,058 0 0 0% 0 855,05831 Finish Hardware 36,938 0 0 0% 0 36,93832 Glazing 208,885 0 0 0% 0 208,885
Division 9 - FINISHES33 Non-Load Bearing Steel Framing 128,835 0 0 0% 0 128,83534 Portland Cement Plaster 15,428 0 0 0% 0 15,42835 Gypsum Board 35,998 0 0 0% 0 35,99837 Acoustical Ceilings 275,638 0 0 0% 0 275,63838 Resilient Flooring 100,042 0 0 0% 0 100,04239 Polyurethane Floor System 20,056 0 0 0% 0 20,05640 Carpet Tiles 98,201 0 0 0% 0 98,20141 Tackable Wallcovering 20,570 0 0 0% 0 20,57042 Exterior Painting 96,679 0 0 0% 0 96,67943 Interior Painting 106,964 0 0 0% 0 106,96444 High-Performance Coatings 14,399 0 0 0% 0 14,39944 High Performance Coatings 14,399 0 0 0% 0 14,399
Division 10 - SPECIALTIES45 Visual Display Surfaces 66,853 0 0 0% 0 66,85346 Interactive Whiteboards 80,187 0 0 0% 0 80,18747 Signage 8,746 0 0 0% 0 8,74649 Fire Extinguishers and Cabinets 1,710 0 0 0% 0 1,71050 Toilet and Janitorial Accessories 617 0 0 0% 0 617
Division 11 - EQUIPMENT51 Audio Visual Equipment 345,324 0 0 0% 0 345,324
Division 15 - MECHANICAL51 Basic Mechanical Materials 42,169 0 0 0% 0 42,16952 Basic Mechanical Hangers & Supports 12,856 0 0 0% 0 12,85652 Basic Mechanical Vibration and Seismic 25,713 0 0 0% 0 25,71353 Basic Mechanical Identification 2,571 0 0 0% 0 2,57154 Basic Mechanical Insulation 46,283 0 0 0% 0 46,28355 Plumbing Systems 151,190 0 0 0% 0 151,19057 Refrigerant Piping 10,285 0 0 0% 0 10,28558 Natural Gas 20,570 0 0 0% 0 20,570
59 Plumbing Fixtures 41,140 0 0 0% 0 41,14060 Water Heaters 2,057 0 0 0% 0 2,05761 Split System AC Units 128,563 0 0 0% 0 128,56362 Rooftop Units 51,425 0 0 0% 0 51,42563 Metal Ducts 82,280 0 0 0% 0 82,28064 Duct Accessories 25,713 0 0 0% 0 25,71365 Power & Gravity Ventilators 41,140 0 0 0% 0 41,14066 Air Terminal Units 17,485 0 0 0% 0 17,48567 Air Inlets & Outlets 10,285 0 0 0% 0 10,28568 Air Duct Cleaning 3,600 0 0 0% 0 3,60069 Building Management System 154,275 0 0 0% 0 154,27570 Testing, Adjusting, & Balancing 25,713 0 0 0% 0 25,71371 HVAC Commisioning 15,428 0 0 0% 0 15,428
Division 16 - ELECTRICAL72 Short Circuit & Protective Device Study 514 0 0 0% 0 51473 Grounding and Bonding 12,342 0 0 0% 0 12,34274 Electrical Hangers & Supports 34,969 0 0 0% 0 34,96975 Electrical Identification 6,685 0 0 0% 0 6,68576 Surface Metal Raceway 121,363 0 0 0% 0 121,36377 Electrical Wire & Cable 75,595 0 0 0% 0 75,59578 Raceways & Boxes 424,256 0 0 0% 0 424,25679 Cabinets & Enclosures 16,456 0 0 0% 0 16,45680 Wiring Devices 24,684 0 0 0% 0 24,68481 Panelboards 12,342 0 0 0% 0 12,34282 Fuses 2,571 0 0 0% 0 2,57183 Interior Luminaires 368,203 0 0 0% 0 368,20383 Interior Luminaires 368,203 0 0 0% 0 368,20384 Exterior Luminaires 22,627 0 0 0% 0 22,62785 Fire Alarm System 133,705 0 0 0% 0 133,70586 Master Clock System 1,440 0 0 0% 0 1,44087 Premise Wiring 54,511 0 0 0% 0 54,51188 Public Address System 41,140 0 0 0% 0 41,140
Subtotals 6,847,684 0 0 0 0% 0 6,847,684
0 0 0 0% 0 0
0 0 0 0 0% 0 0
PHASE 2 - TOTALS 6,847,684 0 0 0 0% 0 6,847,684
TENNANT IMPROVEMENT PAYMENTLINE ITEM BREAKDOWN
Project:Application No.: 1 Period From: 11/1/2011
Application Date: 11/30/2011 Period To: 11/30/2011Bernards Job No.: 1466
PHASE 3 Invoice No.: 15260
Harley Ellis Devereaux Project #2009-0001-000A B C D E F G H I
LINE DESCRIPTION OF WORK SCHEDULED WORK COMPLETED TOTAL % LEASE PAYMENT BALANCE
NO. VALUE FROM PREVIOUS THIS COMPLETED (F/C) 10% TO FINISHAPPLICATION PERIOD TO DATE
(D+E) (C-F+H)Division 1 - GENERAL REQUIREMENTS
1 General Conditions 1,141,154 0 0 0% 0 1,141,154
Division 2 - SITE CONSTRUCTION2 Surveying 24,144 0 0 0% 0 24,1443 Shoring 42,786 0 0 0% 0 42,7864 Demolition & Earthwork 866,306 0 0 0% 0 866,3065 Site Concrete Work 684,699 0 0 0% 0 684,6996 Asphalt Paving 66,853 0 0 0% 0 66,8537 Site Utilities 776,582 0 0 0% 0 776,5828 Pavement Joint Sealants 31,010 0 0 0% 0 31,0109 Irrigation Systems 65,843 0 0 0% 0 65,84310 O t l F d G t 16 158 0 0 0% 0 16 158
MCHS Measure BB Campus Improvements
10 Ornamental Fences and Gates 16,158 0 0 0% 0 16,15811 Landscape Planting 145,321 0 0 0% 0 145,321
Division 3 - CONCRETE12 Concrete Reinforcement 98,293 0 0 0% 0 98,29313 Cast-In-Place Concrete 464,873 0 0 0% 0 464,873
Division 4 - MASONRY14 Concrete Unit Masonry 720,392 0 0 0% 0 720,392
Division 5 - METALS15 Structural Steel 683,027 0 0 0% 0 683,02716 Metal Decking 66,853 0 0 0% 0 66,85317 Load-Bearing Metal Studs 341,614 0 0 0% 0 341,61418 Metal Fabrications 105,833 0 0 0% 0 105,833
Division 6 - WOOD AND PLASTICS19 Rough Carpentry 66,853 0 0 0% 0 66,85320 Interior Finish Carpentry 143,649 0 0 0% 0 143,64921 Wood Flooring 39,597 0 0 0% 0 39,597
22 Architectural Woodwork 51,834 0 0 0% 0 51,83423 Quartz Solid Surfacing 32,214 0 0 0% 0 32,214
Division 7 - THERM & MOIST PROTECTION24 Self Adhering Waterproofing 27,872 0 0 0% 0 27,87225 Building Insulation 25,090 0 0 0% 0 25,09026 Thermoplastic Membrane Roofing 177,104 0 0 0% 0 177,10427 Sheet Metal 10,760 0 0 0% 0 10,76028 Automatic Roof Fire Vents 34,083 0 0 0% 0 34,08329 Through Penetration Firestop Systems 3,600 0 0 0% 0 3,60030 Fire-Resistive Joint Systems 10,285 0 0 0% 0 10,28531 Joint Sealants 17,526 0 0 0% 0 17,526
Division 8 - DOORS AND WINDOWS33 Steel Doors and Frames 54,551 0 0 0% 0 54,55134 Aluminum Doors & Frames 10,902 0 0 0% 0 10,90235 Sliding Metal Doors 4,475 0 0 0% 0 4,47536 Wood Doors 5,505 0 0 0% 0 5,50537 Door & Frame Installation 34,944 0 0 0% 0 34,94438 Access Doors 5,143 0 0 0% 0 5,14339 Aluminum Framed Storefront 64,427 0 0 0% 0 64,42740 Awning & Hopper Windows 14,662 0 0 0% 0 14,66241 Double Hung Windows 2,571 0 0 0% 0 2,57142 Sound Control Windows 20,467 0 0 0% 0 20,46743 Double Sliding Windows 10,182 0 0 0% 0 10,18244 Finish Hardware 71,566 0 0 0% 0 71,56645 Glazing 57,493 0 0 0% 0 57,49345 Glazing 57,493 0 0 0% 0 57,49346 Mirrors 4,628 0 0 0% 0 4,62847 Glazed Aluminum Curtain Wall 52,003 0 0 0% 0 52,00348 Light Shelves 24,325 0 0 0% 0 24,32549 Exterior Sun Control Devices 37,755 0 0 0% 0 37,755
Division 9 - FINISHES50 Non-Load Bearing Steel Framing 227,743 0 0 0% 0 227,74351 Portland Cement Plaster 208,909 0 0 0% 0 208,90952 Gypsum Board 225,761 0 0 0% 0 225,76153 Ceramic Tile 43,851 0 0 0% 0 43,85154 Terrazzo Flooring 4,320 0 0 0% 0 4,32055 Acoustic Boards 24,684 0 0 0% 0 24,68456 Acoustical Ceilings 51,425 0 0 0% 0 51,42557 Resilient Flooring 45,089 0 0 0% 0 45,08958 Carpet Tiles 11,574 0 0 0% 0 11,57459 Tackable Wallcovering 2,571 0 0 0% 0 2,57160 Fiberglass Reinforced Panels 2,571 0 0 0% 0 2,57161 Sound Absorbing Fabric Panels 41,140 0 0 0% 0 41,14062 One Dimensional Sound Diffusers 149,647 0 0 0% 0 149,64763 Exterior Painting 45,254 0 0 0% 0 45,254
64 Interior Painting 58,110 0 0 0% 0 58,11065 High-Performance Coatings 9,257 0 0 0% 0 9,25766 Graffiti Resistant Coatings 8,228 0 0 0% 0 8,228
Division 10 - SPECIALTIES67 Visual Display Surfaces 10,285 0 0 0% 0 10,28568 Interactive Whiteboards 2,587 0 0 0% 0 2,58769 Toilet Compartments 6,582 0 0 0% 0 6,58270 Signage 12,313 0 0 0% 0 12,31371 Locker Room Benches 514 0 0 0% 0 51472 Fire Extinguishers and Cabinets 3,668 0 0 0% 0 3,66873 Toilet and Janitorial Accessories 5,746 0 0 0% 0 5,746
Division 11 - EQUIPMENT74 Production Rigging 524,637 0 0 0% 0 524,63775 Production Lighting Control & Fixtures 159,418 0 0 0% 0 159,41876 Production AV Systems 267,410 0 0 0% 0 267,41077 Audio Visual Equipment 15,929 0 0 0% 0 15,92978 Food Service Equipment 119,330 0 0 0% 0 119,330
Division 12 - FURNISHINGS79 Music Educational Storage 67,954 0 0 0% 0 67,95480 Stainless Steel Counter Tops 9,685 0 0 0% 0 9,68581 Telescopic and Fixed Seating 151,159 0 0 0% 0 151,159
Division 13 - SPECIAL CONSTRUCTION83 Fire Sprinkler System 121,877 0 0 0% 0 121,87783 Fire Sprinkler System 121,877 0 0 0% 0 121,877
Division 14 - CONVEYING SYSTEMS84 Limited Use Elevators 91,183 0 0 0% 0 91,183
Division 15 - MECHANICAL85 Basic Mechanical Materials 26,227 0 0 0% 0 26,22786 Basic Mechanical Supports 10,285 0 0 0% 0 10,28587 Basic Mechanical Vibration and Seismic 14,399 0 0 0% 0 14,39988 Basic Mechanical Identification 2,571 0 0 0% 0 2,57189 Basic Mechanical Insulation 34,969 0 0 0% 0 34,96990 Plumbing Systems 143,990 0 0 0% 0 143,99091 General Duty Valves 15,428 0 0 0% 0 15,42892 Hydronic Piping 20,570 0 0 0% 0 20,57093 Refrigerant Piping 10,285 0 0 0% 0 10,28594 Natural Gas 97,708 0 0 0% 0 97,70895 Hydronic Pumps 15,428 0 0 0% 0 15,42896 Plumbing Fixtures 61,710 0 0 0% 0 61,71097 Domestic Water Heaters 10,285 0 0 0% 0 10,28598 Condensing Boilers 20,570 0 0 0% 0 20,57099 Furnaces 20,570 0 0 0% 0 20,570
100 Water Treatment System 3,600 0 0 0% 0 3,600101 Custom Packaged DX Units 215,985 0 0 0% 0 215,985102 Split System AC Units 56,568 0 0 0% 0 56,568103 Metal Ducts 215,985 0 0 0% 0 215,985104 Duct Accessories 35,998 0 0 0% 0 35,998105 Sound Attenuators 3,600 0 0 0% 0 3,600106 Power & Gravity Ventilators 10,285 0 0 0% 0 10,285107 Air Terminal Units 10,285 0 0 0% 0 10,285108 Air Inlets & Outlets 41,140 0 0 0% 0 41,140109 Air Duct Cleaning 3,600 0 0 0% 0 3,600110 Building Management System 123,420 0 0 0% 0 123,420111 Testing, Adjusting, & Balancing 15,428 0 0 0% 0 15,428112 HVAC Commisioning 10,285 0 0 0% 0 10,285
Division 16 - ELECTRICAL116 Short Circuit & Protective Device Study 2,263 0 0 0% 0 2,263117 Grounding and Bonding 18,513 0 0 0% 0 18,513118 Production Systems Electrical Installation 32,912 0 0 0% 0 32,912119 Electrical Hangers & Supports 43,197 0 0 0% 0 43,197120 Electrical Identification 6,685 0 0 0% 0 6,685121 Electrical Wire & Cable 306,493 0 0 0% 0 306,493122 Electrical Conduit & Boxes 521,450 0 0 0% 0 521,450123 Cabinets & Enclosures 56,568 0 0 0% 0 56,568124 Wiring Devices 32,912 0 0 0% 0 32,912125 Transient Voltage Surge Suppression 15,428 0 0 0% 0 15,428126 Enclosed Switches 15,428 0 0 0% 0 15,428127 Enclosed Contactors 15,428 0 0 0% 0 15,428127 Enclosed Contactors 15,428 0 0 0% 0 15,428128 Switchboards 15,428 0 0 0% 0 15,428129 Panelboards 15,428 0 0 0% 0 15,428130 Transformers 15,428 0 0 0% 0 15,428131 Fuses 6,685 0 0 0% 0 6,685132 Interior Luminaires 264,325 0 0 0% 0 264,325133 Exterior Luminaires 95,651 0 0 0% 0 95,651134 Fire Alarm System 80,223 0 0 0% 0 80,223135 Master Clock System 4,114 0 0 0% 0 4,114136 Premise Wiring 63,767 0 0 0% 0 63,767137 Intrusion Detection System 17,999 0 0 0% 0 17,999138 Public Address System 56,568 0 0 0% 0 56,568
Base Contract Subtotals 13,142,273 0 0 0 0% 0 13,142,273
0 0 0 0% 0 0
0 0 0 0 0 0
PHASE 3 - TOTALS 13,142,273 0 0 0 0% 0 13,142,273
TENNANT IMPROVEMENT PAYMENTSUMMARY ALL PHASES
Project:Application No.: 1 Period From: 11/1/2011
Application Date: 11/30/2011 Period To: 11/30/2011Bernards Job No.: 1466
SUMMARY ALL PHASES Invoice No.: 15260
Harley Ellis Devereaux Project #2009-0001-000
SUMMARY
Phase 1 25,810,236$ 693,013$ 25,186,524$ Phase 2 6,847,684$ -$ 6,847,684$ Phase 3 13,142,273$ -$ 13,142,273$
Total All Phases 45,800,193$ 693,013$ 45,176,481$
Balance To Finish
Completed To Date
MCHS Measure BB Campus Improvements
GMP By Phase
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 1 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Measure BB Campus ImprovementsPhase 1 - Science/Math BuildingNotice to Proceed - MobilizationTemporary Facilities
Contractor's Staging Area
TF0000 Start 0 100 07NOV11A
TF0100 Mobilization 5 100 07NOV11A 07NOV11A
TF0200 Initial Temporary Fencing 5 100 07NOV11A 07NOV11A
TF0300 Initial SWPP Provisions 5 100 07NOV11A 14NOV11A
TF0400 Temp Office Preparation 5 100 07NOV11A 07NOV11A
TF0500 Trailers, Office Equip & Storage Bins 10 100 07NOV11A 11NOV11A
TF0600 Temporary Services 10 100 07NOV11A 14NOV11A
TF0700 Temporary Facilities Complete 0 100 28NOV11A
Initial SiteworkSite ImprovementsGrade LevelScience/Math BuildingStartIS0000 Start 0 100 21NOV11A
DemolitionIS1000 Mark Removals & Protection Items 5 60 21NOV11A 01DEC11 42
