55
Draft Work Product- Intended for Deliberative Use Only Page 1 of 2 Note: This is a written explanation of the meeting and the materials included. All of these materials are in DRAFT form and have been made for the sole purpose of stimulating conversation and documenting any necessary information to be considered by the team. Tailings Design Tech Transfer Meeting May 12, 2009 The following people were invited to attend the meeting: Name Company/Agency The following people attended the meeting: Name Eli Curiel Company/Agency Coronado National Forest John Able Coronado National Forest Salek Shafiqullah Coronado National Forest Teresa Ann Ciapusci Coronado National Forest Bev Everson Coronado National Forest Walt Keyes Coronado National Forest Debby Kriegel Coronado National Forest Roger Congdon Coronado National Forest Tom Furgason SWCA Dale Ortman SWCA Melissa Reichard SWCA Mike Sieber SRK Clara Balasko SRK Orlanthia Henderson Town of Sahuarita Bob Casavant Arizona State Parks Bob Sejkora Arizona State Parks David Pfordt Town of Sahuarita Derek Wittwer AMEC John Lupo AMEC Goal: This meeting was conducted in order to convey the technical information from the Dry Tailings design to the Forest Service and Cooperating Agencies and provide a venue for deliberation among the specialists.

Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

Draft Work Product- Intended for Deliberative Use Only Page 1 of 2

Note: This is a written explanation of the meeting and the materials included. All of these materials are in DRAFT form and have been made for the sole purpose of stimulating conversation and documenting any necessary information to be considered by the team.

Tailings Design Tech Transfer Meeting

May 12, 2009

The following people were invited to attend the meeting: Name

Company/Agency

The following people attended the meeting: Name Eli Curiel

Company/Agency Coronado National Forest

John Able Coronado National Forest Salek Shafiqullah Coronado National Forest Teresa Ann Ciapusci Coronado National Forest Bev Everson Coronado National Forest Walt Keyes Coronado National Forest Debby Kriegel Coronado National Forest Roger Congdon Coronado National Forest Tom Furgason SWCA Dale Ortman SWCA Melissa Reichard SWCA Mike Sieber SRK Clara Balasko SRK Orlanthia Henderson Town of Sahuarita Bob Casavant Arizona State Parks Bob Sejkora Arizona State Parks David Pfordt Town of Sahuarita Derek Wittwer AMEC John Lupo AMEC

Goal: This meeting was conducted in order to convey the technical information from the Dry Tailings design to the Forest Service and Cooperating Agencies and provide a venue for deliberation among the specialists.

Page 2: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

Draft Work Product- Intended for Deliberative Use Only Page 2 of 2

Meeting Overview: John Lupo of AMEC presented general information about tailing types and necessary processes involved. Derek Wittwer of AMEC had a much more detailed explanation of the tailings process, design and new possibilities in the design. Cooperating Agencies sent representatives to the meeting. The Forest Service specialists along with the Cooperators were able to ask detailed questions and make comments based on the presentation. There was much discussion about the technicalities of the process and design of Dry Stack Tailings in general and the proposal. List of attached presentations: Dry Tailings Overview Dry Tailings Facility Design List of attached handouts: None

Page 3: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

Proposed Rosemont Copper Project ID Team Meeting Guest Sign- In

Date I \\c Sf-e-Lc h

,,A , or1)9

First Name Last Name Company & Role

1 K.

r ,

7/4"/"e4

Oi-htvi1cw 5aYI "TD-4,3-y7 or EL.A,,A.e0). t 'i---g...--

--8,0 Ca o..poki•)'k- A - - S - -

c, 6 <S-TeL\ nca: 4-, 5---(-- 71-e_ )e-L-d--ks

1/U kl-1 t'CCie u sFs

/-<?‹,/e.f.Y-- C16 y7 .57c-* 5 n (.,ts-Fs ppi\i' i 0 77-eo k-cit --coo,,,,, o r Sckhuao::1--<\_.

Page 4: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

Proposed Rosemont Copper Project ID Team Meeting Sign-In

Date 5\1210 Dr

First Name

Alan

Andrea

Bev

Bob

Camille

Cara

Chris

Dave

Deanne

Debby

Deborah

Eli

Geoff

George

Glenn

Harmony

Heidi

Heidi

Janet

Jeanine

Jeff

Jennifer

Jerome

Joe

John

John

Keith

Ken

Kendall

Kendra

Kristen

La ra

Larry

Marcie

Mary

Melissa

Ralph

Reta

Rion

Last Name Belauskas

Campbell

Everson Lefevre Ensle

Bellavia

LeBlanc

Morrow

Rietz

Kriegel

Sebesta

Curiel

Soroka

McKay

Dunno

Hall

Orcutt-Gachiri

Schewel

Jones

Derby

Connell

Ruyle

Hesse

Ezzo

Able

MacIvor

Graves

Kertell

Brown

Bourgart

Cox

Mitchell

Jones

Bidwell

Farrell

Reichard

Ellis

Laford

Bowers

Role

Noise

NEPA Cornpliance/FOIA Officer

ID Team Leader Air Resources, Clean Water Act

Presentation

Social & Economic Environments Heritage

Air Resources

Hazardous Waste

Light (Night Skies)

Vegetation, Reclamation, Wildlife

Hazardous Waste, Mining Vegetation, Reclamation, Wildlife Access/Lands/Realty

Data Management

External Communications

Tech Editing

Media

Admin Support

Forest Supervisor

Social & Economic Environments

Forest Planner Geology

Heritage

Communications Team

SWCA Project Leader

Recreation, Social & Economic Env.

