Activity ID Activity Name Original Duration Start Finish Total Float Al Reem Island Development-Sector 5&6-Baseline TB01[200109] 394 20-Jan-09 17-Feb-10 0 Major Milestones 394 20-Jan-09 17-Feb-10 0 Major Milestones by Contractor 394 20-Jan-09 17-Feb-10 0 Milestones 394 20-Jan-09 17-Feb-10 0 A5660 Receive Letter of Acceptance [LOA] 0 20-Jan-09 0 A5670 Hammock Project Duration 387 27-Jan-09 17-Feb-10 0 A5690 Possession/Access To Site 21 27-Jan-09 16-Feb-09 67 A5700 Submit of Advance Payment Bank Guarantee 18 27-Jan-09 13-Feb-09 66 A29580 Commencement Day of The Contract 0 27-Jan-09 0 A5710 Provision of Certificates of Verification of Insurance Cover 7 14-Feb-09 20-Feb-09 66 A5740 Completion of Sorbonne Area 0 30-Jul-09* 0 A5750 Contract Completion Day 0 17-Feb-10* 0 Completion of Roads Milestones 54 30-Nov-09 23-Jan-10 15 A5820 Completion of Road 7 0 30-Nov-09 69 A5830 Completion of Road 8 0 30-Dec-09 39 A5810 Completion of Road 6 0 05-Jan-10 33 A5800 Completion of Road 5 0 11-Jan-10 27 A5790 Completion of Road 4 0 18-Jan-10 20 A5780 Completion of Road 3 0 23-Jan-10 15 Utilities Milestones 150 25-May-09 22-Oct-09 34 A30170 End of Utilities of Road A3 0 25-May-09 36 A6000 End of Utilities of Road H3 0 07-Jun-09 23 A5900 End of Utilities of Road C5 0 10-Jun-09 20 A5870 End of Utilities of Road C2 0 18-Jun-09 12 A5860 End of Utilities of Road B5 0 22-Jun-09 8 A5880 End of Utilities of Road C3 0 25-Jun-09 5 A6040 End of Utilities of Ramp 2 0 28-Jun-09 150 A5890 End of Utilities of Road C4 0 30-Jun-09 0 A5950 End of Utilities of Road F2 0 30-Jun-09 148 A5960 End of Utilities of Road F3 0 18-Jul-09 130 A5980 End of Utilities of Road G3 0 28-Jul-09 120 A5930 End of Utilities of Road E3 0 01-Aug-09 116 A6030 End of Utilities of Road K 0 13-Aug-09 104 D J F M A M J Jul A S O N D J F M 2009 2010 Receive Letter of Acceptance [LOA] Ham Possession/Access To Site Submit of Advance Payment Bank Guarantee Commencement Day of The Contract Provision of Certificates of Verification of Insuran Completion of Sorbonne Area Con Completion o Completio Completi Complet Comple Compl End of Utilities of Road A3 End of Utilities of Road H3 End of Utilities of Road C5 End of Utilities of Road C2 End of Utilities of Road B5 End of Utilities of Road C3 End of Utilities of Ramp 2 End of Utilities of Road C4 End of Utilities of Road F2 End of Utilities of Road F3 End of Utilities of Road G3 End of Utilities of Road E3 End of Utilities of Road K Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09 Remaining Level of Effort Actual Work Remaining Work Critical Remaining Work Milestone Actual Level ... Page 1 of 43

TB01[200109] All Activities Layout

Embed Size (px)

Citation preview

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    Al Reem Island Development-Sector 5&6-Baseline TB01[200109]Al Reem Island Development-Sector 5&6-Baseline TB01[200109] 394 20-Jan-09 17-Feb-10 0Major MilestonesMajor Milestones 394 20-Jan-09 17-Feb-10 0Major Milestones by ContractorMajor Milestones by Contractor 394 20-Jan-09 17-Feb-10 0MilestonesMilestones 394 20-Jan-09 17-Feb-10 0A5660 Receive Letter of Acceptance [LOA] 0 20-Jan-09 0A5670 Hammock Project Duration 387 27-Jan-09 17-Feb-10 0A5690 Possession/Access To Site 21 27-Jan-09 16-Feb-09 67A5700 Submit of Advance Payment Bank Guarantee 18 27-Jan-09 13-Feb-09 66A29580 Commencement Day of The Contract 0 27-Jan-09 0A5710 Provision of Certificates of Verification of Insurance Cover 7 14-Feb-09 20-Feb-09 66A5740 Completion of Sorbonne Area 0 30-Jul-09* 0A5750 Contract Completion Day 0 17-Feb-10* 0

    Completion of Roads MilestonesCompletion of Roads Milestones 54 30-Nov-09 23-Jan-10 15A5820 Completion of Road 7 0 30-Nov-09 69A5830 Completion of Road 8 0 30-Dec-09 39A5810 Completion of Road 6 0 05-Jan-10 33A5800 Completion of Road 5 0 11-Jan-10 27A5790 Completion of Road 4 0 18-Jan-10 20A5780 Completion of Road 3 0 23-Jan-10 15

    Utilities MilestonesUtilities Milestones 150 25-May-09 22-Oct-09 34A30170 End of Utilities of Road A3 0 25-May-09 36A6000 End of Utilities of Road H3 0 07-Jun-09 23A5900 End of Utilities of Road C5 0 10-Jun-09 20A5870 End of Utilities of Road C2 0 18-Jun-09 12A5860 End of Utilities of Road B5 0 22-Jun-09 8

    A5880 End of Utilities of Road C3 0 25-Jun-09 5A6040 End of Utilities of Ramp 2 0 28-Jun-09 150A5890 End of Utilities of Road C4 0 30-Jun-09 0A5950 End of Utilities of Road F2 0 30-Jun-09 148A5960 End of Utilities of Road F3 0 18-Jul-09 130A5980 End of Utilities of Road G3 0 28-Jul-09 120A5930 End of Utilities of Road E3 0 01-Aug-09 116A6030 End of Utilities of Road K 0 13-Aug-09 104

    D J F M A M J Jul A S O N D J F M2009 2010

    Receive Letter of Acceptance [LOA]Hammock Project Duration

    Possession/Access To SiteSubmit of Advance Payment Bank Guarantee

    Commencement Day of The ContractProvision of Certificates of Verification of Insurance Cover

    Completion of Sorbonne AreaContract Completion Day

    Completion of Road 7Completion of Road 8Completion of Road 6Completion of Road 5Completion of Road 4Completion of Road 3

    End of Utilities of Road A3End of Utilities of Road H3End of Utilities of Road C5End of Utilities of Road C2End of Utilities of Road B5

    End of Utilities of Road C3End of Utilities of Ramp 2End of Utilities of Road C4End of Utilities of Road F2

    End of Utilities of Road F3End of Utilities of Road G3End of Utilities of Road E3

    End of Utilities of Road K

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 1 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A6010 End of Utilities of Road J1 0 23-Aug-09 94A6050 End of Utilities of Road 1 0 23-Aug-09 94A5990 End of Utilities of Road H2 0 25-Aug-09 92A6020 End of Utilities of Road J2 0 25-Aug-09 92A5910 End of Utilities of Road E1 0 27-Aug-09 90A5850 End of Utilities of Road B4 0 29-Aug-09 88A5920 End of Utilities of Road E2 0 30-Aug-09 87A5940 End of Utilities of Road E4 0 15-Sep-09 71A5970 End of Utilities of Road G2 0 19-Sep-09 67A6120 End of Utilities of Road 8 0 03-Oct-09 53A6090 End of Utilities of Road 5 0 05-Oct-09 51A6100 End of Utilities of Road 6 0 12-Oct-09 44A6110 End of Utilities of Road 7 0 14-Oct-09 42A6080 End of Utilities of Road 4 0 18-Oct-09 38A6070 End of Utilities of Road 3 0 22-Oct-09 34

    Networks MilestonesNetworks Milestones 88 01-Aug-09 28-Oct-09 28A6130 Completion of Sewerage Network 0 01-Aug-09 116A6160 Completion of Potable Water Network 0 17-Aug-09 100A6150 Completion of Gas Network 0 26-Aug-09 91A6180 Completion of Telecommunication Network 0 29-Aug-09 88A6140 Completion of Irrigation Network 0 06-Sep-09 80A6210 Completion of Low Voltage Network 0 29-Sep-09 57A6170 Completion of Surface Water Network 0 03-Oct-09 53A6190 Completion of Street Lighting Network 0 27-Oct-09 29A6200 Completion of 22KV Electrical Network 0 28-Oct-09 28

    Major Milestones by ClientMajor Milestones by Client 22 27-Jan-09 17-Feb-09 66MilestonesMilestones 22 27-Jan-09 17-Feb-09 66A6300 Receipt of IFC (Furnished by Client) 1 27-Jan-09 27-Jan-09 0A6250 Receipt of Advance Payment from Employer 4 14-Feb-09 17-Feb-09 66

    Engineering & SubmittalsEngineering & Submittals 42 27-Jan-09 09-Mar-09 70A6330 Sub of Proposed HSE Management Plan 28 27-Jan-09 23-Feb-09 60A6340 Sub of Proposed QA/QC Plan 28 27-Jan-09 23-Feb-09 60A6360 Sub & Prep Baseline Schedule 28 27-Jan-09 23-Feb-09 70A6370 Rev & App Baseline Schedule 14 24-Feb-09 09-Mar-09 70

    D J F M A M J Jul A S O N D J F M2009 2010

    End of Utilities of Road J1End of Utilities of Road 1End of Utilities of Road H2End of Utilities of Road J2End of Utilities of Road E1End of Utilities of Road B4End of Utilities of Road E2

    End of Utilities of Road E4End of Utilities of Road G2

    End of Utilities of Road 8End of Utilities of Road 5End of Utilities of Road 6End of Utilities of Road 7End of Utilities of Road 4End of Utilities of Road 3

    Completion of Sewerage NetworkCompletion of Potable Water NetworkCompletion of Gas NetworkCompletion of Telecommunication NetworkCompletion of Irrigation Network

    Completion of Low Voltage NetworkCompletion of Surface Water Network

    Completion of Street Lighting NetworkCompletion of 22KV Electrical Network

    Receipt of IFC (Furnished by Client)Receipt of Advance Payment from Employer

    Sub of Proposed HSE Management PlanSub of Proposed QA/QC PlanSub & Prep Baseline Schedule

    Rev & App Baseline Schedule

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 2 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    Shop DrawingsShop Drawings 213 28-Jan-09 28-Aug-09 15Submittal & Preparation for Sorbonne CrossingsSubmittal & Preparation for Sorbonne Crossings 90 28-Jan-09 27-Apr-09 36A30480 Sub&Prep Shop Drawings for Sorbonne Sewage Crossing 15 28-Jan-09 11-Feb-09 19A30490 Sub&Prep Shop Drawings for Sorbonne Potable Water Crossing 30 28-Jan-09 26-Feb-09 11A30500 Sub&Prep Shop Drawings for Sorbonne Gas Crossing 45 28-Jan-09 13-Mar-09 9A30510 Sub&Prep Shop Drawings for Sorbonne Irrigation Crossing 60 28-Jan-09 28-Mar-09 10A30520 Sub&Prep Shop Drawings for Sorbonne 22kv Crossing 75 28-Jan-09 12-Apr-09 14A30530 Sub&Prep Shop Drawings for Sorbonne Street Lighting Crossing 90 28-Jan-09 27-Apr-09 36

    Review & Approval for Sorbonne CrossingsReview & Approval for Sorbonne Crossings 90 12-Feb-09 12-May-09 40A30550 Review and Approval Shop Drawings for Sorbonne Sewage Crossing 15 12-Feb-09 26-Feb-09 48A30560 Review and Approval Shop Drawings for Sorbonne Potable Water Crossing 15 27-Feb-09 13-Mar-09 42A30570 Review and Approval Shop Drawings for Sorbonne Gas Crossing 15 14-Mar-09 28-Mar-09 53A30580 Review and Approval Shop Drawings for Sorbonne Irrigation Crossing 15 29-Mar-09 12-Apr-09 59A30590 Review and Approval Shop Drawings for Sorbonne 22kv Crossing 15 13-Apr-09 27-Apr-09 33A30600 Review and Approval Shop Drawings for Sorbonne Street Lighting Crossing 15 28-Apr-09 12-May-09 40

