Upload
andresende
View
70
Download
17
Embed Size (px)
Citation preview
Hindustan Construction Co Ltd
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 2
Erecting Long Span Briges to suit Indian Conditions and Requirements
Presentation by
Suhas P Khedkar
(AVP- Engineering,) Hindustan Construction Company
To 3rd Annual Bridges India Summit 2012
On 17th May 2012
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 3
Table of Contents
Different Methods of erection of Superstructure
Cast in Situ Construction
Comparison of Conventional and Cantilever Construction Method
Innovative Construction of III rd Godavari Railway Bridge at Rajamahendri
Bandra Worli Sea Link – Superstructure Construction entirely by Precast segmental Construction.
Segment Casting and Erection of Appraoch Spans
Specaial Challenge during Construction- Relocation of LG
Construction of Cable stayed bridge
Conclusions
Different Methods of Erection of Superstructure
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 5
Different methods of Superstructure Erection
• Cast in situ construction
1. Conventional method for normal spans by use of staging
2. Using specialized technology for longer span bridges:
• e.g.. Use of centering girders,
• and bridge builders for cantilevering superstructures
• Construction using Precast elements
• Construction using precast girders of entire length,
• Construction using precast segments to be assembled during erection to form
girders of complete length
• Special techniques like Incremental launching method
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 6
Different methods of Superstructure Erection
• Method of Erection of Superstructure is site specific. And also design specific.
• In fact design should suit the method of erection dictated by site conditions and other constraints
• Final Choice is to be made from cost considerations. Evaluation of a couple of alternatives is many times necessary for major projects to decide cost effectiveness.
Cast in Situ Construction
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 8
Cast in Situ Construction for Superstructure
• Conventional casting on staging
• Method suitable for normal spans
1. More suitable for normal span viaducts as staging can be supported on ground
2. Has been used for both I girders and Box Girders.
3. If number of spans are small , use of precast girders and launching system is not cost effective
4. For box girders conventional casting can not be avoided as launching system may not be feasible due to excessive weight of span.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 9
Cast in Situ Construction for Superstructure
• Conventional casting on staging of long span superstructure is generally not feasible beyond about 50 m span due to
– excessive weight,
– Large quantity of staging and
– increased cycle time and concrete pour size.
– Especially difficult for River Bridges as staging needs to be supported on temporary piles.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 10
Cast in Situ Construction for Superstructure
• Cast in Situ Cantilever Segmental Technique
.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 11
Cast in Situ Construction for Superstructure
• Cast in Situ Cantilever Segmental Technique
Method suitable for long span box girders. Advantages as follows:
1. Each stage of construction is self supporting after completion. The erection system or the bridge builder can be erected on the tip of units cast earlier.
2. Construction is done in segments of convenient length, so that formwork and bridge builder frames supporting the formwork can be optimally
designed.
3. Construction progresses from pier in both directions towards centre of span. This allows maintaining feed lines for concrete and access for men
and material from the pier location up to the working point.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 12
Conventional Casting Vs Cantilever Construction
Comparison of two methods:
• Yamuna bridge at Naini Allahabad – 60 m spans Cast in Situ on Conventional staging
Elaborate staging arrangement needed for the span at 20 m from water level
• Bridge over River Brahmaputra at Tezpur
• Compare the small Bridge Builder on the tip of the cantilever with the staging of Naini Bridge
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 13
Conventional Casting Vs Cantilever Construction
Yamuna Bridge Staging – Elevation and Side View
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 14
Conventional Casting Vs Cantilever Construction
Tezpur Bridge Bridge Builder – Elevation and Side View
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 15
Cast in Situ Cantilever Construction for Long Span River Bridges
Tezpur Bridge over River Brahmaputra – Different spans in different stages of construction
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 16
Cast in Situ Cantilever Construction for Long Span River Bridges
Ganga Bridge at Varanasi - Bridge Builder in Elevation and Side View
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 17
Cast in Situ Cantilever Construction for Long Span River Bridges
Ganga Bridge at Varanasi – after Completion
Innovative Construction for III Godavari Railway Bridge at Rajamahendri
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 19
Innovative Construction for III Godavari Bridge Superstructure
III Godavari Railway Bridge
28 spans of 98 m each – 94 m C/C of bearings
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 20
Innovative Construction for III Godavari Bridge Superstructure
• III Godavari Railway Bridge near Rajamahendri has been constructed using an innovative technique.
