123
1 Table of contents EXECUTIVE SUMMARY ................................................................................................................. 6 1 INTRODUCTION ................................................................................................................. 17 1.1 PROJECT PROPONENT ..................................................................................................................17 1.2 NEED OF THE PROJECT .................................................................................................................17 1.3 BACK GROUND OF THE PROJECT ..................................................................................................18 1.4 Project Objectives.........................................................................................................................18 1.5 Policy and Legal framework .........................................................................................................19 1.6 Scope of the EIA Study..................................................................................................................19 1.7 Organization of the Report ...........................................................................................................20 2 PROJECT DESCRIPTION ...................................................................................................... 21 2.1 PROJECT LOCATION ......................................................................................................................21 2.2 PROJECT DESCRIPTION .................................................................................................................23 2.3 Process Description ......................................................................................................................25 2.4 Utilities Requirement & Source ....................................................................................................27 2.4.1 Water ..........................................................................................................................................27 2.4.2 Power ..........................................................................................................................................28 2.5 Project Cost ..................................................................................................................................28 2.6 Air pollution Sources ....................................................................................................................28 2.7 Noise generation and its management ........................................................................................29 2.8 Solid waste generation and Management ...................................................................................29 2.9 Land Use Plan ...............................................................................................................................30 2.10 Assessment of Infrastructure Demand.........................................................................................30 2.9.1 Roadways ....................................................................................................................................31 2.9.2 Water supply & sewerage infrastructure ...................................................................................31 2.11 Instrumentation & Control System ..............................................................................................31 2.12 Telecommunication System .........................................................................................................31 2.13 Design and Safety System.............................................................................................................31 2.14 Effluent Treatment Plant (ETP).....................................................................................................34 2.15 Civil Works ....................................................................................................................................34

Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

Embed Size (px)

Citation preview

Page 1: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

1

Table of contents

EXECUTIVE SUMMARY ................................................................................................................. 6

1 INTRODUCTION ................................................................................................................. 17

1.1 PROJECT PROPONENT .................................................................................................................. 17

1.2 NEED OF THE PROJECT ................................................................................................................. 17

1.3 BACK GROUND OF THE PROJECT .................................................................................................. 18

1.4 Project Objectives ......................................................................................................................... 18

1.5 Policy and Legal framework ......................................................................................................... 19

1.6 Scope of the EIA Study.................................................................................................................. 19

1.7 Organization of the Report ........................................................................................................... 20

2 PROJECT DESCRIPTION ...................................................................................................... 21

2.1 PROJECT LOCATION ...................................................................................................................... 21

2.2 PROJECT DESCRIPTION ................................................................................................................. 23

2.3 Process Description ...................................................................................................................... 25

2.4 Utilities Requirement & Source .................................................................................................... 27

2.4.1 Water .......................................................................................................................................... 27

2.4.2 Power .......................................................................................................................................... 28

2.5 Project Cost .................................................................................................................................. 28

2.6 Air pollution Sources .................................................................................................................... 28

2.7 Noise generation and its management ........................................................................................ 29

2.8 Solid waste generation and Management ................................................................................... 29

2.9 Land Use Plan ............................................................................................................................... 30

2.10 Assessment of Infrastructure Demand ......................................................................................... 30

2.9.1 Roadways .................................................................................................................................... 31

2.9.2 Water supply & sewerage infrastructure ................................................................................... 31

2.11 Instrumentation & Control System .............................................................................................. 31

2.12 Telecommunication System ......................................................................................................... 31

2.13 Design and Safety System............................................................................................................. 31

2.14 Effluent Treatment Plant (ETP) ..................................................................................................... 34

2.15 Civil Works .................................................................................................................................... 34

Page 2: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

2

2.16 Green Belt Development Plan ...................................................................................................... 35

3 BASELINE ENVIRONMENTAL SCENARIO .............................................................................. 36

3.1 BASELINE DATA ............................................................................................................................. 36

3.2 Study Area .................................................................................................................................... 36

3.3 LAND USE PLAN ............................................................................................................................ 37

3.4 GEOMORPHOLOGY: ...................................................................................................................... 39

3.5 BASELINE DATA ............................................................................................................................. 40

3.5.1 AIR ENVIRONMENT ................................................................................................................... 40

3.6 Micro metrology ........................................................................................................................... 45

3.7 Noise Environment ....................................................................................................................... 47

3.8 WATER ENVIRONMENT ............................................................................................................ 49

3.8.2 Baseline Water quality Status ..................................................................................................... 54

3.9 SOIL ENVIRONMENT ..................................................................................................................... 57

3.10 ECOLOGY ...................................................................................................................................... 59

3.11.1 Terrestrial Ecology .................................................................................................................... 59

3.10.2 Aquatic Ecology ......................................................................................................................... 63

3.11 Socio Economic Environment: ...................................................................................................... 67

4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES ............................ 77

4.1 ENVIRONMENTAL IMPACTS ......................................................................................................... 77

4.2 Activities during Construction Phase ............................................................................................ 77

4.3 Activities during Operational Phase ............................................................................................. 78

4.4 Impacts during Construction Phase .............................................................................................. 78

4.4.1 Impacts on Soil ............................................................................................................................ 79

4.4.2 Mitigation Measures ................................................................................................................... 79

4.4.3 Impacts on Land Use ................................................................................................................... 79

4.4.4 Mitigation Measures ................................................................................................................... 79

4.5 Impacts on Hydrology and Water Use .......................................................................................... 79

4.5.1 Impacts on Hydrology ................................................................................................................. 79

4.5.2 Mitigation Measures ................................................................................................................... 79

4.5.3 Impacts on Water Quality ........................................................................................................... 80

4.5.4 Mitigation Measures ................................................................................................................... 80

4.6 Air Quality ..................................................................................................................................... 80

Page 3: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

3

4.6.1 Impacts on Air Quality ................................................................................................................ 80

4.6.2 Mitigation Measures: .................................................................................................................. 80

4.7 Noise Quality ................................................................................................................................ 80

4.7.1 Impacts on Noise .................................................................................................................. 80

4.7.2 Mitigation Measures ............................................................................................................ 81

4.8 Flora & Fauna ............................................................................................................................... 81

4.8.1 Impacts on Flora ................................................................................................................... 81

4.8.2 Mitigation Measures: ........................................................................................................... 81

4.8.3 Impacts on Fauna: ................................................................................................................ 81

4.8.4 Impacts on Aquatic Life ........................................................................................................ 82

4.9 Impacts on Socio-economics ........................................................................................................ 82

4.10 Impacts & Mitigation Measures During Operation Phase ........................................................... 82

4.10.1 Soil ............................................................................................................................................ 82

4.10.2 Water ........................................................................................................................................ 83

4.11 OPERATIONAL PHASE IMPACTS .................................................................................................... 83

AIR ENVIRONMENT .............................................................................................................................. 83

5 ENVIRONMENTAL MANAGEMENT PLAN ............................................................................ 89

5.1 Environmental Management Plan During Construction Phase .................................................... 89

5.2 Environmental Management Plan During Operation Phase ........................................................ 90

5.2.1 Greenbelt Development Plan ..................................................................................................... 91

5.2.2 Development of green belt will include: .................................................................................... 93

5.2.3 Solid Waste Management .......................................................................................................... 94

5.3 SOCIO – ECONOMIC ENVIRONMENT............................................................................................ 94

5.4 POST PROJECT ENVIRONMENTAL MONITORING ......................................................................... 97

5.3.1 Monitoring Program ................................................................................................................... 97

5.3.2 Institutional Set-up for Monitoring ............................................................................................ 97

5.3.3 Fire and Safety Management ..................................................................................................... 97

5.3.4 Legal and Statutory compliance ................................................................................................. 98

5.3.5 Information Dissemination and Public Relations ....................................................................... 98

5.3.6 Mutual Aid Arrangement ............................................................................................................ 98

5.5 Occupational Health and Safety ................................................................................................... 98

5.4.1 Safety Plan ................................................................................................................................ 100

Page 4: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

4

5.4.2 Safety Training .......................................................................................................................... 100

5.6 EXPENDITURE ON ENVIRONMENTAL MEASURES ...................................................................... 101

5.7 Project Schedule ......................................................................................................................... 102

5.6.1 Manpower ................................................................................................................................ 102

5.6.2 Implementation schedule: ........................................................................................................ 102

5.6.3 Engineering Surveys: ................................................................................................................. 103

6 ADDITIONAL STUDIES ...................................................................................................... 104

6.1 Risk Assessment: ........................................................................................................................ 104

6.2 Disaster Management Plan: ....................................................................................................... 104

7 PROJECT BENEFITS ........................................................................................................... 105

8 CONCLUSION ................................................................................................................... 106

List of Tables

Table 0-2: CRZ Locations within the project site ............................................................................................ 9

Table 0-3: Petroleum Products and their storage capacity .......................................................................... 10

Table 0-4: Land Use Breakup ........................................................................................................................ 11

Table 0-5 Raw materials Storage facilities ................................................................................................... 11

Table 2-1 Salient Features of the project area ............................................................................................. 21

Table 2-2 CRZ zones within the Project Site ................................................................................................. 22

Table 2-4 Details of Storage Facility proposed ............................................................................................. 24

Table 2-5 D.G Set Details .............................................................................................................................. 28

Table 2-7 Solid waste generation ................................................................................................................. 29

Table 2-8 Land-use Break up ........................................................................................................................ 30

Table 2-9 Civil Construction .......................................................................................................................... 34

Table 2-10 Details of Structural Buildings .................................................................................................... 34

Table 3-1 land use ........................................................................................................................................ 39

Table 3-2 Air Quality in and around the Project Site .................................................................................... 43

Table 3-3 Micrometerology .......................................................................................................................... 45

Table 3-5 Ambient Noise Standards ............................................................................................................. 48

Table 3-6 Test methods used for analysis of water quality .......................................................................... 53

Table 3-7 Water Quality in Project Site ........................................................................................................ 55

Table 3-8 Physical and Chemical Characteristics of Soil in the Study Area .................................................. 58

Table 3-9 List of Domestic Fauna in the Study Area ..................................................................................... 60

Table 3-10 List of Wild Fauna in the Study Area .......................................................................................... 61

Table 3-11 List of amphibians ....................................................................................................................... 62

Table 3-12 List of Zooplankton identified within the Study Area................................................................. 65

Table 3-13 Demographic Detail .................................................................................................................... 67

Table 3-14 Crop Details ................................................................................................................................ 68

Table 3-15 Fisheries profile of the district;- ................................................................................................. 69

Page 5: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

5

Table 3-16 Education Details ........................................................................................................................ 70

Table 3-17 Hospital Details ........................................................................................................................... 70

Table 3-18 Worker profile details ................................................................................................................. 72

Table 4-2Predicted GLC for proposed stack ................................................................................................. 88

Table 5-1 Plant Details .................................................................................................................................. 92

List of Figures

Figure 2-1 Layout showing CRZ Zone within the site ................................................................................... 23

Figure 2-2 Process Flow Chart ...................................................................................................................... 26

Figure 2-4 Fire Safety Provision .................................................................................................................... 33

Figure 3-1 Proposed Site .............................................................................................................................. 36

Figure 3-2 Site photographs ......................................................................................................................... 37

Figure 3-3 Geomorphology of the project site ............................................................................................. 39

Figure 3-4 10 km Radius map ....................................................................................................................... 41

Figure 3-5 Meteorological observations ...................................................................................................... 46

Figure 3-6 Hydro geological map of Thiruvallur district ............................................................................... 51

Figure 3-7Ground water sampling location .................................................................................................. 54

Figure 3-8 Soil sampling location .................................................................................................................. 57

Figure 4-1 Maximum incremental value for SOX ......................................................................................... 85

Figure 4-2 Zoomed Image of SOX Incremental value ................................................................................... 86

Figure 4-3 Maximum incremental value for NOX ......................................................................................... 86

Figure 4-4 Zoomed Image of NOX Incremental value ................................................................................... 87

Figure 4-5 Maximum Incremental value for PM .......................................................................................... 87

Figure 4-6 Zoomed Image of PM Incremental value .................................................................................... 88

Figure 5-1 Sluice work of Ilanthaikulam kanmoi, Vaddaku Aavarangadu - Before & After ......................... 96

Page 6: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

6

EXECUTIVE SUMMARY

1. Introduction

Bharat Petroleum Corporation Limited (BPCL) is an Indian state-controlled oil and gas company

headquartered in Mumbai, Maharashtra. BPCL has been ranked 225th in the Fortune Global 500

rankings of the world's biggest corporations for the year 2012. BPCL, with an equity base of

Rs. 723.08 Crore, is a leading player in the Petroleum Sector in the country. BPCL currently has

Refineries at Mumbai and Kochi with a capacity of 12 Million Metric Tonnes per Annum

(MMTPA) and 9.5 MMTPA respectively for refining crude oil. BPC's subsidiary at Numaligarh

has a capacity of 3 MMTPA. Also, Bharat Oman Refineries Ltd. (BORL) a joint venture of BPCL, a

state-of-art, grass root refinery with a capacity of 6 MMTPA at Bina, Dist. Sagar, Madhya

Pradesh is also a part of BPCL. This Refinery is on stream and completely operational from 2011

1.1. Project Details

Bharat Petroleum Corporation Limited (BPCL), Ennore Installation will be one of the major Oil

installations in the country for feeding the important market of Chennai city; Revenue districts

of Chennai Urban and Chennai Rural and some districts of Tamilnadu incl. Pondichery. Ennore

Installation will be feeding approximately 182 Retail outlets, 84 Industrial Customers and 1

Aviation Filling Stations.

Ennore Installation will get its inputs through ocean tanker from Mumbai and KR refinery at

ETTPL jetty and the product shall be transferred from jetty to HPCL exchange pit through

existing HPCL pipeline. From HPCL exchange pit, two nos pipeline will be laid to BPCL exchange

pit for receipt into BPCL storage tanks.

The total Petroleum storage tankage capacity will be 1,17,035 KL.

Product will be dispatched to retail customers through tank Lorries.

ES-1 Salient features of the project Site:

Page 7: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

7

S.No Particulars Details

1. Project Bharat Petroleum Corpn. Ltd/. Ennore

Installation (construction of new

petroleum storage installation)

2. Geographical Location Village : Vallur & Athipattu

Taluk : Ponneri

Metro : North Chennai city

District: Thiruvallur

State: Tamil Nadu

3. Project Cost Rs. 369 crores

4. Power Requirement 600 KVA (approx)

DG Capacity Proposed: 1x500 & 1x250 KVA

5. Project land area 100 acres

6. Land use Special and Hazardous Industrial Use Zone

7. CRZ Classification of area Zone IA, Zone IB, Zone III

8. Nearest Railway Station Chennai central-17.59 Km

Ennore -2.94 Km East

9. Nearest Airport Chennai Meenambakkam Airport - 30 km

in south west direction

10. Nearest habitation Attipattu Pudu Nagar -2.94Km

11. Densely populated area Attipattu Pudu Nagar -2.94Km

Page 8: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

8

12. Inland water bodies Ennore Creek – 1.45 Km

Lake in Jayalalitha Nagar – 3.1 Km

Kadapakkam Panchayath Lake- 6.96Km

Periyathopu Lake-9.46 Km

13. Source of water supply CPCL Desalination Plant through HPCL

Existing Line

14. Highway SH 56, SH 104 road- Adjacent to site

15. Sea port Chennai port – 17.75 Km South East

Ennore Port – 3.17 Km North East

16. Forest/Wildlife Sanctuary Nil within 10Km radius

17. Industries around the project area North Chennai Thermal Power Plant, HPCL,

NTPC – Tamilnadu Energy Company

Limited, Indian Additives Limited

1.2. Scope and Methodology of the Study.

The EIA process structure is composed of the following stages:

1) Study of project information

2) Screening & Scoping

3) Environmental Pre-feasibility study & Application for Approval of TOR

4) Preparation of Detailed Project Management Plan/Report

5) Baseline Data Collection

6) Impact Identification, Prediction & Evaluation

7) Mitigation measures & Delineation of EMP

Page 9: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

9

8) Risk assessment and Safety & Disaster Management Plan

9) Review & Finalization of EIA Report

10) Submission of EIA Report for implementation of Mitigation Measures & EMP as well as

necessary clearances from relevant Authority.

1.3. Type of Project

Ennore Installation comes under Isolated storage & handling of hazardous chemicals (As

per threshold planning quantity indicated in column 3 of Schedule2 & 3 of MSIHC Rules

1989 amended 2000) which is categorized under category 6(b). However, SEIAA after

issuing TOR transferred the project to MOEF&CC citing that receipt terminal is integrated

facility with the pipeline and as the installation is receiving the product through pipeline,

Project shall be treated as category A . The report is in accordance to the Terms of

Reference (TORs) given for Environmental Clearance application.

2. Project Description

2.1 Location

The proposed project, Ennore Installation of Bharat Petroleum Corp. Ltd is 80°20’E and

13°15’N located in Survey No: 1556 B Vallur village and 354/1 Athipattu village, Ponneri

Taluk, Thiruvallur District, Tamilnadu. State highways number SH 56 passes by the site.

The total area of the project site is 100 acres. It is located in north of Chennai City. It is

25 kms away from the Chennai city.

The following project falls in CRZ area. The following table shows the construction falling

in the CRZ area:

ES-2 CRZ Locations within the project site

S.No CRZ Area Constructions

1. CRZ – 1A No constructions comes under this area

2. CRZ – 1B No constructions comes under this area

3. CRZ III a) Tank lorry parking area b) Roads

Page 10: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

10

c) ETP

2.2 Storage Terminal:

It is intended to store and dispatch of petroleum products and the receipt of these

products will be through Ocean tankers from Mumbai and KR refinery (text to be

incerted) and products will be dispatched to retail customers through tank lorries.

