    Software Verification and Validation Plan (SVVP) Template

    Items that are intended to stay in as part of your document are in bold;

    explanatory comments are in italic text. Plain text is used where you

    might insert wording about your project.

    This document is an annotated outline for a Software Verification and

    Validation Plan, adapted from the IEEE Standard for Software

    Verification and Validation Plans (Standard 1012), and the IEEE Guide

    for Software Verification and Validation Plans (Guide 1059).

    Tailor as appropriate. Where you decide to omit a section, you might

    keep the header, but insert a comment saying why you omit the

    element (e.g., This section is not applicable to the plan.)

  • 8/2/2019 SVVPLAN

    2/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 2 01/17/01

    (Agency)

    (Project)

    Software Verification and Validation Plan

    Version: (n) Date: (mm/dd/yyyy)

  • 8/2/2019 SVVPLAN

    3/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 1 01/17/01

    TABLE OF CONTENTS

    1. PURPOSE 3

    2. REFERENCED DOCUMENTS 4

    3. DEFINITIONS 5

    4. VERIFICATION AND VALIDATION OVERVIEW 5

    4.1 Organization 5

    4.2 Master Schedule 6

    4.3 Resource Summary 6

    4.4 Responsibilities 7

    4.5 Tools, Techniques, and Methodologies 7

    5. LIFECYCLE VERIFICATION AND VALIDATION 7

    5.1 Management of V&V 7

    5.2 Concept Phase 8

    5.3 Requirements Phase 9

    5.4 Design Phase 9

    5.5 Implementation Phase 10

    5.6 Test Phase 11

    5.7 Installation and Checkout Phase 11

    5.8 Operation and Maintenance Phase 12

    6. Reporting 12

  • 8/2/2019 SVVPLAN

    4/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 2 01/17/01

    TABLE OF CONTENTS (CONTINUED)

    7. Administrative Procedures 13

    7.1 Anomaly Reporting and Resolution 13

    7.2 Task Iteration Policy 13

    7.3 Deviation Policy 13

    7.4 Control Procedures 14

    7.5 Standards, Practices, and Conventions 14

    8. Plan Approvals 14

  • 8/2/2019 SVVPLAN

    5/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 3 01/17/01

    1. PURPOSE

    (NOTE 1: THE SOFTWARE VERIFICATION AND VALIDATION PLAN GUIDELINES WERE

    DERIVED AND DEVELOPED FROM IEEE STANDARD FOR SOFTWARE VERIFICATION ANDVALIDATION (STANDARD 1012) AND THE IEEE GUIDE FOR SOFTWARE VERIFICATION ANDVALIDATION PLANS (GUIDE 1059)).

    (Note 2: The ordering of Software Verification and Validation Plan (SVVP) elements

    is not meant to imply that the sections or subsections must be developed or

    presented in that order. The order of presentation is intended for ease of use, not as a

    guide to preparing the various elements of the Software Verification and Validation

    Plan. If some or all of the content of a section is in another document, then a

    reference to that material may be listed in place of the corresponding content.)

    (The Purpose section of the Software Verification and Validation Plan defines the purpose,

    scope, and goals of the plan. The software project must be identified and the specific

    software product items, covered by the plan, must be identified. The specific goals of the

    verification and validation effort must be specified.

    The SVVP purpose section provides the highest level description of verification and

    validation efforts. The following topics must be addressed:

    Project identification, Plan goals,

    Summary of verification and validation efforts,

    Responsibilities conveyed with the plan,

    Software to be verified and validated,

    Identification of waivers and changes to organization standards, and

    SVVP assumptions.)

    Software verification and validation (V&V) is a disciplined approach to assessing software

    products throughout the software development life cycle. Verification and validation strives toensure that quality is built into the software and that the software satisfies business functional

    requirements.

    Software verification and validation employs review, analysis, and testing techniques to

    determine whether a software product and its intermediate deliverables comply with

    requirements. These requirements include both business functional capabilities and quality

    attributes.

  • 8/2/2019 SVVPLAN

    6/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 4 01/17/01

    The objectives of the V&V effort are to find defects and to determine if required functions and

    attributes are built into the software system. V&V activities are designed to support:1. Verification that the products of each software life cycle phase:

    - Comply with previous life cycle phase requirements and products for

    correctness, completeness, consistency, and accuracy,

    - Satisfy the standards, policies, practices, procedures, and conventions of the

    phase, and

    - Establish the proper basis for initiating the next life cycle phase.

