64
CMPDI Annexure No-I _________________________________________________________________ Summarised EIA-EMP of Krishnashila OCP (7Mtpa) A-2 _________________________________________________________________ Summarised Environmental Impact Assessment (EIA) & Environmental Management Plan (EMP) For Krishnashila OCP (6.25 to 7.00 Mtpa) CONTENTS PARTICULARS PAGE NO. Summarised EIA-EMP A-1 TO A-56 1.0 Introduction A-3 2.0 Project description A-5 TO A-6 3.0 Description of the environment A-6 TO A-9 4.0 Detail of anticipated environmental impacts & mitigation measures A-9 TO A-15 5.0 Analysis of alternatives A-15 6.0 Environmental Monitoring Program A-15 7.0 Project benefits A-16 8.0 Environmental management plan A-16 9.0 Mine closure planning A-16 10.0 Disclosure of consultants A-16 TO A-17 11.0 Cost of environmental control measures A-17 12.0 Justification for grant of Environmental Clearance A-17 TO A-18 LIST OF TABLES Sl.No. Particulars Table No. 1. Ambient Air Quality Report Table No. -1 2. Water / Effluent Quality Data Table No. -2 3. Noise Level Measurement Data Table No. -3 4. Ground Water Level Data Table No. -4 5. Ground Water quality Data Table No. -5

Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP (7Mtpa) A-2

_________________________________________________________________

Summarised Environmental Impact Assessment (EIA)

& Environmental Management Plan (EMP)

For Krishnashila OCP (6.25 to 7.00 Mtpa)

CONTENTS

PARTICULARS PAGE NO.

Summarised EIA-EMP A-1 TO A-56

1.0 Introduction A-3

2.0 Project description A-5 TO A-6

3.0 Description of the environment A-6 TO A-9

4.0 Detail of anticipated environmental impacts & mitigation measures A-9 TO A-15

5.0 Analysis of alternatives A-15

6.0 Environmental Monitoring Program A-15

7.0 Project benefits A-16

8.0 Environmental management plan A-16

9.0 Mine closure planning A-16

10.0 Disclosure of consultants A-16 TO A-17

11.0 Cost of environmental control measures A-17

12.0 Justification for grant of Environmental Clearance

A-17 TO A-18

LIST OF TABLES

Sl.No. Particulars Table No.

1. Ambient Air Quality Report Table No. -1

2. Water / Effluent Quality Data Table No. -2

3. Noise Level Measurement Data Table No. -3

4. Ground Water Level Data Table No. -4

5. Ground Water quality Data Table No. -5

Page 2: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-3

___________________________________________________________________

Summarised Environmental Impact Assessment (EIA) &

Environmental Management Plan (EMP) For

Krishnashila OCP (6.25 to 7.00 MTPA)

1.0 INTRODUCTION

Krishnashila Opencast Project is an existing operating mine in Singrauli Coalfields, NCL in an area of 851.78 Ha. The mine is in operation since 2007 and has produced 36.49 MT of coal and removed 117.23 Mm3 of OB till 01.04.2017.

1.2 Purpose of the report

This application has been made as per the MoEFCC OM No.J-11015/224/2015-IA.II dated 15.09.2017 for grant of prior Environmental Clearance (EC) for increased capacity of Krishnashila OCP to 7.00 MTPA considering the following points.

A In view of the proposed shifting of 33 m3/72mR Dragline from Krishnashila OCP to Khadia OCP and increased energy demand of coal in the country, it is imperative that production from Krishnashila OCP be further increased owing to its favorable geo-mining conditions.

B The total leasehold area as per earlier approved EMP is 851.78 Ha (extra land is not required and the forestry and other clearances have already been obtained).

C No change in technology is proposed.

D No change in backfilling & land reclamation plan will take place. Krishnashila OCP has got Environmental Clearance and the land reclamation plan has been approved by MoEFCC. There is no change in the land reclamation plan and the same shall continue after including the increased capacity of the mine to 7.0 MTPA also.

E The total approved manpower is 634 (3 shift working), no increase in which is proposed. The total existing manpower as on 01.11.2017 is 478.

F The grade of coal is grade G-8 and the linkage of coal is with M/s Hindalco Industries Ltd. as well as Basket Linkage.

G The mine-able coal reserves was estimated to be 99.12 MT and the average stripping ratio is 3.38 m3/T. Approximately 62.63 Mt of mineable coal reserve is left to be mined as on 01.04.2017.

H Due to the increasing demand of coal for the nation, it is requested to consider the proposal for grant of environmental clearance from MoEFCC for increased capacity of 7.00 MTPA (from 6.25 MTPA present capacity to increased capacity of 7.00 MTPA.).

Therefore this project qualifies for EC as per the MoEFCC OM No.J-11015/224/2015-IA.II dated 15.09.2017 for inclusion of increased production capacity from 6.25 MTPA to 7.00 MTPA. The filled up Form-I and this EIA of the Project are put up for due diligence of EAC for inclusion of 7.00 MTPA increase in capacity of existing and approved Krishnashila OCP.

Page 3: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-4

___________________________________________________________________

1.3 Previous Coal Production

The production of this project for the last 10 years is given below.

Sl No Year Production MT OBR(Mm3)

1 2007-2008 0.06 9.10

2 2008-2009 1.08 10.48

3 2009-2010 3.52 8.82

4 2010-2011 3.57 10.68

5 2011-2012 4.00 14.60

6 2012-2013 5.00 5.34

7. 2013-2014 4.00 9.36

8. 2014-2015 4.95 9.83

9. 2015-2016 5.00 18.51

10. 2016-2017 5.31 20.52

Total 36.49 117.23

1.4 Calendar Plan of proposed enhanced production and Life of the Mine The balance mineable coal left in Krishnashila OCP as on 01.04.2017 is 62.63 MT. The mining plan for Krishnashila OCP has been prepared for a rated capacity of 7.00 Mtpa. Corresponding to this, the balance life of Krishnashila opencast is 10 years (up to 2026-27) i.e. the life will be decreased by one year only due to increase to proposed capacity.

Year Normative Coal Production

(Mt)

Future coal production Program for existing Project as per proposed Mining Plan

Upton 2016-17

36.49 36.49

2017-18 6.25 7.00

2018-19 6.25 7.00

2019-20 6.25 7.00

2020-21 6.25 7.00

2021-22 6.25 7.00

2022-23 6.25 7.00

2023-24 6.25 7.00

2024-25 6.25 7.00

2025-26 6.25 6.00

2026-27 4.19 0.63

2027-28 2.19 -

Total 99.12 99.12

1.5 Identification of project & project proponent

The project under consideration, i.e. Krishnashila OCP is administratively under the NCL headed by General Manager, Krishnashila project. Geologically, it falls in Moher Sub-basin of Singrauli Coalfield in Singrauli District of Madhya Pradesh.

Page 4: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-5

___________________________________________________________________

The mailing address of the Project Officer is given below: General Manager Krishnashila OCP, NCL. PO: Bina Project Dist. Sonebhadra Pin: 231220 (Uttar Pradesh)

1.6 Location & Communication

The Project is located in Moher basin of Singrauli Coalfields at a distance of 18 Km southeast of Singrauli Town. Project is covered under Topo sheet no. 63-L /12 and L/16 on 1:50000 (1970) between latitude 240 07' 17" to 240 09' North and longitudes 820 44' 11" to 820 45' 46" East. The Singrauli and Krishnashila Railway Station on Singrauli-Obra and Shaktinagar-Karaila rail links of East-Central Railway are located at a distance of 11 Km Northwest and 3 Km East of Krishnashila Opencast Project , respectively. The project is in connection with the all-weather metaled road to Shaktinagar and Renukut. The nearest airport is in Varanasi at a distance of 220 Km. Refer location plan at Plate No -1 and plan showing leasehold area of project in KML format in Plate no. 1(A) attached with accompanying Form-I.

1.7 Description of importance to the country and region

Northern Coalfields Limited is facing increasing demand of coal because of increased demand from industry and power sector. Continuing and augmentation of coal production from the mines of NCL will help to bridge the gap of demand and supply of coal in India. To meet the growing demand of coal, especially in power and steel sectors, the Ministry of Coal has given target to NCL for the year 2017-18 as 90.00 Mt which will increase to 110.00 Mt by the terminal year of XIIIth Plan ( 1.0 BT plan) period i.e. in year 2019-20.

Krishnashila Opencast Project will make available additional coal @ 0.75 MTPA apart from 6.25 MTPA that it is already producing, to meet the growing demand of non-coking coal.

2.0 PROJECT DESCRIPTION

2.1 Nature and size of the project Design, development and operation of Krishnashila OCP are done by Northern Coalfields Limited. This project originally had an operating capacity of 5.00 Mtpa ROM coal production. The project has already increase production capacity by 25% i.e., 6.25 Mtpa and again proposed to increase production capacity to 7.00 Mtpa. Refer Plate No-2 showing surface features in surface plan of Krishnashila Project.

Krishnashila is mined by opencast method. It is characterised by the presence of up to three seams with dip angles of 2°-3°. Seam thickness ranges from 3.00 m to 9.90 m (Purewa Top seam), 10.40 to 13.50 m (Purewa bottom Seam), and 19.36 to 25.60 m (Turra Seam). Original mineable reserve was 99.12 Mt at average strip ratio of 3.38 cum/t.

2.2 Quarry Parameters

As per existing scenario, the balance coal production will come as per detail given below.

Page 5: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-6

___________________________________________________________________

Sl. No.

Seam Stripping Ratio & other Quarry Parameters for balance reserves

1 Total Coal ( Mt) (as on 01.04.2017)

62.63

2 Total OBR(Mm3) (as on 01.04.2017)

218.11

3 S. Ratio (m3/te.) 3.38

4 Life ( Years)from 2017-18 10

5 Dip of seams (Degree) 2°-3°. 6 Strike Length (Km) 2.50(surface)

7 Maximum depth (m) 180

8 Present quarry depth (m) (as on 01.11.2017)

165

9 Toatal quarry land broken (Ha) (as on 01.11.2017)

246

2.3 Coal trasportation outide the Mine lease :

Krishnashila OCP is linked to M/s. Hindalco Industries Ltd. It also serves as Basket Linkage to meet the overall demand on NCL. Detail of dispatch of coal for last 2 years is given below:

Consumer

2015-16 (Mt) 2016-17 (Mt)

By Rail By Belt Pipe

Conveyor By

Road By Rail

By Belt Pipe

Conveyor By Road

OTPS, Obra 0.95 0.70

Renusagar, BPC 1.84 2.96

Basket Linkage 0.97 1.34 1.25 0.43

Total 1.92 1.84 1.34 1.95 2.96 0.43

G Total 5.10 5.34

Presently, around 56% of Coal Off-take is being done by belt pipe conveyor and 37% by rail transport. As construction of CHP is about to complete, the coal transportation will be through conveyor system up to the silo and then loading to railway wagons.

Also, NCL are already dispatching coal through e-auction to small consumers at present, therefore, provision of dispatch of coal by road upto 10 % of the EC capacity for meeting the demands of the small consumers of varied industries (Bricks, Foundries, Ceramics and Other small Industries). There is a government guidelines for e-auction of 10% of the production vide MOC, GOI, OM No.23011/4/2007-CPD dtd. 18th October 2007 {Clause No.10 (V)}.

3.0 DESCRIPTION OF THE ENVIRONMENT 3.1 Ambient Air Quality Status:

A. Baseline Ambient Air Quality Status:

Page 6: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-7

___________________________________________________________________

Baseline Ambient air quality study was done in core & buffer zone of Krishnashila OCP during winter season from Oct’2012 to Dec’12 by ICFRE, Dehradun at the following stations.

Stn No. Name of sampling station

Location of sampling station and its description

AQ -2 Junior Guest House (Buffer Zone)

This location is situated at 2.5 km distance towards north East direction from proposed mine area. It is selected for Air Quality Monitoring to assess the effect of pollutants in the populated area.

AQ - 3 Dudhichua This location is situated at a distance of 6 km towards West direction from the proposed mine area. It is selected to assess the effect of pollutants in the populated area.

AQ-4 Field Office (Core Zone)

This location is in the core region of the mine. It is selected to assess the effect of pollutants in the core region of the mine.

AQ - 5 Chanduwar Village (Buffer Zone )

This location is situated at a distance of 3.0 km towards East North East direction from the proposed mine area. It is selected to assess the effect of pollutants in the populated area.

AQ-6 Khadia This location is situated at a distance of 3 km towards West direction from the proposed mine area. It is selected to assess the effect of pollutants in the populated area.

Location of the sampling points is indicated in Plate No.-2 Summary of the observations made during the study period are as follows:

Sl. No.

Parameters Value Range* (Core one)

Value Range* (Buffer Zone)

Permissible Limits*

1 SPM 297-377 128-189 600

2 PM10 144-196 68-97 Core zone-300 buffer zone-100

3 PM2.5 73-110 41-57 Core zone-NA buffer zone 60

4 SOx 17-28 10.5-19 80

5 NOx 21-36 15-27 80

6 Pb 0.05-0.23 0.05-0.16 1.0

7 As Not Detected Not Detected 6.0

8 Ni 0.005-0.012 0.001-0.009 20

9 Hg Not Detected Not Detected --

* All values are in µg/ m3

B. Routine Environmental Monitoring: The project is regularly monitored for environmental parameters like Ambient Air, water /effluent and noise levels. Location of the sampling points is indicated in Plate No.1& 2. Ambient Air quality at present level of production with control measures is found to be within specified limit (as per Gazette notification no GSR 742(E) dt.