IS1010 Site Demolition 10 20 21NOV11A 13DEC11 42
IS1115 Temporary Shoring 10 0 10FEB12 23FEB12 2
IS1120 Temporary Sewer 15 0 24FEB12 15MAR12 2
IS1130 Remove Sanitary Sewer 10 0 16MAR12 29MAR12 2
IS1140 Remove Fire Water 10 0 30MAR12 12APR12 2
Underground Utilities - InteruptionsIS1150 UG Sanitary Sewer 15 0 10FEB12 01MAR12 2
IS1155 UG Storm Water 15 0 02MAR12 22MAR12 2
IS1160 UG Fire Water 15 0 23MAR12 12APR12 2
IS1170 UG Electric 15 0 13APR12 03MAY12 2
EarthworkIS1180 SWPP's Provisions 10 0 24FEB12 08MAR12 27
IS1185 Earthwork 15 0 13APR12 03MAY12 2
IS1190 Pad Fine Grade & Certification 5 0 04MAY12 10MAY12 2
2011 2012 2013 2014 2015
Start
Mobilization
Initial Temporary Fencing
Initial SWPP Provisions
Temp Office Preparation
Trailers, Office Equip & Storage Bins
Temporary Services
Temporary Facilities Complete
Start
Mark Removals & Protection Items
Site Demolition
Temporary Shoring
Temporary Sewer
Remove Sanitary Sewer
Remove Fire Water
UG Sanitary Sewer
UG Storm Water
UG Fire Water
UG Electric
SWPP's Provisions
Earthwork
Pad Fine Grade & Certification
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 2 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
CompletionIS1195 Area Completion 0 0 10MAY12 2
Math/Science BuildingBuilding SuperstructureAllAllStartBS0000 Start Superstructure 0 0 11MAY12 2
Grade to First LevelAllFoundationsBS0005 Conc Deep Footings 15 0 15MAY12 05JUN12 2
BS0010 Conc Footings & Grade Beams 15 0 06JUN12 26JUN12 5
BS0015 Conc Elev Pit/Sump/Trench Walls 10 0 13JUN12 26JUN12 5
BS0020 Conc Elev Pit/Sumps/Trench SOG 10 0 27JUN12 11JUL12 10
BS0025 Conc Pit/Sump/Trench Final Cure/Strip/Patch 5 0 27JUN12 03JUL12 5
BS0030 Elev Pit/Sump/Trench Wall Wateproofing 5 0 05JUL12 11JUL12 5
BS0035 Elev Pit/Sump/Trench Structural Backfill 5 0 12JUL12 18JUL12 5
BS0040 Drill & Set Elevator Casings 2 0 19JUL12 20JUL12 5
Walls & ColumnsBS0045 Conc Ret Walls 20 0 30MAY12 26JUN12 2
BS0050 Conc Ret Walls Final Cure/Strip/Patch 10 0 20JUN12 03JUL12 2
BS0052 Conc Columns, Beams, & Pedestals 10 0 20JUN12 03JUL12 2
BS0055 Conc Ret Wall Wateproofing 5 0 05JUL12 11JUL12 2
BS0060 Conc Ret Wall Drainage 5 0 12JUL12 18JUL12 2
Interior Structural BackfillBS0065 Structural Backfill & Ro Grading 5 0 19JUL12 25JUL12 2
BS0066 Structural Backfill & Ro Grading 5 0 21SEP12 27SEP12 7
Grade to Roof LevelAllStructural SteelBS0070 Erect Structural Steel - Metal Deck - Stairs 15 0 26JUL12 15AUG12 2
BS0075 Structural Steel Plum & Align 10 0 16AUG12 29AUG12 2
BS0080 Primary Structural Steel Bolt & Weld 20 0 30AUG12 27SEP12 2
BS0085 Steel Column Nelson Studs 5 0 14SEP12 20SEP12 2
BS0090 Secondary Structural Steel Opgs & Misc Framing 10 0 28SEP12 11OCT12 2
BS0095 Final Structural Steel Bolt & Weld 5 0 12OCT12 18OCT12 2
2011 2012 2013 2014 2015
Area Completion
Start Superstructure
Conc Deep Footings
Conc Footings & Grade Beams
Conc Elev Pit/Sump/Trench Walls
Conc Elev Pit/Sumps/Trench SOG
Conc Pit/Sump/Trench Final Cure/Strip/Patch
Elev Pit/Sump/Trench Wall Wateproofing
Elev Pit/Sump/Trench Structural Backfill
Drill & Set Elevator Casings
Conc Ret Walls
Conc Ret Walls Final Cure/Strip/Patch
Conc Columns, Beams, & Pedestals
Conc Ret Wall Wateproofing
Conc Ret Wall Drainage
Structural Backfill & Ro Grading
Structural Backfill & Ro Grading
Erect Structural Steel - Metal Deck - Stairs
Structural Steel Plum & Align
Primary Structural Steel Bolt & Weld
Steel Column Nelson Studs
Secondary Structural Steel Opgs & Misc Framing
Final Structural Steel Bolt & Weld
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 3 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Basement LevelAllWalls & ColumnsBS0110 Conc Walls & Columns (Form/Rebar/MEP/Place) 20 0 21SEP12 18OCT12 2
BS0115 Conc Walls Final Cure/Strip/Patch 10 0 12OCT12 25OCT12 4
Underslab Plumbing & ElectricalBS0120 Underslab Plumbing 10 0 05OCT12 18OCT12 2
BS0125 Underslab Fire Water 5 0 10OCT12 16OCT12 8
BS0130 Underslab Electrical 10 0 11OCT12 24OCT12 2
Slab on GradeBS0135 Fine Grade for CIP Conc SOG 5 0 25OCT12 31OCT12 2
BS0140 Conc Slab on Grade (Form/Rebar/MEP/Place) 15 0 30OCT12 20NOV12 2
BS0145 Conc Stairs (Form/Rebar/Place) 10 0 14NOV12 29NOV12 18
BS0150 Conc Curbs & Bases 10 0 30NOV12 13DEC12 18
BS0155 Conc Deferred Column Floor Fill 5 0 14DEC12 20DEC12 18
First LevelAllUnderslab Plumbing & ElectricalBS1120 Underslab Plumbing 10 0 19OCT12 01NOV12 7
BS1125 Underslab Fire Water 5 0 02NOV12 08NOV12 7
BS1130 Underslab Electrical 10 0 09NOV12 27NOV12 7
Slab on GradeBS1135 Fine Grade for Conc SOG 5 0 28NOV12 04DEC12 7
BS1140 Conc Slab on Grade (Form/Rebar/MEP/Place) 15 0 10DEC12 31DEC12 7
BS1145 Conc Stairs (Form/Rebar/Place) 10 0 24DEC12 08JAN13 12
BS1150 Conc Curbs & Bases 10 0 02JAN13 15JAN13 7
BS1155 Conc Deferred Column Floor Fill 5 0 02JAN13 08JAN13 12
Metal Deck & Concrete FillBS1000 Metal Deck Closures, Shear Studs & Final Welding 10 0 24OCT12 06NOV12 2
BS1010 Conc MtlDeck Fill (Form/Rebar/MEP/Place) 10 0 07NOV12 21NOV12 2
Conc Curbs & BasesBS1020 Conc Curbs & Bases 10 0 26NOV12 07DEC12 32
Second LevelAllMetal Deck & Concrete FillBS2000 Metal Deck Closures, Shear Studs & Final Welding 15 0 19OCT12 08NOV12 2
BS2010 Conc MtlDeck Fill (Form/Rebar/MEP/Place) 10 0 09NOV12 27NOV12 2
Conc Curbs & BasesBS2020 Conc Curbs & Bases 10 0 28NOV12 11DEC12 20
2011 2012 2013 2014 2015
Conc Walls & Columns (Form/Rebar/MEP/Place)
Conc Walls Final Cure/Strip/Patch
Underslab Plumbing
Underslab Fire Water
Underslab Electrical
Fine Grade for CIP Conc SOG
Conc Slab on Grade (Form/Rebar/MEP/Place)
Conc Stairs (Form/Rebar/Place)
Conc Curbs & Bases
Conc Deferred Column Floor Fill
Underslab Plumbing
Underslab Fire Water
Underslab Electrical
Fine Grade for Conc SOG
Conc Slab on Grade (Form/Rebar/MEP/Place)
Conc Stairs (Form/Rebar/Place)
Conc Curbs & Bases
Conc Deferred Column Floor Fill
Metal Deck Closures, Shear Studs & Final Welding
Conc MtlDeck Fill (Form/Rebar/MEP/Place)
Conc Curbs & Bases
Metal Deck Closures, Shear Studs & Final Welding
Conc MtlDeck Fill (Form/Rebar/MEP/Place)
Conc Curbs & Bases
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 4 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Lower Roof LevelAllStructural SteelLR4030 Mech Screen Supports 10 0 26OCT12 08NOV12 4
LR4032 PV Array Supports 10 0 07NOV12 21NOV12 4
LR4033 Guardrail & Gate Supports 10 0 15NOV12 30NOV12 4
Metal Deck & Concrete FillLR4040 Metal Deck Closures, Shear Studs & Final Welding 10 0 02NOV12 16NOV12 2
LR4050 MEP Penetration Sleeves 5 0 19NOV12 27NOV12 2
LR4060 Roof Drain Sumps 5 0 28NOV12 04DEC12 2
LR4070 Conc Metal Deck Fill (Form/Rebar/MEP/Place) 10 0 05DEC12 18DEC12 2
Conc Curbs & BasesLR4080 Conc Curbs & Bases 10 0 19DEC12 03JAN13 15
Upper Roof LevelAllStructural SteelUR5001 Roof Canopy Supports 10 0 26NOV12 07DEC12 18
UR5002 PV Array Supports 15 0 03DEC12 21DEC12 22
ALL AX CompletionBS9000 Superstructure Complete 0 0 15JAN13 7
Building EnvelopeGrade to Roof LevelWest AreasExterior & Inteior EnvelopeWE1000 Start 0 0 19DEC12 2
WE1005 Erect Scaffolding 5 0 19DEC12 26DEC12 5
WE1010 MEP Supports 10 0 27DEC12 10JAN13 5
WE1015 Misc Metal, & Pefab Supports 10 0 31DEC12 14JAN13 5
WE1020 Mtl Stud Stickers & Tracks 10 0 04JAN13 17JAN13 5
WE1025 Cementitious Fireproofing 10 0 18JAN13 31JAN13 5
WE1030 Metal Stud Framing & Hollow Metal 20 0 25JAN13 21FEB13 5
WE1031 Fire Sprinklers 10 0 01FEB13 14FEB13 5
WE1032 Plum - Drain Waste Vent 10 0 08FEB13 21FEB13 5
WE1033 Elec Branch Conduit/Boxes & Lt Fixtures Cans 10 0 15FEB13 28FEB13 5
WE1034 Plum - Water 5 0 22FEB13 28FEB13 5
WE1035 Insulation & Sheathing 15 0 01MAR13 21MAR13 5
WE1040 WP Membrane & Flashing 10 0 08MAR13 21MAR13 5
2011 2012 2013 2014 2015
Mech Screen Supports
PV Array Supports
Guardrail & Gate Supports
Metal Deck Closures, Shear Studs & Final Welding
MEP Penetration Sleeves
Roof Drain Sumps
Conc Metal Deck Fill (Form/Rebar/MEP/Place)
Conc Curbs & Bases
Roof Canopy Supports
PV Array Supports
Superstructure Complete
Start
Erect Scaffolding
MEP Supports
Misc Metal, & Pefab Supports
Mtl Stud Stickers & Tracks
Cementitious Fireproofing
Metal Stud Framing & Hollow Metal
Fire Sprinklers
Plum - Drain Waste Vent
Elec Branch Conduit/Boxes & Lt Fixtures Cans
Plum - Water
Insulation & Sheathing
WP Membrane & Flashing
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 5 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exterior & Inteior EnvelopeWE1045 Plaster Lathing, Flashings & Accys 15 0 15MAR13 04APR13 5
WE1046 Plaster Scratch (Incl Cure) 5 0 05APR13 11APR13 5
WE1047 Plaster Brown (Incl Cure) 10 0 12APR13 25APR13 5
WE1048 Plaster Finish Coat 5 0 24APR13 30APR13 5
WE1049 Plaster Finish Coat Final Cure 15 0 01MAY13 21MAY13 5
WE1050 Exterior Panel Systems 15 0 01MAY13 21MAY13 6
WE1055 Initial Paint 20 0 22MAY13 19JUN13 5
WE1060 Remove Scaffolding 5 0 22MAY13 29MAY13 6
WE1065 Sheet Metal 10 0 22MAY13 05JUN13 39
WE1070 Alum Storefront & Entrances 10 0 30MAY13 12JUN13 10
WE1080 Metal Screens & Metal Mesh 20 0 30MAY13 26JUN13 19
WE1090 Alum Windows 20 0 30MAY13 26JUN13 29
WE1100 Storefront & Entrance Glazing 5 0 13JUN13 19JUN13 10
WE1115 Doors, Gates, & Initial Hardware 10 0 27JUN13 11JUL13 19
WE1120 Sunshades & Lightshelfs 10 0 20JUN13 03JUL13 34
WE1125 Guardrails & Handrails 15 0 20JUN13 11JUL13 5
WE1126 Depressed Slab Waterproofing 10 0 26JUN13 10JUL13 5
WE1130 Conc Topping Slabs 10 0 11JUL13 24JUL13 5
WE1135 Sheet Metal Fascia 10 0 18JUL13 31JUL13 15
WE1140 Stair Treads 10 0 18JUL13 31JUL13 15
WE1145 Final Finish Hardware 10 0 25JUL13 07AUG13 10
WE1150 MEP Devices, Fixtures & Finish 15 0 25JUL13 14AUG13 5
WE1155 Sealants 10 0 25JUL13 07AUG13 10
WE1160 Final Paints & Coatings 15 0 25JUL13 14AUG13 5
WE1165 Cable Banner System 10 0 29JUL13 09AUG13 8
WE1180 Signage & Finish Specialties 10 0 29JUL13 09AUG13 8
WE1190 Area Completion (Temp Space Conditioning) 0 0 14AUG13 5
South AreasExterior & Inteior EnvelopeSE1000 Start 0 0 27DEC12 2
SE1005 Erect Scaffolding 5 0 27DEC12 03JAN13 5
SE1010 MEP Supports 10 0 04JAN13 17JAN13 5
SE1015 Misc Metal, & Pefab Supports 10 0 04JAN13 17JAN13 5
SE1020 Mtl Stud Stickers & Tracks 10 0 04JAN13 17JAN13 5
SE1025 Cementitious Fireproofing 10 0 18JAN13 31JAN13 5
SE1030 Metal Stud Framing & Hollow Metal 20 0 25JAN13 21FEB13 5
SE1031 Fire Sprinklers 10 0 01FEB13 14FEB13 5
SE1032 Plum - Drain Waste Vent 10 0 08FEB13 21FEB13 5
2011 2012 2013 2014 2015
Plaster Lathing, Flashings & Accys
Plaster Scratch (Incl Cure)
Plaster Brown (Incl Cure)
Plaster Finish Coat
Plaster Finish Coat Final Cure
Exterior Panel Systems
Initial Paint
Remove Scaffolding
Sheet Metal
Alum Storefront & Entrances
Metal Screens & Metal Mesh
Alum Windows
Storefront & Entrance Glazing
Doors, Gates, & Initial Hardware
Sunshades & Lightshelfs
Guardrails & Handrails
Depressed Slab Waterproofing
Conc Topping Slabs
Sheet Metal Fascia
Stair Treads
Final Finish Hardware
MEP Devices, Fixtures & Finish
Sealants
Final Paints & Coatings
Cable Banner System
Signage & Finish Specialties
Area Completion (Temp Space Conditioning)
Start
Erect Scaffolding
MEP Supports
Misc Metal, & Pefab Supports
Mtl Stud Stickers & Tracks
Cementitious Fireproofing
Metal Stud Framing & Hollow Metal
Fire Sprinklers
Plum - Drain Waste Vent
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 6 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exterior & Inteior EnvelopeSE1033 Elec Branch Conduit/Boxes & Lt Fixtures Cans 10 0 15FEB13 28FEB13 5
SE1034 Plum - Water 5 0 22FEB13 28FEB13 5
SE1035 Insulation & Sheathing 15 0 27FEB13 19MAR13 5
SE1040 WP Membrane & Flashing 10 0 06MAR13 19MAR13 5
SE1045 Plaster Lathing, Flashings & Accys 15 0 13MAR13 02APR13 5
SE1046 Plaster Scratch (Incl Cure) 5 0 03APR13 09APR13 5
SE1047 Plaster Brown (Incl Cure) 10 0 10APR13 23APR13 5
SE1048 Plaster Finish Coat 5 0 24APR13 30APR13 5
SE1049 Plaster Finish Coat Final Cure 15 0 01MAY13 21MAY13 5