    2. Validate that the completed end product complies with established software and

    system requirements.

    Verification and validation provide management with insights into the state of the project and

    the software products, allowing for timely change in the products or in the software

    development life cycle approach.

    (Verification and validation effort is typically applied in parallel with software development and

    support activities. Verification and validation planning may be broken down into the following

    steps:

    - Identify the V&V scope,

    - Establish specific objectives from the general project scope,

    - Analyze the project input prior to selecting V&V tools and techniques,

    - Select tools and techniques, and

    - Develop the Software Verification and Validation Plan (SVVP)).

    2. REFERENCE DOCUMENTS

    (This section shall identify the binding compliance documents, documents referenced in the

    plan, and any supporting documents required to implement, or supplement, the SVVP.

    Ensure that the reference document list is consistent with other project documentation.

    Ensure that all documents listed in the plan are referenced. Specify documents completely

  • 8/2/2019 SVVPLAN

    7/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 5 01/17/01

    including the version and date reference.)

  • 8/2/2019 SVVPLAN

    8/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 6 01/17/01

    3. Definitions

    (The definition section provides a reference to the definition of all terms required to properlyinterpret the SVVP. This section also notes acronyms and notations used in the plan. Include

    only terms necessary for understanding the SVVP. Refer to other project documentation for a

    comprehensive list of project definitions (e.g., Software Project Management Plan, Software

    Quality Assurance Plan). For SVVP purposes, the following definitions apply:)

    SVVP Software Verification and Validation Plan.

    Validation The process of evaluating software at the end of the software development

    process to ensure compliance to software requirements.

    Verification The process of determining whether or not products of a given phase of the

    software development process fulfill the requirements established during the previous phase.

    V&V Verification and validation.

    4. VERIFICATION AND VALIDATION OVERVIEW

    (Describe the organization, schedule, resources, responsibilities, tools, techniques, and

    methodologies to be deployed in order to perform the verification and validation activities.)

    4.1 Organization

    (Define the relationship of verification and validation to other efforts such as

    development, project management, quality assurance, and configuration

    management. Define the lines of communication within the verification and

    validation effort, the authority for resolving issues, and the authority for

    approving verification and validation deliverables.)

  • 8/2/2019 SVVPLAN

    9/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 7 01/17/01

    (The specific organization structure of the V&V effort will depend on the nature

    of the system under development, the developing organizations, and any

    contractual arrangements.)

    4.2 Master Schedule

    (The master schedule summarizes the various verification and validation tasks

    and their relationship to the overall project.)

    (Describe the project life cycle and project milestones including completion dates.

    Summarize the schedule of verification and validation tasks and how verification

    and validation results provide feedback to the development process to support

    overall project management functions.)

    (The objective of this section is to define an orderly flow of material between

    project activities and verification and validation tasks. Use reference to PERT,

    CPM, and Gantt Charts to define the relationship of activities.)

    (If the life cycle used in the SVVP differs from the life cycle model defined in IEEE

    Standard 1012, this section must show how all requirements of the Standard will

    be satisfied. The summary of tasks may be in narrative, tabular, or graphic form.)

    4.3 Resource Summary

    (This section summarizes the resources needed to perform verification and

    validation tasks, including staffing, facilities, tools, finances, and special

    procedural requirements such as security, access rights, and documentation

    control. In this section:

    Use graphs and tables to present resource utilization,

    Include equipment and laboratory resources required,

    Summarize the purpose and cost of hardware and software tools to be

    employed, and

    Take all resources into account and allow for additional time and money to

    cope with contingencies.)

  • 8/2/2019 SVVPLAN

    10/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 8 01/17/01

    4.4 Responsibilities

    (Identify the organization responsible for performing verification and validation

    tasks. There are two levels of responsibility general responsibilities assigned to

    different organizations and specific responsibilities for the V&V tasks to be

    performed should be assigned to individuals. General responsibilities should be

    supplemented with specific responsibility for each task in the verification and

    validation plan.)

    4.5 Tools, Techniques, and Methodology

    (Identify the special software tools, techniques, and methodologies to be employed

    by the verification and validation team. The purpose of each should be defined

    and plans for the acquisition, training, support, and qualification of each shall be

    described in this section. This section may be in narrative or graphic format. A

    separate tool plan may be developed for software tool acquisition, development,

    or modification. In this case, a separate Tool Plan section may be added to the

    plan.)