Wildlife Resources

Range

Team Admin Asst Light (Night Skies)

Data Management

Wildlife Resources

Recreation

Heritage

Team Admin Asst

Transportation/Engineering

Deputy Forest Supervisor Clean Water Act Compliance

Initials

Page 5: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

, 4e--5// 2/6 7

Roxane Raley Mailing Database Salek Shafiqullah Hydrologist, Hydrogeologist Shane Lyman Fire/Fuels Suzanne Griset Heritage Tami Emmett Access/Lands/Realty

Teresa Ann Ciapusci Ecosystem Management & Planning Tom Furgason SWCA Project Manager Tom Skinner Water Resources/Riparian Walt Keyes Transportation/Engineering William Gillespie Heritage

sf.--%0--c107414

Page 6: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

Rosemont Copper Project May 12, 2009

Last Name First Name CompanyAble John USFSBalasko Clara SRKCasavant Bob AZ State ParksCiapusci Teresa Ann USFSCongdon Roger USFSCuriel Eli USFSEverson Bev USFSFurgason Tom SWCAHenderson Orlanthia Town of SahuaritaKeyes Walt USFSOrtman Dale SWCAPfordt David Town of SahuaritaSebesta Debra USFSSejkora Bob AZ State ParksShafiqullah Salek USFSSieber Mike SRK

2009 05 12 Transcribed Participant List.xls

Page 7: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

1

Dry Stack Tailings OverviewDry Stack Tailings OverviewJohn F. Lupo, Ph.D., P.E.John F. Lupo, Ph.D., P.E.

Principal EngineerPrincipal Engineer

Introduction

Types of tailings materials Filtered (Dry Stack) tailings Benefits

Page 8: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

2

Tailings Materials Typesg yp

Tailings Continuum

Tailings Slurry

Thickened Tailings BL

E

Thin milk shake

Water w/ sand

NT

EN

T

Tailings Type Consistency

g

Paste Tailings

Wet Filtered Tailings

PU

MP

AP

UM

PA

BL

E

Wet Sand

Sandy yoghurt

RE

AS

ING

WA

TE

R C

O

Fully Saturated

Unsaturated

Dry Filtered Tailings NO

N-P

Moist SandDE

CR

Page 9: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

3

67 % Tailings Slurry: 30% solids by wt

Tailings Percent Water

42 %

27 %

Thickened Tailings: 60% solids by wt

Paste Tailings: 75% solids by wt27 %

19 %

Paste Tailings: 75% solids by wt

Filter Tailings: 18% moisture content

Tailings Slurry

Page 10: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

4

Tailings Slurry

Least water conservative. Losses to: Evaporation Seepage Lock-up (in tailings pore space)

Seepage issues depending on water quality and impoundment design

Water management (reclaim pool) critical to facility operation

Most often lowest operating cost option

Tailings Slurry Design Considerations

Containment dam: Usually High Hazard Impoundment of water pool Piping concerns through dam

Seepage management: Underdrains Underdrains Cut-off walls Pump back systems

Page 11: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5

Tailings Slurry Closure Considerations

Closure challenges:g Concurrent reclamation difficult Long-term consolidation settlements Water management (seepage, consolidation,

etc) continue during post-closure Changing geochemical environment (saturated g g g (

to unsaturated)

Thickened Tailings

Page 12: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

6

Thickened Tailings

Dewatered material but still a slurry. Better water conservative than slurry. Losses

to: Evaporation Seepage Lock-up (in tailings pore space)

Seepage issues depending on water quality Seepage issues depending on water quality and impoundment design

Moisture content control – deposition angle Non-segregating (suspended fines)

Thickened Tailings Design Considerations

Containment dam: Low, Medium, High Hazard Containment of process water and tailings Tailings “stacked” (.5 to 1 % slope) Stability of tailings stack (seismic, high rainfall,

etc)) Seepage management: Underdrains Pump back systems

Page 13: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

7

Thickened Tailings Closure Considerations

Closure challenges:g Concurrent reclamation difficult, but can be

accomplished after surface drying Long-term consolidation settlements Water management (seepage, consolidation,

etc) continue during post-closure Changing geochemical environment (saturated

to unsaturated)

Paste Tailings

Page 14: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

8

Paste Tailings

Dewatered, but still a slurry (100% saturated) Better water conservative than thickened.

Losses to: Evaporation Seepage Lock-up (in tailings pore space)

Seepage issues depending on water quality and impoundment design

Moisture content control - slope Non-segregating (suspended fines)

Paste Tailings Design Considerations

Containment dam: Low, Medium, High Hazard Containment of process water and tailings Tailings “stacked” (.5 to 3 % slope) Stability of tailings stack (seismic, high rainfall,

etc)) Seepage management: Underdrains Pump back systems

Page 15: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

9

Paste Tailings Closure Considerations

Closure challenges:g Concurrent reclamation difficult, but can be

accomplished after surface drying Long-term consolidation settlements Water management (seepage, consolidation,

etc) continue during post-closure Changing geochemical environment (saturated

to unsaturated)

Filtered Tailings

Page 16: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

10

What Are Filtered Tailings ?Crushing

CircuitMill

CircuitProcess Circuit

Recovered Metal

Tailings

ThickenerCommon to all tailings

Filter Press

Vacuum Belt/Plate

Filtered/Dry StackOR

Filtered Tailings

Most water conservative. Losses to: Evaporation Seepage Lock-up (in tailings pore space)

Seepage issues depending on water quality and impoundment design

Moisture content and dust control critical to facility operation

One of the highest operating cost option

Page 17: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

11

Filtered Tailings Design Considerations

Containment dam: Low to Medium Hazard Tailings stacked (+10% slope). Tailings become construction material. Stability of tailings stack. No liquefaction

Seepage management: Seepage management: Underdrains Pump back systems

Filtered Tailings Closure Considerations

Closure challenges:g Amenable to concurrent reclamation No long-term consolidation settlements Minimal water management during post-closure No changing geochemical environment

Page 18: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

12

Filtered Tailings Benefitsg

Filtered Tailings

Limited seepage compared to other tailings. Rate Rate Quantity

Material can be used as construction material Compacted fill with high shear strength.

