Upload
geraldtrumbule
View
218
Download
0
Embed Size (px)
Citation preview
7/29/2019 Still Building a Better Denver with Borrowed Money
1/12
Still Building a Better Citywith Borrowed Money
7/29/2019 Still Building a Better Denver with Borrowed Money
2/12
Office of the Auditor
Communications DivisionDenis Berckefeldt
Sharon Bailey, Ph.D.City and County of Denver
Dennis J. GallagherAuditor
7/29/2019 Still Building a Better Denver with Borrowed Money
3/12
has had a positive impact on Denvers
infrastructure and quality of life. And it has done so by accelerating the
completion of over 275 capital projects in just four years.
Denver has a long history of borrowing to build a better City. Since the turn of the
century, citizens have authorized the issuance of bonds to undertake a variety of
projects, which in turn have provided an improved quality of life. Denver votershave historically approved capital improvements for infrastructure (streets, sewers,
etc.), libraries, cultural facilities, parks, and recreation facilities. The issuance of
general obligation bonds are public decisions based on the vision of City leadership
and economic, political, and social landscapes. Increasing taxpayer debt has always
been subject to extensive debate, scrutiny of citizens and the media, controversies,
and even struggles in the courts. That is part of the democratic process and why the
undertaking of taxpayer debt is subject to the will of the people.
In 2004, Mayor John Hickenlooper appointed a 115-member Infrastructure Task Force to examine and
prioritize the Citys capital facility and infrastructure needs. In a process that lasted more than a yearand included input from more than 1,500 residents, the taskforce developed eight separate ballot
questions (the Better Denver Ballot Questions) authorizing debt in the aggregate principal amount of
$549,730,000. In November of 2007, Denvers citizens passed the ballot initiatives that established this
program and its bond financing. This program targeted City facilities, health and human services facilities
public safety facilities, cultural facilities, libraries, parks, and roads for improvement, preservation, and
renovation. A separate but companion ballot question, authorizing a 2.5-mill levy on all taxable property
was also approved at the same election in order to fund the restoration, rehabilitation, refurbishment
and replacement of the Citys capital infrastructure.
In January 2008, the City began implementing the program. In light of the economic downturn then occurring
Mayor Hickenlooper implemented an acceleration effort in October 2008 to begin construction projects
and speed the flow of construction dollars into the economy. The Better Denver Bond Program responded
by facilitating an aggressive contractor outreach program in November 2008. The City held a large event for
potential contractors in December 2008 at the Colorado Convention Center. Over 600 people attended! This
event, along with information on the Better Denver Bond Website, helped to stimulate awareness of and
interest in the projects from the design and construction community. This in turn generated extraordinary
competition, with many more bidders and proposals than projects typically receive. This competition drove
down pricing which resulted in the $20 million of savings that
enabled the creation of new projects. Those projects are set tocomplete by early 2014.
This report summarizes the progress, accomplishments, and
challenges of the Better Denver Bond Program. Overall, it is my
observation and belief that the Better Denver Bond Program
has stayed consistent with voter intent, was delivered on-time
and on-budget, and is providing Denvers citizens with quality
and value for their dollars. Additional factors contributing to the
7/29/2019 Still Building a Better Denver with Borrowed Money
4/12
overall success of the program include the commitment to communication, public outreach, transparency,
and the management of risk. The program has also integrated opportunities for disadvantaged and small
businesses, focused on sustainability, and incorporated public art into many projects. One of the Better
Denver Bond Programs most significant accomplishments has been to accelerate the delivery of the vast
majority of projects for completion in four years instead of the originally anticipated five years. This is a
great improvement over the ten years it took to complete bond
projects approved in the 1990s.
The Better Denver Bond Program has allowed us to invest in our
infrastructure, beautify our City, improve our quality of life, and
aid our economic recovery. Over 290 projects were initially slated
for design and construction. However, because of cost savings
generated during Program implementation, funds were leveraged
by the Bond Executive Committee and City Council to complete 321 existing projects and create additiona
contingency funds within each Program category.
The Better Denver Bond Program has had the added benefit of serving as an economic stimulus in this challenging
economy. It has helped the City put people to work and pumped millions of dollars into the local economy. Focompanies working on these bond projects, it has been very welcome at a time when design and construction
work was in short supply. Bond projects gave the local construction economy a much needed boost.