SE1050 Exterior Panel Systems 15 0 01MAY13 21MAY13 6
SE1055 Initial Paint 20 0 22MAY13 19JUN13 5
SE1060 Remove Scaffolding 5 0 22MAY13 29MAY13 6
SE1065 Sheetmetal 10 0 22MAY13 05JUN13 42
SE1070 Alum Storefront & Entrances 10 0 30MAY13 12JUN13 10
SE1080 Alum Windows 20 0 30MAY13 26JUN13 27
SE1090 Storefront & Entrance Glazing 5 0 13JUN13 19JUN13 10
SE1115 Doors, Gates, & Initial Hardware 10 0 13JUN13 26JUN13 32
SE1120 Sunshades & Lightshelfs 10 0 20JUN13 03JUL13 34
SE1125 Guardrails & Handrails 15 0 20JUN13 11JUL13 5
SE1126 Depressed Slab Waterproofing 10 0 01JUL13 15JUL13 5
SE1130 Conc Topping Slabs 10 0 16JUL13 29JUL13 5
SE1135 Sheet Metal Fascia 10 0 23JUL13 05AUG13 10
SE1140 Stair Treads 10 0 23JUL13 05AUG13 10
SE1145 Final Finish Hardware 10 0 30JUL13 12AUG13 7
SE1150 MEP Devices, Fixtures & Finish 10 0 30JUL13 12AUG13 7
SE1155 Sealants 10 0 30JUL13 12AUG13 5
SE1160 Final Paints & Coatings 10 0 30JUL13 12AUG13 5
SE1170 Cable Banner System 10 0 01AUG13 14AUG13 5
SE1180 Signage & Finish Specialties 10 0 01AUG13 14AUG13 5
SE1190 Area Completion 0 0 14AUG13 5
East AreasExterior & Inteior EnvelopeEE1000 Start 0 0 04JAN13 2
EE1005 Erect Scaffolding 5 0 04JAN13 10JAN13 5
EE1010 MEP Supports 10 0 11JAN13 24JAN13 5
EE1015 Misc Metal, & Pefab Supports 10 0 11JAN13 24JAN13 5
EE1020 Mtl Stud Stickers & Tracks 10 0 11JAN13 24JAN13 5
EE1025 Cementitious Fireproofing 10 0 25JAN13 07FEB13 5
2011 2012 2013 2014 2015
Elec Branch Conduit/Boxes & Lt Fixtures Cans
Plum - Water
Insulation & Sheathing
WP Membrane & Flashing
Plaster Lathing, Flashings & Accys
Plaster Scratch (Incl Cure)
Plaster Brown (Incl Cure)
Plaster Finish Coat
Plaster Finish Coat Final Cure
Exterior Panel Systems
Initial Paint
Remove Scaffolding
Sheetmetal
Alum Storefront & Entrances
Alum Windows
Storefront & Entrance Glazing
Doors, Gates, & Initial Hardware
Sunshades & Lightshelfs
Guardrails & Handrails
Depressed Slab Waterproofing
Conc Topping Slabs
Sheet Metal Fascia
Stair Treads
Final Finish Hardware
MEP Devices, Fixtures & Finish
Sealants
Final Paints & Coatings
Cable Banner System
Signage & Finish Specialties
Area Completion
Start
Erect Scaffolding
MEP Supports
Misc Metal, & Pefab Supports
Mtl Stud Stickers & Tracks
Cementitious Fireproofing
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 7 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exterior & Inteior EnvelopeEE1030 Metal Stud Framing & Hollow Metal 20 0 01FEB13 28FEB13 5
EE1031 Fire Sprinklers 10 0 07FEB13 20FEB13 5
EE1032 Plum - Drain Waste Vent 10 0 14FEB13 27FEB13 5
EE1033 Elec Branch Conduit/Boxes & Lt Fixtures Cans 10 0 21FEB13 06MAR13 5
EE1034 Plum - Water 5 0 28FEB13 06MAR13 5
EE1035 Insulation & Sheathing 15 0 01MAR13 21MAR13 5
EE1040 WP Membrane & Flashing 10 0 08MAR13 21MAR13 5
EE1045 Plaster Lathing, Flashings & Accys 15 0 15MAR13 04APR13 5
EE1046 Plaster Scratch (Incl Cure) 5 0 05APR13 11APR13 5
EE1047 Plaster Brown (Incl Cure) 10 0 12APR13 25APR13 5
EE1048 Plaster Finish Coat 5 0 24APR13 30APR13 5
EE1049 Plaster Finish Coat Final Cure 15 0 01MAY13 21MAY13 5
EE1050 Exterior Panel Systems 15 0 01MAY13 21MAY13 6
EE1052 Exterior Fire Risers 5 0 22MAY13 29MAY13 6
EE1055 Initial Paint 20 0 22MAY13 19JUN13 5
EE1060 Remove Scaffolding 5 0 22MAY13 29MAY13 6
EE1065 Sheet Metal 10 0 22MAY13 05JUN13 42
EE1070 Alum Storefront & Entrances 10 0 30MAY13 12JUN13 10
EE1080 Metal Screens & Metal Mesh 20 0 30MAY13 26JUN13 22
EE1090 Alum Windows 20 0 30MAY13 26JUN13 27
EE1100 Storefront & Entrance Glazing 10 0 13JUN13 26JUN13 10
EE1115 Doors, Gates, & Initial Hardware 10 0 27JUN13 11JUL13 22
EE1120 Sunshades & Lightshelfs 10 0 27JUN13 11JUL13 29
EE1125 Guardrails & Handrails 15 0 20JUN13 11JUL13 5
EE1126 Depressed Slab Waterproofing 10 0 26JUN13 10JUL13 5
EE1130 Conc Topping Slabs 10 0 11JUL13 24JUL13 5
EE1135 Sheet Metal Fascia 10 0 18JUL13 31JUL13 13
EE1140 Stair Treads 10 0 18JUL13 31JUL13 13
EE1145 Final Finish Hardware 10 0 25JUL13 07AUG13 10
EE1150 MEP Devices, Fixtures & Finish 15 0 25JUL13 14AUG13 5
EE1155 Sealants 10 0 25JUL13 07AUG13 8
EE1160 Final Paints & Coatings 10 0 25JUL13 07AUG13 8
EE1170 Cable Banner System 10 0 29JUL13 09AUG13 8
EE1180 Signage & Finish Specialties 10 0 29JUL13 09AUG13 8
EE1190 Area Completion 0 0 14AUG13 5
North AreasExterior & Inteior EnvelopeNE1000 Start 0 0 11JAN13 2
2011 2012 2013 2014 2015
Metal Stud Framing & Hollow Metal
Fire Sprinklers
Plum - Drain Waste Vent
Elec Branch Conduit/Boxes & Lt Fixtures Cans
Plum - Water
Insulation & Sheathing
WP Membrane & Flashing
Plaster Lathing, Flashings & Accys
Plaster Scratch (Incl Cure)
Plaster Brown (Incl Cure)
Plaster Finish Coat
Plaster Finish Coat Final Cure
Exterior Panel Systems
Exterior Fire Risers
Initial Paint
Remove Scaffolding
Sheet Metal
Alum Storefront & Entrances
Metal Screens & Metal Mesh
Alum Windows
Storefront & Entrance Glazing
Doors, Gates, & Initial Hardware
Sunshades & Lightshelfs
Guardrails & Handrails
Depressed Slab Waterproofing
Conc Topping Slabs
Sheet Metal Fascia
Stair Treads
Final Finish Hardware
MEP Devices, Fixtures & Finish
Sealants
Final Paints & Coatings
Cable Banner System
Signage & Finish Specialties
Area Completion
Start
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 8 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exterior & Inteior EnvelopeNE1005 Erect Scaffolding 5 0 11JAN13 17JAN13 2
NE1010 MEP Supports 10 0 18JAN13 31JAN13 2
NE1015 Misc Metal, & Pefab Supports 10 0 18JAN13 31JAN13 2
NE1020 Mtl Stud Stickers & Tracks 10 0 18JAN13 31JAN13 2
NE1025 Cementitious Fireproofing 10 0 01FEB13 14FEB13 2
NE1030 Metal Stud Framing & Hollow Metal 20 0 08FEB13 07MAR13 2
NE1031 Fire Sprinklers 10 0 12FEB13 25FEB13 2
NE1032 Plum - Drain Waste Vent 10 0 19FEB13 04MAR13 2
NE1033 Elec Branch Conduit/Boxes & Lt Fixtures Cans 10 0 21FEB13 06MAR13 2
NE1034 Plum - Water 5 0 25FEB13 01MAR13 2
NE1035 Insulation & Sheathing 15 0 27FEB13 19MAR13 2
NE1040 WP Membrane & Flashing 10 0 06MAR13 19MAR13 2
NE1045 Plaster Lathing, Flashings & Accys 15 0 13MAR13 02APR13 2
NE1046 Plaster Scratch (Incl Cure) 5 0 03APR13 09APR13 2
NE1047 Plaster Brown (Incl Cure) 10 0 10APR13 23APR13 2
NE1048 Plaster Finish Coat 5 0 22APR13 26APR13 2
NE1049 Plaster Finish Coat Final Cure 15 0 29APR13 17MAY13 2
NE1050 Exterior Panel Systems 15 0 29APR13 17MAY13 2
NE1055 Initial Paint 20 0 20MAY13 17JUN13 7
NE1060 Remove Scaffolding 5 0 20MAY13 24MAY13 2
NE1065 Sheet Metal 10 0 20MAY13 03JUN13 44
NE1070 Alum Storefront & Entrances 10 0 28MAY13 10JUN13 2
NE1090 Metal Screens & Metal Mesh 20 0 28MAY13 24JUN13 24
NE1100 Alum Windows 20 0 28MAY13 24JUN13 29
NE1110 Storefront & Entrance Glazing 10 0 11JUN13 24JUN13 2
NE1115 Doors, Gates, & Initial Hardware 10 0 25JUN13 09JUL13 24
NE1120 Sunshades & Lightshelfs 10 0 25JUN13 09JUL13 31
NE1125 Guardrails & Handrails 15 0 25JUN13 16JUL13 2
NE1126 Depressed Slab Waterproofing 10 0 05JUL13 18JUL13 2
NE1130 Conc Topping Slabs 10 0 19JUL13 01AUG13 2
NE1135 Sheet Metal Fascia 10 0 26JUL13 08AUG13 7
NE1140 Stair Treads 10 0 26JUL13 08AUG13 7
NE1145 Final Finish Hardware 10 0 02AUG13 15AUG13 4
NE1150 MEP Devices, Fixtures & Finish 10 0 02AUG13 15AUG13 4
NE1155 Sealants 10 0 02AUG13 15AUG13 2
NE1160 Final Paints & Coatings 10 0 02AUG13 15AUG13 2
NE1165 Cable Banner System 10 0 06AUG13 19AUG13 2
NE1180 Signage & Finish Specialties 10 0 06AUG13 19AUG13 2
2011 2012 2013 2014 2015
Erect Scaffolding
MEP Supports
Misc Metal, & Pefab Supports
Mtl Stud Stickers & Tracks
Cementitious Fireproofing
Metal Stud Framing & Hollow Metal
Fire Sprinklers
Plum - Drain Waste Vent
Elec Branch Conduit/Boxes & Lt Fixtures Cans
Plum - Water
Insulation & Sheathing
WP Membrane & Flashing
Plaster Lathing, Flashings & Accys
Plaster Scratch (Incl Cure)
Plaster Brown (Incl Cure)
Plaster Finish Coat
Plaster Finish Coat Final Cure
Exterior Panel Systems
Initial Paint
Remove Scaffolding
Sheet Metal
Alum Storefront & Entrances
Metal Screens & Metal Mesh
Alum Windows
Storefront & Entrance Glazing
Doors, Gates, & Initial Hardware
Sunshades & Lightshelfs
Guardrails & Handrails
Depressed Slab Waterproofing
Conc Topping Slabs
Sheet Metal Fascia
Stair Treads
Final Finish Hardware
MEP Devices, Fixtures & Finish
Sealants
Final Paints & Coatings
Cable Banner System
Signage & Finish Specialties
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 9 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exterior & Inteior EnvelopeNE1190 Area Completion (Permanent Space Enclosure) 0 0 19AUG13 2
Lower Roof LevelRoof AreasStartLRE5000 Start 0 0 19DEC12 6
Exterior EnvelopeLRE5005 Metal Stud Framing 15 0 19DEC12 10JAN13 6
LRE5010 Insulation & Sheathing 10 0 11JAN13 24JAN13 6
LRE5015 WP Membrane & Flashing 10 0 18JAN13 31JAN13 11
LRE5020 Plaster Lathing, Flashings & Accys 15 0 25JAN13 14FEB13 11
LRE5025 Plaster Scratch (Incl Cure) 5 0 15FEB13 21FEB13 42
LRE5030 Plaster Brown (Incl Cure) 10 0 22FEB13 07MAR13 42
LRE5035 Plaster Finish Coat 2 0 08MAR13 11MAR13 42
LRE5040 Plaster Finish Coat Final Cure 15 0 12MAR13 01APR13 42
LRE5045 Pre-Fab Roof Curbs 10 0 19DEC12 03JAN13 8
LRE5050 Roof Drain Sump Receivers 10 0 24DEC12 08JAN13 8
LRE5055 MEP Roof Jacks/Penetrations 15 0 27DEC12 17JAN13 8
LRE5060 MEP Sleeper Supports 10 0 31DEC12 14JAN13 8
LRE5065 Elec Unistrut Supports 10 0 03JAN13 16JAN13 8
LRE5070 HVAC Duct Supports 10 0 07JAN13 18JAN13 8
LRE5075 Mech Screen Flashings 10 0 09JAN13 22JAN13 8
LRE5080 Roofing Base Flashings & Nailers 10 0 25JAN13 07FEB13 6
LRE5085 Insulation & Roofing 15 0 08FEB13 28FEB13 6
LRE5090 Roof Walkway Pads 10 0 01MAR13 14MAR13 54
Mechancial EquipmentLRE5105 Set HVAC Equipment 1 0 04JAN13 04JAN13 13
LRE5110 Fit-Out HVAC Equipment 20 0 07JAN13 01FEB13 28
LRE5120 HVAC Duct 20 0 04FEB13 01MAR13 48
LRE5125 HVAC Duct Insulation & WP Wrap 10 0 04MAR13 15MAR13 48
LRE5135 HVAC Refrigerant Piping 10 0 15JAN13 28JAN13 30
LRE5140 HVAC Refrigerant Piping Final Connections 5 0 29JAN13 04FEB13 30
LRE5145 HVAC Refrigerant Piping Insulation & WP Wrap 10 0 05FEB13 18FEB13 30
LRE5150 HVAC Charge Refrigerant 2 0 19FEB13 20FEB13 30
LRE5155 HVAC Hydronic Piping 20 0 21FEB13 20MAR13 30
LRE5160 HVAC Hydronic Piping Final Connections 15 0 21MAR13 10APR13 30
LRE5165 HVAC Hydronic Piping Insulation & WP Wrap 10 0 11APR13 24APR13 30
LRE5175 HVAC Controls 15 0 25APR13 15MAY13 30
LRE5180 HVAC Equip - Start Equip Motors 5 0 16MAY13 22MAY13 30
2011 2012 2013 2014 2015
Area Completion (Permanent Space Enclosure)
Start
Metal Stud Framing
Insulation & Sheathing
WP Membrane & Flashing
Plaster Lathing, Flashings & Accys
Plaster Scratch (Incl Cure)
Plaster Brown (Incl Cure)
Plaster Finish Coat
Plaster Finish Coat Final Cure
Pre-Fab Roof Curbs
Roof Drain Sump Receivers
MEP Roof Jacks/Penetrations
MEP Sleeper Supports
Elec Unistrut Supports
HVAC Duct Supports
Mech Screen Flashings
Roofing Base Flashings & Nailers
Insulation & Roofing
Roof Walkway Pads
Set HVAC Equipment
Fit-Out HVAC Equipment
HVAC Duct
HVAC Duct Insulation & WP Wrap
HVAC Refrigerant Piping
HVAC Refrigerant Piping Final Connections
HVAC Refrigerant Piping Insulation & WP Wrap
HVAC Charge Refrigerant
HVAC Hydronic Piping
HVAC Hydronic Piping Final Connections
HVAC Hydronic Piping Insulation & WP Wrap
HVAC Controls
HVAC Equip - Start Equip Motors
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 10 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Mechancial EquipmentLRE5185 HVAC Indentification & Finish 10 0 23MAY13 06JUN13 30
Plumbing SystemsLRE5200 Plumbing - Drains 10 0 04FEB13 15FEB13 28
LRE5210 Plumbing - Water & Hose Bibs 15 0 18FEB13 08MAR13 38
LRE5215 Plumbing - Natural Gas 15 0 11MAR13 29MAR13 38
LRE5220 Plumbing Identification & Finish 5 0 01APR13 05APR13 38
Fire Sprinkler SystemsLRE5230 Fire Sprinker Risers 10 0 04FEB13 15FEB13 28
LRE5232 Fire Sprinker Laterals 15 0 18FEB13 08MAR13 28
LRE5234 Fire Sprinker Drops & Heads 15 0 11MAR13 29MAR13 28