    Submittal & Preparation for Sorbonne NetworkSubmittal & Preparation for Sorbonne Network 111 28-Jan-09 18-May-09 14A30090 Sub&Prep Shop Drawings for Temporary STP 81 28-Jan-09 18-Apr-09 17A30280 Sub&Prep Shop Drawings for Sorbonne Sewage Network 15 12-Feb-09 26-Feb-09 19A30290 Sub&Prep Shop Drawings for Sorbonne Potable Water Network 21 27-Feb-09 19-Mar-09 11A30300 Sub&Prep Shop Drawings for Sorbonne Gas Network 21 14-Mar-09 03-Apr-09 9A30310 Sub&Prep Shop Drawings for Sorbonne Telecommunication Network 21 29-Mar-09 18-Apr-09 10A30320 Sub&Prep Shop Drawings for Sorbonne 22kv Network 21 13-Apr-09 03-May-09 15A30330 Sub&Prep Shop Drawings for Sorbonne Low Voltage Network 36 13-Apr-09 18-May-09 14

    Review & Approval for Sorbonne NetworkReview & Approval for Sorbonne Network 96 27-Feb-09 02-Jun-09 14A30340 Review and Approval Shop Drawings for Sorbonne Sewage Network 15 27-Feb-09 13-Mar-09 19

    A30350 Review and Approval Shop Drawings for Sorbonne Potable Water Network 15 20-Mar-09 03-Apr-09 17A30360 Review and Approval Shop Drawings for Sorbonne Gas Network 15 04-Apr-09 18-Apr-09 17A30100 Review and Approval Shop Drawings for Temporary STP 15 19-Apr-09 03-May-09 17A30370 Review and Approval Shop Drawings for Sorbonne Telecommunication Network 15 19-Apr-09 03-May-09 18A30380 Review and Approval Shop Drawings for Sorbonne 22kv Network 15 04-May-09 18-May-09 15A30390 Review and Approval Shop Drawings for Sorbonne Low Voltage Network 15 19-May-09 02-Jun-09 14

    Submittal & Preparation for Remaining ProjectSubmittal & Preparation for Remaining Project 147 20-Mar-09 13-Aug-09 15A21620 Sub&Prep Shop Drawings for Potable Water Network 57 20-Mar-09 15-May-09 11

    D J F M A M J Jul A S O N D J F M2009 2010

    Sub&Prep Shop Drawings for Sorbonne Sewage CrossingSub&Prep Shop Drawings for Sorbonne Potable Water Crossing

    Sub&Prep Shop Drawings for Sorbonne Gas CrossingSub&Prep Shop Drawings for Sorbonne Irrigation Crossing

    Sub&Prep Shop Drawings for Sorbonne 22kv CrossingSub&Prep Shop Drawings for Sorbonne Street Lighting Crossing

    Review and Approval Shop Drawings for Sorbonne Sewage CrossingReview and Approval Shop Drawings for Sorbonne Potable Water Crossing

    Review and Approval Shop Drawings for Sorbonne Gas CrossingReview and Approval Shop Drawings for Sorbonne Irrigation Crossing

    Review and Approval Shop Drawings for Sorbonne 22kv CrossingReview and Approval Shop Drawings for Sorbonne Street Lighting Crossing

    Sub&Prep Shop Drawings for Temporary STPSub&Prep Shop Drawings for Sorbonne Sewage Network

    Sub&Prep Shop Drawings for Sorbonne Potable Water NetworkSub&Prep Shop Drawings for Sorbonne Gas Network

    Sub&Prep Shop Drawings for Sorbonne Telecommunication NetworkSub&Prep Shop Drawings for Sorbonne 22kv Network

    Sub&Prep Shop Drawings for Sorbonne Low Voltage Network

    Review and Approval Shop Drawings for Sorbonne Sewage Network

    Review and Approval Shop Drawings for Sorbonne Potable Water NetworkReview and Approval Shop Drawings for Sorbonne Gas Network

    Review and Approval Shop Drawings for Temporary STPReview and Approval Shop Drawings for Sorbonne Telecommunication Network

    Review and Approval Shop Drawings for Sorbonne 22kv NetworkReview and Approval Shop Drawings for Sorbonne Low Voltage Network

    Sub&Prep Shop Drawings for Potable Water Network

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 3 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A21580 Sub&Prep Shop Drawings for Sewage Network 21 04-Apr-09 24-Apr-09 15A21590 Sub&Prep Shop Drawings for Gas Network 57 04-Apr-09 30-May-09 21A21600 Sub&Prep Shop Drawings for Irrigation Network 72 04-Apr-09 14-Jun-09 9A21570 Sub&Prep Shop Drawings for Storm Water Network 87 19-Apr-09 14-Jul-09 10A21660 Sub&Prep Shop Drawings for Telecommunication Network 72 19-Apr-09 29-Jun-09 20A21650 Sub&Prep Shop Drawings for 22kv Network 87 04-May-09 29-Jul-09 20A21670 Sub&Prep Shop Drawings for Street Lighting Network 87 19-May-09 13-Aug-09 15A21690 Sub&Prep Shop Drawings for Low Voltage Network 87 19-May-09 13-Aug-09 15

    Review & Approval for Remaining ProjectReview & Approval for Remaining Project 126 25-Apr-09 28-Aug-09 15A27710 Review and Approval Shop Drawings for Sewage Network 15 25-Apr-09 09-May-09 15A27750 Review and Approval Shop Drawings for Potable Water Network 15 16-May-09 30-May-09 11A27720 Review and Approval Shop Drawings for Gas Network 15 31-May-09 14-Jun-09 21A27730 Review and Approval Shop Drawings for Irrigation Network 15 15-Jun-09 29-Jun-09 9A27790 Review and Approval Shop Drawings for Telecommunication Network 15 30-Jun-09 14-Jul-09 20A27700 Review and Approval Shop Drawings for Storm Water Network 15 15-Jul-09 29-Jul-09 10A27780 Review and Approval Shop Drawings for 22kv Network 15 30-Jul-09 13-Aug-09 20A27800 Review and Approval Shop Drawings for Street Lighting Network 15 14-Aug-09 28-Aug-09 15A27820 Review and Approval Shop Drawings for Low Voltage Network 15 14-Aug-09 28-Aug-09 15

    Procurement and DeliveryProcurement and Delivery 240 27-Jan-09 23-Sep-09 111Bid & AwardBid & Award 90 28-Jan-09 27-Apr-09 142A29800 Bid & Award - Valve (Irrigation) 14 28-Jan-09 10-Feb-09 40A29810 Bid & Award - Geotextile Fabric 14 28-Jan-09 10-Feb-09 213A29820 Bid & Award - Traffic Sign 14 28-Jan-09 10-Feb-09 218A29830 Bid & Award - Light Pole & Luminaries 60 28-Jan-09 28-Mar-09 0A29840 Bid & Award - Control Cabinet (Street Light) 90 28-Jan-09 27-Apr-09 69

    A29850 Bid & Award - LV Cable (Street Light) 90 28-Jan-09 27-Apr-09 22A29880 Bid & Award - HDPE Pipe (Irrigation) 30 28-Jan-09 26-Feb-09 47A29900 Bid & Award - PE100 Pipe (Gas) 30 28-Jan-09 26-Feb-09 17A29910 Bid & Award - UPVC Duct (Telecom) 30 28-Jan-09 26-Feb-09 34A29920 Bid & Award - LV Cable (Power) 30 28-Jan-09 26-Feb-09 59A29930 Bid & Award - Valve (Gas) 30 28-Jan-09 26-Feb-09 25A29940 Bid & Award - 22kv Cable (Power) 30 28-Jan-09 26-Feb-09 40A29960 Bid & Award - HDPE Pipe (Potable Water) 15 28-Jan-09 11-Feb-09 17

    D J F M A M J Jul A S O N D J F M2009 2010

    Sub&Prep Shop Drawings for Sewage NetworkSub&Prep Shop Drawings for Gas Network

    Sub&Prep Shop Drawings for Irrigation NetworkSub&Prep Shop Drawings for Storm Water Network

    Sub&Prep Shop Drawings for Telecommunication NetworkSub&Prep Shop Drawings for 22kv Network

    Sub&Prep Shop Drawings for Street Lighting NetworkSub&Prep Shop Drawings for Low Voltage Network

    Review and Approval Shop Drawings for Sewage NetworkReview and Approval Shop Drawings for Potable Water Network

    Review and Approval Shop Drawings for Gas NetworkReview and Approval Shop Drawings for Irrigation Network

    Review and Approval Shop Drawings for Telecommunication NetworkReview and Approval Shop Drawings for Storm Water Network

    Review and Approval Shop Drawings for 22kv NetworkReview and Approval Shop Drawings for Street Lighting NetworkReview and Approval Shop Drawings for Low Voltage Network

    Bid & Award - Valve (Irrigation)Bid & Award - Geotextile FabricBid & Award - Traffic Sign

    Bid & Award - Light Pole & LuminariesBid & Award - Control Cabinet (Street Light)

    Bid & Award - LV Cable (Street Light)Bid & Award - HDPE Pipe (Irrigation)Bid & Award - PE100 Pipe (Gas)Bid & Award - UPVC Duct (Telecom)Bid & Award - LV Cable (Power)Bid & Award - Valve (Gas)Bid & Award - 22kv Cable (Power)

    Bid & Award - HDPE Pipe (Potable Water)

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 4 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A29970 Bid & Award - GRP Duct Pipe (Potable Water) 15 28-Jan-09 11-Feb-09 17A29980 Bid & Award - GRP Duct Pipe (Surface Water) 15 28-Jan-09 11-Feb-09 110A29990 Bid & Award - Valve (Potable Water) 30 28-Jan-09 26-Feb-09 9A30000 Bid & Award - RC Pipe (Surface Water) 14 28-Jan-09 10-Feb-09 93A30110 Bid & Award - Temporary STP Tank 30 28-Jan-09 26-Feb-09 0A29860 Bid & Award - Fire Hydrant & Fittings 14 28-Jan-09 10-Feb-09 5A29870 Bid & Award - UPVC Pipe (Sewerage) 14 28-Jan-09 10-Feb-09 0A29950 Bid & Award - GRP Pipe (Sewerage) 14 28-Jan-09 10-Feb-09 0

    Submittal & Preparation for Sorbonne Crossing & IntersectionsSubmittal & Preparation for Sorbonne Crossing & Intersections 14 27-Jan-09 09-Feb-09 106A30670 Sub & Prep - UPVC Duct Pipe (Sewerage) 14 27-Jan-09 09-Feb-09 37A30680 Sub & Prep - GRP Duct Pipe (Potable Water) 14 27-Jan-09 09-Feb-09 48A30690 Sub & Prep - GRP Duct Pipe (Irrigation Water) 14 27-Jan-09 09-Feb-09 96A30700 Sub & Prep - UPVC Duct Pipe (Gas) 14 27-Jan-09 09-Feb-09 76A30710 Sub & Prep - UPVC Duct Pipe (Street Lighting) 14 27-Jan-09 09-Feb-09 106A30720 Sub & Prep - UPVC Duct Pipe (22kV) 14 27-Jan-09 09-Feb-09 84

    Submittal & Preparation Remaining ProjectSubmittal & Preparation Remaining Project 90 11-Feb-09 11-May-09 142A28950 Sub & Prep - Valve (Irrigation) 14 11-Feb-09 24-Feb-09 40A28960 Sub & Prep - Geotextile Fabric 14 11-Feb-09 24-Feb-09 213A28970 Sub & Prep - Traffic Sign 14 11-Feb-09 24-Feb-09 218A14140 Sub & Prep - Fire Hydrant & Fittings 14 11-Feb-09 24-Feb-09 5A14170 Sub & Prep - UPVC Pipe (Sewerage) 14 11-Feb-09 24-Feb-09 0A18690 Sub & Prep - GRP Pipe (Sewerage) 14 11-Feb-09 24-Feb-09 0A28750 Sub & Prep - RC Pipe (Surface Water) 14 11-Feb-09 24-Feb-09 93A21930 Sub & Prep - HDPE Pipe (Potable Water) 14 12-Feb-09 25-Feb-09 17A21960 Sub & Prep - GRP Duct Pipe (Potable Water) 14 12-Feb-09 25-Feb-09 17

    A29000 Sub & Prep - GRP Duct Pipe (Surface Water) 14 12-Feb-09 25-Feb-09 110A14200 Sub & Prep - HDPE Pipe (Irrigation) 14 27-Feb-09 12-Mar-09 47A18280 Sub & Prep - PE100 Pipe (Gas) 14 27-Feb-09 12-Mar-09 17A18310 Sub & Prep - UPVC Duct (Telecom) 14 27-Feb-09 12-Mar-09 34A18490 Sub & Prep - LV Cable (Power) 14 27-Feb-09 12-Mar-09 59A18530 Sub & Prep - Valve (Gas) 14 27-Feb-09 12-Mar-09 25A18620 Sub & Prep - 22kv Cable (Power) 14 27-Feb-09 12-Mar-09 40A28310 Sub & Prep - Valve (Potable Water) 14 27-Feb-09 12-Mar-09 9A30120 Sub & Prep - Temporary STP Tank 14 27-Feb-09 12-Mar-09 0

