Upload
hoangcong
View
222
Download
6
Embed Size (px)
Citation preview
T T T Working Group for
Putney Embankment Foreshore & Barn Elms
Tuesday 27th September 2016
Community Liaison Working Group (CLWG)
The CLWG will serve as a two-way communications channel between
Tideway and local communities.
CLWG will provide a forum for open discussion on matters concerning
construction and communications with local authorities and community
representatives.
The principal aims are:
• To promote communication across the communities affected
• To keep stakeholders, communities and businesses well informed about the
project’s progress
• To give the community an opportunity to express their views and influence
local communication activity
• Provide a forum for the local community to discuss, understand and
potentially influence the way we undertake construction activity
• In 2014, 62 million cubic metres of sewage discharged to the tidal River Thames.
• 50 discharges on average in a typical year
2
1860
2 million
1910
4 million
20138 million
Bazalgette
design capacity
Population of London
3
Combined Sewer Overflow (CSO)
4
Thames Tideway Tunnel
5
Main Contractors
West
BMB
Central
FLO
East
CVB
System
Integrator
7
Putney Embankment Foreshore
8
The Putney Embankment Foreshore site is on the southern bank of the River Thames. There are two sites: a main construction site and an area to build a temporary slipway to maintain public access to the River Thames.This site will be used to intercept the Putney Bridge combined sewer overflow.
Putney Embankment Foreshore
Overview
9
The Problem:At this location, in a typical year, there would be 33 discharges of untreated sewage with a volume of about 68,000 tonnes into the tidal River Thames.
The Solution:Our Putney Embankment Foreshore site will control the discharges from the Putney Bridge combined sewer overflow. When the tunnel is in operation it is expected that only one discharge will occur.
Project Duration:Construction is due to be begin in 2016 and will take approximately three and a half years.
Site details: A temporary slip way will be constructed approximately 300m upstream of Putney Bridge. CSO drop shaft will have a depth of approximately 36m and an internal diameter of approximately 6m.
Putney Embankment Foreshore
Overview
10
Pre works:First stage Navigational Risk Assessment for in river works completeRelocation of moored vessels prior to building temporary slipwayStart of temporary slipway construction: Late 2016Temporary slipway complete prior to March 2017 Boat Race season
Main works: Construction of underground structures to connect the CSO to the shaftShaft (36m deep, 6m diameter) to be constructed within the river foreshoreShaft will transfer combined sewage flows from the CSO to main tunnel via 48m long connection tunnel
Putney Embankment Foreshore
Overview
11
Temporary Slipway plan
ChasNewens
ConstitutionalClub
Temporary slipway
12
Temporary Slipway plan
Putney Slip
Construction Working Hours: Weekdays 08:00 – 18:00Saturday 08:00 – 13:00Sunday No works
13
Temporary Slipway plan
Construction deliveries:93% by river/ by barge7% by road
Construction deliveries via Glendarvon Road limited to 10:00 – 15:00
14
Main Site Plan
Start of works: July 2017Duration: Approx. 3 ½ years
15
Putney Embankment ForeshoreTimeline of Work
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Temporary Slipway Set up and Construction November 16 - March 17
Foreshore Set Up July 17 - November 17
Drop Shaft including cofferdam October 17 - April 19
Short Connection Tunnel June 18- April 19
CSO Modifcations February 18- April 19
Connection Culvert March 19 - August 19
Valve Chambers September 18 - July 19
Fit Out, Landscape and MEICA July 19- May 20
2016 2017 2018 2019 2020
Main works put back to end of July 2017 to accommodate fish spawning March-June and to allow the public to enjoy the river during the summer season.
20
Putney Embankment Foreshore
Questions
17
Barn Elms
18
Barn Elms
Overview
Boat house
Boat house access road
Wetland centre
BESC
Residential properties
Residential properties
19
Barn Elms
Overview
20
Barn Elms
Changing Rooms
21
Barn ElmsTimeline of Work
20
Barn Elms
Questions
AIR QUALITY AND NOISE MONITORS
Noise Monitor
23
Air Quality Monitor
AIR QUALITY AND NOISE MONITORS
Air Quality Monitor Locations
24
AIR QUALITY AND NOISE MONITORS
Noise Monitor Locations
25
1 volunteer
hour for each 3
FTEs per annum
towards STEM
education
Skills and Employment
Underpinned by contractors’Skills and Employment Plan
30% river
workforce from
Kent, Essex
and Greater
London
1 in 50jobs an
apprenticeship
25% overall
workforce from
affected
boroughs
20% jobs
within drive
site boroughs
Sustainable
target for
employment of
unemployed
Community Relations
• Proactive approach
• Develop Community Engagement
• Community link to Project Team
• Liaison with local schools
• Identify Community Investment
Opportunities
• Current Volunteering
• Complaint handling
20
Questions