PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 1 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
Revision Table
Revision Date Paragraph Description
1.0 2015-04-09 New document First Issue
2.0 2015-06-01 Logos and scope Changed logos
3.0 2016-06-06 Attachments & Document Updated attachments and titles of personnel to reflect current Quality Control Manual
SYSTEM TURNOVER
DCM-PR-AQ-008-A
Approved By:
Name: Gordon Canning
Title: Corporate Quality Manager, Western Canada
Signature:
Date: 2016-06-06
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 2 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
TABLE OF CONTENTS
2.0 THE TURNOVER PROCESS: ......................................................................................................................... 3
3.0 THE SYSTEM TURNOVER PLAN .................................................................................................................. 3
3.1 Keys to Success .......................................................................................................................................... 3
3.2 DEFINING SYSTEM BOUNDARIES, PROCEDURE, PACKAGE FORMAT & CONTENT .................................... 4
3.3 CLIENT ACCEPTANCE OF THE PLAN ........................................................................................................... 5
3.4 RECORDS .................................................................................................................................................... 5
3.5 PUNCH LIST ................................................................................................................................................ 5
3.5 TURNOVER DOCUMENTS AND THE PROJECT ............................................................................................ 6
4.0 OBSTACLES TO SUCCESS ............................................................................................................................ 6
5.0 REFERENCES: .............................................................................................................................................. 7
6.0 SYSTEM TURNOVER DETAILS ..................................................................................................................... 7
7. DEFINE THE SYSTEM BOUNDARIES ............................................................................................................ 8
8. PROJECT CONTROLS ................................................................................................................................ 10
9.0 TURNOVER PROCEDURES ........................................................................................................................ 10
10.0 TURNOVER PACKAGE CONTENT .............................................................................................................. 11
11.0 CLIENT ACCEPTANCE OF THE TURNOVER PLAN ...................................................................................... 12
12.0 COMPLETING THE WORK ......................................................................................................................... 12
13.0 RECORDS – IMPLEMENTAITON & TRACKING .......................................................................................... 13
14.0 ESTABLISHING THE START UP SEQUENCE ............................................................................................... 13
15.0 WORK-REMAINING LIST ........................................................................................................................... 14
16.0 PUNCH LIST .............................................................................................................................................. 15
17.0 TURNOVER THE PACKAGES AND PROJECT .............................................................................................. 16
18.0 TURNOVER THE PACKAGES AND THE PROJECT PLANNING CHART ......................................................... 17
18.1 PROJECT PLANNING STAGE-FLOW CHART NOTES ................................................................................... 17
18.2 PROJECT PLANNING CHART ..................................................................................................................... 18
18.3 TURNOVER PACKAGE TABLE OF CONTENTS - EXAMPLE - A .................................................................... 19
19.0 SYSTEM TURNOVER– TCCC - EXAMPLE - B .............................................................................................. 22
19.1 PUNCH LIST / WORK-REMAINING - EXAMPLE- C ..................................................................................... 23
19.2 TURNOVER TRACKING SHEET - EXAMPLE -D ........................................................................................... 24
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 3 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
1.0 PURPOSE:
1.1 The purpose of this guide is to present how to plan and execute the Systems Turnover Process.
o Based on the experiences of company staff.
o Follows our Core Values.
o Includes industry best practices.
1.2 This procedure covers the timeline from pre-job project planning to the transfer of the System Turnover
Packages and the Care, Custody and Control of the project to the Client.
2.0 THE TURNOVER PROCESS:
• Plan – The Quality Control Supervisor (QCS) in conjunction with the Project Planner shall prepare the
Systems Turnover Plan. On large projects where the size and scope warrants, this function may be
assigned to a Turnover Manager.
• Define- The Project Management group shall ensure the owner has defined the systems/boundaries,
and accepted the procedures and turnover package table of contents.
• Acceptance - The CM shall obtain acceptance of the plan from the Client.
• Records – The QCS shall ensure that all records are signed, collected and assembled into turnover
packages.
• Punch List – The QCS shall manage the work-remaining list and punch list using the QC staff.
• Turnover – The QCS or (For Larger Projects) the Turnover Supervisorshall be responsible for
managing the process for transferring the project turnover documents to the Client.
3.0 THE SYSTEM TURNOVER PLAN
• The Quality Control Supervisor (QCS) & Project Planner (PP) shall start development of the turnover
plan at the “Project Set-Up” stage. This plan shall be identified in the Quality Plan and either form part of
the quality plan or for larger projects be referenced in the plan as a stand alone procedure. The Project
Manager (PM) shall approve the turnover plan for the project.
• The QCS & PP shall ensure the plan is complete - include all parts - Definition, Approval, Records,
Punch list and Turnover & Transfer of Care Custody and Control etc.
• The QCS and PP shall ensure that the Systems and Boundaries are completely defined and
referenced in the turnover plan.