    D J F M A M J Jul A S O N D J F M2009 2010

    Bid & Award - GRP Duct Pipe (Potable Water)Bid & Award - GRP Duct Pipe (Surface Water)

    Bid & Award - Valve (Potable Water)Bid & Award - RC Pipe (Surface Water)

    Bid & Award - Temporary STP TankBid & Award - Fire Hydrant & FittingsBid & Award - UPVC Pipe (Sewerage)Bid & Award - GRP Pipe (Sewerage)

    Sub & Prep - UPVC Duct Pipe (Sewerage)Sub & Prep - GRP Duct Pipe (Potable Water)Sub & Prep - GRP Duct Pipe (Irrigation Water)Sub & Prep - UPVC Duct Pipe (Gas)Sub & Prep - UPVC Duct Pipe (Street Lighting)Sub & Prep - UPVC Duct Pipe (22kV)

    Sub & Prep - Valve (Irrigation)Sub & Prep - Geotextile FabricSub & Prep - Traffic SignSub & Prep - Fire Hydrant & FittingsSub & Prep - UPVC Pipe (Sewerage)Sub & Prep - GRP Pipe (Sewerage)Sub & Prep - RC Pipe (Surface Water)Sub & Prep - HDPE Pipe (Potable Water)Sub & Prep - GRP Duct Pipe (Potable Water)

    Sub & Prep - GRP Duct Pipe (Surface Water)Sub & Prep - HDPE Pipe (Irrigation)Sub & Prep - PE100 Pipe (Gas)Sub & Prep - UPVC Duct (Telecom)Sub & Prep - LV Cable (Power)Sub & Prep - Valve (Gas)Sub & Prep - 22kv Cable (Power)Sub & Prep - Valve (Potable Water)Sub & Prep - Temporary STP Tank

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 5 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A28980 Sub & Prep - Light Pole & Luminaries 14 29-Mar-09 11-Apr-09 0A14080 Sub & Prep - Control Cabinet (Street Light) 14 28-Apr-09 11-May-09 69A14110 Sub & Prep - LV Cable (Street Light) 14 28-Apr-09 11-May-09 22

    Review & Approval for Sorbonne Crossing & IntersectionsReview & Approval for Sorbonne Crossing & Intersections 14 10-Feb-09 23-Feb-09 106A30730 Rev & App - GRP Duct Pipe (Irrigation Water) 14 10-Feb-09 23-Feb-09 96A30740 Rev & App - GRP Duct Pipe (Potable Water) 14 10-Feb-09 23-Feb-09 48A30750 Rev & App - UPVC Duct Pipe (22kV) 14 10-Feb-09 23-Feb-09 84A30760 Rev & App - UPVC Duct Pipe (Gas) 14 10-Feb-09 23-Feb-09 76A30770 Rev & App - UPVC Duct Pipe (Sewerage) 14 10-Feb-09 23-Feb-09 37A30780 Rev & App - UPVC Duct Pipe (Street Lighting) 14 10-Feb-09 23-Feb-09 106

    Review & Approval Remaining ProjectReview & Approval Remaining Project 90 25-Feb-09 25-May-09 142A2360 Rev & App - Valve (Irrigation) 14 25-Feb-09 10-Mar-09 40A2370 Rev & App - Geotextile Fabric 14 25-Feb-09 10-Mar-09 213A2380 Rev & App - Traffic Sign 14 25-Feb-09 10-Mar-09 218A14150 Rev & App - Fire Hydrant & Fittings 14 25-Feb-09 10-Mar-09 5A14180 Rev & App - UPVC Pipe (Sewerage) 14 25-Feb-09 10-Mar-09 0A18700 Rev & App - GRP Pipe (Sewerage) 14 25-Feb-09 10-Mar-09 0A28760 Rev & App - RC Pipe (Surface Water) 14 25-Feb-09 10-Mar-09 93A21920 Rev & App - HDPE Pipe (Potable Water) 14 26-Feb-09 11-Mar-09 17A21950 Rev & App - GRP Duct Pipe (Potable Water) 14 26-Feb-09 11-Mar-09 17A2400 Rev & App - GRP Duct Pipe (Surface Water) 14 26-Feb-09 11-Mar-09 110A14210 Rev & App - HDPE Pipe (Irrigation) 14 13-Mar-09 26-Mar-09 47A18290 Rev & App - PE100 Pipe (Gas) 14 13-Mar-09 26-Mar-09 17A18320 Rev & App - UPVC Duct (Telecom) 14 13-Mar-09 26-Mar-09 34A18500 Rev & App - LV Cable (Power) 14 13-Mar-09 26-Mar-09 59

    A18540 Rev & App - Valve (Gas) 14 13-Mar-09 26-Mar-09 25A18630 Rev & App - 22kv Cable (Power) 14 13-Mar-09 26-Mar-09 40A28320 Rev & App - Valve (Potable Water) 14 13-Mar-09 26-Mar-09 9A30130 Rev & App - Temporary STP Tank 14 13-Mar-09 26-Mar-09 0A2390 Rev & App - Light Pole & Luminaries 14 12-Apr-09 25-Apr-09 0A14090 Rev & App - Control Cabinet (Street Light) 14 12-May-09 25-May-09 69A14120 Rev & App - LV Cable (Street Light) 14 12-May-09 25-May-09 22

    Fabrication & DeliveryFabrication & Delivery 197 11-Mar-09 23-Sep-09 111Fabrication & Delivery for SorbonneFabrication & Delivery for Sorbonne 96 11-Mar-09 14-Jun-09 4

    D J F M A M J Jul A S O N D J F M2009 2010

    Sub & Prep - Light Pole & LuminariesSub & Prep - Control Cabinet (Street Light)Sub & Prep - LV Cable (Street Light)

    Rev & App - GRP Duct Pipe (Irrigation Water)Rev & App - GRP Duct Pipe (Potable Water)Rev & App - UPVC Duct Pipe (22kV)Rev & App - UPVC Duct Pipe (Gas)Rev & App - UPVC Duct Pipe (Sewerage)Rev & App - UPVC Duct Pipe (Street Lighting)

    Rev & App - Valve (Irrigation)Rev & App - Geotextile FabricRev & App - Traffic SignRev & App - Fire Hydrant & FittingsRev & App - UPVC Pipe (Sewerage)Rev & App - GRP Pipe (Sewerage)Rev & App - RC Pipe (Surface Water)Rev & App - HDPE Pipe (Potable Water)Rev & App - GRP Duct Pipe (Potable Water)Rev & App - GRP Duct Pipe (Surface Water)

    Rev & App - HDPE Pipe (Irrigation)Rev & App - PE100 Pipe (Gas)Rev & App - UPVC Duct (Telecom)Rev & App - LV Cable (Power)

    Rev & App - Valve (Gas)Rev & App - 22kv Cable (Power)Rev & App - Valve (Potable Water)Rev & App - Temporary STP Tank

    Rev & App - Light Pole & LuminariesRev & App - Control Cabinet (Street Light)Rev & App - LV Cable (Street Light)

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 6 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A29640 Fab & Del [Sorbonne]- Fire Hydrant & Fittings 25 11-Mar-09 04-Apr-09 28A29650 Fab & Del [Sorbonne]- UPVC Pipe (Sewerage) 25 11-Mar-09 04-Apr-09 0A29740 Fab & Del [Sorbonne]- GRP Pipe (Sewerage) 25 11-Mar-09 04-Apr-09 0A29760 Fab & Del [Sorbonne]- HDPE Pipe (Potable Water) 25 12-Mar-09 05-Apr-09 17A29770 Fab & Del [Sorbonne]- GRP Duct Pipe (Potable Water) 25 12-Mar-09 05-Apr-09 17A29680 Fab & Del [Sorbonne]- PE100 Pipe (Gas) 25 27-Mar-09 20-Apr-09 17A29690 Fab & Del [Sorbonne]- UPVC Duct(Telecom) 25 27-Mar-09 20-Apr-09 34A29700 Fab & Del [Sorbonne]- Valve (Gas) 25 27-Mar-09 20-Apr-09 30A29750 Fab & Del [Sorbonne]- LV Cable (Power) 25 27-Mar-09 20-Apr-09 59A29790 Fab & Del [Sorbonne]- Valve (Potable Water) 25 27-Mar-09 20-Apr-09 9A30140 Fab & Del - Temporary STP Tank 80 27-Mar-09 14-Jun-09 0

    Fabrication & Delivery For Remaining ProjectFabrication & Delivery For Remaining Project 197 11-Mar-09 23-Sep-09 111A29010 Fab & Del - Valve (Irrigation) 90 11-Mar-09 08-Jun-09 40A29020 Fab & Del - Geotextile Fabric 30 11-Mar-09 09-Apr-09 213A29030 Fab & Del - Traffic Sign 90 11-Mar-09 08-Jun-09 218A14160 Fab & Del - Fire Hydrant & Fittings 100 11-Mar-09 18-Jun-09 5A14190 Fab & Del - UPVC Pipe (Sewerage) 30 11-Mar-09 09-Apr-09 32A21750 Fab & Del - GRP Pipe (Sewerage) 28 11-Mar-09 07-Apr-09 34A28770 Fab & Del - RC Pipe (Surface Water) 60 11-Mar-09 09-May-09 93A21910 Fab & Del - HDPE Pipe (Potable Water) 60 12-Mar-09 10-May-09 22A21940 Fab & Del - GRP Duct Pipe (Potable Water) 42 12-Mar-09 22-Apr-09 40A29060 Fab & Del - GRP Duct Pipe (Surface Water) 42 12-Mar-09 22-Apr-09 110A14220 Fab & Del - HDPE Pipe (Irrigation) 60 27-Mar-09 25-May-09 47A18300 Fab & Del - PE100 Pipe (Gas) 60 27-Mar-09 25-May-09 48A18330 Fab & Del - UPVC Duct(Telecom) 30 27-Mar-09 25-Apr-09 53

    A18550 Fab & Del - Valve (Gas) 100 27-Mar-09 04-Jul-09 25A18640 Fab & Del - 22kv Cable (Power) 30 27-Mar-09 25-Apr-09 40A21790 Fab & Del - LV Cable (Power) 90 27-Mar-09 24-Jun-09 82A28330 Fab & Del - Valve (Potable Water) 100 27-Mar-09 04-Jul-09 60A29040 Fab & Del - Light Pole & Luminaries 151 26-Apr-09 23-Sep-09 0A21700 Fab & Del - LV Cable (Street Light) 90 26-May-09 23-Aug-09 22A21710 Fab & Del - Control Cabinet (Street Light) 112 26-May-09 14-Sep-09 69

    Procurement For Sorbonne Intersections/CrossingsProcurement For Sorbonne Intersections/Crossings 14 24-Feb-09 09-Mar-09 106A29500 Proc [Sorbonne] - UPVC Duct Pipe (Sewerage) 14 24-Feb-09 09-Mar-09 37

    D J F M A M J Jul A S O N D J F M2009 2010

    Fab & Del [Sorbonne]- Fire Hydrant & FittingsFab & Del [Sorbonne]- UPVC Pipe (Sewerage)Fab & Del [Sorbonne]- GRP Pipe (Sewerage)Fab & Del [Sorbonne]- HDPE Pipe (Potable Water)Fab & Del [Sorbonne]- GRP Duct Pipe (Potable Water)

    Fab & Del [Sorbonne]- PE100 Pipe (Gas)Fab & Del [Sorbonne]- UPVC Duct(Telecom)Fab & Del [Sorbonne]- Valve (Gas)Fab & Del [Sorbonne]- LV Cable (Power)Fab & Del [Sorbonne]- Valve (Potable Water)

    Fab & Del - Temporary STP Tank

    Fab & Del - Valve (Irrigation)Fab & Del - Geotextile Fabric

    Fab & Del - Traffic SignFab & Del - Fire Hydrant & Fittings

    Fab & Del - UPVC Pipe (Sewerage)Fab & Del - GRP Pipe (Sewerage)

    Fab & Del - RC Pipe (Surface Water)Fab & Del - HDPE Pipe (Potable Water)

    Fab & Del - GRP Duct Pipe (Potable Water)Fab & Del - GRP Duct Pipe (Surface Water)

    Fab & Del - HDPE Pipe (Irrigation)Fab & Del - PE100 Pipe (Gas)

    Fab & Del - UPVC Duct(Telecom)

    Fab & Del - Valve (Gas)Fab & Del - 22kv Cable (Power)

    Fab & Del - LV Cable (Power)Fab & Del - Valve (Potable Water)

    Fab & Del - Light Pole & LuminariesFab & Del - LV Cable (Street Light)

    Fab & Del - Control Cabinet (Street Light)

