2
Tasmanian Irrigation NEIS Newsletter November 2017 Scheme Update We are pleased to announce that the successful design and construct contractors for the North Esk Irrigaon Scheme are Gradco Pty Ltd, who will build the dam, and Shaw Contracng (Aust.), who will build the pump staons and pipeline network. Landholders will have received noficaon indicang that access to their property, for the purposes of survey and construcon works, will be required. This noficaon enables the contractor to undertake necessary preliminary surveys and design works and is the first trigger for their contact and engagement with landholders. Through the tender process, an opportunity to modify the dam design slightly such that the White Hills boost pump can be removed was idenfied. This is a significant benefit to the scheme as it will further improve the operang efficiencies of the scheme as all distribuon lines, except for the Logan line, will now be able to be delivered under gravity. For those on the White Hills line, this will provide an esmated operang cost saving of around $15.00 per ML. Second Instalment Payment for 10% deposits With the commencement of construcon planning and works, TI will now issue invoicing for the 8% remaining for the water purchase contract deposits. This will also mean that those wanng to transfer their rights are now able to do so. Construcon The majority of landholders will deal with Shaw Contracng in their capacity as the pipeline designers and installers. Shaws landholder liaison will seek to meet with every landholder to work with them to understand the construcon requirements (both landholder and contractor) for every property. Construcon works will inially focus on the transfer pipeline, North Esk pump staon and the new dam located on Dalness with the distribuon network construcon later in the pro- ject. The contractors will complete a Landholder access agreement with each property holder to confirm what works are proposed, the locaon of infrastructure to be installed, the locaon of exisng farm infrastructure to be worked around, ming and restoraon. These agreements form the cornerstone for ensuring works are completed as agreed with landholders post construcon. Noce under the Irrigaon Clauses Act 1973. As part of the commencement of construcon, Tasmanian Irrigaon have issued noce under the Irrigaon Clauses Act to relevant landholders of our intenon to commence work. This is a statutory noce required and indicates the formal commencement of the design and construcon works. From this point, the contractors will connue to contact landhold- ers directly in relaon to works and land access. Construcon Schedule Broadly, the current construcon plans will see the period through to the end of January 2018 used for the detailed design and planning required for construcon. This period will be used parcularly by Shaw for establishing landholder access agreements, walking the alignment and finalising the pipeline and infrastructure locaons. The period to May 2018 will primarily focus on construcon of the Rocklands Dam on the Dalness property, the North Esk pump staon and transfer pipelines. Construcon of the distribuon network is targeted to be complete by the end of 2018. Shaw Contracng (Aust.) hps://www.shawcontracng.com.au/ Shaw Contracng have a long relaonship with Tasmanian Irrigaon projects and have completed the Winnaleah Irriga- on Scheme augmentaon, including upgrade of the Frome Dam in 2011, The Sprent Dam at the Kindred North Moon Scheme, Lake Leake Dam repair, Arthurs Lake inlet works, the Dunns Creek Dam associated with the Upper Ringarooma scheme, the South Riana Dam and the Dial Blythe Irrigaon Scheme pumps and pipeline network. They are currently working on the Duck Irrigaon Scheme at Smithton where they are the sole contractor responsible for the construcon of both the Mill Creek Dam and the pipelines and pump staon contracts. Shaws project Manager will be Mike Lurell with IPD Consulng the design engineers and Cromarty as the communicaons contractor. North Esk Irrigation Scheme Copyright Tasmanian Irrigation November 2017—Page 1

Tasmanian Irrigation · Aaron Cassidy – TI Scheme Engineer 0400 143 114 [email protected] Working Group harles Watson 0417 390 848 Peter Lindsay 0417 320 503 Kellie

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Tasmanian Irrigation · Aaron Cassidy – TI Scheme Engineer 0400 143 114 aaron.cassidy@tasirrigation.com.au Working Group harles Watson 0417 390 848 Peter Lindsay 0417 320 503 Kellie

Tasmanian Irrigation

NEIS Newsletter November 2017

Scheme Update

We are pleased to announce that the successful design and

construct contractors for the North Esk Irrigation Scheme are

Gradco Pty Ltd, who will build the dam, and Shaw Contracting

(Aust.), who will build the pump stations and pipeline

network.

Landholders will have received notification indicating that

access to their property, for the purposes of survey and

construction works, will be required. This notification enables

the contractor to undertake necessary preliminary surveys

and design works and is the first trigger for their contact and

engagement with landholders.

Through the tender process, an opportunity to modify the

dam design slightly such that the White Hills boost pump can

be removed was identified. This is a significant benefit to the

scheme as it will further improve the operating efficiencies of

the scheme as all distribution lines, except for the Logan line,

will now be able to be delivered under gravity. For those on

the White Hills line, this will provide an estimated operating

cost saving of around $15.00 per ML.