• The Project Manager (PM) shall ensure the system turnover plan into is incorporated into Project
Controls – including the master schedule and document control process.
3.1 Keys to Success
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 4 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
• Together the PM and QCS shall be responsible for managing the resources and processes for the
document control department and for providing guidance and direction to personnel for the collection,
storage, handling, security and turnover of documents.
• The PM and Construction Manager (CM) shall collaborate with the QCS on the development and
support a strong project QA/QC program.
• PM, and CM, and QCS shall coordinate with Start-Up Team (if part of contract and scope of work).
• QCS shall include (when applicable) Vendor and Subcontractor documentation in the turnover process.
• The system turnover plan shall include instruction of Supervision and Craft on document completion
and submission.
• The QCS shall set up a turnover tracking system and a work-remaining/punch list management system.
(See section 20.1.)
• The PM shall ensure the QCS /Turnover Supervisoris empowered to manage the project turnover
process.
3.2 DEFINING SYSTEM BOUNDARIES, PROCEDURE, PACKAGE FORMAT & CONTENT
• The PM shall be responsible for ensuring that the system boundaries are defined early in the project.
• The PP and QCS shall ensure that the systems and boundaries are project specific and are
coordinated with start-up needs and contract requirements.
• The PP and QCS shall ensure that there are a balanced number of systems and that they are arranged
so that they are logical and manageable.
• The PP and QCS shall ensure that only documents that absolutely need to be included in the package
are added to the FIWP’s.
• The QCS shall establish a workable system to track documents and work remaining.
• The QCS shall avoid duplication of records, and submit a single package for entire project when
sensible, for example RT work, concrete, structural steel and grouting. Use cross references between
packages.
• Turnover Packages shall include vendor and subcontractor records when applicable.
• The QCS shall develop a project specific turnover procedure of tasks and responsibilities to include
examination and testing. Refer to the QA/QC Turnover Inspection and Test Plan (ITP).
• When defining the contents of the turnover package, considerable thought shall be given to the
establishment of “Common” or General Turnover Binders which contain records that apply to the
project as a whole not just the individual systems. It is important to identify which documents are to be
by system verses general binder early in the project to accommodate labelling and tracking documents
by system if required.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 5 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
3.3 CLIENT ACCEPTANCE OF THE PLAN
• The QCS shall obtain and document the Client acceptance of the plan and forms before starting to
accumulate documents.
• The QCS shall present the Client with the complete picture – the systems/boundaries, a sample system
turnover package with index, completed sample forms and a copy of every form that will be included.
• The PM and QCS shall agree to the turnover procedures with all stake holders.
• The QCS shall establish exactly where and when the Client will signoff forms, punch lists and
packages.
• The QCS shall push for electronic transmittal, or electronic and a limited number of hard copies.
• The PM and QCS shall obtain Client acceptance of the plan and get approval in writing.
• The PM and QCS shall agree on what work needs to be completed and documented for each project
milestone and add milestones to project schedule.
3.4 RECORDS
The Quality Control Supervisor (QCS) shall:
• Review the QA/QC Inspection and Test Plans (ITP).
• Instruct supervision and craft on what, when and how to record their work.
• Ensure records get from the field into the central project file as soon as practical.
• Ensure every record is filled out properly with no blanks, use N/A if not applicable.
• Direct the Quality Department/Document Control Department to scan, catalogue and file every
completed record as soon as it is received.
• Establish a system to track and maintain records. (i.e. Sign in and out log) Lost records equal likely
rework; treat the records and turnover books like gold.
• Establish a secure room to house and protect the turnover documents.
3.5 PUNCH LIST
The Project Manger (PM) and Quality Control Supervisor (QCS) shall:
• Implement a punch list tracking system that is tailored to the project needs (See example in Section
19.1). Ensure every item is assigned an individual ID.
• Ensure that all item are never deleted and that every item is closed it when it is completed.
• Fully describe each item, don’t generalize, and be specific.
• Prioritize items.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 6 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
• Hold adequate punch list review meetings, adjust frequency to project needs.
• Identify the date each item is added to punch list and by whom.
• Assign a due date to each item.
• Assign names to each item not just department or company and hold individuals accountable.
• Get signoff initials and keep the originals.
• Keep track of changes in the due dates, don’t just change the dates.
• Have Inspectors walk down the systems as soon as possible so recurring items can be prevented.
• Ensure punch list items don’t pile up. Get upper management acceptance on timely completion and
enforce if necessary.
• Identify and track material and equipment needs.
3.5 TURNOVER DOCUMENTS AND THE PROJECT
• The QCS shall keep track of the turnover systems using a project specific Turnover Tracking
Spreadsheet (See sample in section 19.2).
• First impressions count – The QCS shall be responsible for ensuring that hard copy binder covers look
professional, by using consistent formatting, adding spine inserts and spending the few extra dollars on
new good quality binders.
• The QCS and PM shall work together to obtain the Client signoffs, especially for Transfer of Care,
Custody (TCCC) and Control of systems and turnover documents.