    Proc [Sorbonne] - UPVC Duct Pipe (Sewerage)

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 7 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A29510 Proc [Sorbonne] - GRP Duct Pipe (Potable Water) 14 24-Feb-09 09-Mar-09 48A29520 Proc [Sorbonne] - UPVC Duct Pipe (Gas) 14 24-Feb-09 09-Mar-09 76A29530 Proc [Sorbonne] - UPVC Duct Pipe (Street Lighting) 14 24-Feb-09 09-Mar-09 106A29550 Proc [Sorbonne] - GRP Duct Pipe (Irrigation Water) 14 24-Feb-09 09-Mar-09 96A29570 Proc [Sorbonne] - UPVC Duct Pipe (22kV) 14 24-Feb-09 09-Mar-09 84

    Mobilization & Temporary WorksMobilization & Temporary Works 46 03-Feb-09 20-Mar-09 60Pre-Construction WorksPre-Construction Works 46 03-Feb-09 20-Mar-09 60Site Preparation WorksSite Preparation Works 46 03-Feb-09 20-Mar-09 60A5730 Mobilization 21 03-Feb-09 23-Feb-09 60A1970 Site Clearance, Removal & Disposal of any Structures, Trees & Obstructions 10 24-Feb-09 05-Mar-09 60A1620 Grading & Grabbing Works 10 06-Mar-09 15-Mar-09 60A1650 Site Leveling Works 10 11-Mar-09 20-Mar-09 60

    ConstructionConstruction 331 27-Feb-09 23-Jan-10 0Crossings For SorbonneCrossings For Sorbonne 76 10-Mar-09 24-May-09 37Utilities in Crossing-C5Utilities in Crossing-C5 32 10-Mar-09 10-Apr-09 51Sewerage NetworkSewerage Network 11 10-Mar-09 20-Mar-09 37B6090 Excavation & Surface Preparation 3 10-Mar-09 12-Mar-09 37B6230 Pipe Laying 4 13-Mar-09 16-Mar-09 37B6290 Concrete Encasement 4 14-Mar-09 17-Mar-09 37B6240 Testing/Backfilling & Compaction 3 18-Mar-09 20-Mar-09 37

    Potable Water NetworkPotable Water Network 10 21-Mar-09 30-Mar-09 37B6580 Excavation & Surface Preparation 4 21-Mar-09 24-Mar-09 37B6590 Pipe Laying 3 25-Mar-09 27-Mar-09 37B6610 Concrete Encasement 3 26-Mar-09 28-Mar-09 37B6600 Testing/Backfilling & Compaction 2 29-Mar-09 30-Mar-09 37

    Gas NetworkGas Network 11 31-Mar-09 10-Apr-09 51B6320 Excavation & Surface Preparation 4 31-Mar-09 03-Apr-09 51B6330 Pipe Laying 3 04-Apr-09 06-Apr-09 51B6440 Concrete Encasement 3 05-Apr-09 07-Apr-09 51B6400 Testing/Backfilling & Compaction 3 08-Apr-09 10-Apr-09 51

    Utilities in Crossing-C4Utilities in Crossing-C4 62 21-Mar-09 21-May-09 40Sewerage NetworkSewerage Network 9 21-Mar-09 29-Mar-09 93B6100 Excavation & Surface Preparation 3 21-Mar-09 23-Mar-09 44B6250 Pipe Laying 3 24-Mar-09 26-Mar-09 93

    D J F M A M J Jul A S O N D J F M2009 2010

    Proc [Sorbonne] - GRP Duct Pipe (Potable Water)Proc [Sorbonne] - UPVC Duct Pipe (Gas)Proc [Sorbonne] - UPVC Duct Pipe (Street Lighting)Proc [Sorbonne] - GRP Duct Pipe (Irrigation Water)Proc [Sorbonne] - UPVC Duct Pipe (22kV)

    MobilizationSite Clearance, Removal & Disposal of any Structures, Trees & ObstructionsGrading & Grabbing WorksSite Leveling Works

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe Laying

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 8 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B6300 Concrete Encasement 3 25-Mar-09 27-Mar-09 93B6410 Testing/Backfilling & Compaction 2 28-Mar-09 29-Mar-09 93

    Potable Water NetworkPotable Water Network 12 31-Mar-09 11-Apr-09 37B6640 Excavation & Surface Preparation 4 31-Mar-09 03-Apr-09 37B6650 Pipe Laying 4 04-Apr-09 07-Apr-09 37B6740 Concrete Encasement 4 05-Apr-09 08-Apr-09 37B6660 Testing/Backfilling & Compaction 3 09-Apr-09 11-Apr-09 37

    Gas NetworkGas Network 10 12-Apr-09 21-Apr-09 50B6420 Excavation & Surface Preparation 2 12-Apr-09 13-Apr-09 50B6430 Pipe Laying 4 14-Apr-09 17-Apr-09 50B6450 Concrete Encasement 4 15-Apr-09 18-Apr-09 50B6700 Testing/Backfilling & Compaction 3 19-Apr-09 21-Apr-09 50

    Irrigation NetworkIrrigation Network 11 22-Apr-09 02-May-09 50B6670 Excavation & Surface Preparation 3 22-Apr-09 24-Apr-09 50B6680 Pipe Laying 4 25-Apr-09 28-Apr-09 50B6750 Concrete Encasement 4 26-Apr-09 29-Apr-09 50B6690 Testing/Backfilling & Compaction 3 30-Apr-09 02-May-09 50

    Street Light NetworkStreet Light Network 9 13-May-09 21-May-09 40B6710 Excavation & Surface Preparation 2 13-May-09 14-May-09 40B6720 Pipe Laying 3 15-May-09 17-May-09 40B6760 Concrete Encasement 3 16-May-09 18-May-09 40B6730 Testing/Backfilling & Compaction 3 19-May-09 21-May-09 40

    Utilities in Crossing-C3Utilities in Crossing-C3 9 12-Apr-09 20-Apr-09 71Potable Water NetworkPotable Water Network 9 12-Apr-09 20-Apr-09 71B6830 Excavation & Surface Preparation 2 12-Apr-09 13-Apr-09 37B6840 Pipe Laying 3 14-Apr-09 16-Apr-09 71

    B6880 Concrete Encasement 3 15-Apr-09 17-Apr-09 71B6850 Testing/Backfilling & Compaction 3 18-Apr-09 20-Apr-09 71

    Utilities in Crossing-C2Utilities in Crossing-C2 19 14-Apr-09 02-May-09 52Potable Water NetworkPotable Water Network 9 14-Apr-09 22-Apr-09 37A30430 Excavation & Surface Preparation 2 14-Apr-09 15-Apr-09 37A30440 Pipe Laying 3 16-Apr-09 18-Apr-09 37A30450 Concrete Encasement 3 17-Apr-09 19-Apr-09 37A30460 Testing/Backfilling & Compaction 3 20-Apr-09 22-Apr-09 37

    Gas NetworkGas Network 10 23-Apr-09 02-May-09 52

    D J F M A M J Jul A S O N D J F M2009 2010

    Concrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe Laying

    Concrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 9 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B6890 Excavation & Surface Preparation 3 23-Apr-09 25-Apr-09 52B6900 Pipe Laying 3 26-Apr-09 28-Apr-09 52B6960 Concrete Encasement 3 27-Apr-09 29-Apr-09 52B6910 Testing/Backfilling & Compaction 3 30-Apr-09 02-May-09 52

    Utilities in Crossing-B5Utilities in Crossing-B5 22 23-Apr-09 14-May-09 47Potable Water NetworkPotable Water Network 15 23-Apr-09 07-May-09 37B6770 Excavation & Surface Preparation 4 23-Apr-09 26-Apr-09 37B6780 Pipe Laying 5 27-Apr-09 01-May-09 37B6860 Concrete Encasement 5 28-Apr-09 02-May-09 37B6790 Testing/Backfilling & Compaction 5 03-May-09 07-May-09 37

    Gas NetworkGas Network 7 08-May-09 14-May-09 47B6800 Excavation & Surface Preparation 2 08-May-09 09-May-09 47B6810 Pipe Laying 2 10-May-09 11-May-09 47B6870 Concrete Encasement 2 11-May-09 12-May-09 47B6820 Testing/Backfilling & Compaction 2 13-May-09 14-May-09 47

    Utilities in Crossing-B4Utilities in Crossing-B4 17 08-May-09 24-May-09 37Potable Water NetworkPotable Water Network 17 08-May-09 24-May-09 37B6920 Excavation & Surface Preparation 6 08-May-09 13-May-09 37B6930 Pipe Laying 5 14-May-09 18-May-09 37B6950 Concrete Encasement 5 15-May-09 19-May-09 37B6940 Testing/Backfilling & Compaction 5 20-May-09 24-May-09 37

    Intersections For SorbonneIntersections For Sorbonne 79 27-Feb-09 16-May-09 45Intersection1 [H3-H2-C5]Intersection1 [H3-H2-C5] 24 27-Feb-09 22-Mar-09 75Sewerage NetworkSewerage Network 20 27-Feb-09 18-Mar-09 79B6110 Dewatering 7 27-Feb-09 05-Mar-09 83B6080 Excavation & Surface Preparation 2 10-Mar-09 11-Mar-09 79

    B6210 Pipe Laying 3 12-Mar-09 14-Mar-09 79B6310 Concrete Encasement 3 13-Mar-09 15-Mar-09 79B6220 Testing/Backfilling & Compaction 3 16-Mar-09 18-Mar-09 79

    Potable Water NetworkPotable Water Network 9 14-Mar-09 22-Mar-09 42B6550 Excavation & Surface Preparation 2 14-Mar-09 15-Mar-09 42B6560 Pipe Laying 3 16-Mar-09 18-Mar-09 42B6620 Concrete Encasement 3 17-Mar-09 19-Mar-09 42B6570 Testing/Backfilling & Compaction 3 20-Mar-09 22-Mar-09 42

    Intersection 2 [H4-H3-B5]Intersection 2 [H4-H3-B5] 9 23-Mar-09 31-Mar-09 42

    D J F M A M J Jul A S O N D J F M2009 2010

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    DewateringExcavation & Surface Preparation

    Pipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 10 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    Potable Water NetworkPotable Water Network 9 23-Mar-09 31-Mar-09 42B6370 Excavation & Surface Preparation 2 23-Mar-09 24-Mar-09 42B6380 Pipe Laying 3 25-Mar-09 27-Mar-09 42B6460 Concrete Encasement 3 26-Mar-09 28-Mar-09 42B6390 Testing/Backfilling & Compaction 3 29-Mar-09 31-Mar-09 42

    Intersection 3 [B4-B5-G3]Intersection 3 [B4-B5-G3] 9 01-Apr-09 09-Apr-09 42Potable Water NetworkPotable Water Network 9 01-Apr-09 09-Apr-09 42B5860 Excavation & Surface Preparation 2 01-Apr-09 02-Apr-09 42B5870 Pipe Laying 3 03-Apr-09 05-Apr-09 42B5890 Concrete Encasement 3 04-Apr-09 06-Apr-09 42B5880 Testing/Backfilling & Compaction 3 07-Apr-09 09-Apr-09 42

    Intersection 4 [C4-C5-G3]Intersection 4 [C4-C5-G3] 49 19-Mar-09 06-May-09 55Sewerage NetworkSewerage Network 16 19-Mar-09 03-Apr-09 79B5970 Dewatering 7 19-Mar-09 25-Mar-09 79B5960 Excavation & Surface Preparation 2 26-Mar-09 27-Mar-09 79B6190 Pipe Laying 3 28-Mar-09 30-Mar-09 79B6470 Concrete Encasement 3 29-Mar-09 31-Mar-09 79B6200 Testing/Backfilling & Compaction 3 01-Apr-09 03-Apr-09 79

    Potable Water NetworkPotable Water Network 9 10-Apr-09 18-Apr-09 42B6340 Excavation & Surface Preparation 2 10-Apr-09 11-Apr-09 42B6350 Pipe Laying 3 12-Apr-09 14-Apr-09 42B6480 Concrete Encasement 3 13-Apr-09 15-Apr-09 42B6360 Testing/Backfilling & Compaction 3 16-Apr-09 18-Apr-09 42

    Gas NetworkGas Network 9 04-Apr-09 12-Apr-09 79B6260 Excavation & Surface Preparation 2 04-Apr-09 05-Apr-09 79B6270 Pipe Laying 3 06-Apr-09 08-Apr-09 79

    B6490 Concrete Encasement 3 07-Apr-09 09-Apr-09 79B6280 Testing/Backfilling & Compaction 3 10-Apr-09 12-Apr-09 79