Page 7: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-8

___________________________________________________________________

25-9-2000, Standard for Coal mines). The Baseline and present Monitoring ambient air quality data is given in Table no. -1. The SPM, PM10 and PM2.5 levels from QE March-2017 and QE June.-2017 and are given below. The results reveal that the SPM & PM10 values have increased marginally due to increase in mining activities as the project started in 2007-08. The observed values are within the permissible limits. (All values are in µg/ m3)

Station Name/Code Category Q.E. March, 2017 (Quarterly Average)

Q.E. June, 2017 (Quarterly Average)

SPM PM10 SPM PM10 PM2.5

CORE ZONE LOCATIONS :

1. KSA1 - CGM Office Industrial 433 313 380 252 -

2. KSA2 - Outsourcing Camp Industrial 314 212 390 265 -

3. KSA3 - Radha Krishna Mandir Residential - 126 - 101 29

4. BA3 - Bina STP Residential - 104 - 113 39

BUFFER ZONE LOCATIONS : PM10 PM2.5 SPM PM10 PM2.5

1. KSA4- Kohraul Village Residential 91 36 - 95 27

2. KHA3 – Khadia CGM Office Residential 100 21 - 114 40

3. BA5 – Jawharnagar Residential 88 29 - 115 42

4. KHA5 – IWSS Office Residential 110 31 - 119 41

C. Ambient Air quality impact prediction through Modeling: Except PM (PM10) level no other parameter will be increased which is a major emission from various opencast mining activities. An ambient air Quality Impact Prediction (AAQIP) for enhanced production of 7.00 Mtpa has been predicted by using AIRMOD. This AAQIP reveals that, the increase in PM (PM10) level will be marginal and within permissible limit. The AAQIP details are enclosed as Annexure No.-VIII. Predicted and Monitored 24 hourly average PM10 Concentration Levels at various Receptors are as given below :

Receptor 24 Hours average PM10 concentration (µg/ m3)

Incremental Concentration

with control measures

Background/ Baseline

concentration

Total predicted concentration with control measures

Permissible Limits

KSA1, Krishnashila GM Office 20.096 246 266.096 300*

KSA2, Outsourcing Camp 3.197 108 111.197 300

KSA3, Radha Krishna Mandir 0.559 66 66.559 100**

KSA4, Kohraul Village 0.595 51 51.595 100**

JHA5, Chandrapur Rehabilitation Site 0.696 94 94.696 100**

KKA6, Auri Village 0.354 69 69.354 100**

* Standards for coal mines for monitoring stations at a distance of 500 metres from dust generating

source. ** National Ambient Air Quality Standards

3.2 Noise Level Quality status

Page 8: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-9

___________________________________________________________________

Routine Environmental Monitoring: Noise Level measurement Sites and their rationale: i) Site Office (KSN1) To assess the noise level in the site office area, where the mine activities are in operation ii) Jr. Transit camp, Bina (KSN2) To assess the noise level in the residential area. Noise levels were recorded during day as well as night time. iii) Koharoul Village (KSN3) To assess the noise level in the residential area. Noise levels were recorded during day as well as night time. iv) Jawahar Nagar (KSN4) To assess the ambient noise quality in the residential area is at the southernmost point of the colony. Summary of the observations and noise level measurements are given in Table No-3.

3.3 Water quality status:

Routine Environmental Monitoring: Location of Sampling Stations and their rationale:

i) Tap Water at Jr. Transit Camp (KSW1)

To assess the drinking water quality a water sample from the Transit hostel was taken. ii) Hand Pump at Kohroul Village (KSW2)

This location has been selected to assess the ground water quality and quantity variation due to mining, in the rehabilitation complex.

iii) Mine Effluent at the sump (KSW3) This site has been selected for asses the quality of mine water after pumping and before

being fed into the ETP.

Summary of the observations and water quality are given in Table No-2. Also, the groundwater levels and quality of Dug wells in and around the project area are regularly monitored. The list of Dug wells monitored is given in Table No.4 and locations of Dug wells are shown in Plate No.4. The groundwater levels and quality data is given in Table No.4 & Table No.5 respectively.

4.0 DETAIL OF ANTICIPATED ENVIRONMENTAL IMPACTS & MITIGATION MEASURES

4.1 Air Pollution Control

Sources of air pollution

Page 9: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-10

___________________________________________________________________

The main sources of air pollution are identified as-

1) Drilling & blasting in coal & OB benches.

2) Coal & OB transportation inside the mine.

3) Coal crushing & conveying from the mine.

4) Coal handling activities.

5) Coal conveying to Power plant through closed Tubular Conveyor and by Railway

siding & loading in wagons.

6) Wind erosion from coal stockyard& OB Dump.

Ambient Air Quality Control Measures

Air pollution control measures

Sufficient numbers of movable water sprinkling system has been provided to check fugitive emissions from various parts of mine.

(a) Departmental - 28 KL water tanker : 04 nos

(b) Contractual (BGR) - 12 KL water tanker : 04 nos

(c) Contractual (Monte Carlo) - 18 KL water tanker : 04 nos

(d) At all transfer points of conveyor system water sprinkling system are

available.

Vehicles are regularly being maintained to control the emissions. Coal transportation is being done in covered trucks. The haul road is being graded regularly in order to make it smooth. Coal before being loaded into tippers is watered properly to avoid generation of dust in course of transportation.

Presently, around 56% of Coal Off-take is being done by belt pipe conveyor and 37% by rail transport. As construction of CHP is about to complete, the coal transportation will be through conveyor system up to the silo and then loading to railway wagons.

Coal transportation is done by covered trucks to Railway Siding only. Regular water sprinkling on the transportation roads. The construction of high capacity silo loading system is in process. .

Dust extractors have been provided and made operative in drills. Arrangement of wet drilling has also been made at Project level.

Dust is controlled regularly by spraying water at Haul road, transfer point etc. In mine water sprinklers are used for controlling dust generation.

76.05 Ha of OB dump area has already been planted with 2, 59.500 plants. Species of plants are- Gulmohar, Karaanj, Mahua, Chilbil and bamboo.

Person working in industrial area have been provided with protective respiratory device. Regular training is being imparted to inculcate safety and health aspect. Each person working in or about the mine is being examined periodically by Doctor trained in occupational health services.

Coal transportation to M/s Hindalco Industries Pvt. Ltd./Thermal power plants is done by CHP and Rail. OB is backfilled inside the Quarry. So outside road transportation of coal and OB is reduced to bare minimum.

Outside mine lease area- 3.0 MTY of coal is proposed to be transported by pipe conveyor and the rest is by rail, thus having minimum impact on environment.

Page 10: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-11

___________________________________________________________________

4.2 Water Pollution Control

Sources of water pollution Likely sources of water pollution from this project along with the type of pollutants are as

follows: Water Quality Management:

Likely sources of water pollution from this project along with the type of pollutants are as follows:

(i) Sanitary (domestic) waste water : Suspended solids and BOD.

(ii) Industrial wastewater from workshop

: Suspended solids, oil & grease;

(iii) Waste water from mine : Suspended solids of coal, clay and oil;

(iv) Surface run-off passing through coal stockpiles

: Suspended solids;

(v) Storm water from leasehold area and built-up area

: Suspended solids.

Water pollution control measures

Catch drains and siltation pond of sufficient size has been constructed to arrest the silt and sediment. The clean water so collected is being utilized for watering mine area, roads, green belt developments etc. The drains is being regularly de-silted and maintained properly. Sufficient sump capacity has been provided to have adequate retention period to allow proper settling of silt.

Sufficient check dam shall be maintained in the toe area of dump to arrest silting of sump.

At present there is no effluent going out of the mine premises. A Mini ETP is already working in the project, An integrated Effluent Treatment Plant (ETP) of 4.80 MLD capacity is under process of construction to deal with the effluent from workshop, CHP and mine discharge. There is provision of construction of 443 residential quarters in space available in Bina Township.

Rain Water Harvesting

In order to augment ground water resource, artificial ground water recharge measures have been taken. Further, numerous numbers of hand pumps , wells and ponds have been provided in nearby villages to meet the water requirements of villagers , animals and plants.

Additional Water requirement for the proposed increased Capacity of Krishnashila OCP: Requirement of Water (at 5.00 Mtpa stage) :

Domestic water : 757 m3/day Industrial water : 1312 m3/day

Page 11: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-12

___________________________________________________________________

Total : 2069 m3/day

There is no increase in domestic water requirement as no increase in manpower as per mining plan. This will be met by integrated water supply scheme (IWSS) at Khadia. The average estimated mine water pumping from mine is 1640 m3/day at max. depth.

The industrial requirement of 1312 m3/day is met partially from Krishnashila mine water pumping and IWSS.

The additional industrial water requirement has been estimated about 198 m3/day from that at 5.0 Mt stage for haul road dust suppression and other dust suppression requirements. The mine water and treated ETP water will be Re-use to meet this additional requirements.

4.3 Noise Level Management:

The mining operation may cause noise nuisance if adequate precautions are not taken to keep the noise level within limits. An environment standard for coal mines stipulates that noise level in Industrial area shall not exceed 75 dB (A) Leq. The following measures therefore, have been envisaged to reduce the noise level to protect the workers from noise hazard and to adhere to the Environmental standards in respect of noise. - Use of equipment with arrangements for absorbing the operational noise. - Foundations of vibrating equipment to be designed with isolators to prevent Vibrations so that the noise level does not exceed 85 dB(A) Leq. - Controlled blasting is undertaken under supervision of the blasting officer. Proper blast

design is prepared to control ground vibration and to arrest fly rocks and boulders. Blasting is done with the use of soft tubes.

- Use of insulated cabins for operators - Use of rubber/ polymer liners in chutes and hoppers - Use of ear muffs by workers in the zone of high noise source (if any) - Plantation of trees around the plant area. - Routine maintenance of HEMM. - Regular maintenance with prompt replacement of worn-out parts.

4.4 Land Requirement & Management

The earlier approved Krishnashila OCP involved land requirement of 851.78 Ha, no increase in land requirement is proposed for increase in coal production. There will be no change in total OB quantity, dump area, final dump plan and dumping strategy due to increased peak production from 6.25 to 7.00 Mtpa. Modalities for technical and Biological reclamation will be remain same as mentioned in approved EMP (5.00 Mtpa) of Krishnashila OCP. A. Pre mining Land Use :

1 Forest land 720.89 Ha

2 Agricultural land (Tenancy Land) 10.29 Ha

Page 12: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-13

___________________________________________________________________

3 Govt. Land 120.60 Ha

Total 851.78 Ha

The detail of land use at operational stage as per approved Mining plan of Krishnashila OCP (7.00 MTPA) is given below: * Final dump plan and cross section showing profile of External and Internal OB dump is

shown in Plate-5, 6 & 7.

B. Post-mining land use of core zone with environment management

Sl No

Land Use Total Land

Ha

Post mining land use in Ha

Plantation/ Afforestation

Water Body

Public use

Others

1 Top Soil Dump Not estimated separately. Included in OB dump.

2 External Waste dump(OB Dump)

164.80 164.80 - - -

3 Excavation area (backfill +void)

469.80 435.75 34.05 - -

4 Roads 15.75 - - 15.75 -

5 Built-up Area 4.00 - - 4.00 -

6 Green Belt (Afforestation)

57.43 57.43 - - -

7 Undisturbed land 140.00 - - 140.00

Total 851.78 657.98 34.05 19.75 140.00

* Final reclaimed dump plan and cross section showing profile of internal OB dump at post-

mining stage is shown in Plate-8 & 9 respectively. C. Land use / cover mapping of study area based on Remote Sensing map :

A map showing Land Use/ cover mapping of study area of Krishnashila OCP based on

satellite data(PB/L-IV) of the year 2016, was prepared using remote sensing technique by

Sl. No. Particulars Total required Area (Ha)

1 QUARRY AREA 469.80

2 EXTERNAL DUMP AREA 164.80

3 MINERAL STORAGE 12.00

4 Infrastructure 4.00

5 Roads/Railways 15.75

6 Green Belt/Afforested Area 25.00

7 Effluent Treatment Plant 2.00

8 Coal Handling Plant 10.00

9 Water Body 8.43

10 Others 140.00

Total 851.78

Page 13: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-14

___________________________________________________________________

Geomatics Division (Remote Sensing Cell), CMPDIL, (HQ) Ranchi. The Map is given as Plate No. -3

Land Use pattern of Core Zone based on Satellite Imagery Data of the year-2016.

AREA STATISTICS

Core Zone

Sl. No.

Class of land Sub Class Area

Km2 %

1 Forest

Dense Forest 0.02 0.34

Open forest 1.27 21.38

Total Forest 1.29 21.72

Scrubs 0.94 15.82

Social Forestry 1.03 17.34

Plantation on OB dumps 0.12 2.02

Plantation on backfill 0.02 0.34

Total Plantation 1.17 19.70

Total Vegetation 3.38 57.24

2

Active Mining area

Active quarry 0.69 11.62

Advance quarry site 0.51 8.59

Coal Dump 0.00 0.00

Water filled quarry 0.03 0.51

Total area under Active Mining 1.23 20.71

Reclaimed Area

Barren OB dump 0.39 6.57

Barren backfilled area 0.31 5.22

Area under technical reclamation

0.70 11.79

Total area under mining 1.93 32.49

3 Wasteland

Wasteland 0.06 1.01

Fly ash pond 0.07 1.18

Total wasteland 0.13 2.19

4 Water bodies Reservoir, nallah, ponds 0.03 0.51

Total water bodies 0.03 0.51

5 Agriculture

Crop land 0.19 3.20

Fallow land 0.22 3.70

Total agriculture 0.41 6.90

6 Settlement

Urban settlement 0.01 0.17

Rural settlement 0.02 0.34

Industrial settlement 0.03 0.51

Total settlement 0.60 1.02

Grand Total 5.94 100

The land use (based on satellite imagery) pattern of core zone is shown in Plate-3.

