28
T T T Working Group for Putney Embankment Foreshore & Barn Elms Tuesday 27 th September 2016

T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

Embed Size (px)

Citation preview

Page 1: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

T T T Working Group for

Putney Embankment Foreshore & Barn Elms

Tuesday 27th September 2016

Page 2: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

Community Liaison Working Group (CLWG)

The CLWG will serve as a two-way communications channel between

Tideway and local communities.

CLWG will provide a forum for open discussion on matters concerning

construction and communications with local authorities and community

representatives.

The principal aims are:

• To promote communication across the communities affected

• To keep stakeholders, communities and businesses well informed about the

project’s progress

• To give the community an opportunity to express their views and influence

local communication activity

• Provide a forum for the local community to discuss, understand and

potentially influence the way we undertake construction activity

Page 3: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

• In 2014, 62 million cubic metres of sewage discharged to the tidal River Thames.

• 50 discharges on average in a typical year

2

1860

2 million

1910

4 million

20138 million

Bazalgette

design capacity

Population of London

Page 4: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

3

Combined Sewer Overflow (CSO)

Page 5: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

4

Thames Tideway Tunnel

Page 6: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

5

Main Contractors

West

BMB

Central

FLO

East

CVB

System

Integrator

Page 7: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

7

Putney Embankment Foreshore

Page 8: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

8

The Putney Embankment Foreshore site is on the southern bank of the River Thames. There are two sites: a main construction site and an area to build a temporary slipway to maintain public access to the River Thames.This site will be used to intercept the Putney Bridge combined sewer overflow.

Putney Embankment Foreshore

Overview

Page 9: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

9

The Problem:At this location, in a typical year, there would be 33 discharges of untreated sewage with a volume of about 68,000 tonnes into the tidal River Thames.

The Solution:Our Putney Embankment Foreshore site will control the discharges from the Putney Bridge combined sewer overflow. When the tunnel is in operation it is expected that only one discharge will occur.

Project Duration:Construction is due to be begin in 2016 and will take approximately three and a half years.

Site details: A temporary slip way will be constructed approximately 300m upstream of Putney Bridge. CSO drop shaft will have a depth of approximately 36m and an internal diameter of approximately 6m.

Putney Embankment Foreshore

Overview

Page 10: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

10

Pre works:First stage Navigational Risk Assessment for in river works completeRelocation of moored vessels prior to building temporary slipwayStart of temporary slipway construction: Late 2016Temporary slipway complete prior to March 2017 Boat Race season

Main works: Construction of underground structures to connect the CSO to the shaftShaft (36m deep, 6m diameter) to be constructed within the river foreshoreShaft will transfer combined sewage flows from the CSO to main tunnel via 48m long connection tunnel

Putney Embankment Foreshore

Overview

Page 11: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

11

Temporary Slipway plan

ChasNewens

ConstitutionalClub

Temporary slipway

Page 12: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

12

Temporary Slipway plan

Putney Slip

Construction Working Hours: Weekdays 08:00 – 18:00Saturday 08:00 – 13:00Sunday No works

Page 13: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

13

Temporary Slipway plan

Construction deliveries:93% by river/ by barge7% by road

Construction deliveries via Glendarvon Road limited to 10:00 – 15:00

Page 14: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

14

Main Site Plan

Start of works: July 2017Duration: Approx. 3 ½ years

Page 15: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

15

Putney Embankment ForeshoreTimeline of Work

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Temporary Slipway Set up and Construction November 16 - March 17

Foreshore Set Up July 17 - November 17

Drop Shaft including cofferdam October 17 - April 19

Short Connection Tunnel June 18- April 19

CSO Modifcations February 18- April 19

Connection Culvert March 19 - August 19

Valve Chambers September 18 - July 19

Fit Out, Landscape and MEICA July 19- May 20

2016 2017 2018 2019 2020

Main works put back to end of July 2017 to accommodate fish spawning March-June and to allow the public to enjoy the river during the summer season.

Page 16: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

20

Putney Embankment Foreshore

Questions

Page 17: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

17

Barn Elms

Page 18: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

18

Barn Elms

Overview

Boat house

Boat house access road

Wetland centre

BESC

Residential properties

Residential properties

Page 19: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

19

Barn Elms

Overview

Page 20: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

20

Barn Elms

Changing Rooms

Page 21: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

21

Barn ElmsTimeline of Work

Page 22: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

20

Barn Elms

Questions

Page 23: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

AIR QUALITY AND NOISE MONITORS

Noise Monitor

23

Air Quality Monitor

Page 24: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

AIR QUALITY AND NOISE MONITORS

Air Quality Monitor Locations

24

Page 25: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

AIR QUALITY AND NOISE MONITORS

Noise Monitor Locations

25

Page 26: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

1 volunteer

hour for each 3

FTEs per annum

towards STEM

education

Skills and Employment

Underpinned by contractors’Skills and Employment Plan

30% river

workforce from

Kent, Essex

and Greater

London

1 in 50jobs an

apprenticeship

25% overall

workforce from

affected

boroughs

20% jobs

within drive

site boroughs

Sustainable

target for

employment of

unemployed

Page 27: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

Community Relations

• Proactive approach

• Develop Community Engagement

• Community link to Project Team

• Liaison with local schools

• Identify Community Investment

Opportunities

• Current Volunteering

• Complaint handling

Page 28: T T T Working Group for Putney Embankment Foreshore …€¦ · T T T Working Group for Putney Embankment Foreshore & Barn Elms ... CSO drop shaft will have a depth of ... Start of

20

Questions