LRE5236 Fire Sprinker Identification & Finish 15 0 01APR13 19APR13 28
Electrical SystemsLRE5250 Elec Feeders, Branch, & Boxes 15 0 04FEB13 22FEB13 58
LRE5255 Elec Wiring & Connections 20 0 11FEB13 08MAR13 58
Exterior Fixtures & AssembliesLRE5260 Roof Screen Panels 10 0 07JAN13 18JAN13 13
LRE5265 Guardrails & Handrails 15 0 09JAN13 29JAN13 13
LRE5270 Gates & Hardware 15 0 30JAN13 19FEB13 41
LRE5275 Skylights 20 0 20FEB13 19MAR13 41
LRE5280 Sheet Metal 10 0 20MAR13 02APR13 41
FinishesLRE5285 Initial Paint 15 0 22APR13 10MAY13 28
LRE5290 Sealants 10 0 13MAY13 24MAY13 28
LRE5295 Final Paint 10 0 28MAY13 10JUN13 28
CompletionLRE5300 Area Completion 0 0 10JUN13 28
Upper Roof LevelRoof AreasStartURE6000 Start 0 0 19DEC12 11
Fire Sprinkler SystemsLR36230 Fire Sprinker Risers 10 0 18FEB13 01MAR13 43
LRE6232 Fire Sprinker Laterals 10 0 18FEB13 01MAR13 43
LRE6234 Fire Sprinker Drops & Heads 10 0 04MAR13 15MAR13 43
LRE6236 Fire Sprinker Identification & Finish 10 0 18MAR13 29MAR13 43
Exterior Fixtures & AssembliesURE6250 Canopy Gutters 10 0 19DEC12 03JAN13 11
URE6260 Canopy Skylights 20 0 04JAN13 31JAN13 11
2011 2012 2013 2014 2015
HVAC Indentification & Finish
Plumbing - Drains
Plumbing - Water & Hose Bibs
Plumbing - Natural Gas
Plumbing Identification & Finish
Fire Sprinker Risers
Fire Sprinker Laterals
Fire Sprinker Drops & Heads
Fire Sprinker Identification & Finish
Elec Feeders, Branch, & Boxes
Elec Wiring & Connections
Roof Screen Panels
Guardrails & Handrails
Gates & Hardware
Skylights
Sheet Metal
Initial Paint
Sealants
Final Paint
Area Completion
Start
Fire Sprinker Risers
Fire Sprinker Laterals
Fire Sprinker Drops & Heads
Fire Sprinker Identification & Finish
Canopy Gutters
Canopy Skylights
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 11 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exterior Fixtures & AssembliesURE6265 Photovotaic System 20 0 04JAN13 31JAN13 11
URE6270 Sheet Metal 15 0 01MAR13 21MAR13 49
FinishesURE6280 Initial Paint 15 0 01APR13 19APR13 43
URE6290 Sealants 10 0 22APR13 03MAY13 43
URE6295 Final Paint 10 0 06MAY13 17MAY13 43
CompletionURE6300 Area Completion 0 0 17MAY13 43
InteriorsBasement LevelOverallStartINT0000 Start 0 0 21NOV12 2
Interior FireproofingINT0010 Mtl Stud Stickers & Top Tracks 10 0 21NOV12 06DEC12 2
INT0020 MEP Supports 5 0 30NOV12 06DEC12 2
INT0030 Misc Metal, & Pefab Supports 5 0 30NOV12 06DEC12 2
INT0040 Cementitious Fireproofing 10 0 07DEC12 20DEC12 2
MEP Vertical ShaftsINT0050 Intial Shaftwall Assy 10 0 21DEC12 07JAN13 5
INT0052 Plumbing - Drain Waste Vent 10 0 08JAN13 21JAN13 14
INT0054 Plumbing - Water, IW, & NGas 10 0 08JAN13 21JAN13 14
INT0060 Fire Sprinklers & Risers 15 0 15JAN13 04FEB13 5
INT0062 Plum Insl & Finish 10 0 15JAN13 28JAN13 14
INT0063 Elec Feeders 10 0 22JAN13 04FEB13 5
INT0070 HVAC Ducts 10 0 28JAN13 08FEB13 5
INT0071 HVAC Hydronic Piping 10 0 11FEB13 22FEB13 5
INT0072 HVAC Duct Testing 10 0 11FEB13 22FEB13 5
INT0075 HVAC Refrigerant Piping 10 0 25FEB13 08MAR13 5
INT0080 HVAC Insul & Finish 10 0 25FEB13 08MAR13 5
INT0085 HVAC Controls 10 0 25FEB13 08MAR13 5
INT0090 Drywall Shaftwall Assy 10 0 04MAR13 15MAR13 5
Overhead RoughINT0100 OH Plumbing - Drain Waste Vent 10 0 21DEC12 07JAN13 2
INT0105 OH Plumbing - Water, IW, & NGas 15 0 08JAN13 28JAN13 2
INT0110 OH HVAC Equip 15 0 22JAN13 11FEB13 2
INT0115 OH Elec Feeders 15 0 29JAN13 18FEB13 19
INT0120 OH Plum Insl & Finish 10 0 29JAN13 11FEB13 2
2011 2012 2013 2014 2015
Photovotaic System
Sheet Metal
Initial Paint
Sealants
Final Paint
Area Completion
Start
Mtl Stud Stickers & Top Tracks
MEP Supports
Misc Metal, & Pefab Supports
Cementitious Fireproofing
Intial Shaftwall Assy
Plumbing - Drain Waste Vent
Plumbing - Water, IW, & NGas
Fire Sprinklers & Risers
Plum Insl & Finish
Elec Feeders
HVAC Ducts
HVAC Hydronic Piping
HVAC Duct Testing
HVAC Refrigerant Piping
HVAC Insul & Finish
HVAC Controls
Drywall Shaftwall Assy
OH Plumbing - Drain Waste Vent
OH Plumbing - Water, IW, & NGas
OH HVAC Equip
OH Elec Feeders
OH Plum Insl & Finish
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 12 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Overhead RoughINT0125 OH Fire Sprinklers & Risers 15 0 05FEB13 25FEB13 2
INT0132 OH HVAC Duct 15 0 19FEB13 11MAR13 2
INT0135 OH HVAC Refrigerant Piping 10 0 22FEB13 07MAR13 3
INT0140 OH HVAC Controls 10 0 27FEB13 12MAR13 3
INT0145 OH Elec Power & Lighting Branch 10 0 04MAR13 15MAR13 3
INT0150 OH Elec FA & Low Voltage Branch 10 0 04MAR13 15MAR13 5
INT0155 OH HVAC Duct Testing 10 0 12MAR13 25MAR13 2
INT0160 OH HVAC Insul & Finish 5 0 26MAR13 01APR13 2
Classrooms, Offices, & LabsPartitions & SoffitsINT0210 Metal Studs & HM Frames 15 0 21DEC12 14JAN13 8
INT0215 HVAC Refrigerant Piping 10 0 31DEC12 14JAN13 39
INT0220 HVAC Controls 10 0 08JAN13 21JAN13 39
INT0225 Ro Plumbing - Fixture Carriers 10 0 08JAN13 21JAN13 8
INT0230 Ro Plum - Drain Waste Vent 15 0 15JAN13 04FEB13 8
INT0235 Ro Plum - Water, IW, & NGas 15 0 22JAN13 11FEB13 8
INT0240 Elec Feeders 10 0 29JAN13 11FEB13 8
INT0245 Elec Power & Lighting Branch 15 0 12FEB13 04MAR13 8
INT0250 Elec FA & Low Voltage Branch 10 0 18FEB13 01MAR13 8
INT0260 Plum Insl & Finish 10 0 12FEB13 25FEB13 14
INT0265 Insulation & Drywall 10 0 01MAR13 14MAR13 6
INT0268 Elec Branch Wiring 20 0 06MAR13 02APR13 6
INT0270 Firestop, Tape & Finish Drywall 10 0 18MAR13 29MAR13 5
INT0275 Initial Paint 10 0 26MAR13 08APR13 2
Exposed OverheadINT0280 Initial Paint 10 0 02APR13 15APR13 2
INT0285 Fire Sprinkler Heads 10 0 16APR13 29APR13 2
INT0290 HVAC Registers 10 0 30APR13 13MAY13 2
INT0295 Light Fixtures & Connections 15 0 14MAY13 04JUN13 2
Drywall CeilingsINT0300 Metal Stud & CRS Framing 10 0 04MAR13 15MAR13 3
INT0305 Elec Light Fixture Cans 10 0 11MAR13 22MAR13 3
INT0310 HVAC Drops 10 0 18MAR13 29MAR13 3
INT0315 Elec Power & Lighting Branch 10 0 18MAR13 29MAR13 3
INT0320 Elec FA & Low Voltage Branch 10 0 25MAR13 05APR13 3
INT0325 Drywall 10 0 26MAR13 08APR13 2
INT0330 Elec Branch Wiring 20 0 01APR13 26APR13 18
INT0335 Fire Sprinkler Drops & Heads 10 0 29MAR13 11APR13 2
2011 2012 2013 2014 2015
OH Fire Sprinklers & Risers
OH HVAC Duct
OH HVAC Refrigerant Piping
OH HVAC Controls
OH Elec Power & Lighting Branch
OH Elec FA & Low Voltage Branch
OH HVAC Duct Testing
OH HVAC Insul & Finish
Metal Studs & HM Frames
HVAC Refrigerant Piping
HVAC Controls
Ro Plumbing - Fixture Carriers
Ro Plum - Drain Waste Vent
Ro Plum - Water, IW, & NGas
Elec Feeders
Elec Power & Lighting Branch
Elec FA & Low Voltage Branch
Plum Insl & Finish
Insulation & Drywall
Elec Branch Wiring
Firestop, Tape & Finish Drywall
Initial Paint
Initial Paint
Fire Sprinkler Heads
HVAC Registers
Light Fixtures & Connections
Metal Stud & CRS Framing
Elec Light Fixture Cans
HVAC Drops
Elec Power & Lighting Branch
Elec FA & Low Voltage Branch
Drywall
Elec Branch Wiring
Fire Sprinkler Drops & Heads
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 13 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Drywall CeilingsINT0340 Tape & Finish Drywall 10 0 05APR13 18APR13 2
INT0345 Initial Paint 10 0 09APR13 22APR13 2
INT0350 HVAC Registers & Grills 10 0 23APR13 06MAY13 22
INT0355 Fire Sprinkler Trim 5 0 23APR13 29APR13 27
INT0360 Elec Light Fixture Finish 10 0 29APR13 10MAY13 18
Signal, Communications & Fire Alarm SystemsINT0365 Elec Fire Alarm System Cables 10 0 23APR13 06MAY13 52
INT0370 Elec Fire Alarm System Devices & Connections 10 0 30APR13 13MAY13 52
INT0375 Elec TeleData System Cables 10 0 12JUN13 25JUN13 7
INT0380 Elec Security Systems Cables 10 0 19JUN13 02JUL13 12
INT0385 Elec AV Systems Cables 10 0 19JUN13 02JUL13 12
INT0390 Elec TV System Cables 10 0 26JUN13 10JUL13 7
INT0395 Elec TeleData/AV/TV/Sec Devices & Connections 10 0 03JUL13 17JUL13 7
Suspended Acoustic CeilingsINT0400 Fire Shutters 20 0 02APR13 29APR13 2
INT0402 Projection Screens 10 0 30APR13 13MAY13 2
INT0405 Ceiling Grid 15 0 14MAY13 04JUN13 2
INT0410 Fire Sprinkler Drops & Heads 10 0 16MAY13 30MAY13 30
INT0412 HVAC Registers & Connections 10 0 05JUN13 18JUN13 17
INT0415 Grid Mtd & Pendant Light Fixtures 10 0 16MAY13 30MAY13 5
INT0420 Elec Tile Mtd FA-Com Devices 10 0 21MAY13 04JUN13 2
INT0425 Elec Lighting Branch Conduit 15 0 23MAY13 13JUN13 5
INT0430 Elec FA & Low Voltage Branch 10 0 05JUN13 18JUN13 2
INT0431 Elec Branch Wiring 20 0 19JUN13 17JUL13 2
INT0435 Acoustic Tile 10 0 11JUL13 24JUL13 2
INT0440 Fire Sprinkler Trim 5 0 25JUL13 31JUL13 2
Doors Casework Fixtures EquipmentINT0445 Casework Cabinets & Shelving 15 0 09APR13 29APR13 2
INT0450 Casework Tops 15 0 23APR13 13MAY13 7
INT0451 Doors & Initial Hardware 15 0 30APR13 20MAY13 2
INT0453 Interior Glazing 5 0 07MAY13 13MAY13 2
INT0455 Finish Carpentry 15 0 14MAY13 04JUN13 2
INT0460 Casework Elec Power Branch & Boxes 10 0 21MAY13 04JUN13 2
INT0465 Casework Elec Data-Signal-Com Branch 15 0 21MAY13 11JUN13 2
INT0470 Casework Plum Fixtures, Trim & Connections 5 0 29MAY13 04JUN13 2
INT0474 Tack/Markerboards-FE Cabs-Misc Specialties 10 0 05JUN13 18JUN13 32
INT0480 Casework Elec Branch Wiring 15 0 12JUN13 02JUL13 22
2011 2012 2013 2014 2015
Tape & Finish Drywall
Initial Paint
HVAC Registers & Grills
Fire Sprinkler Trim
Elec Light Fixture Finish
Elec Fire Alarm System Cables
Elec Fire Alarm System Devices & Connections
Elec TeleData System Cables
Elec Security Systems Cables
Elec AV Systems Cables
Elec TV System Cables
Elec TeleData/AV/TV/Sec Devices & Connections
Fire Shutters
Projection Screens
Ceiling Grid
Fire Sprinkler Drops & Heads
HVAC Registers & Connections
Grid Mtd & Pendant Light Fixtures
Elec Tile Mtd FA-Com Devices
Elec Lighting Branch Conduit
Elec FA & Low Voltage Branch
Elec Branch Wiring
Acoustic Tile
Fire Sprinkler Trim
Casework Cabinets & Shelving
Casework Tops
Doors & Initial Hardware
Interior Glazing
Finish Carpentry
Casework Elec Power Branch & Boxes
Casework Elec Data-Signal-Com Branch
Casework Plum Fixtures, Trim & Connections
Tack/Markerboards-FE Cabs-Misc Specialties
Casework Elec Branch Wiring
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 14 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Restroom FinishesINT0500 WP - Tile Setting Beds - Floor Drains 10 0 23APR13 06MAY13 2
INT0510 Tile - Walls 10 0 07MAY13 20MAY13 2
INT0520 Tile - Floors 10 0 21MAY13 04JUN13 2
INT0530 Plumbing Fixtures 10 0 05JUN13 18JUN13 2
INT0540 Plumbing Trim & Connections 5 0 12JUN13 18JUN13 2
INT0550 Toilet Partitions & Accys 10 0 19JUN13 02JUL13 2
INT0560 Final Paint 10 0 03JUL13 17JUL13 2
INT0570 HVAC Registers & Finish 10 0 18JUL13 31JUL13 2
INT0580 Elec Devices & Finish 5 0 18JUL13 24JUL13 7
FinishesINT0615 Final Paint 15 0 05JUN13 25JUN13 2
INT0620 FRP Panels 5 0 26JUN13 02JUL13 2
INT0625 VCT, RSF & Carpet & Base 10 0 26JUN13 10JUL13 2
INT0630 Signage - Window Treatment - Misc Fin Spec 15 0 03JUL13 24JUL13 7
INT0635 Finish Hardware Completion 10 0 03JUL13 17JUL13 2
INT0640 Plum Finish 10 0 11JUL13 24JUL13 2
INT0645 HVAC & Controls Finish 10 0 15JUL13 26JUL13 2
INT0650 Elec Exit Signs, Devices & Finish 10 0 18JUL13 31JUL13 2
Plumbing Equipment RoomsPlumbing EquipmentINT0660 Plumbing - Sewer Ejector Pumps 10 0 23APR13 06MAY13 2
INT0662 Plumbing - Circulating Pumps 10 0 23APR13 06MAY13 2
INT0664 Plumbing - Water Heaters/Boilers 10 0 30APR13 13MAY13 2
INT0668 Plumbing - Storage Tanks 10 0 07MAY13 20MAY13 2
INT0670 Plumbing - Air Compressors 10 0 14MAY13 28MAY13 2
INT0672 Pluming - Air Dryers 10 0 29MAY13 11JUN13 2
INT0674 Plumbing - Piping & Connections 10 0 12JUN13 25JUN13 2
INT0676 Plumbing - Fixtures 15 0 26JUN13 17JUL13 12
INT0678 Plumbing - Controls 5 0 26JUN13 02JUL13 2
INT0680 Equip Power & Connections 10 0 03JUL13 17JUL13 2
INT0682 Plumbing - Pipe Insulation 10 0 18JUL13 31JUL13 2
INT0684 Plumbing - Identification 10 0 01AUG13 14AUG13 2
INT0686 Plumbing - Grates & Covers 10 0 01AUG13 14AUG13 2