ES-3 Petroleum Products and their storage capacity

S.No Product Proposed

1 MS (Motor Spirit) 56620 KL

2 HSD (High Speed Diesel) 60115 KL

3 ETHANOL 200 KL

3 SLOP ( MIXED PRODUCTS) 100 KL

TOTAL 117035 KL

2.3 Justification of The Project

1. A Terminal in tune with company’s vision of safe and environment friendly operations.

2. The shifting of terminal from Tondiarpet shall facilitate shifting of the 200 trucks

attached to this location from the heart of city to Ennore which is outside the city limits.

This shall reduce the traffic congestion caused by these vehicular movements in the

North Chennai area. Increased storage capacity to meet the increasing market demand.

3. Tondiarpet Installation was put up way back in 1929 in a total area of 40 acres. Around

11 lakhs KL of product handled per annum of MS / HSD / SKO/ATF/ FO / LDO / MTO etc.

4. Tondiarpet Installation have been catering to the need of 6 Revenue Districts of Tamil

Nadu and Union Territory of Pondicherry.

Page 11: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

11

5. The product movement to Tondiarpet is mainly through 5 Pipelines from CPCL

6. Over a period of time, the area has become thickly populated and no space is available

inside the Installation for further expansion.

7. BPCL , as per the long term plan has been looking for land for shifting of operations from

Tondiarpet.

8. This terminal would make BPCL Self reliant in feeding critical demand of Chennai &

nearby markets .

2.4 Land Requirements

ES-4 Land Use Breakup

Sl.

No.

Particulars Area

(m2)

Area in Acres

1 Utilised area 275186 68

2 Total CRZ area 84984 21

3 Green Area ( incl 12 acres

of CRZ area)

84984 21

4 Open area 44515 11

2.5 Raw materials Storage Facilities:

ES-5 Raw materials Storage facilities

Tank

No.

Tank

Dia(m)

Tank

Ht( m) Nature of Tank Product

Total

Capacity

(KL)

safe

Capacity

(KL)

Classification

Page 12: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

12

Tank

No.

Tank

Dia(m)

Tank

Ht( m) Nature of Tank Product

Total

Capacity

(KL)

safe

Capacity

(KL)

Classification

T1 40 16.80 A/G Fixed Roof BS 4 HSD 20000 19400 Class – B

T2 40 16.80 A/G Fixed Roof BS 3 HSD 20000 19400 Class – B

T3 40 16.80 A/G Fixed Roof BS 3 HSD 20000 19400 Class – B

T4 38 16.80 A/G Floating Roof BS 4 MS 18840 16950 Class – A

T5 38 16.80 A/G Floating Roof BS 4 MS 18840 16950 Class – A

T6 38 16.80 A/G Floating Roof BS 3 MS 18840 16950 Class – A

T7 3.20 14.10 U/G Horizontal MS 100 100 Class – A

T8 3.20 14.10 U/G Horizontal HSD 100 100 Class – B

T9 3.20 14.10 U/G Horizontal SLOP 100 100 Class – A

T10 2.00 5.00 U/G Horizontal HSD 15 15 Class – B

T11 3.20 14.10 A/G Horizontal ETHANOL 100 100 Class – A

T12 3.20 14.10 A/G Horizontal ETHANOL 100 100 Class – A

Total 117035 109565

3. Description of The Environment

The baseline environmental study comprises of investigation of Air, Water, Soil and

Noise quality parameters and its results are discussed briefly.

3.1 Air and Meteorological Environment

Page 13: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

13

To achieve this objective, five ambient air quality stations are proposed within a radius of

10 km from the project site. The frequencies were computed on 00-24hrs corresponding

to study period as shown in subsequent sections. The hourly meteorological data of wind

speed, wind direction, temperature and solar radiation were recorded at the project site.

Parameters such as heavy metals, Gaseous pollutants and particulate matters are

analyzed and monitoring results are within the prescribed limits.

3.2 Noise Environment

The prevailing ambient noise levels at study area were monitored at five locations within

10km radius. The field observations during the study period indicate that the ambient

noise levels in the study area were well within the prescribed standards at all the

different noise zones prescribed by CPCB.

3.3 Water Environment

To assess the quality of water around the project site three sampling locations of surface

water and three locations for ground water were selected within 10km Radius of the site

for Physiochemical parameters, heavy metals, and biological parameters.

3.4 Soil Environment

Soil characteristics such as color, porosity, soil texture, aluminium, chromium, copper,

sodium, chlorides etc. were analyzed at five sampling locations within 10km radius of the

site.

3.5 Ecology

There is no Wild life sanctuaries/ National / Reserved forest within 10 Km radius of the

site and there is no rare/ endangered species in the project study area.

3.6 Socio-Economic Environment

Proposed change of product mix is to be taken up in existing site with some

modifications and there will be no rehabilitation and resettlement.

4. Anticipated Environmental Impacts & Mitigation Measures

Page 14: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

14

The methodology adopted for carrying out the Environmental Impact Assessment for the

proposed Project has been based on the Guidelines issued by Ministry of Environment &

Forests (MoEF). An effective environmental impact assessment calls for establishing

sufficient background data on various environmental components through

reconnaissance survey, sampling and available literature sources etc. The proposed

project will have impacts on the environment in two distinct phases. During the

construction phase which may be regarded as temporary or short-term; the other during

the operation stage, which will have long term effects.

A careful examination of each of these activities with respect to the environmental

components establishes a “Cause and Effect” relationship between the activity and

environmental parameters.

The potential Environmental Impacts on Air, water, Soil, Hydrology, Flora and Fauna are

all studied carefully and the necessary mitigation measures were all proposed.

5. Environmental Management Plan

The Environmental Management Plan during construction and operation phase is

discussed to ensure the environmental protection around the project area.

EMP has been prepared addressing the issues like:

Mitigatory measures for abatement of the undesirable impacts caused during the

construction and operation stage.

Details of management plans (Greenbelt development plan, Solid waste

management plan etc.).

Institutional set up identified & recommended for implementation of the EMP.

Post project environmental monitoring programme to be undertaken after

commissioning of the project.

Expenditures for environmental protection measures.

Moreover, the recommendations for Disaster Management Plan, Occupational Health

and Safety Plan, fire and explosion controls, greenbelt development and rain water

Page 15: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

15

harvesting system and energy conservation schemes should be considered and

implemented in the project.

6. Risk Assessment

Predicting and evaluating risk to take appropriate preventive measures during the

operation phase.

• The methodology and approach for the studies are based on Indian Standards IS

15656:2006 HAZARD IDENTIFICATION & RISK ANALYSIS – CODE OF PRACTICE.

• Risk analysis tools used in the assessment include PHA – Process Hazard Analysis,

consequence and frequency analyses.

• The onsite storage units consist of underground & above ground tanks. The total

petroleum storage tankage capacity will be 1,17,035 KL.

• As the activities involve flammable materials and are classified as hazardous, risk analysis

studies were conducted to assess the degree of risk.

• The Study has assessed the site for potential to initiate and propagate an unintentional

event or sequence of events that can lead to an incident and / or an emergency situation

within the installation.

• The risk zones will be mainly within the plant site and will not have any effect on the

persons outside the plant.

• The maximum individual risk at manned location in the installation was assessed and

found to range between 10 -10/Yr to 10-11/Yr.

Also, additional safety measures are recommended for the same.

Emergency management plan, policies and principles for safety aspects of the employees

is given which are to be strictly followed by management and employees.

7. Conclusion:

Due to the proposed Oil storage Terminal the impact on environment will be minimum

and can be further reduced by implementing various mitigating measures and regular

monitoring programs.

Page 16: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

16

The proposed Oil Storage Terminal will serve as a southern hub and have beneficial

impacts in terms of supply of petroleum products in the region with incidental benefits

like employment opportunities both in the construction stage and operation stage. Also

the modernized installation will facilitate greater level of operating safety.

BPCL has a successful track record of implementing various EMP’s & DMP’s in their

existing recently constructed installations.

Due to the proposed project the socio economic activities will be developed in and

around the project area.

As zero discharge Effluent Treatment Plant is envisaged and the impact on water

environment will be minimum. Various conservatory measures are proposed to be taken

for minimizing water consumption.

Tank bottom sludge Management and its action Plan

Proper disposal method such as Bio-remediation or disposal through authorised vendor

as per directives of TNPCB have been planned to carried out for disposal of solid waste

generated from the periodic cleaning of the tanks (once in 5 years) Hence the project is

recommended by the consultant.

Page 17: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

17

1 INTRODUCTION

1.1 PROJECT PROPONENT

Bharat Petroleum Corporation Limited (BPCL) is an Indian state-controlled oil and gas company

headquartered in Mumbai, Maharashtra. BPCL has been ranked 225th in the Fortune Global 500

rankings of the world's biggest corporations for the year 2012.

BPCL, with an equity base of Rs. 723.08 Crore, is a leading player in the Petroleum Sector in the

country. BPCL currently has Refineries at Mumbai and Kochi with a capacity of 12 Million Metric

Tonnes per Annum (MMTPA) and 9.5 MMTPA respectively for refining crude oil. BPC's

subsidiary at Numaligarh has a capacity of 3 MMTPA.

Also, Bharat Oman Refineries Ltd. (BORL) a joint venture of BPCL, a state-of-art, grass root

refinery with a capacity of 6 MMTPA at Bina, Dist. Sagar, Madhya Pradesh is also a part of BPCL.

This Refinery is on stream and completely operational from 2011.

1.2 NEED OF THE PROJECT

Presently Tondiarpet Installation which was put up way back in 1929 in a total area of 40 acres.

This installation has been catering to the need of 6 revenue districts of Tamil Nadu and union

Territory of Pondicherry. Besides MS/HSD were also moved on stock transfer to Tada depot and

ATF to Coimbatore / Devangonthi by means of tank Lorries. The installation was handling

around 11 lakhs KL of product per annum of MS/HSD/SKO/ATF/FO/LDO etc., the product

movement to Tondiarpet was mainly through costal movement by 3 dock lines from Chennai

port and 5 pipelines from CPCL.

Over a period of time, the area has become thickly populated and no space is available inside

the installation for further expansion. BPCL in the long term plan has been looking for land from

early 2003 for shifting of operations from Tondiarpet. Currently dock lines have been cut and

are not in use as per the direction of Central Pollution Control Board (CPCB).

Page 18: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

18

The land measuring 100 acres from salt commissioner, Departmental of industrial Promotion &

Policy, Ministry of Commerce & Industry at Athipattu village, Ennore will be used for Storage

Terminal and it is enclosed in (Annexure – 23)

The project is important in view of the energy security of the nation and will also contribute to

the socio-economic development in that region.

The received petroleum products will be stored and dispatched to the Chennai urban and rural

via Tank Lorries and to the entire state of Tamil Nadu and some Northern some parts of Andhra

Pradesh through Tank Lorries.

1.3 BACK GROUND OF THE PROJECT

Bharat Petroleum Corporation Limited (BPCL), Ennore Installation will be one of the major Oil

installations in the country for feeding the important market of Chennai city; Revenue districts

of Chennai Urban and Chennai Rural and some districts of Tamil Nadu. Ennore Installation will

be feeding approximately 182 Retail outlets, 84 Industrial Customers and 1 Aviation Filling

Stations.

Ennore Installation will get its inputs through ocean tanker from Mumbai and KR refinery at

ETTPL jetty and the product shall be transferred from jetty to HPCL exchange pit through

existing HPCL pipeline. From HPCL exchange pit, two nos pipeline will be laid to BPCL exchange

pit for receipt into BPCL storage tanks. The total Petroleum storage capacity will be 1,17,035 KL.

The Product will be dispatched to retail customers through tank Lorries.

1.4 Project Objectives

Construction of 1,17,035 KL tankages along with associated facilities for receipt, storage

and dispatch of petroleum products

Provision of fire fighting, automation and allied facilities

Terminal shall cater to the needs of TN and UT of Pondicherry.

Page 19: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

19

1.5 Policy and Legal framework

The projected cost of the proposed new petroleum storage terminal project being Rs. 369

Crores, as per the provisions of the EIA notification, Environmental Clearance from Ministry of

Environment and Forest is required for this proposed project. As vide Environmental Impact

assessment Notification amended on September 14, 2006 as notified under the provisions of

the Environmental (Protection) Act, 1986, this project requires an Environmental Clearance from

the Ministry of Environment and Forests & Climate Change (MoEFCC).

1.6 Scope of the EIA Study

In order to assess the potential environmental impacts due to the proposed project M/s. Bharat

Petroleum Corporation Limited appointed M/s Hubert Enviro Care Systems Pvt Ltd, Chennai to

undertake Environmental Impact Assessment Study incorporating baseline data for various

environment components Viz. air, Meteorology, noise, water, land & biological data along with

socio-economic parameters of human interest, to assess the potential input & to prepare EMP

for mitigating/ minimizing adverse impact including Occupational health & safety, Disaster

management plan, Risk analysis, delineation of the post project Environmental Monitoring

program.

The major scope of the Environmental Impact Assessment study is listed below:

A detailed characterization of the existing environment within the area of 10 km radius from

the project site for environmental components viz. air, noise, water, soil, biological and

socioeconomic aspects.

A brief description of the project

Prediction and evaluation of positive and negative impacts that may result from proposed

project.

Delineation of environmental management plant to eliminate or minimize the adverse

impacts of the project on the surrounding environment.

To propose plans for post project monitoring

Page 20: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

20

Developing occupational health and safety as well as Disaster Management Plan to minimize

any accident or emergency situation.

To prepare an Environmental Management Plan (EMP) this includes the measures for

improving the eco profile of the study area as per the guidelines provided by the MoEF&CC.

To identify the risks involved in the project and to prepare a Risk Assessment and Disaster

Management Report.

The study provides the mitigatory measures and will be implemented during emergency

situations.

1.7 Organization of the Report

The basic objective of identification of impacts is to aid the proponents of the project to

upgrade the procedure for an effective environmental management plan, leading to an

improvement in environmental quality. This has been attempted by the following procedures:

Collection and analysis of baseline data for various environmental attributes;

Identification of Impacts;

Impact Assessment;

Evaluation of Impacts leading to preparation of Environmental management Plan;

and

Risk Assessment and Disaster Management Plan;

Page 21: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

21

2 PROJECT DESCRIPTION

2.1 PROJECT LOCATION

The proposed project, Ennore Installation of Bharat Petroleum is 80°20’E and 13°15’N located in

Survey No: 1556 B Vallur Village and 354/1 Athipattu Village, Ponneri Taluk, Thiruvallur District,

Tamil Nadu. State highway SH 56 passes by the site. The total area of the project site is 100

acres. Salient features of the project location are specified in the table given below. The

following project falls in CRZ area.

Table 2-1 Salient Features of the project area

S.No Particulars Details

1. Project Bharat Petroleum Corpn. Ltd/. Ennore Installation

(construction of new petroleum storage installation)

2. Geographical Location Village : Vallur & Athipattu

Taluk : Ponneri

Metro : North Chennai city

District: Thiruvallur

State: Tamil Nadu

3. Project Cost Rs. 369 crores

4. Power Requirement 600 KVA (Approx)

DG Capacity Proposed: 1x500 & 1x250 KVA

5. Project land area 100 acres

6. Land use Special and Hazardous Industrial Use Zone

7. CRZ Classification of area Zone IA, Zone IB, Zone III

8. Nearest Railway Station Chennai central-17.59 Km

Ennore -2.94 Km East

9. Nearest Airport Chennai Meenambakkam Airport - 30 km in south west

direction

10. Nearest habitation Attipattu Pudu Nagar -2.94Km

Page 22: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

22

11. Densely populated area Attipattu Pudu Nagar -2.94Km

12. Inland water bodies Ennore Creek – 1.45 Km

Lake in Jayalalitha Nagar – 3.1 Km

Kadapakkam Panchayath Lake- 6.96Km

Periyathopu Lake-9.46 Km

13. Source of water supply CPCL Desalination Plant through HPCL Existing Line

14. Highway SH 56, SH 104 road- Adjacent to site

15. Sea port Chennai port – 17.75 Km South East

Ennore Port – 3.17 Km North East

16. Forest/Wildlife Sanctuary Nil within 10Km radius

17. Industries around the

project area

North Chennai Thermal Power Plant, HPCL, NTPC –

Tamilnadu Energy Company Limited, Indian Additives

Limited

The following table shows the utility buildings that will be proposed in the CRZ zones:

Table 2-2 CRZ zones within the Project Site

S.No CRZ Area Constructions

1. CRZ – 1A No constructions comes under this area

2. CRZ – 1B No constructions comes under this area

3. CRZ III a) Tank lorry parking area

b) Roads

c) ETP

Page 23: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

23

Figure 2-1 Layout showing CRZ Zone within the site

2.2 PROJECT DESCRIPTION

It is intended to store and dispatch of petroleum products and the receipt of these products will

be through Ocean tankers from Mumbai and KR refinery at ETTPL jetty and the product shall be

transferred from jetty to HPCL exchange pit through existing HPCL pipeline. From HPCL

exchange pit, two nos pipeline will be laid to BPCL exchange pit for receipt into BPCL storage

tanks.and products will be dispatched to retail customers through tanker lorries.