• The design itself was developed for the innovative erection technique, under typical constraints posed in the tender specifications.
• The foundations and substructure was designed to suit standard railway span of 94.0 m using steel girders.
• The tender for superstructure invited alternatives with prestressed concrete (PSC) superstructure.
• Challenge to design a PSC superstructure within the design capacity of the substructure and foundations, which were designed and constructed for the lighter loads of the steel superstructure.
• A bow string girder design was proposed by HCC.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 21
Innovative Construction for III Godavari Bridge Superstructure
Salient Features:
1. Structural System – Bow String Girder in Prestressed Concrete
2. Span of Girder: 94.0 m
3. Arches in Reinforced concrete Constructed using Cast in situ segmental technique
4. Suspenders in High tensile Steel – BBR Dyna hangars
5. Tie Girder in Prestressed Concrete – Box shaped
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 22
Innovative Construction for III Godavari Bridge Superstructure
Innovative Features:
1. Top down Construction – Arch was constructed first
2. Tie girder constructed using formwork supported on suspenders
3. Arch was constructed using cast in situ cantilevering segmental technique in 7 stages
4. Arches from the two piers progressed to meet at the midspan, connected by a closure pour
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 23
Innovative Construction for III Godavari Bridge Superstructure
Stages of Construction of Arch:
1. Erect central tower
2. Cast starting stubs
3. Erect formwork for typical segment supported by stay cables
4. Cast first segment
5. Repeat stages 3 and 4 for balance 6 segments
6. Erect formwork for closure pour on the last segment at crown
7. Cast closure pour
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 24
Innovative Construction for III Godavari Bridge Superstructure
Stage 1 Cast starting stubs Stage 2 Erect Formwork for first
segment on starting stubs
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 25
Innovative Construction for III Godavari Bridge Superstructure
Itermediate Stage: Formwork supported on completed arch ready to receive for concrete for the next segment
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 26
Innovative Construction for III Godavari Bridge Superstructure
Itermediate Stage: Formwork supported on completed arch ready to receive for concrete for the next segment
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 27
Innovative Construction for III Godavari Bridge Superstructure
Closure Pour: Formwork supported on the last segment of 1/2 arch
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 28
Innovative Construction for III Godavari Bridge Superstructure
Arches for various spans completed
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 29
Innovative Construction for III Godavari Bridge Superstructure
Construction of Tie Girder
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 30
Innovative Construction for III Godavari Bridge Superstructure
Completed Bridge
Bandra Worli Sea Link Project Superstructure Construction entirely by Precast Segmental Technique, for both Cable Stayed and Approach Spans.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 32
Bandra Worli Sea Link Project – special Features • First Sea Link in India and with
Precast Segmental construction
• The entire sea link, including the cable stayed bridges has been constructed using precast segments for the superstructure.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 33
Bandra Worli Sea Link Project – special Features Many Firsts in our country
• First Cable Stayed Bridge across sea: India’s first open sea and longest cable stayed bridge.
• First Cable Stayed Bridge with a Single Central Pylon.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 34
Bandra Worli Sea Link Project – special Features Many Firsts in our country
• The entire sea link, including the cable stayed bridges has been constructed using precast segments for the superstructure. Total 2342 segments have been cast and used.
• The precast segments used for this sea link are one of the widest and heaviest in our country; - 18.1 m & 20 m in width , weight 120 to 140 MT
•Needing a very large casting yard with short line casting cells, large capacity gantries, matching capacity multi axle trailer for segment transportation, and specially designed gantries for segment erection.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 35
Special Features of the Project
Engagement of Asian Hercules, one of the largest floating shear leg crane in the world for shifting 1260 MT launching truss from Bandra end to Worli end of the main cable stay bridge
Up to 25-m high piers in open sea, giving ample headroom to marine traffic
Use of Politron Disc bearings for the first time in India
Piling through rocks exceeding 120 Mpa crushing strength
Use of Automatic Climbing Formwork for Pylon Construction
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 36
Bandra Worli Sea Link Salient Design Features • Precast Segmental superstrucure except KAGK Link Bridge • Aesthetically pleasing deck profile, with uniform depth for all
bridges - Bandra approach , Bandra Cable Stayed, Worli Cable Stayed, Worli Approach.
