79
GOVERNMENT OF THE PUNJAB IRRIGATION AND POWER DEPARTMENT PROJECT MANAGEMENT OFFICE TAUNSA BARRAGE EMERGENCY REHABILITATION AND MODERNIZATION PROJECT El 031 VOL. 2 CHANGE MANAGEMENT STATEMENT (FINAL) MAY 2006 PUNJAB BARRAGES CONSULTANTS CONSULTANCY SERVICES FOR CONSTRUCTION SUPERVISION A JOINT VENTURE OF r National Development Consultants (Regd), National Engineering Services Pakistan, 62-M Gulberg-III, Lahore _ 1-C, Block-N, Model Town Extension, Lahore In Association with ATKINS ATKINS Global (Water) UK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

GOVERNMENT OF THE PUNJABIRRIGATION AND POWER DEPARTMENT

PROJECT MANAGEMENT OFFICE

TAUNSA BARRAGE EMERGENCY REHABILITATIONAND MODERNIZATION PROJECT

El 031VOL. 2

CHANGE MANAGEMENT STATEMENT(FINAL)

MAY 2006

PUNJAB BARRAGES CONSULTANTSCONSULTANCY SERVICES FOR CONSTRUCTION SUPERVISION

A JOINT VENTURE OF

r National Development Consultants (Regd), National Engineering Services Pakistan,62-M Gulberg-III, Lahore _ 1-C, Block-N, Model Town Extension, Lahore

In Association with

ATKINS ATKINS Global (Water) UK

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

TAUNSA BARRAGE EMERGENCY REHABILITATION AND

MODERNIZATION PROJECT

CHANGE MANAGEMENT STATEMENT

TABLE OF CONTENTS

EXECUTIVE SUMMARY .................. 1

BACKGROUND ............. 1-1

1.1 THE CHANGE IN THE PROJECT ....................................... 1-11.2 OBJECTIVES OF CMS .. 1-2

1.2.1 The Problems .1-21.2.2 The Solutions .1-31.2.3 Changes in Construction Design .1-31.2.4 Implementation .1-61.2.5 Salient Features of the Proposed Changes .1-6

1.3 EIA, EMP & EMMP .. 1-91.3.1 Adequacy of Provisions in EIA, EMP and EMMP Proposed Change

Management .1-91.3.2 Impacts Due to Change .1-111.3.3 Public Hearing .1-121.3.4 Public Disclosure .1-12

1.4 CHANGE MANAGEMENT PROVISION . .1-121.5 TAUNSA BARRAGE WILDLIFE SANCTUARY AND RAMSAR SITE .. 1-13

2. SCOPE OF CHANGE, JUSTIFICATION AND BENEFITS ........................................... 2-1

2.1 LABOUR CAMP .. 2-12.2 WORK PLACE ON THE RIGHT SIDE DOWNSTREAM . .2-12.3 WORK PLACE ON THE LEFT SIDE DOWNSTREAM . .2-22.4 CONSTRUCTION ACTIVITY UPSTREAM OF BARRAGE GATE LINE .. 2-2

2.4.1 Construction of Coffer Dam .2-22.4.2 Piezometers .2-22.4.3 Grouting Activities .2-3

2.5 EXTENDED CLOSURE OF CANALS . .2-32.6 LEAD CHANNEL FOR D.G. KHAN CANALS . .2-32.7 WORKS ON MECHANICAL GATES (ICB-02) . .2-4

2.7.1 Fabrication and Installation of Gates .2-42.7.2 Building of Workplace Area for ICB-02 .2-42.7.3 Work of Silt Excluder D.G. Khan Canal Headworks .2-42.7.4 Construction of Jetty .2-52.7.5 Change of Earth Borrow Areas .2-5

3. ANALYSIS OF ADVERSE IMPACTS CAUSED DUE TO CHANGES ........................ 3-1

Page 3: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

3.1 ADVERSE IMPACTS DUE TO LABOUR CAMP RIGHT SIDE UPSTREAM3-13.2 ADVERSE IMPACTS DUE TO WORKPLACE ON THE RIGHTSIDE,

DOWNSTREAM ......................................................... 3-33.3 ADVERSE IMPACTS DUE TO WORKPLACE ON THE LEFT SIDE

DOWNSTREAM ........... 3-33.4 ADVERSE IMPACTS DUE TO CONSTRUCTION ACTIVITIES UPSTREAM

OF BARRAGE GATE LINE .......................... 3-43.4.1 Work of Silt Excluder .......................... 3-43.4.2 Construction of Coffer Dam .......................... 3-43.4.3 Piezometer .......................... 3-53.4.4 Grouting Activities .......................... 3-5

3.5 ADVERSE IMPACTS DUE TO EXTENDED CLOSURE OF CANALS &LOWERING OF WATER LEVELS IN PONDED AREA ................................. 3-5

3.6 ADVERSE IMPACTS DUE TO LEAD CHANNEL FOR FEEDING D.G. KHANCANAL .3-6

3.7 CHANGE OF EARTH BORROW AREAS .3-73.8 ADVERSE IMPACTS DUE TO WORKS ON THE MECHANICAL GATES ...3-7

3.8.1 Fabrication and Installation of Gates .3-73.8.2 Building of Workplace Area for ICB-02 .3-83.8.3 Construction of Jetty .3-83.8.4 Upgrading of the existing fish ladders .3-9

3.9 CUMULATIVE IMPACTS IN PONDED AREA . .3-93.10 EVALUATION OF ENVIRONMENTAL IMPACTS OF CHANGE

MANAGEMENT OF TAUNSA BARRAGE REHABILITATION ANDMODERNIZATION PROJECT . .3-10

4. SUPPLEMENTARY ENVIRONMENTAL MANAGEMENT PLAN (EMP) .................... 4-1

4.1 GENERAL .. 4-14.2 MITIGATION PLAN FOR CHANGE . .4-14.3 MANAGEMENT OF CHANGES IN SOCIO-ECONOMIC IMPACTS .. 4-254.4 ENVIRONMENTAL MANAGEMENT MONITORING PLAN (EMMP) FOR

CHANGES IN EMP I.E. CHANGES IN EMMP . .4-254.5 INSTITUTIONAL ARRANGEMENTS FOR CHANGE MANAGEMENT.. 4-25

4.5.1 Management Responsibility .4-254.5.2 Institutional Strengthening .4-254.5.3 Reporting and Supervision .4-264.5.4 Financial Implications .4-26

4.6 RECOMMENDATIONS . .4-264.6.1 Avoidance through Design of New Structures and Work Designs . 4-264.6.2 Contractor's Obligation towards Change Management .4-264.6.3 Social Framework Agreement (SFA) readjustments with Change

Management .4-274.6.4 PMO Responsibilities in Change Management .4-274.6.5 Supervision Consultants Role in Change Management .4-274.6.6 Action by wildlife department Punjab in Change Management . 4-274.6.7 Action by Environment Protection Department (EPD) in Change

Management .4-284.6.8 Action by WWF in Change Management .4-294.6.9 Donor's Patronage in Change Management .4-294.6.10 Operational Management Readjustments with Change Management 4-29

NDC i NESPAK I ATKINS ii

Page 4: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

LIST OF TABLES

Table 3.1 Evaluation of Change Management Impacts

Table 4.1 Supplemental Environmental management Plan (EMP) for Change

Management

LIST OF ANNEXES

Annex-I: Taunsa Barrage Wildlife Sanctuary and the Taunsa Barrage.

Annex-Il: Location of Facilities and Works for Change Management

NDC I NESPAK I ATKINS Hii

Page 5: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

ACRONYMS & ABBREVIATIONS

BOQ Bill of Quantities

CCA Canal Command Area

CMS Change Management Statement

CRE Chief Resident Engineer

DGK Dera Ghazi Khan

EIA Environment Impact Assessment

EMMP Environment Management Monitoring Plan

EMP Environment Management Plan

EPD Environment Management Department

EU Environmental Unit

ICB International Contract Bidding

JICA Japanese International Cooperation Agency

NGO Non Governmental Agency

OP Operational Plan

PDWP Provincial Department Working Party

PEPD Provincial Environmental Protection Department

PM Project Manager

PMO Project Management Office

PWD Pakistan Wildlife Department

RAP Resettlement Action Plan

RE Resident Engineer

SFA Social Framework Agreement

TBWS Taunsa Barrage Wildlife Sanctuary

WWF World Wide Fund for Conservation of Nature

NDC I NESPAK I ATKINS iv

Page 6: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

I

EXECUTIVE SUMMARY

Page 7: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

EXECUTIVE SUMMARY

Taunsa Barrage Rehabilitation and Modernization Project was taken up by the World Bankon fast track. Consequently its EIA study was carried out when the details of constructiondesign had not yet been fully worked out. Consequently while setting up the site constructionfacilities, some new requirements and activities emerged which could not be anticipated atthe initial stage. Also, at the time of writing the EIA, the barrage from the Guide Bunds downto the gateline, according to the interpretation of the Irrigation and Power Department, wasconsidered to be outside the wildlife sanctuary and the Ramsar site. However, in retrospectthis interpretation was incorrect, as the barrage falls inside the official boundaries of thewildlife sanctuary. The change of status of works upstream of gateline has thereforenecessitated the need for further changes. These change include clearance of additionalland for work bases on the right and left banks downstream; shifting of a part of the labourcamp and batching plants upstream adjacent to the right bank; construction of earthencofferdam upstream; construction of workplace and jetty upstream left side; construction ofsilt excluder and lead channel for feeding DG Khan canal. Further, the closure of canalswhich is normally limited to 5 weeks is now expected to be about 12 weeks. Some works likefixing of piezometers and filling up cavities in old civil works structures (bascially, the base ofthe barrage) by grouting will also take place upstream. As it is now realised that the Taunsabarrage is partially located within a wildlife sanctuary and Ramsar site, an approval for thechanges is necessary. This Change Management Statement (CMS) is therefore beingsubmitted.

Detailed analysis of the environmental and social impacts for Taunsa Barrage is contained inthe comprehensive EIA. This CMS makes reference to only those impacts which are likely toemerge only as a result of the changes. These identified impacts have been, analyzed andevaluated viz-a-viz the necessity and benefits of the proposed changes. Based upon that, asupplemental Environmental Management Plan has been produced.

CMS suggests that the Change Management has essentially been necessitated by thebelated realization that the entire barrage up to the gateline is included in the wildlifesanctuary. So for the purpose of Change Management, 61 possible impacts have beendivided into those to be handled at construction stage (98%) and those to be mitigated atoperational stage (2%). The supplemental EIA prescribes the mitigation measures for all theadverse factors. The CMS concludes that the envisaged change is manageable andpracticable and almost all the required mitigation measures are already included in thecomprehensive EIA. A separate Change Management Statement will be prepared by theend of June 2006, covering (i) the identification and mitigation of impacts associated with lowflows in the DG Khan canal in the period extending from December 2005 through February2006, and (ii) measures to mitigate the impacts of any proposed future extensions of thecanal closure period.

NDC I NESPAK I ATKINS 1

Page 8: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

The CMS recommends various actions to be taken by all concerned organizations andDepartments. It also seeks formal approval of the proposed changes from the concernedauthorities.

NDC I NESPAK I ATKINS 2

Page 9: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

1. BACKGROUND

Page 10: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

1. BACKGROUND

1.1 THE CHANGE IN THE PROJECT

The Taunsa Barrage Rehabilitation and Modernization Project has a comprehensive

Environmental Assessment Report (EIA), wherein paragraphs 1.1 and 1.2 in Chapter 1

amply describe the Taunsa Barrage Rehabilitation and Modernization Project.

In view of the emergent threat of possible toppling over of the barrage, the World Bank

accepted to take up the Project following fast track procedures. The EIA study was carried

out last year and completed in September 2004. At the time, details of the construction

design had been worked out only on a tentative basis, and not all information had become

available. Since then two major 'changes' have occurred:

* the final design includes new land requirements and activities that have emerged

since September 2004, which were not anticipated by the Irrigation and Power

Department (I&PD) at the time of offering information for the EIA; and

* it has become apparent that the assertion in the EIA that the Taunsa Barrage Wildlife

Sanctuary (TBWS) is located to the north of the barrage guide banks (and therefore

outside all anticipated activities) was incorrect, as the sanctuary's southern boundary

coincides with the gate line of the barrage.

These changes have necessitated the formulation of this Change Management Statement

(CMS), to ensure that newly emerging environmental issues are adequately dealt with. Both

categories of change are described in below, and in more detail in 1.2.3 and 1.2.5; the

location of the changes is indicated in the map included as Annex-1.

New land requirements and activities. The field realities and nature of the works have led to

the expansion and/or adaptation of the original design with following activities:

* clearing of additional land for work bases on the right and left banks downstream of

the barrage;

* shifting of a part of the labor camp and batching plants upstream to right side of the

barrage, adjacent to the right guide bund;

* planned construction of an earthen coffer dam to facilitate construction activities

upstream of the barrage gate line;

construction of a work place and jetty for facilitating the works on mechanical gates;

construction of a silt excluder and construction of a lead channel for feeding D.G.