4.0 OBSTACLES TO SUCCESS
The PM, QCS and Turnover group shall be aware of, prepare for, and address potential obstacles such as:
• Failure to identify systems and set up turnover packages early in the project.
• Lack of understanding of systems and their components.
• Incomplete or missing documentation.
• Overly large and complicated turnover system.
• Unrealistic construction schedule.
• Poor workmanship leading to many punch list items that delay construction progress and lower
productivity.
• Changes in system boundaries.
• Design changes.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 7 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
• Construction generally progresses by “area” but turnover must be by system. It takes constant effort to
make a smooth transition to complete systems from area construction.
5.0 REFERENCES:
The following are key reference sources for developing and implementing site-specific turnover plans and procedures:
• Intranet: Share Point Publications \ DCM-MA-AQ-02 \Quality Control Manual:
• System Turnover-Project Planning Chart (Section 18.2 of this document)
• Inspection and Test Plan (ITP)
• Project Quality Plan
• Exhibit A – Example - Turnover Package Table of Contents (TOC)
• Exhibit B – Example - Transfer of Care, Custody & Control (TCCC)
• Exhibit C – Example - Punch List / Work Remaining List
• Exhibit D – Turnover Tracking Sheet
Also available:
• Intranet: Eliot - Applicable Information Areas
6.0 SYSTEM TURNOVER DETAILS
• Know your customers - There may be one or several - the contractual customer, the owner, and the
end user of the facility or the start-up and commissioning entity.
• One or two turnovers? - On some projects, there may be two turnovers (i.e. .when there is a “Start-Up
Team” that has been assembled as part of contract and scope of work). There may be one turnover
from DCM construction to start-up team and then one from DCM to the Client/Engineer after start-up is
complete
• Think! - Defining systems and turnover requirements in a way that supports the efficient performance of
construction, checkout and turnover will improve the overall project schedule and reduce costs.
• Tailor to the job - The system turnover and start-up requirements will vary from contract to contract.
Guidelines for systems turnover must be tailored for the specific project contract scope of work. This
should be planned as early in the project as possible.
• Turnover Supervisor - For smaller projects, this responsibility is assigned to the Quality Control
Supervisor (QCS) who is ultimately responsible for managing the turnover process. The QCS shall
have sufficient knowledge and experience in each of the project disciplines. On larger project this may
be a separate position, but ultimately the responsibility for managing turnover resides with the project
QCS.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 8 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
• Coordination with Planners – The QCS shall coordinate the turnover planning with the Project
Planner(s). For electrical system turnover, ensure electrical circuit schedules have a column for
turnover packages.
• Involve the client - The project management team shall engage the client early in the project to
establish systems. Systems definition must involve the Client and occur early enough in the project so
documentation is generated and packaged appropriately from the start.
• Get the Flows - The project management team shall obtain an up to date set of the Process Flow
Diagrams (PFDs), Piping & Instrumentation Diagrams (P&IDs) and Electrical single line (one-line)
drawings. (System Scoping P&ID’s).
• Identify the Systems –The project management team shall work with the Client in order to identify the
systems on the Process Flow Diagrams (PFDs) and using the additional details shown on the P&IDs
and electrical single line drawings, identify the different process flows and start deciding how to
breakdown the project into systems for turnover. Follow the raw material through the process and see
where it goes, what gets added and what side-streams or other products are produced.
• Match the contractual requirements – The project management team shall ensure the choice of
systems and their boundaries are compatible with contract requirements for any required order or
schedule for turnover of systems or areas.
• Match the construction and energization schedules – The project management team shall ensure
the systems and boundaries are compatible with other construction milestones and follow the planned
sequence of energization and start-up of the facility. This requires at least a general awareness of the
start-up process.
• Match start-up needs - The project management team shall match the needs of the start-up
personnel. If start-up personnel are available they will be responsible for system definition for process
items that involve start-up. Sometimes a system will be defined based on a start-up need such as
chemical cleaning.
• Boundaries for start-up – The project management team shall consider boundaries for start up. In
order to define a system to be turned over for start-up it must be separate from the rest of the facility,
and it must be capable of being isolated. This means the boundaries must be set at valves, dampers,
switches or other block/disconnect locations.
• Start-up sequence - The project management team shall ensure the sequence of systems start-up is
defined. Again, ensure it ties with the scheduled order of construction completion and turnover. When
start-up personnel become available they will take over responsibility for the finalized start-up sequence
• Project wide turnover systems - The project management team shall ensure that when part of the
scope of work that earthwork, concrete and structural steel disciplines are turned over for the total
project instead of by individual systems unless the client requires otherwise. Similarly, installations such
as plant and instrument air or electrical power distribution to switchgear of MCCs may be turned over
for the total project.