Concurrent reclamationS f t t Surface water management No water pool to manage No chance of upset condition discharge

Page 19: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

13

Filtered Tailings Seepage

Saturated ~ 25 % Moisture Content

Seepage occurs as draindown from as-

As-Placed ~ 18 % Moisture Content

Moisture Content

Draindown moisture

draindown from as-placed to field capacity moisture content.

No water pool providing constant

Field Capacity ~ 11 % Moisture Content

recharge (like slurry tailings)

LIMITED VOLUME OF SEEPAGE WATER

Seepage Rates

Slurry tailings: 6.4 gpm/ac Paste/Thickened tailings: 0.4 gpm/ac Filtered tailings: 0.007 gpm/ac

Page 20: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

14

Construction

Dry Stack ExamplePogo - Alaska

Page 21: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

15

Dry Stack ExamplePogo - Alaska

Dry Stack ExampleLa Coipa Mine – Chile

Page 22: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

16

THANK YOU

Page 23: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

1

SSDry StackDry StackTailings Storage FacilityTailings Storage Facility

Advantages of Dry Stack TSF Over Conventional Advantages of Dry Stack TSF Over Conventional Slurry Tailings Slurry Tailings

Tailings are placed under unsaturated conditions resulting in minimal seepage

Dry Stack TSF not susceptible to breaching because there is no reclaim pond

Significant water conservation minimizes water usage and consumption requirements

Facilitates concurrent reclamation and revegetation during operation

Minimizes disturbance area

Minimizes visual impact from surrounding areas

Page 24: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

2

Dry Stack TSF Design CriteriaDry Stack TSF Design Criteria Production rate = 75,000 tpd (tons per day) or 27 MT per yearProduction rate = 75,000 tpd (tons per day) or 27 MT per year

Storage capacity estimated at 596 MT and mine life estimated at approximatelyStorage capacity estimated at 596 MT and mine life estimated at approximately Storage capacity estimated at 596 MT and mine life estimated at approximately Storage capacity estimated at 596 MT and mine life estimated at approximately 21 years21 years

Average tailings inAverage tailings in--place dry density = 109 pcf (pounds per cubic foot)place dry density = 109 pcf (pounds per cubic foot)

Compliance with all applicable regulations including the Arizona Best Available Compliance with all applicable regulations including the Arizona Best Available Demonstrated Control Technology (BADCT) standardsDemonstrated Control Technology (BADCT) standards

Rockfill Buttresses are placed around the perimeter of the facility in 50Rockfill Buttresses are placed around the perimeter of the facility in 50--foot high foot high lifts with 3H:1V side slopes and 25 foot bencheslifts with 3H:1V side slopes and 25 foot benches

3.5H:1V overall side slope3.5H:1V overall side slope

D St k TSF ill b t t d i t h (Ph I d II)D St k TSF ill b t t d i t h (Ph I d II) Dry Stack TSF will be constructed in two phases (Phases I and II)Dry Stack TSF will be constructed in two phases (Phases I and II)

Implement dust control suppression measures throughout the production periodImplement dust control suppression measures throughout the production period

Concurrent reclamation and revegetation during operationsConcurrent reclamation and revegetation during operations

Phase I Dry Stack TSF CharacteristicsPhase I Dry Stack TSF Characteristics Contains Approximately 12 years of productionContains Approximately 12 years of production

Maximum Buttress elevation = 5250 feetMaximum Buttress elevation = 5250 feet

Maximum Tailings surface elevation = 5237.5 feetMaximum Tailings surface elevation = 5237.5 feet

Total capacity = 343 million tons (MT)Total capacity = 343 million tons (MT)

Total footprint of 706 AcresTotal footprint of 706 Acres

Footprint outside of McCleary CanyonFootprint outside of McCleary Canyon

Page 25: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

3

Phase I Dry Stack TSF CharacteristicsPhase I Dry Stack TSF Characteristics Evaporation ponds will be incorporated into tailings lifts to capture Evaporation ponds will be incorporated into tailings lifts to capture

stormwater runoff from the tailings surfacestormwater runoff from the tailings surfacestormwater runoff from the tailings surfacestormwater runoff from the tailings surface

Temporary perimeter ditches will be constructed where necessary to route Temporary perimeter ditches will be constructed where necessary to route stormwater runoff to evaporation pondsstormwater runoff to evaporation ponds

A temporary diversion channel will be constructed at startA temporary diversion channel will be constructed at start--up to capture up to capture stormwater runoff upstream of the phase I Dry Stack TSF through stormwater runoff upstream of the phase I Dry Stack TSF through production year 4production year 4

A permanent Diversion Channel sized for the PMF and armored for the 200 A permanent Diversion Channel sized for the PMF and armored for the 200 year storm will be constructed at startyear storm will be constructed at start--up and will divert stormwater up and will divert stormwater yy ppupgradientupgradient of the plant site into of the plant site into McLearyMcLeary canyon north of Phase Icanyon north of Phase I

Phase I Dry Stack TSFPhase I Dry Stack TSF

Page 26: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

4

Phase I Dry Stack TSF Typical SectionsPhase I Dry Stack TSF Typical Sections

Phase I Dry Stack TSF Filling CurvePhase I Dry Stack TSF Filling Curve

Page 27: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

5

Phase II Dry Stack TSF CharacteristicsPhase II Dry Stack TSF Characteristics

Contains approximately 8 years of production Contains approximately 8 years of production pp y y ppp y y p