Khan canal;

NDC I NESPAK I ATKINS 1-1

Page 11: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

* the closure of canals, which is normally limited to five weeks, is now expected to be

extended to about 12 weeks to facilitate adequate time for de-silting, repair and

maintenance of the canal;

* fitting of piezometers on the upper side of the barrage line;

* adjustment of the existing fish ladders; and

* the grouting of existing masonry structures on the upper side of the barrage line.

The expansion of the work bases beyond the original design has also lead to the

displacement and resettlement of 800 persons (157 households). This is beyond the scope

of the approved EIA, and therefore necessitated the formulation and implementation of a

Resettlement Action Plan (RAP). Relocation has already occurred, although final

resettlement still needs to be completed as at the time of formulating the CMS, pending

acceptance of the compensation rates.

Taunsa Barrage Wildlife Sanctuary. The EIA was carried out on the assumption that all

works and activities carried out between the guide bunds and the gate line fell within the

barrage limits and were located outside the boundaries of the Taunsa Barrage Wildlife

Sanctuary and Ramsar site. However, this assumption was mistaken, as subsequent

information from the Punjab Wildlife Department made it clear that the southern boundary of

the TBWS coincides with the gate line of the barrage. An approval from PWD is therefore

necessary before carrying out any physical changes upstream of the barrage as this area is

located within the TBWS. As a result, a Change Management Statement (CMS) has become

an absolute necessity, to meet both national and World Bank requirements. The latter was

clearly stated in the Aide Memoire of Supervision Mission (September 25-October 5, 2005),

which reads as follows: "No activities will commence within TBWS before a CMS acceptable

to the World Bank is approved by the PEPD and PWD."

1.2 OBJECTIVES OF CMS

1.2.1 The Problems

The location of some of the proposed works, such as the silt excluder, coffer dam, lead channel

for feeding D.G. Khan canal, placing of piezometers, grouting work and jetty are of special

concern as the water body upstream of the barrage gates is located within the Taunsa Barrage

Wildlife Sanctuary (TBWS), which has been designated a Ramsarl site since 22nd March 1996.

' Ramsar sites are areas designated as 'Wetlands of International Importance' under the Ramsar Convention onWetlands of International Importance, especially as Waterfowl Habitat (Ramsar, Iran, 1971). The repository forRamsar sites is UNESCO.

NDC I NESPAK I ATKINS 1-2

Page 12: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

The other construction works such as the labor camp, the work base for ICB-02, and the activity

of fabrication and installation of gates are located outside the limits of the TBWS. However, as

they are located in close proximity to the TBWS, these works and activities are likely to impact

the nearby wetland and TBWS. Therefore, the entire set of the upstream works and activities

can be regarded a potential direct threat to the TBWS and the Ramsar site. On the downstream

side, the expansion of the work bases has caused displacement and shifting of 800 persons

(157 households - 21 on the right and 136 on the left banks). This activity has also taken place

beyond the scope of the approved EIA. In nutshell, major changes in the construction design

and layout have taken place, and therefore a change management statement has become

necessary.

1.2.2 The Solutions

The approved Environment Management Monitoring Plan (EMMP) for the Project allows for

preparation of a Change Management Statement (CMS) to assess and manage the

environmental and social impacts of such unanticipated works and activities. As per

provision in the EMMP, this CMS has been produced collectively by the PMO, Supervision

Consultants (PBC) and the Construction Contractor (DESCON).

1.2.3 Changes in Construction Design

Sr CagsPooe Work / Activity As provided in approved EIA Changes Proposed

No. Resulted

1. Site for labor camp, At the old workshop area Right side of the river

equipment yard, (Refer EIA para. 3.9.1, page upstream, about 100 meters

batching plant and 3.15, Figure 3.1) from the right protection

Japanese International bund on the unused borrow

Cooperation Agency area (Refer item 7 at page

(JICA) work base 6-11 of EIA)

2. Work place on right At the end of the right d/s The area expanded to about

side downstream protection bund in available 9 acres, leading to the need

open place on about 5 acres for relocation and

(Refer EIA para. 3.9.4 page resettlement of 21

3-21) households, under RAP.

NDC I NESPAK I ATKINS 1-3

Page 13: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

3. Work place on left side At the end of the left d/s The work place expanded to

downstream protection bund in already about 14 acres leading to

available open place on the need for relocation and

about 9 acres (Refer to EIA resettlement of 136

para. 3.9.4 page 3-21) households, under RAP.

4. Works of silt excluder Already provided in EIA at Due to more complete

at the head of D.G. present site (Refer EIA page information, the site now

Khan canal 3-7, para. 3.4). falls inside the TBWS and

hence requires approval/

concurrence by PEPD, PWD

and WB.

5. Construction of coffer Not in EIA, as it is a new Requirement for carrying out

dam upstream of the addition. construction upstream on

barrage. the gates and silt excluder.

Temporary earthen coffer

dam across width of

barrage; falls within TBWS.

6. Piezometer installation Not in EIA, as it is a new An instrument for measuring

addition. magnitude and direction of

river pressure; is to be

buried in the river floor;

located within TBWS.

7. Grouting activity Not in EIA, as it is a new The old masonry of the main

upstream addition. barrage structure, now

almost 50 years old, needs

strengthening by means of

grouting. Located within the

TBWS.

8. Fabrication and Not in EIA, as it is a new Being part of ICB-02, it is an

installation of gates addition. additional work to the civil

works of ICB-01. Mostly

outside the barrage area,

but inside the TBWS.

NDC NESPAK I ATKINS 1-4

Page 14: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

9. Building of work place Not in EIA, as it is a new Required for Fabrication of

for ICB-02 addition. the Gates. Will be built in the

unused borrow area on left

side upstream. Located

inside the TBWS.

10. Construction of jetty Not in EIA, as it is a new This will be a platform/jetty

addition. combination built on the left

bank and protruding out into

the ponded area by about 6

meters. Both platform and

jetty are located in the

TBWS.

11. Canal closure Not in EIA, as this In order to accommodate

requirement was not the physical work above and

foreseen at the time. below the barrage closure

required from November 15

to February 15 (12 weeks),

instead of usual 5 weeks.

Water levels will be reduced,

but within normal limits.

12. Lead channel for Not in EIA, as this This is to supply water to

feeding DGK canal requirement was not D.G. Khan canal during

foreseen at the time. extended drought period.

Consists of excavation of

silted up canal used during

construction in the 1950s.

Located in TBWS.

13. Change of earth Original borrow areas are Because of availability of

borrow areas located beside the right and earth from D.G. Khan canal

left guide bunds (Refer bank spoils, the earth was

Project map as Figure 3.1 of obtained from there. A small

EIA reproduced as Annex-2 part of the proposed borrow

of CMS. Also before para. 6- area has been used for

11, item 7, of EIA.) constructing the Contractor's

campsite on the right and for

NDC I NESPAK I ATKINS 1-5

Page 15: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

creating ICB-02 work place

and jetty on the left side.

14. Fish ladders. Not foreseen in EIA. The two existing fish ladders

no longer meet current

standards, and will be

adjusted at request of

Fisheries Department.

1.2.4 Implementation

Once approved, the 'Change Management' shall be implemented through the same chain of

command and control as is for the main Project. See para. 1.2.4 on page 1-7 of the EIA.

1.2.5 Salient Features of the Proposed Changes

The proposed changes shall have the following salient features:-

1. Labor Camp: A part of the contractor's camp facilities were shifted to the present

location for a better utilization of the site. On approval of Change Management, the site

shall house the facilities of labor camp, batching plants, vehicle & equipment yard, pre-

cast yard and work base for activities funded by the Japanese Intemational Cooperation

Agency (JICA) over the Project period, on about 20 acres.

2. Work place on the right side downstream: The work base, on approval, shall expand

to just over 9 acres (from the original 5 acres), which will be adequate for the housing

work base and the material depot.

3. Work place on the left side downstream: The work base, on approval, shall expand

to over 14 acres (from the original 9 acres), and shall be adequate for housing work

base, material yard, vehicle yard and batching plant.

4. Silt Excluder: A Silt Excluder has been proposed in 3 out of 4 bays of the right pocket

of the barrage, in front of the Head Regulator for D.G. Khan Canal, to exclude heavier

silt particles from the water flowing into the D.G. Khan canal and reduce the high level

of siltation in the canal. The silt excluder consists of 12 rectangular reinforced concrete

(RCC) barrels varying in length from 253 ft to 27 ft, the largest being adjacent to the

Head Regulator. It has a design discharge capacity of about 25,000 cusecs.

5. Coffer dam on upstream side: In order to facilitate the civil works on the upstream

side a temporary earthen coffer dam shall be built in parts, across the width of the river

above the gate line, which is 4648 ft. Its approval is necessary to facilitate the other

NDC I NESPAK I ATKINS 1-6

Page 16: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

upstream works. Once the works have been completed, the coffer dam will be flattened,

and it is expected that the material will largely be flushed out of the system and washed

downstream in 1-2 seasons. This will partly be retained between the barrage and the

newly constructed weir downstream of the barrage, thereby adding to the protection of

the toe of the barrage. The coffer dam will be constructed one compartment at a time,

and each compartment will be demolished after it has served its purpose.

6. Piezometers: These are the instruments that will measure the water pressure. Their

installation near the inside base of the main barrage structure does not add any volume

on the size of civil work, but enhances the technical capacity of barrage management.

7. Grouting activities: These are necessary to fill up cavities that have gradually formed

within (and mainly at the base of) existing main barrage structures, so as to reinforce

the strength of these structures. A quick-hardening cement slurry will be fed by pipes

into existing cavities, following the removal of loose fragments. It will not involve external

work.

8. Fabrication and installation of gates: As ICB-02, JICA have offered to

repair/rehabilitate 29 out of 65 gates of the barrage. The width of the barrage between

the abutments is 4648 ft. The clear span between piers is 60 ft, and width of the piers is

7 ft while the height of the gate in weir portion is 19 ft and in the under sluice it is 19 ft.

The barrage contains a 22 ft. navigation gate and two fish ladder with spans of 20 ft

each.

9. Building of work place area for ICB-02: A work place shall be built by Japanese

Engineers for carrying out works for replacement of the gates and fixing their

operational components. This will be located on left side upstream of the barrage and

near the head regulator of TP Link canal; this will be located in an unused borrow area

located in the wildlife sanctuary.

10. Construction of jetty: The jetty / plafform shall consist of an earthen structure paved

with concrete, and with a fixed set of rails; it will be located on the left bank just

upstream of the left pocket. Construction will not require piling. This platform/jetty will be

used for transporting the gates to/from a barge or boat, and from there to the barrage

gate line. The platform will be about 100 meters wide and located east of the left guide

bank, while the jetty shall protrude about 6 meters into the barrage ponded area. Both

jetty and platform will be located in the wildlife sanctuary.

11. Canal closure: In order to accommodate the physical work above and below the

barrage, canal closure will be required from November 15 to February 28 (15 weeks)

for the D.G. Khan canal, extended from the existing annual close of five weeks. For

the two other primary canals, the closure shall be shorter - from 15 December to

early to late February (9-12 weeks), instead of the normal 5 weeks. During closure

NDC I NESPAK I ATKINS 1-7

Page 17: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

the water level in pond area shall be lowered, but not below the normal range, as it

will be stabilized at a level of about 430-431 ft at the barrage, which is normal during

this time of the year. It will take about 1 1/2 days for water levels to drop, and once the

works have been completed, about a same time to fill again.

12. Lead channel for feeding DGH canal: The Lead Channel is needed to supply water

to D.G. Khan Canal during the extended period during which there will not be any

flow through the three primary canals. The command area of the D.G. Khan canal

has limited groundwater availability (of dubious quality), and the lead channel flow

will serve to provide drinking water to the area during the construction period. The

canal command areas (CCAs) of the two other primary canals located on the left

bank (TP-Link Canal and Muzaffargarh Canal) have ample groundwater of good

quality; hence there will not be a similar requirement for supplying drinking water to

these areas. Also, the CCA of the Muzaffargarh Canal is equipped with many deep

tubewells for irrigation purposes, while the CCA of the TP-Link Canal is supplied with

water via this conduit only when required, and pending availability. The Lead

Channel will not be a new structure, as use will be made of the channel used during

construction in the 1950s. As this has silted up to some extent, works will consist of

desilting/excavation. It is located within the boundary of the TBWS.

13. Change of earth borrow areas: Borrow areas are located beside the right and left

guide bunds (Refer Project map as Figure 3.1 of EIA reproduced as Annex-2 of

CMS. Also before para. 6-11, item 7, of EIA.). Because of availability of earth from

D.G. Khan Canal bank spoils, the earth was obtained from there. A small part of the

borrow area has been used for constructing the Contractor's campsite on the right

bank, and for creating the ICB-02 work place and the jetty on the left bank.

14. Upgrading of fish ladders. Two 20 ft wide fish ladders were installed during

construction of the barrage in the 1950s. These are located downstream, between the

central weir and the left and right pockets, respectively. While they facilitate the

migration of some fish species, they are not particularly effective: they are too small for

movement of dolphins, and do not meet current standards. They are also in need of

repairs, as the gates have disappeared, they are silted up, and some of the concrete

structures are damaged. Both will be repaired, or replaced by more modem structures,

as the Fisheries Department has been requested to provide details of an improved

design. Works entailed with this are located downstream of the barrage gate line.