    22kV Network22kV Network 9 28-Apr-09 06-May-09 55B22130 Excavation & Surface Preparation 2 28-Apr-09 29-Apr-09 33B22140 Pipe Laying 3 30-Apr-09 02-May-09 33B22160 Concrete Encasement 3 01-May-09 03-May-09 55B22150 Testing/Backfilling & Compaction 3 04-May-09 06-May-09 55

    Intersection 5 [C3-C4-F3]Intersection 5 [C3-C4-F3] 14 19-Apr-09 02-May-09 45Potable Water NetworkPotable Water Network 14 19-Apr-09 02-May-09 45

    D J F M A M J Jul A S O N D J F M2009 2010

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    DewateringExcavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe Laying

    Concrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 11 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B5350 Dewatering 7 19-Apr-09 25-Apr-09 45B5270 Excavation & Surface Preparation 2 26-Apr-09 27-Apr-09 45B5280 Pipe Laying 2 28-Apr-09 29-Apr-09 45B5300 Concrete Encasement 2 29-Apr-09 30-Apr-09 45B5290 Testing/Backfilling & Compaction 2 01-May-09 02-May-09 45

    Intersection 6 [B4-F3]Intersection 6 [B4-F3] 7 03-May-09 09-May-09 45Potable Water NetworkPotable Water Network 7 03-May-09 09-May-09 45B6500 Excavation & Surface Preparation 2 03-May-09 04-May-09 45B6510 Pipe Laying 2 05-May-09 06-May-09 45B6530 Concrete Encasement 2 06-May-09 07-May-09 45B6520 Testing/Backfilling & Compaction 2 08-May-09 09-May-09 45

    Intersection 7 [C2-C3-J2]Intersection 7 [C2-C3-J2] 7 10-May-09 16-May-09 45Potable Water NetworkPotable Water Network 7 10-May-09 16-May-09 45B4690 Excavation & Surface Preparation 2 10-May-09 11-May-09 45B4700 Pipe Laying 2 12-May-09 13-May-09 45B4710 Concrete Encasement 2 13-May-09 14-May-09 45B4750 Testing/Backfilling & Compaction 2 15-May-09 16-May-09 45

    Utilities of Sorbonne RouteUtilities of Sorbonne Route 109 14-Mar-09 30-Jun-09 0Road C5Road C5 89 14-Mar-09 10-Jun-09 20Utilities WorksUtilities Works 89 14-Mar-09 10-Jun-09 20Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 89 14-Mar-09 10-Jun-09 20Sewerage NetworkSewerage Network 44 14-Mar-09 26-Apr-09 0B16830 Excavation & Surface Preparation 6 14-Mar-09 19-Mar-09 17B16850 Manhole 6 16-Mar-09 22-Mar-09 17B16840 Pipe Laying 6 05-Apr-09 11-Apr-09 0B16860 Inspection & Testing 6 06-Apr-09 12-Apr-09 0

    B16870 Backfilling & Compaction 17 07-Apr-09 26-Apr-09 0Potable Water NetworkPotable Water Network 25 27-Apr-09 21-May-09 0B16980 Excavation & Surface Preparation 7 27-Apr-09 04-May-09 0B16990 Pipe Laying 7 29-Apr-09 06-May-09 0B17000 Valve Chamber 4 05-May-09 09-May-09 0B17010 Valve Fittings 4 07-May-09 11-May-09 0B17020 Fire Hydrant 6 10-May-09 16-May-09 0B17030 Inspection & Testing 2 16-May-09 17-May-09 0B17040 Backfilling & Compaction 4 18-May-09 21-May-09 0

    D J F M A M J Jul A S O N D J F M2009 2010

    DewateringExcavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingConcrete EncasementTesting/Backfilling & Compaction

    Excavation & Surface PreparationManhole

    Pipe LayingInspection & Testing

    Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 12 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    Telecommunication NetworkTelecommunication Network 11 23-May-09 02-Jun-09 0B11620 Excavation & Surface Preparation 3 23-May-09 25-May-09 0B16880 Duct Laying 3 25-May-09 27-May-09 0B16890 Joint Box 3 27-May-09 30-May-09 0B16900 Inspection & Testing 2 30-May-09 31-May-09 0B16910 Backfilling & Compaction 3 31-May-09 02-Jun-09 0

    22kV Network22kV Network 8 03-Jun-09 10-Jun-09 20B17050 Excavation & Surface Preparation 3 03-Jun-09 06-Jun-09 0B17060 Cable Laying 3 04-Jun-09 07-Jun-09 1B17070 Inspection & Testing 2 07-Jun-09 08-Jun-09 17B17090 Backfilling & Compaction 2 09-Jun-09 10-Jun-09 17

    Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 55 21-Mar-09 14-May-09 47Sewerage NetworkSewerage Network 33 21-Mar-09 22-Apr-09 13B16950 Excavation & Surface Preparation 7 21-Mar-09 28-Mar-09 21B17260 Manhole 6 24-Mar-09 30-Mar-09 21B17080 Pipe Laying 6 05-Apr-09 11-Apr-09 11B17270 Inspection & Testing 6 06-Apr-09 12-Apr-09 11B17250 Backfilling & Compaction 14 07-Apr-09 22-Apr-09 11

    Gas NetworkGas Network 22 23-Apr-09 14-May-09 47B17100 Excavation & Surface Preparation 7 23-Apr-09 30-Apr-09 11B17110 Pipe Laying 7 26-Apr-09 03-May-09 11B17120 Valve Fittings 7 28-Apr-09 05-May-09 40B17130 Inspection & Testing 2 05-May-09 06-May-09 40B17140 Backfilling & Compaction 8 06-May-09 14-May-09 40

    Road C4Road C4 94 29-Mar-09 30-Jun-09 0Utilities WorksUtilities Works 94 29-Mar-09 30-Jun-09 0Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 57 05-May-09 30-Jun-09 0Potable Water NetworkPotable Water Network 24 05-May-09 28-May-09 9B16420 Excavation & Surface Preparation 7 05-May-09 12-May-09 7B16430 Pipe Laying 7 07-May-09 14-May-09 7B16440 Valve Chamber 5 12-May-09 17-May-09 7B16450 Valve Fittings 5 14-May-09 19-May-09 7B16460 Fire Hydrant 6 17-May-09 23-May-09 7B16470 Inspection & Testing 2 23-May-09 24-May-09 7B16480 Backfilling & Compaction 4 25-May-09 28-May-09 7

    D J F M A M J Jul A S O N D J F M2009 2010

    Excavation & Surface PreparationDuct LayingJoint BoxInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationManhole

    Pipe LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 13 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    22kV Network22kV Network 10 07-Jun-09 16-Jun-09 0B16490 Excavation & Surface Preparation 4 07-Jun-09 10-Jun-09 0B16500 Cable Laying 4 09-Jun-09 13-Jun-09 0B16510 Inspection & Testing 2 13-Jun-09 14-Jun-09 0B16530 Backfilling & Compaction 2 15-Jun-09 16-Jun-09 0

    LV NetworkLV Network 14 17-Jun-09 30-Jun-09 0B16700 Excavation & Surface Preparation 4 17-Jun-09 21-Jun-09 0B16710 Cable Laying 4 20-Jun-09 23-Jun-09 0B16720 Inspection & Testing 2 24-Jun-09 25-Jun-09 0B16740 Backfilling & Compaction 4 27-Jun-09 30-Jun-09 0

    Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 85 29-Mar-09 21-Jun-09 9Sewerage NetworkSewerage Network 33 29-Mar-09 30-Apr-09 13B16540 Excavation & Surface Preparation 8 29-Mar-09 06-Apr-09 21B16560 Manhole 8 31-Mar-09 08-Apr-09 21B16550 Pipe Laying 8 12-Apr-09 20-Apr-09 11B16570 Inspection & Testing 8 13-Apr-09 21-Apr-09 11B16580 Backfilling & Compaction 15 14-Apr-09 30-Apr-09 11

    Gas NetworkGas Network 19 02-May-09 20-May-09 13B16650 Excavation & Surface Preparation 7 02-May-09 09-May-09 11B16660 Pipe Laying 7 04-May-09 11-May-09 11B16670 Valve Fittings 5 09-May-09 13-May-09 11B16680 Inspection & Testing 2 13-May-09 14-May-09 11B16690 Backfilling & Compaction 6 14-May-09 20-May-09 11

    Telecommunication NetworkTelecommunication Network 17 26-May-09 11-Jun-09 10B16590 Excavation & Surface Preparation 7 26-May-09 02-Jun-09 7B16600 Duct Laying 7 28-May-09 04-Jun-09 7

    B16610 Joint Box 7 31-May-09 07-Jun-09 8B16620 Manhole 7 31-May-09 07-Jun-09 8B16630 Inspection & Testing 7 02-Jun-09 09-Jun-09 8B16640 Backfilling & Compaction 7 04-Jun-09 11-Jun-09 8

    22kV Network22kV Network 9 13-Jun-09 21-Jun-09 9B16770 Excavation & Surface Preparation 4 13-Jun-09 16-Jun-09 8B16780 Cable Laying 4 15-Jun-09 18-Jun-09 8B16790 Inspection & Testing 3 17-Jun-09 20-Jun-09 8

    D J F M A M J Jul A S O N D J F M2009 2010

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationManhole

    Pipe LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationDuct Laying

    Joint BoxManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & Testing

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 14 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B16810 Backfilling & Compaction 2 20-Jun-09 21-Jun-09 8Road H3Road H3 26 13-May-09 07-Jun-09 23Utilities WorksUtilities Works 26 13-May-09 07-Jun-09 23Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 26 13-May-09 07-Jun-09 23Potable Water NetworkPotable Water Network 26 13-May-09 07-Jun-09 23B18810 Excavation & Surface Preparation 7 13-May-09 20-May-09 9B18820 Pipe Laying 7 16-May-09 23-May-09 9B18830 Valve Chamber 4 21-May-09 25-May-09 20B18840 Valve Fittings 4 24-May-09 27-May-09 20B18850 Fire Hydrant 6 26-May-09 01-Jun-09 20B18860 Inspection & Testing 2 01-Jun-09 02-Jun-09 20B18870 Backfilling & Compaction 4 03-Jun-09 07-Jun-09 20

    Road B5Road B5 77 07-Apr-09 22-Jun-09 8Utilities WorksUtilities Works 77 07-Apr-09 22-Jun-09 8Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 27 21-May-09 16-Jun-09 14Potable Water NetworkPotable Water Network 27 21-May-09 16-Jun-09 14B15660 Excavation & Surface Preparation 9 21-May-09 31-May-09 9B15670 Pipe Laying 9 24-May-09 02-Jun-09 9B15680 Valve Chamber 5 31-May-09 04-Jun-09 12B15690 Valve Fittings 5 02-Jun-09 07-Jun-09 12B15700 Fire Hydrant 6 04-Jun-09 10-Jun-09 12B15710 Inspection & Testing 2 10-Jun-09 11-Jun-09 12B15720 Backfilling & Compaction 5 11-Jun-09 16-Jun-09 12

    Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 77 07-Apr-09 22-Jun-09 8Sewerage NetworkSewerage Network 29 07-Apr-09 05-May-09 36B15730 Excavation & Surface Preparation 7 07-Apr-09 14-Apr-09 34

    B15750 Manhole 7 09-Apr-09 16-Apr-09 41B15740 Pipe Laying 7 21-Apr-09 28-Apr-09 24B15760 Inspection & Testing 7 22-Apr-09 29-Apr-09 31B15770 Backfilling & Compaction 11 23-Apr-09 05-May-09 31

    Telecommunication NetworkTelecommunication Network 20 03-Jun-09 22-Jun-09 8B15780 Excavation & Surface Preparation 10 03-Jun-09 14-Jun-09 7B15790 Duct Laying 10 06-Jun-09 16-Jun-09 7B15800 Joint Box 5 13-Jun-09 17-Jun-09 7B15810 Inspection & Testing 5 15-Jun-09 20-Jun-09 7

    D J F M A M J Jul A S O N D J F M2009 2010

    Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface Preparation

    ManholePipe LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationDuct LayingJoint BoxInspection & Testing

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 15 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B15820 Backfilling & Compaction 3 20-Jun-09 22-Jun-09 7Road C3Road C3 104 14-Mar-09 25-Jun-09 5Utilities WorksUtilities Works 104 14-Mar-09 25-Jun-09 5Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 104 14-Mar-09 25-Jun-09 5Sewerage NetworkSewerage Network 36 14-Mar-09 18-Apr-09 2B15990 Excavation & Surface Preparation 4 14-Mar-09 17-Mar-09 19B16010 Manhole 4 15-Mar-09 18-Mar-09 20B16000 Pipe Laying 4 05-Apr-09 08-Apr-09 2B16020 Inspection & Testing 2 08-Apr-09 09-Apr-09 2B16030 Backfilling & Compaction 8 09-Apr-09 18-Apr-09 2