• Unique Design of Bandra Cable Stayed - 250 m spans on either side , supported on a Central Pylon,
A1
P19
P19
A1 P17
16x50 = 800m
600mBANDRA CABLE STAY
4X50=200m(SPAN-BY-SPAN)
350mWORLI CABLE STAY
28X50 = 1400mPRECAST SEGMENTAL (SPAN-BY-SPAN)
P6 P12
500mPRECAST SEGMENTAL
(BALANCED CANTILEVER) 150mPRECAST SEGMENTAL
(FORWARD CANTILEVER)
PRECAST SEGMENTAL
BANDRA CABLE STAY600m
WORLI CABLE STAY350m
NORTH 800m
NORTH APPROACH BRIDGE SOUTH APPROACH BRIDGE
BANDRA
WORLI
APPROACH ROAD
546m
APPROACHBRIDGE
& TOLL PLAZABANDRA
WORLI
200mSOUTH APPROACH BRIDGE
1400m
LIN
K BR
IDG
E81
1m
(SPAN-BY-SPAN)
Bandra Worli Sea Link Project Segment Casting and Erection
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 38
Casting Yard and Erection Gantry at BWSLP The project needed a very large casting yard, and two specially designed LGs, which needed to to be supplemented by one more LG from Worli end in the last season.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 39
Advantages of Precast Superstructure Vs Cast in Situ
• Construction of Superstructure in parallel with Foundation construction.
• When Foundations are being constructed at various site locations, superstructure elements can be precast in a separate casting facility.
• Advantages of factory production, with ease in quality control, and dimensional accuracy, due to easy acces, and dedictaed equipment, and survey stations.
• Good quality control due to planned facilities like proper curing arrangement, dedicated supervision.
• The above are relatively much difficult at actual site locations due to difficult access, great heights and different locations.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 40
Principles of Precast Segmental Construction
• Span is divided into a number of segments of full deck width
• The segments are match cast to attain the final geometry as of the erected span.
• Match casting and geometric control are of great importance as the bridge is virtually built in the casting yard. Any error in match casting will be difficult to correct during erection, as the span will not fit on the piers.
• Precision Survey in casting yard to attain desired geometry
• Precast Segmental Construction offers use of industrialized, repetitive construction procedures, which contribute to improved quality control as well as reduction in construction time .
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 41
Importance of Precision in Precast Segmental Construction
• Span is divided into a number of segments which are match cast to attain the final geometry as of the erected span.
• The bridge is virtually built in the casting yard. Any error in match casting will be difficult to correct during erection, as the span will not fit on the piers.
• The bridge has both vertical gradient, and Horizontal curvature.
• The bridge deck therefore follows a space curve.
Precast Segmental Construction for Bandra Worli Sea Link Project, Mumbai – CEMCON 2007
February, 23 - 2007 Page 42
SEGMENT : MATCH CASTING
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 43
Planning and Management for Casting Yard
(LONGITUDINAL DIRECTION)TYPICAL CROSS SECTION AT SEGMENT STORAGE AREA
(TRANSVERSE DIRECTION)TYPICAL CROSS SECTION AT CASTING CELL AND STORAGE AREA
(STORAGE BAY 1) (STORAGE BAY 2)
(REBAR JIGS)
CASTING YARD & STACKING YARD CROSS-SECTION
(CASTING CELL)
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 44
Precasting Yard at BWSLP- Capacity to stack 400 segments. And 9 casting cells.
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 45
Prefab Reinforcement Cage handling
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 46
Match casting at Precasting Yard
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 47
Precast Segment Pour Sequence
3.17 CUM
1.26 CUM
1.26 CUM
2.52 CUM2.19 CUM2.69 CUM4.28 CUM
1.66 CUM
1.66 CUM
7 89
2.52 CUM 2.19 CUM 2.69 CUM
2
3
45
3.17 CUM
1.26 CUM
1.26 CUM 1.66 CUM
1.66 CUM6
CONCRETE PLACING SEQUENCETOTAL CONCRETE QUANTITY = 44.30 CUM
12a
3a
4a 5a
6a
7a8a 9a10
5.33 CUM
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 48
Segment Handling at Precast Yard
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 49
Segment Transportation on Special Trailer
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 50
Main Truss
Front Leg
Suspension Frames
Rear Leg
Rear Pylon
Front Pylon
Center Leg
Connection Beam
Rear Trolley
Front Trolley
Launching Girder at BWSLP
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 51
Segment Transportation in Sea on Barge
Main Challenge During Construction of Approach Span: Relocation of LG from Bandra Approach spans beyond Bandra Cable Stayed bridge: Shifting by 500 m in the sea.