NDC I NESPAK I ATKINS 1-8

Page 18: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

1.3 EIA, EMP & EMMP

1.3.1 Adequacy of Provisions in EIA, EMP and EMMP Proposed Change

Management

Sr Item of Change Related Provision in Status of Adequacy of

No. Management E IA/EMP/EMMP Mitigation Cover

1 Site for labor camp, New site. Only general Site specific mitigation of

equipment yard, batching provisions have been adverse impacts need

plant and JICA work base mentioned in EIA para. improvement by way of

3.9.1 page 3.15 and Figure creating a buffer zone and

3.1 along with EMP No 1.1, finding appropriate disposal

1.3, 1.5 para. 8.10.2, of solid and liquid waste.

EMMP para. 8.7 and table

8.2 also item 7 at page 6-11

of EIA.

2 Construction of workplace Expanded site. General Site specific adverse

on the right side provisions contained in EIA factors need improvement;

downstream para. 3.9.4, page 3-21 and mitigation of social impacts

the EMP. required through RAP.

3 Construction of workplace Expanded site. Only Site specific adverse

on the left side downstream general provision contained factors need improvement;

in EIA para. 3.9.4, page 3- mitigation of social impacts

21 and the EMP. required through RAP.

4 Construction of coffer dam New work on a fresh site. It has to be examined for

upstream Not indicated in the EIA. adverse factors that require

mitigation and allied

suggestions.

5 Installation of piezometer New work on a fresh site. It has to be examined for

upstream Not indicated in the EIA. adverse factors that require

mitigation and allied

suggestions.

6 Grouting activity upstream New work not indicated in It has to be examined for

the EIA. adverse factors that require

mitigation and allied

NDC i NESPAK I ATKINS 1-9

Page 19: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Item of Change Related Provision in Status of Adequacy of

No. Management EIA/EMP/EMMP Mitigation Cover

suggestions.

7 Fabrication and installation New work not indicated in It has to be examined for

of gates the EIA. adverse factors that require

mitigation.

8 Building of work place for Not mentioned in EIA. It has to be examined for

ICB-02 adverse factors that require

mitigation and allied

suggestions.

9 Construction of jetty New work not indicated in It has to be examined for

the EIA. adverse factors that require

mitigation and allied

suggestions.

10 Canal closure Covered in the EIA in 6.2, It has to be examined for

page 6-4. adverse factors that require

mitigation and allied

suggestions.

11 Change of earth borrow Initially the borrow pits were It has to be examined for

areas located on upstream right adverse factors that require

and left side. Some borrow mitigation and allied

area has been used as site suggestions.

for buildings shown project

map as Figure 3.1 of EIA,

reproduced as Annexe-2 of

CMS. Also para. 6.11, item

7 of EIA.

12 Lead channel for feeding New work. It has to be examined for

DGK canal adverse factors that require

mitigation.

13 Works pertaining to silt New work. EIA para. 3.4 It has to be examined for

excluder DGK canal head page 3-7 only describes it. adverse factors that require

mitigation.

14 Fish ladders. New work, not described in It has to be examined for

EIA. adverse factors that require

mitigation.

NDC I NESPAK I ATKINS 1-10

Page 20: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

1.3.2 Impacts Due to Change

1 2 3 4 5 6 7 8 9

C -o ~~~~~~~~~~~~0Sr. Item under 9! E, m> CD0 3 -CD-CD ) %Jn aCf 0 - 0.

No Examination j0.D o a - CD0 CD CD

_ 0) D) Cfl -, Cfl ~~: -o 0. 0

-' -, ~~ ~ ~~CD 0f

1 Site for labor camp,

equipment yard, /

batching plant and

J ICA work base

2 Workplace on the

right site V / / / V

downstream

3 Workplace on the

left side downstream

4 Work pertaining to

silt excluder DGK X /

canal head

5 Coffer dam

construction / V

upstream

6 Installation of

piezometer

7 Grouting activity

upstream

8 Fabrication and

installation of gates

9 Building of work

base for ICB-02

10 Construction of jetty X/ V

11 Canal closure / / / V /

12 Lead channel for

feeding DGK canal

13 Change of earth X V

borrow areas

14 Fish ladders V _

See further explanation in chapter 3.

NDC I NESPAK I ATKINS 1-11

Page 21: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

1.3.3 Public Hearing

Chapter 6 of the EIA describes the outcome of the public consultation, held with different

stakeholder groups who may be affected by the project. The consultation process was

carried out in accordance with the World Bank Operational Policy (OP 4.01) on Public

consultation. Details of the process and the outcome are given in chapter 6 of the EIA. It

may be added here that during the Public hearing, when the representative of PMO

answered the questions from members of the Public, they were under the impression that

the barrage consisted of the gate line and the water up to the upper ends of the Guide

Bunds. Accordingly, the part of the river below the line joining the upper ends of Guide

Bunds was considered to be outside the Wildlife Sanctuary. Therefore, in one of her

answers, the PMO representative incorrectly stated that the construction activity shall be

downstream of the barrage and outside the bounds of the Wildlife Sanctuary and the

Ramsar site. It was further stated that any construction (within or below the barrage) will in

no way cause any negative impact on Indus Dolphin, and the flora and fauna of the ponded

area within the Taunsa Barrage. This position has now changed in view of the recognition

that the southern boundary of the TBWS coincides with the gate line of the barrage. All the

construction works to be carried out upstream of the barrage gate line fall within the Wildlife

Sanctuary and therefore require concurrence of the Wildlife Department as part of the

Change Management being proposed.

1.3.4 Public Disclosure

Copies of the EIA were placed at the Office of the EPB Punjab, the Project Site Office i.e.

Taunsa Barrage Control Office and the Punjab Public Library Lahore, so as to be accessible

to the project beneficiaries, local NGOS and general public. In addition, a public

announcement board providing the salient features of the EIA has been placed at the

barrage. An approved Change Management Statement, as a supplement to the main EIA,

shall also be placed at all the points where main EIA was disclosed.

1.4 CHANGE MANAGEMENT PROVISION

For monitoring the implementation of the EMP a comprehensive EMMP has been provided

in para. 8.7 of the EIA. An approved Change Management Statement shall form an essential

supplement to the EMP in the EIA. As a minimum, the monitoring plan provided in table 8.2

of the EIA shall also be followed for the CMS. For institutional arrangements, the provisions

of para. 8.8 of the EIA are also considered adequate for the change management.

NDC I NESPAK I ATKINS 1-12

Page 22: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Accordingly, all new EMP points have been highlighted for appending to the approved

EMMP by the PMO.

1.5 TAUNSA BARRAGE WILDLIFE SANCTUARY AND RAMSAR SITE

The Taunsa Barrage Wildlife Sanctuary was first gazetted in 1974, and designated as a

Ramsar site in 1996. It is world class protected area, providing a habitat for rare species

such as the Indus Dolphin Platanista minor, otter Lutra perspicillata and hog deer Axis

porcinus. The area upstream of the Taunsa barrage provides a habitat for a population of

about 84 Indus dolphins2. The site also forms an important wintering area for waterbirds

(especially ducks), a breeding area for several species (notably whistling duck Dendrocygna

javanica, of which 325 in August 1995), and a staging area for cranes (Grus grus and

Anthropoides virgo) and shorebirds. Over 24,000 waterbirds were present during the mid-

January count in 1987, with a total of 21 species. Since then, mid-winter bird counts have

been considerably lower, numbering 3,128 in 1994 (24 spp.), 8,826 in 1997 (21 spp.),

11,142 in 1999 (28 spp.), 10,880 in 2000 (35 spp.) and 4,640 in 2001 (24 spp.)3 . Species

lists and further details are provided in para. 4.3.3 and 4.3.4 of the EIA. Reportedly,

migratory waterbirds arrive in December, and remain until February.

The main areas utilized by the waterbirds are the main barrage water body (ponded area),

and the main island (Matwani Wala). The latter is largely covered with a dense, woody

vegetation dominated by Tamarix dioica and Tamarix articulata, with Populus euphratica

further inland. This is interspersed with open patches of grass and sedgeland, dominated by

Saccharum spontaneum, Saccharum (Erythrium) munja, Cynodon dactylon, Typha

elephantina and Cyperus sp., and small (temporary) bodies of water with lotus (Nelumbo).

The official PWD boundary of the reserve is as indicated in the Map in Annex-1, which gives

the TBWS a total area of 6,756 ha. According to the Ramsar description, the sanctuary has

been renotified by the PWD in 1983, 1988 and again in 1993. More recently (in 1999), a draft

renotification has been submitted to the PWD by the District WD in Muzaffargarh. This as yet

not accepted revision would reduce the area to 7,000 acres (or 2800 ha), and basically

consist of the main barrage water body between the two guard bunds, and only a small

southern part of the main island (Matwani Wala). It must be noted that areas outside the

2 These are not only located in the ponded area near the barrage, but may be found anywhere between theChashma and Taunsa barrages, although they prefer large expanses of deeper water.3Asian Waterfowl Census, coordinated by Wetlands International (www.wetlands.org).

NDC I NESPAK I ATKINS 1-13

Page 23: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

main island and the main water body are all under intensive agriculture (mainly wheat and

sugarcane), with little or no natural habitat remaining.

PWD has a small office and facility at Taunsa, a supervisor based at Kotaddu, and in

addition 4-5 wildlife watchers and one boatman. The wildlife watchers - who are all recruited

from outside Taunsa - are based at the TBWS on a rotational basis, with each team staying

one month at a time. Patrolling of the site by PWD staff seems irregular at best. During the

CMS field survey (23-24 November 2005) the Taunsa PWD facility was not in use, and

according to locals no-one had been there for at least a month; no staff were encountered in

the field. There are signs located at the barrage indicating that the area is a protected area,

and stating which activities are not permitted. There are no displays, maps or other

interpretive material.

During a field trip on 23 November 2005 it was noticed that the main island, Matwani Wala,

is utilized by the local community in numerous ways:

* as a source of fuel wood, and several boats loaded bunches of brushwood with were

observed leaving the island; tracks left by oxcarts indicates that this may at times be

at a large scale;

* fishing: locals fish around the island, but also in residual ponds and pools that remain

once floodwaters recede; locals were seen using gillnets and funnel-shaped

pushnets, working in groups;

* buffalo grazing - one hard of about 20 animals was observed; and

* collecting of grass (notably Saccharum munja) for making brooms.

Most of these activities have a fairly low impacts, and as the island is still largely covered

with a dense woody vegetation, collection of fuel wood at the present level seems benign.

However, activities carried out during the breeding season (May-June) for resident birds, and

when migratory birds are present (December-February) may lead to unwanted levels of

disturbance. Additionally, fires - presumably lit to encourage new growth of Saccharum

munja - have affected parts of the northern part of the island. Given the lack of PWD staff

presence, hunting could also be a problem in the peak migratory season.

NDC I NESPAK I ATKINS 1-14

Page 24: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

2. SCOPE OF CHANGE,JUSTIFICATION AND BENEFITS

Page 25: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

2. SCOPE OF CHANGE, JUSTIFICATION AND BENEFITS

2.1 LABOUR CAMP

In the EIA, the areas adjacent to the right and left upstream guide bunds have been earmarked

as the borrow areas for earth (see EIA Project map at Figures 3.1, also para. 6.11 and items 7

of para. 6.5 of EIA and Annex 3.2 of CMS). As earth subsequently became available from the

spoils of DGK canal, the designated borrow areas were no longer required for obtaining earth.

However, 20 acres near the right guide bund have been used to house the contractor's labor

camp, batching plant, pre-cast yard, equipment yard and the JICA work base.

Initially, the labor camp had to be accommodated at the old workshop site of l&P Department

about one kilometer from the main project site. As labor for the mechanical part of ICB-02 has

to be accommodated at the workshop site, the labor camp for ICB-01 has been shifted to the

proposed site on the right bank upstream. In conjunction with this, the batching plant and the

pre-cast areas have also been shifted.

This change has created an easy accommodation for the labor of ICB-01 as well as ICB-02.

The batching plant is now located closer to the main project and this will save a lot of transport

costs and resource wastage. After completion of the project, it is proposed that the labor camp

site be used as a tourist accommodation for the visitors to Taunsa Barrage Wildlife Sanctuary.

The tourist resort can, at a later stage, be improved, by constructing an observation tower for

tourists to see the wildlife in the sanctuary by means of a fixed but rotating telescope, or using

binoculars.

2.2 WORK PLACE ON THE RIGHT SIDE DOWNSTREAM

Initially, a 5-acre open place was available near the end of the downstream Right Guide Bund.

To meet the requirement of the contractor for a larger work base, another 4 acres were added.

This meant that 21 households had to be relocated to a nearby site; these persons are now

being compensated under arrangements confirmed in a RAP.

The expansion of the work place has created ample space for temporary dumping of materials,

and for locating the heavy machinery yard required for construction of the coffer dam and the

main sub-weir.