4.5 Bio-Environment Conservation at Krishnashila OCP:

Page 14: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-15

___________________________________________________________________

Plantation is being done as per the norms and guidelines of forest department. This helps in enriching the flora and fauna of project area. The density of plantations undertaken is 2500 plants per Ha in plain area and 3500 plants per Ha on OB dumps. So far, 76.05 Ha of OB dump area has already been planted. Total no of saplings planted: 2.595 lakhs

Species of plantation : Sagaon , Chipal , Sheeesam , Pletafarm , Kachnar , Akesia , Prosopis , JangalJalebi , Ber , Babool , Amala , Karani ,Babul etc. The year wise detail of plantation done in the Krishnashila Expansion OCP lease area is given below.

Sl. No.

Year Plantation done on OB dump

Area in Ha. No of plants Type of OB Dump

1 2009-10 6.00 21,500 External Dump

2 2010-11 10.00 35,000 External Dump

3 2011-12 10.00 35,000 External Dump

4 2012-13 12.85 45,000 External Dump

5 2013-14 10.00 35,000 External Dump

6 2014-15 20.00 70,000 External Dump

7 2015-16 - - -

8 2016-17 1.20 3000 Internal Dump

9 2017-18 6.00 15000 Internal Dump

Total 76.05 259500

Also, Eco-restoration was carried out by FRI Dehradun on 5.00 Ha area on external dump in 2014-15 and in 2016-17, 2000 nos. plants have been planted along haul roads.

4.6 Socio-Economic Issues:

The proposed project Expansion will further give a boost to the economy of the area by providing primary and secondary employment to local people. The infra-structural facilities provided by the project are benefitting local villagers also. The mine closure activity is likely to significantly reduce the impact of industrial activity on the land apart from increasing the green cover and surface water availability. The standard of living of the local inhabitants has improved significantly due to indirect employment and service opportunities. Resettlement & Rehabilitation of PAPs

The project has already provided compensation and rehabilitation of affected families. There are a total 21 PAPs and all PAPs have already been rehabilitated. The rehabilitation site is Jawahar Nagar at a distance of 3km. All PAPs have already been rehabilitated.

Corporate Social Responsibility

Corporate Social Responsibility (CSR) is taken up at Krishnashila Project level (Krishnashila OCP). Different villages falling in core zone and adjoining areas are benefited through CSR activities run at project level. The nature of benefits include maintenance of ponds and community buildings, well digging and renovation, road repair, renovation of schools and construction of boundary wall, medical camps, water supply, skill development for

Page 15: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-16

___________________________________________________________________

employment generation etc. The expenditure on CSR activities in Krishnashila Area in last few years is given below:

Year 2014-15 2015-16 2016-17

Amount Spent (Rs. Lakh)

22.41 132.03 31.62

As per the CIL CSR policy of June-2014, the fund for the CSR should be allocated based on 2% of the average net profit of the company for the three immediate preceding financial years or Rs. 2/- per tonne of coal production of previous year whichever is higher. Out of above, 80% would be allocated for CSR activities to be carried out within the radius of 25 Km of the project site and the balance 20% would be allocated for carrying out CSR activities by company in the state to which it belongs.

4.7 Detail of Last Public Hearing The public hearing was conducted for 5.0 Mtpa production capacity on 6th October, 2012 at Workers Recreation Centre, Bina Project, and NCL. Detail of Public hearing along with ATR is given in Annexure No.-VI.

5.0 Analysis of Alternatives Not applicable, as this is an increase in production capacity to 7.00 Mtpa of existing opencast mine.

6.0 Environmental Monitoring Program

For effective implementation, a time bound action plan for environmental management including all aspects are being followed by the project. Samples for study of ambient air quality, water/Effluent quality, groundwater level and noise level are collected and tested quarterly at strategic places representing all the categories of location. Refer Plate No.2 and Plate No.4 for sampling point location details.

7.0 Project Benefits

Development of Krishnashila OCP has considerably improved the socio-economic status of the adjoining areas. This has resulted in following benefits:

Improvements in Physical Infrastructure

Improvements in Social Infrastructure

Increase in Employment Potential

Contribution to the Exchequer

Meet energy requirement

Post-mining Enhancement of Green Cover

8.0 Environmental Management Plan

Page 16: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-17

___________________________________________________________________

Northern Coalfields Limited, the owner of this project has already set-up an Environmental Department headed by a General Manager at its HQs. The cell provides necessary support that is required for Environmental Management of various projects and mines under the jurisdiction of the company.

9.0 Mine Closure Planning:

Mine closure planning has to be carried out at the starting of the mine and needs periodic reviewing and revision during its life cycle to cope with the geo-technical constraints, safety and economic risks, social & environmental challenges. Various other objectives are as follows.

a) To allow a productive and sustainable after-use of the site this is acceptable to the mine owner and the regulatory authority.

b) To protect public health and safety.

c) To alleviate or eliminate environmental damage and thereby encourage environmental sustainability.

d) To minimize adverse socio-economic impacts.

As Per Mining plan (Nov., 2017) the Mine closure cost has been estimated as Rs. 9417.64 lakhs based on the guide lines provided by MOC. Final reclaimed dump plan and cross section are given in Plate-8, &9.

10.0 Disclosure of Consultants

Environmental baseline data generation was done from Oct.’ 2012 to Dec.’2012. The detail of consultants employed for different studies is given below.

Sl. No.

Nature of Study Date and duration of study

Name of Agency which has conducted the study

1 Seasonal Ambient Air Quality Study

Oct’12 - Dec’12

ICFRE, Dehradun

2 Soil Quality study

3 Socio- Economic Study

4 Flora & Fauna study

5 Ambient Noise Level Study

6 Water Quality study

7 Hydro-geological Study Nov’2012 CMPDI

Page 17: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-18

___________________________________________________________________

8 Geology, Mining & economic parameter

Re-cast Project Report-March-2010

CMPDI

9 Groundwater level data for Observation wells

From 1990 to 2012 M.P. State Groundwater Data Centre, Bhopal & CMPDI

11.0 Capital Cost of Environmental Control Measures (As per EMP-Dec.-2012)

S No. Particulars Cost

(Rs Lakh)

1 Rehabilitation 85.12

2 Compensatory Afforestation 603.98

3 Cost of Technical Reclamation 369.00

4 Anti-Pollution Measures In Mine area 389.00

5 Anti-Pollution Measures In Industrial area 395.77

6 Anti-Pollution Measures In Colony area 265.97

7 Other Provisions 192.00

Total 2300.84

12.0 Justification for grant of Environmental Clearance

1. The project has already obtained Environmental Clearance for 6.25 Mtpa by EAC of MOEFCC vide letter No.J-11015/243/2011.IA.II (M) dated 13.02.2017. (Ref. Annexure. No-IV with accompanying Form-I). There is no change in mining lease area, mining technology, project economics, product mix and other project parameters.

2. The increase in production capacity is only 0.75 Mtpa which is well within the ceiling of 40% as specified in MOEFCC OM No.J-11015/224/2015-IA.II dated 15.09.2017.

3. A summarised EIA-EMP has been prepared on existing environmental scenario, impact assessment & control measures, disaster management due to increased production. By increasing the capacity of mine from 6.25 Mtpa to 7.00 Mtpa, there will be no increase in the pollution load except marginal increase of PM10 level which is also within the permissible limit.

Page 18: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-19

___________________________________________________________________

The summarised Environmental Impact Assessment (EIA) is given in Annexure No.-I.

The Project authority is monitoring the Environmental Quality to determine the pollution level and ensuring that Ambient Air, Water & Noise quality is kept within permissible limit.

4. It is assessed that there will be no increase in the pollution load and the air quality level due to peak production will be within the prescribed limit. No additional land is required for the project. No additional Resettlement and Rehabilitation is required. The EC for 6.25 Mtpa production level already exists.

5. All the statutory environmental requirements are complied with, therefore, it is kindly

submitted that approval for environmental clearance as per the MOEFCC OM No.J-11015/224/2015-IA.II dated 15.09.2017 for 7.00 Mtpa (increase in capacity), in respect of Krishnashila OCP of NCL may please be granted.

Page 19: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-20

___________________________________________________________________

Table No.-1

Baseline Ambient Air Quality Data for October, 2012 (Krishnashila)

Buffer Zone

(AQ-2, Junior Guest House)

Monitoring

Date 04/10 05/10 11/10 12/10 15/10 16/10 23/10 24/10 28/10 29/10

SPM 197 173 147 169 227 161 193 187 217 214

PM10 107 86 74 89 104 87 94 85 102 97

PM2.5 61 49 42 55 61 47 56 47 54 52

SOx 10 14 12 13 11 14 12 10 11 13

NOx 16 24 19 17 23 21 19 18 20 22

Pb 0.06 0.20 0.12 0.14 0.18 0.16 0.09 0.17 0.10 0.08

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.006 0.003 0.002 0.005 0.001 0.003 0.002 0.004 0.005

Hg ND ND ND ND ND ND ND ND ND ND

Buffer Zone

(AQ-3,Dudhichua)

Monitoring Date

04/10 05/10 11/10 12/10 15/10 16/10 23/10 24/10 28/10 29/10

SPM 138 142 162 174 160 148 155 162 146 149

PM10 65 68 72 59 74 77 72 67 70 75

PM2.5 45 34 40 44 38 41 45 36 40 47

Sox 10 12 9.5 11 10.5 12 14 12 14 15

NOx 13 15 18 16 14 19 18 21 17 20

Pb 0.05 0.08 0.10 0.09 0.10 0.11 0.14 0.14 0.10 0.15

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.005 0.002 0.003 0.001 0.004 0.003 0.002 0.005 0.001

Hg ND ND ND ND ND ND ND ND ND ND

Page 20: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-21

___________________________________________________________________

Table No.-1

Baseline Ambient Air Quality Data for October, 2012 (Krishnashila)

Core Zone

(AQ-4, Field Office)

Monitoring Date

06/10 07/10 13/10 14/10 17/10 18/10 25/10 26/10 30/10 31/10

SPM 364 297 338 354 317 377 336 352 314 307

PM10 175 155 157 171 155 178 154 170 157 144

PM2.5 102 93 94 98 76 107 76 98 92 73

SOx 17 26 20 19 22 18 24 22 24 23

NOx 21 30 26 27 26 24 22 27 28 26

Pb 0.05 0.21 0.13 0.07 0.10 0.08 0.14 0.11 0.15 0.13

As ND ND ND ND ND ND ND ND ND ND

Ni 0.006 0.012 0.009 0.007 0.006 0.009 0.011 0.010 0.009 0.007

Hg ND ND ND ND ND ND ND ND ND ND

Buffer Zone

(AQ-5, Chanduwar

Village)

Monitoring Date

06/10 07/10 13/10 14/10 17/10 18/10 25/10 26/10 30/10 31/10

SPM 147 140 187 174 189 149 167 176 162 149

PM10 76 68 92 90 94 77 81 87 79 75

PM2.5 44 42 54 52 48 41 49 54 48 47

SOx 12 16 14 15 14 12 16 12 14 15

NOx 15 22 18 17 19 16 18 22 17 15

Pb 0.05 0.18 0.10 0.12 0.10 0.08 0.13 0.14 0.10 0.15

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.005 0.002 0.003 0.001 0.004 0.003 0.002 0.005 0.001

Hg ND ND ND

ND ND ND ND ND

ND ND

Buffer Zone

(AQ-6, Khadia)

Monitoring Date

06/10 07/10 13/10 14/10 17/10 18/10 25/10 26/10 30/10 31/10

SPM 132 128 134 138 134 140 130 132 136 134

PM10 56 54 60 74 68 62 56 62 58 62

PM2.5 34 36 32 37 34 36 34 38 39 41

SOx 12 12 14 12 15 12 14 13 10.5 12

NOx 22 18 20 16 19 17 21 18 17 15

Pb 0.05 0.12 0.14 0.16 0.12 0.08 0.10 0.12 0.14 0.12

As ND ND ND ND ND ND ND ND ND ND

Ni 0.002 0.005 0.004 0.005 0.002 0.001 0.003 0.002 0.004 0.001

Hg ND ND ND ND ND ND ND ND ND N

Page 21: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-22

___________________________________________________________________

Table No.-1

Baseline Ambient Air Quality Data for November, 2012 (Krishnashila)

Buffer Zone

(AQ-2, Junior Guest House)

Monitoring Date

04/11 05/11 12/11 13/11 15/11 16/11 24/11 25/11 28/11 29/11

SPM 189 183 157 160 237 158 195 196 210 207

PM10 110 89 78 93 114 82 98 78 99 92

PM2.5 62 55 48 58 64 52 48 54 58 52

SOx 12 17 14 15 13 17 16 15 15 17

NOx 21 25 23 23 19 25 26 19 21 24

Pb 0.06 0.19 0.15 0.18 0.14 0.18 0.07 0.13 0.09 0.09

As ND ND ND ND ND ND ND ND ND ND

Ni 0.002 0.005 0.003 0.003 0.006 0.002 0.005 0.003 0.006 0.005

Hg ND ND ND

ND ND ND ND ND

ND ND

Buffer Zone

(AQ-3,Dudhichua)

Monitoring Date

04/11 05/11 12/11 13/11 15/11 16/11 24/11 25/11 28/11 29/11

SPM 128 148 168 170 160 140 151 154 158 142

PM10 71 74 78 67 80 83 78 72 75 81

PM2.5 42 30 43 41 35 44 49 40 43 51

SOx 13 15 11 14 9 16 11 14 12 13

NOx 16 18 21 19 17 22 20 24 21 20

Pb 0.06 0.09 0.11 0.08 0.18 0.15 0.19 0.10 0.12 0.14

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.002 0.003 0.005 0.001 0.003 0.002 0.002 0.004 0.001