    5. LIFECYCLE VERIFICATION AND VALIDATION

    (This section of the SVVP provides the detailed plan for the verification and validation

    tasks throughout the project life cycle. Please refer to IEEE Standard 1012 and IEEE

    Guide 1059 for detailed descriptions of lifecycle verification and validation activities.)

    5.1 Management of V & V

    This section shall address the following general topics:

    Verification and validation tasks,

    Methods and criteria,

    Inputs and outputs,

    Schedule,

    Resources,

  • 8/2/2019 SVVPLAN

    11/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 9 01/17/01

    Risks and assumptions, and

    Roles and responsibilities.

    (In addition, all sub-sections of this major heading (5) must specifically address all

    seven of the topics noted above.)

    (For all software projects, the Management of Verification and Validation section

    must include the following minimum tasks:

    Software Verification and Validation Plan Generation,

    Baseline Change Assessment,

    Management Review of V&V, and

    Review Support.)

    (Initiate the Software Verification and Validation Plan during the Concept phase

    of the project life cycle. However, verification and validation planning may be

    dependent on things outside of your control. Therefore, V&V planning may be

    most effectively performed in conjunction with the overall software development

    planning effort. The SVVP is often best developed incrementally.)

    (Evaluate proposed software changes for effects on previously completed V&V

    tasks. The request for baseline change assessment should be formally documented

    in a change proposal.)

    (Conduct periodic reviews of V&V efforts, technical accomplishments, resource

    utilization, future planning, and risk management. Management review comprises

    all of the general responsibilities of management for monitoring, controlling,

    reporting, and managing the plan.)

    (Identify key review support milestones. Correlate V&V task results to support

    project management and technical reviews.)

    5.2 Concept Phase

    (This section of the plan shall address the seven topics identified in section 5.1 of

    this document. Evaluate concept documentation to determine if the proposed

    project concept satisfies user needs and project objectives. Identify major

    constraints of interfacing systems and limitations of the proposed approach.

    Assess the criticality of each software item.)

    (The concept phase establishes the reason for the system. Evaluation in the

  • 8/2/2019 SVVPLAN

    12/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 10 01/17/01

    concept phase should establish that the objectives of the system define the user

    needs to be addressed and the technical and business advantages to be expected.)

    5.3 Requirements Phase

    (The requirements phase is when the functional and technical capabilities of the

    software product are defined and documented. The product from the

    requirements phase (Software Requirements Specification) should accurately state

    the software mission and what the software is intended to do. Requirements must

    be traceable to user needs and the system concept.)

    (This section of the plan shall address the seven topics identified in section 5.1 of

    this document. For critical software, Requirements Phase Verification and

    Validation must include the following tasks:

    Software requirements traceability analysis, (Trace SRS requirements tosystem requirements in concept documentation. Analyze identified

    relationships for correctness, consistency, completeness, and accuracy. Do the

    requirements completely satisfy the capabilities specified in the concept

    document?)

    Software requirements evaluation, (Evaluate SRS requirements forcorrectness, consistency, completeness, accuracy, readability, and testability.

    Assess the technical merits of the requirements.)

    Software requirements interface analysis, (Evaluate the SRS with hardware,user, operator, and software interface requirements documentation for

    correctness, consistency, completeness, accuracy, and readability Ensure that

    all external interfaces to the software and internal interfaces between

    software functions are complete and correctly specified.) and

    Test plan analysis for- System test, and- Acceptance test.)

    5.4 Design Phase

    (The design phase in the software life cycle involves the designs for architecture,

    software components, interfaces, and data creation, documentation, and

    verification. Design must trace back to requirements.)

  • 8/2/2019 SVVPLAN

    13/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 11 01/17/01

    (This section of the plan shall address the seven topics identified in section 5.1 of

    this document. For critical software, design phase V&V will include the following

    tasks:

    Software design traceability analysis (Trace design documentation torequirements. Analyze identified relationships for correctness, consistency,

    completeness, and accuracy.),

    Software design evaluation (Evaluate design for correctness, consistency,completeness, accuracy, readability, and testability. Assess the technical

    merits of the requirements and compliance to organization standards.),

    Software design interface analysis, (Evaluate design with hardware, operator,and software interface requirements documentation for correctness,

    consistency, completeness, accuracy, and readability At a minimum, analyze

    data elements at each interface.) and

    Test design generation

    - Component test plan, and

    - Integration test plan.)