DCI NESPAK I ATKINS 2-1

Page 26: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

2.3 WORK PLACE ON THE LEFT SIDE DOWNSTREAM

Initially, 9 acres of land were available as a work base on the lower tip of the d/s left guide bund.

Five acres of land was added to expand the work base in consideration of the scale of the

activities. This meant that 136 households had to be relocated to a nearby site; these persons

are now being compensated under arrangements confirmed in a RAP.

As with the right bank site (see 2.2), the expansion of the work place has created ample space

for storing materials, operating heavy machinery and creating an executing convenience for the

construction of the coffer dam and (later) the main sub-weir.

2.4 CONSTRUCTION ACTIVITY UPSTREAM OF BARRAGE GATE LINE

The construction activities upstream of the gate line of the barrage have taken the status of a

"Change" now it has become known that the southern boundary of the Taunsa Barrage Wildlife

Sanctuary coincides with the gate line of the barrage.

2.4.1 Construction of Coffer Dam

To facilitate the works on the upstream side of the barrage gate line an earthen Coffer Dam has

to be constructed. The Coffer Dam shall be built in stages of 500-550 ft each over a length of

4648 ft. span of the barrage. It will be about 10 meters wide at the top to allow vehicles to pass.

The coffer dam will be a temporary, earthen structure that will be flattened after use and left in

situ. However, it is expected that this material will be removed in 1-2 flood seasons and be at

least partly deposited between the barrage and new weir, adding to the protection of the base

of the barrage. The coffer dam will be constructed one compartment at a time, and each

compartment will be demolished after it has served its purpose.

2.4.2 Piezometers

Piezometers are instruments rather than structures, and are used from a fixed point to measure

the pressure of water. Their installment near the upstream base of the main barrage structure

will enhance the technical capacity of the Barrage Management by measuring the downward

pressure of the river water. This will in turn help to balance the upward hydraulic pressure of the

concrete flooring.

DC I NESPAK I ATKINS 2-2

Page 27: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

2.4.3 Grouting Activities

The civil work structures of the main Taunsa Barrage structure have, over past 50 years, and

developed cavities and structural weaknesses at a number of locations at the base and

foundations. It will be reinforced and strengthened by filling the cavities by means of grouting,

which involves removing loose material and injecting the cavities with a slurry of fast setting

cement. It is estimated that the grouting activity can help the structure to stay firm and functional

for another 50 years.

2.5 EXTENDED CLOSURE OF CANALS

The normal operational canal closure schedule for the Taunsa barrage is as follows:

. Name of Canals Muzaffargarh Canal

DG.Khan Canal

T-P link Canal

* Status of Canals Non-Perennial

. Period when Canals are run April 15 to October 15

. Period of Canal Closure for December 22 to January 31 (5 weeks)

repairs and maintenance

. Only Drinking water released February 01 to April 14 and October16 to December 21.

As a special measure during implementation of the project, the annual canal closure of the D.G.

Khan Canal has been extended from 15 November to 28 February, i.e. for 15 weeks instead of

the normal 5 weeks. For the two other primary canals closure will be from 15 December until

early or late February (9-13 weeks), instead of the usually 5 weeks. Water levels in the barrage

will be lowered during closure in the course of 1 12 days, but lowering will be within limits that are

normal during the dry season, i.e. stabilized at 430-421 ft at the barrage.

2.6 LEAD CHANNEL FOR D.G. KHAN CANALS

A channel, about 6 km long, with a capacity of 1,000 cusecs shall be used to provide water to

DGK canal during the extended period during which there will not be any flow through the

three primary canals. The canal command area (CCA) of the D.G. Khan Canal has limited

groundwater availability (of dubious quality), and the Lead Channel flow will serve to provide

drinking water to the CCA during the construction period. The Lead Channel will not be a

DC I NESPAK I ATKINS 2-3

Page 28: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

new structure, as use will be made of the channel used during construction in the 1950s.

<This original channel was in turn constructed along an existing natural drainage feature.>

As the 1950s channel has silted up to some extent, works will consist of desilting/excavation

and widening (by about 20 ft.). This channel shall be required only during implementation of

the project, after which it will be abandoned.

2.7 WORKS ON MECHANICAL GATES (ICB-02)

2.7.1 Fabrication and Installation of Gates

After running for over about five decades the moving components for the gates of the barrage

have deteriorated, causing serious malfunctioning and posing a threat to the safety of the

barrage. Therefore, for modification in design, studies were carried out by JICA who offered to

repair/rehabilitate 29 out of 65 gates of the barrage. The clear span between piers is 60 ft. and

the width of the piers is 7 ft., while the height of the gate in the weir portion is 19 ft. and in the

undersluice it is 22 ft. The barrage also incorporates a navigation gate with a span of 22 ft, and

two 20 ft. fish ladders on the other side. Change of gates would increase the efficiency of the

gate line.

2.7.2 Building of Workplace Area for ICB-02

A working platform of about 100 meters width (i.e. one ha in area) will be built by Japanese

Engineers on the left bank of the barrage, upstream of the TP Link canal regulator, along with a

stock yard for carrying out necessary replacement/repair of gates and the operational set up.

For building the work place a small part of the unused borrow area on the left bank upstream

has been used. This is a less intensive use than excavating earth from there. The work place

will be used to carry out repairs and for the replacement of the barrage gates. After the

completion of the project, the cleared land may be re-utilized for other purposes.

2.7.3 Work of Silt Excluder D.G. Khan Canal Headworks

To save D.G. Khan Canal from heavy siltation, a silt excluder shall be built, inside the river; infront of the headworks of D.G. Khan Canal, i.e. in the TBWS. The silt excluder will consist of silttrapping system covering three bays in the right pocket of the barrage. The system will re-release the trapped silt into the river. The D.G. Khan canal will receive water with reduced

sediments.

DC I NESPAK I ATKINS 2-4

Page 29: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

The silt excluder comprises of 12 rectangular RCC barrels, varying in length from 253 down

to 25 ft., the longest being adjacent to the Head Regulator. It has a design discharge

capacity of about 25,000 cusecs.

2.7.4 Construction of Jetty

Prefabricated gates, repaired gates and new parts of the gate holding system have to be

brought in to the system. Also, some of the gates and other repairable parts have to be

taken out of water. To facilitate that, a jetty will be constructed that is contiguous with the

plafform for gate construction (see 2.7.2). The jetty / plafform shall consist of an earthen

structure paved with concrete, and with a fixed set of rails; it will be located on the left bank

just upstream of the left pocket. Construction will not require piling. As indicated above, the

plafform will be about 100 meters wide and located east of the left guide bank, while the jetty

shall protrude about 6 meters into the barrage ponded area. They will be left for alternative

use (e.g. by barrage operators) after construction has been completed.

2.7.5 Change of Earth Borrow Areas

Due to availability of earth from D.G. Khan Canal bank spoils, the earth was obtained from

there. A small part of the originally proposed borrow area has been used for constructing the

Contractor's campsite on the right and for creating the ICB-02 work place and the

jetty/plafform on the left side.

DC I NESPAK I ATKINS 2-5

Page 30: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

3. ANALYSIS OF ADVERSEIMPACTS CAUSED DUE TO

CHANGES

Page 31: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

3. ANALYSIS OF ADVERSE IMPACTS CAUSED DUE TO CHANGES

3.1 ADVERSE IMPACTS DUE TO LABOUR CAMP RIGHT SIDE UPSTREAM

Twenty acres of land, about 100 meters away from the right upstream guide bund has been

utilized to construct a labor camp and house batching plants, pre-cast area equipment yard and

the JICA work base. This area is located within the southwestern part of the officially gazetted

TBWS. While having a lower visual impact than impact than the originally intended use as

borrow area, it may affect the wildlife sanctuary in the following ways.

3.1.1 Biodiversity The disturbance created by frequent movement of heavy vehicles, noise

of batching plants and presence of a large number of inhabitants of the camp may scare

away waterfowl and other wildlife from the ponded area and guide bund. Impacts on the

landward side are negligible, as the area was either under agricultural use, or had been

otherwise largely disturbed and had little value as a natural habitat.

3.1.2 Water quality of the river will be affected due to dust produced by a chain of trucks

carrying materials and goods to and from the construction site. Given the silt load of the

river in its natural state, this effect is expected to be negligible, local and temporary.

3.1.3 Quality of ground water is likely to suffer from the local disposal of solid and liquid

wastes. The effects can be of local significance, but can also be readily managed and

mitigated, by following appropriate methods for disposal and storage.

3.1.4 Endangered Species like Indus Dolphin and waterbirds such as the marbled teal may

be further threatened by human activity near and inside the barrage waters. The threat

will largely be due to disturbance - fortunately, the water body is fairly large and wildlife

can easily move away from areas of disturbance.

3.1.5 Potential impacts specific to the Wetland formed by the water body behind the gate

line of the barrage, are as follows: -

* Water, water quality & microclimate:

o Impact on sediment in the right river pocket and erosion control along the right

guide bank.

o Impacts on flood control by way of any damage to right guide bund due to heavy

traffic on its top.

o Impact on maintenance of water quality and abatement of pollution by way of

providing a source of solid and liquid wastes contributed directly or though

seepage.

DC I NESPAK I ATKINS 3-1

Page 32: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

o Impact on maintenance of surface and underground water supply by way of

addition of solid and liquid waste and soil compaction because of vehicular and

human activity.

o An impact on microclimate is likely due to physical disturbance and biological

interference.

Biological resources:

o Fisheries may suffer because of the presence of large number of labor and their

possible activities, including fishing, which may adversely affect the balance of

fish and Indus Dolphin.

o Impacts on waterfowl habitat will be adverse, caused by extensive human and

vehicular activity in the area.

o Impacts on the biodiversity will be obvious when the habitat is disturbed.

* Socio-economics:

o Impact on outdoor recreation and education about wetlands will be caused by

the exclusion of visitors to this area because of the camp. This function of the

wetland may, however, be restored after the completion of the project, and even

enhanced if the facilities are re-used for (eco-)tourism.

o Impacts on socio-economic values of the wetland will become apparent to local

people when they are excluded from the area. (Note: they are already excluded

from utilizing this area under the existing management of the barrage

operations).

* Management of the area:

o Impacts on sustainable practices shall be caused by habitat destruction.

o Impacts on technology already under use shall be caused by way of

construction activities on the upstream side of the gate line.

o Impact on further efforts of restoring the wetland shall inadvertently be

negatively impacted.

o Impacts may be caused on other projects already under implementation by way

of strong interference.

o Impacts may also be caused by the utilization of natural wetland resources in an

unplanned and unprecedented way.

o Impacts on continued status as Ramsar site; the continual high level of

disturbance in the barrage area may lead to this 20-acre area having to be

excluded from the overall Taunsa Barrage Wildlife Sanctuary.

DC I NESPAK I ATKINS 3-2

Page 33: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

While the list of potential impacts on the ponded area behind the barrage is long, most of these

effects are minor, or can easily be mitigated so that they are minor. Most of the effects are alsotemporary, and will be reversed after completion of the project. Care must be taken, however,

to rehabilitate the area of the labor camp after the project, to remove unsightly piles of materials

and remaining equipment (-parts), loosen compacted areas, and removing buildings that will

not be re-used. It has been suggested that some of the buildings can be re-used for the

development of eco-tourism; this will require careful planning to ensure that no new (and long-

term) disturbance results from this. A plan should be produced by the contractor for

environmentally friendly re-use of some of the facility, and dismantling of the rest.

3.2 ADVERSE IMPACTS DUE TO WORKPLACE ON THE RIGHTSIDE, DOWNSTREAM

To create a greater facility for execution of work, the work base was expanded from 5 acres to

9 acres. The expansion caused the following impacts.

* 21 households had to be relocated, and a RAP had to be produced and implemented to

safeguard local livelihoods and interests.

* Local land use was changed from residential to operational, thus causing compaction

and exposure to oil spillage and solid/liquid waste dumps on the new site, near the river

bank, from where local residents were shifted. This affects both surface and ground

water quality, albeit in a minor and temporary way.

. Biodiversity has been affected by removal of vegetation and leveling the area. A

seepage pond had to be filled up to improve the approach to work place which indirectly

could have upset the biodiversity balance in that niche. Apart from the small seepage

pond, the habitats were already largely disturbed and of little biodiversity value.

3.3 ADVERSE IMPACTS DUE TO WORKPLACE ON THE LEFT SIDE DOWNSTREAM

To create a larger facility for execution of work, the work base on the left side downstream of

the barrage, was expanded from 9 acres to 14 acres. The expansion caused the following

impacts:

* 136 households had to be shifted elsewhere and a RAP had to be produced and

implemented to safeguard local livelihoods and interests.

* Local land use was changed form residential to operational, thus causing compaction

and exposure to oil spillage and solid and liquid waste dumps on the new site near the

DC I NESPAK I ATKINS 3-3

Page 34: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

river bank where squatters were shifted. This affects both surface and ground water

quality.

Biodiversity was affected by removal of vegetation and leveling the area. These impacts

are minimal, as the habitats were already largely disturbed and of little biodiversity

value.