    Potable Water NetworkPotable Water Network 25 19-Apr-09 13-May-09 3B16170 Excavation & Surface Preparation 7 19-Apr-09 26-Apr-09 2B16180 Pipe Laying 7 21-Apr-09 28-Apr-09 2B16190 Valve Chamber 5 26-Apr-09 30-Apr-09 2B16200 Valve Fittings 5 28-Apr-09 03-May-09 2B16210 Fire Hydrant 6 30-Apr-09 06-May-09 2B16220 Inspection & Testing 2 06-May-09 07-May-09 2B16230 Backfilling & Compaction 5 09-May-09 13-May-09 2

    Gas NetworkGas Network 18 14-May-09 31-May-09 4B16300 Excavation & Surface Preparation 7 14-May-09 21-May-09 2B16310 Pipe Laying 7 17-May-09 24-May-09 2B16320 Valve Fittings 4 23-May-09 26-May-09 4B16330 Inspection & Testing 2 26-May-09 27-May-09 4B16340 Backfilling & Compaction 4 27-May-09 31-May-09 4

    Telecommunication NetworkTelecommunication Network 17 01-Jun-09 17-Jun-09 5B16040 Excavation & Surface Preparation 7 01-Jun-09 08-Jun-09 4

    B16050 Duct Laying 7 03-Jun-09 10-Jun-09 4B16060 Joint Box 4 08-Jun-09 11-Jun-09 6B16070 Manhole 3 10-Jun-09 13-Jun-09 4B16080 Inspection & Testing 2 14-Jun-09 15-Jun-09 4B16090 Backfilling & Compaction 3 15-Jun-09 17-Jun-09 4

    22kV Network22kV Network 8 18-Jun-09 25-Jun-09 5B16240 Excavation & Surface Preparation 2 18-Jun-09 20-Jun-09 4B16250 Cable Laying 2 21-Jun-09 22-Jun-09 4B16260 Inspection & Testing 2 23-Jun-09 24-Jun-09 4

    D J F M A M J Jul A S O N D J F M2009 2010

    Backfilling & Compaction

    Excavation & Surface PreparationManhole

    Pipe LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface Preparation

    Duct LayingJoint BoxManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & Testing

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 16 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B16280 Backfilling & Compaction 2 24-Jun-09 25-Jun-09 4Road C2Road C2 53 27-Apr-09 18-Jun-09 12Utilities WorksUtilities Works 53 27-Apr-09 18-Jun-09 12Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 53 27-Apr-09 18-Jun-09 12Potable Water NetworkPotable Water Network 27 27-Apr-09 23-May-09 28B16270 Excavation & Surface Preparation 7 27-Apr-09 04-May-09 15B16350 Pipe Laying 7 29-Apr-09 06-May-09 15B16370 Valve Chamber 5 04-May-09 09-May-09 24B16380 Valve Fittings 5 06-May-09 11-May-09 24B16390 Fire Hydrant 6 09-May-09 14-May-09 24B16400 Inspection & Testing 2 16-May-09 17-May-09 24B16360 Backfilling & Compaction 5 18-May-09 23-May-09 24

    Telecommunication NetworkTelecommunication Network 10 09-Jun-09 18-Jun-09 12B15830 Excavation & Surface Preparation 2 09-Jun-09 10-Jun-09 10B15840 Duct Laying 2 11-Jun-09 13-Jun-09 10B15850 Joint Box 2 14-Jun-09 15-Jun-09 10B15860 Inspection & Testing 2 16-Jun-09 17-Jun-09 10B15870 Backfilling & Compaction 2 17-Jun-09 18-Jun-09 10

    Road A3 Road A3 21 05-May-09 25-May-09 36Utilities WorksUtilities Works 21 05-May-09 25-May-09 36Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 21 05-May-09 25-May-09 36Potable Water NetworkPotable Water Network 21 05-May-09 25-May-09 36B16410 Excavation & Surface Preparation 4 05-May-09 09-May-09 15B16520 Pipe Laying 4 07-May-09 11-May-09 15B16730 Valve Chamber 4 10-May-09 13-May-09 31B16800 Valve Fittings 4 12-May-09 16-May-09 31

    B16920 Fire Hydrant 2 17-May-09 18-May-09 31B16930 Inspection & Testing 2 19-May-09 20-May-09 31B16940 Backfilling & Compaction 4 21-May-09 25-May-09 31

    Local RoadsLocal Roads 309 21-Mar-09 23-Jan-10 0Road 8Road 8 285 21-Mar-09 30-Dec-09 24Road 8Road 8 285 21-Mar-09 30-Dec-09 24Utility CorridorsUtility Corridors 212 21-Mar-09 18-Oct-09 91A5250 Earthworks for Utility Corridors 4 21-Mar-09 24-Mar-09 52Interlock Paving for Utility CorridorsInterlock Paving for Utility Corridors 15 04-Oct-09 18-Oct-09 91

    D J F M A M J Jul A S O N D J F M2009 2010

    Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationDuct LayingJoint BoxInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve Fittings

    Fire HydrantInspection & TestingBackfilling & Compaction

    Earthworks for Utility Corridors

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 17 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A9240 Subgarde for Interlock Paving 4 04-Oct-09 07-Oct-09 0A9270 150mm Aggregate Base Course for Interlock Paving 2 08-Oct-09 10-Oct-09 75A9280 50mm Black Sand for Interlock Paving 2 11-Oct-09 12-Oct-09 75A9290 Installing 60mm Interlocking Vehicular Pavers 3 13-Oct-09 15-Oct-09 75A9300 Sand Filler Material for Interlock Paving 2 17-Oct-09 18-Oct-09 75

    Roads Carriage CorridorRoads Carriage Corridor 266 25-Mar-09 15-Dec-09 0A9310 Earthworks 4 25-Mar-09 29-Mar-09 159A9320 Sub grade 3 04-Oct-09 06-Oct-09 1A9250 Curb Stone 11 08-Oct-09 20-Oct-09 0A9330 Geo textile Surface 2 21-Oct-09 22-Oct-09 16A9340 300mm Aggregate Base Course 2 24-Oct-09 25-Oct-09 16A9350 180mm Asphalt Base Course 2 26-Oct-09 27-Oct-09 21A9360 100mm Asphalt Wearing Course 5 10-Dec-09 15-Dec-09 0

    Utilities WorksUtilities Works 147 10-May-09 03-Oct-09 0Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 145 10-May-09 01-Oct-09 2Sewerage NetworkSewerage Network 17 10-May-09 26-May-09 15B12740 Excavation & Surface Preparation 4 10-May-09 13-May-09 13B12750 Pipe Laying 4 12-May-09 16-May-09 13B12760 Manhole 4 12-May-09 16-May-09 13B15180 Inspection & Testing 3 14-May-09 17-May-09 13B12770 Backfilling & Compaction 10 16-May-09 26-May-09 13

    Potable Water NetworkPotable Water Network 30 01-Jun-09 30-Jun-09 5B12910 Excavation & Surface Preparation 7 01-Jun-09 08-Jun-09 9B12920 Pipe Laying 7 03-Jun-09 10-Jun-09 9B12930 Valve Chamber 4 09-Jun-09 13-Jun-09 9B12940 Valve Fittings 4 11-Jun-09 15-Jun-09 9

    B12950 Fire Hydrant 6 20-Jun-09 25-Jun-09 4B15240 Inspection & Testing 2 25-Jun-09 27-Jun-09 4B12960 Backfilling & Compaction 4 27-Jun-09 30-Jun-09 4

    Gas NetworkGas Network 23 01-Jul-09 23-Jul-09 72B12870 Excavation & Surface Preparation 6 01-Jul-09 07-Jul-09 4B12880 Pipe Laying 6 08-Jul-09 14-Jul-09 4B12890 Valve Fittings 5 12-Jul-09 16-Jul-09 59B15230 Inspection & Testing 2 16-Jul-09 18-Jul-09 59

    D J F M A M J Jul A S O N D J F M2009 2010

    Subgarde for Interlock Paving150mm Aggregate Base Course for Interlock Paving50mm Black Sand for Interlock PavingInstalling 60mm Interlocking Vehicular PaversSand Filler Material for Interlock Paving

    EarthworksSub grade

    Curb StoneGeo textile Surface300mm Aggregate Base Course180mm Asphalt Base Course

    100mm Asphalt Wearing Course

    Excavation & Surface PreparationPipe LayingManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve Fittings

    Fire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve FittingsInspection & Testing

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 18 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B12900 Backfilling & Compaction 5 18-Jul-09 23-Jul-09 59Irrigation NetworkIrrigation Network 26 30-Jun-09 25-Jul-09 9B12970 Excavation & Surface Preparation 7 30-Jun-09 07-Jul-09 8B12980 Pipe Laying 7 02-Jul-09 09-Jul-09 8B12990 Valve Chamber 5 07-Jul-09 12-Jul-09 8B13000 Valve Fittings 5 09-Jul-09 14-Jul-09 8B15250 Inspection & Testing 2 15-Jul-09 16-Jul-09 8B15260 Backfilling & Compaction 6 18-Jul-09 25-Jul-09 8

    Telecommunication NetworkTelecommunication Network 12 26-Jul-09 06-Aug-09 58B12820 Excavation & Surface Preparation 3 26-Jul-09 28-Jul-09 8B12830 Duct Laying 3 28-Jul-09 30-Jul-09 8B12850 Joint Box 3 30-Jul-09 02-Aug-09 48B12840 Manhole 3 30-Jul-09 02-Aug-09 47B15220 Inspection & Testing 2 03-Aug-09 04-Aug-09 47B12860 Backfilling & Compaction 3 04-Aug-09 06-Aug-09 47

    Surface Water NetworkSurface Water Network 18 30-Jul-09 16-Aug-09 27A9370 Excavation & Surface Preparation 7 30-Jul-09 06-Aug-09 8A9380 Pipe Laying 7 02-Aug-09 09-Aug-09 8A9390 Manhole 4 08-Aug-09 11-Aug-09 23A9400 Inspection & Testing 2 11-Aug-09 12-Aug-09 23A9410 Backfilling & Compaction 4 12-Aug-09 16-Aug-09 23

    Street Light NetworkStreet Light Network 34 29-Aug-09 01-Oct-09 2B12780 Excavation & Surface Preparation 2 29-Aug-09 30-Aug-09 13B12790 Cable Laying 2 31-Aug-09 01-Sep-09 13B12800 Smart Pole Foundation 3 02-Sep-09 05-Sep-09 16B15190 Smart Pole Erection 3 24-Sep-09 27-Sep-09 1

    B15200 Inspection & Testing 2 28-Sep-09 29-Sep-09 1B12810 Backfilling & Compaction 2 30-Sep-09 01-Oct-09 1

    Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 57 08-Aug-09 03-Oct-09 0Surface Water Network (Main)Surface Water Network (Main) 13 08-Aug-09 20-Aug-09 25A9420 Excavation & Surface Preparation 5 08-Aug-09 12-Aug-09 8A9430 Pipe Laying 5 10-Aug-09 15-Aug-09 8A9440 Manhole 3 15-Aug-09 17-Aug-09 21A9450 Inspection & Testing 2 17-Aug-09 18-Aug-09 21

    D J F M A M J Jul A S O N D J F M2009 2010

    Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationDuct LayingJoint BoxManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingSmart Pole Foundation

    Smart Pole Erection

    Inspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingManholeInspection & Testing

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 19 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A9460 Backfilling & Compaction 3 18-Aug-09 20-Aug-09 2122kV Network22kV Network 9 19-Aug-09 27-Aug-09 23B15300 Excavation & Surface Preparation 2 19-Aug-09 20-Aug-09 17B15310 Cable Laying 2 22-Aug-09 23-Aug-09 18B15320 Inspection & Testing 2 24-Aug-09 25-Aug-09 19B15340 Backfilling & Compaction 2 26-Aug-09 27-Aug-09 19

    LV NetworkLV Network 14 10-Sep-09 23-Sep-09 10B12230 Excavation & Surface Preparation 3 10-Sep-09 13-Sep-09 8B12240 Cable Laying 3 13-Sep-09 15-Sep-09 8B15000 Inspection & Testing 2 16-Sep-09 17-Sep-09 8B12260 Backfilling & Compaction 3 19-Sep-09 23-Sep-09 8

    Street Light NetworkStreet Light Network 34 31-Aug-09 03-Oct-09 0B13010 Excavation & Surface Preparation 2 31-Aug-09 01-Sep-09 13B13020 Cable Laying 2 02-Sep-09 03-Sep-09 13B13030 Smart Pole Foundation 3 05-Sep-09 07-Sep-09 13B15270 Smart Pole Erection 3 24-Sep-09 27-Sep-09 0B15280 Inspection & Testing 2 28-Sep-09 29-Sep-09 0B13040 Backfilling & Compaction 3 30-Sep-09 03-Oct-09 0