Text (Font Arial 16, Color Black, Line Spacing 30 points).
Text (Font Arial 16, Color Black, Line Spacing 30 points).
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 54
Text (Font Arial 16, Color Black, Line Spacing 30 points).
Text (Font Arial 16, Color Black, Line Spacing 30 points).
Need for Relocation
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 55
Text (Font Arial 16, Color Black, Line Spacing 30 points).
Text (Font Arial 16, Color Black, Line Spacing 30 points).
Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane – Asian Hercules
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 56
Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane – Asian Hercules
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 57
Relocation of Launching Trusses using 1600 MT capacity Barge Mounted Crane – Asian Hercules
Entire LG weighing 1260 MT , of length 105 m was physically lifted and shifted from P17-P18 to P20-P21
Construction of Cable Stayed bridge
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 59
Need for detailed Construction Stage Analysis
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 60
Results of stage-by-stage Analysis
Stage-by-Stage Analysis
Tower Construction Deck Erection
Precamber Values Fibre Stresses
Strutting Requirements and Force Levels Casting Curve, Erection Curve and Control Lines
Stay Cable Forces for Installation, Tensioning and fine tuning Forces
Stage Deformations
Temporary PT
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 61
Casting Curve
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 62
Stage by Stage Deck Camber Curves Deck Camber Curves for Bandra Bridge Stage by Stage
-100-90-80-70-60-50-40-30-20-10
0102030405060708090
100110120130140150160170180190200210220230240250260270280290300310320330340350360370380390400410420430440450
-300
-275
-250
-225
-200
-175
-150
-125
-100 -7
5
-50
-25 0 25 50 75 100
125
150
175
200
225
250
275
300
Chainage x [m]
Ele
vatio
n y
[mm
]
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 63
66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 3 2 1 0 1 2 3 6 7 8 9 10 11 12 13
Segment Node No. 5090 Segment Node No. 5113
1
76
543
2
424140393837363534333231
3029
282726252423
2221
2019
1817
161514
131211
109
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
S25
S26
S27
S28
S29
S30
S31
S32
S33 S33
S7
Stage Deflections
-80
-30
20
70
120
170
220
270
320
370
420
-300 -294 -288 -282 -276 -270 -264 -258 -252 -246 -240 -234 -228 -222 -216 -210 -204 -198 -192 -186 -180 -174 -168 -162 -156 -150 -144 -138 -132 -126 -120 -114 -108 -102 -96 -90 -84 -78 -72 -66 -60 -54 -48 -42 -36 -30 -24 -18 -12 -6 0 6 12 18 24 30 36 42
Deformation at previous stage Deformation after completion of this stage : LC1190 Deformation at handover for traff ic movement (Design Camber) @ T=0 : LC1298
Lift Non-stay Segment
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 64
66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 3 2 1 0 1 2 3 6 7 8 9 10 11 12 13
Segment Node No. 5090 Segment Node No. 5113
1
76
543
2
424140393837363534333231
3029
282726252423
2221
2019
1817
161514
131211
109
S7
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
S25
S26
S27
S28
S29
S30
S31
S32
S33 S33
Stage Deflections
-80
-30
20
70
120
170
220
270
320
370
420
-300 -294 -288 -282 -276 -270 -264 -258 -252 -246 -240 -234 -228 -222 -216 -210 -204 -198 -192 -186 -180 -174 -168 -162 -156 -150 -144 -138 -132 -126 -120 -114 -108 -102 -96 -90 -84 -78 -72 -66 -60 -54 -48 -42 -36 -30 -24 -18 -12 -6 0 6 12 18 24 30 36 42
Deformation at previous stage Deformation after completion of this stage : LC1191 Deformation at handover for traff ic movement (Design Camber) @ T=0 : LC1298
Stress Previous Cable to Ft
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 65
67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 3 2 1 0 1 2 3 6 7 8 9 10 11 12 13
Segment Node No. 5090 Segment Node No. 5113
1
76
543
2
424140393837363534333231
3029
282726252423
2221
2019
1817
161514
131211
109
S7
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