7. DEFINE THE SYSTEM BOUNDARIES
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 9 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
• General discipline guidelines – The QCS shall ensure that the following components are included in
a system as applicable:
Mechanical - All pieces of equipment. Heat Exchangers are included in the system that receives the energy in the media flowing from the heat exchanger.
Piping - All piping valves, supports and specialty items. The boundaries for piping systems must be a process blind, valve, code boundary, or other method of isolation.
Electrical - All electrical components required for power and control of the equipment included in the package back to the individual motor starters. Individual motor starters are included in the system for the equipment; however the MCCs and buses are part of an electrical distribution package.
Instrumentation - All instruments on the piping or equipment in the system including power and signal wiring that will allow completion of loop checks.
• Maintain balance - Maintain a balance between creating too many systems and making systems too
large; both will be unmanageable.
• Mark-up the P&IDs - After the systems and their boundaries are defined, they shall be marked up in
color on a copy of the P&IDs and PFDs.
• Prepare turnover package index – The QCS shall prepare the Turnover Package Index (See Section
18.3 Turnover Table Of Contents Example A) of a standard system breakdown for a typical project. For
smaller project types use a simpler index if practical. The system numbers differ with various equipment
suppliers and design firms, and of course plant equipment and systems vary from project to project.
Each system is typically discipline specific and may have one or more subsystems as well. Example A
in section 18.3 should be modified to be project specific.
• Brief description of systems – The Quality Supervisor & Project Planner shall prepare a brief
description of each system and the system components. While a utility system may show on several
P&IDs and a process system on only one or two, it should be possible to describe the system and its
boundaries in two or three sentences. All equipment, piping and instruments within the boundaries,
including the electrical and instrument circuits serving those items are included in the system. If the
design is not complete, system boundaries may need to be broad and require further breakdown later.
• Get buy-in and acceptance - Distribute the turnover index, system descriptions and the marked up
and highlighted PFDs/P&IDs and get buy in and approval from the Project Manager, Project Engineer,
discipline Superintendents, Planners and the Client QA . It is important all parties review and thoroughly
understand the system boundaries.
• Assign system IDs - Once the turnover systems are defined and approved, assign the turnover
system identification to each equipment item, pipeline number, electrical circuit and instrument. Cross-
reference the line lists, indexes, and cable and equipment schedules to the turnover systems. Every
facility component must belong to one and only one system; leave nothing undefined.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 10 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
8. PROJECT CONTROLS
• Incorporate into Project Controls - As turnover systems are defined, it is important to incorporate this
information into DCM’s project controls systems. The Quality Control Supervisor shall ensure that the
Project Control personnel are provided with the turnover systems.
• Balance between too much and too little - It is equally important to maintain a balance and not
incorporate excessive "systems" information into the project controls; they may become too
complicated or diluted to serve their purpose.
• Keep it straight forward - The primary discipline tools for tracking progress of components of systems
for turnover are the cable pull card system, pipe tracking system (Weld Tracking system) and the
equipment list and instrument index with their associated inspection and test matrices. They will track
the progress of the components of the turnover systems, show their individual status at a reasonable
level of detail, and provide the overall status of each system.
• Turnover Tracking Systems - For projects with heavy document loads, the QCS shall employ a
tracking program. The “In-house” system shall include systems turnover, punch list, and hydro test
tracking.
• Include turnover dates in the project schedule - The project schedule shall include turnover dates
which shall tie them to the schedule logic. Turnover dates shall be identified as contractual
requirements or goals. Do not over complicate the schedule with turnover activities. When possible,
identify schedule activities with systems as well as phase codes.
• Baseline Scope - The project scheduler shall identify and track the baseline scope by discipline and
system in order to provide meaningful information on the status of turnover systems.
9.0 TURNOVER PROCEDURES
• Client approval – The QCS shall ensure that procedures for checkout and testing are accepted by and
coordinated with the client.
• Inspections and tests – Refer to the Inspection and Test Plans (ITP) for both turnover and the
individual disciplines. The project ITP’s are included in the Quality Manual as exhibits.
o Responsibilities of each party: Owner, Client, Design Engineer, DCM Personnel, DCM Subcontractors, Suppliers, etc. shall be identified in the Quality Plan and project procedures.
o Required Inspections and Tests: The specific test methods and acceptance criteria shall be established within the Quality Plan and project specific Inspection & Test Plans.
• The Quality Plan and project Specifications shall identify the persons authorized to accept the work
for each party and clear rules as to when parties are required to witness and/or sign off.
• The Project Quality Plan – The Project Quality Plan shall identify project specific procedures and
forms that are made project specific and include all relevant contract requirements. The QCS shall
ensure that once accepted all parties follow them.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 11 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
10.0 TURNOVER PACKAGE CONTENT
• Content - Turnover packages consist of the inspection and test documents required to certify
completion of the system. This may be up to mechanical completion or also include commissioning and
start-up phases when included in the contract scope.