The details of the proposed product storage capacity of installation for which EC is applied:

Table 2-3 Proposed Storage Facilities

S.No Products Proposed (KL)

Page 24: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

24

1 MS (Motor Spirit) 56620

2 HSD (High Speed Diesel) 60115

3 ETHANOL 200

4 SLOP ( MIXED PRODUCTS) 100

TOTAL 117035

Proposed Storage Tanks with product allocation at BPCL Ennore Installation.

Table 2-4 Details of Storage Facility proposed

Tank

No.

Tank Size ( Dia* Ht) in m

Nature Of Tank Product

Total

Capacity

(KL)

Classification

T1 40 * 16.80 A/G C R BS 4 HSD 20000 B

T2 40 * 16.80 A/G C R BS 3 HSD 20000 B

T3 40 * 16.80 A/G C R BS 3 HSD 20000 B

T4 38 * 16.80 A/G F R BS 4 MS 18840 A

T5 38 * 16.80 A/G F R BS 4 MS 18840 A

T6 38 * 16.80 A/G F R BS 3 MS 18840 A

T7 3.200 * 14.10 U/G Horizontal MS 100 A

T8 3.200 * 14.10 U/G Horizontal HSD 100 B

T9 3.200 * 14.10 U/G Horizontal SLOP 100 A

T10 2.0 * 5.0 U/G Horizontal HSD 15 B

T11 3.200 * 14.10 A/G Horizontal ETHANOL 100 A

T12 3.200 * 14.10 A/G Horizontal ETHANOL 100 A

Page 25: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

25

Tank

No.

Tank Size ( Dia* Ht) in m

Nature Of Tank Product

Total

Capacity

(KL)

Classification

Total 117035

2.3 Process Description

The project involves 3 steps

a) Receipt

b) Storage

c) Dispatch

Proposed Receipt: The products will be received to our installation through Ocean tanker via

HPCL pipeline. The existing pipelines from HPCL terminal are extended to BPCL terminal to

receive the products. The plant layout showing the entire pipeline facilities and the extension of

pipelines from HPCL is enclosed inAnnexure 2.

Storage: The storage tanks for 1,17,035 KL are used for storage of different products. The

details of tankers with sizes are detailed in Table 3.1.

Dispatch: The products received will be stored in respective tanks and will be dispatched to

retail outlets through tanker Lorries.

Page 26: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

26

Figure 2-2 Process Flow Chart

DESPATCH

DISPATCH OF PRODUCTS TO RETAIL OUTLETS THROUGH TANK LORRIES

STORAGE

Product transferred to tanks

(Above ground and underground)

Proposed: Tanks are proposed for storage of products

RECEIPT HSD and MS through ocean tanker via existing HPCL pipeline

Ethanol is received and transferred through tanker lorries

SLOP (mixture of oils) – Incase of accidental mixture of oils in pipelines. it will be considered as slop and it will be used for preparing lower

grade fuel

Quantity and Quality Checks

Quantity and Quality Checks

Page 27: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

27

2.4 Utilities Requirement & Source

2.4.1 Water

The requirement of water for the construction purpose will be supplied through authorized

suppliers.

Figure 2-3 Water Balance Chart

Water Supply - CPCL

Desalination Plant through HPCL existing

Line

Domestic water requirement is

10 m3/day

Sewage generated is 4.4 m3/day

Treated through STP (6 KLD) and Used for green belt

Effluent from Gantry washings & Rain water 50 m3/Hr

Treated through ETP (50 KL/Hr) for oil seperation and Used for Green belt / Flushing / Make up

/ Fire fighting

Page 28: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

28

2.4.2 Power

The total power requirement for the industry is about 600 kVA which is to be obtained from

TANGEDCO.

Further DG was proposed to serve as alternative sources of power supply to this unit in emergencies

during power failure.

Table 2-5 D.G Set Details

Project No. of DG

Sets

Capacity

Oil Storage Terminal 1 500 KVA

1 250 KVA

2.5 Project Cost

The investment required for the construction of proposed terminal has been estimated as Rs.369

Crores.

2.6 Air pollution Sources

The major air pollution sources from the industry are DG sets. These generator sets are provided

with stack of stipulated height as per consent of TNPCB which is adequate to disperse the gaseous

emissions of the resort to the surrounding environment.

The sources of air pollution, type of fuel used, fuel consumption and chimney height details are

indicated in the table below.

Page 29: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

29

Table 2-6 Air pollution sources, fuel consumption and chimney height details

Sl. no. Stack details Stack attached to

a. Physical details D.G set

Capacity Proposed: 1x500 & 1x250 kVA

Fuel quantity 90 l/hr & 45 l/hr

Fuel used HSD

Stack height 10 m, 9m AGL for each DG set

respectively

Control measures Acoustic enclosures are provided.

Emission Details

1 Sulphur dioxide 0.02078 g/s for 500 kVA

2 Suspended Particulate Matter

(SPM)

0.00113 g/s for 500 kVA

3 Oxides of Nitrogen 0.03397 g/s for 500 kVA

4 Carbon monoxide 0.29442 g/s for 500 kVA

2.7 Noise generation and its management

The major source of noise pollution in the industry is the DG set for which acoustic enclosure is

proposed. Also ambient noise levels will be ensured within the ambient standards by inbuilt design of

mechanical equipment and building apart from vegetation (tree plantations) along the periphery and

at various locations within the industry premises.

2.8 Solid waste generation and Management

The quantity of solid waste generated from the industry is calculated as follows

Table 2-7 Solid waste generation

Total no. of employees 100 ( incl. Unskilled labour

on contract basis)

Assuming per capita solid waste generation rate as 0.20 kg/capita/day

Page 30: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

30

Total no. of employees 100 ( incl. Unskilled labour

on contract basis)

Quantity of solid waste generated 24 kg/day

Organic solid waste : 60 % of the total waste 10 kg/day

Inorganic solid waste : 40 % of the total waste 09 kg/day

Disposal of domestic solid waste The domestic wastes are

segregated at source,

collected in bins and

composted.

2.9 Land Use Plan

The industry is designed envisaging adequate area for landscape, product storage, and internal

movement of vehicles as shown in the table below.

Table 2-8 Land-use Break up

Sl.

No.

Particulars Area

(m2)

Area in Acres

1 Utilised area 275186 68

2 Total CRZ area 84984 21

3 Green Area ( incl 12 acres

of CRZ area)

84984 21

4 Open area 44515 11

2.10 Assessment of Infrastructure Demand

M/s. Bharat Petroleum Corporation Limited has proposed to construct New Storage facilities for

Petroleum Products. The infrastructure demand for the project is detailed in the following sections

Page 31: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

31

2.9.1 Roadways

Roadways are required for transportation of Products and employees to & from the industry during

the operation phase. The existing state highway roads SH56, SH 104 will be used for connectivity.

2.9.2 Water supply & sewerage infrastructure

Water demand for the industry will be met from CPCL Desalination Plant through HPCL existing water

supply lines. The domestic sewage generated is treated in STP of 6 KLD.

2.11 Instrumentation & Control System

Terminal shall be fully automated with PLC systems, PD meters, batch controllers, tank measuring

gauges etc.

2.12 Telecommunication System

Landline connection from BSNL shall be taken and EPABX shall be provided for in plant calling.. VHF

sets shall be provided for communication.

2.13 Design and Safety System

The design standards and guidelines followed are enclosed in Annexure – 6.

OISD (Oil Industry Safety Directorate) STANDARD -118 and 244(LAYOUT)

OISD – 117 (FIRE FIGHTING)

PETROLEUM RULES

FACTORIES ACT – 1948

ELECTRICAL INSTALLATION UNDER ELECTRICITY RULES –1956

Earthing Pit as per IS 3043

Pressurized fire fighting network system with required capacity of Fire water storage and

pumping systems

Medium Velocity Sprinkler system

HVLR ( High velocity long range monitor)

Hydrants & Monitors

Provision of Fire Extinguisher and other equipments

Page 32: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

32

Hydro carbon detectors

MEFG ( Medium expansion foam generator) for Class A tank farm

Impervious dyke

Rim seal fire protection system ( RSFPS)

Complete automation for both tank farm and tank lorry loading.

1. Emergency Shut Down:

a) Shuts down all the plant Operations

b) Trips EB Power

c) Indication at Control panel

d) Opens the barrier gate

2. High level Switch in Tanks:

a) Closes inlet and outlet Remote operated solenoid valve ( ROSOV).

b) Shuts down all the Plant Operations

c) Trips EB Power

Indication at Control panel

Radar Gauge

Servo level guage

Temperature Transmitter

High Level Alarm

Pressure Transmitter

Sprinkler system

Foam system (check)

Rim seal fire protection system

The following fire protection facilities are envisaged at the terminal as per the requirements of OISD -

117. Enclosed in Annexure - 4

a. Fire water tanks

b. Fire water pumps

Page 33: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

33

c. Jockey Pumps

d. Pressurized hydrant system

e. Centralized foam system

f. Medium expansion foam generator for A class tank farm

g. Rim seal fire protection system

h. Hydrocarbon detectors

i. High velocity long range monitors

j. Remote operated Shut off valves

k. Impervious dyke

l. Pressurized fire fighting network system with required capacity of fire storage and pumping

systems.

m. Provision of fire extinguisher and other equipments

n. Medium Velocity Sprinkler systems

Figure 2-4 Fire Safety Provision

Page 34: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

34

2.14 Effluent Treatment Plant (ETP)

The Effluent treatment plant receives oily water through a separate drain line connecting tanks

farms, TT Gantry area, Pump house manifold area etc. The plant includes a Primary separation unit

consisting of a bar screen, Tilted Plate Interceptor and Belt type Oil Skimmer. Subsequently Effluent

will be pumped to Filtration unit using a multimedia filter and coalescing filter. The slop oil collected

will be pumped to the slop tank.

2.15 Civil Works

General

Major civil works for terminal consists of Tank foundations on piles, plant buildings, service building

units and includes RCC paved area, flexible internal roads, drainage system and compound walls.

RCC Buildings

The following units are RCC framed structure on concrete piles with RCC roof, covered with brick

work with necessary finishes incl. structural sheds. The concept of Green buildings will be adopted in

the design of main buildings

Table 2-9 Civil Construction

SLNO DESCRIPTION SIZE in Meters

1. Security Cabin 5*5

2. Planning room 5*15

3. Admin Block G +1 30*20

4. Control Room 30*20

5. QC LAB 20*10

Table 2-10 Details of Structural Buildings

SL.NO DESCRIPTION SIZE in Meters

1. Car/ Cycle shed 5*30

2. PCVO Crew Shelter 40*10

3. TLF Gantry 2Nos Each 8 Bays 6.5*15

Page 35: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

35

SL.NO DESCRIPTION SIZE in Meters

4. Calibration Tower With Water Tank 15*7.5

5. Inspection/Sealing Platform 1.5*7.5

6. Substation 40*20

7. Engg. Store 30*10

8. TLF Pump House 7.5*40

9. Fire water pump cum Air comp. 7.5*40

10. Tank Lorry Parking 16000 SQ M

11. Fire Water Tank (2Nos) 24.0M Dia * 15 HT

12. Under Ground Water Tank 5*5*2

13. ETP 30 * 20

2.16 Green Belt Development Plan

For maintaining the ecological balance, dust control and mitigate noise pollution, greenery is

proposed to be developed to the maximum extent as permitted by the lay out along the proposed

plant boundary and inside the plant. Green belt area will be developed in and around the project

area.

The green lawns and the water-bodies compliment the grace and symmetry of the buildings. The

nature of plantation comprises of trees, lawns, shrubs along the periphery of boundary wall , islands

and pathways.

Extensive plantation and landscaping is proposed to mitigate any impacts during this phase.

Development of a green belt in and around the building area is an effective way to check pollutants

and their dispersion into the surrounding areas. The degree of pollution attenuation by a greenbelt

depends on its height and width, foliage, surface area density, dry deposition velocity of the

pollutants and the average wind speed through the greenbelt.

The objectives of green belt management are:

To create a soothing environment for people to work

To mitigate vehicular emissions and noise pollution

Page 36: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

36

To cultivate culture of greenery within and outside the project site.

To maintain landscaping by optimal use of resources

Garden waste is accumulated in a designated area and shall be disposed accordingly.

3 BASELINE ENVIRONMENTAL SCENARIO

3.1 BASELINE DATA

The baseline environmental status with respect to various environmental components like air,

noise, water, land, flora and fauna and socioeconomic, being integral part of an EIA, forms the basis

for predicting/assessing the environmental impacts of the proposed project. Field monitoring at

site was performed for a period of one season from March 2015 to May 2015, representing the

Pre-monsoon season. Various environmental components were monitored and samples were

analyzed.

The Baseline data for Air, Water and soil has been carried out. The monitoring locations are located

within 10 kilometer radius of the site.

3.2 Study Area

Figure 3-1 Proposed Site

Page 37: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

37

Figure 3-2 Site photographs

3.3 LAND USE PLAN

Land use information of an area in the form of map and statistical data are very vital for spatial

analysis, planning, management and utilization of land for agriculture, forestry, urban and

Page 38: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

38

industrial planning. The level of spatial classification is classed under 4 categories. They are Level 1

with 1:1 million scale, Level 2 with 1:250,000 scale, Level 3 with 1:50,000 scale and level with

1:25,000 or larger scale. The cost and availability of data and purpose for which the land use

classification is to be taken up is important for taking up the level of classification. In the present

study Level 3 classification is made which is fairly a good classification of urban and industrial

planning. However, level 4 classifications is the ultimate for all kind of planning and management.

Owing to the exorbitant cost and time of obtaining the Satellite Data from the concerned agencies,

the present land use classification has been restricted to level 3

The land use of the study area reflects the socio-economic conditions of the people in addition to

the natural environmental factors. The factors controlling the land use pattern of the area are land

forms, slope, shape of the land, soil, natural resources and natural and man made hazards. In the

hills of the study area there is no dense vegetation. Vegetation consists of thorny bushes and

shrubs. The uncultivable area includes barren and non-cultivable waste.

The crop land occupies 45.47% percentage of the study area followed by Forest Plantation (19.31

%). Agricultural fallow occupies 19.31 % followed by Wetlands of 9.82%.

Page 39: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

39

Table 3-1 land use

LULC Class Area (Sq.Km)

LULC Class Area (Sq.Km)

Builtup,Urban 185.7

Builtup,Rural 100.5

Builtup,Mining 0.39

Agriculture,Crop land 1556.25

Agriculture,Plantation 81.62

Agriculture,Fallow 660.93

Forest,Evergreen/ Semi evergreen

22.26

Forest,Deciduous 66.76

Forest,Forest Plantation

15.57

Forest,Scrub Forest 16.96

Barren/unculturable/ Wastelands, Salt Affected land

18.41

Barren/unculturable/ Wastelands, Gullied/Ravinous Land

0.42

Barren/unculturable/ Wastelands, Scrub land

182.15

Barren/unculturable/ Wastelands, Sandy area

5.98

Wetlands/Water Bodies, Inland Wetland

0.32

Wetlands/Water Bodies, CoastalWetland

120.51

Wetlands/Water Bodies, River/Stream/canals

52.03

Wetlands/Water Bodies, Reservoir/Lakes/Ponds

336.12

Total 3423.00

3.4 GEOMORPHOLOGY:

Figure 3-3 Geomorphology of the project site

Proposed

Site

Page 40: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

40

3.5 BASELINE DATA

3.5.1 AIR ENVIRONMENT

Micro-meteorological factors have direct bearing on the dispersion and dilution of Pollutants/

contaminants discharged into the atmosphere with consequent impact on air environment. It

governs the concentration of pollutants and varies with time and location with respect to their

sources.

3.5.2 SAMPLING LOCATION AND RATIONALE

Micro-meteorological station was installed in the core zone area, with the objective of recording

wind direction and speed, temperature & humidity. The data thus collected from the station will be

representative of the prevailing micro - meteorological aspects of core and buffer zone.

Page 41: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

41

Figure 3-4 10 km Radius map

3.5.3 Wind Speed / Direction

Hourly data on wind speed and direction has been analyzed for 16 wind directions.

3.5.4 Methods of Collection of Ambient Air Parameter

The Hi-Volume samplers were placed at height of 2.5 mts above the ground level, free from

obstructions. Samples were collected for various parameters as listed above, at 24 hourly intervals

twice in a week for four weeks, thus totaling to eight days /location in a study period of one month.

The collected samples are shifted to HECS laboratory through standard chain of custody norms and

practices and they are analyzed according to the Standards prescribed by Indian Standards (IS).

3.5.5 Data Inference

All the Ambient Air quality monitoring is under the category of commercial and industrial zone. In

all the location the observed values of SPM, SOx, & NOX, are within the prescribed limits of TNPCB.

The following table consist of the all the data for ambient air quality of both HPCL and NCTP. The

detailed air quality data are given below. From these data it is clear that Manali Newtown has

Page 42: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

42

highest RPM, SPM, SOx and NOx. Minjur has highest RPM, Kattupalli has highest SPM, SOx and

Kattor has highest NOx concentration.