Hg ND* ND ND ND ND ND ND ND ND ND

* ND-Not Detected

Page 22: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-23

___________________________________________________________________

Table No.-1

Baseline Ambient Air Quality Data for October, 2012 (Krishnashila)

Core Zone

(AQ-4, Field Office)

Monitoring Date

06/11 07/11 14/11 15/11 18/11 19/11 26/11 27/11 30/11 01/12

SPM 354 299 348 372 327 372 339 345 334 317

PM10 168 150 149 166 159 168 162 184 159 138

PM2.5 99 93 95 90 77 110 82 85 101 73

SOx 19 23 17 21 24 23 19 28 22 25

NOx 28 34 25 29 31 34 24 36 26 31

Pb 0.07 0.23 0.18 0.07 0.14 0.08 0.10 0.15 0.15 0.11

As ND ND ND ND ND ND ND ND ND ND

Ni 0.007 0.010 0.009 0.008 0.009 0.011 0.014 0.012 0.009 0.009

Hg ND ND ND ND ND ND ND ND ND ND

Buffer Zone

(AQ-5, Chanduwar Village)

Monitoring Date

06/11 07/11 14/11 15/11 18/11 19/11 26/11 27/11 30/11 01/12

SPM 130 147 167 184 184 142 162 182 166 154

PM10 66 72 86 97 85 69 84 92 81 92

PM2.5 42 46 57 48 57 38 44 49 53 54

SOx 11 14 17 16 19 10 19 15 18 14

NOx 16 27 23 20 24 17 22 20 23 19

Pb 0.06 0.10 0.10 0.14 0.09 0.09 0.11 0.12 0.16 0.15

As ND ND ND ND ND ND ND ND ND ND

Ni 0.002 0.006 0.003 0.005 0.006 0.007 0.003 0.004 0.003 0.002

Hg ND ND ND

ND ND ND ND ND

ND ND

Buffer Zone

(AQ-6, Khadia)

Monitoring Date

06/11 07/11 14/11 15/11 18/11 19/11 26/11 27/11 30/11 01/12

SPM 135 134 139 145 140 135 132 137 144 134

PM10 53 57 63 70 71 60 49 65 55 7

PM2.5 31 38 29 33 36 34 39 42 43 41

SOx 11 13 15 10 15 13 11 18 11 15

NOx 18 17 21 16 22 16 15 22 16 21

Pb 0.05 0.10 0.16 0.10 0.15 0.09 0.11 0.15 0.16 0.11

As ND ND ND ND ND ND ND ND ND ND

Ni 0.004 0.003 0.007 0.005 0.003 0.006 0.009 0.005 0.006 0.003

Hg ND* ND ND ND ND ND ND ND ND ND

* ND-Not Detected

Page 23: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-24

___________________________________________________________________

Table No.-1

Baseline Ambient Air Quality Data for December, 2012 (Krishnashila)

Buffer Zone

(AQ-2, Junior Guest House)

Monitoring Date

04/12 05/11 12/12 13/12 17/12 18/12 23/12 24/12 27/12 28/12

SPM 201 164 155 174 210 168 188 175 223 210

PM10 110 93 75 81 109 83 96 81 112 95

PM2.5 65 53 40 63 58 51 62 55 58 52

SOx 11 12 14 13 11 17 12 9 13 13

NOx 15 18 18 21 19 23 19 15 18 17

Pb 0.06 0.21 0.13 0.15 0.19 0.13 0.08 0.16 0.10 0.09

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.005 0.006 0.002 0.004 0.001 0.004 0.002 0.004 0.003

Hg ND ND ND

ND ND ND ND ND

ND ND

Buffer Zone

(AQ-3,Dudhichua)

Monitoring Date

04/12 05/11 12/12 13/12 17/12 18/12 23/12 24/12 27/12 28/12

SPM 138 140 156 174 160 152 158 160 146 148

PM10 65 68 72 59 74 77 69 68 69 74

PM2.5 44 36 40 46 38 45 42 36 40 47

SOx 10 12 9.5 11 10.5 12 14 12 14 15

NOx 13 15 18 16 14 19 18 21 17 20

Pb 0.05 0.08 0.10 0.09 0.10 0.11 0.14 0.14 0.10 0.15

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.005 0.002 0.003 0.001 0.004 0.003 0.002 0.005 0.001

Hg ND* ND ND ND ND ND ND ND ND ND

* ND-Not Detected

Page 24: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-25

___________________________________________________________________

Table No.-1

Baseline Ambient Air Quality Data for October, 2012 (Krishnashila)

Core Zone

(AQ-4, Field Office)

Monitoring Date

06/12 07/12 14/12 15/12 19/12 20/12 25/12 26/12 29/12 30/12

SPM 360 292 336 350 323 371 330 352 314 307

PM10 175 155 157 171 155 178 154 196 152 140

PM2.5 101 91 96 90 81 110 79 96 91 75

SOx 18 26 21 20 23 19 18 21 25 22

NOx 21 28 26 29 31 24 25 27 28 28

Pb 0.05 0.10 0.13 0.08 0.11 0.08 0.13 0.11 0.14 0.13

As ND ND ND ND ND ND ND ND ND ND

Ni 0.006 0.08 0.009 0.007 0.009 0.009 0.013 0.010 0.008 0.006

Hg ND ND ND ND ND ND ND ND ND ND

Buffer Zone

(AQ-5, Chanduwar

Village)

Monitoring Date

06/12 07/12 14/12 15/12 19/12 20/12 25/12 26/12 29/12 30/12

SPM 145 139 165 174 182 149 168 171 166 152

PM10 76 68 93

88 92 76 80 85

78 74

PM2.5 43 40 55 50 48 43 47 55 48 46

SOx 12 17 13 15 13 12 17 12 11 15

NOx 15 22 18 17 19 16 18 22 17 15

Pb 0.05 0.17 0.11 0.13 0.10 0.09 0.15 0.11 0.10 0.14

As ND ND ND ND ND ND ND ND ND ND

Ni 0.001 0.005 0.002 0.003 0.001 0.004 0.003 0.002 0.005 0.001

Hg ND ND ND ND ND ND ND ND ND ND

Buffer Zone

(AQ-6, Khadia)

Monitoring Date

06/12 07/12 14/12 15/12 19/12 20/12 25/12 26/12 29/12 30/12

SPM 133 125 129 134 136 140 130 136 139 133

PM10 56 54 60 74 68 66 56 62 58 58

PM2.5 34 31 27 45 30 39 34 40 38 41

SOx 11 12 15 12 15 13 14 13 10.5 12

NOx 17 18 20 19 19 17 21 19 17 15

Pb 0.05 0.10 0.11 0.14 0.09 0.06 0.10 0.13 0.10 0.12

As ND ND ND ND ND ND ND ND ND ND

Ni 0.002 0.002 0.005 0.002 0.003 0.001 0.005 0.002 0.003 0.001

Hg ND* ND ND ND ND ND ND ND ND ND

* ND-Not Detected

Page 25: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-26

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY MONITORING

Location of sampling station and their rationale ( as per G.S.R. 742 (E) dt. 25th December,2000)

Ambient Air Quality Sampling Locations:

I. CORE ZONE Monitoring Location (Refer Plate No.- 1)

i) Krishnashila GM Office (KSA1): Industrial Area

The sampler was placed at the GM Office near mine working zone. The station was selected to assess the ambient air quality in the core zone where mining activities are in progress.

ii) Outsourcing Camp (KSA2) : Industrial Area

The Air sampler was placed at outsourcing camp office. This station was selected to assess the ambient air quality in the core zone where mining activities are in progress.

iii) Radha Krishna Mandir (KSA3): Residential Area

The sampler was placed Radha Krishna Mandir near Residential Colony. This location will represent the ambient air quality of residential area in Core zone of Krishnashila Project.

iv) Bina STP (BA3): Residential Area

The sampler was placed at Bina STP. This site was selected to assess the present ambient air quality status in residential area in Core zone of Krishnashila Project.

II. BUFFER ZONE Monitoring Location (Refer Plate No.- 2)

i) Kohroul Village (KSA4):: Residential Area

This location will represent the ambient air quality of buffer zone of Krishnashila Project.

ii) Khadia CGM Office (KHA3): Residential Area.

The sampler was placed at roof top of Khadia CGM Office STP. This site was selected to assess the present ambient air quality status in residential area in buffer Zone of Krishnashila OCP

iii) Jawharnagar (BA5): Residential Area

This site was selected to assess the present ambient air quality status in residential area in buffer Zone of Krishnashila OCP

iv) IWSS Office (KHA5): Residential Area

The Air sampler was placed in the IWSS Office. The station was selected to assess the impact of mining activities of Krishnashila Project in its buffer zone.

Page 26: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-27

___________________________________________________________________

Table No.-1

Methodology of sampling and analysis

Parameters chosen for assessment of ambient air quality were Suspended Particulate Matter, Respirable Particulate Matter (PM 10), Fine Particulate Matter (PM 2.5), Sulphur Di-oxide (SO2) and Nitrogen Oxides (NOx). Respirable Dust Samplers (RDS) & Fine particulate

Sampler (FPS) were used for sampling “SPM, PM 10, SO2 & NOx” and “PM 2.5” respectively at 24 hours interval once in a fortnight. The samples were analysed in Environmental Laboratory of CMPDI, RI-VI, Jayant.

Results & Interpretations The results of Ambient Air Quality are presented in tabular form along with Bar chart for each monitoring station. The interpretations of different parameters are given below:

Ambient air quality

Suspended Particulate Matter

In core zone under Industrial area varies from 225 to 517 µg/m3. Respirable Particulate Matter (PM 10)

In core zone under Industrial area varies from 149 to 410 µg/m3 & in Residential area 89 to

192 µg/m3. In buffer zone in Residential area varies from 73 to 140 µg/m3. PM 2.5:

In core zone under Industrial area varies from 11 to 61 µg/m3 & in core zone under

Residential area PM 2.5 varies from 19 to 116 µg/m3. In buffer zone in Residential area

varies from 16 to 71 µg/m3. Sulphur Dioxide:

In core zone under Industrial area varies from 15 to 71 µg/m3 & in Residential area 12 to 40

µg/m3. In buffer zone in Residential area varies from 10 to 42 µg/m3. Oxides of Nitrogen:

In core zone under Industrial area varies from 14 to 43 µg/m3 & in Residential area 11 to 45

µg/m3. In buffer zone in Residential area varies from 12 to 45 µg/m3.

Page 27: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-28

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2016-17.

Name of the Project : Krishnashila Opencast Project Q.E.: March’2017.

Core Zone

Name of the Stations & Code :

1. KSA1 - Krishnashila CGM Office 2. KSA2 - Outsourcing Camp

3. KSA3 - Radha Krishna Mandir 4. BA3 - Bina STP

1. Station Code/Name: KSA1 - Krishnashila CGM Office, Category: Industrial.

2. Station Code/Name: KSA2 - Outsourcing Camp, Category: Industrial.

Note: *NA- Standards for coal mines inserted in Environment (Protection) Rules, 1986 via Rule 2(1) of the Environment (Protection) Amendment Rules, 2000 notified vide notification G.S.R. 742(E), dated 5.9.2000. do not stipulate permissible limit for PM 2.5.

Note: All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

SPM RPM PM 2.5

SO2 NOx

06/07.01.2017 377 270 40 36 33

18/19.01.2017 421 299 39 21 21

06/07.02.2017 517 410 50 32 29

21/22.02.2017 436 300 42 24 40

06/07.03.2017 410 309 40 15 14

21/22.03.2017 435 288 39 37 24

Quarterly Average 433 313 42 28 27

Permissible Limits 600 300 *NA 120 120

Dates of sampling

SPM RPM PM 2.5

SO2 NOx

06/07.01.2017 344 232 52 71 43

18/19.01.2017 342 210 57 41 32

06/07.02.2017 299 198 61 25 40

21/22.02.2017 225 149 47 16 38

06/07.03.2017 258 155 11 32 16

21/22.03.2017 416 321 42 40 28

Quarterly Average 314 211 45 38 33

Permissible Limits 600 300 *NA 120 120

Page 28: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-29

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2016-17.

Name of the Project : Krishnashila Opencast Project Q.E.: March’2017.

Core Zone

3. Station Code/Name: KSA3- Radha Krishna Mandir, Category: Residential.

4. Station Code/Name: BA3 - Bina STP, Category: Residential.

Note: All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

PM 10 PM 2.5

SO2 NOx

09/10.01.2017 137 42 12 15

23/24.01.2017 101 58 21 16

07/08.02.2017 192 116 12 11

21/22.02.2017 111 28 13 22

10/11.03.2017 95 32 14 38

23/24.03.2017 121 42 29 41

Quarterly Average 126 53 17 24

Permissible Limits 100 60 80 80

Dates of sampling

PM 10 PM 2.5

SO2 NOx

07/08.01.2017 110 34 24 40

27/28.01.2017 124 29 29 45

11/12.02.2017 100 40 40 29

26/27.02.2017 108 19 13 37

03/04.03.2017 93 34 21 28

23/24.03.2017 89 19 29 40

Quarterly Average 104 29 26 37

Permissible Limits 100 60 80 80

Page 29: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-30

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2016-17.

Name of the Project : Krishnashila Opencast Project Q.E.: March’2017.