• Only include what absolutely has to be there. (Check the contract documents for a “Contractor
Document Requirements List” (CDRL) or similar document. This document typically defines both
“system” and “general” turnover arrangement.
• The Transfer of Care, Custody and Control (TCCC) must also be included.(See Example B shown
in section 19.0)
• The System Turnover Books can be included with all start-up documentation in “Project Vendor Data
Books” that cover the entire project if requested by the Client.
• The scope will depend on the client and the project type. Each turnover package usually requires:
A description of the systems/disciplines and the system boundaries. o Signed-off punch list and a list of any exceptions along with their projected completion
dates for final acceptance of the system. o Test and inspection documents included for equipment and items within the package with
an index of contents. o As- built or redline drawings as applicable to the system. o A turnover form to transfer responsibility for the system which must: o Be tailored to the contract requirements, o Identify the level of acceptance being requested, o State the degree of transfer of care, custody and control, and o Require the client's signature to confirm acceptance.
• Sample package forms - A sample of forms to track System Turnover Packages (Turnover Package
Table of Contents, Inspection and Test Plan, and Care, Custody & Control Letter may be found on
DCM’s share point data base.
• A sample form “System Turnover for Start-up/Commissioning” for disciplines and other parties to
sign off a system ready for turnover to the start up team is attached also. This form is for use when
start- up is included in contract scope. The formal transfer of Care, Custody and Control to the client will
happen after start-up is completed.
• Other contents - The system turnover packages may also include other documents and manuals
required by contract such as Operating and Maintenance manuals and sub-vendor manuals for
equipment included in the system.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 12 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
11.0 CLIENT ACCEPTANCE OF THE TURNOVER PLAN
• Sample package – The Quality Supervisor shall prepare one sample turnover package for client
review and approval. This shall be done at the early stages of the project; the QCS shall propose
submitting the packages electronically instead of the typical multiple hard copies. The QCS shall strive
to limit the number of hard copies needed to save copying time and expense.
• Client acceptance – The QCS shall ensure the systems breakdown, turnover procedures, signoffs,
and the scope, exact content, arrangement and presentation of the turnover documents are acceptable
to the client and obtain written approval. The QCS shall ensure the Client understands the importance
of holding to agreed format and the time and cost impacts of changing it. Where possible ensure that all
groups within the Client organization, such as turnover, operating and maintenance groups, accept the
scope and format. The Client should have already approved the Project Quality Plan with the tests and
inspections required and the test forms to be used.
• Multiple Originals - Some items are not amenable to copying or scanning, or the original must be kept
by DCM such as Code Radiographic film. The QCS shall plan for the production of more than one
original if required.
• Set up turnover master files - The QCS shall scan the client approved sample and send to document
control. The QCS shall ensure both hard copy and electronic master turnover files are prepared that
match the accepted turnover package format. This will make assembling the packages easier and
quicker. Ensure turnover hard copies are scanned promptly and then filed in the master turnover file.
12.0 COMPLETING THE WORK
• Progress Review - The QCS shall conduct periodic reviews with all disciplines to review schedule
status and identify potential conflicts. The short interval schedules prepared by each field supervisor
must include the turnover dates and planned walk-through of their work.
• Detailed reviews – The project team shall review system status with each discipline well in advance of
the required turnover date. The emphasis shall be on completeness of documentation, work items
remaining and the date they will be completed. The project team shall review status again shortly
before the required turnover date.
• Quality Control Supervisor is responsible for conducting routine reviews of all aspects of the process,
including physical inspection, documentation, completeness and quality of documentation, package
review and schedule status.
• Transfer to Start-up Team - On projects where responsibility extends to commissioning and start-up
there will be a point as the system construction work is completed to handover the “ownership”, the
care, custody and control of the system and any work remaining to the start-up team. The QCS shall
ensure this handover is formalized and documented the same as if the transfer was to the Client.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 13 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
13.0 RECORDS – IMPLEMENTAITON & TRACKING
• Records and Responsibility - The Inspection and Test Plans (ITP) in the site specific QA/QC Plan,
the turnover procedures and the project schedule define the requirements and responsibilities for the
required inspections, documentation and time frame for the completion and turnover of the work.
• Ready for turnover - Whenever possible systems should be complete prior to the actual turnover date.
The turnover documentation package shall also be complete and ready to submit. However, the
agreed turnover procedure should allow for when this does not happen. If the Client agrees, readiness
for system acceptance may be determined by a review of documentation, a walk down inspection, and
recording of all outstanding items on the punch list. The turnover package can then be submitted later
as part of the final acceptance process.
• Partial turnovers - The project team and the Client must be aware of the implications of turning over
portions of the project. Warranty and maintenance responsibility issues as well as safety concerns need
to be addressed. Be sure the Client understands that by occupying a portion of the work and by
accepting Transfer of Care, Custody and Control of systems prior to final acceptance of the total
project, they will be accepting full responsibility for operation, maintenance and repair of those systems
and that the warranty period begins on that portion.