Page 43: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

43

Table 3-2 Air Quality in and around the Project Site

S.N

o

Place Parameters

Sulphu

r

Dioxid

e

Nitroge

n Oxide

Particulat

e Matter

Size Less

than 10

µm

Particulat

e Matter

Size Less

than 2.5

µm

Carbon

Monoxid

e

Lea

d

Ozon

e

Ammoni

a

Benzen

e

Benezo(a)pyren

e

Arseni

c

Nicke

l

1. BPCL

site

10.65 25.79 56.27 26.12 BDL BDL BDL 5.2 BDL BDL BDL BDL

2. Kattupall

i

11.09 30.09 61.56 27.36 BDL BDL BDL 4.3 BDL BDL BDL BDL

3. Sadayan

Kuppam

11.35 29.52 53.48 29.78 BDL BDL BDL 8.6 BDL BDL BDL BDL

4. Minjur 12.9 19 60 25 BDL BDL BDL 6.3 BDL BDL BDL BDL

5. Vichoor 13.2 23 56 30 BDL BDL BDL 6.3 BDL BDL BDL BDL

Page 44: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

44

6. Manali

New

town

13.8 20 51 21 BDL BDL BDL 8.6 BDL BDL BDL BDL

Page 45: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

45

3.6 Micro metrology

The study of micro-meteorological conditions of a particular region is of utmost importance to

understand the variations in ambient air quality status. The prevailing micrometeorology at project

site plays a crucial role in transport and dispersion of air pollutants released from the plant. The

persistence of the predominant wind direction and wind speed at the project site will decide the

direction and extent of the air pollution impact zone. The principal variables which affect the air

pollution dispersion and resultant air quality status micrometeorology are horizontal transport and

dispersion (average wind speed and directions), convective transport and vertical mixing

(atmospheric stability) and also topography of the area towards local influences.

For determining the prevailing micro-meteorological conditions during the study period, an

automatic continuous digital weather station was installed at project site. The location is chosen

such that there is no obstruction to the flow of wind and sunlight. The hourly meteorological data

of wind speed, wind direction, temperature and solar radiation were recorded at the project site.

These frequencies were computed on 8 hourly as well as 24 hourly basis and the corresponding

results are used to draw wind rose for 00-08hrs, 08-16 hrs, 16-24 hrs and 00-24hrs corresponding

to study period as shown in subsequent sections. The terrain is flat and elevation varied from 3-6 m

above mean sea level when one travels from coast and landward. The wind rose for the months of

March and April 2015 shows the predominant winds . The wind directions during the study period

are SW-W-WSW and SE. Accordingly, the impact zone will be spread in NE-E-ENE and NW

directions. The average wind speed observed during the study period is 3 m/sec with the

considerable frequency of a wind range of calm to about 22 km/hour. Due to its proximity with the

Bay of Bengal, the ambient temperature at project site ranged between 25-40°C while the relative

humidity range from 49-79% at project site. The meteorological data collected during monitoring is

used for interpretation of baseline status and to simulate the meteorological conditions for

prediction of impacts in modeling studies.

Table 3-3 Micrometerology

Page 46: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

46

S.No Parameter Observation

1 Wind Direction SW-SE-W-WSW

2 Wind Speed Range 2 to 8.8 m/sec

3 Average rainfall 1211 mm

4 Average Wind Speed 3 m/sec

5 Temperature Range Max. Temp: 40°C

Min. Temp: 25°C

6 Average Temperature 32°C

7 Humidity Range (24hr) 41% to 89 %

8 Cloud cover Partly cloudy

Figure 3-5 Meteorological observations

Page 47: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

47

3.7 Noise Environment

The study area consists of 10 km radius from the site which consists of urban, rural and industrial

area. The noise generated due to operation of individual process units at an industrial site cause

significant impacts on the surrounding environment including nearby residential areas. Such

operations fall in the category of continuous primary sources. There are also some secondary noise

sources associated with almost all types of large scale industrial projects, which are mainly vehicles

used for transportation of materials as well as employees and material handling equipment at the

project site. However, such sources could be categorized as intermittent noise sources.

The prevailing ambient noise level at a particular location is nothing but the resultant (total) of all

kinds of noise sources existing at various distances around that location. The ambient noise level at a

location varies continuously depending on the type of surrounding activities. The ambient noise level

generally does not reflect any seasonal variation, however, the wind direction, rain, snow, fog or any

other barrier as well as direction of source play significant role in regulating the noise propagation

and ultimately the intensity of impact.

The current status of noise environment around the existing industries is assessed through

identification of major noise sources, characterization of such noise sources, measurement of

prevailing ambient noise levels in the study area and measurement of noise levels due to vehicular

movements, according to existing land use pattern. The prevailing noise levels in the neighboring

industrial areas shall represent the baseline status for assessment of noise impacts from proposed

developments. The baseline study for noise environment has been carried out through

reconnaissance in the impact zone, identification of representative sampling locations and

monitoring of prevailing noise levels during study period.

3.7.1 Reconnaissance

Reconnaissance survey was conducted to locate the existing noise generating sources and identify

suitable locations to evaluate background noise levels. The project site is located in north coast of

Tamil Nadu in Thiruvallur district. The surrounding impact zone of 10 km radial distance consisting of

the rural, urban and industrial areas is marked. State highways number SH 56 passes by the site.

Page 48: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

48

Table 3-4 Ambient Noise Levels Recorded In The Study Area [dB(A)]

S.No Date Time Location Noise level in dB (A)

Day Night

1. 21.03.2015 12.30 BPCL Site 69 55

2. 21.03.2015 16.00 Kattupalli 72 60

3. 21.03.2015 17.00 Sadayan Kuppam 59 49

4. 21.03.2015 13.30 Minjur 50 40

5. 21.03.2015 15.00 Vichoor 57 47

Table 3-5 Ambient Noise Standards

Category of Area Noise Levels dB (A) eq

Day time* Night time

Residential Area 55 45

Since the project site is located in industrial zone there are many small scale and few large scale

industries which contribute to baseline noise levels. The heavy vehicular traffic on state highway SH

56 contributes significantly to the noise levels in study area. The commercial activities in the

individual villages also influence the background noise levels. The noise levels in surrounding selected

villages, industrial complexes and junction of the state highways were monitored using a precision

noise level meter.

3.7.2 Community noise levels

The community noise is determined by recording the day-night noise level (Ldn). Ldn is defined as the

24 hours equivalent sound level derived with a penalty of 10 dB (A) is added to the measured

instantaneous noise level measured during night time. i.e. from 2200 hrs to 0600 hrs. This is because

the same level of noise during night time is more annoying than day time. Ldn for a given location is

calculated from hourly equivalent sound levels (Leq) using the following equation:

Page 49: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

49

Ldn = 10 log [1/24{16(10(Ld/10)) + 8(10(Ln+10)/10))}]

Where, Ld – equivalent noise level during day time (0600 to 2200 hrs)

Ln – equivalent noise level during night time (2200 to 0600 hrs)

3.7.3 Baseline Noise status

The prevailing ambient noise levels along, the sites were monitored at 5 locations. During the study

period day time noise levels varied between50 to 72dB (A) across the sampling stations and night

time noise levels varied from40 to 60 dB (A) across the sampling stations. The details of the

monitoring stations are presented in Table 3-5. The field observations during the study period

indicate that the ambient noise levels in the study area were well within the prescribed standards at

all the different noise zones prescribed by CPCB.

Limits set by CPCB

Industrial Area: Day Time -75 dB (A); Night Time - 70 dB (A)

Commercial: Day Time -65 dB (A); Night Time - 55 dB (A)

Residential Area: Day Time -55 dB (A); Night Time -45 dB (A)

Silence Zone: Day Time -50 dB (A); Night Time - 40 dB (A)

3.8 WATER ENVIRONMENT

The study area has medium sized water courses namely Periyathoppu Lake, Korttalaiyar River etc.

The project site is located 3.16 Km west of the Bay of Bengal. The project site is located in Ennore,

Thiruvallur district.

3.8.1 Hydrogeology:

Hydrogeology in the district is underlain by both porous and fissured formations. . The important

aquifer systems in the district are constituted by

i) unconsolidated & semi-consolidated formations and

ii) weathered, fissured and fractured crystalline rocks.

Page 50: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

50

The porous formations in the district include sandstones and clays of Jurassic age (Upper Gondwana),

marine sediments of Cretaceous age, Sandstones of Tertiary age and Recent alluvial formations. As

the Gondwana formations are well-compacted and poorly jointed, the movement of ground water in

these formations is mostly restricted to shallow levels. Ground water occurs under phreatic to semi-

confined conditions in the inter-granular pore spaces in sands and sandstones and the bedding

planes and thin fractures in shales. In the area underlain by Cretaceous sediments, ground water

development is rather poor due to the rugged nature of the terrain and the poor quality of the

formation water. Quaternary formations comprising mainly sands, clays and gravels are confined to

major drainage courses in the district. The maximum thickness of alluvium is 30.0 m. whereas the

average thickness is about 15.0 m. Ground water occurs under phreatic to semi-confined conditions

in these formations and is being developed by means of dug wells and filter points. Alluvium, which

forms a good aquifer system along the Araniyar and Korattalaiyar river bed which is one of the major

sources of water supply to urban areas of Chennai city and also to the industrial units. Ground water

generally occurs under phreatic conditions in the weathered mantle and under semi-confined

conditions in the fissured and fractured zones at deeper levels. The thickness of weathered zone in

the district is in the range of 2 to 12 m. The depth of the wells ranged from 8.00 to 15.00 m bgl. The

yield of large diameter wells tapping the weathered mantle of crystalline rocks ranges from 100 to

500 lpm and are able to sustain pumping for 2 to 6 hours per day. The yield of bore wells drilled

down to a depth of 50 to 60 m ranges from 20 to 400 lpm. The yield of successful bore wells drilled

down to a depth of 150 m bgl during the ground water exploration programme of Central Ground

Water Board ranged from 1.2 to 7.6 lpm.

Page 51: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

51

Figure 3-6 Hydro geological map of Thiruvallur district

Page 52: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

52

3.8.2 Reconnaissance

Reconnaissance survey was undertaken to ascertain the location of water bodies viz streams, rivers,

lakes etc. The sampling stations were chosen based on the existing pollution sources near these

water bodies and threat of pollution in the future. The flow in the rivers passing through the study

region are seasonal, high flows occur during monsoon season and low flow occurs during summer

season.

The region receives rainfall predominantly during monsoon season with an average annual rainfall of

about 1211 mm per year. The South west monsoon season is from July – September and North east

monsoon is from October to December. Groundwater is the principal source for domestic and

drinking purposes in almost all villages near the study area. The water samples were collected and

analyzed by standard test methods which are given in table: The prevailing status of water quality

has been assessed during March - May. Three sampling stations for ground water and seven

sampling stations for surface water were selected for the study the details are given the findings of

the water quality monitoring study is summarized in Table 3-8.

Page 53: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

53

Table 3-6 Test methods used for analysis of water quality

S.No Parameter Measured Test Method

1. pH (at 25°C) IS:3025 (Part - 11): 1983 (Reaff: 2006)

2. Electrical Conductivity IS:3025 (Part - 14): 1983 (Reaff: 2006)

3. Color IS:3025 (Part- 4) 1983 (Reaff 2006)

4. Total Hardness as CaCO3 IS:3025 (Part - 21) 1983 (Reaff 2006)

5. Total Alkalinity as CaCO3 IS:3025,1 (Part - 23) 1986 (Reaff 2009)

6. Cadmium IS:3025 (Part 41) 1991

7. Chloride as Cl IS:3025 (Part - 32) 1988(Reaff 2009)

8. Total Dissolved Solids IS:3025:1(Part - 16) 1984 (Reaff 2006)

9. Aluminium as Al IS:3025 (Part - 55) 2003 (Reaff 2009)

10. Chromium as Cr IS:3025 (Part - 52) 2003 (Reaff 2009)

11. Lead as Pb IS:3025 (Part - 47) 1994 (Reaff 2009)

12. Zinc as Zn IS:3025 (Part - 49) 1994 (Reaff 2009)

13. Sodium as Na IS:3025,5(Part - 45) 1993 (Reaff 2006)

14. Temperature IS:3025 (Part - 9) 1983 (Reaff 2006)

15. Chemical oxygen demand as O2 IS:3025 (Part-58)-2006

16. Dissolved Oxygen (mg/l) IS:3025 (Part - 38)1989 (Reaff 2009)

17. Salinity -

18. Copper as Cu IS:3025 (Part - 42)1992 (Reaff: 2009)

19. BOD,5 days @200C as O2 5210B APHA22nd Edn 2012

20. Total coliform bacteria

(MPN/100ml) IS:1622 1981 (Reaff: 2009)

21. F-Coli IS:1622, 1981 (Reaff: 2009)

Page 54: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

54

3.8.2 Baseline Water quality Status

Physico-chemical parameters along with biological indicators of pollution have been identified for

assessing the baseline status of water environment and identification of impacts due to proposed

developmental activities. In order to assess the water quality, standard methods (IS Standards) were

followed for sample collection, preservation and analysis in the laboratory. The water quality was

assessed by various Physiochemical parameters such as pH, Electrical conductivity(µohms/cm),

Color(Hazen Unit), Total Hardness (mg/l), Aluminium(mg/l), Zinc (mg/l), Total Alkalinity (mg/l),

Chloride (mg/l),Cadmium (mg/l), Total Dissolved Solids (mg/l), Sodium (mg/l), Lead(mg/l), Chromium

(mg/l), copper (mg/l) and chemical Oxygen Demand (mg/l).

Figure 3-7Ground water sampling location

Page 55: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

55

Table 3-7 Water Quality in Project Site

S. No. Parameters Unit SW1 BPCL

SW2 Ennore Creek water

Kattupalli

SW1 IAL

Sadayan Kuppam

sw 3 IAL

Minjur

sw 2

Kattupalli

gw1

Sadayan Kuppam

gw 2

Manali New Town

gw 3

1 Colour Hazen

Colourless Colourless Colourless Colourless Colourless Colourless Colourless Colourless

2 Odour - Odurless Odurless Odurless Odurless Odurless Odurless Odurless Odurless

3 Turbidity NTU 3 5 BDL 4 2 BDL BDL BDL

4 pH -- 7.09 7.89 7.81 8.03 8.22 6.93 7.57 6.89

5 Conductivity µS/cm 39900 49500 1990 50200 75440 12500 4860 4410

6 Total Dissolve Solids mg/l 33117 37198 1353 39666 59598 9250 3207.6 2998.8

9 Alkalinity as CaCO3 mg/l 215 390 185 130 2150 270 110 240

10 Total Hardness as CaCo3 mg/l 8094 6941 496 7407 1512 1650 1298 1075

11 Calcium as Ca mg/l 341 365 56 405 65 281 281 244

12 Magnesium as Mg mg/l 1760 1465 87 1554 328 230 145 113

13 Chloride as Cl mg/l 15094 19300 416 19795 35137 3450 713 891

14 Sulphate as SO4 mg/l 2167 3472 203 2705 2078 1653 1617 853

15 Carbonate mg/l 0 0 0 0 0 0 0 0

16 Bi carbonate mg/l 262 476 226 159 2623 329 134 293

17 Nitrate as NO3 mg/l 1.46 1.45 2.56 2.89 1.33 1.42 2.87 2.65

18 Fluorides as F mg/l 0.045 0.144 0.065 0.047 0.056 0.234 0.145 0.177

19 Sodium mg/l 8720 11350 260 10800 21000 2345 452 516

20 Potassium mg/l 575 770 22 780 22 56.2 28.5 24.6

21 Cadmium mg/l BDL (DL

0.01) BDL (DL

0.01) BDL (DL

0.01) BDL (DL

0.01) BDL (DL

0.01) BDL (DL

0.01) BDL (DL

0.01) BDL (DL

0.01)

Page 56: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

56

S. No. Parameters Unit SW1 BPCL

SW2 Ennore Creek water

Kattupalli

SW1 IAL

Sadayan Kuppam

sw 3 IAL

Minjur

sw 2

Kattupalli

gw1

Sadayan Kuppam

gw 2

Manali New Town

gw 3

22 Chromium, Total mg/l

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

23 Copper mg/l

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

24 Iron mg/l 0.237 0.346 0.218 0.339 0.26 0.436 0.276 0.339

25 Lead mg/l

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

Manganese mg/l

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

Nickel mg/l

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

BDL (DL 0.01)

26 Zinc mg/l 0.231 0.383 0.154 0.567 0.346 0.452 0.986 0.578

27 Dissolved Oxygen mg/l 6.2 6.4 6.4 6.7 6.3 NA NA NA

28 COD mg/l 5.3 5.2 6.3 4 5.9 BDL (DL 2.0) BDL (DL 2.0) BDL (DL 2.0)

29 BOD mg/l 3.5 2.6 2.9 2.6 2.2 BDL (DL 1.0) BDL (DL 1.0) BDL (DL 1.0)

NA - Not Applicable

Page 57: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

57

3.9 SOIL ENVIRONMENT

Assessment of soil characteristics is of paramount importance since the vegetation growth,

agricultural practices and production is directly related to the soil fertility and quality. The

predominant soil type is Brown soil followed by alluvial and sandy soils in the coastal areas. The pH

of the soil samples ranged from 7.3 to 7.54 across the sampling stations. The Electrical conductivity

of the soil samples ranged from 126 to 756 µohms/cm across the sampling stations.. The texture of

sandy soil varied from 52 to 71.5 % across both the industries. The highest percentage of sandy soil

for is 71.5% was recorded. The highest percentage of sandy soil is 70.3% was recorded. The

concentration of total phosphorus ranged from 0.21 to 0.38 %. Other parameters like cadmium

(mg/l), Chromium (mg/l), were below the detection limit.