Buffer Zone

Name of the Stations & Code :

1. KSA4- Kohraul Village 2. KHA3 – Khadia CGM Office

3. BA5 – Jawhar nagar 4. KHA5 – IWSS Office

1. Station Code/Name: KSA4- Kohraul Village, Category: Residential.

2. Station Code/Name: KHA3 – Khadia CGM Office, Category: Residential.

Note:

All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

PM 10 PM 2.5 SO2 NOx

07/08.01.2017 100 42 14 40

27/28.01.2017 85 55 18 35

11/12.02.2017 73 16 37 26

26/27.02.2017 95 37 16 37

03/04.03.2017 102 28 29 12

23/24.03.2017 88 40 15 18

Quarterly Average 91 36 22 28

Permissible Limits 100 60 80 80

Dates of sampling

PM 10 PM 2.5 SO2 NOx

08/09.01.2017 125 29 14 21

27/28.01.2017 140 30 16 28

03/04.02.2017 121 71 11 22

23/24.02.2017 100 29 10 21

14/15.03.2017 135 22 20 36

25/26.03.2017 100 21 15 30

Quarterly Average 120 34 14 26

Permissible Limits 100 60 80 80

Page 30: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-31

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2016-17.

Name of the Project : Krishnashila Opencast Project Q.E.: March’2017.

Buffer Zone

3. Station Code/Name: BA5 – Jawharnagar, Category: Residential.

4. Station Code/Name: KHA5 – IWSS Office, Category: Residential.

Note:

All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

PM 10

PM 2.5

SO2 NOx

06/07.01.2017 98 25 20 40

24/25.01.2017 87 37 42 42

14/15.02.2017 86 19 28 45

26/27.02.2017 94 40 31 39

13/14.03.2017 76 19 21 28

27/28.032017 85 32 18 21

Quarterly Average

88 29 27 36

Permissible Limits 100 60 80 80

Dates of sampling

PM 10 PM 2.5 SO2 NOx

12/13.01.2017 110 26 26 43

30/31.01.2017 121 24 24 26

12/13.02.2017 100 20 16 21

22/23.02.2017 125 22 19 25

10/11.03.2017 100 31 12 16

30/31.03.2017 104 62 37 13

Quarterly Average 110 31 23 24

Permissible Limits 100 60 80 80

Page 31: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-32

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E.: June’2017.

Core Zone

Name of the Stations & Code :

1. KSA1 - Krishnashila CGM Office 2. KSA2 - Outsourcing Camp

3. KSA3 - Radha Krishna Mandir 4. BA3 - Bina STP

3. Station Code/Name: KSA1 - Krishnashila CGM Office, Category: Industrial.

4. Station Code/Name: KSA2 - Outsourcing Camp, Category: Industrial.

Note: All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

SPM RPM PM 2.5

SO2 NOx

08/09.04.2017 398 270 54 30 11

20/21.04.2017 375 245 87 25 25

08/09.05.2017 364 222 38 34 18

22/23.05.2017 399 266 51 16 14

14/15.06.2017 429 309 60 16 23

21/22.06.2017 317 200 39 26 26

Quarterly Average 380 252 55 25 19

Permissible Limits 600 300 *NA 120 120

Dates of sampling

SPM RPM PM 2.5

SO2 NOx

14/15.04.2017 456 310 61 26 17

20/21.04.2017 426 300 75 23 17

08/09.05.2017 395 288 61 13 10

22/23.05.2017 367 261 67 12 10

14/15.06.2017 328 210 58 28 25

21/22.06.2017 367 221 49 29 15

Quarterly Average 390 265 62 22 16

Permissible Limits 600 300 *NA 120 120

Page 32: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-33

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E.: June’2017.

Core Zone

3. Station Code/Name: KSA3- Radha Krishna Mandir, Category: Residential.

4. Station Code/Name: BA3 - Bina STP, Category: Residential.

Note: *NA- Standards for coal mines inserted in Environment (Protection) Rules, 1986 via Rule 2(1) of the Environment (Protection) Amendment Rules, 2000 notified vide notification G.S.R. 742(E), dated 5.9.2000. do not stipulate permissible limit for PM 2.5.

Dates of sampling

PM 10 PM 2.5

SO2 NOx

08/09.04.2017 137 31 23 26

27/28.04.217 125 28 28 33

06/07.05.2017 92 34 29 35

29/30.05.2017 96 28 35 17

08/09.06.2017 104 28 29 23

27/28.06.2017 54 24 25 27

Quarterly Average 101 29 28 27

Permissible Limits 100 60 80 80

Dates of sampling

PM 10 PM 2.5

SO2 NOx

14/15.04.2017 136 42 25 30

26/27.04.2017 140 59 18 34

12/13.05.2017 134 33 16 25

25/26.05.2017 104 22 27 16

13/14.06.2017 98 40 15 28

27/28.06.2017 68 38 16 40

Quarterly Average 113 39 20 29

Permissible Limits 100 60 80 80

Page 33: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-34

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E.: June’2017.

Buffer Zone

Name of the Stations & Code :

1. KSA4- Kohraul Village 2. KHA3 – Khadia CGM Office

3. BA5 – Jawhar nagar 4. KHA5 – IWSS Office

1. Station Code/Name: KSA4- Kohraul Village, Category: Residential.

2. Station Code/Name: KHA3 – Khadia CGM Office, Category: Residential.

Note: All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

PM 10 PM 2.5 SO2 NOx

08/09.04.2017 124 35 11 25

27/28.04.217 100 25 13 25

06/07.05.2017 92 21 21 10

29/30.05.2017 87 39 22 14

08/09.06.2017 98 21 21 18

27/28.06.2017 67 18 17 10

Quarterly Average 95 27 18 17

Permissible Limits 100 60 80 80

Dates of sampling

PM 10 PM 2.5 SO2 NOx

13/14.04.2017 124 45 12 32

26/27.04.2017 105 41 16 14

13/14.05.2017 114 58 18 19

24/25.05.2017 121 38 24 16

16/14.06.2017 99 22 22 27

26/27.06.2017 123 36 31 32

Quarterly Average 114 40 21 23

Permissible Limits 100 60 80 80

Page 34: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-35

___________________________________________________________________

Table No.-1

AMBIENT AIR QUALITY DATA

Name of the Company: Northern Coalfield Limited Year: 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E.: June’2017.

Buffer Zone

3. Station Code/Name: BA5 – Jawharnagar, Category: Residential.

4. Station Code/Name: KHA5 – IWSS Office, Category: Residential.

Note:

All values are expressed in microgram per cubic meter.

24 hours duration

Dates of sampling

PM 10

PM 2.5

SO2 NOx

06/07.04.2017 133 45 24 28

24/25.04.2017 92 38 15 24

14/15.05.2017 118 55 16 26

26/27.05.2017 137 32 28 30

13/14.06.2017 107 39 20 24

27/28.06.2017 103 40 21 28

Quarterly Average 115 42 21 27

Permissible Limits 100 60 80 80

Dates of sampling

PM 10 PM 2.5 SO2 NOx

09/10.04.2017 161 41 16 22

25/26.04.2017 102 24 10 14

13/14.05.2017 133 61 11 19

25/26.05.2017 126 22 31 15

07/08.06.2017 98 41 59 36

27/28.06.2017 91 56 11 19

Quarterly Average 119 41 23 21

Permissible Limits 100 60 80 80

Page 35: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-36

___________________________________________________________________

Table No.-1

Heavy Metal Analysis of PM 10 in Ambient Air of Krishnashila Project (Half year ending June’ 17)

Sl No. Name of Station & Code Area Hg As Pb Cr Ni

I. Core Zone Monitoring Stations

1. Krishnashila GM Office -KSA1 Industrial BDL BDL BDL BDL BDL

2. Outsourcing Camp- KSA2 Industrial BDL BDL BDL BDL BDL

3. Radha Krishna Mandir- KSA3 Industrial BDL BDL BDL BDL BDL

4. Bina STP - BA3 Residential BDL BDL BDL BDL BDL

II. Buffer Zone Monitoring Stations

5. Kohroul Village - KSA4 Residential BDL BDL BDL BDL BDL

6. Khadia CGM Office - KHA3 Residential BDL BDL BDL BDL BDL

7. Jawahar Nagar- BA5 Residential BDL BDL BDL BDL BDL

8. IWSS Office -KHA5 Residential BDL BDL BDL BDL BDL

Note: All values are in µg/m3

Page 36: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-37

___________________________________________________________________

Table No.-2

WATER QUALITY MONITORING

Location of Sampling Stations and their rationale: (Refer Fig. No. - II) i) Mine Sump water (KSW3) The quality of the mine sump water needs to be monitored. Sampling site is selected to check the water quality of mine water after pumping.

ii) Tap water at Jr. Transit camp, Bina (KSW1) To assess the drinking water quality, a water sample from Transit hostel was taken. iii) Hand Pump at Kohroul Village (KSW2) To assess the ground water quality variation due to mining in rehabilitation complex, this site was selected.

Methodology of sampling and analysis

Water samples were collected as per standard practice. The effluent samples and drinking water samples were collected and analyzed for four/five parameters on fortnightly basis. The drinking water samples were collected and analysed for all parameters on quarterly basis. Parameters like pH, Temperature and Dissolved Oxygen were analyzed on-site while collecting the samples. Thereafter the samples were preserved and analyzed at the field laboratory located at RI-VI Office campus.

Results & Interpretations

The results are given in tabular form along with the applicable standards. Results are compared with as per MoEFCC Gazette Notification No. GSR 742(E) dt 25.09.2000 Std. for Coal mines (For 4/5 parameters of effluent and drinking water) & IS.10500/2012 (All parameters of Drinking water). Results show that most of the parameters are within the permissible limits.

.

Page 37: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-38

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Mine Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month: January.

Name of the Stations & Code : 1. KSW3- Mine Sump water

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

02.01.2017

4:15PM

1 Total Suspended Solids 184

2 pH 5.58

3 Oil & Grease 5

4 COD 36

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

16.01.2017

4:15PM

1 Total Suspended Solids 110

2 pH 7.82

3 Oil & Grease 4

4 COD 40

All values are expressed in mg/lit unless specified.

Page 38: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-39

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Mine Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month: February.

Name of the Stations & Code :

1. KSW3- Mine Sump water

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

01.02.2017

4:15PM

1 Total Suspended Solids 380

2 pH 7.13

3 Oil & Grease 11

4 COD 36

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

16.02.2017

4:15PM

1 Total Suspended Solids 340

2 pH 7.85

3 Oil & Grease 12

4 COD 76

All values are expressed in mg/lit unless specified.

Page 39: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-40

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Mine Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month: March. Name of the Stations & Code : 1. KSW3- Mine Sump water

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

01.03.2016

4:15PM

1 Total Suspended Solids 148

2 pH 7.7

3 Oil & Grease 9

4 COD 45

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

16.03.2017

4:15PM

1 Total Suspended Solids 399

2 pH 7.39

3 Oil & Grease 10

4 COD 36

All values are expressed in mg/lit unless specified.

Page 40: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-41

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month. : January.

Name of the stations & Code:

1. KSW1- Tap Water of Jr. Transit camp, Bina 2. KSW2- Hand Pump water from Kohroul Village

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

Requirement ( Acceptable Limit)

Permissible Limit in the absence of Alternate Source

02.01.2017 02.01.2017

6:30PM 5:40PM

1 Dissolved Solid 85 349 500 2000

2 pH 7.48 7.06 6.5 – 8.5 No

relaxation

3 Fluoride 0.5 BDL 1.0 1.5

4 Turbidity, NTU 8 3 1 5

5 Residual Free Chlorine 0.05 - 0.2 1

6 MPN (Coliforms) - NIL NIL No

relaxation

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

16.01.2017 16.01.2017 Requirement ( Acceptable

Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 301 374 500 2000

2 pH 7.78 7.22 6.5 – 8.5 No relaxation

3 Fluoride 0.3 0.7 1.0 1.5

4 Turbidity, NTU 1 3 1 5

5 Residual Free Chlorine 0.04 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

All values are expressed in mg/lit unless specified

Page 41: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-42

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month. : February.

Name of the stations & Code :

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

01.02.2017 01. 02.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid

Analysis Results are included in all Parameters for Q.E. March,

2017 given separately.

500 2000

2 pH 6.5 – 8.5 No relaxation

3 Fluoride 1.0 1.5

4 Turbidity, NTU 1 5

5 Residual Free Chlorine 0.2 1

6 MPN (Coliforms) NIL No relaxation

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

16.02.2017 16.02.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 163 245 500 2000

2 pH 7.94 7.81 6.5 – 8.5 No relaxation

3 Fluoride 0.3 0.1 1.0 1.5

4 Turbidity, NTU 4 1 1 5

5 Residual Free Chlorine 0.02 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

All values are expressed in mg/lit unless specified

Page 42: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-43

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month. : March.