JOBSThe City used a combination of the American Recovery and Reinvestment Act (ARRA) and the Association of
General Contractors (AGC) calculations to establish the number of jobs generated by the Better Denver Bond
Program. Roughly 1,000 annual jobs are created or preserved for every
$100 million of capital expenditure. Therefore, with a $500 million capital
program, it is estimated that Better Denver Bonds provided for 5,000 jobs
over the life of the program, or roughly 1,000 full-time equivalent jobs per
year. This is the direct impact of the Bond Program. That impact extends
and is multiplied throughout the economy with the work that the projects
generate for contractors, subcontractors, suppliers, and workers. Based
on the data from both the ARRA and AGC it is probably safe to say that
the impact of the Better Denver Bond Program on the metro Denver area is 5,000 direct construction jobs
over the 5-year timeframe, nearly 7,500 when considering the beneficial impacts of related supply and
manufacturing jobs.
COMPANIESAs of June 2012, the number of companies under direct contract with the City was in excess of 500.Additionally, those companies have subcontractors and suppliers. A conservative estimate suggests that
over 1,000 companies have had opportunities that they would not otherwise have had as a result of the
Better Denver Bond Program.
Among those companies were ones that were minority- and/or woman-owned business enterprises
(M/WBE). The City requires participation by MBE and WBE on City projects. With the Better Denver
Bond Program, nearly $75 million worth of work went to MBE and WBE companies.
i
Over 290 projects were
originally planned but
cost savings allowed
funding for 321!
7/29/2019 Still Building a Better Denver with Borrowed Money
5/12
There are more than 321 bond projects throughout the Denver Metro area that were made possible by the
Better Denver Bond Program. If youre a Denver resident, youve probably seen evidence of construction
throughout the City, but do you know how the Program isbenefiting your neighborhood specifically? The City of Denvers
official Better Denver Bond Program website provides information
on bond projects, maps, and the ability to search by neighborhood:
www.denvergov.org/betterdenver
The passage of the Better Denver Ballot Questions authorized
funding totaling $549.73 million for capital projects across the
following eight categories:
Purpose 1 Ballot Issue FDeferred Maintenance for Public Office Facilities ($10,350,000)Denvers historic City and County Building, opened in 1932, has
received exterior maintenance that included repair of front steps,
replacement concrete, masonry cleaning, and exterior upgrades
including replacement of windows and blinds for energy conservation
and functionality. Projects also included the remodeling of restrooms,
addition of exit lights, modification of existing bronze doors, repair
of heating, ventilation, and cooling systems, and installation of asprinkler system in the basement. Public office building projects
were also funded at the Denver Permit Center and included repair of heating, ventilation, and
cooling systems, upgrade of electrical systems, and repair of exterior concrete and sidewalks.
Purpose 2 Ballot Issue GDeferred Maintenance on Cultural Facilities ($60,546,000)The Botanic Gardens, Boettcher Concert Hall, and
the Denver Museum of Nature and Science (DMNS)
are a few of the Citys most prized cultural facilities in
need of maintenance and repair authorized through
two Better Denver Ballot Questions, 1G and 1F.
That work included renovation and improvements
to DMNS Phipps Hall and the Newton Theatre;
The Botanic Gardens Greenhouse and Irrigation
as well as ADA improvement; Boettcher Concert Hall had necessary repair work done.
Better Denver Bond
Questions authorized
funding totaling
$549.73 Million for
Capital Projects!
7/29/2019 Still Building a Better Denver with Borrowed Money
6/12
Purpose 3 Ballot Issue BHealth and Human Services ($48,583,000)Bonds issued under this Better Denver Ballot Question
have funded projects including the expansion of
hospital facilities at Denver Health, and the renovation
and repair of heating, plumbing, and electrical
systems in five low-income child care facilities as well
as Denver Cares Drug & Alcohol Treatment Center.
Additionally a new Eastside Human Services Building
and new Animal Shelter were built.
Purpose 4 Ballot Issue EParks System Facilities ($93,387,000)The construction of a new recreation center,refurbishment of existing park features, replacement
of outdated irrigation systems, and attending to
overdue park maintenance projects are some of
the projects funded pursuant to this Better Denver
Ballot Question.