Figure 3-8 Soil sampling location

Page 58: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

58

Table 3-8 Physical and Chemical Characteristics of Soil in the Study Area

S.No. Parameter Units BPCL

Kattupalli

Sadayan

Kuppam Minjur

Vichoor

1 Colour Dark

brown Light

brown dark

brown dark

brown Brown

2 Soil Texture claye silt sandy loam

sandy loam

claye loam

sandy loam

3 Sand % 13 26 19 15 28

4 Silt % 24 26 28 28 22

5 Clay % 63 48 53 57 50

6 Total 100 100 100 100 100

7 pH 7.54 7.51 5.72 7.35 7.3

8 Electrical conductivity umhos/cm 756 126 172 331 175

9 Infiltration Rate cm/hr 1.11 1.46 1.25 1.36 1.28

10 Bulk Density gm/cc 1.36 1.24 1.15 1.48 1.65

11 Cation Exchange Capacity

meq/100 gm 19.86 16.2 16.5 32.2 10.8

12 Moisture content % 19.43 1.14 0.655 16.35 0.45

13 Organic Carbon % 0.432 0.299 0.713 0.428 0.237

14 Organic matter % 0.745 0.516 1.229 0.738 0.409

15 Nitrogen as N % 0.062 0.047 0.098 0.052 0.027

17 Phosphorus % 0.03 0.02 0.04 0.02 0.01

18 Potash % 0.20 0.16 0.28 0.18 0.06

19 Calcium % 0.28 0.62 0.57 0.39 0.52

20 Magnesium % 0.58 0.63 0.58 0.73 0.66

21 Cadmium mg/kg 0.79 0.78 0.48 0.79 0.78

22 Copper mg/kg 9.23 4.46 6.34 8.57 9.66

23 Chromium mg/kg 2.12 1.15 1.78 2.97 1.22

24 Iron mg/kg 467 298 244 476 294

25 Lead mg/kg 1.56 1.35 0.345 2.17 1.94

26 Manganese mg/kg 12.5 16.4 21.5 9.46 12.7

27 Zinc mg/kg 23.8 19.5 14.5 10.4 14.5

Page 59: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

59

3.10 ECOLOGY

3.11.1 Terrestrial Ecology

The study of terrestrial ecology within the study area of 10 km radius has been carried out

through field investigation and satellite imagery data as discussed earlier. The area can be

classified into the following ecological zone.

i. Scrub Eco-system (dry evergreen vegetation)

This type of ecosystem is dominated by Phoenix sylvestris species. Apart from typical scrub jungle

species, a few salt tolerant species were also recorded, probably because of the proximity to the

sea and the estuary.

ii. Tidal Eco-system

The plant growing in this area are salt tolerant as they are covered by the saline water during

high tides. The species like Arthrocnemum indicum, Suaeda Maritima are dominating species in

this ecosystem.

iii. Mangrove Eco-system

This type of ecosystem existed in western bank of the river Korattailar. This is dominated by

Avicinnia marine. Sesuvium Portulacastrum & Suaeda Maritima. These plants are periodically

washed by the tides and as result in some areas quick sands are noticed.

iv Marsh Eco-system

The marshes are essentially fresh water supporting variety of plant. Acacia nilotica and

Azadirachata indica are the common species of the study area.

v. Agro Ecosystem

Rice and banana species of plant are the main species of this ecosystem.

Page 60: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

60

vi. Flora

The field investigation and satellite imagery data show, that the study area is a mixture of

agricultural, wasteland and get irrigated by the tanks and tube wells.

The dry tropical vegetation is observed within the study area. The experimental finding of the pre

monsoon season shows the dominance of grasses like Cyanodon followed by Parthenium

hysterophorous, Croton sparsiflorus & Odina odiya and trees like Acacia nilotica, Azadirechta

indica, Anona squamosa, Delonix regia, Ficus benghalensis within the study area.

vii. Fauna

The domestic animals are mainly mammals. The domestic animals present in the study area are

listed in the Table – 3.14.1

viii. Wild Animal

Since the natural forests constitute negligible of the forest area and since they are in isolated

pockets, the wild life does not offer a wide spectrum of species. Wild animals are rarely seen due

to absence of natural dense forest and land occupied by human being. The wild animals like

Nilgai, Jackals, Fox and Rabbit have drastically reduced due to increase in human population and

clearance of wild flora for making residential and commercial land. Other than these, some

reptiles and amphibians can also be seen with a number of bird species.

A list of birds, reptiles, amphibians and rodents based on information gathered from local

inquiries is presented.

Table 3-9 List of Domestic Fauna in the Study Area

SI. No Botanical Name Comman Name

1 Azadiachta indica Veppam

2 Acacia nilotica Karuvelamaram

Page 61: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

61

SI. No Botanical Name Comman Name

3 Terminalia catappa Natvadom

4 Taraindus indica Amilampul

5 Mangifera indica Munga

6 Psidium guayava Koyya

7 Phoenix sylvestris Lcham

8 Ficus religiosa Arasu

9 Ficus benghalensis Mayarum

10 Delonix regia Mayaram

11 Citrus auvanlilum Narattai

12 Anthocephalus chinensis Vellai

13 Ziziphus mautifiana Elentha

14 Anona squamosa Atta

15 Alstonia scholaris Elilappalai

16 Bambusa arundinacia Mullumungil

17 Bauhinia varigata Shemmandarai

Table 3-10 List of Wild Fauna in the Study Area

Page 62: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

62

SI.No Zoological Name Comman Name

1 Canis aureus Jackal

2 Felis chaus Jungle cat

3 Funambulums pennanti and F palmarum Palm squirrels

4 Lepus nigricollis nigricollis Hare

5 Harpestes edwardsi Comman mongoose

6 Suscus sp Shrew

7 Manis crassicaudata Pangolin

8 Milvus migrans govinda Pariyakite

9 Haliastuf Indus Brahminy kite

10 Francolinus pondicerians Patridge

11 Eudynamys scolopacea Koel

12 Athene brahma Spotted owlet

13 Ptyas mucosus Comman rat snake

14 Naja naja Cobra

15 Ahaetulla nasutus Green whip snake

a. AMPHIBIAN

Table 3-11 List of amphibians

Page 63: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

63

1 Bufo malanostidus Toad

2 Rana cynophlyctis Frog

3 Rana tigrina Frog

4 Rhacophorus bimaculatus Tree frog

5 Hyla arborea Tree frog

b. RODENTS

1 Bandicota indica Badicoot

2 Mus muscatus Mouse

3 Rathucs rathus House

4 Ratufa indica Squirrel

3.10.2 Aquatic Ecology

The specific biological species (Fishes, Phytoplankton, Zooplankton etc.) for a particular

environmental conditions are the best indicators of environmental conditions are the best

indicators of environmental quality. Information on the environmental stress due to the impacts

of any industrial activities on the community structure serves as inexpensive and efficient early

warning and control system to check the effectiveness of the measures to prevent damage to a

particular ecosystem.

a. Planktons

Phytoplankton and Zooplankton are indicators of environmental stress. The quality and quality of

such biological species in a particular environmental largely depends on various physicochemical

characteristics of water such as pH, Conductivity, nutrients, BOD, alkalinity etc.,

Page 64: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

64

b. Fishes

The fishes/ aquatic fauna of the study area is reported based on the field sampling and confirmed

by the local people and secondary data provided by Thiruvallur district office is listed. The fishes

like Chirocenttrus, Lesser Sardines, Thriossocles, Anchoviella, Flying Fish, Sciaenids, Caranx,

Meckerel, Seer, Crabs found in good number in the study area.

Page 65: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

65

Table 3-12 List of Zooplankton identified within the Study Area

S.No Zooplankton

1 Favella species

2 Tintinnopsis species

3 Globigerina Species

4 Acartia donae

5 Acartia erythraca

6 Acartia clansi

7 Calanns finmarchicns

8 C furcatns

9 Paracalanus parvus

10 Microsetella norvegica

11 Microsetella rosea

12 Capilla Vitrea

13 Corycaeus danae

14 Oithona rigida

15 Oncacea venusta

16 Gastropod veliger

Page 66: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

66

17 Barochinnous Unceolaris

18 Barochinnous Candatns

19 Monostyla bulla

20 Nancocalanus minor

21 Paracalanus parvus

22 Labidocera acuta

23 Euterpina acutifrous

24 Microsetella norvegica

25 Microsetella gracilis

26 Metis jousseaumei

27 Copilia vitrea

28 Corycaeus danae

29 Oithona bervicornis

30 Oithona rigida

31 Oncacea venusta

32 Bivalve veliger

33 Gastropod veliger

34 Copepod nauplius

Page 67: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

67

3.11 Socio Economic Environment:

District Profile:

The district Thiruvallur is surrounded by Kancheepuram district in the South, Vellore district

in the West. Bay of Bengal in the East & Andhra Pradesh State in the North. The district spreads

over an area of about 3422 Sq. kms.

The district has four revenue divisions viz, Tiruvallur, Tiruttani and Ponnari and Ambattur.

There are 11 taluks in the district. There are 46 firkas and 820 revenue villages. Likewise, there

are 14 blocks, 5 Municipalities and 10 town Panchayats, which implement rural development

activities.

Demographic profile:

The district had the population of 3725697 as per 2011 census. It comprises of 1878559 of

the male population and 1847138 of the female population.

The total geographical area of the district is 3,42,243 hectares.

Table 3-13 Demographic Detail

Details Area Ha.

% Share to Total Area

Forests 19736 5.77

Barren and Unculturable Lands 13727 4.01

Land put to Non - Agricultural Uses

98729 28.85

Culturable Waste 8286 2.42

Permanent Pasture and other Grazing Lands

8142 2.38

Miscellaneous Tree Crops and Groves not included in the Net Area Sown

8280 2.42

Page 68: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

68

Current Fallow 13361 3.00

Other Fallow Lands 51813 15.14

Net Area Sown 120169 35.11

Social Indicators:

Population growth: 35.33%

Density/ sq.km: 1098

Sex ratio: 987

Average literacy: 84.03%

Female literacy: 78.32%

Urban population: 65.14%

Occupation:

The main occupation of the district is agriculture and allied activities.

The major crops grown in the district are rice, cumbu - ragi, green gram, black gram, sugar

cane and groundnut. Apart from this, certain horticultural crops like mango, guava and

vegetables have also been cultivated successfully. The following table shows the area of the

important crop cultivation for the year 2012-13 (area in Hectares)

Table 3-14 Crop Details

Paddy Total cereals Total pulses Total food

grains

Sugar cane Ground nut

78337 79069 8844 87913 7669 10232

Source: Department of Economics and Statistics, GoTN.

Page 69: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

69

Rivers like Kesathaliar, Aravar, Nandi, Kallar, Coovam and Buckhingham Canal are seasonal,

but there is no perennial river in the district. Since these seasonal rivers are not sufficient,

irrigation mainly done through tanks, tube wells and open wells .

Livestock:

The livestock in rural plays very important economic, social and cultural roles. Livestock

contributes on food supply, family nutrition, family income, asset savings, soil productivity,

livelihoods, transport, agricultural traction, agricultural diversification and sustainable

agricultural production, family and community employment, ritual purposes and social status.

The table shows the cattle population in the district as per Livestock Censes 2007.

Cattle Buffaloas Sheep Goat Poultry

324222 194532 92970 321462 1104539

Source: Department of Economics and Statistics, GoTN.

Fisheries

The total coastal area of the district is about 49803 ha and has a coast line of 80 kms for

marine fisheries. Prawn/shrimp culture is famous at the coast line of Gummidipoondi and Minjur.

The total fish production is to the tune of 11372 tonnes.

Table 3-15 Fisheries profile of the district;-

Landing centres Fisheries village Fishing family Fisheriers population

18 26 7544 28109 Source: Marine Fisheries Census 2010

Education:

The literacy has well connected with the growth rate of the economy, birth rate, death rate,

infant mortality rate (IMR). The district has good primary and secondary education infrastructure

in urban and rural areas.

Page 70: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

70

The literacy rate is 84% which is higher than same of Tamil nadu (80%) and of India(73%).

The literacy rate has been the major determinant of the rise or fall of the other indicators.

The accessibility of Primary and Upper Primary education is paramount importance for

increasing literacy rate as well as reducing the dropout rate. One of the main reason for the

falling dropout rate due to the distance to the schools is at minimal distance.

Table 3-16 Education Details

Type of school Total schools Rural Schools

Govt Private Govt Private

Primary 931 527 819 291

Primary+ Upper Primary 277 66 221 39

P+UP+Secondary+Higher secondary

7 330 3 139

UP only 2 0 2 0

UP+Sec+HS 237 52 182 21

Source: DISE report card 2013-14

Health care:

Primary Health Centers (PHCs) and Health Sub-centers (HSCs) are rendering the preventive,

curative and rehabilitative health care services to the rural people. The district has good number

of public health systems accessible and affordable apart from the existing private health

facilities.

Table 3-17 Hospital Details

Name of the District

Type of Hospital

Sub centers PHCs CHCs Sub Divisional

Hospital District

Hospital

Thiruvallur 303 42 14 13 1 Source: National Health Mission, as on March 31, 2015

Page 71: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

71

Industries: The district as highest number of Industrial estate in the state. The project is

already surrounded by Industries like Ashok leyland , North Chennai thermal power

station, NTPC thermal nadu energy company ltd, Ennore power station and Ennore port

etc

Government Industrial Estates:

o Sidco Industrial Estate, Ambattur o Sidco Industrial Estate, Tirumazhisai o Sidco Industrial Estate, Gummidipoondi o Sidco Industrial Estate, Kakkalur o Sidco Industrial Estate, R. K. Pet o Sidco Industrial Estate, Vichoor o Sidco Industrial Park, Thirumullaivoyal o Sipcot Industrial Complex, Gummidipoondi o TIIC Industrial Estate, Mogappair o Department Electrical Industrial Estate, Kakkalur o Talco Leather Industrial Estate, Madhavaram.

Private Industrial Estates

G.K. Industrial Estate, Porur M.M. Industrial Estate, Alapakkam Moccaram Industries,, Velappan Chavadi Nagappa Industrial Estate, Puzhal Ekambara Naicker Industrial Estate, Alapakkam.

Study area:

The study area comprises of mostly rural areas with some urbanized locations like Ennore,

Manali new town and Minjur.

The proposed project shall be in the villages of Athipattu and Vallur

Athipattu and Vallur:

Demographic details

Population : Athipattu Village: The village population is 11034 comprising 5623 male and 5411

female as per 2011 Census.

Page 72: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

72

Vallur: The village population is 11935 comprising 6089 male and 5846 female as per 2011

Census.

Social Indicators

a.Population:

Athipattu: 11034

Vallur: 11935

b.Female Population:

Athipattu: 5411 (49%)

Vallur: 5846 (49%)

c.SC population

Athipattu: 4505(40.82%)

Vallur: 7803(65%)

Workers profile: In each village, the main workers are around 80%, i.e. Those workers who had

worked for the major part of the reference period (i.e. 6 months or more) are termed as Main

Workers.

Table 3-18 Worker profile details

Village Name Mainworker

Mainworker

Marginal workers Cultivators Agri.labour

Household Industries

Other workers

Athipattu 83.42 0.29 0.21 2.38 97.12 16.58

Vallur 79.32 1.67 3.77 3.19 90.93 20.68 Source: India Census 2011

In the both villages, the percentage of other workers category is more due to proximity to

Chennai City and industries around the area. The other workers are include all government

servants, municipal employees, teachers, factory workers, plantation workers, those engaged in

trade, commerce, business, transport banking, mining, construction, political or social work.

The area is surrounded by many fishermen villages. There are 26 vllages/hamlets along the 80

km stretch of coastal line of the district. The village Thazhankuppam is nearby village has 702

Page 73: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

73

fishermen families of 2855 fishermen population.

There are many industries like NTPC, North Chennai Thermal power, EID Parry, Ashok

Leyland , HPCL etc. In the area. The reasons for the rapid industrization due to the locational

advantages like Port, National highways, Railway facilities, availability of semi skilled and un

skilled labour fource, closeness to Chennai city.

Housing:

Athipattu: The village has 73.4% houses in good condtion and 56.7% of the houses are with

concrete roof. 71.1% of the residents have own houses. Of the total houses only 69.5% have

toilets facilities.

The village only 66.9% of residents has access to treated water source. Most of the residents

(64.4%) use LPG as fuel. In case of family size, 34.6 % families have the family size of 4

memebers.

Vallur: The village has 64.3% houses in good condtion and 54.2% of the houses are with

concrete roof. 78.9% of the residents have own houses. Of the total houses only 50.2% have

toilets facilities.

The village only 70.7% of residents has access to treated water source. Most of the residents

(60.1%) use LPG as fuel. In case of family size, 34.8 % families have the family size of 4

memebers.

The Corporate Social Responsibility

The Corporate Social Responsibility commitments in respect of project area development will

be priority for the villages .

In the context of public sector enterprises Corporate Social Responsibility (CSR) should be viewed

as a way of conducting business, which enables the creation and distribution of wealth for the

betterment of its stakeholders, through the implementation and integration of ethical systems

and sustainable management practices.

Page 74: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

74

In the guidelines (Guidelines on Corporate Social Responsibility And Sustainability For Central

Public Sector Enterprises, (F.No.15(13)/2013-DPE(GM) dt 21.10.2014), has emphasized of CSR

and Sustainability is clearly on capacity building, empowerment of communities, inclusive socio-

economic growth, environment protection, promotion of green and energy efficient

technologies, development of backward regions, and upliftment of the marginalised and under-

privileged sections of the society. In their normal business activities, public sector companies

should try to conduct business in a manner that is beneficial to both, business and society. They

are prompted to use social responsibility and sustainability initiatives for business gains as well as

social value creation through adoption of “shared value” approach, wherever possible in their

routine business operations.