Electrical Equipment RoomsSignal & Com Systems Equipment & TerminationsINT0740 Elec Equip Room Cable Tray 15 0 09APR13 29APR13 12
INT0741 Elec Equip Room Plywood Backboards 5 0 30APR13 06MAY13 12
INT0742 Elec TeleData Systems Panels, Racks & Equip 15 0 07MAY13 28MAY13 12
2011 2012 2013 2014 2015
WP - Tile Setting Beds - Floor Drains
Tile - Walls
Tile - Floors
Plumbing Fixtures
Plumbing Trim & Connections
Toilet Partitions & Accys
Final Paint
HVAC Registers & Finish
Elec Devices & Finish
Final Paint
FRP Panels
VCT, RSF & Carpet & Base
Signage - Window Treatment - Misc Fin Spec
Finish Hardware Completion
Plum Finish
HVAC & Controls Finish
Elec Exit Signs, Devices & Finish
Plumbing - Sewer Ejector Pumps
Plumbing - Circulating Pumps
Plumbing - Water Heaters/Boilers
Plumbing - Storage Tanks
Plumbing - Air Compressors
Pluming - Air Dryers
Plumbing - Piping & Connections
Plumbing - Fixtures
Plumbing - Controls
Equip Power & Connections
Plumbing - Pipe Insulation
Plumbing - Identification
Plumbing - Grates & Covers
Elec Equip Room Cable Tray
Elec Equip Room Plywood Backboards
Elec TeleData Systems Panels, Racks & Equip
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 15 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Signal & Com Systems Equipment & TerminationsINT0743 Elec PA Systems Panels, Racks & Equip 15 0 14MAY13 04JUN13 12
INT0744 Elec Clock System Racks & Equip 10 0 21MAY13 04JUN13 12
INT0745 Elec Security Systems Panels, Racks & Equip 15 0 29MAY13 18JUN13 12
INT0746 Elec TeleData SystemsTerminations 15 0 26JUN13 17JUL13 7
INT0747 Elec PA Systems Cable Terminations 15 0 26JUN13 17JUL13 12
INT0748 Elec Clock System Cable Terminations 10 0 03JUL13 17JUL13 12
INT0749 Elec Security Systems Cable Terminations 15 0 03JUL13 24JUL13 12
Fire Alarm System Equipment & TerminationsINT0750 Elec Fire Alarm Panels 10 0 07MAY13 20MAY13 37
INT0755 Fire Alarm Terminations 10 0 21MAY13 04JUN13 37
Electrical Equipment & TerminationsINT0730 Elec Switchboards 10 0 09APR13 22APR13 12
INT0731 Elec Transformers 10 0 23APR13 06MAY13 12
INT0732 Elec Panels 10 0 07MAY13 20MAY13 12
INT0733 Elec Feeders 15 0 14MAY13 04JUN13 12
INT0734 Elec Feeder Termination 15 0 21MAY13 11JUN13 12
INT0735 Elec Panel Breakers & Branch Terminations 15 0 29MAY13 18JUN13 12
INT0736 Elec Panel Covers & Directories 10 0 19JUN13 02JUL13 12
CompletionINT0790 Area Completion 0 0 14AUG13 2
First LevelOverallStartINT1000 Start 0 0 26NOV12 2
Interior FireproofingINT1010 Mtl Stud Stickers & Top Tracks 10 0 26NOV12 07DEC12 2
INT1020 MEP Supports 5 0 03DEC12 07DEC12 2
INT1030 Misc Metal, & Pefab Supports 5 0 05DEC12 11DEC12 2
INT1040 Cementitious Fireproofing 10 0 12DEC12 26DEC12 2
MEP Vertical ShaftsINT1050 Intial Shaftwall Assy 10 0 27DEC12 10JAN13 2
INT1052 Plumbing - Drain Waste Vent 10 0 11JAN13 24JAN13 37
INT1054 OH Plumbing - Water, IW, & NGas 10 0 11JAN13 24JAN13 37
INT1060 Fire Sprinklers & Risers 15 0 18JAN13 07FEB13 2
INT1062 OH Plum Insl & Finish 10 0 18JAN13 31JAN13 37
INT1063 OH Elec Feeders 10 0 25JAN13 07FEB13 2
INT1070 HVAC Ducts 15 0 01FEB13 21FEB13 2
INT1071 HVAC Hydronic Piping 10 0 22FEB13 07MAR13 2
2011 2012 2013 2014 2015
Elec PA Systems Panels, Racks & Equip
Elec Clock System Racks & Equip
Elec Security Systems Panels, Racks & Equip
Elec TeleData SystemsTerminations
Elec PA Systems Cable Terminations
Elec Clock System Cable Terminations
Elec Security Systems Cable Terminations
Elec Fire Alarm Panels
Fire Alarm Terminations
Elec Switchboards
Elec Transformers
Elec Panels
Elec Feeders
Elec Feeder Termination
Elec Panel Breakers & Branch Terminations
Elec Panel Covers & Directories
Area Completion
Start
Mtl Stud Stickers & Top Tracks
MEP Supports
Misc Metal, & Pefab Supports
Cementitious Fireproofing
Intial Shaftwall Assy
Plumbing - Drain Waste Vent
OH Plumbing - Water, IW, & NGas
Fire Sprinklers & Risers
OH Plum Insl & Finish
OH Elec Feeders
HVAC Ducts
HVAC Hydronic Piping
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 16 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
MEP Vertical ShaftsINT1072 HVAC Duct Testing 10 0 22FEB13 07MAR13 2
INT1075 HVAC Refrigerant Piping 5 0 08MAR13 14MAR13 2
INT1080 HVAC Insul & Finish 10 0 08MAR13 21MAR13 2
INT1085 HVAC Controls 10 0 05MAR13 18MAR13 3
INT1090 Drywall Shaftwall Assy 10 0 15MAR13 28MAR13 2
Overhead RoughINT1100 OH Plumbing - Drain Waste Vent 10 0 27DEC12 10JAN13 2
INT1105 OH Plumbing - Water, IW, & NGas 15 0 11JAN13 31JAN13 2
INT1110 OH HVAC Equip 15 0 18JAN13 07FEB13 2
INT1112 OH Elec Cable Tray 10 0 25JAN13 07FEB13 2
INT1115 OH Elec Feeders 15 0 01FEB13 21FEB13 2
INT1120 OH Plum Insl & Finish 10 0 06FEB13 19FEB13 2
INT1125 OH Fire Sprinklers & Risers 15 0 11FEB13 01MAR13 2
INT1130 OH HVAC Duct 10 0 14FEB13 27FEB13 2
INT1135 OH HVAC Refrigerant Piping 10 0 19FEB13 04MAR13 2
INT1140 OH HVAC Controls 10 0 22FEB13 07MAR13 2
INT1145 OH Elec Power & Lighting Branch 10 0 01MAR13 14MAR13 2
INT1150 OH Elec FA & Low Voltage Branch 10 0 08MAR13 21MAR13 2
INT1155 OH HVAC Duct Testing 10 0 15MAR13 28MAR13 2
INT1160 OH HVAC Insul & Finish 5 0 29MAR13 04APR13 2
Classrooms, Offices, & LabsPartitions & SoffitsINT1210 Metal Studs & HM Frames 15 0 27DEC12 17JAN13 17
INT1215 HVAC Refrigerant Piping 10 0 04JAN13 17JAN13 47
INT1220 HVAC Controls 10 0 11JAN13 24JAN13 47
INT1225 Ro Plumbing - Fixture Carriers 10 0 04JAN13 17JAN13 17
INT1230 Ro Plum - Drain Waste Vent 15 0 11JAN13 31JAN13 17
INT1235 Ro Plum - Water, IW, & NGas 15 0 18JAN13 07FEB13 17
INT1240 Elec Feeders 10 0 25JAN13 07FEB13 17
INT1245 Elec Power & Lighting Branch 15 0 08FEB13 28FEB13 17
INT1250 Elec FA & Low Voltage Branch 10 0 15FEB13 28FEB13 17
INT1260 Plum Insl & Finish 10 0 22FEB13 07MAR13 17
INT1265 Insulation & Drywall 10 0 01MAR13 14MAR13 17
INT1268 Elec Branch Wiring 20 0 01MAR13 28MAR13 17
INT1270 Firestop, Tape & Finish Drywall 10 0 29MAR13 11APR13 2
INT1275 Initial Paint 10 0 05APR13 18APR13 2
Exposed OverheadINT1280 Initial Paint 10 0 05APR13 18APR13 7
2011 2012 2013 2014 2015
HVAC Duct Testing
HVAC Refrigerant Piping
HVAC Insul & Finish
HVAC Controls
Drywall Shaftwall Assy
OH Plumbing - Drain Waste Vent
OH Plumbing - Water, IW, & NGas
OH HVAC Equip
OH Elec Cable Tray
OH Elec Feeders
OH Plum Insl & Finish
OH Fire Sprinklers & Risers
OH HVAC Duct
OH HVAC Refrigerant Piping
OH HVAC Controls
OH Elec Power & Lighting Branch
OH Elec FA & Low Voltage Branch
OH HVAC Duct Testing
OH HVAC Insul & Finish
Metal Studs & HM Frames
HVAC Refrigerant Piping
HVAC Controls
Ro Plumbing - Fixture Carriers
Ro Plum - Drain Waste Vent
Ro Plum - Water, IW, & NGas
Elec Feeders
Elec Power & Lighting Branch
Elec FA & Low Voltage Branch
Plum Insl & Finish
Insulation & Drywall
Elec Branch Wiring
Firestop, Tape & Finish Drywall
Initial Paint
Initial Paint
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 17 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Exposed OverheadINT1285 Fire Sprinkler Heads 10 0 19APR13 02MAY13 7
INT1290 HVAC Registers 10 0 03MAY13 16MAY13 7
INT1295 Light Fixtures & Connections 10 0 17MAY13 31MAY13 7
Drywall CeilingsINT1300 Metal Stud & CRS Framing 10 0 01MAR13 14MAR13 2
INT1305 Elec Light Fixture Cans 10 0 08MAR13 21MAR13 2
INT1310 HVAC Drops 10 0 15MAR13 28MAR13 7
INT1315 Elec Power & Lighting Branch 10 0 15MAR13 28MAR13 2
INT1320 Elec FA & Low Voltage Branch 10 0 22MAR13 04APR13 2
INT1325 Drywall 10 0 29MAR13 11APR13 2
INT1330 Elec Branch Wiring 20 0 05APR13 02MAY13 17
INT1335 Fire Sprinkler Drops & Heads 5 0 03APR13 09APR13 9
INT1340 Tape & Finish Drywall 10 0 05APR13 18APR13 2
INT1345 Initial Paint 10 0 12APR13 25APR13 2
INT1350 HVAC Registers & Grills 10 0 26APR13 09MAY13 22
INT1355 Fire Sprinkler Trim 5 0 26APR13 02MAY13 27
INT1360 Elec Light Fixture Finish 10 0 03MAY13 16MAY13 17
Signal, Communications & Fire Alarm SystemsINT1365 Elec Fire Alarm System Cables 10 0 17MAY13 31MAY13 34
INT1370 Elec Fire Alarm System Devices & Connections 10 0 24MAY13 07JUN13 34
INT1375 Elec TeleData System Cables 10 0 17JUN13 28JUN13 4
INT1380 Elec Security Systems Cables 10 0 17JUN13 28JUN13 14
INT1385 Elec AV Systems Cables 10 0 24JUN13 08JUL13 9
INT1390 Elec TV System Cables 5 0 01JUL13 08JUL13 4
INT1395 Elec TeleData/AV/TV/Sec Devices & Connections 10 0 09JUL13 22JUL13 4
Suspended Acoustic CeilingsINT1400 Fire Shutters 20 0 12APR13 09MAY13 7
INT1402 Projection Screens 10 0 26APR13 09MAY13 7
INT1405 Ceiling Grid 15 0 10MAY13 31MAY13 7
INT1410 Fire Sprinkler Drops & Heads 10 0 17MAY13 31MAY13 37
INT1412 HVAC Registers & Connections 10 0 17MAY13 31MAY13 37
INT1415 Grid Mtd & Pendant Light Fixtures 10 0 17MAY13 31MAY13 7
INT1420 Elec Tile Mtd FA-Com Devices 10 0 17MAY13 31MAY13 7
INT1425 Elec Lighting Branch 15 0 24MAY13 14JUN13 7
INT1430 Elec FA & LV Branch 10 0 03JUN13 14JUN13 7
INT1431 Elec Branch Wiring 20 0 17JUN13 15JUL13 7
INT1435 Acoustic Tile 10 0 16JUL13 29JUL13 7
INT1440 Fire Sprinkler Trim 5 0 18JUL13 24JUL13 7
2011 2012 2013 2014 2015
Fire Sprinkler Heads
HVAC Registers
Light Fixtures & Connections
Metal Stud & CRS Framing
Elec Light Fixture Cans
HVAC Drops
Elec Power & Lighting Branch
Elec FA & Low Voltage Branch
Drywall
Elec Branch Wiring
Fire Sprinkler Drops & Heads
Tape & Finish Drywall
Initial Paint
HVAC Registers & Grills
Fire Sprinkler Trim
Elec Light Fixture Finish
Elec Fire Alarm System Cables
Elec Fire Alarm System Devices & Connections
Elec TeleData System Cables
Elec Security Systems Cables
Elec AV Systems Cables
Elec TV System Cables
Elec TeleData/AV/TV/Sec Devices & Connections
Fire Shutters
Projection Screens
Ceiling Grid
Fire Sprinkler Drops & Heads
HVAC Registers & Connections
Grid Mtd & Pendant Light Fixtures
Elec Tile Mtd FA-Com Devices
Elec Lighting Branch
Elec FA & LV Branch
Elec Branch Wiring
Acoustic Tile
Fire Sprinkler Trim
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 18 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Doors Casework Fixtures EquipmentINT1445 Casework Cabinets & Shelving 15 0 19APR13 09MAY13 2
INT1446 Lab Casework Cabinets & Furnishings 15 0 03MAY13 23MAY13 2
INT1447 Laboratory Fume Hoods 10 0 10MAY13 23MAY13 12
INT1450 Casework Tops 15 0 10MAY13 31MAY13 2
INT1452 Lab Casework Tops & Sinks 15 0 10MAY13 31MAY13 2
INT1453 Misc Laboratory Equipment 10 0 17MAY13 31MAY13 2
INT1455 Doors & Initial Hardware 15 0 17MAY13 07JUN13 2
INT1456 Sectional Doors 10 0 24MAY13 07JUN13 2
INT1457 Interior Glazing 5 0 03JUN13 07JUN13 29
INT1458 Finish Carpentry 15 0 03JUN13 21JUN13 9
INT1460 Casework Elec Power Branch 10 0 24MAY13 07JUN13 4
INT1465 Casework Elec Data-Signal-Com Branch 15 0 24MAY13 14JUN13 4
INT1470 Casework Plum Fixtures, Trim & Connections 10 0 24MAY13 07JUN13 2
INT1475 Tack/Markerboards-FE Cabs-Misc Specialties 10 0 01JUL13 15JUL13 9
INT1480 Casework Elec Branch Wiring 10 0 09JUL13 22JUL13 9
Restroom FinishesINT1500 WP - Tile Setting Beds - Floor Drains 15 0 26APR13 16MAY13 2
INT1510 Tile - Walls 10 0 10MAY13 23MAY13 2
INT1520 Tile - Floors 10 0 24MAY13 07JUN13 2
INT1530 Plumbing Fixtures 10 0 10JUN13 21JUN13 2
INT1540 Plumbing Trim & Connections 10 0 17JUN13 28JUN13 2
INT1550 Toilet Partitions & Accys 10 0 01JUL13 15JUL13 2
INT1560 Final Paint 10 0 16JUL13 29JUL13 2
INT1570 HVAC Registers & Finish 5 0 23JUL13 29JUL13 2
INT1580 Elec Devices & Finish 5 0 25JUL13 31JUL13 2
FinishesINT1615 Final Paint 15 0 10JUN13 28JUN13 2
INT1620 FRP Panels 10 0 17JUN13 28JUN13 2
INT1625 VCT, RSF & Carpet & Base 10 0 19JUN13 02JUL13 2
INT1630 Signage - Window Treatment - Misc Fin Spec 20 0 19JUN13 17JUL13 7
INT1635 Finish Hardware Completion 10 0 26JUN13 10JUL13 2
INT1640 Plum Finish 10 0 11JUL13 24JUL13 7
INT1645 HVAC & Controls Finish 10 0 18JUL13 31JUL13 2
INT1650 Elec Exit Signs, Devices & Finish 10 0 11JUL13 24JUL13 7
Electrical Equipment RoomsSignal & Com Systems Equipment & TerminationsINT1740 Elec Equip Room Cable Tray 15 0 19APR13 09MAY13 4