3.4 ADVERSE IMPACTS DUE TO CONSTRUCTION ACTIVITIES UPSTREAM OF

BARRAGE GATE LINE

3.4.1 Work of Silt Excluder

The silt excluder shall reduce the quantity of silt from the water flowing into D.G.Khan Canal,

preventing it from silting up and guaranteeing its capacity for a longer period. Construction will

take place once the right pocket has been shielded from flooding by the coffer dam. Once in

place the silt excluder may some negative impacts, including:

* The accumulation of greater quantities of silt in the right pocket and three bays adjacent

to the right bank.

. In the right pocket the change in the physical conditions will change the micro-

environment, affecting wetlands and associated biodiversity. However, the latter effect

is expected to be minor, at most.

3.4.2 Construction of Coffer Dam

The coffer dam located upstream of the barrage shall:

* Cause obstruction to the normal flow of water to the extent it is built. It will temporarily

raise the water level behind the coffer dam and due to pressure created there; increase

the velocity of water flowing towards the gate line. Rise in level and velocity can create

problems downstream, particularly on the glacis. As the coffer dam will be constructed

and demolished one compartment at a time, this effect will be limited.

. During construction, water quality will be affected as earth is deposited in the water

body will cause an increase in ambient levels of suspended matter. This will in turn

affect biodiversity, endangered species such as the Indus Dolphin, and peripheral

wetlands.

. After the work is finished, the earth used for building the coffer dam, cannot be directly

removed. It will have to be spread on the bottom of the ponded area, causing a

DC I NESPAK I ATKINS 3-4

Page 35: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

temporary reduction in water depth, affecting fish and Indus Dolphin, wetlands, and

indirectly impacting waterfowl. This effect is expected to be moderate and temporary, as

during the next period of flooding most of these sediments are likely to be flushed out of

the barrage.

Biodiversity will be adversely affected during the period the coffered area remains dry

and at times when heavy quantities of earth are converted into sediment load of the

river water. However, as the total coffered area is small compared to the total ponded

area (600 ft of coffered length versus 5000 ft total length N-S of the ponded area), the

reduction in available habitat for dolphins or waterfowl is moderate and temporary. Also,

as the coffer dam will be constructed and demolished one compartment at a time, this

effect will be limited.

3.4.3 Piezometer

Piezometers are measuring instruments that will be installed upstream near the base of the

main barrage structure, and will be linked by wires to the barrage operations office. The

environmental effect of their installation is expected to be negligible. At the most, they may

provide shelter for certain deep water fish, where they may be able to hide from the Indus

Dolphin. During installation, there may be some minor disturbance to wildlife in the areas, and

minor resuspension of sediments. Environmental effects will therefore be minor and temporary.

3.4.4 Grouting Activities

Grouting is one time operation of pumping cement slurry into the cavities at or near the base of

the main barrage structure. However, any leakage may end up in the river water, and this may

temporarily affect surface water quality downstream of the barrage. Smaller wildlife living in the

cavities, such as amphibians and fish, may be affected as the may be smothered by the

cement slurry, and available shelter will disappear. Overall, the effects on the wildlife sanctuary

will be small, although impacts on certain biodiversity may be long-lasting.

3.5 ADVERSE IMPACTS DUE TO EXTENDED CLOSURE OF CANALS & LOWERING

OF WATER LEVELS IN PONDED AREA

Canals are artificial structures and for their maintenance and repairs, a closure is prescribed in

their operational manuals. The D.G.Khan Canal shall remain closed during the implementation

of the project, from 15 November to 28 February (15 weeks) instead of the usual closure from

December 22 to January 31 (5 weeks).

DC I NESPAK I ATKINS 3-5

Page 36: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

The two other primary canals (TP-Link Canal and Muzaffargarh Canal) will be closed from 15

December to early or late February (9-12 weeks), instead of the usual 5 weeks. A longer

closure is necessary for better silt clearance and maintenance of the D.G. Khan Canal, and for

allowing works on the main barrage, but this will also have adverse impacts:

* It will cut off drinking water supply for a large human population in the D.G. Khan CCA

for the extended period, as groundwater in the command area is of poor quality and

cannot be used for human consumption. To mitigate this, the Lead Channel (see 3.6)

will be used to provide the D.G. Khan canal with 1,000 cusecs so as to be able to serve

drinking water requirements.

* Agricultural crops, especially the raising of the Rabi crop, may suffer during the

closure season, especially in the D.G. Khan CCA. A separate Change Management

Statement will be prepared by the end of June, 2006, covering (i) the identification

and mitigation of impacts associated with low flows in the DG Khan canal in the

period extending from December 2005 through February 2006, and (ii) measures to

mitigate the impacts of any proposed future extensions of the canal closure period.

* Due to fall of water in the river, aquatic life will suffer and it may be forced to move into

deeper waters in other parts upstream. This lowering of water levels and desiccation

may affect endangered species such as the Indus Dolphin, and also affect wildlife, fish,

wetlands and biodiversity in the TBWS. Some of these impacts may be temporary, but

others may be longer-lasting. The lowering of water levels is expected to be within the

normal range, however, and not below the 430-431 ft level. As a result, the overall

effects are not expected to be relatively significant, but not irreversible.

* The fall in the water levels will temporarily increase the size of islands in the Indus River

north of the barrage, and if left undisturbed these could potentially provide more habitat

for birds.

3.6 ADVERSE IMPACTS DUE TO LEAD CHANNEL FOR FEEDING D.G. KHAN CANAL

This is a temporary channel which will be used to supply drinking water to D.G.Khan Canal,

over the extended canal closure period during the project period. It is not a new structure, but

an upgraded existing structure previously used during the 1950s construction. The present

channel will be widened by about 10-20 ft along much of its length, and deepened. It will be

abandoned as soon as the need for the extended Canal closure is finished. The following

environmental and socio-economic effects are to be expected:

DC I NESPAK I ATKINS 3-6

Page 37: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Impacts are expected on wildlife, biodiversity, endangered species, surface waters and

wetlands during construction, as these activities will cause disturbance and increased

levels of suspended sediment in surface waters. While the channel is officially located

within the TBWS, the area has totally been converted to agriculture and land use

consists of wheat fields, sugarcane areas, and human habitation. Impacts on

biodiversity, wildlife and wetlands is therefore expected to be minor.

After abandonment, however, the effects may be beneficial as extra wetland habitat will

be available. This is largely due to the excavation and enlargement of the existing

channel, which apart from an increase in size, can also be expected to hold water for

longer periods in the dry season. Both aspects will be beneficial to wetland species in

the medium to long-term.

Excavation of the channel will waste land, as the channel will remain operational only

temporarily and afterward, it will be abandoned. The total area affected will only be

about 5-10 hectares (about 3-6 meters widened channel, spoils on banks are about 6

meters wide, total length is 6 km), which is a moderate loss.

3.7 CHANGE OF EARTH BORROW AREAS

Not using the borrow areas and instead obtaining earth from spoils of D.G.Khan Canal has had

the following environmental effects:

* Led to change in the land use: habitation instead of created ponds (left after excavation

of borrow pits).

* Created a buffer zone between the agricultural field, and the Wildlife Sanctuary.

3.8 ADVERSE IMPACTS DUE TO WORKS ON THE MECHANICAL GATES

3.8.1 Fabrication and Installation of Gates

The gates will be fabricated ex situ and shall be brought on rail track up to the jetty from where

these shall be floated on barges/with tug boats to the site of installation. This activity may have

following impacts:

The risk of accidents is high and therefore while receiving, conveying and installing the

gates, a high Health and Security alert is to be issued by the HSE section staff to

prevent accidents.

DC NESPAK I ATKINS 3-7

Page 38: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

* Installation and fabrication may disturb the normal water flow in the Barrage, and affect

ambient air quality.

* It will require modification of the river bank from where the gates, etcetera have to be

guided along a ramp down into the river (see 3.8.3).

3.8.2 Building of Workplace Area for ICB-02

Construction of the Workplace for ICB-2 (the platform associated with the jetty) will cause

following impacts:-

* It will require clearance of some vegetation, and therefore cause local loss of

biodiversity. This impact will be minimal, for although the site is officially located within

the wildlife sanctuary, most of this area is already very heavily disturbed.

* A small part of the area, originally meant for borrowing earth shall now be used as

workplace for ICB-02.

3.8.3 Construction of Jetty

The construction and operation of the jetty will have the following effects:

* Construction of the jetty will elevate suspended matter levels and thereby affect surface

water quality, nearby wetlands, and biodiversity at a localized level. Construction

activities will also disturb wildlife. As the size of the jetty is small (protruding only 6m into

river), certainly compared to the entire ponded area, the impacts will be minor. Piling will

not be required.

* The fact that it protrudes into the water will affect water flows at a local level, and

therefore have lasting effects on local hydrology and wetlands. However, as the

dimensions are small, the impact on the hydrology is likely to be negligible.

* Activities on the jetty may have an impact locally in the left pocket, thus affecting any

aquatic life below. This will be mainly in the form of (some) disturbance during

construction, as fishing and hunting are prohibited by barrage operators.

* The jetty will use a part of the riverbank adjacent to which lies the area originally meant

as the borrow area. This will cause a change in the land use, especially considering that

the jetty is located inside the wildlife sanctuary.

DC NESPAK I ATKINS 3-8

Page 39: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

3.8.4 Upgrading of the existing fish ladders

The upgrading of the two existing fish ladders will bring about positive environmental effects inthe medium- to long-term, but during reconstruction they will not be in use, and therefore there

will possibly not be any passage of fish via this route during part of one seasons.

3.9 CUMULATIVE IMPACTS IN PONDED AREA

While all individual impacts of project activities on the ponded area are expected to be minor or

moderate, it is possible that the cumulative effects of the coffer dam, lowering of the water

table, grouting, and construction activity that increase suspended sediment levels will besignificant, at least for aquatic species such as the Indus Dolphin. Together, smaller volumes of

water and impacts on water quality may combine to create adverse conditions. The project

should therefore carefully monitor:

* water levels in the ponded area to ensure that a minimal depth of 430-431 ft. is truly

maintained;

* water quality4, to ensure that oxygen levels are within safe levels (>2.0 mg/I),suspended sediment is generally below 80 mg/l (and never above 400 mg/I)5, and

cement is not spilled into the river;

* possible fish kills (and immediately investigate any report by taking water and fish

samples for analysis in Lahore); and

• the Indus Dolphin and waterbird populations in the ponded area, to ensure that levels

remain constant, or within normal (pre-project) fluctuations.

Monitoring of water quality and quantity is to be carried out by the Contractor, at least on a

weekly basis, using at least six sites: four in the ponded part of the barrage (i.e. between the

guide bunds), and two in the water body upstream of the guide bunds. Monitoring of Indus

dolphin and waterbirds should be carried out by WWF-Pakistan at least on a fortnightly basis

(during project implementation, and monthly during intermittent periods).

4 Adapted from Alabaster, J.S. & Lloyd, R.L. (1980) - Water quality criteria for freshwater fish. ButterworthsPubi., London.5The suspended sediment level of incoming waters upstream of the barrage guide bunds must also be measured,as this may, on occasion, also be elevated (e.g. during peak floods).

DC I NESPAK I ATKINS 3-9

Page 40: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

3.10 EVALUATION OF ENVIRONMENTAL IMPACTS OF CHANGE MANAGEMENT OF

TAUNSA BARRAGE REHABILITATION AND MODERNIZATION PROJECT

(A comprehensive analysis of overall impacts has been given in EIA, Table 7.1 page 7-3. In the

following table 3.1 only those impacts are included which have been caused due to change

management and should be read as a supplemental list to that given in EIA.)

DC I NESPAK I ATKINS 3-10

Page 41: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Table 3.1

Evaluation of Change Management Impacts

Assessment

No Change Aspect Impact Slight Moderate High

1 2 3 1 2 3 1 2 3

1 . Contractors labor camp 1.1 Biodiversity 1.1.1 Noise due to frequent

and batching plants, movement of vehicles

equipment plant and JICA 1.1.2 Noise due to batching plans X

work base taken to right 1.1.3 Large No. of labor V

bank upstream from old 1.1.4 Threat to Flora /

factory area. 1.1.5 Threat to Fauna ==/

1.1.6 Threat to Indus Dolphin v/

1.2 Water quality of the river 1.2.1 Dust effect

1.3 Quality of ground water 1.3.1 Disposal of solid waste /

1.3.2 disposal of liquid waste /

1.4 Threatened species under 1.4.1 Human activity near river VI'

social pressure bank

6 NOTES: I = Avoidable through design (Preventative);2 = Mitigation through Contractor's obligation or by communities through Social Framework Agreements (SFAs) (Curative);3 = Irreversible/permanent Change (to be adopted).