Name of the stations & Code:

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

01.03.2017 01.03.2017 Requireme

nt (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 230 336 500 2000

2 pH 7.15 7.43 6.5 – 8.5 No relaxation

3 Fluoride 0.4 0.6 1.0 1.5

4 Turbidity, NTU 2 6 1 5

5 Residual Free Chlorine 0.02 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

16.03.2017 16.03.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 246 363 500 2000

2 pH 7.1 7.45 6.5 – 8.5 No relaxation

3 Fluoride 0.5 0.2 1.0 1.5

4 Turbidity, NTU 2 3 1 5

5 Residual Free Chlorine 0.01 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

All values are expressed in mg/lit unless specified

Page 43: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-44

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Q.E. : March, 2017

Name of the stations & Code:

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp,)

KSW2 (Hand Pump-

Kohraol Village)

02.02.2017 02.02.2017 Requirement ( Acceptable

Limit)

Permissible Limit in the absence of Alternate Source

6:35PM 5:45PM

1 Colour, Hazen Unit. 7 4 5 15

2 Odour Unobjectionable Unobjectionable Agreeable Agreeable

3 Taste Agreeable Agreeable Agreeable Agreeable

4 Turbidity, NTU 5 4 1 5

5 pH Value 7.59 7.29 6.5 – 8.5 No relaxation

6 Total Hardness 96 266 200 600

7 Iron 0.2 0.268 0.3 No relaxation

8 Chlorides 140 126 250 1000

9 Residual Free Chlorine

0.06 - 0.2 1

10 Dissolved Solids 140 345 500 2000

11 Calcium 14 30 75 200

12 Sulphate 38 32 200 400

13 Nitrate 4 4.5 45 No relaxation

14 Fluoride 0.1 0.4 1.0 1.5

15 Phenolics BDL (<0.001) BDL (<0.001) 0.001 0.002

16 Alkalinity 140 440 200 600

17 MPN - NIL NIL No relaxation

18 Hexavalent Chromium

BDL BDL 0.05 No relaxation

19 Boron BDL (<0.01) BDL (<0.01) 0.5 1.0

20 Copper 0.024 0.033 0.05 1.5

21 Manganese BDL (<0.05) 0.109 0.1 0.3

22 Arsenic BDL (<0.01) BDL (<0.01) 0.01 0.05

23 Selenium BDL (<0.01) BDL (<0.01) 0.01 No relaxation

24 Lead BDL (<0.05) BDL (<0.05) 0.01 No relaxation

25 Zinc 0.0606 0.3026 5 15

26 Mercury BDL (<0.001) BDL (<0.001) 0.001 No relaxation

All values are expressed in mg/lit unless specified

Page 44: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-45

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Mine Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month: April.

Name of the Stations & Code : 1. KSW3- Mine Sump water

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

01.04.2017

4:15PM

1 Total Suspended Solids 74

2 pH 7.31

3 Oil & Grease 4

4 COD 39

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

17.04.2017

4:15PM

1 Total Suspended Solids 71

2 pH 7.68

3 Oil & Grease 4

4 COD 39

All values are expressed in mg/lit unless specified.

Page 45: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-46

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Mine Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month: May.

Name of the Stations & Code :

1. KSW3- Mine Sump water

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

02.05.2017

4:15PM

1 Total Suspended Solids 54

2 pH 7.29

3 Oil & Grease 6

4 COD 36

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

16.05.2017

4:15PM

1 Total Suspended Solids 70

2 pH 7.3

3 Oil & Grease 5

4 COD 43

All values are expressed in mg/lit unless specified.

Page 46: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-47

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Mine Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month: June.

Name of the Stations & Code :

1. KSW3- Mine Sump water

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

01.06.2017

4:15PM

1 Total Suspended Solids 70

2 pH 7.39

3 Oil & Grease 9

4 COD 29

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

KSW3 (Mine Sump )

16.06.2017

4:15PM

1 Total Suspended Solids 55

2 pH 7.98

3 Oil & Grease 4

4 COD 28

All values are expressed in mg/lit unless specified.

Page 47: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-48

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month. : April.

Name of the stations & Code:

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

01.04.2017 01.04.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 110 321 500 2000

2 pH 7.66 7.01 6.5 – 8.5 No relaxation

3 Fluoride 0.1 0.1 1.0 1.5

4 Turbidity, NTU 2 1 1 5

5 Residual Free Chlorine 0.03 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

17.04.2017 17.04.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 200 406 500 2000

2 pH 7.99 7.8 6.5 – 8.5 No relaxation

3 Fluoride 0.4 0.3 1.0 1.5

4 Turbidity, NTU 1 6 1 5

5 Residual Free Chlorine 0.03 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

All values are expressed in mg/lit unless specified

Page 48: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-49

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month. : May.

Name of the stations & Code :

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

02.05.2017 02. 05.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid

Analysis Results are included in all Parameters for Q.E. June,

2017 given separately.

500 2000

2 pH 6.5 – 8.5 No relaxation

3 Fluoride 1.0 1.5

4 Turbidity, NTU 1 5

5 Residual Free Chlorine 0.2 1

6 MPN (Coliforms) NIL No relaxation

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

16.05.2017 16.05.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 220 392 500 2000

2 pH 7.86 7.52 6.5 – 8.5 No relaxation

3 Fluoride 0.2 0.6 1.0 1.5

4 Turbidity, NTU 1 4 1 5

5 Residual Free Chlorine 0.02 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

All values are expressed in mg/lit unless specified

Page 49: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-50

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month. : June.

Name of the stations & Code:

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

First Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

01.06.2017 01.06.2017 Requireme

nt (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 239 368 500 2000

2 pH 7.35 6.85 6.5 – 8.5 No relaxation

3 Fluoride 0.2 0.6 1.0 1.5

4 Turbidity, NTU 2 4 1 5

5 Residual Free Chlorine 0.04 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

Second Fortnight data

Sl. No.

Parameters

Sampling station & sampling date/time

Tolerance Limit (As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp, Bina)

KSW2 (Hand Pump-

Kohroul Village)

16.06.2017 16.06.2017 Requirement (

Acceptable Limit)

Permissible Limit in the absence of Alternate Source

6:30PM 5:40PM

1 Dissolved Solid 214 392 500 2000

2 pH 7.39 6.92 6.5 – 8.5 No relaxation

3 Fluoride 0.4 0.1 1.0 1.5

4 Turbidity, NTU 2 3 1 5

5 Residual Free Chlorine 0.04 - 0.2 1

6 MPN (Coliforms) - NIL NIL No relaxation

All values are expressed in mg/lit unless specified

Page 50: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-51

___________________________________________________________________

Table No.-2

WATER QUALITY DATA (Drinking Water)

Name of the Company: Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E. : June, 2017

Name of the stations & Code:

1. KSW1- Tap Water of Jr. Transit camp, Bina

2. KSW2- Hand Pump water from Kohroul Village

Sl. No.

Parameters

Sampling station & sampling date/time Tolerance Limit

(As per IS-10500/2012 for Drinking water Standard)

KSW1 (Tap Water

Jr.Trasit camp,)

KSW2 (Hand Pump-

Kohraol Village)

02.05.2017 02.05.2017 Requirement ( Acceptable

Limit)

Permissible Limit in the absence of Alternate Source

6:35PM 5:45PM

1 Colour, Hazen Unit. 5 4 5 15

2 Odour Unobjectionable Unobjectionable Agreeable Agreeable

3 Taste Agreeable Agreeable Agreeable Agreeable

4 Turbidity, NTU 3 3 1 5

5 pH Value 7.71 7.02 6.5 – 8.5 No relaxation

6 Total Hardness 156 250 200 600

7 Iron 0.2 0.214 0.3 No relaxation

8 Chlorides 144 122 250 1000

9 Residual Free Chlorine

0.06 - 0.2 1

10 Dissolved Solids 144 320 500 2000

11 Calcium 40 30 75 200

12 Sulphate 75 36 200 400

13 Nitrate 0.3 1.2 45 No relaxation

14 Fluoride 0.2 0.4 1.0 1.5

15 Phenolics BDL (<0.001) BDL (<0.001) 0.001 0.002

16 Alkalinity 100 82 200 600

17 MPN - NIL NIL No relaxation

18 Hexavalent Chromium

BDL BDL 0.05 No relaxation

19 Boron BDL (<0.01) BDL (<0.01) 0.5 1.0

20 Copper BDL (<0.02) BDL (<0.02) 0.05 1.5

21 Manganese BDL (<0.05) 0.064 0.1 0.3

22 Arsenic BDL (<0.01) BDL (<0.01) 0.01 0.05

23 Selenium BDL (<0.01) BDL (<0.01) 0.01 No relaxation

24 Lead BDL (<0.05) BDL (<0.05) 0.01 No relaxation

25 Zinc 0.066 0.312 5 15

26 Mercury BDL (<0.001) BDL (<0.001) 0.001 No relaxation

All values are expressed in mg/lit unless specified

Page 51: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-52

___________________________________________________________________

Table No.-3

NOISE LEVEL QUALITY MONITORING

Noise Level Sites and their rationale :( Refer Plate No. - 2) i) Site Office (KSN1) This area will represent the ambient noise level near the site office area, where the mining activities are in operation. ii) Jr.Transit camp, Bina (KSN2) This location is selected to assess the ambient noise quality in the residential area. iii) Kohroul Village (KSN3) This location is selected to assess the ambient noise quality in the residential area. iv) Jawahar Nagar (KSN4) This location is selected to assess the ambient noise quality in the residential area which is at the southernmost point of the colony and this point is in the predominant wind direction NW & SE and the mining area (core zone) is in the NW to the site. Methodology of sampling and analysis Noise level measurements in form of 'LEQ' were taken using Integrated Averaging Sound Level Meter (CR: 812C) during day and night time. Noise levels were measured for about one hour time in day and night time. Noise levels were measured in Decibels, 'A' weighted average, i.e. dB (A).

Results & Interpretations Ambient noise levels were recorded during day and night time and the observed values were compared with standards prescribed by MoEF&CC.

The results of Noise levels recorded during day and night time on fortnightly basis are presented in tabular form along with the applicable standard permissible limits. The observed values in terms of LEQ are presented.

The observed values at all the monitoring locations are found to be within permissible limits.

Page 52: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-53

___________________________________________________________________

Table No.-3

NOISE LEVEL DATA

Name of the Company : Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month. : January. Name of the stations & Code :

1. KSN1 – Site Office 2. KSN2 - Jr.Tr. Camp, Bina

3. KSN3 - Kohroul Village 4. KSN4 - Jawahar Nagar

First Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of

Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

09.01.2017 Day 09.10 to 10.10 68.2 75

07.01.2017 Night 23.15 to 00.15 54.2 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

09.01.2017 Day 08.00 to 09.00 43.8 55

07.01.2017 Night 22.00 to 23.00 41.4 45

3 Koharoul

Village KSN3

Residential area

09.01.2017 Day 10.20 to 11.20 48.2 55

07.01.2017 Night 00.25 to 01.25 35.9 45

4 Jawahar

Nagar KSN4 Residential

area

09.01.2017 Day 11.40 to 12.40 48.7 55

07.01.2017 Night 01.35 to 02.35 43.8 45

Second Fortnight data

Sl

No.

Station

Name/Code

Category of

area

Measurement Details *Permissible Limit Of

Noise level in dB(A)

Date

Time +Day Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

31.01.2017 Day 09.20 to 10.20 65.8 75

23.01.2017 Night 23.10 to 00.10 54.2 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

31.01.2017 Day 08.05 to 09.05 52.7 55

23.01.2017 Night 22.00 to 23.00 41.4 45

3 Koharoul

Village KSN3

Residential area

31.01.2017 Day 10.30 to 11.30 43.2 55

23.01.2017 Night 00.15 to 01.15 35.8 45

4 Jawahar

Nagar KSN4 Residential

area

31.01.2017 Day 09.10 to 10.10 49.8 55

23.01.2017 Night 01.35 to 02.35 43.8 45

+ Day Time: 6.00 AM to 10.00 PM, +Night Time: 10.00 PM to 6.00 AM. *Permissible limits of Noise Level as per MOEF&CC Gazette Notification No. GSR 742(E) dt. 25.09.2000 Standards for Coal Mines and Noise Pollution (Regulation and Control) Rules, 2000.

Page 53: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-54

___________________________________________________________________

Table No.-3

NOISE LEVEL DATA

Name of the Company : Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month. : February. Name of the stations & Code :

1. KSN1 – Site Office 2. KSN2 - Jr.Tr. Camp, Bina

3. KSN3 - Koharoul Village 4. KSN4 - Jawahar Nagar

First Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of

Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

14.02.2017 Day 09.20 to 10.20 50.8 75

04.02.2017 Night 23.15 to 00.15 47.5 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

14.02.2017 Day 08.10 to 09.10 42.5 55

04.02.2017 Night 22.00 to 23.00 37.4 45

3 Koharoul

Village KSN3

Residential area

14.02.2017 Day 10.30 to 11.30 43.7 55

04.02.2017 Night 00.25 to 01.25 35.2 45

4 Jawahar

Nagar KSN4 Residential

area

14.02.2017 Day 11.20 to 12.20 44.2 55

04.02.2017 Night 01.35 to 02.35 35.3 45

Second Fortnight data

Sl

No.

Station

Name/Code

Category of

area

Measurement Details *Permissible Limit Of

Noise level in dB(A)

Date

Time +Day Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

28.02.2017 Day 09.25 to 10.25 54.8 75

20.02.2017 Night 23.15 to 00.15 46.5 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

28.02.2017 Day 08.10 to 09.10 43.2 55

20.02.2017 Night 22.00 to 23.00 35.7 45

3 Koharoul

Village KSN3

Residential area

28.02.2017 Day 10.40 to 11.40 40.6 55

20.02.2017 Night 00.30 to 01.30 35.1 45

4 Jawahar

Nagar KSN4 Residential

area

28.02.2017 Day 11.25 to 12.15 41.6 55

20.02.2017 Night 01.35 to 02.35 35.8 45

+ Day Time: 6.00 AM to 10.00 PM, +Night Time: 10.00 PM to 6.00 AM. *Permissible limits of Noise Level as per MOEF&CC Gazette Notification No. GSR 742(E) dt. 25.09.2000 Standards for Coal Mines and Noise Pollution (Regulation and Control) Rules, 2000.

Page 54: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-55

___________________________________________________________________

Table No.-3

NOISE LEVEL DATA

Name of the Company : Northern Coalfield Limited Year : 2016-17.

Name of the Project : Krishnashila Opencast Project Month. : March.

