  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    SCHEDULE T-8 Labour Forces

    1 Labour Forces(To be attached herewith)

    1.1 T-8-1 Labour Forces (LIST OF LABOUR FORCES REQUIRED)1.2 T-8-2 Labour Forces (Labour Flow Tabulation)

    Name of Bidder: LILAMA 18/LILAMA 45.4 JOINT VENTURE

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    1.1 T-8-1 Labour Forces (LIST OF LABOUR FORCES REQUIRED)1.2 T-8-2 Labour Forces (Labour Flow Tabulation)

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    SCHEDULE T-8 Labour Forces

    LILAMA 18/LILAMA 45.4 JOINT VENTURE

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    No. Types of LabourLocal Foreign

    Total (MM) Nos. at Peak Total (MM)

    A-1 Supervisor/Foremen/Security Officer 512.0 31.0 NA

    A-2 3,795.0 240.0 NA

    A-3 Unskilled Labour 332.0 30.0 NA

    A-4 Equipment Operators 263.0 16.0 NA

    A-5 Mechanicals, electricians and maintenance personel 142.0 8.0 NA

    A-6 588.0 28.0 NA

    Bidders Official Representative:Signature:

    Date:

    Company Stamp:

    SCHEDULE T-8-1 Labour Forces (LIST OF LABOUR FORCESREQUIRED)

    Skilled Labour (such as welders, rigger, fitters, painter, etc.)

    Other site employees (such as guard-man, vehicle drivers, cocks, boys, etc.)

    Name: Trn S QunhPosition: General Director

    Company: LILAMA 18 Joint Stock Company.

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    Foreign

    Nos. at Peak

    NA

    NA

    NA

    NA

    NA

    NA

    SCHEDULE T-8-1 Labour Forces (LIST OF LABOUR FORCESREQUIRED)

    Company: LILAMA 18 Joint Stock Company.

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    SCHEDULE T-8-2 Labour Forces (Labour Flow Tabulation)

    Month

    1st2nd3rd4th5th6th 13.0 30.0 4.0 4.0 7th 21.0 70.0 8.0 4.0 8th 29.0 80.0 8.0 6.0 9th 31.0 170.0 27.0 10.0 10th 31.0 210.0 30.0 12.0 11th 31.0 229.0 30.0 12.0 12th 31.0 214.0 30.0 12.0 13th 31.0 240.0 30.0 16.0 14th 31.0 239.0 25.0 16.0 15th 31.0 239.0 25.0 16.0 16th 26.0 238.0 15.0 16.0 17th 23.0 231.0 15.0 16.0 18th 23.0 225.0 15.0 16.0 19th 23.0 215.0 15.0 16.0 20th 23.0 215.0 15.0 16.0 21st 23.0 215.0 15.0 16.0 22nd 23.0 215.0 10.0 16.0 23rd 23.0 215.0 10.0 16.0 24th 23.0 135.0 5.0 11.0 25th 11.0 85.0 8.0 26th 11.0 85.0 8.0 27th28th

    Bidders Official Representative:Signature:

    Date:

    Company Stamp:

    Supervisor/Foremen/Security Officer

    Skilled Labour (such as welders, rigger, fitters,

    painter, etc.)UnskilledLabour

    EquipmentOperators

    Name: Trn S QunhPosition: General Director

    Company: LILAMA 18 Joint Stock Company.

  • Da Nhim Hydropower Plant Expansion ProjectBidding documents Package 12.02 (DNE-D2)

    SCHEDULE T-8-2 Labour Forces (Labour Flow Tabulation)

    2.0 4.0 4.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 8.0 2.0 2.0

    Bidders Official Representative:

    Mechanicals, electricians and maintenance personel

    Name: Trn S QunhPosition: General Director

    Company: LILAMA 18 Joint Stock Company.

    T-8T-8-1 summaryT-8-2 in VietNam