• Turnover to start-up team - When a system is turned over to the start-up team the components of the
system the QCS shall ensure each system is tagged as being under the control of the start-up team.
14.0 ESTABLISHING THE START UP SEQUENCE
• Coordinate with start-up – The QCS shall ensure that as part of the system definition the sequence of
systems start-up is coordinated with the construction completion and turnover schedules.
• Be proactive - Whenever practicable, be proactive in developing the start-up sequence of the facility.
This has an effect in our overall schedule, manpower and equipment resources. It will also affect
required deliveries of materials supplied by DCM and others.
• Contract requirements - In defining the start-up sequence contractual requirements must be
addressed. The establishment of new or changed schedule milestones to accommodate a turnover
schedule creates a contractual change to the schedule.
• Get buy-in - Regardless of who develops it, to assure a safe and logical start-up of the facility, the
owner, engineer and construction personnel should review in detail and accept the start-up sequence.
• Start early - The start-up sequence and the turnover milestones shall be set early in the project to
identify and resolve potential conflicts between the contract construction schedule and the systems
turnover milestones.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 14 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
15.0 WORK-REMAINING LIST
• Prepare a work-remaining list – The QCS shall ensure that a spreadsheet of remaining work is
prepared (See example C shown in section 19.1). The format will be similar or identical to that of the
punch list. The work- remaining list and the punch list can be combined, but first check with the Project
Manager on the contractual implications if such a list becomes available to the Client. If combined,
leave the flexibility to separate them, so only the punch list of work items remaining at the time of the
turnover walk down with the Client appear in the turnover packages
• Headings – the Work-Remaining list should identify for each item:
o DCM Test Package Number
o Punch Item Number
o Drawing Number
o Category
o Description
o Location
o System
o Initials of inspector or requestor
o Request date
o Punch type A, B,C
o Priority
o Date completed by Construction
o Individual responsible for completing- Initials of person who completed the item
o Date Cleared by QC and the Inspectors initials
o Completion date
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 15 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
• Priority - Priority assignment is important. A comprehensive list to modify for the project is as follows.
Reduce the number categories, if practical based, on the project milestones.
o Required for mechanical completion per contract
o Start commissioning
o Begin start-up
o Commercial operation
o Substantial completion
o Final completion
o Client responsibility
o ‘Wish list’
Note: use three or four categories, maximum
• Work remaining sample - A sample form for work remaining (and punch list) is attached (See
example C shown in section 19.1.). An Excel version is available for modifying to be project specific.
• Manage the list – The QCS shall keep track of the list and report to the project team with regular
updates including how many outstanding items, how many completed, items soon due and any items of
concern. A written process for requesting additions to the list or notifying of completion is best.
16.0 PUNCH LIST
• Agree on a single punch list - A single punch list for all project items is best for most project types.
The Project Manager and QCS shall ensure this becomes a mandatory part of the turnover procedure
for the project..
• Conduct system walk downs - When work on a system is complete, or the only outstanding work
items are not required for turnover, request and conduct a walk down inspection of the system and the
documentation, following the agreed turnover procedure. The point at which work- remaining items are
transferred to the punch list is normally when all contract work on a system is thought complete and the
final walk down of the system is performed with the client.
• Prepare and administer the punch list - With the Client’s approval, the QCS or his delegate shall
compile items from all parties including the Owner and the Engineer and manage the resolution or
completion of all punch list items. This will include any work remaining items already identified and not
yet closed. Once the punch list is prepared for a system, the system’s work remaining list is voided. The
QCS shall use a spreadsheet, similar to example C shown in section 19.1.
• Resolve outstanding punch list items – The QCS shall ensure that punch list items are corrected
promptly. As punch list items or exceptions to the package are cleared, the QCS shall notify the Client
and agree that the item has been corrected and is accepted. Generating and clearing punch lists is a
critical part of the turnover process.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 16 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
17.0 TURNOVER THE PACKAGES AND PROJECT
• Turnover packages - Based on contract requirements and accepted turnover procedures the QCS or
delegate shall prepare the turnover packages:
• Master copy of package - the QCS or delegate shall assemble a complete master package for each
system using the original documents.
• Check the package - the QCS shall review the master copy of the package for conformance to
contract requirements and the Project Quality Assurance/Quality Control Plan as well as to verify
completeness. This requires that documents be crosschecked against each other. The QCS shall also
check the package for errors and have them corrected by the responsible QC Inspector.
• Copy & check again - If transmitting hard copies, make the required number of copies and assemble
the identical books. The QCS shall double-check the packages for copy quality, content and assembly.
• Retain the originals - DCM retains the originals unless the contract explicitly requires otherwise. The
QCS shall stamp and sign each package as a “Certified Original Copy” Note: for ASME Section I Code
work DCM is required to retain the original code documents.