Name of the stations & Code :

1. KSN1 – Site Office 2. KSN2 - Jr.Tr. Camp, Bina

3. KSN3 - Koharoul Village 4. KSN4 - Jawahar Nagar

First Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office KSN1

Industrial area

15.03.2017 Day 09.30 to 10.30 50.6 75

04.03.2017 Night 23.15 to 00.15 47.5 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

15.03.2017 Day 08.10 to 09.10 40.2 55

04.03.2017 Night 22.00 to 23.00 36.2 45

3 Kohroul Village KSN3

Residential area

15.03.2017 Day 10.40 to 11.40 43.7 55

04.03.2017 Night 00.30 to 01.30 35.5 45

4 Jawahar Nagar KSN4

Residential area

15.03.2017 Day 11.15 to 12.15 38.8 55

04.03.2017 Night 01.25 to 02.25 36.3 45

Second Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office KSN1

Industrial area

29.03.2017 Day 09.20 to 10.20 61.2 75

20.03.2017 Night 00.20 to 01.20 46.3 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

29.03.2017 Day 08.10 to 09.10 48.5 55

20.03.2017 Night 23.15 to 00.15 40.2 45

3 Kohroul Village KSN3

Residential area

29.03.2017 Day 10.40 to 11.40 46.3 55

20.03.2017 Night 22.00 to 23.00 38.7 45

4 Jawahar Nagar KSN4

Residential area

29.03.2017 Day 11.15 to 12.15 46.2 55

20.03.2017 Night 22.10 to 23.10 36.8 45

+ Day Time: 6.00 AM to 10.00 PM, +Night Time: 10.00 PM to 6.00 AM. *Permissible limits of Noise Level as per MOEF&CC Gazette Notification No. GSR 742(E) dt. 25.09.2000 Standards for Coal Mines and Noise Pollution (Regulation and Control) Rules, 2000.

Page 55: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-56

___________________________________________________________________

Table No.-3 NOISE LEVEL DATA

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month. : April. Name of the stations & Code :

1. KSN1 – Site Office 2. KSN2 - Jr.Tr. Camp, Bina

3. KSN3 - Kohroul Village 4. KSN4 - Jawahar Nagar

First Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of

Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

01.04.2017 Day 09.10 to 10.10 52.7 75

06.04.2017 Night 23.15 to 00.15 49.2 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

01.04.2017 Day 08.00 to 09.00 38.5 55

06.04.2017 Night 22.00 to 23.00 37.5 45

3 Koharoul

Village KSN3

Residential area

01.04.2017 Day 10.20 to 11.20 35.6 55

06.04.2017 Night 00.25 to 01.25 34.6 45

4 Jawahar

Nagar KSN4 Residential

area

01.04.2017 Day 11.40 to 12.40 38.5 55

06.04.2017 Night 01.35 to 02.35 35.6 45

Second Fortnight data

Sl

No.

Station

Name/Code

Category of

area

Measurement Details *Permissible Limit Of

Noise level in dB(A)

Date

Time +Day Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

29.04.2017 Day 09.20 to 10.20 50.8 75

20.04.2017 Night 23.10 to 00.10 47.5 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

29.04.2017 Day 08.05 to 09.05 43.6 55

20.04.2017 Night 22.00 to 23.00 37.8 45

3 Koharoul

Village KSN3

Residential area

29.04.2017 Day 10.30 to 11.30 45.2 55

20.04.2017 Night 00.15 to 01.15 35.4 45

4 Jawahar

Nagar KSN4 Residential

area

29.04.2017 Day 09.10 to 10.10 40.7 55

20.04.2017 Night 01.35 to 02.35 35.2 45

+ Day Time: 6.00 AM to 10.00 PM, +Night Time: 10.00 PM to 6.00 AM. *Permissible limits of Noise Level as per MOEF&CC Gazette Notification No. GSR 742(E) dt. 25.09.2000 Standards for Coal Mines and Noise Pollution (Regulation and Control) Rules, 2000.

Page 56: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-57

___________________________________________________________________

Table No.-3

NOISE LEVEL DATA

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month. : May. Name of the stations & Code :

1. KSN1 – Site Office 2. KSN2 - Jr.Tr. Camp, Bina

3. KSN3 - Koharoul Village 4. KSN4 - Jawahar Nagar

First Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of

Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

15.05.2017 Day 09.20 to 10.20 57.5 75

05.05.2017 Night 23.15 to 00.15 48.6 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

15.05.2017 Day 08.10 to 09.10 40.3 55

05.05.2017 Night 22.00 to 23.00 37.3 45

3 Koharoul

Village KSN3

Residential area

15.05.2017 Day 10.30 to 11.30 42.6 55

05.05.2017 Night 00.25 to 01.25 35.9 45

4 Jawahar

Nagar KSN4 Residential

area

15.05.2017 Day 11.20 to 12.20 43.5 55

05.05.2017 Night 01.35 to 02.35 35.6 45

Second Fortnight data

Sl

No.

Station

Name/Code

Category of

area

Measurement Details *Permissible Limit Of

Noise level in dB(A)

Date

Time +Day Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office

KSN1 Industrial

area

30.05.2017 Day 09.25 to 10.25 50.5 75

19.05.2017 Night 23.15 to 00.15 47.2 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

30.05.2017 Day 08.10 to 09.10 40.3 55

19.05.2017 Night 22.00 to 23.00 36.4 45

3 Koharoul

Village KSN3

Residential area

30.05.2017 Day 10.40 to 11.40 43.7 55

19.05.2017 Night 00.30 to 01.30 35.6 45

4 Jawahar

Nagar KSN4 Residential

area

30.05.2017 Day 11.25 to 12.15 39.4 55

19.05.2017 Night 01.35 to 02.35 36.3 45

+ Day Time: 6.00 AM to 10.00 PM, +Night Time: 10.00 PM to 6.00 AM. *Permissible limits of Noise Level as per MOEF&CC Gazette Notification No. GSR 742(E) dt. 25.09.2000 Standards for Coal Mines and Noise Pollution (Regulation and Control) Rules, 2000.

Page 57: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-58

___________________________________________________________________

Table No.-3

NOISE LEVEL DATA

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Month. : June.

Name of the stations & Code :

1. KSN1 – Site Office 2. KSN2 - Jr.Tr. Camp, Bina

3. KSN3 - Koharoul Village 4. KSN4 - Jawahar Nagar

First Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office KSN1

Industrial area

15.06.2017 Day 09.30 to 10.30 53.2 75

05.06.2017 Night 23.15 to 00.15 46.5 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

15.06.2017 Day 08.10 to 09.10 43.5 55

05.06.2017 Night 22.00 to 23.00 36.2 45

3 Kohroul Village KSN3

Residential area

15.06.2017 Day 10.40 to 11.40 44.2 55

05.06.2017 Night 00.30 to 01.30 35.0 45

4 Jawahar Nagar KSN4

Residential area

15.06.2017 Day 11.15 to 12.15 41.4 55

05.06.2017 Night 01.25 to 02.25 35.2 45

Second Fortnight data

Sl. No.

Station

Name/ Code

Category of

area

Measurement details *Permissible Limit of Noise level in dB(A)

Date

Time +Day/ Night

Duration (In Hrs.)

Noise level dB(A) LEQ

1 Site Office KSN1

Industrial area

30.06.2017 Day 09.20 to 10.20 50.7 75

20.06.2017 Night 00.20 to 01.20 45.2 70

2 Jr.Tr. Camp, Bina KSN2

Residential area

30.06.2017 Day 08.10 to 09.10 40.5 55

20.06.2017 Night 23.15 to 00.15 36.8 45

3 Kohroul Village KSN3

Residential area

30.06.2017 Day 10.40 to 11.40 38.6 55

20.06.2017 Night 22.00 to 23.00 35.4 45

4 Jawahar Nagar KSN4

Residential area

30.06.2017 Day 11.15 to 12.15 40.5 55

20.06.2017 Night 22.10 to 23.10 35.2 45

+ Day Time: 6.00 AM to 10.00 PM, +Night Time: 10.00 PM to 6.00 AM. *Permissible limits of Noise Level as per MOEF&CC Gazette Notification No. GSR 742(E) dt. 25.09.2000 Standards for Coal Mines and Noise Pollution (Regulation and Control) Rules, 2000.

Page 58: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-59

___________________________________________________________________

Table No.-4 GROUNDWATER LEVEL MONITORING DATA

Dug Well Inventory - KRISHNASHILA PROJECT

S.No. Well No. Village Owner

M.P. T.D. Dia. R.L.

Geology Use (m.agl) (m.bgl) (m) of M.P.

1 N-21 CMPDI Colony CMPDI,RI-VI 0.80 6.37 2.27 305.2 Barakar sst Domestic

2 J-1 Pipralal S.P.Tiwari 0.33 9.03 1.64 293.35 Talchir Domestic

3 J-2 Jaitpur Ram Kumar Sahu 0.20 5.56 1.50 292.02 Barakar sst Domestic

4 J-3 Sarswa Raja Nand Lal Kushwaha 0.78 10.05 1.23 294.33 Barakar sst Domestic

5 J-14A* Merhauli Dewan Waisya G.L 12.69 4.11 384.00 Barakar sst Domestic

6 J-15A* Motwani Dam Deepak kumar G.L 9.18 3.33 303.86 Barakar sst Domestic

7 KD-2 Kota Basti NPCC 0.73 6.78 2.75 275.00 Talchir Domestic

8 KD-5 Bhairwan Krishna Kanti Pandey

0.30 13.00 1.37 273.06 Barakar sst Domestic

9 KD-6A* Khadia DAV NCL 0.47 8.90 2.47 NA Barakar sst Domestic

10 KD-7 Khadia Sitaram Sahu 0.57 6.14 1.50 273.30 Barakar sst Domestic

11 KD-8 Chilka Dand Kanti Chaube G.L 12.60 1.45 284.55 Barakar sst Domestic

12 KD-10 Chilka Dand NTPC 0.62 6.65 2.57 290.97 Barakar sst Domestic

13 B-1 Mishra

Ramidshan Kushwah

0.47 9.72 2.97 272.66 Talchirs Domestic

14 B-2 Kohraul Lalit Singh 0.93 10.75 2.26 272.97 Talchirs Domestic

15 B-3 Chandauri Shyam Sunder 0.35 11.82 1.93 278.97 Talchirs Domestic

16 B-4A Gharsari NCL 1.03 13.52 2.98 NA Talchirs Domestic

17 B-5 Basi Kaustryalya Yadav 0.47 10.30 2.98 271.13 Talchirs Domestic

18 B-6 Jawaharnagar srithari Charan 0.51 8.00 1.20 277.27 Talchirs Domestic

19 K-1 Audi Mode Abdul Kayyum Khan 0.58 14.83 1.14 295.11 Archaeans Domestic

20 K-3 Parasi C.Kumar Gupts 0.33 13.25 2.20 281.52 Talchir Domestic

21 K-4 Kakri Manjit Yadav 0.20 10.52 1.98 272.95 Talchir Domestic

22 K-5 Kakri GM Office

Gulab Chand Chamar

0.74 13.75 1.28 276.32 Talchir Domestic

23 JH-4 Kanhana Public Well 0.98 6.80 2.00 367.22 Archaeans Domestic

24 JH-9 Chandrapur NCL 0.29 9.76 2.99 357.66 Barakar sst Domestic

25 JH-11 Morwa CETI Surendra Pd.Dwedi 0.31 14.33 1.30 378.79 Barakar sst Domestic

26 JH-13 Bhuse Mode public well 1.36 10.21 2.30 364.63 Barakar sst Domestic

27 JH-15

Jhingurdah Mode

Jagannath 0.63 7.55 2.78 356.74 Barakar sst Domestic

28 JH-18 Khanhana Tola Maheshwari Prasad 0.26 9.26 2.20 365.53 Archaeans Domestic

29 D-4 Mirchaghar Sabhapati GL 13.75 2.00 383.37 Barakar sst Domestic

M.P. = Measuring Point Dia. = Diameter agl = Above Ground Level

T.D. = Total Depth R.L. = Reduced Level Above MSL bgl = Below Ground Level NA=Not Available *Note: New dugwells included for monitoring.

Page 59: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-60

___________________________________________________________________

Table No.-4 GROUNDWATER LEVEL MONITORING DATA

Dugwells Water Level Details - KRISHNASHILA PROJECT

S. No.

Well No.

