117
METHOD STATEMENT TBM OPERATION FOR TUNNELING WORK Doc. No.: DOC/SDC/MS/019 Rev. No. : - Est. date: OCT 2015 SDC-C2 CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD METHOD STATEMENT TBM OPERATION FOR TUNNELING WORK Revision Status Rev. No. Date Description Remarks DESIGNATION TUNNEL/ PROJECT ENGINEER DEPUTY TUNNEL MANAGER/ CONSTRUCTION MANAGER TUNNEL MANAGER PROJECT MANAGER NAME SIGNATURE DATE

TBM Operation for Tunneling Work (Final).pdf

Embed Size (px)

Citation preview

Page 1: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 1 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

CONSTRUCTION OF STAMFORD DIVERSION

CANAL CONTRACT 2 – GRANGE ROAD TO

RIVER VALLEY ROAD

METHOD STATEMENT

TBM OPERATION FOR TUNNELING WORK

Revision Status

Rev. No. Date Description Remarks

DESIGNATION

TUNNEL/

PROJECT

ENGINEER

DEPUTY

TUNNEL

MANAGER/

CONSTRUCTION

MANAGER

TUNNEL

MANAGER

PROJECT

MANAGER

NAME

SIGNATURE

DATE

Page 2: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 2 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Method of Work Yes N.A. Remarks

1. Date, time and duration of works. √

2. Site Plants/Schematic Diagrams. √

3. Preparatory works. √

4. Mode of transportation. √

5. Actual work/installation/delivery. √

6. Use of special equipment/machine. √

7. Hoisting operations (including hoisting √

8. Inspection/Supervision. √

9. Temporary Traffic Diversion/Control. √

10. Liaising/Interfacing with other √

Manpower Yes N.A. Remarks

1. Organizational/Hierarchy Chart/Person-in

charge.

2. List of manpower. √

3. Evidence of Site Safety Induction Training. √

4. Evidence of Competency Training (E.g. Trade Cert., Crane Operator’s License etc.).

Health and Safety Yes N.A. Remarks

1. Hazard analysis. √

2. Preventive measures. √

3. Safe Work Procedures. √

4. Permit-to-work system. √

5. List of Personal Protective Equipment. √

6. Material Safety Data Sheet. √

7. First aid/Firefighting equipment. √

8. Tool Box Meetings. √

9. Reference to CONSTRUCTION

REGULATION

10. Public Safety √

Page 3: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 3 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Tools and Equipment Yes N.A. Remarks

1. List of approved tools/equipment. √

2. 110 volts for hand-held tools. √

3. Relevant statutory certifications (E.g. LM Cert., LG Cert., PE Cert. etc.).

Materials Yes N.A. Remarks

1. List of approved materials. √

2. Schematic diagrams. √

3. Data sheet. √

Emergency Plan Yes N.A. Remarks

1. Emergency evacuation plan. √

2. Emergency reporting procedures. √

3. List of essential personnel with contact √

4. Contingency Plan √ refer to Risk

Assessment

Page 4: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 4 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Contents

1. Overview

2. Responsibilities

3. Equipments

4. TBM Operation

A. Reference

i. MS Entrance Portal & Ring, 1st Reaction Frame, Backing Concrete

ii. MS TBM Cradle

iii. MS Gantry Crane Installation

iv. Material Submission – TBM Oil and Grease

v. Material Submission – Foam Agent

B. Temporary Work

i. Cradle

ii. Entrance

iii. Reaction Frame

iv. Temporary Segment Support

v. Muck Pit and Tipping Frame

vi. 2nd Reaction Frame

vii. Single Rail and Double Rail(Y-Switch) for TBM Operation

C. Ancillary facilities and Equipment

i. Backfill Plant

ii. Gantry Crane

iii. Substation

iv. Cooling Water Tower and Water Silo

v. Rolling Stock

1. Locomotive

2. Muck Skip

3. Segment Car

vi. Tunnel Utilities

1. Rail Sleeper

Page 5: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 5 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

2. Service Pipes and Cable Hanger

3. Backup Gantry Rail Support and Tunnel Walkway

D. Operation

i. Sequence of TBM Operation

1. Initial Driving

A. Launching the TBM

B. Umbilical Cable and Hose

C. Erection of Temporary Segment

D. Rolling Stock Operation Plan

2. Main Driving

A. Backup Gantry Setting Plan

B. Rolling Stock Operation Plan

ii. Soil Conditioning

iii. Backfill Grouting

iv. Segment Ring Building

v. Cutter Head Intervention

1. CHI on Planned Location

2. Cutter Head Entry

3. Scope of Work

A. Replacement of Cutting Tools

B. Inspection of Geological Condition

C. Re-Launching of TBM after Cutterhead Intervention

vi. TBM Operation for Control the Face Pressure

1. Face Pressure Information

2. The Measure of Shallow Overburden

A. Sink Hole

B. Blow Out

C. Heaving

3. Operation Method

A. Settlement Monitoring

B. TBM Parameter

Page 6: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 6 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