• Transmittal of the packages - the QCS shall provide under transmittal the required number of copies
for completed systems or disciplines to the Client for their acceptance of the work and documented
turnover package, each turnover package shall have a Transfer of Care, Custody and Control included
in the packages for the Client to sign and return. Retain the copy of the transmittal & TCCC form
containing the Client’s signature acknowledging receipt of the package.
• Track progress – Turnover is typically performed progressively and as such the QCS shall keep track
of ongoing progress for submission and Client approval of turnover packages and signing of the
Transfer of Care, Custody and Control forms. (See Section 19.2 for a sample Turnover Tracking Sheet)
• Retain a file copy - the QCS shall retain an electronic copy (and a hard copy if also submitted) of the
accepted system packages including the signed TCCC form in the document control department and
for record retention.
• Project Close Out – At the end of the project the QCS shall ensure that the Turnover Packages and all
Code Radiography film are placed into banker boxes, Labeled with the project name, job number and
shipped or delivered to the corporate office in Sherwood Park to the Attention of the Corporate Quality
Manager for the purpose of storage and archiving.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 17 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
18.0 TURNOVER THE PACKAGES AND THE PROJECT PLANNING CHART
18.1 PROJECT PLANNING STAGE-FLOW CHART NOTES
• If there is no contractual obligation for DCM to turn the facility over by systems but there
is a cost benefit to do so, the QCS shall obtain Client approval prior to initiating a system
approach.
• DCM’s Planning Group, Corporate QA/QC Department or the design engineers can
assist with defining the systems. Taking this initiative can help present DCM in a positive
light and assure that we understand the system boundaries. At this stage of the project,
the system boundaries may be broad and require further breakdowns later in the project.
• Turnover dates shown on the project schedule shall clearly define whether they are
contractual requirements or goals.
• The QCS and Client shall agree on forms and format to be used. Refer to the Inspection
and Test Plans (ITP’s) in the Project Quality Plan & Quality Manual. A matrix identifying
specific forms for each activity is an excellent tool.
• The QA/QC plans shall also address testing and inspection methods and who will be
qualified to do it. Everyone involved needs to understand how to complete the
documentation.
• In-house system walk-through shall be performed by Construction and QC and DCM
generated work remaining/punch list items shall be documented and completed.
• The Project Quality Plan will identify the required quantity of turnover packages, sign-off
sheets, allowance for punch list, etc. On some projects, it may be possible to have two
turnovers. One from construction to Client start-up and then one from DCM to the
Client/Engineer after start-up is complete.
• Phase 2 is the Project Execution Stage and starts with preparing the sample turnover
package for Client review and acceptance.
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 18 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
Review the contractual
documents to determine
DCM’s scope, mechanical
completion, commissioning,
Operations, etc. ,
Are there contractual
requirements to turn
the facility over by
system?
Has the Owner or
Engineering Firm
defined system
boundaries / scope etc.
Use process flow diagrams and
single lines, mark up systems
required and issue to the Client /
Engineer for review and comment
Has the start up sequence and
dates been established?
Does it make sense to
turn the plant over by
systems by DCM or the
Owner?
Phase 2
Incorporate Turnover
Documentation
Requirements into
discipline QA/QC Plans
and establish a method
for tracking
Based on the process flow
diagrams and single line
drawings and discussions with
start up teams determine
sequencing dates and issue to
the Client or Engineering Firm for
review.
Incorporate Turnover Dates into
the project Schedule
Using DCM’s QA/QC
Standards ,and the
Supplier’s Document
Requirements List (if
defined in the contract)
determine required
documentation and submit
to Client for review &
comment.
Does the contract
documents define turnover
documentation
requirements?
Review Productivity
Report and schedule to
determine the best
method for incorporating
systems into these
documents without
making it complex or
loosing their other
purpose.
Yes
Yes
No
Yes
Yes
No
No
No
Yes
18.2 PROJECT PLANNING CHART
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 19 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
18.3 TURNOVER PACKAGE TABLE OF CONTENTS - EXAMPLE - A
No.: Required: Administrative Complete Date Resp.
1.1 Yes Description SU 1.2 Yes Turnover P&ID SU 1.3 No Single lines SU 1.4 Yes Equipment list ENG 1.5 Yes Valve list ENG 1.6 Yes Instrument List ENG 1.7 No Line list ENG 1.8 No DCS I/O List ENG 1.9 Yes Commissioning and testing SU 1.10 Yes Work remaining list SU 1.11 Yes Construction Punch list SU 1.12 Yes COD Punch list SU 1.13 No Permits DCM 1.14 Yes Construction completion and SU 1.15 Yes Turnover to Owner Form SU
No.: Required: Civil / Foundations /
Structural Complete Date Resp.
