JOB PROCEDURE FOR SURVEYING WORK PROJECT:- “GOLDEN PANORAMA” RESIDENSIAL LUXURY APARTMENTS PROJECT NAME : “GOLDEN PANORAMA” RESIDENTIAL LUXURY APARTMENTS. BANGALORE CLIENT : GOLDEN GATE PROPERTIES LIMITED. BENGALURU. CONSULTENT : FBA CONSULTING PMC. DOCUMENT NO : FBA/GGP/JP/00. Procedure No: FBA/GGP/JP/001 ISSUED FOR APPROVAL& IMPLEMENTATION REV 0 DATE DESCRIPTION PREP B! FBA C"D B! FBA APPROVED B! FBA REVIE#ED & APPROVED B! GGPL P$%e o' ( PROCEDURE FOR SURVEYING WORKS

Survey Job Procedure

Embed Size (px)

DESCRIPTION

PROCEDURE

Citation preview

JOB PROCEDURE FOR

SURVEYING WORK

PROJECT:- GOLDEN PANORAMA RESIDENSIAL LUXURY APARTMENTS

PROJECT NAME: GOLDEN PANORAMA RESIDENTIAL

LUXURY APARTMENTS. BANGALORECLIENT: GOLDEN GATE PROPERTIES LIMITED.

BENGALURU.

CONSULTENT: FBA CONSULTING PMC.DOCUMENT NO: FBA/GGP/JP/001.Procedure No: FBA/GGP/JP/001ISSUED FOR APPROVAL& IMPLEMENTATION

REV 0DATE DESCRIPTIONPREP.

BY

FBACHD.

BY

FBAAPPROVED

BY

FBAREVIEWED & APPROVED

BY GGPL

CONTENTS:

1.PURPOSE

2.SCOPE

3. REFERENCES & CONTROLLING

SPECIFICATIONS4.METHODOLOGY5. PREPARATION OF FIELD SURVEY LAYOUT

5. HEALTH, SAFETY AND ENVIRONMENT

FBAGOLDEN GATE

6.0 PURPOSE

The purpose of this procedure is to prepare a sequential system & control on the Survey activities to achieve the desired product to the satisfaction of client/consultant.

6.0 SCOPE

This procedure is applicable for the survey work for all kind of land survey required to establish Temporary Bench Marks(TBM), Levels and to fix -up Coordinates of battery limit, Centre line markings for all Towers in Golden PANORAMA site.

In brief it controls the following activities.

1Site clearance.

2Fixing of permanent and Temporary Bench marks.

3Fixing of reference points / Grid pillars.4Layout and survey.

In case of conflict between this procedure and the contracts specification, the contract specification shall govern.

6.0 REFERENCES & CONTROLLING SPECIFICATIONS

1. Applicable Technical Amendments.

2. AFC Drawings.

FBAGOLDEN GATE

4.0 METHODOLOGY4.1 Equipments

Measuring steel tapes, Electronic Total Station, Auto Level, Leveling staff, plumb bob, line threads, lime powder for marking, wooden pegs, nails, paints, and other helping aids. All measuring and survey instruments shall have valid calibration certificate. Project approved drawings and specifications will be the basis of acceptance criteria

4.2Acceptance Criteria

The sequential activities and corresponding methods are detailed below:

4.3 Site clearance

Shrubs, bushes etc, shall be cleared off from site location. Cleaning, grubbing etc. shall be completed before starting of site layout, Necessary profiles with pegs, bamboos, buries shall be made to show the formation levels before survey work starts, if required.

4.4 Bench Mark

Permanent bench mark at site shall be established at battery limit or at the suitable location with reference to the standard local benchmark approved by client/ consultant. For all construction activities, the same bench mark shall be used and this permanent Bench mark shall be made of concrete pillars of sufficient depth & size as per site requirement. It will be fixed with punched mark nail to be executed and cross direction to be marked with respective coordinates & RL.

FBAGOLDEN GATE

4.5 Reference Points

Reference Points in and around sites with respect to permanent benchmark shall be marked and these points shall be made of masonry pillars or wooden pegs with a nail on top. All reference points shall be checked and guarded against any disturbances. All the survey pillars shall be marked with reference level, coordinates and these shall be offered for PMC inspection.

4.6 Layout and Survey works

The Layout shall be done in accordance with approved drawings and shall be offered for PMC inspection and records of this layout inspection shall be submitted to PMC.Detailed layout of survey work for the location of individual structures shall be done with respect to North direction.Checking of survey work and confirmation of location and orientation of structures shall be done with respect to the whole project layout plan.All the marking / grid lines / levels, etc shall be transferred to permanent structures after completion of jobs. All utilities, under ground and above ground shall be identified and recorded on Survey inspection report-Format. 5 PREPARATION OF FIELD SURVEY LAYOUTS

Prepare the surveying layouts for all Towers in Golden PANORAMA Site in the given format and submit to concern PMC Engineer and get his Review and Approval sign.

FBAGOLDEN GATE

6.0 HEALTH, SAFETY AND ENVIRONMENTFollowing measures but not limited to here under shall be taken for the execution of Survey Works. Risk Assessment of all activities associated with this procedure shall be done before starting any activity.

Entire working area shall be within the boundary limit. Only authorized equipment/ personnel will be allowed within the working area.

All utilities shall be identified and protected.

All lifting tools and tackles shall be periodically inspected against any

Damage.

All instruments / equipments shall be maintained in good working condition as per maintenance schedule.

All workmen supervisors and engineers shall use proper personnel

Protection gears.

All employees shall follow the employee Health , Safety & Environment rules.