Maximum Buttress elevation = 5250 feetMaximum Buttress elevation = 5250 feet

Maximum Tailings surface elevation = 5237.5 feetMaximum Tailings surface elevation = 5237.5 feet

Total capacity = 253 million tons (MT)Total capacity = 253 million tons (MT)

Total footprint 400 AcresTotal footprint 400 Acres

Phase II Dry Stack TSF CharacteristicsPhase II Dry Stack TSF Characteristics Evaporation ponds will be incorporated into tailings lifts to capture runoff Evaporation ponds will be incorporated into tailings lifts to capture runoff

from the tailings surfacefrom the tailings surfacefrom the tailings surface from the tailings surface

Temporary perimeter ditches will be constructed where necessary to divert Temporary perimeter ditches will be constructed where necessary to divert stormwaterstormwater to evaporation pondsto evaporation ponds

An additional permanent diversion channel will be constructed in year 12 to An additional permanent diversion channel will be constructed in year 12 to divert divert stormwaterstormwater upstream of phase II as well as from the diversion channel upstream of phase II as well as from the diversion channel upgradientupgradient of the Plant siteof the Plant site

Dry Detention Basins will be constructed as part of Permanent Diversion Dry Detention Basins will be constructed as part of Permanent Diversion Channel system and will greatly reduce peak runoff produced by storm Channel system and will greatly reduce peak runoff produced by storm y g y p p yy g y p p yeventsevents

Page 28: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

6

Phase II Dry Stack TSFPhase II Dry Stack TSF

Phase II Dry Stack TSF Typical SectionsPhase II Dry Stack TSF Typical Sections

Page 29: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

7

Phase II Dry Stack TSF Filling CurvePhase II Dry Stack TSF Filling Curve

Ultimate Dry Stack TSFUltimate Dry Stack TSF

Page 30: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

8

Dry Stack TSFDry Stack TSFProduction ProgressionProduction Progression

Production Year 0 to Year 1Tailings capacity = 30 MT

Page 31: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

9

Production Year 2 to Year 5Tailings capacity = 153 MT

Production Year 6 to Year 10Tailings capacity = 288 MT

Page 32: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

10

Production Year 11 to Year 12Tailings capacity = 333 MT

End of Phase I-Start of Phase IIProduction Year 13

Tailings capacity = 357 MT

Page 33: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

11

Production Year 14 to Year 15Tailings capacity = 425 MT

Production Year 16 to Year 20Ultimate Dry Stack TSF

Tailings capacity = 586 MT

Page 34: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

12

Dry Stack TSF Site ConditionsDry Stack TSF Site Conditions

ClimateClimate Tetra Tech conducted the meteorological analysis as part of their Feb 2009 design Tetra Tech conducted the meteorological analysis as part of their Feb 2009 design

processprocessMonth Precipitation Pan Evaporation Projected Pan EvaporationMonth Precipitation Pan Evaporation Projected Pan EvaporationJanuary 1.10 3.59 4.13February 0.85 4.46 4.28

March 0.90 7.01 7.11April 0.39 9.35 8.50May 0.22 11.91 10.38June 0.47 13.31 10.75July 4.34 10.00 4.93

August 4.13 8.28 2.89September 1.55 8.06 4.40

October 1.33 7.17 6.15November 0.66 4.49 4.11December 1.43 3.57 3.89

Total 17.37 91.20 71.52

Event 1-Hour 3-Hour 6-Hour 24-Hour2-yr 1.42 1.60 1.83 2.215-yr 1.85 2.03 2.30 2.7510-yr 2.16 2.38 2.68 3.1825-yr 2.57 2.86 3.22 3.7750-yr 2.87 3.24 3.66 4.23100-yr 3.17 3.63 4.12 4.75500-yr 3.84 4.59 5.24 6.001000-yr 4.14 5.03 5.76 6.57

Page 35: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

13

Site Geology SummarySite Geology Summary

Project specific geology is discussed in the Tetra Tech report entitled “Geologic Project specific geology is discussed in the Tetra Tech report entitled “Geologic j p g gy p gj p g gy p gHazards Assessment” dated June 2007Hazards Assessment” dated June 2007

The geologic units underlying the Dry Stack TSF includeThe geologic units underlying the Dry Stack TSF include

•• Gila ConglomerateGila Conglomerate

•• Mount Fagan Mount Fagan RhyoliteRhyolite

•• Apache Canyon FormationApache Canyon Formation

•• Willow Creek FormationWillow Creek Formation

•• Alluvial materialsAlluvial materials

Page 36: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

14

Seismic Hazard Analysis SummarySeismic Hazard Analysis Summary

The Maximum Credible Earthquake (MCE) based on a deterministic The Maximum Credible Earthquake (MCE) based on a deterministic q ( )q ( )analysis was used for the design of the TSFanalysis was used for the design of the TSF

The deterministic analysis included:The deterministic analysis included:•• Identifying the largest potentially active fault close to the siteIdentifying the largest potentially active fault close to the site•• Determining earthquake magnitude that the fault is capable of producingDetermining earthquake magnitude that the fault is capable of producing•• Determining the Peak Ground Acceleration (PGA) that will be produced at the site from this Determining the Peak Ground Acceleration (PGA) that will be produced at the site from this

eventevent

The Santa Rita fault zone determined to be the controlling of 27 The Santa Rita fault zone determined to be the controlling of 27 contributing fault sources within a 200 kilometer radius of the project site contributing fault sources within a 200 kilometer radius of the project site with a distance from site of 11.2 kilometers and a length of with a distance from site of 11.2 kilometers and a length of

i t l 52 kil ti t l 52 kil tapproximately 52 kilometers.approximately 52 kilometers.