    Roads Furnishing, Marking, OthersRoads Furnishing, Marking, Others 9 16-Dec-09 24-Dec-09 24A5630 Road Marking 4 16-Dec-09 20-Dec-09 20A5640 Road Furnishings 4 21-Dec-09 24-Dec-09 20

    TestingTesting 5 26-Dec-09 30-Dec-09 24A5650 Punch List 5 26-Dec-09 30-Dec-09 20

    Road 7Road 7 251 25-Mar-09 30-Nov-09 54Road 7Road 7 251 25-Mar-09 30-Nov-09 54Utility CorridorsUtility Corridors 218 25-Mar-09 28-Oct-09 81A4870 Earthworks for Utility Corridors 4 25-Mar-09 29-Mar-09 63Interlock Paving for Utility CorridorsInterlock Paving for Utility Corridors 17 12-Oct-09 28-Oct-09 81A8810 Subgarde for Interlock Paving 3 12-Oct-09 14-Oct-09 5A8840 150mm Aggregate Base Course for Interlock Paving 3 15-Oct-09 18-Oct-09 66A8850 50mm Black Sand for Interlock Paving 3 19-Oct-09 21-Oct-09 66A8860 Installing 60mm Interlocking Vehicular Pavers 3 22-Oct-09 25-Oct-09 66A8870 Sand Filler Material for Interlock Paving 3 26-Oct-09 28-Oct-09 66

    Roads Carriage CorridorRoads Carriage Corridor 229 30-Mar-09 13-Nov-09 55A8880 Earthworks 4 30-Mar-09 02-Apr-09 165

    D J F M A M J Jul A S O N D J F M2009 2010

    Backfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingSmart Pole Foundation

    Smart Pole ErectionInspection & TestingBackfilling & Compaction

    Road MarkingRoad Furnishings

    Punch List

    Earthworks for Utility Corridors

    Subgarde for Interlock Paving150mm Aggregate Base Course for Interlock Paving50mm Black Sand for Interlock PavingInstalling 60mm Interlocking Vehicular PaversSand Filler Material for Interlock Paving

    Earthworks

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 20 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A8890 Sub grade 4 12-Oct-09 15-Oct-09 4A8820 Curb Stone 7 21-Oct-09 28-Oct-09 0A8900 Geo textile Surface 2 29-Oct-09 31-Oct-09 11A8910 200mm Aggregate Base Course 3 01-Nov-09 03-Nov-09 11A8920 50mm Black Sand for Interlock Paving 3 04-Nov-09 07-Nov-09 44A8930 Installing 80mm Interlocking Vehicular Pavers 5 08-Nov-09 12-Nov-09 44A9040 Sand Filler Material for Interlock Paving 1 13-Nov-09 13-Nov-09 55

    Utilities WorksUtilities Works 154 14-May-09 14-Oct-09 42Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 141 14-May-09 01-Oct-09 14Sewerage NetworkSewerage Network 17 14-May-09 30-May-09 68B12000 Excavation & Surface Preparation 4 14-May-09 18-May-09 33B12010 Pipe Laying 4 17-May-09 20-May-09 33B12020 Manhole 4 17-May-09 20-May-09 58B14910 Inspection & Testing 3 19-May-09 21-May-09 58B12030 Backfilling & Compaction 9 20-May-09 30-May-09 58

    Telecommunication NetworkTelecommunication Network 14 29-Jul-09 11-Aug-09 11B12090 Excavation & Surface Preparation 2 29-Jul-09 30-Jul-09 8B12100 Duct Laying 2 01-Aug-09 02-Aug-09 8B12110 Joint Box 4 03-Aug-09 06-Aug-09 10B12120 Manhole 4 03-Aug-09 06-Aug-09 9B14950 Inspection & Testing 2 08-Aug-09 09-Aug-09 9B12130 Backfilling & Compaction 2 10-Aug-09 11-Aug-09 9

    Surface Water NetworkSurface Water Network 14 13-Aug-09 26-Aug-09 27A8940 Excavation & Surface Preparation 5 13-Aug-09 18-Aug-09 8A8950 Pipe Laying 5 16-Aug-09 20-Aug-09 8A8960 Inlet Chamber 4 19-Aug-09 23-Aug-09 21

    A8970 Inspection & Testing 2 23-Aug-09 24-Aug-09 21A8980 Backfilling & Compaction 3 24-Aug-09 26-Aug-09 21

    Street Light NetworkStreet Light Network 30 02-Sep-09 01-Oct-09 14B12040 Excavation & Surface Preparation 2 02-Sep-09 03-Sep-09 16B12050 Cable Laying 2 05-Sep-09 06-Sep-09 17B12060 Smart Pole Foundation 3 07-Sep-09 09-Sep-09 23B14920 Smart Pole Erection 3 24-Sep-09 27-Sep-09 12B14930 Inspection & Testing 2 28-Sep-09 29-Sep-09 12

    D J F M A M J Jul A S O N D J F M2009 2010

    Sub gradeCurb StoneGeo textile Surface200mm Aggregate Base Course50mm Black Sand for Interlock PavingInstalling 80mm Interlocking Vehicular PaversSand Filler Material for Interlock Paving

    Excavation & Surface PreparationPipe LayingManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationDuct LayingJoint BoxManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingInlet Chamber

    Inspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingSmart Pole Foundation

    Smart Pole ErectionInspection & Testing

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 21 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B12070 Backfilling & Compaction 2 30-Sep-09 01-Oct-09 12Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 128 09-Jun-09 14-Oct-09 42Potable Water NetworkPotable Water Network 23 09-Jun-09 01-Jul-09 15B12290 Excavation & Surface Preparation 6 09-Jun-09 15-Jun-09 13B12300 Pipe Laying 6 11-Jun-09 17-Jun-09 13B12310 Valve Chamber 4 16-Jun-09 20-Jun-09 13B12320 Valve Fittings 4 18-Jun-09 22-Jun-09 13B12330 Fire Hydrant 6 21-Jun-09 27-Jun-09 13B15010 Inspection & Testing 2 27-Jun-09 28-Jun-09 13B12340 Backfilling & Compaction 3 29-Jun-09 01-Jul-09 13

    Gas NetworkGas Network 29 08-Jul-09 05-Aug-09 5B12190 Excavation & Surface Preparation 8 08-Jul-09 16-Jul-09 8B12200 Pipe Laying 8 15-Jul-09 25-Jul-09 4B12210 Valve Fittings 4 26-Jul-09 29-Jul-09 4B14990 Inspection & Testing 2 30-Jul-09 01-Aug-09 4B12220 Backfilling & Compaction 4 02-Aug-09 05-Aug-09 4

    Irrigation NetworkIrrigation Network 18 06-Aug-09 23-Aug-09 4B12400 Excavation & Surface Preparation 6 06-Aug-09 12-Aug-09 4B12410 Pipe Laying 6 08-Aug-09 13-Aug-09 4B12420 Valve Chamber 3 12-Aug-09 15-Aug-09 4B12430 Valve Fittings 3 15-Aug-09 17-Aug-09 4B15030 Inspection & Testing 2 18-Aug-09 19-Aug-09 4B15040 Backfilling & Compaction 3 20-Aug-09 23-Aug-09 4

    Surface Water Network (Main)Surface Water Network (Main) 13 24-Aug-09 05-Sep-09 4A8990 Excavation & Surface Preparation 3 24-Aug-09 26-Aug-09 4A9000 Pipe Laying 3 26-Aug-09 29-Aug-09 4

    A9010 Manhole 2 30-Aug-09 31-Aug-09 4A9020 Inspection & Testing 2 01-Sep-09 02-Sep-09 4A9030 Backfilling & Compaction 2 03-Sep-09 05-Sep-09 4

    22kV Network22kV Network 12 06-Sep-09 17-Sep-09 7B12350 Excavation & Surface Preparation 3 06-Sep-09 08-Sep-09 4B12360 Cable Laying 3 09-Sep-09 12-Sep-09 4B15020 Inspection & Testing 2 13-Sep-09 14-Sep-09 4B12380 Backfilling & Compaction 3 15-Sep-09 17-Sep-09 4

    D J F M A M J Jul A S O N D J F M2009 2010

    Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe Laying

    ManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 22 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    Street Light NetworkStreet Light Network 26 19-Sep-09 14-Oct-09 42B12140 Excavation & Surface Preparation 3 19-Sep-09 23-Sep-09 4B12150 Cable Laying 3 24-Sep-09 27-Sep-09 4B12160 Smart Pole Foundation 3 28-Sep-09 30-Sep-09 4B14960 Smart Pole Erection 3 01-Oct-09 04-Oct-09 4B14980 Inspection & Testing 3 05-Oct-09 07-Oct-09 4B12180 Backfilling & Compaction 3 08-Oct-09 11-Oct-09 4B12170 Control Cabinet 3 12-Oct-09 14-Oct-09 36

    Roads Furnishing, Marking, OthersRoads Furnishing, Marking, Others 9 14-Nov-09 22-Nov-09 56A5220 Road Marking 4 14-Nov-09 17-Nov-09 45A5230 Road Furnishings 4 18-Nov-09 22-Nov-09 45

    TestingTesting 8 23-Nov-09 30-Nov-09 54A5240 Punch List 5 23-Nov-09 30-Nov-09 45

    Road 6Road 6 282 30-Mar-09 05-Jan-10 18Road 6Road 6 282 30-Mar-09 05-Jan-10 18Utility CorridorsUtility Corridors 217 30-Mar-09 01-Nov-09 77A4530 Earthworks for Utility Corridors 3 30-Mar-09 01-Apr-09 63Interlock Paving for Utility CorridorsInterlock Paving for Utility Corridors 18 15-Oct-09 01-Nov-09 77A8580 Subgarde for Interlock Paving 3 15-Oct-09 18-Oct-09 9A8610 150mm Aggregate Base Course for Interlock Paving 3 19-Oct-09 21-Oct-09 63A8620 50mm Black Sand for Interlock Paving 3 22-Oct-09 25-Oct-09 63A8630 Installing 60mm Interlocking Vehicular Pavers 3 26-Oct-09 28-Oct-09 63A8640 Sand Filler Material for Interlock Paving 3 29-Oct-09 01-Nov-09 63

    Roads Carriage CorridorRoads Carriage Corridor 262 04-Apr-09 21-Dec-09 0A8650 Earthworks 3 04-Apr-09 06-Apr-09 169A8660 Sub grade 4 17-Oct-09 20-Oct-09 7

    A8590 Curb Stone 6 29-Oct-09 04-Nov-09 0A8670 Geo textile Surface 2 05-Nov-09 07-Nov-09 8A8680 300mm Aggregate Base Course 3 08-Nov-09 10-Nov-09 8A8690 180mm Asphalt Base Course 3 11-Nov-09 14-Nov-09 9A8700 100mm Asphalt Wearing Course 5 16-Dec-09 21-Dec-09 0

    Utilities WorksUtilities Works 147 19-May-09 12-Oct-09 12Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 118 15-Jun-09 10-Oct-09 14Gas NetworkGas Network 29 15-Jun-09 13-Jul-09 42B11470 Excavation & Surface Preparation 4 15-Jun-09 18-Jun-09 35

    D J F M A M J Jul A S O N D J F M2009 2010

    Excavation & Surface PreparationCable LayingSmart Pole FoundationSmart Pole ErectionInspection & TestingBackfilling & CompactionControl Cabinet

    Road MarkingRoad Furnishings

    Punch List

    Earthworks for Utility Corridors

    Subgarde for Interlock Paving150mm Aggregate Base Course for Interlock Paving50mm Black Sand for Interlock PavingInstalling 60mm Interlocking Vehicular PaversSand Filler Material for Interlock Paving

    EarthworksSub grade

    Curb StoneGeo textile Surface300mm Aggregate Base Course180mm Asphalt Base Course

    100mm Asphalt Wearing Course

    Excavation & Surface Preparation

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 23 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B11480 Pipe Laying 4 17-Jun-09 21-Jun-09 35B11490 Valve Fittings 4 05-Jul-09 08-Jul-09 35B14650 Inspection & Testing 2 08-Jul-09 09-Jul-09 35B11500 Backfilling & Compaction 4 09-Jul-09 13-Jul-09 35

    Irrigation NetworkIrrigation Network 19 13-Aug-09 31-Aug-09 12B11510 Excavation & Surface Preparation 5 13-Aug-09 18-Aug-09 10B11520 Pipe Laying 5 16-Aug-09 20-Aug-09 10B11530 Valve Chamber 3 20-Aug-09 23-Aug-09 10B11540 Valve Fittings 3 23-Aug-09 25-Aug-09 10B14710 Inspection & Testing 2 26-Aug-09 27-Aug-09 10B14720 Backfilling & Compaction 3 29-Aug-09 31-Aug-09 10