S25
S26
S27
S28
S29
S30
S31
S32
S33 S33
Stage Deflections Lift Stay Segment
-80
-30
20
70
120
170
220
270
320
370
420
-300 -294 -288 -282 -276 -270 -264 -258 -252 -246 -240 -234 -228 -222 -216 -210 -204 -198 -192 -186 -180 -174 -168 -162 -156 -150 -144 -138 -132 -126 -120 -114 -108 -102 -96 -90 -84 -78 -72 -66 -60 -54 -48 -42 -36 -30 -24 -18 -12 -6 0 6 12 18 24 30 36 42
Deformation at previous stage Deformation after completion of this stage : LC1192 Deformation at handover for traff ic movement (Design Camber) @ T=0 : LC1298
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 66
Stage Deflections Install Cable and stress to Fi
67 66 65 64 63 62 61 60 59 58 57 56 55 54 53 52 51 50 49 48 47 46 45 44 43 42 41 40 39 38 37 36 35 34 33 32 31 30 29 28 27 26 25 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 3 2 1 0 1 2 3 6 7 8 9 10 11 12 13
Segment Node No. 5090 Segment Node No. 5113
1
76
543
2
424140393837363534333231
3029
282726252423
2221
2019
1817
161514
131211
109
S6
S7
S8
S9
S10
S11
S12
S13
S14
S15
S16
S17
S18
S19
S20
S21
S22
S23
S24
S25
S26
S27
S28
S29
S30
S31
S32
S33 S33
-80
-30
20
70
120
170
220
270
320
370
420
-300 -294 -288 -282 -276 -270 -264 -258 -252 -246 -240 -234 -228 -222 -216 -210 -204 -198 -192 -186 -180 -174 -168 -162 -156 -150 -144 -138 -132 -126 -120 -114 -108 -102 -96 -90 -84 -78 -72 -66 -60 -54 -48 -42 -36 -30 -24 -18 -12 -6 0 6 12 18 24 30 36 42
Deformation at previous stage Deformation after completion of this stage : LC1194 Deformation at handover for traff ic movement (Design Camber) @ T=0 : LC1298
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 67
Erection Monitoring
P19 tower Pilecap
Tower Leg Construction in Progress
Isometric View of Piertable
Piertable Truss Erection
Pier table Truss Erection
Lifting Frame Operations
Lifting Frame Operations
Segment Transportation on Barge
Piertable Segment Lifting with Lifting Frame
Pier Table Segment Alignment
Segment Supported on Pier Table Truss
Pier Table Segments Alignment in Progress
Diaphragm Concreting
Isometric view of Middle Tower Legs
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
Construction of Middle Tower with ACS
P19 Middle tower leg in Progress
P19 Middle tower leg in Progress
P19 Middle tower leg in Progress
Strutting at Junction Top
Strutting at Junction Top
Assembly of tower head formwork prototype
Alignment of Anchorage Boxes at 100m above MSL
Construction of Tower Head
Erection of Deck
Erection of Deck
Erection of Parallel Wire Stay Cables
Erection of Parallel Wire Stay Cables
Erection of Parallel Wire Stay Cables
Erection of Precast Segmental Deck
Erection of Precast Segmental Deck
Erection of Precast Segmental Deck – Deck Closure
Erection of Precast Segmental Deck
Erection of Precast Segmental Deck
Erection of Precast Segmental Deck
Completed View of Bandra CSB
28 May 2012 Presetation to 3rd annual Bridges India Summit 2012 112
Conclusions
• Indian Engineers are Well Experienced in Construction of loang Span Bridges, and Erection of Bridge Decks, using various methods
• Choice of the method is Site Specific and Design Specific • Bridge Design should Suit Erection Method
I acknowledge with Thanks opportunity given to me for presentation of a very important and interesting topic. I thank the organizers, and the audience.
Disclaimer
This presentation contains certain forward looking statements concerning future business prospects and profitability of HCC, which are subject to a
number of risks and uncertainties and actual results could materially differ from those in such forward looking statements, important developments
that could affect the company's operations include a downtrend in the infrastructure sector, significant changes in political and economic
environment in India, tax laws, labor relations, litigation etc. The company does not undertake to make any announcement in case any of these
forward looking statements become materially incorrect in future or update any forward looking statements made from time to time by or on behalf
of the company.