INT1741 Elec Equip Rm Plywood Backboards 5 0 10MAY13 16MAY13 4
2011 2012 2013 2014 2015
Casework Cabinets & Shelving
Lab Casework Cabinets & Furnishings
Laboratory Fume Hoods
Casework Tops
Lab Casework Tops & Sinks
Misc Laboratory Equipment
Doors & Initial Hardware
Sectional Doors
Interior Glazing
Finish Carpentry
Casework Elec Power Branch
Casework Elec Data-Signal-Com Branch
Casework Plum Fixtures, Trim & Connections
Tack/Markerboards-FE Cabs-Misc Specialties
Casework Elec Branch Wiring
WP - Tile Setting Beds - Floor Drains
Tile - Walls
Tile - Floors
Plumbing Fixtures
Plumbing Trim & Connections
Toilet Partitions & Accys
Final Paint
HVAC Registers & Finish
Elec Devices & Finish
Final Paint
FRP Panels
VCT, RSF & Carpet & Base
Signage - Window Treatment - Misc Fin Spec
Finish Hardware Completion
Plum Finish
HVAC & Controls Finish
Elec Exit Signs, Devices & Finish
Elec Equip Room Cable Tray
Elec Equip Rm Plywood Backboards
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 19 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Signal & Com Systems Equipment & TerminationsINT1742 Elec TeleData Systems Panels, Racks & Equip 15 0 17MAY13 07JUN13 4
INT1743 Elec PA Systems Panels, Racks & Equip 15 0 24MAY13 14JUN13 4
INT1744 Elec Clock System Racks & Equip 10 0 03JUN13 14JUN13 4
INT1745 Elec Security Systems Panels, Racks & Equip 15 0 10JUN13 28JUN13 4
INT1746 Elec TeleData SystemsTerminations 15 0 01JUL13 22JUL13 4
INT1747 Elec PA Systems Cable Terminations 15 0 01JUL13 22JUL13 19
INT1748 Elec Clock System Cable Terminations 10 0 09JUL13 22JUL13 9
INT1749 Elec Security Systems Cable Terminations 15 0 25JUL13 14AUG13 7
Fire Alarm System Equipment & TerminationsINT1750 Elec Fire Alarm Panels 15 0 17MAY13 07JUN13 19
INT1755 Fire Alarm Terminations 15 0 10JUN13 28JUN13 19
Electrical Equipment & TerminationsINT1732 Elec Panels 10 0 26APR13 09MAY13 4
INT1733 Elec Feeders 15 0 03MAY13 23MAY13 4
INT1734 Elec Feeder Termination 15 0 24MAY13 14JUN13 4
INT1735 Elec Panel Breakers & Branch Terminations 10 0 17JUN13 28JUN13 4
INT1736 Elec Panel Covers & Directories 10 0 01JUL13 15JUL13 4
Second LevelOverallStartINT2000 Start 0 0 28NOV12 2
Interior FireproofingINT2010 Mtl Stud Stickers & Top Tracks 10 0 28NOV12 11DEC12 2
INT2020 MEP Supports 10 0 05DEC12 18DEC12 2
INT2030 Misc Metal, & Pefab Supports 10 0 05DEC12 18DEC12 2
INT2040 Cementitious Fireproofing 10 0 19DEC12 03JAN13 2
MEP Vertical ShaftsINT2050 Intial Shaftwall Assy 10 0 04JAN13 17JAN13 2
INT2052 Plumbing - Drain Waste Vent 10 0 18JAN13 31JAN13 41
INT2054 Plumbing - Water, IW, & NGas 10 0 18JAN13 31JAN13 41
INT2060 Fire Sprinklers & Risers 15 0 24JAN13 13FEB13 2
INT2062 Plum Insl & Finish 10 0 25JAN13 07FEB13 41
INT2063 Elec Feeders 10 0 31JAN13 13FEB13 2
INT2070 HVAC Ducts 15 0 07FEB13 27FEB13 2
INT2071 HVAC Hydronic Piping 10 0 28FEB13 13MAR13 2
INT2072 HVAC Duct Testing 10 0 07MAR13 20MAR13 2
INT2075 HVAC Refrigerant Piping 5 0 14MAR13 20MAR13 2
INT2080 HVAC Insul & Finish 10 0 21MAR13 03APR13 2
2011 2012 2013 2014 2015
Elec TeleData Systems Panels, Racks & Equip
Elec PA Systems Panels, Racks & Equip
Elec Clock System Racks & Equip
Elec Security Systems Panels, Racks & Equip
Elec TeleData SystemsTerminations
Elec PA Systems Cable Terminations
Elec Clock System Cable Terminations
Elec Security Systems Cable Terminations
Elec Fire Alarm Panels
Fire Alarm Terminations
Elec Panels
Elec Feeders
Elec Feeder Termination
Elec Panel Breakers & Branch Terminations
Elec Panel Covers & Directories
Start
Mtl Stud Stickers & Top Tracks
MEP Supports
Misc Metal, & Pefab Supports
Cementitious Fireproofing
Intial Shaftwall Assy
Plumbing - Drain Waste Vent
Plumbing - Water, IW, & NGas
Fire Sprinklers & Risers
Plum Insl & Finish
Elec Feeders
HVAC Ducts
HVAC Hydronic Piping
HVAC Duct Testing
HVAC Refrigerant Piping
HVAC Insul & Finish
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 20 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
MEP Vertical ShaftsINT2085 HVAC Controls 10 0 21MAR13 03APR13 2
INT2090 Drywall Shaftwall Assy 10 0 28MAR13 10APR13 2
Overhead RoughINT2100 OH Plumbing - Drain Waste Vent 10 0 04JAN13 17JAN13 2
INT2105 OH Plumbing - Water, IW, & NGas 15 0 11JAN13 31JAN13 2
INT2110 OH HVAC Equip 15 0 18JAN13 07FEB13 2
INT2115 OH Elec Feeders 15 0 25JAN13 14FEB13 27
INT2120 OH Plum Insl & Finish 10 0 01FEB13 14FEB13 2
INT2125 OH Fire Sprinklers & Risers 15 0 08FEB13 28FEB13 2
INT2130 OH HVAC Duct 10 0 15FEB13 28FEB13 2
INT2135 OH HVAC Refrigerant Piping 5 0 22FEB13 28FEB13 2
INT2140 OH HVAC Controls 10 0 01MAR13 14MAR13 2
INT2145 OH Elec Power & Lighting Branch 10 0 08MAR13 21MAR13 2
INT2150 OH Elec FA & LV Branch 10 0 15MAR13 28MAR13 2
INT2155 OH HVAC Duct Testing 10 0 22MAR13 04APR13 2
INT2160 OH HVAC Insul & Finish 10 0 04APR13 17APR13 2
Classrooms, Offices, & LabsPartitions & SoffitsINT2210 Metal Studs & HM Frames 15 0 04JAN13 24JAN13 12
INT2215 HVAC Refrigerant Piping 15 0 17JAN13 06FEB13 12
INT2220 HVAC Controls 10 0 11JAN13 24JAN13 16
INT2225 Ro Plum - Fixture Carriers 10 0 18JAN13 31JAN13 16
INT2230 Ro Plum - Drain Waste Vent 15 0 25JAN13 14FEB13 16
INT2235 Ro Plum - Water, IW, & NGas 15 0 07FEB13 27FEB13 12
INT2240 Elec Feeders 10 0 14FEB13 27FEB13 12
INT2245 Elec Power & Lighting Branch 15 0 28FEB13 20MAR13 12
INT2250 Elec FA & Low Voltage Branch 15 0 07MAR13 27MAR13 12
INT2260 Plum Insl & Finish 10 0 14MAR13 27MAR13 12
INT2265 Insulation & Drywall 10 0 21MAR13 03APR13 12
INT2268 Elec Branch Wiring 20 0 21MAR13 17APR13 12
INT2270 Firestop, Tape & Finish Drywall 10 0 11APR13 24APR13 2
INT2275 Initial Paint 10 0 18APR13 01MAY13 2
Exposed OverheadINT2280 Initial Paint 10 0 18APR13 01MAY13 10
INT2285 Fire Sprinkler Heads 10 0 02MAY13 15MAY13 10
INT2290 HVAC Registers 10 0 16MAY13 30MAY13 10
INT2295 Light Fixtures & Connections 15 0 31MAY13 20JUN13 10
2011 2012 2013 2014 2015
HVAC Controls
Drywall Shaftwall Assy
OH Plumbing - Drain Waste Vent
OH Plumbing - Water, IW, & NGas
OH HVAC Equip
OH Elec Feeders
OH Plum Insl & Finish
OH Fire Sprinklers & Risers
OH HVAC Duct
OH HVAC Refrigerant Piping
OH HVAC Controls
OH Elec Power & Lighting Branch
OH Elec FA & LV Branch
OH HVAC Duct Testing
OH HVAC Insul & Finish
Metal Studs & HM Frames
HVAC Refrigerant Piping
HVAC Controls
Ro Plum - Fixture Carriers
Ro Plum - Drain Waste Vent
Ro Plum - Water, IW, & NGas
Elec Feeders
Elec Power & Lighting Branch
Elec FA & Low Voltage Branch
Plum Insl & Finish
Insulation & Drywall
Elec Branch Wiring
Firestop, Tape & Finish Drywall
Initial Paint
Initial Paint
Fire Sprinkler Heads
HVAC Registers
Light Fixtures & Connections
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 21 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Drywall CeilingsINT2300 Metal Stud & CRS Framing 10 0 08MAR13 21MAR13 11
INT2305 Elec Light Fixture Cans 10 0 15MAR13 28MAR13 11
INT2310 HVAC Drops 15 0 22MAR13 11APR13 11
INT2315 Elec Power & Lighting Branch 10 0 22MAR13 04APR13 11
INT2320 Elec FA & Low Voltage Branch 10 0 29MAR13 11APR13 11
INT2325 Drywall 10 0 18APR13 01MAY13 2
INT2330 Elec Branch Wiring 20 0 02MAY13 30MAY13 15
INT2335 Fire Sprinkler Drops & Heads 10 0 23APR13 06MAY13 2
INT2340 Tape & Finish Drywall 10 0 30APR13 13MAY13 2
INT2345 Initial Paint 10 0 07MAY13 20MAY13 2
INT2350 HVAC Registers & Grills 10 0 21MAY13 04JUN13 22
INT2355 Fire Sprinkler Trim 10 0 21MAY13 04JUN13 22
INT2360 Elec Light Fixture Finish 10 0 31MAY13 13JUN13 15
Signal, Communications & Fire Alarm SystemsINT2365 Elec Fire Alarm System Cables 10 0 21MAY13 04JUN13 32
INT2370 Elec Fire Alarm System Devices & Connections 10 0 29MAY13 11JUN13 32
INT2375 Elec TeleData System Cables 10 0 19JUN13 02JUL13 2
INT2380 Elec Security Systems Cables 10 0 19JUN13 02JUL13 12
INT2385 Elec AV Systems Cables 10 0 26JUN13 10JUL13 7
INT2390 Elec TV System Cables 10 0 03JUL13 17JUL13 2
INT2395 Elec TeleData/AV/TV/Sec Devices & Connections 10 0 11JUL13 24JUL13 2
Suspended Acoustic CeilingsINT2400 Fire Shutters 15 0 25APR13 15MAY13 5
INT2402 Projection Screens 5 0 16MAY13 22MAY13 5
INT2405 Ceiling Grid 15 0 23MAY13 13JUN13 5
INT2410 Fire Sprinkler Drops & Heads 10 0 28MAY13 10JUN13 30
INT2415 Grid Mtd & Pendant Light Fixtures 10 0 28MAY13 10JUN13 5
INT2420 Elec Tile Mtd FA-Com Devices 10 0 31MAY13 13JUN13 7
INT2425 Elec Lighting Branch Conduit & Boxes 15 0 04JUN13 24JUN13 5
INT2430 Elec FA & Low Voltage Branch Conduit & Boxes 10 0 07JUN13 20JUN13 7
INT2431 Elec Branch Wiring 20 0 25JUN13 23JUL13 5
INT2435 Acoustic Tile 10 0 10JUL13 23JUL13 5
INT2440 Fire Sprinkler Trim 10 0 15JUL13 26JUL13 5
Doors Casework Fixtures EquipmentINT2445 Casework Cabinets & Shelving 15 0 02MAY13 22MAY13 5
INT2446 Lab Casework Cabinets & Furnishings 15 0 02MAY13 22MAY13 2
INT2447 Laboratory Fume Hoods 10 0 09MAY13 22MAY13 7
INT2450 Casework Tops 15 0 09MAY13 30MAY13 12
2011 2012 2013 2014 2015
Metal Stud & CRS Framing
Elec Light Fixture Cans
HVAC Drops
Elec Power & Lighting Branch
Elec FA & Low Voltage Branch
Drywall
Elec Branch Wiring
Fire Sprinkler Drops & Heads
Tape & Finish Drywall
Initial Paint
HVAC Registers & Grills
Fire Sprinkler Trim
Elec Light Fixture Finish
Elec Fire Alarm System Cables
Elec Fire Alarm System Devices & Connections
Elec TeleData System Cables
Elec Security Systems Cables
Elec AV Systems Cables
Elec TV System Cables
Elec TeleData/AV/TV/Sec Devices & Connections
Fire Shutters
Projection Screens
Ceiling Grid
Fire Sprinkler Drops & Heads
Grid Mtd & Pendant Light Fixtures
Elec Tile Mtd FA-Com Devices
Elec Lighting Branch Conduit & Boxes
Elec FA & Low Voltage Branch Conduit & Boxes
Elec Branch Wiring
Acoustic Tile
Fire Sprinkler Trim
Casework Cabinets & Shelving
Lab Casework Cabinets & Furnishings
Laboratory Fume Hoods
Casework Tops
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 22 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Doors Casework Fixtures EquipmentINT2452 Lab Casework Tops & Sinks 15 0 09MAY13 30MAY13 2
INT2453 Misc Laboratory Equipment 10 0 16MAY13 30MAY13 2
INT2455 Doors & Initial Hardware 15 0 16MAY13 06JUN13 15
INT2456 Sectional Doors 5 0 07JUN13 13JUN13 15
INT2457 Interior Glazing 5 0 07JUN13 13JUN13 22
INT2458 Finish Carpentry 15 0 31MAY13 20JUN13 17
INT2460 Casework Elec Power Branch & Boxes 10 0 31MAY13 13JUN13 2
INT2465 Casework Elec Data-Signal-Com Branch & Boxes 15 0 29MAY13 18JUN13 2
INT2470 Casework Plum Fixtures, Trim & Connections 10 0 31MAY13 13JUN13 15
INT2475 Tack/Markerboards-FE Cabs-Misc Specialties 10 0 21JUN13 05JUL13 17
INT2480 Casework Elec Branch Wiring 10 0 26JUN13 10JUL13 17
Restroom FinishesINT2500 WP - Tile Setting Beds - Floor Drains 15 0 21MAY13 11JUN13 2
INT2510 Tile - Walls 15 0 29MAY13 18JUN13 2
INT2520 Tile - Floors 10 0 05JUN13 18JUN13 2
INT2530 Plumbing Fixtures 10 0 19JUN13 02JUL13 2
INT2540 Plumbing Trim & Connections 5 0 26JUN13 02JUL13 2
INT2550 Toilet Partitions & Accys 10 0 03JUL13 17JUL13 2
INT2560 Final Paint 5 0 18JUL13 24JUL13 2
INT2570 HVAC Registers & Finish 5 0 25JUL13 31JUL13 2
INT2580 Elec Devices & Finish 5 0 25JUL13 31JUL13 2
FinishesINT2620 Final Paint 10 0 21JUN13 05JUL13 10
INT2622 FRP Panels 5 0 28JUN13 05JUL13 15
INT2625 VCT, RSF & Carpet & Base 10 0 28JUN13 12JUL13 10
INT2630 Signage - Window Treatment - Misc Fin Spec 15 0 28JUN13 19JUL13 10
INT2635 Finish Hardware Completion 10 0 08JUL13 19JUL13 10
INT2640 Plum Finish 5 0 08JUL13 12JUL13 15
INT2645 HVAC & Controls Finish 10 0 08JUL13 19JUL13 10
INT2650 Elec Exit Signs, Devices & Finish 10 0 08JUL13 19JUL13 10
Electrical Equipment RoomsSignal & Com Systems Equipment & TerminationsINT2740 Elec Equip Room Cable Tray 15 0 02MAY13 22MAY13 10
INT2741 Elec Equip Rm Plywood Backboards 5 0 23MAY13 30MAY13 10
INT2742 Elec TeleData Systems Panels, Racks & Equip 15 0 31MAY13 20JUN13 10
INT2743 Elec PA Systems Panels, Racks & Equip 15 0 31MAY13 20JUN13 15
INT2744 Elec Clock System Racks & Equip 5 0 31MAY13 06JUN13 30