Projects included work at City Park, Sloans Lake,
Ruby Hill Park, Berkeley Park, Parkfield Lake Park, and
historic park facilities at Civic Center Park, CheesmanPavilion, City Park Bandstand and Washington Park Boathouse. Funds were also used for land
acquisition for a future Central Denver Recreation Center on Colfax.
Purpose 5 Ballot Issue IPublic Safety ($65,195,000)This Better Denver Ballot Question authorized
funding for a new Crime Lab, a firing range, Traffic
Operations Center and a Police Command Vehicle
Garage for the Police Department. It also included
the future Lowry Fire Station and the renovation of
six existing fire stations.
The new crime lab is state of the art and is a prime
center for DNA testing and other laboratory
procedures in the western United States.
7/29/2019 Still Building a Better Denver with Borrowed Money
7/12
Purpose 6 Ballot Issue DStreets, Transportation, and Public Works ($149,786,000)Projects funded under this Better Denver Ballot Question are intended to increase traffic capacity
in targeted areas and help make Denver more pedestrian-friendly and sustainable. Specific projects
included construction and reconstruction of roadways and streetscapes, widening of sidewalks,
improvement of pedestrian walkways, provision of access to transit lines, and facilitation of transit-
oriented development. The new Central Park Interchange at I-70 was constructed as part of this.
Purpose 7 Ballot Issue C Libraries ($51,883,000)All 23 of the City library facilities (except for
the Denver Public Library main branch) are
being improved under this Better Denver Ballot
Question. Improvements have included repair of
roofs, heating, ventilation and cooling systems,
boilers, electrical systems, fire alarms, and network infrastructure in many locations. Some fundsare also being used to bring libraries into compliance with the Americans with Disabilities Act.
In addition, funding was provided for the construction of three new branch libraries for under-
served or high-growth communities: Green Valley Ranch Branch Library, Sam Gary Branch Library
(Stapleton) and the future West Denver Library.
Purpose 8 Ballot Issue HNew Construction of Cultural Facilities ($70,000,000)This Better Denver Ballot Question authorized overdue maintenance and repairs of each of the
Citys cultural facilities, as well as both an extensive renovation and expansion of BoettcherConcert Hall and the construction of a new storage facility at the Denver Museum of Nature
and Science. This ballot measure contemplated a public-private componentprivate funds
were to be raised and then matched by bond funds for each particular project. In the case of
Boettcher Concert Hall, there was to be $25 million in private funds raised. Unfortunately, due to
the serious fund raising challenges presented by the economic downturn, this project has been
deferred. The remaining authorized amounts in both 1G and 1H have not been issued, but the
authorization is there and the bonds could be issued at any time for use on a project or projects
that would fit under the terms of the original bond authorization. The City proposes to use that
bonding capacity for the improvement of City cultural
facilities. Proposals have been solicited from cultural
facilities for maintenance or construction projects. A
review committee has evaluated those proposals and
forwarded recommendations to the Mayor. (See Mayor
Hancocks recommendations regarding the final projects
to receive the remaining cultural bond funds from the
Better Denver Bond Program on page 7)
Three new branch librarieswere constructed in under-
served or high-growth areas
7/29/2019 Still Building a Better Denver with Borrowed Money
8/12
Nearly all of the bonds approved in the 2007 election have been
issued. The remaining authorization includes $3,533,794 for Parks
and Recreation, $18,497,001 for refurbishment of cultural facilities,
and $38,629,205 for new construction on cultural facilities. Under
the terms of the bond authorization, City Council can move funds
from one project to another, but the projects must be within the
category approved by voters. For instance, bonds approved for
Parks and Recreation can be moved from one project to another
within Parks and Recreation but could not be moved to projects for cultural facilities, Human Services, etc.
The Parks and Recreation money is for the Central Denver Recreation Center. Land acquisition and conceptua
design work have been completed, however additional private funds must be raised before the bond money
can be spent on construction.
The Cultural Facilities bonds are discussed below.