DC I NESPAK I ATKINS 3-11

Page 42: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

1.5 Impacts specific to wetland 1.5.1 Sedimentation along river

pocket

1.5.2 Flood control

1.5.3 Water quality _

1.5.4 Surface and ground water /

supply

1.5.5 Fisheries /

1.5.6 Outdoor recreation

1.5.7 Temporary habitat of water

fowls

1.5.8 Climatic stability /

1.5.9 Socio-economic values X

1.5.10 Biodiversity & habitat

stability

1.5.11 Sustainable fisheries

practices

1.5.12 Barrage technology

already in practice

1.5.13 Restoration of wetland

1.5.14 Utilization of wetland

system

1.5.15 Status as Ramsar site =

DCj NESPAK ATKINS 3-12

Page 43: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

2. Expansion of work place on 2.1 RAP undertaken (separate 2.1.1 Twenty one households

the right side downstream & independent report) shifted

2.1.2 Change in land use X _

2.1.3 Biodiversity effects due to

removal of vegetation.

2.1.4 Effects on water quality.

3. Expansion of work place on 3.1 RAP undertaken (separate 3.1.1 One hundred thirty six X

the left side downstream and independent report) households shifted

3.1.2 Change in land use _t

3.1.3 Biodiversity effects _

3.1.4 Effects on water quality. X_

4. Construction of coffer dam 4.1 Works inside wildlife 4.1.1 Obstruction to the normal

upstream sanctuary flow of water

4.1.2 Disposal of coffer dam X

material

4.1.3 Biodiversity effects & _t

endangered species

4.1.4 Effects on wetland

4.1.5 Effects on water quality X

5. Work of silt excluder 5.1 Reduction of silt in D.G. 5.1.1 Addition of removed silt into

Khan canal right pocket

5.1.2 Effect of physical change on

micro-environment

DC I NESPAK I ATKINS 3-13

Page 44: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

6. Piezometer 6.1 Water pressure 6.1.1 Fish =

6.1.2 Water quality. X

7. Grouting Activity 7.1 Filling up cavities 7.1.1 Drinking water shortage =

7.1.2 Affecting water quality

during construction

7.1.3 Wildlife/biota will be

displaced and/or killed by filling of

cracks; species dependent on X

these as food source will also

decline.

8. Extended canal closure 8.1 Water availability 8.1.1 Drinking water shortage

8.1.2 Shortage of agricultural __

irrigation water

8.1.3 Affecting wetlands,

endangered species and X

biodiversity.

9. Lead channel for feeding 9.1 Coverage water supply 9.1.1 Availability of water

D.G. Khan canal during extended canal closure 9.1.2 Loss of land for construction

of the channel

9.1.3 Water quality affected

during construction.

10. Works on mechanical gates 10.1 Fabrication and installation 10.1.1 Disturbance in flow of

of gates water

DCI NESPAK I ATKINS 3-14

Page 45: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

10.1.2 Modification of river bank

point

11. Building of work base for 11.1 Clearance of place 11.1.1 Biodiversityeffects _

ICB-02 upstream left side upstream of TP Link 11.1.2 Change in land use /

12. Change of earth borrow pit 12.1 Excavation of earth 12.1.1 Biodiversity effects /

area 12.1.2 Change in land use

12.1.3 Buffer zone between

wildlife sanctuary and agricultural

land

13. Construction of jetty 13.1 Modification of a part of 13.1.1 Protruding into the river

river bank for facilitating fixing affecting hydrology & wetlands

of gates 13.1.2 Construction of a jetty in a

wildlife sanctuary disturbing /

wildlife

13.1.3 Water quality adversely /

affected during construction

14. Fish ladders 14.1 Fish ladders will be 14.1.1 During reconstruction, the

modified during the project, to fish ladders will not be in use. X

improve their design/capacity.

DC I NESPAK I ATKINS 3-15

Page 46: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Since the construction work has already started and all designs are already in place, there is no possibility of taking up option 1 i.e. incorporation of

change management in the new design, in any of the categories. The change management has caused 61 impacts of which:

27 are slight and mitigable

01 is slight and irreversible

28 are moderate and mitigable

01 is moderate and irreversible

03 are high and mitigable

01 is high and irreversible

DC I NESPAK I ATKINS 3-16

Page 47: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

4. SUPPLEMENTALENVIRONMENTAL

MANAGEMENT PLAN (EMP)

Page 48: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

4. SUPPLEMENTARY ENVIRONMENTAL MANAGEMENT PLAN

(EMP)

4.1 GENERAL

This is primarily a supplementary EMP to the one given in chapter 8 of the EIA of Taunsa

Barrage Rehabilitation and Modernization Project. On the pattern of the main EIA, this also

includes each of the following:

1. Mitigation plan for each adverse factor.

2. Implementation responsibility.

3. Monitoring responsibility.

4. Institutional strengthening.

For convenience sake, each change has been taken separately for dealing with the impacts

emanating from it. It is understood that this Supplementary EMP shall be read together with the

main EMP, provided in the EIA. See Table 4.1 for the Supplementary EIA.

4.2 MITIGATION PLAN FOR CHANGE

The main reason for the Change Management Statement is that the EIA overlooked the fact

that the entire Barrage upstream of the gate line is located within the Taunsa Barrage

Wildlife Sanctuary. In addition, there were several changes to the design that directly affect

the TBWS, such as the construction of the coffer dam, the Lead Channel, and the grouting

activity. All the design works have already been finalized and the project has currently

entered the Construction Phase. As a result, the entire change has to be implemented

through readjustments during construction and in the operational phase. For the purpose of

Change Management, the 61 possible impacts have been divided into those to be handled

at Construction Phase and those to be addressed during the Operational Phase. It will be

noted that 98% of the adverse impacts indicated in the Change Management shall be

mitigated during the Construction Phase, only 2% of those shall be taken up at the

Operational Phase. It is therefore a practicable Change Management with few additional

costs.

NDC I NESPAK I ATKINS 4-1

Page 49: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Table 4.1

Supplemental Environmental management Plan (EMP) for Change Management

Sr Mitigation Responsibility Quantities andImpact ~~~~~~~Provision in Contract

No. Impact Mitigation Measure Provisior S FA Implementation Monitoring Costs

A. CONSTRUCTION PHASE1. Contractor's labor camp and batching plant, equipment plant and JICA work base taken to right bank upstream from old factory area1.1 Biodiversity

1.1.1 Noise and dust 1) Keep a buffer Contract provides Chief Resident Project Manager Cost alreadydue to frequent between camp and control refer EIA page Engineer (CRE) (PM) and PMO covered in BOQmovement of vehicles sanctuary 8-5 Sr No. 20. Also and Contractor

2) Provide C.l. sheet EIA page 8-26 Sr No.

fence 3.1.

3) Carry out buffer

plantation

1.1.2 Noise due to 1) Provide a buffer Contract provides Contractor and PM and PMO Cost alreadybatching plants around the site contractors EIA page CRE covered in BOQ

2) Provide Gl sheet 8-5 Sr No. 22 and

cover EIA, page 8-27 No.

3) Fast growing 3.3.

vegetation all around

NDC I NESPAK I ATKINS 4-2

Page 50: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation ResponsibilitySr ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Quantities andImpact ~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pmvisior SEA Implementation Monitoring Costs

1.1.3 Large number of There are control Contract already Contractor and PM and PMO Cost already

laborers is a threat to measures involved in provides control on CRE covered in BOQ

the sanctuary contractor's labor. Also see EIA

obligations page 8-3 Sr No. 07

and page 8-20 Sr No.

1.3.

1.1.4 Threat to Flora A special clause 1) Contractual Contractor and PM and PMO Cost already

incorporated in the obligation RE covered in BOQ

contract documents to 2) Provide necessary

conserve biodiversity. signology for

Also see page 8-28 Sr protection

No. 4.1 of EIA; 3) Communities to be

rehabilitation of the involved.

area after completion.

Contractor to provide

alternative fuel to

laborers housed on-

site, to reduce

impacts on local

fuelwood resources

NDC I NESPAK I ATKINS 4-3

Page 51: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr Quantities andImpact ~~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pror SEa Implementation Monitoring Costsor SFA

(mostly taken from

TBWS).

1.1.5 Threat to Fauna Unnecessary and out A special clause was Contractor and PM and PMO Cost already

of bound activities and incorporated in the RE covered in BOQ

movements are contract to that effect.

prohibited Also see EIA pages 8-

27, 8-28 and 8-29;

clauses 4.1, 4.2 & 4.3

1.1.6 Threat to Indus Catching, killing, Contractor's obligation Contractor and PM and PMO Cost already

Dolphin eating or chasing the in the contract at the RE covered in BOQ

Indus Dolphin pain of heavy penalty

upstream or to protect dolphin;

downstream is strictly wildlife laws also

prohibited prohibit. Also see IEA

page 8-29 para. 4.2.

1.2 Dust effect on water - Sprinkling of water Contractor's obligation Contractor and PM and PMO Cost already

quality of river in on all kacha road defined in the contract RE covered in BOQ

barrage area - Keeping traffic to document. Also EIA

minimum page 8-26.

- Protective measures

NDC I NESPAK I ATKINS 4-4

Page 52: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility Quantities andImpact ~~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pror SE a Implementation Monitoring Costsor SFA

1.3 Impact of project 1) Regularized Clause regarding Contractor and PM and PMO Cost already

activity on quality of disposal of solid location and CRE covered in BOQ

ground water waste of the camp management of labor

2) Regularized camps included in the

disposal of liquid contract. Also

waste of the camp provision in EIA item

3) Drainage 1.3 on page 8-20 of

EIA and item 1.9 page

8-22 of EIA.

1.4 Threatened species Control and Clause in the contract Contractor and PM and PMO Cost already

under social pressure regularized human to respect wildlife, CRE covered in BOQ

activity by organizing forests and fisheries

the communities laws. Also see EIA

page 8-28, item 4.1.

1.5 Impacts specific to By suitably opening Clause in contract the Mainly CRE and PM and PMO Cost already

ponded area and closing of barrage CRE to ensure that the PMO covered in BOQ

1.5.1 Sedimentation gates and removing EIA is respected.

along river pocket all obstructions from Refer clause 2.4 on

the flow of water page 8-25 of EIA.

NDC NESPAK I ATKINS 4-5

Page 53: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility Quantities andImpact ~~~~~~~~Provision in Contract

No. p Mitigation Measure on in Implementation Monitoring Costsor SEA

1.5.2 Flood control Provision is made to Clause in contract PMO and CRE PM and PMO Cost already

protect the provision in EIA page covered in BOQ

construction from 8-25

flood by adopting

waming and

engineering methods

1.5.3 Water quality (in 1) Control on solid There is a clause in Contractor and PM and PMO Cost built in the

the wetland) pollution waste disposal the contract. Also EIA CRE BOQ

2) Control on oil spills provides coverage

into water page 8-24 section 2.2

3) Awareness in and sections 1.13.

works and community

1.5.4 Surface and 1) Earthen embank- There is a clause in Contractor and PM and PMO Cost built in the

ground water viz-a-viz ments, protection the contract. Also EIA CRE BOQ

the ponded area of the bunds provides coverage

barrage. 2) Control on spills. page 8-23 section

3) Control of solid and 1.10 and page 8-22,

liquid waste disposal. sections 1.8.

NDC I NESPAK I ATKINS 4-6

Page 54: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr ____________Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SFA Implementation Monitoring Costs

1.5.5. Fisheries possible 1) Prefer 1) Training of staff Contractor and PM and PMO Cost built in theadverse effect implementation of 2) Organization of CRE BOQ

fisheries act. communities

2) Facilitate inspections

3) Training of

communities through

SFA

1.5.6 Adverse impacts 1) All such sites will There are clauses in Contractor and PM and PMO Cost built in theon outdoor recreation be rehabilitated by the the contract to cover CRE BOQ

by way of spoiling the contractor. all these mitigation

top of bunds and 2) The bunds shall be measures. Also see

producing dust. maintained by rip rap EIA pages 8-21 and

work and protection 8-22 at serial number

walls. 1.4, 1.5 and 1.10.

3) Water sprinkling

daily to keep the dust

production low.

1.5.7 Temporary habitat 1) Unnecessary out of Contractor's Contractor and PM and PMO Cost built in theof waterfowl shall be bound activities and contractual obligations CRE BOQ

disturbed due to movement shall be already provided in

NDC I NESPAK I ATKINS 4-7

Page 55: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation ResponsibilitySr ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Quantities andImpact ~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SEA Implementation Monitoring Costs

destruction of biological prevented. the contract. Also see

resources 2) Activities during the EIA page 8-28 para.

period of migratory 4.1.

waterfowl shall be

kept at the lowest

level possible near

and in areas where

birds congregate.

1.5.8 Wetland stability 1) Unnecessary and PMO and SFA to PMO and CRE in PM and PMO No direct cost. All(esp. in the ponded out of bound operate in collaboration with indirect costs built inarea above the barrage) movement to be collaboration local communities BOQhinges on proper prohibited

maintenance of the 2) Barrage water level

ecosystem. to be maintained at a

constant level.