The Corporate Social Responsibility commitments in respect of project area development will be

priority for the villages .

1.Education: Providing infrastructure to Primary and Secondary schools by constructing new

building or rehabilitating the existing building, provisions of excellence award to the topppers,

strengthing the labs and libararies.

2. Health- Campaign for Health awareness and sanitation , contributing infrastructure and

equipments to Rural Health centres, Conducting health camp for Vaccination, Eye care, maternal

health.

3. Women empowerment by initiating SHG and Income Generation program like tailoring training

centre, development of algae/seaweeds culture, ornamental fish culture etc.

4. Social forestry and farm forestry, conducting tree plantation program, development and

maintenace of avenue plantation etc.

Conclusion:

Page 75: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

75

Due to the Industrilization and consequential urbanisation, the people expectations on

infrastructure developments, skill development and job opportunities as part of Corporate Social

responsibilities of up coming industries, sustainability of fishing are high. Any business

enterprises are expected to conduct their business activities and operations in socially

responsible and sustainable manner.

It is understood that BPCL being a Navaratna company and one of the fortune 500 companies

have a structured CSR department which carries out CSR activities Pan India basis as per the

Guidelines on Corporate Social Responsibility And Sustainability For Central Public Sector

Enterprises, (F.No.15(13)/2013-DPE(GM) dt 21.10.2014.

Page 76: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

76

Page 77: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

77

4 ANTICIPATED ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES

4.1 ENVIRONMENTAL IMPACTS

The methodology adopted for carrying out the Environmental Impact Assessment for the proposed

Project has been based on the Guidelines issued by Ministry of Environment & Forests (MoEF & CC).

An effective environmental impact assessment calls for establishing sufficient background data on

various environmental components through reconnaissance survey, sampling and available literature

sources etc. The proposed project will have impacts on the environment in two distinct phases.

During the construction phase which may be regarded as temporary or short-term; the other during

the operation stage, which will have long term effects.

The impact identification of each of the environmental parameters is the first step of assessment. In

order to identify the impact comprehensively, all the activities associated with the proposed project

during the construction as well as operational phase are identified and listed. A careful examination

of each of these activities with respect to the environmental components establishes a “Cause and

Effect” relationship between the activity and environmental parameters.

4.2 Activities during Construction Phase

During the construction phase, the following activities among many are considered to be important

towards creating environmental impacts:

a) Site preparation (fencing, boundary & clearing of site)

b) Excavation, backfilling and leveling

c) Hauling and dumping of earth materials & construction spoils

d) Foundation works

e) Fabrication erection of Steel structures such as, Tanks, Pipelines and Sheds.

f) Construction of internal roads, drains & water supply

g) Painting and finishing

Page 78: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

78

h) Clean up operations, landscaping and plantations

The activities can be divided into two categories, viz.

Sub-structural

Super-structural work.

Sub-structural construction work will involve cutting of trenches, excavation, concreting etc. All these

activities will give rise to dust pollution. The super-structural work will involve concrete & masonry

work etc. and will involve construction equipment like cranes, concrete mixers, hoists, welding sets

etc. There may be dust, gaseous and noise pollution from these activities. Concrete and masonry

works involve considerable amount of water, which generally induce certain impact on the local

water source.

Mechanical erection work involves extensive use of mechanical equipment for storage,

transportation, erection and on-site fabrication work. These activities generally produce some air

contaminants and noise pollution. On the other hand electrical work is less polluting- in general. The

main sources of pollution & impacts during construction phase are cutting of few trees, dust

generation, noise generation by construction equipment & traffic, inflow of construction labour,

sediment load in construction water, and generation of solid waste in the form of construction spoils.

4.3 Activities during Operational Phase

During the operation stage, there will not be any significant sources of pollution & impacts. The main

activity during operation is transfer of petroleum products (like MS & HSD) and spillage of such

products at certain intermediate points.

4.4 Impacts during Construction Phase

Project activities during construction phase include laying of pipeline and construction of Oil Storage

Terminal. These activities will result in dust generation, noise generation by construction equipment

& traffic, inflow of construction labour, sediment load in construction water, and generation of solid

waste in the form of construction spoils.

Page 79: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

79

Therefore, construction phase activities would have moderate impacts on on-site noise & air quality,

land use and ecology. It could also develop minor impacts on on-site soils, water use and water

quality. The other impacts of construction phase will be small in magnitude as well as temporary in

nature and are expected to wear out gradually once the construction activity is completed.

4.4.1 Impacts on Soil

The level of the entire site area will be raised by filling and suitable garden soil filled in areas where

Green Belt/ Landscaping are proposed.

4.4.2 Mitigation Measures

Plantation & turfing wherever needed in the project site would be undertaken to appease the

chances of soil erosion. Construction materials would be stored in godowns or enclosed spaces.

4.4.3 Impacts on Land Use

Preparatory activities like construction of access roads, temporary offices, quarters and godowns,

storage of construction materials etc. will be confined within the project area. These will not

generally exercise any significant impact except altering the land use pattern of the proposed project

sites. There will be no impact on the adjoining land.

4.4.4 Mitigation Measures

Construction camp for construction personnel to avoid indiscriminate settlement of construction

labourers. The small amount of construction debris will be disposed of in suitable pre-identified

areas/ low lying areas along as per the advice of local bodies. Appropriate dust suppression measures

will be implemented within the project site during construction, material handling.

4.5 Impacts on Hydrology and Water Use

4.5.1 Impacts on Hydrology

No impact on hydrological regime as the project will not obstruct the water flow in rivers & canals

during construction. Drainage pattern of overland water flow of the storage terminal will be changed

according to the existing profile and slope of the land.

4.5.2 Mitigation Measures

The water demand during construction period will be met from the private water suppliers/ Metro

water therefore, not likely to have impacts on other users.

Page 80: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

80

Water Quality

4.5.3 Impacts on Water Quality

Wastewater from construction activities would contain suspended impurities. Deterioration of water

quality due to wastewater disposal from the workers camp and sullage generated from construction

sites.

4.5.4 Mitigation Measures

The construction activities would be limited to small area. Proper sanitation and drainage facilities

would be provided at the construction site.

4.6 Air Quality

4.6.1 Impacts on Air Quality

Generation of dust due to excavation, backfilling & hauling operations and transportation.

Deterioration of air quality due to emission from construction machineries and automobile traffic.

4.6.2 Mitigation Measures:

Construction materials would be stored in godowns or enclosed spaces. To reduce fugitive dust

emission at the proposed site due to vehicular movement and material transportation, sprinkling of

water would be undertaken wherever unpaved haul roads pass through habitation. Low emission

construction vehicles and generator sets should be used. Construction machinery should be in good

working condition and engines turned off when not in use.

4.7 Noise Quality

4.7.1 Impacts on Noise

During the construction phase, noise will be generated due to movement of vehicles, and operation

of light & heavy construction machineries including pneumatic tools (bull dozers, scrapers, concrete

mixers, generators, pumps, vibrators, cranes, compressors etc.) that are known to emit sounds with

moderate to high decibel value. Noise generated from sources mentioned above will be intermittent

and of short duration mostly during daytime.

Therefore, no significant impact is anticipated on account of noise generation around the project

site. Moreover, villages/settlements being mostly far away from the site, no significant impact on

Page 81: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

81

local people are apprehended, as the noise will generally die down by the time it reaches them.

However, the workers are likely to be exposed to high noise levels that may affect them.

Careful planning of the operation of construction equipment is required during this period so that

minimum disturbances are caused. Construction camp would be located away from the construction

sites and major road traffic.

4.7.2 Mitigation Measures

Impacts of noise on construction workers shall be minimized through adoption of adequate

protective measures in the form of

(a) Use of personal protective equipment (ear plugs, ear muffs, noise helmets etc.),

(b) Education and public awareness, and

(c) Exposure control through the rotation of work assignments in the intense noise (above 90 dBA for

8-hr exposure as per Factories Act) areas.

Low noise construction equipment should be used. It would be ensured that all the equipment used

during construction are properly maintained to keep noise within the permissible limits. Construction

machinery should be in good working condition and engines turned off when not in use.

4.8 Flora & Fauna

4.8.1 Impacts on Flora

Loss of flora due to construction of the proposed Oil Storage Terminal.

4.8.2 Mitigation Measures:

Plantation in the open spaces of the project site is proposed to be implemented under plantation

programme.

4.8.3 Impacts on Fauna:

No impact on fauna during construction as the project site is a barren land.

Page 82: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

82

4.8.4 Impacts on Aquatic Life

As the water quality of the surface water bodies is not likely to change due to the construction

activities, no impacts on the aquatic life is expected.

4.9 Impacts on Socio-economics

Impacts on Employment & Trading Opportunities

Substantial construction personnel including skilled, semi-skilled and unskilled labourers will be

employed by various contractors at site during the peak period of construction phase. The

construction materials like stone chips and sand will be procured locally.

4.10 Impacts & Mitigation Measures During Operation Phase

Project activities during operation phase include transfer of petroleum products through the pipeline

under pressurized flow and tap off of such products at certain intermediate points. These activities

will result in enhancement of chemical hazards and socio economic benefits. There will have as such

no other sources of pollution & negative impacts.

Therefore, operation phase activities would have moderate impacts on socioeconomics. It could also

develop minor impacts on noise. The main impacts of operation phase are chemical hazards and

socio-economic benefits and such operational impacts are long term.

4.10.1 Soil

4.10.1.1 Impacts on Soil

Generation of dust in the project area due to soil erosion.

4.10.1.2 Mitigation Measures

The soil conditions of the project site would be allowed to stabilize during this period after the

impacts of the construction phase. The top soil in non-built up areas of the project site would be

restored and such portions of the site would be subjected to plantations which would help in

Page 83: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

83

bonding together of the soil, thus increasing its strength. Laying of roads and internal pathways will

reduce top soil erosion.

4.10.2 Water

4.10.1.3 Impacts

Drainage water from the site. Regular water requirement for operation & maintenance. The Effluent

Treatment Plant receives oily water through a separate drain line connecting tank farms, TT Gantry

area, Pump house manifold area etc.

4.10.1.4 Mitigation Measures

Effluent Treatment Plant of capacity 50 KL/HR and Sewage treatment Plant of capacity 6 KLD is

planned for the proposed project. Treated water from ETP will be used for gardening. Appropriate

drainage facilities will be developed within the site including proper disposal to drains. Regular water

requirement would be met from private water suppliers. Adequate water will be stored for fire

fighting in fire water storage tanks.

4.11 OPERATIONAL PHASE IMPACTS

Because of its potential to create long-term impacts, this phase is very important from the

environmental impact point of view. The basic impacts like gaseous emissions, water

consumption/ pollution and solid waste will have the potential to adversely affect air, water

and land / soil in the vicinity of the project site.

AIR ENVIRONMENT

Base line data reveals that ambient air quality in the study area for the Parameters PM2.5,

PM10, SO2, NO2, are well within the permissible Limits as prescribed by the National Ambient

Air Quality Standards (NAAQ’S) for Industrial Area, Residential, Rural & Other area. Stack

Emission of PM, SOx & NOx are attached to DG’s are the source of air pollution.

METEROLOGICAL DATA

The site specific meteorological data for three months from February 2015 to April 2015 were

obtained from onsite metrological station. Other data included for AERMET were daily wind

speed, wind direction, temperature, relative humidity, air pressure, precipitation, and solar

Page 84: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

84

radiation recorded during the period. AERMET reformats meteorological data so that it can be

used as input for AERMOD model.

AERMET PROCESS

For the 3 phase AERMET processing of the meteorological data, specifications of the land

use in the area are required to determine the terrain roughness for modelling. The land use

was characterized for in and around the site. The surface characteristics for the site and

surroundings were selected and used to calculate the albedo, Bowen ratio, and surface

roughness parameter. The meteorological data were processed in the AERMET software to

generate wind flow pattern & to generate surface meteorological data and profile

meteorological data in a prescribed format that can be fed to AERMOD for modeling.

AERMOD PROCESS

AERMOD Software Version 7.5.0 was used for air dispersion modelling and is applicable to a

wide range of buoyant or neutrally buoyant emissions up to a range of 50km. In addition to

more straight forward cases, AERMOD is also suitable for complex terrain and urban

dispersion scenarios.

AERMOD is a steady-state plume model. In the stable boundary layer (SBL), it assumes the

concentration distribution to be Gaussian in both the vertical and horizontal. In the

convective boundary layer (CBL), the horizontal distribution is also assumed to be Gaussian,

but the vertical distribution is described with a bi-Gaussian probability density function

(pdf). This behaviour of the concentration distributions in the CBL was demonstrated by

Willis and Deardorff (1981) and Briggs (1993). Additionally, in the CBL, AERMOD treats

“plume lofting,” whereby a portion of plume mass, released from a buoyant source, rises to

and remains near the top of the boundary layer before becoming mixed into the CBL.

AERMOD also tracks any plume mass that penetrates into the elevated stable layer, and

then allows it to re-enter the boundary layer when and if appropriate. For sources in both

the CBL and the SBL AERMOD treats the enhancement of lateral dispersion resulting from

plume meander. The emissions from existing and proposed stacks have been taken as basis

for modeling and are shown below:

Page 85: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

85

Table 4-1 Stack emission details

S.No. Stack Fuel quantity (l/hr) Emission Rate (g/sec) Stack height

(m) SOX NOX PM

DG 500 kVA 90

0.02078 0.03397 0.00113 10

DG 250 kVA 45 9

Figure 4-1 Maximum incremental value for SOX

Page 86: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

86

Figure 4-2 Zoomed Image of SOX Incremental value

Figure 4-3 Maximum incremental value for NOX

Page 87: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

87

Figure 4-4 Zoomed Image of NOX Incremental value

Figure 4-5 Maximum Incremental value for PM

Page 88: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

88

Figure 4-6 Zoomed Image of PM Incremental value

Table 4-2Predicted GLC for proposed stack

Parameters Baseline

data

(µg/m3)

Estimated

Maximum

Incremental

Concentration

(µg/m3)

Predicted

Maximum

GLC

(µg/m3)

NAAQ

standard

g/m3

(24hrly)

Direction Downwind

distance

(km)

SOX 10.65 2.303 12.953 80 SE Site

NOX 25.79 3.570 29.36 80 SE Site

PM 56.27 0.083 56.353 100 SE Site

As seen from the above table the concentration levels arising from the proposed project are

well within the NAAQ Standards.

Page 89: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

89

5 ENVIRONMENTAL MANAGEMENT PLAN

Environmental Management Plan (EMP) is the key to ensure a safe and clean environment. The EMP

envisages the plans for the proper implementation of mitigation measures to reduce the adverse

impacts arising out of the project activities.

EMP has been prepared addressing the issues like:

Mitigatory measures for abatement of the undesirable impacts caused during the

construction and operation stage.

Details of management plans (Greenbelt development plan, Solid waste management plan

etc.).

Institutional set up identified & recommended for implementation of the EMP.

Post project environmental monitoring programme to be undertaken after commissioning of

the project.

Expenditures for environmental protection measures.

The environmental mitigation measures for construction and operation phases has been given

below:

5.1 Environmental Management Plan During Construction Phase

Environmental impacts during the construction phase can be attributed to the site preparation

activity and the mobilization of workforce. The impacts of the construction phase on the

environment would be basically of transient nature and are expected to wear out gradually on

completion of the construction programme. However, once the construction of the project is

completed and its operations started, these operation stage impacts would overlap the impacts due

to the construction activities.

In order to mitigate such impacts and restrict them within tolerable levels, the following measures

shall be adopted:

Page 90: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

90

1. Proper and prior planning of approach and access roads, and appropriate sequencing and

scheduling of all major construction activities.

2. Adoption of appropriate soil conservation programme and its timely implementation in the

proposed project site.

3. Initiation of an appropriate landscape programme including plantation of trees and flowering

plants in and around the project site particularly, at all available spaces which would serve the dual

purpose of controlling fugitive dust and abatement of noise levels in addition to improving the

aesthetics of the area.

4. Water sprinkling in the vulnerable areas to suppress the dust generated during excavation, leveling

and other operations.

5. Use of properly tuned construction machinery & vehicles in good working condition with low noise

& emission and engines turned off when not in use.

6. Control of quality of construction wastewater within the construction site through suitable

drainage system with traps for arresting the sediment load for its proposed disposal into the main

natural drainage system around the site.

7. Implementation of suitable disposal methods of sediment/ construction debris at designated

places to avoid water logging at construction site.

8. Provision of protective gears such as ear mufflers etc. for construction personnel exposed to high

noise levels and locating the temporary labour sheds for housing the construction labourers away

from the construction site.

5.2 Environmental Management Plan During Operation Phase

The following mitigation measures shall be adopted during the operation phase of the project so as

to minimize the impact :

1. Regular monitoring for various components of environment should be undertaken to ensure

effective functioning of pollution control measures as well as to safeguard against any

unforeseen changes in environment.

Page 91: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

91

2. Provision of Floating Roof for various Storage Tanks will reduce the emissions of Vapors into

the Atmosphere.

3. The liquid effluents from the project are suitably treated in Effluent Treatment Plant. Sewage

Treatment Plant for treating canteen and sanitary waste water. Excess effluent, if any, would be

let out of the premises, after satisfying the stipulated regulatory standards.

4. It should be ensured that all the pollution control systems are commissioned as a part of main

plant equipment, before the commencement of operation of the project.

5. Noise pollution will be controlled by proper maintenance & acoustic enclosure for pumps,

compressors & DG sets. Personal protective equipment for people working in high noise areas

6. Greenbelt will be maintained properly including replacement of the decayed trees and raising

of seasonal flowering plants.