2.1 No Material receiving report CS 2.2 No Off-site manufacturing CS 2.3 No Soils testing plan and results QA 2.4 No Concrete placement release, CS 2.5 No Concrete placement CS 2.6 No Concrete pour log CS 2.7 No Concrete compressive strength QA 2.7 No Concrete foundation release QA 2.9 No Mass concrete temperature log QA 2.10 No Grout log CS 2.11 No Batch plant check list CS 2.12 No Pile driving log CS 2.13 No Structural steel checkout CS 2.14 No Structural weld inspection SC 2.15 No Structural steel torque SC 2.16 No Structural steel torque records SC
No.: Required: Piping Complete Date Resp.
3.1 No Weld test log PS 3.2 No Weld maps / travelers PS 3.3 No Weld inspection request / log PS 3.4 No Post weld heat treatment log PS 3.5 No NDE reports QA 3.6 No Boiler code data PS 3.7 No Pipe blow down and cleaning PS 3.8 No Flushing cleaning inspection PS 3.9 No Jeep test report QA 3.10 No Pipe pressure / leakage report PS 3.11 No Pressure test report QA 3.12 No Pressure test log QA 3.13 No Pipe hydrostatic / Leak test QA
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 20 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
3.14 No Pipe hanger / support PS 3.15 No Vessel acceptance and PS 3.16 No Test Log Package PS 3.17 No Inspection Report PS
No.: Required: Mechanical Complete Date Resp.
4.1 No Mechanical alignment form MS 4.2 No Lubrication tag and log MS 4.3 No Shaft rotation tag and log MS 4.4 No Sole plate / foundation release MS 4.5 No Grout pour / cube test log MS 4.6 No Turbine alignment worksheet MS 4.7 No Periodic storage / maintenance MS 4.8 Yes On site vendor records VENDORS
No.: Required: Electrical Complete Date Resp.
5.1 No Unit sub station checklist ES 5.2 No Power transformer check list ES 5.3 No Medium voltage motor starters ES 5.4 No Draw out air circuit breakers ES 5.5 No Medium voltage air switches ES 5.6 No Switchgear and switchboard ES 5.7 No Motor control center sections, ES 5.8 No MCC Starters ES 5.9 No MCC Breaker ES 5.10 No Dry Type transformers megger ES 5.11 No Insulation resistance tests ES 5.12 No Motor test and MCC data ES 5.13 No Lighting and distribution panel ES 5.14 No Cable dielectric test ES 5.15 No Cable termination log ES 5.16 No Circuit schedule ES 5.17 No Generator, sync and wound ES 5.18 No Inspection of packaged ES 5.19 No Ground systems test record ES 5.20 No Ground/earthling system ES 5.21 No Motor run-in record SU 5.22 No Bus duct check list ES 5.23 No Panel list and schedules ES 5.24 No Protective relaying and meter EPS 5.25 No Current Transformer test report EPS
No.: Required: Instrumentation Complete Date Resp.
6.1 No Calibrator cal sheets IS 6.2 No Loop status SU 6.3 No Loop check SU 6.4 No Temperature indicator check IS 6.5 No Pressure indicator check list IS 6.6 No Transmitter calibration IS 6.7 No Control valve calibration IS 6.8 No Indicator calibration IS 6.9 No Electro pneumatic converter IS 6.10 No Switch device IS
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 21 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
6.11 No Controller IS 6.12 No Thermocouple / RTD check list
No.: Required: Start-up Complete Date Resp.
7.1 SU 7.2 SU 7.3 SU
Legend:
DCM DCM CONSTRUCTION PV Painting subcontractor
QA DCM QA/QC IV Insulation subcontractor
EN Engineer HV Heat tracing subcontractor
CS Civil superintendent SV Switchyard subcontractor
SS Structural superintendent ES Electrical subcontractor
ES Electrical Superintendent CTG CTG Vendor
PS Piping Superintendent HRSG HRSG Vendor
IS Instrumentation superintendent ACC Air Cooled Condenser
MS Mechanical superintendent SU SU Start-up group
FV Fire protection subcontractor ACCE ACC erection contractor
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 22 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
19.0 SYSTEM TURNOVER– TCCC - EXAMPLE - B
TRANSFER OF CARE CUSTODY & CONTROL (TCCC)
System
System Description
Scope
This system has been completed except as noted on the attached Construction
Punch List. This system will be turned over to the start-up and commissioning group
and will be off limits to any further construction activities unless expressly directed by
Civil
Structural
Piping
Mechanical
Electrical / Instrum.
Instrument Cal’s
DCS System
QA / QC
Construction Mgmt.
Vendors
Owner
DCM Start-up
Comments / Notes
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 23 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
19.1 PUNCH LIST / WORK-REMAINING - EXAMPLE- C
PROCEDURE
SYSTEM TURNOVER
Uncontrolled if printed. Confidential – Property of DCM Group Reproduction, recording and distribution, in whole or in part, in any form or by any means, is strictly prohibited without prior written authorization from DCM Group.
Page 24 of 24 Rev. 3.0 – 2016-06-06 DCM-PR-AQ-008-A
19.2 TURNOVER TRACKING SHEET - EXAMPLE -D