Cultural Facilities BondsThe economic downturn, which began at the same time that the City was preparing to issue bonds, negatively
impacted the public-private component of the cultural facilities project. Private funds were to be raised and
then matched by bond funds. In the case of Boettcher Concert Hall, the $25 million in private funds were not
raised, so the demolition and reconstruction of this cultural facility did not move forward, and the bonds
were not issued. Now, however, the City has decided to reauthorize this remaining bonding capacity. The
City is required to reauthorize this remaining bonding capacity within the original purpose approved by
voters. Question G related to deferred maintenance for City-owned cultural facilities, and the remaining
amount is $18,497,011. Question H related to financing the cost of new construction of City-owned culturafacilities, and the remaining amount is $38,629,205. The proposed allocation of proceeds of this bonding
reauthorization will be $53,526,000 toward projects and $3,600,000 toward Bond Program management
During this past summer, a Cultural Facilities Steering Committee, appointed
by the Mayor and comprising individuals from the public and private sectors
and nonprofits, was convened to request proposals from City cultural facilities
for projects that might be done with the proceeds from the bonds, to review
and evaluate the submitted proposals, and then forward recommendations
to the Mayor for final selection. The eligible applicants were required to:
Demonstrate that the project proposed is for a cultural facility within
the context of the voter-approved 2007 ballot issue;
Demonstrate that it is a City-owned facility;
Demonstrate that it may complete its proposed project within the time
and financial constraints of the Better Denver Bond Program; and
Respond sufficiently to each question contained in the subject Request
for Proposals.1
1 Source: Office of the Mayor, 2007 Better Denver Bond RFP Process, Presentation to Denver City Council- Government and Finance Committee, 8/22/2012
7/29/2019 Still Building a Better Denver with Borrowed Money
9/12
The Mayor has now selected the projects that will go forward. City Council must approve ordinance changes
to allow the bonds to be issued and the proceeds used for the specific projects selected. The projects
selected are listed in the table below.CITYOWNED CULTURAL FACILITY QUESTION G QUESTION H TOTAL
Boettcher Concert Hall - Improvements $6,700,000 $10,075,000 $16,775,000
Denver Performing Arts Complex - Champa Street Bridge $2,500,000 $2,500,000
Denver Art Museum - Ponti Building $3,000,000 $3,000,000
Denver Botanic Gardens - Caf & Restrooms and Science Pyramid $6,619,000 $6,619,000
Denver Center for the Performing Arts - Deferred Maintenance $9,932,000 $9,932,000
Denver Museum of Nature and Science and the Denver Zoo - Parking $4,400,000 $4,400,000
Levitt Pavilion Amphitheatre - $2,000,000 $2,000,000
McNichols Building - Improvements $700,000 $4,800,000 $5,500,000
Red Rocks Amphitheater - Water Supply and Concession $2,800,000 $2,800,000
Total $17,332,000 $36,194,000 $53,526,000
Better Denver Bond Program
10
30
50
70
90
110
130
150
2008 2009 2010 2011 2012 2013 2014
44
82
120
121
62
3
71
29
33
MillionsEstimated vs. Actual Expenditures By Year
Post P rogram
Current Estimate
Actuals
Better Denver Bond Program
78%
14%
5% 3%Expenditures To-Date
By Type
Construction, Eqt, Materials
Planning, Design , Pro Svcs
Land
Program Management
Expenditures To-Date
Description Amount %
Construction, Eqt, Materials 332,512,137$ 78%
Planning, Design , Pro Svcs 58,260,584$ 14%Land 22,225,511$ 5%
Program Management 14,964,972$ 3%
Public Art 1,619,172$ 0%
429,582,375$ 100%
Components of Program Management Costs
Description Amount %
Program Management 11,651,584$ 78%
Agency Staff & Office Exp 2,072,719$ 14%
Legal Services 693,954$ 5%
Tech Services 477,015$ 3%
Signage 69,700$ 0%14,964,972$ 100%
Source: Better Denver Bond Program Financial Update November 2012
78 percent of
Better DenverBond expenditures
have been forconstruction,
equipment andmaterials.
7/29/2019 Still Building a Better Denver with Borrowed Money
10/12
Over the life of the program, the Better Denver Bond Program has continued to meet its financial objectives
Total savings from projects completed by the end of 2010, when the economy was struggling, of $20
million have been re-invested in other projects consistent with the original ballot measures where
the savings were generated.
As of Q4 2012 (thru Dec.) $451 million (89%) of Bond Program funds have been contracted or
committed and financing is complete for authorized projects.