The Santa Rita fault zone capable of producing a PGA of 0.33g and a The Santa Rita fault zone capable of producing a PGA of 0.33g and a magnitude 7.1 eventmagnitude 7.1 event

Geotechnical InvestigationGeotechnical Investigation

Geotechnical field investigation were carried out in two phases by Tetra Geotechnical field investigation were carried out in two phases by Tetra g p yg p yTech, between November 2006 and March 2007 and between May and July Tech, between November 2006 and March 2007 and between May and July of 2008. The objective of the investigations included the following:of 2008. The objective of the investigations included the following:

•• To define general subsurface conditions for use in evaluation of the Dry Stack TSF stabilityTo define general subsurface conditions for use in evaluation of the Dry Stack TSF stability

•• To identify suspect zones that could affect the performance of the Dry Stack TSFTo identify suspect zones that could affect the performance of the Dry Stack TSF

•• To quantify engineering characteristics of the materials incorporated into the Dry Stack TSFTo quantify engineering characteristics of the materials incorporated into the Dry Stack TSF

A total of 10 test pits and 38 geotechnical borings in the vicinity of the Dry A total of 10 test pits and 38 geotechnical borings in the vicinity of the Dry Stack TSF allowed subsurface conditions to be definedStack TSF allowed subsurface conditions to be defined

A total of approximately 13,000 feet of seismic refraction survey was also A total of approximately 13,000 feet of seismic refraction survey was also completed near the vicinity of the Dry Stack TSF footprintcompleted near the vicinity of the Dry Stack TSF footprint

Page 37: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

15

Geotechnical InvestigationGeotechnical Investigation

Geotechnical Investigation SummaryGeotechnical Investigation Summary

Depth of Bedrock varied across the footprint from 0 to 100 feetDepth of Bedrock varied across the footprint from 0 to 100 feet

Average depth to bedrock approximately 40 feetAverage depth to bedrock approximately 40 feet

Soils included 1 to 3 feet of topsoil underlain by alluvial materialSoils included 1 to 3 feet of topsoil underlain by alluvial material

Groundwater elevations vary across the footprint from elevations 4,650 Groundwater elevations vary across the footprint from elevations 4,650 to 4,850 feetto 4,850 feet

Page 38: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

16

Geotechnical Investigation SummaryGeotechnical Investigation Summary

The foundation consists primarily of relatively shallow, dense to very dense The foundation consists primarily of relatively shallow, dense to very dense granular soils.granular soils.

Foundation preparation will require stripping loose Foundation preparation will require stripping loose surficialsurficial soils providing a soils providing a uniformly dense founding surface for the tailings.uniformly dense founding surface for the tailings.

A Laboratory testing program was completed on select disturbed samples and A Laboratory testing program was completed on select disturbed samples and bench scale tailing samples obtained from field investigations and pilot plant bench scale tailing samples obtained from field investigations and pilot plant studies.studies.

Two bench scale tailings samples, Colina and MSRDTwo bench scale tailings samples, Colina and MSRD--1 were tested. Both samples 1 were tested. Both samples were determined to be lowwere determined to be low--plastic silt (ML) with a plasticity index of 1.plastic silt (ML) with a plasticity index of 1.

Colina maximum dry density of 115.8 at 14.9%Colina maximum dry density of 115.8 at 14.9% MSRDMSRD--1 maximum dry 1 maximum dry denstiydenstiy of 118.9 at 14.8%of 118.9 at 14.8%

Geologic Hazard SummaryGeologic Hazard Summary

Landslides or rockfall hazard potential will be minimal within the Dry Stack Landslides or rockfall hazard potential will be minimal within the Dry Stack TSF project area.TSF project area.

Collapsible soils are not considered to be an issue within the footprint.Collapsible soils are not considered to be an issue within the footprint.

Historic mining activity will require further field reconnaissance to Historic mining activity will require further field reconnaissance to determine the extent of workings for remediation purposes.determine the extent of workings for remediation purposes.

Earthquake induced ground failure (liquefaction) is not anticipated to Earthquake induced ground failure (liquefaction) is not anticipated to occur within either the foundation or the Dry Stack TSF.occur within either the foundation or the Dry Stack TSF.yy

Page 39: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

17

Tailings Testing SummaryTailings Testing Summary

Other laboratory testing performed on the bench scale tailings samples included:Other laboratory testing performed on the bench scale tailings samples included:•• OneOne--Dimensional ConsolidationDimensional Consolidation•• TriaxialTriaxial ShearShear•• Flexible Wall PermeabilityFlexible Wall Permeability•• Rigid Wall PermeabilityRigid Wall Permeability•• Moisture Retention TestingMoisture Retention Testing•• Geochemical Tailings Characterization (Tetra Tech)Geochemical Tailings Characterization (Tetra Tech)

AcidAcid--Base AccountingBase Accounting Net Acid GenerationNet Acid Generation pH TestingpH Testing Humidity Cell Testing (Kinetic)Humidity Cell Testing (Kinetic) Synthetic Precipitation LeachingSynthetic Precipitation Leaching Meteoric Water MobilityMeteoric Water Mobility

•• Solids Liquid SeparationSolids Liquid Separation FlocculantFlocculant Screening and EvaluationScreening and Evaluation Static ThickeningStatic Thickening Dynamic High Rate ThickeningDynamic High Rate Thickening Pulp Pulp RheologyRheology Pressure Filtration StudiesPressure Filtration Studies Vacuum Filtration StudiesVacuum Filtration Studies

Geochemical Test ResultsGeochemical Test Results

Tailings generally contain less than 0.01 percent sulfideTailings generally contain less than 0.01 percent sulfide--sulfursulfur