7. Adequate safety measures complying to the occupational safety manuals to prevent accidents

/ hazards to the workers.

8. Adequate fire fighting system and fire water tanks will be provided at all stations.

9. Adequate safety equipment will be available within the project site.

10. OFC based communication system (including data and voice mail)

11. Adequate protection against stray current and interference will be provided.

5.2.1 Greenbelt Development Plan

The green belt has been recommended as one of the major components of the EMP which will

further enhance the environmental quality through:

1. Mitigation of air pollution problems

2. Attenuation of noise level

3. Maintain the bio diversity of the area and improve aesthetics.

Page 92: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

92

For maintaining the ecological balance, dust control and mitigate noise pollution, greenery is

proposed to be developed to the maximum extent as permitted by the lay out along the proposed

plant boundary and inside the plant.Green belt will also be developed in and around the project

area.

The green lawns and the water-bodies compliment the grace and symmetry of the buildings. The

nature of plantation comprises of trees, lawns, shrubs and roads and pathways.

Extensive plantation and landscaping is proposed to mitigate any impacts during this phase.

Development of a green belt in and around the building area is an effective way to check pollutants

and their dispersion into the surrounding areas. The degree of pollution attenuation by a greenbelt

depends on its height and width, foliage, surface area density, dry deposition velocity of the

pollutants and the average wind speed through the greenbelt.

The objectives of green belt management are:

To create a soothing environment for people to work

To mitigate vehicular emissions and noise pollution

To cultivate culture of greenery within and outside the project site.

To maintain landscaping by optimal use of resources

Garden waste is accumulated in a designated area and used in the composting pits.

Therefore, development of green belt is nowadays imperative around industrial complexes.

Adequate plantation programme in and around the project site And the following plants are

suggested:

Table 5-1 Plant Details

Sl. No. Botanical Name Common Name.

1 Alstonia scholaris Elilappalai

2 Mimusops elengi Magilam

3 Cassia fistula Arakkuvadam

Page 93: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

93

Sl. No. Botanical Name Common Name.

4 Bauhinia purpurea Mandaram

5 Zizyphus mauanitiana Elentha

6 Cassia siamea Manja-konnai

7 Ficus religiosa Arasu

8 Albizia lebbeck Vakai

9 Polyalthia longifolia Asogam

10 Diospyros melanoxylon Karai

11 Ailanthus excels Perumarautha

12 Melia azedarach Malaivembu

13 Butea monosperma Tarasa

14 Tamarindus indica Amilam

15 Terminalia arjuna Vellamatta

16 Azadirachta Indica Veppam

17 Grevillea robusta Savykkamaram

5.2.2 Development of green belt will include:

1) Plantation along the boundary / periphery and all over the project site for protection against

particulate dispersion and noise dispersion. The peripheral greenbelt will vary in width to suit the

plant design requirement.

2) Plantation along approach road and pathways for protection against noise and vehicular

emissions.

Page 94: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

94

The following general guidelines and measures will be adopted:

- The plantation of trees will be initiated with start of the construction stage so that substantial

growth may be achieved when the project is completed. The greenbelt development programme will

be drawn to conform to natural climatic conditions and adaptability of the species.

- Species involved in plantation / afforestation should include indigenous, fast growing and eco-

friendly.

- Proper drainage system and proper plantation techniques should be adopted.

- Plantation should be properly maintained and protected by fencing from grazing and felling. The

plantations would consist of a mixture of carefully chosen locally available species of trees, shrubs

and herbs, preferably evergreen and resistant to pollution.

5.2.3 Solid Waste Management

The sludge from ETP is treated by a process called Bioremediation. Bioremediation involves

detoxifying hazardous substances instead of merely transferring them from one medium to another.

This process is less disruptive and can be carried out at the site which reduces the need of

transporting these toxic materials to separate treatment sites. Solid waste from STP will be used as

manure.

5.3 SOCIO – ECONOMIC ENVIRONMENT

BPCL is committed to the socio – economic up – lift of the people in region and has actively involved

in formulating and implementing proactive measures as part of the corporate social responsibility.

The following activities are carried on by BPCL as a part of Corporate Social Responsibility (CSR).

CSR in BPCL is recognized in the industry and won numerous accolades

Company with Best CSR and Sustainability Award 2014 – Asian Centre for Corporate

Governance & Sustainability

Excellence Award for Social responsibility – World Petroleum Congress at Moscow

Page 95: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

95

Aaj Tak Care awards for CSR under livelihood category

BPCL has defined CSR Policy and procedures & guidelines are in place.

The following have been identified as Thrust areas for CSR :

Water

Education

Skill Building

Health/ hygiene

Community development

5.3.1 CSR activities carried out in existing BPCL units:

Education:

Enabled over 1.3 lakh children receive quality education spanning 11 states

Water Conservation:

Project BOOND spans across India in Tamil Nadu, Andhra Pradesh, Rajasthan, Maharashtra,

Karnataka and Uttar Pradesh.

Undertook RWH in over 40 villages

Reached out to over 5500 families (Both Direct & indirect benefits)

Around 7 crore liters of water storage capacity created

Skill Development:

1000 youth trained and placed with reputed companies in areas surrounding KR

More than 1500 women, youth and persons with disabilities were skilled

BPCL works with specialized NGO partners in the field of Water Conservation and uses various

models with specific performance indicators and evaluation processes.

Page 96: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

96

We have implemented Boond projects in Maharashtra, Tuticorin, Bharatpur among many

other places

BEFORE:

AFTER:

Figure 5-1Sluice work of Ilanthaikulam kanmoi, Vaddaku Aavarangadu - Before & After

5.3.2 Proposed CSR plan :

The following CSR activities are planned:

- Building Toilets in schools .

- Organizing Medical Camps and health check up for nearby villages .

Page 97: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

97

- Painting of government school buildings.

- Providing books to children.

- Water conservation at Govt. Schools

- Tree plantation

- Skill building / development for local residents.

5.4 POST PROJECT ENVIRONMENTAL MONITORING

It is recommended that the Project Authorities to set up monitoring stations where ever possible to

assess the quality of the neighbouring environment after the commissioning of the project. An

environmental monitoring programme is important as it provides useful information and helps to:

Verify the predictions on environmental impacts presented in this study assist in detecting the

development of any unwanted environmental situation, and thus, provides opportunities for

adopting appropriate control measures, and identify the effectiveness of mitigative measures

suggested in the EMP.

5.3.1 Monitoring Program

After commissioning of the project, post project monitoring of environmental parameters will be

carried out at regular intervals. The monitoring program in different areas of the environment has

been based on the findings of the impact assessment studies. The post project monitoring program

will be done for air, water, soil and noise as per the TNPCB guidelines.

5.3.2 Institutional Set-up for Monitoring

The responsibility of environmental management of an operating station lies mainly with the

Management Staff operating the Plant who handle the Environmental Management at site and co-

ordinate with all other Zone & HQ and CC for environmental matters as well as outside agencies like

State Pollution Control Board. An environmental management group shall be established at project

consisting of Senior Executives and supporting staff.

5.3.3 Fire and Safety Management

Necessary fire fighting facilities will be provided in the project site to tackle any fire contingency.

Regular safety audits will be carried out for improving safety performance. On-site and off-site

Page 98: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

98

Disaster Management Plans (DMP) will be developed and mock drills will be conducted at regular

intervals to keep the disaster management team in a state of full preparedness. In addition, refresher

training programmes will be conducted at regular intervals for employees and selected contractor

labourers to enhance their safety awareness and preparedness.

5.3.4 Legal and Statutory compliance

All the environmental standards/stipulations will be fully complied with. The plant has to obtain

Consent from the State Pollution Control Board for liquid and gaseous wastes disposal as per Water

(Prevention & Control of Pollution) Act and Air (Prevention & Control of Pollution) Act. It will be

supervised that all requirements under these acts and rules are met, and if not met, the satisfactory

explanations for it are sought. The officer in charge for environmental aspects will prepare these

reports.

5.3.5 Information Dissemination and Public Relations

Everybody nowadays is concerned about environment. It is needed that people should be provided

with environmental data related to the plant so that wrong apprehensions can be removed. This

requires a well planned public relation and information dissemination process so that unnecessary

public intervention is avoided. This can be done through organizing different programmes with

participation from local bodies, encouraging local community in environmental projects (like tree

plantation) etc. The management in the project will be entrusted with all these responsibilities.

5.3.6 Mutual Aid Arrangement

In line with the well established practice of oil industry Mutual Aid Arrangement will be

implemented for the proposed oil terminal by entering in to suitable understandings with the

adjacent industries such as HPCL, IOCL, RIL, Ennore port limited.

5.5 Occupational Health and Safety

During construction, excavation, loading and unloading of construction materials, preparation and

processing of construction materials, erection of proposed terminal and other civil structures will

result in problems like occupational health and safety.

Page 99: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

99

Review of occupational health status is being done. Regular monitoring of occupational health

will be done for all employees and appropriate action will be taken to set right any problem in

the areas.

Personal protective equipment’s like gloves, goggles, iron toe boots, face masks will be

provided to employees.

Hospital facility shall be provided in order to attend the emergencies arising out of accidents,

if any.

All deployed personnel will be trained in basic fire fighting and first aid.

During construction, the working personnel shall be given the following appropriate protective

equipments:

Fire Helmets

Rubber hand Gloves

Industrial Safety Helmets

Safe Walk Ladder

Ear Muffs

Oxygen Meter

Fire retardant suits

Hand Operated Siren

Explosive meter

Red/ Green Flag

Industrial safety shoes with steel toe

Slash googles

Gum boots

Page 100: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

100

All working personnel shall be medically examined once in a year and also during pre-employment.

5.4.1 Safety Plan

During construction, safety is an important factor for all personnel working at the site. During

excavation and erection of proposed terminal, the project authority shall formulate safety policy with

the following regulations:

To provide necessary equipment, safety appliances and to ensure their proper use.

To ensure that all safety factors are taken into account in the design, construction, operation

and erection machinery and equipment

To provide training in fire fighting operations

To notify regulations, instructions and notices in the common language of employees

To prepare safety rules for the employees as per the safety policy.

To allocate sufficient resources to maintain safe and healthy conditions of work.

5.4.2 Safety Training

A training center shall be set up for the employees. Safety officers will be provided training by the

faculty members from the corporate center and Industrial safety Institutions. Some remedial

measures proposed to be adopted to prevent the hazards:

Reliable type of fire detection system with proper zoning

Every employee shall cooperate and actively participate in maintaining and improving safety

standards

Proper fire watching by all concerned would be ensured.

Safety officials shall prepare a leaflets regarding safety awareness and shall conduct safety

awareness programme.

Page 101: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

101

5.4.2.1 Training for Emergency Preparedness

Training shall be provided to all personnel who have a role in the planning and operational response

to the emergency. Training should be provided to:

a. All site personnel

b. Medical personnel and public fire service personnel

Emergency scenarios shall be developed to test emergency plans and operational response at all

levels. Fire drills shall be conducted atleast once in a month to ensure that the staff and all the

emergency equipments are kept in good condition. At the end of each exercise/drill an evaluation of

the response call shall be carried out and deficiency noted.

Emergency plan shall be reviewed in case of addition of facilities or change in process. The

improvements and updating procedures should be based on a feedback from the exercises / drill.

A specific person nominated by the incident controller should maintain a chronological log of events

during the entire period of emergency drill at the emergency control center. The following important

data should be recorded.

a) Description of the accident

b) Personnel injuries

c) Equipment damages

d) Response time of various group like medical, transport, CISF, Fire & safety group.

5.6 EXPENDITURE ON ENVIRONMENTAL MEASURES

A capital cost provision of about Rs. 55 LAKHS has been kept towards the environmental measures.

Page 102: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

102

Table 5-2 Budgetary provisions for EMP

S.no Item Description CAPITAL COST ( In lacs)

RECURRING COST ( in lacs per year)

1 SEWERAGE TREATMENT PLANT

10 2

2 EFFLUENT TREATMENT PLANT 30 2

3 OWS 5 1

4 MONITORING OF AIR & WATER 0 1

5 TREE PLANTATION 10 1

TOTAL 55 5

5.7 Project Schedule

5.6.1 Manpower

Manpower requirements for the execution of the project:

1. Chief Project Manager

2. 1 Managers

3. 3Engineers:

1 for civil structures

1 for mechanical structures

1 for Electrical

5.6.2 Implementation schedule:

The detailed Implementation schedule has been prepared in the project office format. The salient

features of the implementation schedule are as follows:

The Pre-Project activities shall involve floating of tenders and obtaining the following statutory

approvals and surveys.

1. Approval from PESO (CCOE)

2. MOE&F Approval

Page 103: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

103

3. Approval from State Pollution Control Board

4. Approval from Inspector of Factories

5. Construction approval from Village Panchayat / Town planning

5.6.3 Engineering Surveys:

1. Topography survey

2. Soil Investigation

The physical project activities shall start after receipt of clearance from MoEF and other approvals

and scheduled to be completed within 24 months thereafter.

Page 104: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

104

6 ADDITIONAL STUDIES

6.1 Risk Assessment:

Due to the storage and transportation of all petroleum products, it requires the risk assessment to be

done.

The Risk Assessment for proposed project is analyzed and attached in the Annexure – 9.

The material safety data sheet of Motor Sprit, High Speed Diesel and Ethanol is enclosed in Annexure

– 11, 12 and 13 respectively.

6.2 Disaster Management Plan:

The On-site Disaster Management Plan is prepared with the objective of defining the functions and

responsibilities of all concerned managerial, operational and supporting services department

personnel with respect to detection and effective implementation of action plan. The ultimate goal is

the effective containment of the situation by proper mitigative action at the place of occurrence,

cautioning people in adjoining affected localities, prompt rescue and medical aid to affected persons

and communication to civil authorities for rushing in help from outside. All concerned are hereby

requested to carefully study and thoroughly familiarize themselves with it in order to ensure its

effectiveness in times of emergency. The detailed disaster Management Plan is attached in

Annexure - 15

Page 105: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

105

7 PROJECT BENEFITS

1. The shifting of terminal from Tondiarpet shall facilitate shifting of the 200 trucks attached to

this location from the heart of city to Ennore which is outside the city limits. This shall reduce

the traffic congestion caused by these vehicular movements in the North Chennai area.

2. Increased storage capacity to meet the increasing market demand.

3. Increase in efficiency due to automation of major activities.

4. Socio Economic benefits

5. Meeting fuel need of general public in the 4th largest city of the country Chennai.

6. A Terminal in tune with company’s vision of safe and environment friendly operations

facilities.

Page 106: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

106

8 CONCLUSION

1. Due to the proposed Oil storage Terminal the impact on environment will be minimum and can be

further reduced by implementing various mitigating measures and regular monitoring programs.

2. The proposed Oil Storage Terminal will serve as a southern hub and have beneficial impacts in

terms of supply of petroleum products in the region with incidental benefits like employment

opportunities both in the construction stage and operation stage. Also the modernized installation

will facilitate greater level of operating safety.

3. BPCL has a successful track record of implementing various EMP’s & DMP’s in their existing

recently constructed installations.

4. Due to the proposed project the socio economic activities will be developed in and around the

project area.

5. As zero discharge Effluent Treatment Plant is envisaged and the impact on water environment will

be minimum. Various conservatory measures are proposed to be taken for minimizing water

consumption.

6. Proper disposal method such as Bio-remediation have been planned to carried out for disposal of

solid waste generated from the periodic cleaning of the tanks (once in 5 years)

7. Hence the project is recommended by the consultant.

Page 107: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

107

Table 8-1 COMPLIANCE TO TOR POINTS

S.No TOR Points Pg No.

1. (A) Executive summary of the project-giving a prima facie

idea of the objectives of the proposal, use of resource,

justification, etc. In addition, it should provide a

compilation of EIA report including EMP and the post-

project monitoring plan, in brief

Executive summary is provided

in the EIA report ( Pg. No.6 to 8)

(B) Details of the proposed petroleum products storage

facility including land area with break up, source, receipt,

storage & distribution of petroleum products, water

requirement for domestic/process, sewage, trade

effluent, method of treatment details, sources of air

emission, APC measures, power back up, project cost etc.

shall be furnished separately.

Detailed in Chapter – 2

(A) Project Description

2. Justification for selecting the proposed site for the

installation of petroleum storage facility.

BPCL has been looking for land

for resitement of Tondiarpet

Installation in view of

operational constraints and also

in lieu of space limitations. The

land needed to be near to CPCL

and Ennore port. Hence the land

near Ennore port which is fast

developing and away from the

city was an ideal location.

Therefore, this Salt land was

selected as it meets our

requirements. HPCL is situated

adjacent to our plot and product

Page 108: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

108

S.No TOR Points Pg No.

input through their jetty

pipeline is possible. Further

railway connectivity is also

present in case we need to use

railways for transport of

products.

3. Land requirement for the project including its break up for

various purposes and its availability and optimization.

Provided in chapter – 2

Pg.No.30

4. Plant layout clearly showing petroleum products storage

installations with pipe line network.

Piping layout given in

Annexure – 2

5. Mode of receiving petroleum products in the isolated

storages and mode of its distribution.

Chapter – 2 Pg No 25-26

6. Justification on the design & adequacy of the pipe line

provided by HPCL from Ennore Port to HPCL storage

installation for conveyance of petroleum products

including proposed additional load of transportation of

petroleum products by BPCL in the existing pipeline

facility.