INT2745 Elec Security Systems Panels, Racks & Equip 15 0 31MAY13 20JUN13 10
2011 2012 2013 2014 2015
Lab Casework Tops & Sinks
Misc Laboratory Equipment
Doors & Initial Hardware
Sectional Doors
Interior Glazing
Finish Carpentry
Casework Elec Power Branch & Boxes
Casework Elec Data-Signal-Com Branch & Boxes
Casework Plum Fixtures, Trim & Connections
Tack/Markerboards-FE Cabs-Misc Specialties
Casework Elec Branch Wiring
WP - Tile Setting Beds - Floor Drains
Tile - Walls
Tile - Floors
Plumbing Fixtures
Plumbing Trim & Connections
Toilet Partitions & Accys
Final Paint
HVAC Registers & Finish
Elec Devices & Finish
Final Paint
FRP Panels
VCT, RSF & Carpet & Base
Signage - Window Treatment - Misc Fin Spec
Finish Hardware Completion
Plum Finish
HVAC & Controls Finish
Elec Exit Signs, Devices & Finish
Elec Equip Room Cable Tray
Elec Equip Rm Plywood Backboards
Elec TeleData Systems Panels, Racks & Equip
Elec PA Systems Panels, Racks & Equip
Elec Clock System Racks & Equip
Elec Security Systems Panels, Racks & Equip
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 23 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Signal & Com Systems Equipment & TerminationsINT2746 Elec TeleData SystemsTerminations 15 0 03JUL13 24JUL13 2
INT2747 Elec PA Systems Cable Terminations 15 0 03JUL13 24JUL13 7
INT2748 Elec Clock System Cable Terminations 10 0 11JUL13 24JUL13 7
INT2749 Elec Security Systems Cable Terminations 15 0 11JUL13 31JUL13 7
Fire Alarm System Equipment & TerminationsINT2750 Elec Fire Alarm Panels 10 0 31MAY13 13JUN13 20
INT2755 Fire Alarm Terminations 10 0 14JUN13 27JUN13 20
Electrical Equipment & TerminationsINT2730 Elec Switchboards 10 0 25APR13 08MAY13 25
INT2732 Elec Panels 10 0 02MAY13 15MAY13 25
INT2733 Elec Feeders 10 0 09MAY13 22MAY13 30
INT2734 Elec Feeder Termination 10 0 16MAY13 30MAY13 25
INT2735 Elec Panel Breakers & Branch Terminations 10 0 16MAY13 30MAY13 25
INT2736 Elec Panel Covers & Directories 10 0 31MAY13 13JUN13 25
CompletionINT0990 Area Completion 0 0 31JUL13 2
ElevatorsALL OverallElevatorEL0000 Start 0 0 26MAR13 22
EL0100 Elevator - Pit Ladder & Sill Support L's 5 0 26MAR13 01APR13 22
EL0110 Elevator - Entrance Frames 5 0 02APR13 08APR13 22
EL0120 Elevator - Rails 15 0 25APR13 15MAY13 15
EL0130 Elevator - Equipment 15 0 25APR13 15MAY13 10
EL0140 Elevator - Platforms 15 0 16MAY13 06JUN13 10
EL0150 Elevator - Cabs 15 0 31MAY13 20JUN13 10
EL0160 Elevator - Entrances 15 0 14JUN13 05JUL13 10
EL0170 Elevator - Finish 10 0 28JUN13 12JUL13 10
EL0190 Area Completion 0 0 12JUL13 10
Site ImprovementsGrade LevelSite AreasStartSI0000 Start 0 0 26JUL12 2
UG Utilities - InteruptionsSI0100 UG Sanitary Sewer 15 0 26JUL12 15AUG12 2
SI0110 UG Storm Drain 15 0 16AUG12 06SEP12 2
2011 2012 2013 2014 2015
Elec TeleData SystemsTerminations
Elec PA Systems Cable Terminations
Elec Clock System Cable Terminations
Elec Security Systems Cable Terminations
Elec Fire Alarm Panels
Fire Alarm Terminations
Elec Switchboards
Elec Panels
Elec Feeders
Elec Feeder Termination
Elec Panel Breakers & Branch Terminations
Elec Panel Covers & Directories
Area Completion
Start
Elevator - Pit Ladder & Sill Support L's
Elevator - Entrance Frames
Elevator - Rails
Elevator - Equipment
Elevator - Platforms
Elevator - Cabs
Elevator - Entrances
Elevator - Finish
Area Completion
Start
UG Sanitary Sewer
UG Storm Drain
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 24 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
UG Utilities - InteruptionsSI0120 UG Fire Water 15 0 07SEP12 27SEP12 2
SI0122 UG Fire Water Valve Vaults 15 0 14SEP12 04OCT12 7
SI0124 UG Fire Water PIV & FDC 15 0 14SEP12 04OCT12 7
SI0130 UG Domestic Water 10 0 28SEP12 11OCT12 2
SI0140 UG Natural Gas 10 0 12OCT12 25OCT12 2
SI0150 Elec UG Conduits & Boxes 10 0 26OCT12 08NOV12 2
SI0151 Elec UG Duct Banks & Boxes - Power 15 0 09NOV12 04DEC12 2
SI0152 Elec UG Duct Banks & Boxes - FA, & Com Systems 15 0 19NOV12 11DEC12 41
SI0153 Elec UG Conductors 15 0 05DEC12 26DEC12 41
SI0154 Elec UG FA & Com System Cables 10 0 12DEC12 26DEC12 41
Main Electrical Service EnclosureUnderground Utilities - ElectricalSI1110 Elec UG Primary Conduits & Boxes 15 0 09NOV12 04DEC12 2
SI1120 Elec UG Branch Conduits 15 0 05DEC12 26DEC12 2
SI1130 Elec UG Grounding 10 0 27DEC12 10JAN13 31
StructuresSI1140 Ro Grading/Grade Restoration 5 0 27DEC12 03JAN13 2
SI1150 Conc Fnds - Conc Walls 15 0 04JAN13 24JAN13 2
SI1160 Conc Fnds - Gate Posts 10 0 11JAN13 24JAN13 2
SI1170 Conc Fnds - Removable Bollards 10 0 17JAN13 30JAN13 2
SI1180 Conc Walls 15 0 31JAN13 20FEB13 2
SI1190 Conc Slab on Grade 15 0 21FEB13 13MAR13 2
SI1200 Conc Equip Pads & Bollards 10 0 14MAR13 27MAR13 2
SI1210 Steel Fences & Gates 15 0 28MAR13 17APR13 65
SI2130 Sealants & Initial Paint 10 0 18APR13 01MAY13 68
Electrical Equipment & TerminationsSI2150 Elec Main Switchgear Set & Anchor 5 0 28MAR13 03APR13 5
SI2151 SCE Switch & Transformer Set & Anchor 5 0 04APR13 10APR13 5
SI2152 Elec Main Switchgear 15 0 11APR13 01MAY13 5
SI2153 SCE Switch & Transformer 15 0 02MAY13 22MAY13 5
SI2154 Elec Secondary Feeder Term (Main Switchgear) 5 0 23MAY13 30MAY13 5
SI2155 Elec Misc Bonding, Connections, & Finish 10 0 31MAY13 13JUN13 5
SI2156 SCE Inspection & Punch List 5 0 14JUN13 20JUN13 5
SI2157 Elec SCE Punch List Work 10 0 21JUN13 05JUL13 5
SI2158 SCE Primary & Secondary Feeder Term 5 0 08JUL13 12JUL13 5
SI2159 SCE Elec Energize Main Switchgear 0 0 15JUL13 12JUL13 5
2011 2012 2013 2014 2015
UG Fire Water
UG Fire Water Valve Vaults
UG Fire Water PIV & FDC
UG Domestic Water
UG Natural Gas
Elec UG Conduits & Boxes
Elec UG Duct Banks & Boxes - Power
Elec UG Duct Banks & Boxes - FA, & Com Systems
Elec UG Conductors
Elec UG FA & Com System Cables
Elec UG Primary Conduits & Boxes
Elec UG Branch Conduits
Elec UG Grounding
Ro Grading/Grade Restoration
Conc Fnds - Conc Walls
Conc Fnds - Gate Posts
Conc Fnds - Removable Bollards
Conc Walls
Conc Slab on Grade
Conc Equip Pads & Bollards
Steel Fences & Gates
Sealants & Initial Paint
Elec Main Switchgear Set & Anchor
SCE Switch & Transformer Set & Anchor
Elec Main Switchgear
SCE Switch & Transformer
Elec Secondary Feeder Term (Main Switchgear)
Elec Misc Bonding, Connections, & Finish
SCE Inspection & Punch List
Elec SCE Punch List Work
SCE Primary & Secondary Feeder Term
SCE Elec Energize Main Switchgear
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 25 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Building AreasStructuresSI2100 Ro Grading/Grade Restoration 4 0 22MAY13 28MAY13 6
SI2210 Conc Fnds - Conc Walls 10 0 29MAY13 11JUN13 6
SI2220 Conc Fnds - Conc Benches 5 0 31MAY13 06JUN13 14
SI2230 Conc Fnds - Fences & Gates 5 0 31MAY13 06JUN13 14
SI2240 Conc Fnds - Sign Posts 5 0 31MAY13 06JUN13 14
SI2250 Conc Fnds - Handrails 5 0 31MAY13 06JUN13 14
SI2260 Conc Walls & Benches 5 0 12JUN13 18JUN13 6
SI2270 Conc Walls - Cure/Strip/Patch 5 0 19JUN13 25JUN13 17
Concrete Flatwork & PavingSI2300 Conc Curbs & Swales 5 0 29MAY13 04JUN13 9
SI2310 Conc Curb Cure & Backfill 5 0 05JUN13 11JUN13 9
SI2320 Adjust Utilities to Final Grade 5 0 05JUN13 11JUN13 9
SI2325 Undersidewalk Parkway Drains 5 0 07JUN13 13JUN13 9
SI2326 UG Storm Drains & CBs 5 0 07JUN13 13JUN13 9
SI2330 Fine Grade for CIP Conc Flatwork 5 0 19JUN13 25JUN13 6
SI2335 Detectable Warning Surfacing 3 0 26JUN13 28JUN13 23
SI2340 Conc Ramps, Steps, Flatwork & Pads 20 0 26JUN13 24JUL13 6
SI2350 Conc Flatwork Final Cure & Backfill 10 0 11JUL13 24JUL13 10
Irrigation SystemSI2400 UG Irrigation Laterals - Underslab 5 0 12JUN13 18JUN13 9
SI2410 UG Irrigation Laterals & Risers - Planted Areas 10 0 18JUL13 31JUL13 7
SI2420 Flush & Install Heads 5 0 01AUG13 07AUG13 7
LandscapingSI2430 Clean Landcape Areas 2 0 11JUL13 12JUL13 6
SI2440 Soil Preparation, Topsoil & Finish Grading 3 0 15JUL13 17JUL13 6
SI2450 Landscaping - Trees 15 0 18JUL13 07AUG13 6
SI2460 Landscaping - Shrubs 15 0 19JUL13 08AUG13 6
SI2470 Landscaping - Misc 10 0 26JUL13 08AUG13 6
Plumbing SystemsSI2500 Plum Gas Meter & PRV 5 0 03JUL13 10JUL13 7
SI2510 Plum Gas Seismic SOV 5 0 11JUL13 17JUL13 7
SI2520 Plum Acid Waste Tank 5 0 18JUL13 24JUL13 7
SI2530 Plum Piping & Connections 5 0 25JUL13 31JUL13 7
SI2540 Plum Controls 5 0 01AUG13 07AUG13 7
Railing-Gates-Fencing-SpecialtiesSI2600 Embedded Handrails 5 0 11JUL13 17JUL13 15
SI2610 Steel Sliding Gates 10 0 18JUL13 31JUL13 7
2011 2012 2013 2014 2015
Ro Grading/Grade Restoration
Conc Fnds - Conc Walls
Conc Fnds - Conc Benches
Conc Fnds - Fences & Gates
Conc Fnds - Sign Posts
Conc Fnds - Handrails
Conc Walls & Benches
Conc Walls - Cure/Strip/Patch
Conc Curbs & Swales
Conc Curb Cure & Backfill
Adjust Utilities to Final Grade
Undersidewalk Parkway Drains
UG Storm Drains & CBs
Fine Grade for CIP Conc Flatwork
Detectable Warning Surfacing
Conc Ramps, Steps, Flatwork & Pads
Conc Flatwork Final Cure & Backfill
UG Irrigation Laterals - Underslab
UG Irrigation Laterals & Risers - Planted Areas
Flush & Install Heads
Clean Landcape Areas
Soil Preparation, Topsoil & Finish Grading
Landscaping - Trees
Landscaping - Shrubs
Landscaping - Misc
Plum Gas Meter & PRV
Plum Gas Seismic SOV
Plum Acid Waste Tank
Plum Piping & Connections
Plum Controls
Embedded Handrails
Steel Sliding Gates
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 26 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Railing-Gates-Fencing-SpecialtiesSI2620 Steel Fences & Gates 15 0 11JUL13 31JUL13 7
SI2625 Chainlink Fences & Gates 15 0 02JUL13 23JUL13 13
SI2635 Trelliage System 15 0 11JUL13 31JUL13 10
SI2640 Site Railings 15 0 11JUL13 31JUL13 10
FinishesSI2700 Sealants & Final Paint 5 0 25JUL13 31JUL13 10
SI2710 Playground Surface System 5 0 29JUL13 02AUG13 10
SI2715 Signage - Misc Finish Specialties 5 0 29JUL13 02AUG13 10
SI2720 Gate Hardware & Accys 5 0 01AUG13 07AUG13 7
CompletionSI2900 Area Completion 0 0 07AUG13 7
Parking Areas NorthStartSI3000 Start 0 0 20MAY13 4
AllSI3100 Ro Grading/Grade Restoration 2 0 20MAY13 21MAY13 4
SI3210 UG Electrical 5 0 22MAY13 29MAY13 4
SI3230 Conc Fnds - Light Poles 3 0 24MAY13 29MAY13 4
SI3240 Conc Fnds - Sign Posts 3 0 24MAY13 29MAY13 4
SI3300 Conc Curbs, Gutters, & Drive Approaches 5 0 30MAY13 05JUN13 4
SI3310 Conc Curb Cure & Backfill 3 0 06JUN13 10JUN13 4
SI3320 Adjust Utilities to Final Grade 3 0 06JUN13 10JUN13 7
SI3325 Undersidewalk Parkway Drains 3 0 10JUN13 12JUN13 7
SI3326 UG Storm Drains 2 0 10JUN13 11JUN13 8
SI3327 UG Irrigation Laterals - Underslab 5 0 11JUN13 17JUN13 4
SI3330 Fine Grade & Certifications 2 0 18JUN13 19JUN13 4
SI3335 Detectable Warning Surfacing 2 0 20JUN13 21JUN13 12
SI3340 Conc Ramps & Flatwork 10 0 20JUN13 03JUL13 4
SI3350 Conc Cure 5 0 05JUL13 11JUL13 4
SI3360 Base & Asphalt Paving 5 0 12JUL13 18JUL13 6
SI3370 Aphalt Paving Cure 5 0 19JUL13 25JUL13 6
SI3375 Light Poles & Connections 5 0 26JUL13 01AUG13 6
SI3376 Elec Conductors/Wiring/Connections 5 0 02AUG13 08AUG13 6
SI3380 Traffic Wheel Stops 2 0 26JUL13 29JUL13 8
SI3390 Pavement Markings 2 0 30JUL13 31JUL13 8
SI3410 UG Irrigation Laterals & Risers - Planted Areas 5 0 12JUL13 18JUL13 4
SI3420 Flush & Install Heads 5 0 19JUL13 25JUL13 4
SI3430 Clean Landcape Areas 2 0 26JUL13 29JUL13 4
2011 2012 2013 2014 2015
Steel Fences & Gates
Chainlink Fences & Gates
Trelliage System
Site Railings
Sealants & Final Paint
Playground Surface System
Signage - Misc Finish Specialties
Gate Hardware & Accys
Area Completion
Start
Ro Grading/Grade Restoration
UG Electrical
Conc Fnds - Light Poles
Conc Fnds - Sign Posts
Conc Curbs, Gutters, & Drive Approaches
Conc Curb Cure & Backfill
Adjust Utilities to Final Grade
Undersidewalk Parkway Drains
UG Storm Drains
UG Irrigation Laterals - Underslab
Fine Grade & Certifications
Detectable Warning Surfacing
Conc Ramps & Flatwork
Conc Cure
Base & Asphalt Paving
Aphalt Paving Cure
Light Poles & Connections