Tailings possess high capacity for acid neutralizationTailings possess high capacity for acid neutralization

Tailings produce very low metal concentrations in the resulting leachateTailings produce very low metal concentrations in the resulting leachate

TotalTotal--sulfur concentrations less than 0.3 percent and a neutralization potential ratio sulfur concentrations less than 0.3 percent and a neutralization potential ratio greater than 3greater than 3

Testing indicate the tailings meet ADEQ criteria as inertTesting indicate the tailings meet ADEQ criteria as inert Testing indicate the tailings meet ADEQ criteria as inertTesting indicate the tailings meet ADEQ criteria as inert

Page 40: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

18

Engineering Properties of TailingsEngineering Properties of Tailings

Laboratory gradations of the tailings indicate an average of approximately 72.6 Laboratory gradations of the tailings indicate an average of approximately 72.6 percent by weight passing the No. 200 sievepercent by weight passing the No. 200 sieve

Atterberg limit testing indicates the tailings have:Atterberg limit testing indicates the tailings have:•• PI of 1PI of 1•• PL of 20PL of 20•• LL of 21LL of 21

The tailings classify as a lowThe tailings classify as a low--plastic silt (ML), as defined by the USCSplastic silt (ML), as defined by the USCS

A ff ti h t th i t l 36 5 dA ff ti h t th i t l 36 5 d Average effective shear strength approximately 36.5 degreesAverage effective shear strength approximately 36.5 degrees

Engineering Properties of Alluvium/FoundationEngineering Properties of Alluvium/Foundation

Average Average of approximately 26.8 percent by weight passing the No. 200 sieveof approximately 26.8 percent by weight passing the No. 200 sieve

Atterberg limits ranging between nonAtterberg limits ranging between non--plastic and 26plastic and 26

Average effective shear strengths ranging between 33 and 41 degrees with Average effective shear strengths ranging between 33 and 41 degrees with cohesions ranging between 1,600 and 2,500 psfcohesions ranging between 1,600 and 2,500 psf

Page 41: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

19

Dry Stack TSFDry Stack TSFDesignDesign

Dry Stack TSF DesignDry Stack TSF Design

The Dry Stack TSF consists of two separate areas referred to as Phase I The Dry Stack TSF consists of two separate areas referred to as Phase I y py pand Phase IIand Phase II

Phase I is located between the McCleary Canyon wash and the Waste Phase I is located between the McCleary Canyon wash and the Waste Rock Storage Area (12 years, 343 MT)Rock Storage Area (12 years, 343 MT)

Phase II is an extension of the phase I facility and will be constructed Phase II is an extension of the phase I facility and will be constructed north of Phase I within McCleary Canyon (years 12north of Phase I within McCleary Canyon (years 12--21, 253 MT)21, 253 MT)

Tailings properties were determined through testing of bench scale Tailings properties were determined through testing of bench scale tailings samples.tailings samples.

The specified moisture range of placed tailings is 15% (by weight) plus or The specified moisture range of placed tailings is 15% (by weight) plus or minus 3%. minus 3%.

Page 42: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

20

Dry Stack TSF DesignDry Stack TSF Design

Foundation preparation will include clearing and grubbing, tree removal, Foundation preparation will include clearing and grubbing, tree removal, p p g g g, ,p p g g g, ,access road construction and topsoil salvaging and stockpiling.access road construction and topsoil salvaging and stockpiling.

In the TSF footprint, most of the existing natural drainages will be filled In the TSF footprint, most of the existing natural drainages will be filled with inert rock and function as flowwith inert rock and function as flow--through drains.through drains.

An initial starter buttress will be constructed in the lower Barrel Canyon An initial starter buttress will be constructed in the lower Barrel Canyon drainage to accommodate three months of tailings storage.drainage to accommodate three months of tailings storage.

Rockfill Buttresses will advance ahead of tailings in 50Rockfill Buttresses will advance ahead of tailings in 50--foot high lifts foot high lifts using upstream construction methods.using upstream construction methods.

Buttresses will have 150Buttresses will have 150--foot top widths to accommodate twofoot top widths to accommodate two--way haul way haul traffic and outer slopes of 3H:1V.traffic and outer slopes of 3H:1V.

Dry Stack TSF DesignDry Stack TSF Design

Dry tailings will be delivered from the filter plant by conveyor and placed Dry tailings will be delivered from the filter plant by conveyor and placed y g p y y py g p y y pin 25in 25--foot lifts using a radial stacker upgradient of the Rock Buttress.foot lifts using a radial stacker upgradient of the Rock Buttress.

Tailings will be spread with a dozer and compacted with a vibratory Tailings will be spread with a dozer and compacted with a vibratory smooth drum roller to provide compaction for trafficability of the smooth drum roller to provide compaction for trafficability of the conveyor and to minimize dust.conveyor and to minimize dust.

The outer perimeter of the tailings beneath the Rock Buttress will be The outer perimeter of the tailings beneath the Rock Buttress will be placed in 5placed in 5--foot lifts and compacted 90% of standard proctor density.foot lifts and compacted 90% of standard proctor density.

A bypass conveyor will be provided to allow temporary disposal of tailings A bypass conveyor will be provided to allow temporary disposal of tailings d i i t i t t ditid i i t i t t ditiduring primary conveyor movement, maintenance or upset conditions.during primary conveyor movement, maintenance or upset conditions.

Page 43: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

21

Dry Stack TSF DesignDry Stack TSF Design

FlowFlow--through drains will be constructed of 12through drains will be constructed of 12--inch minus rockfill and inch minus rockfill and ggseparated from the tailings above by a layer of 10 oz/ydseparated from the tailings above by a layer of 10 oz/yd22 geotextile.geotextile.