    Surface Water NetworkSurface Water Network 12 01-Sep-09 12-Sep-09 24A8710 Excavation & Surface Preparation 3 01-Sep-09 03-Sep-09 10A8720 Pipe Laying 3 03-Sep-09 06-Sep-09 10A8730 Inlet Chamber 3 06-Sep-09 08-Sep-09 19A8740 Inspection & Testing 2 08-Sep-09 09-Sep-09 19A8750 Backfilling & Compaction 3 09-Sep-09 12-Sep-09 19

    Street Light NetworkStreet Light Network 17 24-Sep-09 10-Oct-09 14B11430 Excavation & Surface Preparation 2 24-Sep-09 26-Sep-09 11B11440 Cable Laying 2 28-Sep-09 29-Sep-09 10B11450 Smart Pole Foundation 3 30-Sep-09 03-Oct-09 12B14620 Smart Pole Erection 3 03-Oct-09 05-Oct-09 12B14630 Inspection & Testing 2 06-Oct-09 07-Oct-09 12B11460 Backfilling & Compaction 2 08-Oct-09 10-Oct-09 12

    Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 147 19-May-09 12-Oct-09 12Sewerage NetworkSewerage Network 14 19-May-09 01-Jun-09 38B11550 Excavation & Surface Preparation 3 19-May-09 21-May-09 33B11560 Pipe Laying 3 21-May-09 24-May-09 33B11570 Manhole 3 21-May-09 24-May-09 33B14730 Inspection & Testing 3 23-May-09 25-May-09 33B11580 Backfilling & Compaction 8 24-May-09 01-Jun-09 33

    Potable Water NetworkPotable Water Network 22 16-Jun-09 07-Jul-09 70B11680 Excavation & Surface Preparation 4 16-Jun-09 20-Jun-09 21B11690 Pipe Laying 4 18-Jun-09 22-Jun-09 24

    D J F M A M J Jul A S O N D J F M2009 2010

    Pipe LayingValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingInlet ChamberInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingSmart Pole FoundationSmart Pole ErectionInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingManholeInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe Laying

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 24 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    B11700 Valve Chamber 3 22-Jun-09 24-Jun-09 59B11710 Valve Fittings 3 24-Jun-09 27-Jun-09 59B11720 Fire Hydrant 6 27-Jun-09 02-Jul-09 59B14780 Inspection & Testing 2 02-Jul-09 04-Jul-09 59B11730 Backfilling & Compaction 3 05-Jul-09 07-Jul-09 59

    Surface Water NetworkSurface Water Network 11 05-Sep-09 15-Sep-09 14A8760 Excavation & Surface Preparation 3 05-Sep-09 07-Sep-09 10A8770 Pipe Laying 3 07-Sep-09 09-Sep-09 10A8780 Inlet Chamber 3 09-Sep-09 12-Sep-09 10A8790 Inspection & Testing 2 12-Sep-09 13-Sep-09 10A8800 Backfilling & Compaction 3 13-Sep-09 15-Sep-09 10

    22kV Network22kV Network 12 16-Sep-09 27-Sep-09 11B14660 Excavation & Surface Preparation 2 16-Sep-09 17-Sep-09 10B14670 Cable Laying 2 19-Sep-09 22-Sep-09 10B14680 Inspection & Testing 2 23-Sep-09 24-Sep-09 10B14700 Backfilling & Compaction 2 26-Sep-09 27-Sep-09 10

    Street Light NetworkStreet Light Network 15 28-Sep-09 12-Oct-09 12B11590 Excavation & Surface Preparation 2 28-Sep-09 29-Sep-09 10B11600 Cable Laying 2 30-Sep-09 01-Oct-09 10B11610 Smart Pole Foundation 3 03-Oct-09 05-Oct-09 10B14740 Smart Pole Erection 3 05-Oct-09 07-Oct-09 10B14750 Inspection & Testing 2 08-Oct-09 10-Oct-09 10B11630 Backfilling & Compaction 2 11-Oct-09 12-Oct-09 10

    Roads Furnishing, Marking, OthersRoads Furnishing, Marking, Others 9 22-Dec-09 30-Dec-09 18A4840 Road Marking 4 22-Dec-09 26-Dec-09 15A4850 Road Furnishings 4 27-Dec-09 30-Dec-09 15

    TestingTesting 6 31-Dec-09 05-Jan-10 18A4860 Punch List 5 31-Dec-09 05-Jan-10 15

    Road 5Road 5 285 02-Apr-09 11-Jan-10 12Road 5Road 5 285 02-Apr-09 11-Jan-10 12Utility CorridorsUtility Corridors 218 02-Apr-09 05-Nov-09 73A4190 Earthworks for Utility Corridors 4 02-Apr-09 06-Apr-09 63Interlock Paving for Utility CorridorsInterlock Paving for Utility Corridors 18 19-Oct-09 05-Nov-09 73A8350 Subgarde for Interlock Paving 4 19-Oct-09 22-Oct-09 11A8380 150mm Aggregate Base Course for Interlock Paving 3 24-Oct-09 26-Oct-09 59

    D J F M A M J Jul A S O N D J F M2009 2010

    Valve ChamberValve FittingsFire HydrantInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingInlet ChamberInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingSmart Pole FoundationSmart Pole ErectionInspection & TestingBackfilling & Compaction

    Road MarkingRoad Furnishings

    Punch List

    Earthworks for Utility Corridors

    Subgarde for Interlock Paving150mm Aggregate Base Course for Interlock Paving

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 25 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A8390 50mm Black Sand for Interlock Paving 3 27-Oct-09 29-Oct-09 59A8400 Installing 60mm Interlocking Vehicular Pavers 3 31-Oct-09 02-Nov-09 59A8410 Sand Filler Material for Interlock Paving 3 03-Nov-09 05-Nov-09 59

    Roads Carriage CorridorRoads Carriage Corridor 265 07-Apr-09 27-Dec-09 0A8420 Earthworks 4 07-Apr-09 11-Apr-09 171A8430 Sub grade 4 21-Oct-09 25-Oct-09 9A8360 Curb Stone 6 05-Nov-09 11-Nov-09 0A8440 Geo textile Surface 2 12-Nov-09 14-Nov-09 5A8450 300mm Aggregate Base Course 3 15-Nov-09 17-Nov-09 5A8460 180mm Asphalt Base Course 3 18-Nov-09 21-Nov-09 6A8470 100mm Asphalt Wearing Course 5 22-Dec-09 27-Dec-09 0

    Utilities WorksUtilities Works 145 14-May-09 05-Oct-09 51Utilities in Corridors (Right Side)Utilities in Corridors (Right Side) 108 20-Jun-09 05-Oct-09 51Gas NetworkGas Network 24 20-Jun-09 13-Jul-09 33B10800 Excavation & Surface Preparation 5 20-Jun-09 24-Jun-09 35B10810 Pipe Laying 5 22-Jun-09 27-Jun-09 35B10820 Valve Fittings 4 05-Jul-09 08-Jul-09 27B14390 Inspection & Testing 2 08-Jul-09 09-Jul-09 27B10830 Backfilling & Compaction 4 09-Jul-09 13-Jul-09 27

    Irrigation NetworkIrrigation Network 20 14-Jul-09 02-Aug-09 31B10840 Excavation & Surface Preparation 5 14-Jul-09 20-Jul-09 27B10850 Pipe Laying 5 16-Jul-09 22-Jul-09 27B10860 Valve Chamber 3 22-Jul-09 25-Jul-09 27B10870 Valve Fittings 3 25-Jul-09 27-Jul-09 27B14400 Inspection & Testing 2 28-Jul-09 29-Jul-09 27B14410 Backfilling & Compaction 3 30-Jul-09 02-Aug-09 27

    Telecommunication NetworkTelecommunication Network 13 03-Aug-09 15-Aug-09 31B10760 Excavation & Surface Preparation 2 03-Aug-09 04-Aug-09 27B10770 Duct Laying 2 05-Aug-09 06-Aug-09 27B10780 Joint Box 3 08-Aug-09 10-Aug-09 28B12080 Manhole 3 08-Aug-09 10-Aug-09 27B14380 Inspection & Testing 2 11-Aug-09 12-Aug-09 27B10790 Backfilling & Compaction 2 13-Aug-09 15-Aug-09 27

    Surface Water NetworkSurface Water Network 14 16-Aug-09 29-Aug-09 45

    D J F M A M J Jul A S O N D J F M2009 2010

    50mm Black Sand for Interlock PavingInstalling 60mm Interlocking Vehicular PaversSand Filler Material for Interlock Paving

    EarthworksSub grade

    Curb StoneGeo textile Surface300mm Aggregate Base Course180mm Asphalt Base Course

    100mm Asphalt Wearing Course

    Excavation & Surface PreparationPipe Laying

    Valve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationDuct LayingJoint BoxManholeInspection & TestingBackfilling & Compaction

    Al Reem Island Development-Sector 56-Baseline TB01[200109] Classic Schedule Layout 20-Jan-09

    Remaining Level of Effort

    Actual Work

    Remaining Work

    Critical Remaining Work

    Milestone

    Actual Level ...

    Page 26 of 43

  • Activity ID Activity Name OriginalDuration

    Start Finish TotalFloat

    A8480 Excavation & Surface Preparation 5 16-Aug-09 20-Aug-09 27A8490 Pipe Laying 5 18-Aug-09 23-Aug-09 27A8500 Inlet Chamber 4 22-Aug-09 25-Aug-09 37A8510 Inspection & Testing 2 25-Aug-09 26-Aug-09 37A8520 Backfilling & Compaction 3 26-Aug-09 29-Aug-09 37

    Street Light NetworkStreet Light Network 37 30-Aug-09 05-Oct-09 51B10720 Excavation & Surface Preparation 2 30-Aug-09 31-Aug-09 37B10730 Cable Laying 2 01-Sep-09 02-Sep-09 37B10740 Smart Pole Foundation 3 03-Sep-09 06-Sep-09 39B14350 Smart Pole Erection 3 24-Sep-09 27-Sep-09 25B14370 Inspection & Testing 2 28-Sep-09 29-Sep-09 25B10920 Backfilling & Compaction 2 30-Sep-09 01-Oct-09 25B10750 Control Cabinet 3 03-Oct-09 05-Oct-09 44

    Utilities in Corridors (Left Side)Utilities in Corridors (Left Side) 141 14-May-09 01-Oct-09 30Sewerage NetworkSewerage Network 22 14-May-09 04-Jun-09 37B10880 Excavation & Surface Preparation 5 14-May-09 19-May-09 31B10890 Pipe Laying 5 17-May-09 21-May-09 31B10900 Manhole 5 17-May-09 21-May-09 31B14420 Inspection & Testing 4 19-May-09 23-May-09 31B10910 Backfilling & Compaction 14 20-May-09 04-Jun-09 31

    Potable Water NetworkPotable Water Network 25 06-Jun-09 30-Jun-09 85B11020 Excavation & Surface Preparation 5 06-Jun-09 10-Jun-09 31B11030 Pipe Laying 5 08-Jun-09 13-Jun-09 33B11040 Valve Chamber 4 11-Jun-09 15-Jun-09 73B11050 Valve Fittings 4 14-Jun-09 17-Jun-09 73B11060 Fire Hydrant 6 20-Jun-09 25-Jun-09 70

    B14470 Inspection & Testing 2 25-Jun-09 27-Jun-09 70B11070 Backfilling & Compaction 3 28-Jun-09 30-Jun-09 70

    Surface Water NetworkSurface Water Network 12 22-Aug-09 02-Sep-09 34A8530 Excavation & Surface Preparation 4 22-Aug-09 25-Aug-09 27A8540 Pipe Laying 4 24-Aug-09 27-Aug-09 27A8550 Inlet Chamber 3 27-Aug-09 30-Aug-09 27A8560 Inspection & Testing 2 30-Aug-09 31-Aug-09 27A8570 Backfilling & Compaction 3 31-Aug-09 02-Sep-09 27

    D J F M A M J Jul A S O N D J F M2009 2010

    Excavation & Surface PreparationPipe LayingInlet ChamberInspection & TestingBackfilling & Compaction

    Excavation & Surface PreparationCable LayingSmart Pole Foundation

    Smart Pole ErectionInspection & TestingBackfilling & CompactionControl Cabinet

    Excavation & Surface PreparationPipe LayingManholeInspection & Testing

    Backfilling & Compaction

    Excavation & Surface PreparationPipe LayingValve ChamberValve FittingsFire Hy