Elec Conductors/Wiring/Connections
Traffic Wheel Stops
Pavement Markings
UG Irrigation Laterals & Risers - Planted Areas
Flush & Install Heads
Clean Landcape Areas
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 27 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
AllSI3440 Soil Preparation, Topsoil & Finish Grading 2 0 30JUL13 31JUL13 4
SI3450 Landscaping - Trees 5 0 01AUG13 07AUG13 4
SI3460 Landscaping - Shrubs 5 0 02AUG13 08AUG13 4
SI3470 Landscaping - Misc 2 0 09AUG13 12AUG13 4
SI3700 Sealants & Final Paint 2 0 01AUG13 02AUG13 8
SI3715 Signage - Misc Finish Specialties 2 0 05AUG13 06AUG13 8
CompletionSI3900 Area Completion 0 0 12AUG13 4
Parking Areas SouthStartSI4000 Start 0 0 28MAR13 2
AllSI4002 Primary SWPP's Provisions 2 0 28MAR13 29MAR13 2
SI4005 Mark Removals & Protection Items 2 0 28MAR13 29MAR13 2
SI4010 Site Demolition & Removals 4 0 01APR13 04APR13 2
SI4100 Earthwork 2 0 05APR13 08APR13 2
SI4210 UG Fire Water 5 0 09APR13 15APR13 2
SI4220 UG Electrical 5 0 16APR13 22APR13 2
SI4230 Conc Fnds - Walls 5 0 23APR13 29APR13 2
SI4240 Conc Fnds - Light Poles 3 0 30APR13 02MAY13 2
SI4250 Conc Fnds - Sign Posts 3 0 30APR13 02MAY13 7
SI4300 Conc Walls 5 0 03MAY13 09MAY13 2
SI4310 Conc Walls Cure/Strip/Patch 5 0 10MAY13 16MAY13 2
SI4314 UG Irrigation Laterals - Underslab 5 0 17MAY13 23MAY13 14
SI4315 Conc Wall Waterproofing 5 0 17MAY13 23MAY13 2
SI4316 Conc Wall Drainage 5 0 24MAY13 31MAY13 2
SI4317 Conc Wall Backfill 3 0 03JUN13 05JUN13 2
SI4326 UG Storm Drains 4 0 06JUN13 11JUN13 2
SI4330 Fine Grade & Certifications 2 0 12JUN13 13JUN13 2
SI4335 Detectable Warning Surfacing 4 0 14JUN13 19JUN13 2
SI4340 Site Concrete 10 0 20JUN13 03JUL13 2
SI4350 Conc Cure 5 0 05JUL13 11JUL13 2
SI4355 Site Railings 4 0 12JUL13 17JUL13 16
SI4360 Base & Asphalt Paving 5 0 12JUL13 18JUL13 4
SI4370 Aphalt Paving Cure 5 0 19JUL13 25JUL13 4
SI4375 Light Poles & Connections 5 0 26JUL13 01AUG13 4
SI4376 Elec Conductors/Wiring/Connections 5 0 02AUG13 08AUG13 4
SI4380 Traffic Wheel Stops 2 0 26JUL13 29JUL13 6
2011 2012 2013 2014 2015
Soil Preparation, Topsoil & Finish Grading
Landscaping - Trees
Landscaping - Shrubs
Landscaping - Misc
Sealants & Final Paint
Signage - Misc Finish Specialties
Area Completion
Start
Primary SWPP's Provisions
Mark Removals & Protection Items
Site Demolition & Removals
Earthwork
UG Fire Water
UG Electrical
Conc Fnds - Walls
Conc Fnds - Light Poles
Conc Fnds - Sign Posts
Conc Walls
Conc Walls Cure/Strip/Patch
UG Irrigation Laterals - Underslab
Conc Wall Waterproofing
Conc Wall Drainage
Conc Wall Backfill
UG Storm Drains
Fine Grade & Certifications
Detectable Warning Surfacing
Site Concrete
Conc Cure
Site Railings
Base & Asphalt Paving
Aphalt Paving Cure
Light Poles & Connections
Elec Conductors/Wiring/Connections
Traffic Wheel Stops
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 28 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
AllSI4390 Pavement Markings 2 0 30JUL13 31JUL13 6
SI4410 UG Irrigation Laterals & Risers - Planted Areas 5 0 12JUL13 18JUL13 2
SI4420 Flush & Install Heads 5 0 19JUL13 25JUL13 2
SI4430 Clean Landcape Areas 2 0 26JUL13 29JUL13 2
SI4440 Soil Preparation, Topsoil & Finish Grading 2 0 30JUL13 31JUL13 2
SI4450 Landscaping - Trees 5 0 01AUG13 07AUG13 2
SI4460 Landscaping - Shrubs 5 0 02AUG13 08AUG13 2
SI4470 Landscaping - Misc 2 0 09AUG13 12AUG13 2
SI4700 Sealants & Final Paint 2 0 01AUG13 02AUG13 6
SI4715 Signage - Misc Finish Specialties 2 0 05AUG13 06AUG13 6
SI4720 Remove SWPPP Provisions 2 0 13AUG13 14AUG13 2
CompletionSI4500 Area Completion 0 0 14AUG13 2
Parking Areas ArtesiaStartSI5000 Start 0 0 04JAN13 16
AllSI5002 Primary SWPP's Provisions 2 0 04JAN13 07JAN13 16
SI5005 Mark Removals & Protection Items 2 0 04JAN13 07JAN13 16
SI5010 Site Demolition & Removals 4 0 08JAN13 11JAN13 16
SI5100 Earthwork 5 0 14JAN13 18JAN13 16
SI5120 UG Fire Water 5 0 21JAN13 25JAN13 16
SI5130 UG Electrical 5 0 28JAN13 01FEB13 16
SI5140 Conc Fnds - Walls 5 0 04FEB13 08FEB13 16
SI5150 Conc Fnds - Posts 3 0 11FEB13 13FEB13 16
SI5170 Conc Walls 5 0 14FEB13 20FEB13 16
SI5180 Conc Walls Cure/Strip/Patch 5 0 21FEB13 27FEB13 16
SI5190 UG Irrigation Laterals - Underslab 5 0 28FEB13 06MAR13 28
SI5200 Conc Wall Waterproofing 5 0 28FEB13 06MAR13 16
SI5210 Conc Wall Drainage 5 0 07MAR13 13MAR13 16
SI5220 Conc Wall Backfill 3 0 14MAR13 18MAR13 16
SI5230 UG Storm Drains 4 0 19MAR13 22MAR13 16
SI5240 Fine Grade & Certifications 2 0 25MAR13 26MAR13 16
SI5250 Detectable Warning Surfacing 4 0 27MAR13 01APR13 16
SI5260 Site Concrete 20 0 02APR13 29APR13 16
SI5270 Conc Cure 5 0 30APR13 06MAY13 16
SI5275 Lighting Devices & Connections 5 0 07MAY13 13MAY13 16
SI5276 Elec Conductors/Wiring/Connections 5 0 14MAY13 20MAY13 16
2011 2012 2013 2014 2015
Pavement Markings
UG Irrigation Laterals & Risers - Planted Areas
Flush & Install Heads
Clean Landcape Areas
Soil Preparation, Topsoil & Finish Grading
Landscaping - Trees
Landscaping - Shrubs
Landscaping - Misc
Sealants & Final Paint
Signage - Misc Finish Specialties
Remove SWPPP Provisions
Area Completion
Start
Primary SWPP's Provisions
Mark Removals & Protection Items
Site Demolition & Removals
Earthwork
UG Fire Water
UG Electrical
Conc Fnds - Walls
Conc Fnds - Posts
Conc Walls
Conc Walls Cure/Strip/Patch
UG Irrigation Laterals - Underslab
Conc Wall Waterproofing
Conc Wall Drainage
Conc Wall Backfill
UG Storm Drains
Fine Grade & Certifications
Detectable Warning Surfacing
Site Concrete
Conc Cure
Lighting Devices & Connections
Elec Conductors/Wiring/Connections
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 29 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
AllSI5280 Steel Railings & Guardrails 5 0 21MAY13 28MAY13 16
SI5285 Site Fencing 10 0 29MAY13 11JUN13 16
SI5286 Steel Gates & Hardware 10 0 12JUN13 25JUN13 16
SI5290 Asphalt Patching 5 0 21MAY13 28MAY13 17
SI5300 Aphalt Paving Cure 5 0 29MAY13 04JUN13 17
SI5340 Pavement Markings 2 0 05JUN13 06JUN13 17
SI5350 UG Irrigation Laterals & Risers - Planted Areas 10 0 07JUN13 20JUN13 17
SI5360 Flush & Install Heads 2 0 21JUN13 24JUN13 17
SI5370 Clean Landcape Areas 2 0 26JUN13 27JUN13 16
SI5380 Soil Preparation, Topsoil & Finish Grading 2 0 28JUN13 01JUL13 16
SI5390 Landscaping - Trees 10 0 02JUL13 16JUL13 16
SI5400 Landscaping - Shrubs 10 0 03JUL13 17JUL13 16
SI5410 Landscaping - Misc 2 0 11JUL13 12JUL13 16
SI5420 Sealants & Final Paint 5 0 15JUL13 19JUL13 16
SI5430 Signage - Misc Finish Specialties 2 0 22JUL13 23JUL13 16
SI5440 Remove SWPPP Provisions 2 0 24JUL13 25JUL13 16
CompletionSI5500 Area Completion 0 0 25JUL13 16
Temporary Fire LaneGrade LevelAthletic FieldsAllTFL0000 Start 0 0 04JAN13 36
TFL1002 Temporary Fencing 5 0 04JAN13* 10JAN13 36
TFL1004 Primary SWPP's Provisions 5 0 11JAN13* 17JAN13 36
TFL1006 Mark Removals & Protection Items 2 0 18JAN13 21JAN13 36
TFL1007 Relocate Irrigation Controller 5 0 22JAN13 28JAN13 36
TFL1008 Relocate Sewer Line 5 0 29JAN13 04FEB13 36
TFL1010 Demolition & Removals 10 0 05FEB13 18FEB13 36
TFL1045 Earthwork 10 0 19FEB13 04MAR13 36
TFL1050 UG Fire Water 15 0 05MAR13 25MAR13 36
TFL1055 Fire Hydrants & Service 10 0 19MAR13 01APR13 36
TFL1065 Conc Footings 10 0 02APR13 15APR13 36
TFL1070 Conc Walls 15 0 16APR13 06MAY13 36
TFL1071 Conc Walls Cure/Strip/Patch 5 0 07MAY13 13MAY13 36
TFL1072 Conc Wall Waterproofing 5 0 14MAY13 20MAY13 36
TFL1073 Conc Wall Drainage 5 0 17MAY13 23MAY13 36
TFL1074 Structural Backfill 3 0 24MAY13 29MAY13 36
2011 2012 2013 2014 2015
Steel Railings & Guardrails
Site Fencing
Steel Gates & Hardware
Asphalt Patching
Aphalt Paving Cure
Pavement Markings
UG Irrigation Laterals & Risers - Planted Areas
Flush & Install Heads
Clean Landcape Areas
Soil Preparation, Topsoil & Finish Grading
Landscaping - Trees
Landscaping - Shrubs
Landscaping - Misc
Sealants & Final Paint
Signage - Misc Finish Specialties
Remove SWPPP Provisions
Area Completion
Start
Temporary Fencing
Primary SWPP's Provisions
Mark Removals & Protection Items
Relocate Irrigation Controller
Relocate Sewer Line
Demolition & Removals
Earthwork
UG Fire Water
Fire Hydrants & Service
Conc Footings
Conc Walls
Conc Walls Cure/Strip/Patch
Conc Wall Waterproofing
Conc Wall Drainage
Structural Backfill
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 30 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
AllTFL1075 Site Concrete 10 0 30MAY13 12JUN13 36
TFL1085 Fine Grade & Certification 5 0 13JUN13 19JUN13 36
TFL1095 Base Temp Fire Lane 5 0 20JUN13 26JUN13 36
CompletionTFL1135 Area Completion 0 0 26JUN13 36
Test-Punch-Acceptance - DemobilizationAllAllHVAC CommissioingTPA0110 HVAC Equip Start-Up 5 0 16JUL13 22JUL13 4
TPA0120 HVAC System Commissioning 10 0 23JUL13 05AUG13 9
TPA0125 Building Flush Out 10 0 23JUL13 05AUG13 4
TPA0130 HVAC Test & Balance (Mech Complete) 10 0 30JUL13 12AUG13 4
Electrical CommissioningTPA0210 Energize Elec System 5 0 16JUL13 22JUL13 4
TPA0S20 Elec System Commissioning (Elec Complete) 10 0 23JUL13 05AUG13 9
Signal & Communications CommissioningTPA0310 Elec TeleData Systems Commissioning 10 0 25JUL13 07AUG13 2
TPA0320 Elec PA System Commissioning 10 0 25JUL13 07AUG13 7
TPA0330 Elec Clock System Commissioning 10 0 25JUL13 07AUG13 7
TPA0340 Elec Security Systems Commissioning 10 0 01AUG13 14AUG13 7
Elevator CommissioningTPA0410 Elevator Operational Adjustments & Pretesting 10 0 25JUL13 07AUG13 2
TPA0420 Elevator Test & Inspection 5 0 08AUG13 14AUG13 2
Plumbing CommissioningTPA0510 Plum Chorination 5 0 01AUG13 07AUG13 7
TPA0520 Plum Systems Commissioning 10 0 08AUG13 21AUG13 7
Fire Sprinkler CommissioingTPA0610 Fire Sprinkler System Commissioning 10 0 01AUG13 14AUG13 2
Fire Alarm CommissioningTPA0710 Fire Alarm Fundamental Commissioning 10 0 25JUL13 07AUG13 2
TPA0720 Fire Alarm Test & Insp 5 0 08AUG13 14AUG13 2
Final CleaningTPA0800 Interior Final Cleaning - First Pass 10 0 01AUG13 14AUG13 7
TPA0810 Interior Final Cleaning - Second Pass 10 0 08AUG13 21AUG13 7
Substantial Completion Punch ListTPA0900 Request SC Inspection 0 0 15AUG13 14AUG13 2
TPA0910 Interior SC Punch List Prep 5 0 15AUG13 21AUG13 4
2011 2012 2013 2014 2015
Site Concrete
Fine Grade & Certification
Base Temp Fire Lane
Area Completion
HVAC Equip Start-Up
HVAC System Commissioning
Building Flush Out
HVAC Test & Balance (Mech Complete)
Energize Elec System
Elec System Commissioning (Elec Complete)
Elec TeleData Systems Commissioning
Elec PA System Commissioning
Elec Clock System Commissioning
Elec Security Systems Commissioning
Elevator Operational Adjustments & Pretesting
Elevator Test & Inspection
Plum Chorination
Plum Systems Commissioning
Fire Sprinkler System Commissioning
Fire Alarm Fundamental Commissioning
Fire Alarm Test & Insp
Interior Final Cleaning - First Pass
Interior Final Cleaning - Second Pass
Request SC Inspection
Interior SC Punch List Prep
Bernards Builders-Management Services
Mira Costa High School Measure BB Campus Improvements
Sheet 31 of 31
ActivityID
ActivityDescription
CGS LOC BLD PredecessorsSuccessorsOR LVL AREADurCalID
RemDur
%Comp
LOC PHSELVL GRP EarlyStart
EarlyFinish
LateStartLate
FinishTotalFloat
Substantial Completion Punch ListTPA0920 Interior SC Punch List Work 10 0 16AUG13 29AUG13 4
TPA0930 Exterior SC Punch List Prep 5 0 20AUG13 26AUG13 2
TPA0940 Exterior SC Punch List Work 10 0 20AUG13 03SEP13 2
TPA0950 Demonstrations, Training & Close-Out 10 0 20AUG13 03SEP13 2
Overall CompletionOC1999 Phase 1 Completion 0 0 03SEP13 2
2011 2012 2013 2014 2015
Interior SC Punch List Work
Exterior SC Punch List Prep
Exterior SC Punch List Work
Demonstrations, Training & Close-Out
Phase 1 Completion
© Primavera Systems, Inc.
Start Date 07NOV11Finish Date 29DEC14Data Date 30NOV11Run Date 05DEC11 11:10
Early Bar
Float Bar
Progress Bar
Critical Activity
AS01
Mira Costa High SchoolMeasure BB Campus Improvements
Status Schedule
Sheet 31 of 31
Date Revision CheckedApproved