Seepage is anticipated to peak at year 18 at a rate of 8.4 gpm. Seepage is anticipated to peak at year 18 at a rate of 8.4 gpm.

Natural seepage and springs will be captured with collection drains Natural seepage and springs will be captured with collection drains consisting of shallow trenches filled with rockfill wrapped in 10 oz/ydconsisting of shallow trenches filled with rockfill wrapped in 10 oz/yd22

nonnon--woven geotextile.woven geotextile.

Existing water wells within the Dry Stack TSF footprint will be abandoned Existing water wells within the Dry Stack TSF footprint will be abandoned according to ADWR regulations.according to ADWR regulations.

Dry Stack TSFDry Stack TSFSurface Water ManagementSurface Water Management

Page 44: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

22

Dry Stack TSF Surface Water ManagementDry Stack TSF Surface Water Management

Water management will be addressed in the Water Management Plan to Water management will be addressed in the Water Management Plan to g gg gbe submitted in July 2009. General water management concepts specific be submitted in July 2009. General water management concepts specific to the Dry Stack TSF are listed below:to the Dry Stack TSF are listed below:

Perimeter ditches and evaporation ponds will collect stormwater runoff Perimeter ditches and evaporation ponds will collect stormwater runoff from the tailings surfacefrom the tailings surface

FlowFlow--through drains will allow stormwater that does not come into through drains will allow stormwater that does not come into contact with tailings to be routed beneath the Dry Stack TSFcontact with tailings to be routed beneath the Dry Stack TSF

Diversion channels will be constructed in two phases concurrent with the Diversion channels will be constructed in two phases concurrent with the D St k TSF h Th ill b i d t th PMF d dD St k TSF h Th ill b i d t th PMF d dDry Stack TSF phases. They will be sized to pass the PMF and armored Dry Stack TSF phases. They will be sized to pass the PMF and armored to protect against the 200 year/24 hour storm.to protect against the 200 year/24 hour storm.

A Temporary diversion channel will be constructed upstream of the initial A Temporary diversion channel will be constructed upstream of the initial lifts of phase I and will function through year 4lifts of phase I and will function through year 4

Dry Stack TSFDry Stack TSFSeepage AnalysisSeepage Analysis

Page 45: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

23

Dry Stack TSF Seepage AnalysisDry Stack TSF Seepage Analysis Seepage analysis conducted using the finite element method based Seepage analysis conducted using the finite element method based

computer program computer program SVFluxSVFlux Version 2.0.13Version 2.0.13

Tailings modeled at average moisture content of 18% (or less) by weightTailings modeled at average moisture content of 18% (or less) by weight

OneOne--dimensional tailings column models were incrementally evaluated dimensional tailings column models were incrementally evaluated using 50 foot lifts to the full height of 550 feetusing 50 foot lifts to the full height of 550 feet

Developed Developed isopachisopach maps representing average depths of tailings for each maps representing average depths of tailings for each lift and phaselift and phase

Each successive model incorporated the pore water distributions from the Each successive model incorporated the pore water distributions from the previous modelprevious modelprevious modelprevious model

Dry Stack TSF Seepage AnalysisDry Stack TSF Seepage Analysis Included climatic flux comprised of environmental factors including

precipitation, pan evaporation, relative humidity and temperature.precipitation, pan evaporation, relative humidity and temperature.

The greatest average annual precipitation of 22.2 inches was used, and the lowest average annual pan evaporation of 71.5 inches was used.

The dry stack tailings are considered to be relatively homogeneous in nature.

Laboratory testing was performed to determine hydraulic conductivity at various depths.

Hydraulic conductivity ranges between 4 x 10-3 cm/sec near the top of the Dry Stack TSF and 6 x 10-7 cm/sec at depths of 50 feet or greater.

Page 46: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

24

Saturated Hydraulic Conductivity With DepthSaturated Hydraulic Conductivity With Depth

Dry Stack TSF Seepage AnalysisDry Stack TSF Seepage Analysis

A series of moisture retention laboratory tests were completed on the y ptailings samples .

These tests were used to develop a soil water characteristic curve (SWCC) for the tailings materials.

The SWCC defines the soil’s ability to store and release moisture.

Page 47: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

25

Soil Water Characteristic CurveSoil Water Characteristic Curve

INSERT SWCC CurvesINSERT SWCC Curves

Relative Hydraulic Conductivity FunctionRelative Hydraulic Conductivity Function

Page 48: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

26

Dry Stack TSF Seepage Analysis ResultsDry Stack TSF Seepage Analysis Results

As the Dry Stack TSF expands over time, the estimated seepage rate y p , p gincreases to a peak value of approximately 8.4 gpm, at production year 18.

The upper 8 feet of the tailings performs as a storage-release unit, where moisture lost to evaporation is replenished by precipitation.

Based on the model, the seepage is due solely to drainage of pore water.

Meteoric influences will have a small recharging effect on the top several feet of tailings, but due to the large evaporation rate there will be an overall negative flux at the surface.

A two-dimensional model of the ultimate Dry Stack TSF was also developed to verify the results.