Letter from HPCL and Minutes

of Meeting of OMC’s enclosed

as Annexure – 3

7. Details on design parameters of the storages, procedures,

piping layout, monitoring equipments, emergency

requirements, safety controls, relief systems, etc.

The design parameters of

storages are as per OISD and the

list of standards is attached in

Annexure – 6

Piping layout is provided in

Annexure – 2

Monitoring equipments,

emergency requirements are all

Page 109: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

109

S.No TOR Points Pg No.

provided in Chapter – 2

(Pg no 31-33)

8. Details on list of petroleum products to be stored at the

facility - its category, physical & chemical properties,

storage quantities, etc., and compatibility with the design

parameters of the storages.

Provided in chapter 2

Pg.No.24-25

MSDS is enclosed for HSD, MS

and for Ethanol in Annexure 11

12 and 13

9. Details of domino effect of the storage tanks and

respective preventive measures including distance

between storage units in an isolated storage facility.

The entire storage facilities have

been properly planned as per

OISD. The detail report is given

in Annexure – 9

10. Details on storage tanks including capacity and distance of

storage.

The entire storage facilities have

been properly planned as per

OSID. It is maintained with a

safe storage distance between

the tanks. Layout is enclosed in

Annexure – 1

11. Details on transfer and handling of petroleum products -

piping system, handling techniques, equipments used

standard operating procedures, etc.

Standard Operating Procedure is

attached in Annexure – 7.1, 7.2.

12. Details on specific equipments, flanges, pumps,

compressors proposed to control loss of chemicals.

Designed VOC loss accounting.

There will be no loss during the

operations . The input is

through pipelines hence there is

no loss. The floating roof tanks

being constructed shall be

provided with Rimseal

Page 110: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

110

S.No TOR Points Pg No.

protection system for ensuring

that there is no loss. The tank

lorries are loaded through

bottom loading arms which

ensures that there is no loss,

Centrifugal pumps conforming

to API 610 ( 8th edition) shall be

used which ensures no leakage.

Also flanges conforming to ANSI

B 16.5 shall be used which

ensures no leakage.

13. Details of proposed source-specific pollution control

schemes/equipments.

Provided in Chapter – 2

Pg.No.27-30

14. Details on requirement and availability of power and

water with its source and authorization from the

concerned department.

The nearest substation is Minjur

and we shall be getting power

connection from that substation

A letter in this regard is

submitted to concerned EE and

the same is enclosed in

Annexure – 18

Metro water supply shall be

taken from existing water line

from CPCL desalination plant to

HPCL and letter in this regard

submitted to concerned

authority. The letter is enclosed

in Annexure – 19

Page 111: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

111

S.No TOR Points Pg No.

15. Proposal of package treatment system for treatment of

sewage so as to utilize treated water for green belt

development.

Provided in Chapter – 2 Pg.No.

27

16. Non point pollution sources, their treatment & disposal

shall be addressed in detail.

Provided in Chapter – 4 Pg.No.

58

17. Management plan for solid/hazardous waste generation,

storage, utilization and disposal.

Provided in Chapter – 2 Pg.No.

27

18. Details regarding infrastructure facilities such as

sanitation, fuel storage, restroom etc to the workers

during construction and operation phase.

Provided in Chapter – 4 Pg.No.

77 –83

19. Details on safety management plan. Provided in Chapter – 5 Pg.No.

100

DMP and HSE is enclosed in

Annexure - 15 & 10

20. Details of tank bottom sludge management with action

plan.

Details provided in Executive

Summary Pg.No. 16

21. Any litigation pending against the project and / or any

direction/ order passed by any Court of Law related to the

environmental pollution and impacts in the last two years,

if so, details thereof.

No

(B) Description of the Environment

22. The study area shall be up to a distance of 10 km from the

boundary of the project site.

Yes the study area has been

taken upto 10 Km from the

boundary of Project Site. Map

indicating the same provided Pg

Page 112: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

112

S.No TOR Points Pg No.

no 41 of Chapter 3

23. Location of the storage facility, nearest habitats with

distances from the facility to be demarcated on a topo

sheet (1:50000 scale).

Topo sheet scan annexed as

Annexure -17

24. A CRZ map duly authenticated by the authorized agencies

demarcating LTL, HTL, CRZ area, location of the project

site with respect to CRZ, coastal features such as

mangroves, if any shall be furnished.

Authenticated demarcation

Map obtained from IRS, Anna

University is enclosed as

Annexure – 5

25. CRZ clearance shall be obtained from the concerned

Coastal Zone Management Authority for the project, as

the project area comes under CRZ area.

TNSCZMA recommendation

received and letter is enclosed

as Annexure – 14

26. Land use pattern based on satellite imagery including

location specific sensitivities such as national

parks/wildlife sanctuary, village, industries, etc.

Executive Summary Pg. No. 6 &

Pg no 7 and in Chapter – 3

Pg.No. 41

27. Demography details of the entire village falling within the

study area.

Provided in Chapter – 3

Pg.no.67-73

28. Topography details of the project area. Executive Summary Pg. No. 6 &

7

Topo sheet scan annexed as

Annexure -17

29. The baseline data to be collected from the study area with

respect to different components of environment viz. air,

noise, water, land, biology and socio-economic (please

refer Section 4.4.2 for guidance for assessment of baseline

components (please refer Section 4.4.2 for guidance for

Details provided in Chapter- 3

Page 113: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

113

S.No TOR Points Pg No.

assessment of baseline components and identify

attributes of concern). Actual monitoring of baseline

environmental components shall be strictly in accordance

to the parameters prescribed in the ToR after considering

the proposed coverage of parameters by the proponent in

draft ToR and shall commence after finalization of ToR by

the competent Authority.

30. Base line study shall include VoC emission, groundwater

and surface water in Ennore creek and detailed report

shall be furnished.

Details provided in Chapter -3

Pg 43 to 55

31. Adequate number of monitoring stations on water,

groundwater, air, noise, soil quality shall be fixed on the

downstream of the project site (Ennore Creek) based on

the environment condition to conduct base line study.

Details provided in Chapter -3

Pg 41 to 58

32. Geological features and geo-hydrological status of the

study area.

Details provided in Chapter – 3

Pg. No.49 to 51

33. Details on surface water quality of nearby water sources

and other surface drains.

Details provided in Chapter 3

Pg.49 – 56

34. Details on ground water quality. Details provided in Chapter 3 Pg

54

35. Relevant ambient air quality parameters for monitoring

including combustion emissions due to traffic, VOCs and

stored chemicals, etc

Details provided in Chapter 3 Pg

41 – 46

36. Existing ambient air quality, expected emissions such as

combustion emissions* due to traffic, VOCs*, stored

chemicals*, etc.) and evaluation of the adequacy of the

Details provided in Chapter 3 Pg

41 - 46 and Chapter – 4 Pg 83-88

Page 114: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

114

S.No TOR Points Pg No.

proposed pollution control devices to meet standards for

point sources and to meet AAQ standards. (* - as

applicable).

37. The air quality contours may be plotted on a location map

showing the location of storage facility habitation nearby,

sensitive receptors, if any and wind roses.

Details provided in Chapter – 3

40 to 47

38. Details on noise levels at sensitive/commercial receptor. Details provided in Chapter 3 Pg

47-49

39. Site-specific micro-meteorological data including mixing

height.

Details provided in Chapter 3 Pg

45 to 46

40. One season site-specific data excluding monsoon season. Details provided in Chapter 3

41. Proposed baseline monitoring network for the

consideration and approval of the competent Authority.

The committee can verify and

approve the baseline line

monitoring report in Chapter –

3.

42. Ecological status (terrestrial and aquatic) of the study area

such as habitat type and quality, species, diversity, rarity,

fragmentation, ecological linkage, age, abundance, etc.

Details provided in Chapter 3 Pg

59

43. If any incompatible land use attributes fall within the

study area, proponent shall describe the sensitivity

(distance, area and significance) and propose the

additional points based on significance for review and

acceptance by the EAC/SEAC.

Nil

Page 115: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

115

S.No TOR Points Pg No.

Incompatible land use attributes include:-

> Public water supply areas from rivers/surface water

bodies, from ground water.

> Scenic areas/tourism areas/hill resorts

> Religious place, pilgrim centers that attract over 10 lakh

pilgrims a year

> Protected tribal settlements (notified tribal areas where

industrial activity is not permitted)

> Monuments of national significance, World Heritage

Sites

> Cyclone, Tsunami prone areas (based on last 25 years)

> Airport areas

Any other feature as specified by the State or local

government and other features as locally applicable,

including prime agricultural lands, pastures, migratory

corridors, etc

> If ecologically sensitive attributes fall within the study

area, proponent shall describe the sensitivity (distance,

area and significance) and propose the additional points

based on significance for review and acceptance by the

EAC/ SEAC.

Ecological sensitive attributes include:

Nil

Nil

Nil

Nil

Nil

Nil

Nil

Nil

Yes. CRZ area falls in the project

site and the details are

described in chapter 2 pg 22

Nil

Page 116: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

116

S.No TOR Points Pg No.

> National parks

> Wild life sanctuaries Game reserve

> Tiger reserve/elephant reserve / turtle nesting ground

> Mangrove area

> Wetlands

> Reserved forests and protected forests

> Any other closed/protected area under the Wild Life

(Protection) Act, 1972

> Any other eco-sensitive areas, etc.

Nil

Nil

CSR plans are provided to

preserve the Mangrove area

and the same is enclosed as

Annexure – 16

Nil

Nil

Nil

Nil

(C) Anticipated Environmental Impacts and

Mitigation Measures:

44. Anticipated generic environmental impacts due to this

project shall be furnished. Base Line studies shall be

conducted for all the concerned VECs and likely impacts

will have to be assessed for their magnitude in order to

identify mitigation measures.

Details provided in Chapter – 4

Pg 77 to 83

45. Appropriate assessment of environmental impacts shall be

done and the same may be submitted in draft ToR for

consideration and approval by EAC/SEAC.

Final TOR received and

compliance for the same in

terms of EIA studies etc has

been done accordingly.

Page 117: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

117

S.No TOR Points Pg No.

46. While identifying the likely impacts, also include the

following for analysis of significance and required

mitigation measures:

> impacts due to emissions from entry and evacuation of

chemicals at storage points

> Impacts due to temperature variations in the tanks

> impacts due to emissions from handling of chemicals

> impacts due to emissions from cleaning operations

> impacts due to odor pollution

> Impacts due to generation of wastewater from drainage

facilities, cleaning, tanks, seepage, etc.

> Impacts due to noise from tank installations, conveyors,

transportation of products, etc.

> Impacts due to fugitive emissions/VOCs.

> Impacts due to catastrophic failures.

> impacts due to residues/tank bottom sludge, etc

> Impacts due to fire/accidents.

> impact on health of workers due to proposed project

activities

Details provided in Chapter 4

Pg.No.77 to 83.

RRS studies carried out and the

same is enclosed as Annexure 9

47. In case of likely impacts from the proposed storage facility

on the surrounding reserve forests, plan for the

conservation of wild fauna in consultation with the State

Forest Department shall be furnished.

The site does not fall in any

forest area hence permission

from forest department is not

required.

Page 118: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

118

S.No TOR Points Pg No.

48. Action plan for the green belt development - species,

width of plantations, planning schedule, etc., in

accordance to CPCB published guidelines.

Details provided in Chapter 5 –

Pg No 91 to 94

(D) Analysis Of Alternative Resources And

Technologies :

49. Reasons for selecting the existing site for the proposed

project. Conformity of the site with the prescribed

guidelines in terms of CRZ, river, highways, railways, etc.

BPCL has been looking for land

for resitement of Tondiarpet

Installation in view of

operational constraints and also

in lieu of space limitations. The

land needed to be near to CPCL

and Ennore port. Hence the land

near Ennore port which is fast

developing and away from the

city was an ideal location.

Therefore, this Salt land was

selected as it meets our

requirements. HPCL is

presenting adjacent to our plot

and product input through their

jetty pipeline is possible as the

pipeline is coming up to HPCL

and can be further extended to

BPCL. Further railway

connectivity is also present in

case we need to use railways for

transport of products. In terms

of highway connectivity, it is

Page 119: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

119

S.No TOR Points Pg No.

well connected. The plot has

some CRZ area and

recommendations have been

obtained from TNSCZMA which

is annexed as Annexure 14.

50. Details on improved technologies for storing and handling

of petroleum products/ hazardous chemicals.

Details provided in Chapter 2

Pg. No 31

( E ) Environmental Monitoring Program

51. Monitoring programme for source control Details provided in Chapter 5

52. Appropriate monitoring network has to be designed and

proposed to assess the possible residual impacts on VECs.

Post EMP is enclosed in Chapter

5

53. Monitoring pollutants at receiving environment for the

appropriate notified parameters - air quality,

groundwater, surface water, soil etc. during operational

phase of the project.

Details provided in Chapter 5

54. Leak detection and repair programme There is no cross country

pipeline. In case of in-plant

piping, visual checks shall be

carried out regularly and leak if

any shall be arrested

immediately. In addition to it,

hydrocarbon detectors shall be

installed as per latest OISD

recommendations at all

strategic locations

Page 120: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

120

S.No TOR Points Pg No.

55. Specific programme to monitor occupational, safety and

health protection of workers,

Regular health camps shall be

conducted. Proper PPE's shall be

issued to the workers. Further

doctor visit shall be arranged

twice a week for regular health

check ups

56. Details of on-house monitoring capabilities and the

recognized agencies if proposed for conducting

monitoring.

Monitoring shall be done

through TNPCB and no In –

House monitoring will be done.

(F)Additional Studies

57. Marine Ecology Study for the entire ETPC area covering

Ennore coastal Stretch shall be conducted involving all

industries in that location in consultation with NIOT,

Chennai and report shall be furnished.

Study done and report annexed

as Annexure – 20

58. Plan of Marine Monitoring of Coastal Water shall be

furnished in tie with NIOT, Chennai

Plan annexed as Annexure -21

59. Risk Assessment Report and disaster Management Plan

with organization chart

Risk assessment report and

Disaster Management Plan is

enclosed in Annexure 9 and

Annexure 15

60. Details on risk assessment and damage control shall be

addressed with safeguard measures.

Risk Assessment report is

attached as Annexure 9.

61. Details on status of emergency preparedness - safety

procedures, training, personal protective equipments, fire

fighting devises, medical aids, safety control

DMP is enclosed as

Annexure 15

Page 121: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

121

S.No TOR Points Pg No.

62. Details on socio-economic development activities such as

commercial property values, generation of jobs,

education, social conflicts, cultural status, accidents, etc.

Detailed in Chapter -3

63. Proposed plan to handle the socio-economic influence on

the local community. The plan should include quantitative

dimension as far as possible.

Detailed in Chapter -3

64. Details on compensation package for the people affected

by the project, considering the socio-economic status of

the area, homestead ouster and land less laborers.

Since the land is allotted by salt

department to BPCL, there are

no people affected by the

project. Hence no compensation

is payable.

65. Details on plan for corporate social responsibility including

the village, population spread, SC/ST/backward

communities, up gradation of existing schools,

establishing new schools with facilities (such as

laboratories, toilets, etc.), link roads, community halls,

primary health facilities, health camps, etc.

CSR of projects are provided in

Chapter 5

(G) Environmental Management Plan

66. Administrative and technical organizational structure to

ensure proposed post- project monitoring programme for

approved mitigation measures.

Details enclosed as

Annexure – 8

67. EMP devised to mitigate the adverse impacts of the

storage facility should be provided along with item-wise

cost of its implementation (Capital and Recurring costs).

Details provided in chapter - 5

68. As a part of EMP, monitoring of ground water and surface Yes

Page 122: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

122

S.No TOR Points Pg No.

water near to Ennore Creek shall be included.

69. Allocation of resources and responsibilities for plan

implementation.

Allocation of resources is

brought forth in Chapter 5, pg

102

Responsibilities enclosed as

Annexure – 8

70. Details of the emergency preparedness plan and on-site

and off-site disaster management plan.

Details enclosed as Annexure –

8.1

71. Does the company have a well laid down environment

Policy approved by its Board of Directors? If so, it may be

detailed in the EIA report.

Yes, detailed in Annexure - 10

72. Does the environment Policy prescribe for standard

operating process/procedures to bring into focus any

infringement/deviation/violation of the environmental or

forest norms/conditions? If so, it may be detailed In the

EIA.

Yes, detailed in Annexure 7.1,

7.2 and 8

73. What is the hierachical system or administrative order of

the company to deal with the environmental issues and

for ensuring compliance with the EC conditions? Details of

this system may be given.

Enclosed in Annexure – 8

74. Does the company have a system of reporting of non-

compliances/violations of environmental norms to the

Board of Directors of the company and / or shareholders

or stakeholders at large? This reporting mechanism should

be details in the EIA report.

Yes

Enclosed in Annexure – 8

Page 123: Table of contents EXECUTIVE SUMMARY 6 1 INTRODUCTION …environmentclearance.nic.in/writereaddata/EIA/24122015GSYN3198... · Table of contents EXECUTIVE SUMMARY..... 6 ... 5.4.2 Safety

BPCL- EIA for STORAGE TERMINAL

Baseline Environmental Status

123

S.No TOR Points Pg No.

Additional Information

75. Scheme of Implementation of Rain Water Harvesting Shall be provided for collecting

the all the surface water run

off and recharging the ground

water. The drawings and

locations shall be finalized

during the detailed

engineering.

76. Socio Economic development activities As per point No 63

77. Public hearing Public hearing for the project

held on 10.09.2015 and Public

hearing minutes of meeting is

annexed as Annexure - 22