1.5.9 Adverse impact on 1) 21 families from the 1) RAP has been PMO, CRE and PM and PMO 1) Cost ofsocio-economic values right bank and 136 produced for Contractor production and

families from left bank resettlement of 156 Communities implementation ofhave been shifted. families RAP shall be2) SFA has been 2) Social Framework charged separately

NDC I NESPAK I ATKINS 4-8

Page 56: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility~~~~~~~~~~~~~~Quantities andImpact ~~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pror SE a Implementation Monitoring Costsor SFA

signed. Agreement has been 2) Liaison with

incorporated in the community will not

contract. involve extra costs

1.5.10 Adverse impact WWF is undertaking a A separate contract WWF and PMO PMO Cost being charged

on biodiversity baseline survey of the has been awarded to separately under an

barrage and wildlife WWF, which is being independent

sanctuary (wetland). monitored by PMO contract

This will be used as a

baseline to monitor

possible changes,

and to ensure that

biodiversity is

maintained.

1.5.11 Adverse impact 1) Fishing has been 1) Fisheries act PMO and PMO and CRE Regulation and

on sustainable fisheries suspended during pertaining to public Contractor fisheries will not

practices due to construction period waters cost anything to the

construction activities 2) Minimum 2) Contractor's project

disturbance in barrage contractual obligation

area as well as the not to disturb the

sanctuary to be resource.

NDC I NESPAK I ATKINS 4-9

Page 57: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation ResponsibilitySr ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~Quantities andImpact ~~~~~~~Provision in ContractNo. Impact Mitigation Measure Implementation Monitoring Costsor SFA

ensured

1.5.12 Adverse impact Renovation and Strong supervision PMO, Contractor PMO and CRE Quality control ofon barrage technology modemization of shall ensure that there and CRE technology will notalready in practice Taunsa Barrage will is no change in cost anything

not change any technology and hence additional to theessential features of there are no project

the barrage. implications.

1.5.13 Restoration of The coffer dam will be 1) Contractor's Contractor and PMO and CRE Cost built in BOQwetland (esp. the flattened after use, as obligation to restore CRE

ponded area upstream water erosion will the area before he

of the barrage) will be remove the material in leaves.

required after the 1-2 flood seasons. 2) Also see EIA page

upstream coffer dam is This is to be 8-28 section 4.1 and

dismantled. An monitored, to ensure page 8-21 and 1.4.

exception will be made that this does indeed

for some buildings that occur.

are to be left for eco-

toursm facilities.

NDC j NESPAK I ATKINS 4-10

Page 58: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation ResponsibilitySr Quantities andImpact ~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pror SE a Implementation Monitoring Costsor SFA

1.5.14 Adverse impact Notification of wildlife Wildlife sanctuary has PMO and CRE PMO and CRE Notification for

on utilization of wetland sanctuary shall be been notified, under wildlife sanctuary

ecosystem revived for next five Wildlife Act 1974. The would not cost

years. This will also waters behind the anything

supplement the barrage are available

existing Ramsar site for optimal utilization.

designation.

1.5.15 Impact on status 1) The area has been Notification regarding Punjab Wildlife Punjab Wildlife No cost, but

as Ramsar site declared a Wildlife the wildlife sanctuary Department, EPD Department recognition of status

Sanctuary expired in 2003. It is Punjab, PMO and of area.

2) I&P Dept and all being re-notified for WWF

other departments five years

have agreed to

respect the status

2. Expansion of work place on the right side downstream

21 households had to RAP undertaken RAP is a World Bank PMO, CRE and PMO RAP cost calculated

be shifted to expand the (separate indepen- requirement for such Sociologist independently in a

workplace from 5 acres dent report) wherein shifting of population separate report, and

to 9 acres. It has due compensation change in land use will be added to the

caused the following has been proposed. was inevitable. New Change

NDC I NESPAK I ATKINS 4-11

Page 59: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Impact Mitigation Responsibility Quantities and

No. Impact Mitigation Measure Pror SE a Implementation Monitoring Costsor SFA

impacts: Since more land was plantation will replace Management Cost

1) Shifting of local required the land use the original one

persons has temporarily been cleared.

2) Change in land use changed. The

3) Effect on biodiversity vegetation that has

4) Effects on water been cut shall be

quality replaced by means of

reforestation.

3. Works inside wildlife sanctuary

1) Obstructions to the 1) Minimal obstruction Collectively the EMP PMO, Contractor PMO Contract clauses

normal flow of water by making coffer dam contained in EIA, the and CRE already provided

2) Disposal of coffer in parts and by provisions of EMMP are adequate. No

dam material staggering different and the general new contract or

works so that work is contractual clauses contract clauses are

3) Effects on done at one time. and rules look after all required

biodiversity 2) It is an earthen these aspects. No

4) Noise close to coffer dam, which will new contract is

aquatic habitat. be flattened and required.

5) Possible addition of removed by flood

pollutants to water waters. Construction

NDC I NESPAK I ATKINS 4-12

Page 60: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility Quantities andr Impact ~~~~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pmvisior SFA Implementation Monitoring Costs

and flattening will

occur one coffer dam

compartment at a

time.

3) No fishing or

catching of Indus

Dolphin allowed.

4) No pile driving

allowed in the water.

5) Contractor to be

alerted and checked

strictly for any

pollution.

4. Works of Silt Excluder

1) Addition of removed 1) Preferred opening The contract terms Contractor, PMO PMO and CRE Already provided insilt and thus increase in of the gates to already provided and and CRE contract. No new

turbidity of the water in facilitate the removal the procedures to be clause is required atthe right pocket. of silt from the right provided during this stage. An

2) Effect of physical pocket. construction as well operational manual

change in the micro- 2) Effective monitoring as operational should be carefully

NDC I NESPAK I ATKINS 4-13

Page 61: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SE A Implementation Monitoring Costs

environment in the right to ensure that the phases. prepared so as to

pocket biological balance is ensure that no

maintained. serious changes in

3) Collaboration with physical features in

WWF database. the right pocket

occur.

5. Installment of Piezometers

1) A very small No notable impact is No special provision is Contractor, PMO PMO and CRE No additional cost

intervention in barrage expected. During required. The general and CRE shall be incurred.

floor fixing some noise clauses provided in Fixing of

2) A minor obstruction pollution may be the existing contract piezometers is

due to wires etc.. added but that is are adequate. already provided.

expected to be very The provisions

minor. already made are

adequate.

6. Grouting Activity

1) Filling out the cavities 1) Grouting to be Clauses already Contractor and PMO No additional cost.

at the base of the done carefully and provided in the CRE The cost is already

barrage with cement with right mix tube. contract cover the built in BOQ.

slurry. 2) Pipes may be used grouting activity.

NDC I NESPAK I ATKINS 4-14

Page 62: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SFA Implementation Monitoring Costs

2) Some noise will be for conveying the

produced, with local grouting material into

effects. the cavities.

3) Some leakages into 3) Contractor to be

the river, affecting water alerted against any

quality. leakages.

4) Aquatic life hiding in

the cavities shall be

dislocated, killed or

smothered.

7. Extended canal closure

1) Shortage of drinking 1) A lead channel for Provisions already Contractor and PMO No additional cost.

water in the canal feeding D.G. Khan made in the contract CRE The cost is already

command area (CCA). canal during the and SFA are built in BOQ.

2) Shortage of irrigation extended canal adequate to cover the

water for a longer time closure period will be extended canal

in CCA. used to provide closure.

3) Effects on drinking water to the

biodiversity, CCA.

endangered species 2) A separate Change

NDC I NESPAK I ATKINS 4-15

Page 63: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SE A Implementation Monitoring Costs

and wetlands. Management

Statement will be

prepared by the end

of June, 2006,

covering (i) the

identification and

mitigation of impacts

associated with low

flows in the DG Khan

canal in the period

extending from

December 2005

through February

2006, and (ii)

measures to mitigate

the impacts of any

proposed future

extensions of the

canal closure period.

NDC I NESPAK ATKINS 4-16

Page 64: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SE A Implementation Monitoring Costs

3) Vigilant monitoring

for any stranded

aquatic life. Ensuring

that water levels in the

ponded area do not

fall below 430 ft. level.

8. Lead channel for feeding D.G. Khan canal

This impact a mitigation The land used under Building of the PMO and CRE PMO/I&P Dept. Built in BOQ. The

measure in itself. the lead channel after channel is provided in costs at operational

However it may cause it is abandoned after the main project as phase pertain to

the following impacts: the completion of the well as the contract. recurring charges

1) Addition of water into project will be brought The use of land after which are not part of

DGK canal during under plantation the project pertains to the project

extended canal closure under the advice and operational period. expanses.

period. patronage of the

2) Loss of land (5-10 Forest Department. Its

ha) due to modification character as channel

of the existing channel. shall however be

3) Some impacts (on maintained so that it

wildlife) due to can be re-used in

NDC I NESPAK I ATKINS 4-17

Page 65: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Pror SE a Implementation Monitoring Costs

or SFA

excavation disturbance, case some repair or

and possibly due to maintenance work

large amounts of spoils. become essential at

the DGK canal

headworks.

9. Works on mechanical gates

Fabrication and 1) Fabrication shall be 1) Contractor's Contractor, CRE PMO and CRE All cost already

installation of gates done ex situ and contractual obligation and PMO incorporated in

causing: fabricated gates shall to carry out the work BOQ.

1) Disturbance to flow of be conveyed to Jetty as safely as possible.

water by a trolley running on 2) Also refer EIA

2) Modification of the a pair of rails. pages 8-20 section

river bank. 2) For installation, tug 1.1 and page 8-24

boats/barges shall be section 1.13.

used, causing mini-

mum disturbance to

flow of water.

3) Any material,

pieces of old gates

shall not be thrown

NDC I NESPAK I ATKINS 4-18

Page 66: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SFA Implementation Monitoring Costs

into the river, but

brought back to jetty

by boats from where

these will be sent to a

disposal site away

from barrage on the

returning trolleys

which bring the gate.

10. Building of work base for ICB-02 upstream left side

This will involve 1) Some disturbance 1) Contractor's Contractor, PMO PMO All cost already

clearance of an area to existing vegetation obligation to restore and CRE provided in the

upstream TP Link, particulady the trees the site as far as BOQ.

causing: shall be caused. possible provided in

1 ) Effects on 2) After the project the Contract.

biodiversity. work, the contractor 2) Also see EIA

2) Change in land use. shall restore the site provisions at page 8-

nearest to its original 21 section 1.3 and

form as far as section 1.4.

possible.

NDC I NESPAK I ATKINS 4-19

Page 67: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr T- Quantities andNo. Impact Mitigation Measure Proviion in Contract Implementation Monitoring Costs

or SFA

11. Change of Earth Borrow Pit area

On the right bank 11) any activity outside 1) Contractors Contractor CRE PMO All costs already

upstream, instead of the fenced obligation to provide provided in BOQ.

locating borrow pits, the construction site to be full protection to the

Labor Camp and the strictly banned. sites constituting

batching plan has been 2) Traffic on the night Wildlife Sanctuary on

constructed over 20 Guide Bank to be provided in the

acres. The Borrow Area kept to a minimum. Contract.

has been shifted to 3) A buffer Zone of at 2) Also see EIA page

banks of D.G. Khan least 100 meters to be 8-28 Section 4.1 &

Canal where spoils are provided between Section 4.2, and page

available. This Change water edge of side 8-30 section 4.4.

has caused: protection bund and

1) Some effects on the fence.

Biodiversity. 4) Area other than the

2) Change in land use: 20 acres under

Building and Batching buildings not to

Plan instead of Borrow disturbed any further.

Pits.

3) A Buffer Zone is

NDC I NESPAK I ATKINS 4-20

Page 68: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility Quantities and

No. Impact Mitigation Measure Provision in Contract Implementation Monitoring Costsor SFA

formed between Wildlife

Sanctuary and the

construction & Batching

site.

12. Construction of Jetty

This will involve 1) No activity e.g. 1) Contractors Contractor CRE PMO All costs reflected in

modification of a part of boating, netting, contractual obligator the BOQ.

the river bank for angling, etc. to be to ensure no activity

facilitating the fixing of allowed from the jetty. except the contract

gates. This will cause Only essential Project work.

the following impacts:- activities are to be 2) Also see EIA page

1) Protruding into the allowed. 8-27 and 8-28 section

river (by 6m only) and 2) Dolphin to be 1.1. Pages 8-29

causing obstruction to specially protected. section 4.1, 4.2 page

flow in the left pocket, 8-30 Section.4.3.

(marginally) affecting

hydrology and the

ponded area upstream

NDC I NESPAK I ATKINS 4-21

Page 69: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Mitigation ResponsibilitySr Quantities and

Impact ~~~~~~~~Provision in ContractNo. Impact Mitigation Measure Provisior SEA Implementation Monitoring Costs

of the barrage.

2) Construction of a

jetty in a Wildlife

Sanctuary inhabited by

the endangered Indus

Dolphin.

13. Upgrading of fish ladders

This will involve repair The upgrading in itself Repairs and/or Contractor & CRE PMO & CRE Within existing

and/or modifying the is a mitigation modification are part contract.

existing structure so measure. Important is of the current

that it meets current to ensure that the contract.

standards and is better reconstruction occurs

at facilitating fish in a short span of time

migration. Impacts will so that effects on

be felt as during recon- migration are

struction they will not be minimized.

in use.