Water Level in m.bgl

Winter Pre-monsoon

Monsoon Post-monsoon Winter

Pre-monsoon

Monsoon Post-monsoon Winter

Pre-monsoon

Jan'15 May'15 Aug'15 Nov'15 Jan'16 May'16 Aug'16 Nov'16 Feb'17 May'17

1 N-21 1.37 3.34 1.54 1.76 1.91 3.41 1.36 0.96 2.41 3.36

2 J-1 4.92 6.48 5.92 5.07 5.52 6.87 1.07 1.47 2.12 5.82

3 J-2 3.32 4.97 3.19 2.90 3.40 4.90 3.70 3.90 4.60 4.50

4 J-3 4.18 6.43 4.65 4.12 4.47 5.57 4.07 3.32 4.97 5.12

5 J-14A 6.77 8.18 NA NA NA 5.65 3.40 4.30 4.70 5.15

6 J-15 2.66 4.16 2.43 2.55 3.10 4.10 2.25 2.80 3.05 2.70

7 KD-2 1.52 2.71 1.07 2.07 1.57 2.17 0.62 0.67 1.75 1.27

8 KD-5 3.46 4.90 NA NA 3.50 3.05 0.80 2.30 2.90 3.45

9 KD-6A 2.75 4.12 3.78 2.48 2.63 2.68 0.98 NA 2.43 2.88

10 KD-7 0.82 2.38 NA NA 1.33 1.48 0.23 0.63 1.33 1.18

11 KD-8 4.17 5.65 4.34 4.65 4.90 5.00 3.10 4.10 4.20 4.50

12 KD-10 2.67 4.11 3.48 3.03 2.98 3.63 2.18 2.38 2.88 3.38

13 B-1 3.53 5.02 NA 3.23 3.28 3.53 1.28 2.33 2.83 3.18

14 B-2 3.97 7.95 NA 7.17 7.92 8.92 3.82 2.67 5.87 5.52

15 B-3 8.21 5.82 8.35 8.95 9.35 9.95 8.15 8.75 9.20 8.50

16 B-4A 7.38 9.07 8.77 8.27 8.69 9.27 6.97 5.97 6.72 7.97

17 B-5 5.83 7.34 6.30 6.18 6.13 6.48 5.18 4.43 4.83 6.13

18 B-6 4.44 5.91 4.34 4.49 4.64 5.49 3.74 4.14 4.74 5.14

19 K-1 11.52 13.48 12.04 12.22 12.82 13.87 10.22 8.12 9.72 12.27

20 K-3 11.62 11.48 11.32 12.27 12.87 NA 9.37 9.62 9.92 12.92

21 K-4 8.02 9.43 7.05 8.05 8.30 8 6.30 4.6 6.5 8.3

22 K-5 11.32 13.04 11.36 11.01 10.96 11.56 10.51 9.06 10.21 11.21

23 JH-4 3.53 5.78 3.19 2.97 3.67 5.32 1.22 1.82 2.62 3.52

24 JH-9 3.69 5.31 3.46 3.81 5.46 6.96 1.41 1.81 3.01 5.11

25 JH-11 11.86 13.67 13.18 13.79 13.54 NA 12.24 8.29 9.79 9.79

26 JH-13 6.76 7.32 6.48 5.84 8.14 7.79 2.44 3.54 4.29 6.74

27 JH-15 4.27 6.11 2.45 4.27 5.17 6.72 0.72 1.17 2.62 4.02

28 JH-18 6.10 8.88 7.54 5.39 7.09 9.04 1.44 3.04 3.54 4.89

29 D-4 9.66 10.92 9.55 10.30 10.60 11.00 7.90 6.80 8.30 10.20

NA= NOT AVAILABLE , bgl= below ground level

Page 60: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-61

___________________________________________________________________

Table No.-4

GROUNDWATER LEVEL MONITORING DATA

A. Piezometer Inventory - BINA / KRISHNASHILA PROJECT

B. Water level data of Piezometers in m. bgl - BINA / KRISHNASHILA PROJECT

S.No. Piezometer

No.

Pre-

monsoon Monsoon

Post -

monsoon Winter

Pre-

Monsoon

May'16 Aug'16 Nov'16 Feb'17 May'17

1 PDB-1 21.1 20.80 20.85 21.2 5.6

2 PDB-2 NA 63.50 64.3 63.8 9.25

3 PDB-3 50.5 50.60 50.45 51.25 8.5

4 PSB-1 7.45 4.55 3.9 4.8 20.9

5 PSB-2 10.6 9.2 7.8 8.7 63.5

6 PSB-3 6.4 7.6 9.4 7.7 52.65

M.P. = Measuring Point Dia. = Diameter agl = Above Ground Level

T.D. = Total Depth R.L. = Reduced Level Above MSL bgl = Below Ground Level

NA= Not Available.

S.

No.

Piezometer

No.

Latitude ,

Longitude

Nearby

Landmark/Owner

M.P. T.D. Dia. Type of Geology

(m.agl) (m.bgl) (mm) Piezometer

1 PDB-1 24.16861111,

82.73111111

Bina Mine near kakri

border,Bina/NCL 0.4 90 150 Deep Barakar sst

2 PDB-2 24.16305556,

82.72666667

Opposite to GSCO

outsoursing

Camp,Bina/NCL

0.4 168 100 Deep Barakar sst

3 PDB-3 24.15861111,

82.7275

Bina Mine near KSL

Border,Bina/NCL 0.5 78 150 Deep Barakar sst

4 PSB-1 24.16027778,

82.76972222

Inside Bina Forest

Nursery,Bina/NCL 0.6 60 125 Shallow Barakar sst

5 PSB-2 24.14833333,

82.76055556

Near E/M

Office,Bina/NCL 0.5 60 125 Shallow Barakar sst

6 PSB-3 24.14888889,

82.76527778

Near Excavation

Store,Bina/NCL 0.5 57 125 Shallow Barakar sst

Page 61: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-62

___________________________________________________________________

Table No.-5

GROUNDWATER LEVEL MONITORING DATA

WATER QUALITY DATA

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E. : June’17

Name of the Stations & Code :

1. Mishra, Rmidshan Kushwah KS-1 (B – 1)

2. Kohoral, Lalit Singh KS-2 (B – 2)

Sl. No.

Parameters 1 2 Tolerance Limit

(As per IS-10500/2012 for Drinking water Standard)

Date of Sampling 08.05.2017 08.05.2017

Requirement ( Acceptable

Limit)

Permissible Limit in the absence of Alternate Source

1 Colour , Hazen Unit. 2 1 5 15

2 Odour Agreeable Agreeable Agreeable Agreeable

3 Taste Agreeable Agreeable Agreeable Agreeable

4 Turbidity, NTU 0 0 1 5

5 pH Value 8.41 8.2 6.5 – 8.5 No relaxation

6 Total Hardness 144 464 200 600

7 Iron BDL(0.01) BDL(0.01) 0.3 No relaxation

8 Chlorides 14 292 250 1000

9 Dissolved Solids 154 655 500 2000

10 Calcium 48 67 75 200

11 Sulphate 25 92 200 400

12 Nitrate 0.8 0.5 45 No relaxation

13 Flouride 0 0 1.0 1.5

14 Phenolics BDL(<0.001) BDL(<0.001) 0.001 0.002

15 Alkalinity 140 328 200 600

16 Hexavalent Chromium BDL(0.01) BDL(0.01) 0.05 No relaxation

17 Boron BDL(0.01) BDL(0.01) 0.5 1.0

18 Copper BDL(<0.02) BDL(<0.02) 0.05 1.5

19 Manganese BDL(0.005) BDL(0.005) 0.1 0.3

20 Arsenic BDL(0.01) BDL(0.01) 0.01 0.05

21 Selenium BDL(0.01) BDL(0.01) 0.01 No relaxation

22 Lead BDL(0.01) BDL(0.01) 0.01 No relaxation

23 Zinc 0.0576 0.0567 5 15

24 MPN NILL NILL NIL No relaxation

25 Mercury BDL(<0.001) BDL(<0.001) 0.001 No relaxation

All values are expressed in mg/lit unless specified (Except pH)

Page 62: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-63

___________________________________________________________________

Table No.-5

GROUNDWATER LEVEL MONITORING DATA

WATER QUALITY DATA

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Krishnashila Opencast Project Q.E. : June’17

Name of the Stations & Code :

3. Bhairwn, Krishna Kant Pandey KS-4 (KD-5)

4. Khadia, Sitaram Sahu KS-5 (KD-7)

Sl. No.

Parameters 3 4

Tolerance Limit

(As per IS-10500/2012 for Drinking water Standard)

Date of Sampling 08.05.2017 08.05.2017

Requirement ( Acceptable

Limit)

Permissible Limit in the absence of Alternate

Source

1 Colour , Hazen Unit. 2 1 5 15

2 Odour Agreeable Agreeable Agreeable Agreeable

3 Taste Agreeable Agreeable Agreeable Agreeable

4 Turbidity, NTU 0 0 1 5

5 pH Value 8.3 7.95 6.5 – 8.5 No relaxation

6 Total Hardness 264 248 200 600

7 Iron BDL(0.01) BDL(0.01) 0.3 No relaxation

8 Chlorides 86 64 250 1000

9 Dissolved Solids 528 357 500 2000

10 Calcium 30 58 75 200

11 Sulphate 116 86 200 400

12 Nitrate 4.2 2.9 45 No relaxation

13 Flouride 0.5 0 1.0 1.5

14 Phenolics BDL(<0.001) BDL(<0.001) 0.001 0.002

15 Alkalinity 420 280 200 600

16 Hexavalent Chromium BDL(0.01) BDL(0.01) 0.05 No relaxation

17 Boron BDL(0.01) BDL(0.01) 0.5 1.0

18 Copper BDL(<0.02) BDL(<0.02) 0.05 1.5

19 Manganese BDL(0.005) BDL(0.005) 0.1 0.3

20 Arsenic BDL(0.01) BDL(0.01) 0.01 0.05

21 Selenium BDL(0.01) BDL(0.01) 0.01 No relaxation

22 Lead BDL(0.01) BDL(0.01) 0.01 No relaxation

23 Zinc 0.0665 0.0718 5 15

24 MPN NILL NILL NIL No relaxation

25 Mercury BDL(<0.001) BDL(<0.001) 0.001 No relaxation

All values are expressed in mg/lit unless specified (Except pH)

Page 63: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-64

___________________________________________________________________

Table No.-5

WATER QUALITY DATA (FOR PEIZOMETER GROUND WATER MONITORING)

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Bina / Krishnashila Opencast Project Q.E. : June’17 PSB-2 - Near E/M Office,Bina/NCL PSB-3- Near Excavation Store,Bina/NCL PDB- Bina Mine near kakri border,Bina/NCL

Sl. No.

Parameters PSB-2 PSB-3 PDB-1

Tolerance Limit (As per IS-10500/2012

for Drinking water Standard)

Date of Sampling

24.05.2017 24.05.2017 24.05.2017

Requirement ( Acceptable

Limit)

Permissible Limit in the absence of Alternate Source

1 Colour , Hazen Unit. 5 6 3 5 15

2 Odour Agreeable Agreeable Agreeable Agreeable Agreeable

3 Taste Agreeable Agreeable Agreeable Agreeable Agreeable

4 Turbidity, NTU 0 4 3 1 5

5 pH Value 8.04 7.19 6.22 6.5 – 8.5 No relaxation

6 Total Hardness 80 424 84 200 600

7 Iron BDL(0.01) BDL(0.01) BDL(0.01) 0.3 No relaxation

8 Chlorides 14 32 14 250 1000

9 Dissolved Solids 161 368 48 500 2000

10 Calcium 29 95 12 75 200

11 Sulphate < 5 0 0 200 400

12 Nitrate 2.5 1.1 2.5 45 No relaxation

13 Flouride 0 0 0 1.0 1.5

14 Phenolics BDL(<0.001) BDL(<0.001) BDL(<0.001) 0.001 0.002

15 Alkalinity 124 208 36 200 600

16 Hexavalent Chromium BDL(0.01) BDL(0.01) BDL(0.01)

0.05 No relaxation

17 Boron BDL(0.01) BDL(0.01) BDL(0.01) 0.5 1.0

18 Copper BDL(<0.02) BDL(<0.02) BDL(<0.02) 0.05 1.5

19 Manganese BDL(0.005) BDL(0.005) BDL(0.005) 0.1 0.3

20 Arsenic BDL(0.01) BDL(0.01) BDL(0.01) 0.01 0.05

21 Selenium BDL(0.01) BDL(0.01) BDL(0.01) 0.01 No relaxation

22 Lead BDL(0.01) BDL(0.01) BDL(0.01) 0.01 No relaxation

23 Zinc 0.01 BDL(0.02) BDL(0.02) 5 15

24 MPN NILL NILL NILL NIL No relaxation

25 Mercury BDL(<0.001) BDL(<0.001) BDL(<0.001) 0.001 No relaxation

All values are expressed in mg/lit unless specified (Except pH)

Page 64: Summarised Environmental Impact Assessment (EIA ... · Total 99.12 99.12 1.5 Identification of project & project proponent The project under consideration, i.e. Krishnashila OCP is

CMPDI Annexure No-I _________________________________________________________________

Summarised EIA-EMP of Krishnashila OCP A-65

___________________________________________________________________

Table No.-5

WATER QUALITY DATA (FOR PEIZOMETER GROUND WATER MONITORING)

Name of the Company : Northern Coalfield Limited Year : 2017-18.

Name of the Project : Bina / Krishnashila Opencast Project Q.E. : June’17 PDB-2- Opposite to GSCO outsoursing Camp,Bina PDB-3- Bina Mine near KSL Border,

Sl. No.

Parameters PDB-2 PDB-3 Tolerance Limit

(As per IS-10500/2012 for Drinking water Standard)

Date of Sampling

24.05.2017 24.05.2017 Requirement

( Acceptable Limit)

Permissible Limit in the absence of

Alternate Source

1 Colour , Hazen Unit. 36 3 5 15

2 Odour Agreeable Agreeable Agreeable Agreeable

3 Taste Agreeable Agreeable Agreeable Agreeable

4 Turbidity, NTU 17 3 1 5

5 pH Value 7.24 6.08 6.5 – 8.5 No relaxation

6 Total Hardness 116 60 200 600

7 Iron BDL(0.01) BDL(0.01) 0.3 No relaxation

8 Chlorides 12 16 250 1000

9 Dissolved Solids 97 33 500 2000

10 Calcium 26 20 75 200

11 Sulphate 35 0 200 400

12 Nitrate 4.7 1 45 No relaxation

13 Flouride 0 0 1.0 1.5

14 Phenolics BDL(<0.001) BDL(<0.001) 0.001 0.002

15 Alkalinity 100 32 200 600

16 Hexavalent Chromium BDL(0.01) BDL(0.01)

0.05 No relaxation

17 Boron BDL(0.01) BDL(0.01) 0.5 1.0

18 Copper BDL(<0.02) BDL(<0.02) 0.05 1.5

19 Manganese BDL(0.005) BDL(0.005) 0.1 0.3

20 Arsenic BDL(0.01) BDL(0.01) 0.01 0.05

21 Selenium BDL(0.01) BDL(0.01) 0.01 No relaxation

22 Lead BDL(0.01) BDL(0.01) 0.01 No relaxation

23 Zinc BDL(0.02) BDL(0.02) 5 15

24 MPN NILL NILL NIL No relaxation

25 Mercury BDL(<0.001) BDL(<0.001) 0.001 No relaxation

All values are expressed in mg/lit unless specified (Except pH)