    5.5 Implementation Phase

    (This section of the plan shall address the seven topics identified in section 5.1 of

    this document. Implementation phase V&V must include the following tasks:

    Source code traceability analysis (Trace source code to design specificationand assess correctness, consistency, completeness, and accuracy.),

    Source code evaluation (evaluate source code for correctness, consistency,completeness, accuracy, and testability. Assess code quality and compliance to

    organization standards.),

    Source code interface evaluation (Evaluate source code with hardware,operator, and design documentation for correctness, consistency,

    completeness, and accuracy.),

    Source code documentation evaluation (Evaluate draft code-relateddocuments with source code to ensure completeness, correctness, and

    consistency.),

    Test case generation for:

  • 8/2/2019 SVVPLAN

    14/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 12 01/17/01

    - Component test- Integration test- System test and- Acceptance test,

    Test procedure generation for:- Component test

    - Integration test and

    - System test,

    Component test execution.)

    5.6 Test Phase(This section of the plan shall address the seven topics identified in section 5.1 of

    this document. The following tasks must be included in this section:

    Acceptance test procedure generation, (Develop test procedures foracceptance test) and

    Test execution- Integration test,- System test, and

    - Acceptance test.)

    5.7 Installation and Checkout Phase

    (This section of the plan shall address the seven topics identified in section 5.1 of

    this document. The following verification and validation tasks must be included in

    this section:

    Installation configuration audit, (Audit installation package to determine thatall software products required to correctly install and operate the system arepresent and correct), and

    Final V&V report generation, (Summarize all V&V activities and resultsincluding the status and disposition of anomalies in the V&V final report).)

  • 8/2/2019 SVVPLAN

    15/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 13 01/17/01

    5.8 Operation and Maintenance Phase

    (This section of the plan shall address the seven topics identified in section 5.1 of

    this document. Any modifications, enhancements, or additions to software during

    this phase shall be treated as development activity and shall be verified and

    validated. If the original software was verified and validated under this standard,

    the standard must continue to be followed in the Operations and Maintenance

    phase. The minimum V&V tasks to include:

    - Software verification and validation plan revision,- Anomaly Evaluation,- Proposed change assessment, and

    - Phase task iteration.)

    (The operation and maintenance phase is the period of time in the software life

    cycle during which the software product is employed in an operational

    environment, monitored for satisfactory performance, and modified to correct

    problems or respond to changing requirements. Operation and maintenance may

    not be a phase but a sequence of repetitions or subsets of the software

    development life cycle.)

    6. Reporting

    (This section describes how the results of implementing the SVVP will be documented.

    Verification and validation reporting will occur throughout the software life cycle.

    Specify the content, format, and timing of all verification and validation reports.

    The required V&V reports include:

    - Anomaly reports,

    - Task reporting,

    - Phase summary reports, and

    - Final report.)

  • 8/2/2019 SVVPLAN

    16/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 14 01/17/01

    7. Administrative Procedures

    (This section should identify any existing administrative procedures that are to be

    implemented as part of the SVVP. Verification and validation efforts consist of both

    management and technical tasks. At least three audiences should be identified for the V&V

    information personnel performing the V&V tasks, personnel performing development tasks,

    and management.)

    7.1 Anomaly Reporting and Resolution

    (Identify the method of reporting and resolving anomalies including the criteria

    for reporting an anomaly, anomaly report distribution, and the authority and time

    line for resolving anomalies. This section should have the following sub-sections:

    - Methods and criteria for reporting,

    - Report distribution,

    - Methods and criteria for anomaly resolution,

    - Anomaly criticality scheme,

    - Resolution timing.)

    7.2 Task Iteration Policy

    (Describe the criteria used to determine when V&V tasks must be re-performed

    because input has changed. These criteria include assessments of change,

    criticality, cost, schedule, and effects on product quality.)

    7.3 Deviation Policy

    (Describe the procedures and forms used to request a deviation from the SVVP.

    The information required for deviation must include task identification, deviation

    rationale, and effect on software quality. Authority for approving deviations from

  • 8/2/2019 SVVPLAN

    17/17

    Software Verification and Validation Plan

    Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 15 01/17/01

    the plan must also be identified.)

    7.4 Control Procedures

    (Identify all control procedures applied to the verification and validation effort.

    At a minimum, control procedures should be identified for:

    - Configuration management,

    - Archive and retrieval,

    - Security, and

    - Access control.)

    7.5 Standards, Practices, and Conventions

    (This section identifies the standards, practices, and conventions that govern the

    performance of verification and validation tasks. Include IEEE, IRMC, and

    organizational standards, policies, procedures, and guidelines.)

    8. Plan Approvals

    (Identify the plan approvers. List the name, signature and date of plan approval.)