14. Cumulative Effects on Ponded area

Cumulative effects of The contractors Water levels, water Water levels, CRE & PMO No additional costs,

the coffer dam, lowering should therefore quality and fish kill water quality and as Contractor can

NDC I NESPAK I ATKINS 4-22

Page 70: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility Quantities andImpact ~~~~~~~Provision in Contract

No. Impact Mitigation Measure Provisior SEA Implementation Monitoring Costs

of the water table, carefully monitor: monitoring to be possible fish kills include these

grouting, and * water levels in the included in contract to be measured parameters in their

construction activities ponded area to amendment; dolphin by the Contractor; regular program; the

that increase ensure that a & waterbird monitor- rest if already

suspended sediment minimal depth of ing are included in Dolphin and included in the

levels may be 430 ft. is truly present contract with waterbird existing contract

significant for aquatic maintained; WWF for baseline numbers to be with WWF and will

species such as Indus * water quality, to study. assessed on a not involve

Dolphin. Together, ensure that oxygen regular basis by additional costs.

small water volumes & levels are within WWF during their

impacts on water quality safe levels (>2.0 baseline study.

may combine & create mg/I), suspended

adverse conditions. sediment is

generally below 80

mg/l (and never

above 400 mg/I)

due to the project,

and cement is not

spilled into the

river;

NDC INESPAK I ATKINS 4-23

Page 71: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

Sr Mitigation Responsibility Quantities andImpact ~~~~~~~~Provision in Contract

No. Impact Mitigation Measure Pror SE a Implementation Monitoring Costsor SFA

* possible fish kills

(and immediately

investigate any

report by taking

water and fish

samples for

analysis); and

* the Indus Dolphin

population and

waterbirds in the

ponded area and

its extension north

of the barrage, to

ensure that levels

remain constant, or

within normal (pre-

project) fluctuations

NDC I NESPAK I ATKINS 4-24

Page 72: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

4.3 MANAGEMENT OF CHANGES IN SOCIO-ECONOMIC IMPACTS

Since the changes are due to the physical readjustments within the overall Project area and a

better understanding of the location of the TBWS, this does not affect the status of the Social

Framework Agreement (SFA) provided in 8.10.3 of the EIA. The existing SFA can therefore

remain effective and is considered adequate for the purpose of this Change Management Plan.

4.4 ENVIRONMENTAL MANAGEMENT MONITORING PLAN (EMMP) FOR CHANGES

IN EMP I.E. CHANGES IN EMMP.

The EIA for the Taunsa Barrage Emergency Rehabilitation and Modemization Project was

accorded NOC by PEDP by means of letter NO.3521F-93/06091EIA, dated September 6th

2004. Subsequent to that, a detailed Environmental Management Monitoring Plan (EMMP) was

produced as per guidance presented in section 8.7 of the EIA (pages 8-10 to 8-12) and is

available in PMO office. The EMMP covers all types of activities to be carried out under the

contract and EIA in force. The Changes that have been mentioned earlier in this report pertain

to sites and not in type of activity, thus causing no practical change in the methodology of the

implementation of EMMP. Therefore, the EMMP already being implemented can remain

effective and no new EMMP will be required. The CMS can therefore be regarded as a

supplement, to be carried out in conjunction with the existing EMMP.

4.5 INSTITUTIONAL ARRANGEMENTS FOR CHANGE MANAGEMENT.

4.5.1 Management Responsibility

Management Responsibility for the Project as defined in Section 8.8 (pages 8.13 - 8.15) of EIA

covers all the aspects of the Project. Since the changes have been caused by recognition that

some of the activities occur within the Wildlife Sanctuary, and no change has been made to the

type and scope of activities (only in location), there is no need to redefine Management

Responsibilities, which can remain the same.

4.5.2 Institutional Strengthening

Institutional strengthening is referred to in paragraph 8.8.2 of the EIA. The institutional

strengthening already carried out by the project is considered adequate to handle the Change

Management.

4-25

Page 73: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

4.5.3 Reporting and Supervision

Reporting and Supervision are dealt with in paragraph 8.8.3 of the EIA, which provides a

prescription for Reporting and Supervision for the Project. This will generally be adequate for

undertaking the Change Management Plan. However, given that a number of activities are

being carried out in the TBWS, a report on the status of that part of the TBWS most directly

affected - the ponded area behind the barrage - should be produced by the Environmental Unit

(EU), based on water quality/quantity monitoring data collected by the Contractor, and data on

waterbirds and Indus Dolphin collected by WWF's baseline study program. A quarterly report

on the "Status of the TBWS Barrage Area" should be produced by the CRE/supervisors, and

distributed to PMO, who should forward this to IPD, Contractor and PWD for their perusal and

action.

4.5.4 Financial Implications

Since the activities undertaken in the Change Management Plan are already a physical part of

the Project for which a Contract and a BOQ exists, there shall be no new financial liability due

to Change Management on any of the stakeholders of the Project. This is also true for the

monitoring activities to be carried out by WWF, as these are part of the baseline study for which

they have been contracted by the PMO.

4.6 RECOMMENDATIONS

4.6.1 Avoidance through Design of New Structures and Work Designs

No new or revision of the design of any of the construction activities is proposed. There are

changes in the location of some of the structures, particularly those to be constructed inside the

Wildlife Sanctuary above the gate line of the barrage. However, some new activities have been

proposed that are associated with some of the already designed structures. These include the

coffer dam required for the gate repairs, and the lead canal required to mitigate effects of the

closure of the D.G. Khan canal.

4.6.2 Contractor's Obligation towards Change Management

Due to the belated realization that a number of project activities are located within the boundary

of the Wildlife Sanctuary, this perceived "change of site" requires a Change Management.

Physically, however, there shall be no change in the overall obligations of the Contractor.

NDC I NESPAK I ATKINS 4-26

Page 74: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

* Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

4.6.3 Social Framework Agreement (SFA) readjustments with Change Management

As already stated, the Social Framework Agreement already signed with the communities (refer

to the EIA paragraph 8.10.3, pages 8-45 to 8-49) is adequate and shall stay valid and does not

require revision.

4.6.4 PMO Responsibilities in Change Management

The Project Management Office (PMO) is already fully staffed and has adequate capacity to

implement the Project. The PMO should, however, improve coordination with government

departments such as Punjab Wildlife Department, Fisheries Department and Punjab Forest

Department, and with NGOs such as WWF, for reaping full benefits of the Change

Management.

4.6.5 Supervision Consultants Role in Change Management

The Supervision Consultant is already providing services in Monitoring, Reporting and in an

Advisory Capacity. The production of Daily, Weekly, Monthly, Biannual and Annual Reports has

already been agreed to for documentation purposes, and in addition, photographic and video

film coverage has also been provided. The Contractor's complaint Register and Implementation

Register are already being maintained. The elements of Change Management already stand

incorporated in the EIA and in the Contract. With the realization of the official location of the

boundary of the Wildlife Sanctuary, the supervision consultants shall take full care and

precautions that the Wildlife Sanctuary and Ramsar site is fully respected. The supervision

consultants are adequately staffed to handle the change management and no additional

staffing is required by them on their panel.

4.6.6 Action by wildlife department Punjab in Change Management

The Punjab Wildlife Department is advised to:

1. Issue the much-delayed renotification of the Taunsa Barrage Wildlife Sanctuary, which

expired in 2003. The boundaries of the Sanctuary should, however, be realistically

redefined, as both the official boundary of the 6,756 ha TBWS, and the recent 2,800 ha

proposed revision have serious flaws:

NDC I NESPAK I ATKINS 4-27

Page 75: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

* Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

a. The official boundary includes large swathes of intensively cultivated agricultural

land to the east and west of the two guide bunds, but does not include the entire

main island of the reserve (Matwani Wala) - instead, it cuts off the northern tip.

b. The latest draft boundary (2,800 ha) includes only the area between the two guide

bunds, plus a small, balloon-shaped area to the north of this that includes some of

the main island, but does not follow any natural feature.

c. Both boundaries also run up to the gate line of the barrage, which means that

barrage management will continue to run into difficulties in the future.

2. The PWD should consider redefining the TBWS boundary along the following lines:

include the ponded area north of the guide bunds, the entire main island (Matwani

Wala), plus the adjacent sandy islands and waterways. This could be supported by

WWF Pakistan's baseline study program at Taunsa, which is currently using GIS and

Remote Sensing imagery to study the site. The barrage area between the guide bunds

will remain a protected area for Indus Dolphin and waterbirds, as public access, hunting,

fishing and disturbance are not permitted by the Barrage Operator. It can also remain

part of the Ramsar site.

3. PWD should strengthen its management presence at the TBWS. At present, there is

little indication to the public that the site is a protected area, apart from two small signs

indicating prohibitions. There is no awareness raising about the natural value of the

area, nor is there a visitor's center or signage indicating its location. Staff presence is

low, and illegal extractive activities on the island are rampant.

4. Special arrangements for patrolling in the project area may be made for protection of

wildlife in general, and Indus Dolphins and waterfowl in particular, throughout the year.

If required necessary logistic support for PWD may be obtained from the PMO.

4.6.7 Action by Environment Protection Department (EPD) in Change Management

The Environmental Protection Department is requested to:

i. Take up the issue of demarcation of the southern boundary of the Taunsa Barrage

Wildlife Sanctuary. The boundary of Sanctuary may better be placed at the upper end of

the barrage i.e. the line which joins the upper ends of the two Guide bunds. A correct

definition of "barrage" may be incorporated in the notification in consultation with

Irrigation and Power Department.

NDC I NESPAK I ATKINS 4-28

Page 76: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

Taunsa Barrage Emergency Rehabilitation and Modernization Project Change Management Statement

4.6.8 Action by WWF in Change Management

WWF-Pakistan is requested to:

i. Give priority, for the Baseline study, to the waters insides the barrage area i.e. the part

of river between the line joining the ends of two Guide Bunds.

ii. Produce a set of critical indicators specific to the Taunsa Barrage Wetland to be used

as a baseline in any future projects.

iii. Provide recommendations on how the TBWS boundary can best be redefined, and

assess if realignment is required.

iv. Provide information and data on a regular basis regarding the status and population of

Indus dolphin and waterbirds in the barrage area, and in the ponded area to the north of

the barrage. <This information is intended for use in the quarterly monitoring reports,

used for monitoring the effects of the project on the barrage ponded area.>

4.6.9 Donor's Patronage in Change Management

Donor's Patronage is requested in the following ways:

i. Their continued appreciation of the Monitoring and Reporting System of the Project is

highly valued.

ii. Although this Change Management Plan has been produced, recognizing the inclusion

of the Barrage area in the Wildlife Sanctuary, the final notification may be awaited from

the Punjab Wildlife Department.

4.6.10 Operational Management Readjustments with Change Management

The PMO, for the period during the Project period, and the Irrigation and Power Department for

after the Project phase is adequately staffed and suitably organized to adjust with the proposed

Change Management Plan. No new arrangements have been demanded or envisaged at this

stage.

NDC I NESPAK I ATKINS 4-29

Page 77: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

a

ANNEXES

Page 78: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

ANNEX-1

LEGEND:-

*WILDLIFE SANCTUARY AS CLAIMED AFTER

DEFUNCT NOTIFICATION

WILDLIFE SACTUARY BEING PROPOSED IN

RECENT NOTIFICATION

* PROPOSED WILDLIFE SANCTUIARY

*BELA SDNE ONSEDth OF TMANBDX D. EACACIA NUPEA ND PMUIJS EIP,NICAWEr LAND

*OEN WATER L_D WM GRASSES, MMM OM TlPN. /WET LAND

1 PERIPHERY OF THE VILDLIFE S1ACTUARY

* CWA1E 1Y . IY

* MNAGOTUFW LAND /

* WEnAMDEGM USE AS OPEN ERAZiC LAND

*TAMIA WAWBa BETrEN S THEB GLIDEED

AND THE TARAD SWAGAE EAYE LKC

MOM HIHRE BDOJTR SATUOT WACER

* ASE- 2DB APF 2005

EATTEW MC POWER EAOPAI

TAUNSA BARRAGE EMERGENCYREHABILITATION AND MODERNIZATION PROJECT

PUNJAB BARRAGES CONSULTANTS .

TAUNSA BARRAGE

TAUNSA BARRAGE WILDLIFE SANCTUARY

AND THE TAUNSA BARRAGE

OE DI -200 I"2

Page 79: TAUNSA BARRAGE EMERGENCY REHABILITATION AND …

ANNEX -2

TAUNSA BARRAGE

LOCATION OF FACILITES AND WORKS FOR CHANGE MANAGEMENT

a 5T''h , czZ__ -_ _- 'n ~ - \ -N_ O - W , \ ' TAUNSA_ \ <// , ~~, ,__:, ;,/ \ 3 _; ' ~~~-_ Xv \ rBARRAGE aIrr~~ ;Ds [>w ~~ .~~ -BARRAG

RAIL TRACK -

_~~~ ~ -- | 1 r 4 C vV F

| TAUNSA BARRAGE EMERGENCYREHABILITATION AND MODERNIZATION PROJECT

PUNJAB BARRAGES CONSULTANTS

TAUNSA BARRAGE

LOCATION OF FACILITES AND WORKS FOR

CHANGE MANAGEMENT