Second Instalment Payment for 10% deposits

With the commencement of construction planning and

works, TI will now issue invoicing for the 8% remaining for the

water purchase contract deposits. This will also mean that

those wanting to transfer their rights are now able to do so.

Construction

The majority of landholders will deal with Shaw Contracting in

their capacity as the pipeline designers and installers. Shaw’s

landholder liaison will seek to meet with every landholder to

work with them to understand the construction requirements

(both landholder and contractor) for every property.

Construction works will initially focus on the transfer pipeline,

North Esk pump station and the new dam located on Dalness

with the distribution network construction later in the pro-

ject.

The contractors will complete a Landholder access agreement

with each property holder to confirm what works are

proposed, the location of infrastructure to be installed, the

location of existing farm infrastructure to be worked around,

timing and restoration. These agreements form the

cornerstone for ensuring works are completed as agreed with

landholders post construction.

Notice under the Irrigation Clauses Act 1973.

As part of the commencement of construction, Tasmanian

Irrigation have issued notice under the Irrigation Clauses Act

to relevant landholders of our intention to commence work.

This is a statutory notice required and indicates the formal

commencement of the design and construction works. From

this point, the contractors will continue to contact landhold-

ers directly in relation to works and land access.

Construction Schedule

Broadly, the current construction plans will see the period

through to the end of January 2018 used for the detailed

design and planning required for construction. This period

will be used particularly by Shaw for establishing landholder

access agreements, walking the alignment and finalising the

pipeline and infrastructure locations.

The period to May 2018 will primarily focus on construction

of the Rocklands Dam on the Dalness property, the North

Esk pump station and transfer pipelines. Construction of the

distribution network is targeted to be complete by the end

of 2018.

Shaw Contracting (Aust.)

https://www.shawcontracting.com.au/

Shaw Contracting have a long relationship with Tasmanian

Irrigation projects and have completed the Winnaleah Irriga-

tion Scheme augmentation, including upgrade of the Frome

Dam in 2011, The Sprent Dam at the Kindred North Motton

Scheme, Lake Leake Dam repair, Arthurs Lake inlet works,

the Dunn’s Creek Dam associated with the Upper

Ringarooma scheme, the South Riana Dam and the Dial

Blythe Irrigation Scheme pumps and pipeline network. They

are currently working on the Duck Irrigation Scheme at

Smithton where they are the sole contractor responsible for

the construction of both the Mill Creek Dam and the

pipelines and pump station contracts.

Shaw’s project Manager will be Mike Luttrell with IPD

Consulting the design engineers and Cromarty as the

communications contractor.

North Esk Irrigation Scheme

Copyright Tasmanian Irrigation November 2017—Page 1

Page 2: Tasmanian Irrigation · Aaron Cassidy – TI Scheme Engineer 0400 143 114 aaron.cassidy@tasirrigation.com.au Working Group harles Watson 0417 390 848 Peter Lindsay 0417 320 503 Kellie

This newsletter contains information of a general nature and reasonable care has been taken to ensure accuracy at the time of

publication. Scheme details and policies may change and individual circumstances may vary. This newsletter should not be relied

upon as a basis of individual decision-making. For more information and details regarding the articles in this issue,

please contact:

Tasmanian Irrigation Pty Ltd, PO BOX 84 Evandale, TAS, 7212.

Ph: 03 6398 8433 www. tasirrigation.com.au

If you would prefer to receive this newsletter electronically please email [email protected]

North Esk Irrigation Scheme

Copyright Tasmanian Irrigation November 2017 —Page 2

Gradco Pty. Ltd

https://www.gradco.com.au/

Gradco is a well-respected Launceston civil contracting firm who have also worked on several projects with Tasmanian

Irrigation. Gradco has constructed the 6,000ML Milford dam which is part of the Lower South Esk Irrigation Scheme and

the recently completed 7,600ML Southernfield Dam at the Southern Highlands Irrigation Scheme. Tom Diprose will be

Gradco’s Project Manager with GHD Consulting the design engineers.

Figure 1: North Esk Irrigation Scheme Transfer pipeline and Dalness Dam will be the focus of works to May 2018

Contacts

Mike Luttrell – Shaw Contracting 0409 560 107 [email protected]

Tom Diprose – Gradco 0408 326 867 [email protected]

Ian Smith - TI Project Manager 0488 153 346 [email protected]

Aaron Cassidy – TI Scheme Engineer 0400 143 114 [email protected]

Working Group

Charles Watson 0417 390 848 Peter Lindsay 0417 320 503

Kellie Hoffmann 0407 531 271 Jim Cuming 0477 774 344

Michael Hart 0408 542 024 Andrew Hogarth 0438 918 177

Tom Graesser 0407 161 856