Financing is complete for authorized projects.
Denvers financing techniques, and AAA credit ratings from all three credit rating agencies (Standard
and Poors, Fitch, and Moodys ), have resulted in lower interest rates, which have resulted in
savings of over $19 million on debt service. The City would have had to pay approximately $10
million more in interest if it moved from an AAA to a Baa investment grade issuer.
The Citys financial team has continued to explore alternative means to finance the Bond Program
and drive down long-term costs of bond issuance and debt service. The combined Commercial Paper
and General Obligation (G.O.) bond program has provided flexible, cost effective financing. Debt
service interest costs were substantially reduced by the use of the Commercial Paper Program.
The Better Denver Bond Program utilized a financial modeling system that allowed the City to issue
debt just in time. Schedule and cash flow were analyzed for each project; commercial paper was
issued to cover costs on a quarterly basis, with G.O. bonds being issued annually in arrears to pay
off the commercial paper. This technique saved taxpayers millions of dollars in interest over thetraditional method of issuing G.O. bonds in advance.
In response to the tax exempt financial markets facing significant challenges during the Great
Recession, the U.S. government instituted the Build America Bonds (BAB) program as part of the
American Recovery and Reinvestment Act (ARRA). State and local issuers of BABs receive a 35%
direct federal subsidy resulting in lower borrowing costs and a broader group of investors than
normally invest in tax-exempt bonds. In 2010, Denver issued $312 million of BABs for the Bette
Denver Bond Program.
Better Denver Bond Program Sustainability AchievementsBetter Denver Bond Program projects have incorporated green design and construction approaches that
use energy efficiency, recycling, and wise use of land, water, and other materials. In coordination with
Denvers Sustainability Committee, each project was assessed for sustainability opportunities. Projects were
reviewed for energy efficient improvements related to heating and cooling, lighting, waste management,
recycling, water quality, and conservation. These design and construction approaches have saved capital
operations, and maintenance costs.
7/29/2019 Still Building a Better Denver with Borrowed Money
11/12
Where practical and possible, the Better Denver Bond Program has pursued opportunities to build and
design its major new vertical construction projects to achieve LEED certification. Project managers have
continued to identify opportunities to incorporate sustainability into their projects. New construction and
major renovation projects have aimed for a minimum of LEED Silver certification from the U.S. Green Building
Councils Leadership in Energy and Environmental Design (LEED) program.
The Denver Animal Shelter has received Platinum certification and the Museum of Nature and Science
Education and Collections facility has Platinum certification pending.
The Green Valley Branch Library, the Sam Gary Branch Library, the Central Park Recreation Center, the Police
Traffic Operation/Firing Range, the Museum of Nature and Science facility Phipps Exhibit Hall and other
facility renovation have each received Gold certification. The Eastside Human Services Building and the
Crime Laboratory have Gold certification pending.
Public ArtPublic Art Bond Projects Overview
Denvers Public Art Program was first established in 1988, directing1% of any projects over $1 million to be set aside for the inclusion
of artwork. The art program applies to new construction or
improvements to a building or structure, road, streetscape
pedestrian mall or plaza or park or any other project that includes
finished space for human occupancy that will be available for
public view. The Better Denver Bond Program has incorporated
public art into qualifying construction projects that are part of
the Bond Program. Each project has its own Selection Panel. The
Selection Panel ranges anywhere from 7 to 15 participants, including
community members, an artist, an arts professional, the projectmanagers, design team and a City Council representative.
Art is incorporated in a variety of ways in the projects: as a stand-
alone piece, an architectural feature of a building or facility, or
incorporated into landscaping. Approximately 30 bond projects qualified for inclusion in the Public Art
Program. In many cases art was envisioned to be integrated into the project structures or area grounds.
The number of bond-related Public Art Projects completed to date and the cost of these projects
17 bond projects have been completed, resulting in 28 original artworks. The total cost of these
projects: $1,223,782.
The number of Public Art Projects in the contracting phase: Currently 4 artists are in contracting, 8
artists are involved in active projects.
The number of local artists who have received commissions to complete these Public Art Projects
20 local artists out of 34 total have been commissioned for Better Denver Bond Program-related
Public Art Projects.
7/29/2019 Still Building a Better Denver with Borrowed Money
12/12