Seepage Over Life of MineSeepage Over Life of Mine

Page 49: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

27

Seepage After Life of MineSeepage After Life of Mine

Moisture Content with Depth Over TimeMoisture Content with Depth Over TimeNote:The data represents a typical 100-foot column. h lThe initial moisture

content was modeled at 18% by weight

Page 50: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

28

Dry Stack TSF Seepage Analysis ResultsDry Stack TSF Seepage Analysis Results

The estimated maximum seepage from the Dry Stack TSF is expected to p g y pbe 0.007 gpm/acre. For comparison, the following tailings disposal methods and associated expected seepage rates are as follows:

Slurry Tailings (no liner) 6.4 gpm/acre Slurry Tailings (with liner) 0.06 gpm/acre Paste and Thickened tailings 0.4 gpm/acre

Dry Stack TSFDry Stack TSFStability AnalysisStability Analysis

Page 51: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

29

Dry Stack TSF Stability AnalysisDry Stack TSF Stability Analysis

Establishment of stability design criteria for static and seismic loading Establishment of stability design criteria for static and seismic loading y g gy g gconditions based upon laboratory testing, field investigation, and seismic conditions based upon laboratory testing, field investigation, and seismic hazard analysishazard analysis

Development of representative cross sections.Development of representative cross sections.

Completion of static and seismic stability analyses utilizing limit Completion of static and seismic stability analyses utilizing limit equilibrium methods.equilibrium methods.

Slope stability was evaluated using Spencer’s method.Slope stability was evaluated using Spencer’s method.

Dry Stack TSF Stability Analysis MethodologyDry Stack TSF Stability Analysis Methodology

The minimum factors of safety used in accordance with the BADCT The minimum factors of safety used in accordance with the BADCT yyGuidance Manual guidelines are 1.3 and 1.0 for static and seismic Guidance Manual guidelines are 1.3 and 1.0 for static and seismic analyses, respectively with appropriate laboratory and field testing.analyses, respectively with appropriate laboratory and field testing.

The stability of the Dry Stack TSF under earthquake loading was The stability of the Dry Stack TSF under earthquake loading was evaluated using the pseudostatic approach.evaluated using the pseudostatic approach.

The cross sections were developed at the maximum sections of the The cross sections were developed at the maximum sections of the facilityfacility

For conservatism, the tailings 1,100 feet from the crest of the buttress For conservatism, the tailings 1,100 feet from the crest of the buttress d l d h i t thd l d h i t thwere modeled as having no strength.were modeled as having no strength.

Page 52: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

30

Dry Stack TSF Stability Analysis Material Dry Stack TSF Stability Analysis Material PropertiesProperties

Material Type

MoistUnit Weight

(lbs/ft³)

Effective Stress AnalysisStrength Parameters

Total Stress AnalysisStrength Parameters

Friction Angle(degrees)

Cohesion(lbs/ft2)

Friction Angle(degrees)

Cohesion(lbs/ft2)

Alluvium / Colluvium 130 36 0 - -

Tailings 110 28 0 18 1,300

Compacted Tailings 116 32 0 - -Tailings

No Strength Tailings 110 0 0 - -

Rockfill 125 38 0 - -

Dry Stack TSF Stability Analysis ResultsDry Stack TSF Stability Analysis Results

For tailing impoundment facilities the minimum factors of safety, as required by the For tailing impoundment facilities the minimum factors of safety, as required by the g p y q yg p y q yBADCT Guidance Manual, are 1.3 and 1.0 for static and seismic analyses.BADCT Guidance Manual, are 1.3 and 1.0 for static and seismic analyses.

Cross Section Analysis ModeledStatic

Factor of SafetyPseudostatic

Factor of Safety

Phase IEffective 2.3 1.2

Total 1.9 1.0

Ph IIEffective 2.3 1.2

Phase II Total 1.9 1.0

Page 53: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

31

Dry Stack TSF Stability Analysis Dry Stack TSF Stability Analysis -- LiquefactionLiquefaction

Liquefaction can be generally defined as the loss of shear strength in loose, Liquefaction can be generally defined as the loss of shear strength in loose, q g y gq g y gsaturated, and saturated, and cohesionlesscohesionless soils due to the generation of excess pore pressures as soils due to the generation of excess pore pressures as a result of large shear strains induced by a result of large shear strains induced by undrainedundrained cyclic loading.cyclic loading.

The dry stack tailings will be unsaturated and will be under large confining pressures The dry stack tailings will be unsaturated and will be under large confining pressures producing a uniformly dense fill, hence the propensity for liquefaction will be very producing a uniformly dense fill, hence the propensity for liquefaction will be very low and is not anticipated to occurlow and is not anticipated to occur

The majority of native foundation soils were very dense or hard for granular and fine The majority of native foundation soils were very dense or hard for granular and fine grained material and are not susceptible to liquefaction.grained material and are not susceptible to liquefaction.

Phase I Stability AnalysisPhase I Stability Analysis

Page 54: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

32

Phase II Stability AnalysisPhase II Stability Analysis

Dry Stack TSFDry Stack TSFClosure ConceptClosure Concept

Page 55: Tailings Design Tech Transfer Meeting May 12, 2009 The ... · Maximum Tailings surface elevation = 5237.5 feet Total capacity = 253 million tons (MT) Total footprint 400 Acres Phase

5/12/2009

33

Dry Stack TSF Closure ConceptDry Stack TSF Closure Concept

The primary goal of closure/postThe primary goal of closure/post--closure plan is to eliminate any closure plan is to eliminate any p y g pp y g p p yp yreasonable probability of further discharge from the Dry Stack TSF.reasonable probability of further discharge from the Dry Stack TSF.

Concurrent with operations, portions of the Dry Stack TSF will be Concurrent with operations, portions of the Dry Stack TSF will be reclaimed to reduce erosion due to wind and water.reclaimed to reduce erosion due to wind and water.

The top of the Dry Stack TSF will be graded inward to create an The top of the Dry Stack TSF will be graded inward to create an evapotranspirationevapotranspiration pond capable of containing the PMP.pond capable of containing the PMP.

The top of the Dry Stack TSF will be The top of the Dry Stack TSF will be revegetatedrevegetated with native seed mixes with native seed mixes designed to maximize designed to maximize evapotranspirationevapotranspiration..