C. Emergency Response

E. Maintenance of TBM

i. Joint Plan of High Voltage Cable

ii. Extension Plan of Ventilation Duct for Tunnel

iii. Service Pipes

5. Appendices

� Appendix A CNR Lanzou Locomotive Co. Ltd. Company Profile and Supply

Track Record

� Appendix B Face Pressure North and South alignment

� Appendix C Cutterhead Intervention Location along the tunnels

� Appendix D Geological profile along the tunnels based on GIBR

� Appendix E Summary of key pressure for South and North alignment

� Appendix F Settlement based on the Surfer analysis

� Appendix G Risk Assessment

� Appendix H Safe Work Procedures

� Appendix I Sample of TBM Operation Form

TBM Operation Instruction Sheet

Cutterhead Entry

Backfill Grouting

Backfill Grout Testing Record

Inspection of Segment Ring

Ring Building Protocol

Ring Inspection Sheet

Muck skip volume record

Page 7: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 7 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

1. Overview

This method statement (MS) has been prepared to provide the methodology for

TBM operation for tunneling work along Grange Road, as part of contract 2 of Stamford

Diversion Canal (SDC).

The tunnels are to be driven approximately 1,000 meter long using Earth Pressure

Balance (EPB) shield with external diameter and internal diameters of 5.3m and 4.5m.

The TBM will be launched at launching shaft located Southwest at junction

Paterson Hill/Grange Road/Hoot Kiam Road/Irwell Bank Road. The TBM will be received

in docking box culvert at Grange Road between Orchard Blvd. and Cuscaden Road.

2. Responsibilities

2.1 Tunnel Manager

- Review of Method Statement and all the necessary permits and documents related

to construct the tunnel

- Coordination with the Project Manager and Construction Managers for all the

relevant technical details and specifications.

- Consult with SDC C2 RE’s for any discrepancies of the plan and specification, as

well as alteration of the planned sequence of work.

2.2 Deputy Tunnel Manager

- Ensure that the details on the plan and method statement are properly executed

- Liaising with the Tunnel Manager and shift engineers for the work progress and the

activities to be carried out.

- Ensure that proper personnel are executing the job.

Page 8: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 8 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

2.3 Project Manager

- Liaise with the Tunnel Manager and the Deputy Tunnel Manager regarding actual

work progress and the upcoming activities

- Determine the potential causes of delays and hindrances

- Establish the working schedule of the tunnelling work to be constructed with

respect to the baseline schedule of the total project.

- Ensure that the Work Permit System is strictly followed.

2.4 Construction Manager

- Manage equipment, material, manpower relevant to the job scope

- Performs inspection for the facilities needed to execute the work

- Assess the current working situation and determine the possible obstruction and

the potential factor to cause any delays.

2.5 Shift Engineer

- Assist the Tunnel Manager and the Deputy Tunnel Manager for preparation of

Working Schedule.

- Coordinates with the in charge person for all the necessary paperwork needed to

execute the job.

- Check the working situation in accordance with method statement specially the

elevations and chainages are followed.

2.6 Junior Engineer

- Assist the Shift engineer on monitoring of current work activities and the activities

to be done.

- Preparation of shop drawings and other associated documents.

2.7 Tunnel Foreman

- Assist the Engineers for the supervision of the work to be executed

- Co-ordinate between the Shift Engineers for tunneling work.

- Supervise the Workers in performing their designated tasks

2.8 Safety Coordinator or Safety Supervisor

Page 9: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 9 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

- Assess all the equipments and items to be used for all the authorities rules and

regulation regarding the work scope.

- Check the PPEs of all the manpower executing the job and make sure that all the

people involved are properly oriented of the nature and the hazards of the upcoming

task.

2.9 Riggerman / Signalman / Lifting Supervisor

- Ensure that all the proper coordination with their co-workers regarding the lifting

works for proper execution.

- All three of them should be present in any lifting work.

2.10 Scaffolding Supervisor

- Supervision of their respective areas of specialization

2.11 General Workers

- Facilitate welding and general works on the instruction of Supervisors, Engineers,

and Managers.

2.12 Resident Surveyors/Engineers

- Responsible for surveying the elevations and chainages before and after the

Tunneling work.

3. Equipments

Typical equipments that will required on executing the required jobs are as follows:

• 35 ton Gantry Crane, Various capacity of mobile crane

• Boom lift and lifting gear.

• Chain Block (if necessary)

• Air Compressor, Air auger drilling tool, rock drilling tool, Air hose

• Localized lights

• Various Cutting Tools(include hand breaker)

• Ventilation fan, Grout pump, mixer, Water tank, Generator set and packer

• Disposal Bin for scrap & hardcore

Page 10: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 10 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

4. TBM Operation A. Reference

i. MS Entrance Portal & Ring, 1st Reaction Frame, Backing Concrete - DOC/SDC/MS/015

ii. MS TBM Cradle

DOC/SDC/MS/017

iii. MS Gantry Crane Installation

DOC/SDC/MS/014

iv. Material Submission – TBM Oil and Grease

DOC/SDC/MAT/004

v. Material Submission – Foam Agent DOC/SDC/MAT/009

B. Temporary Work

i. Cradle Assembly of the Tunnel Boring Machines (TBMs) is generally done on the TBM cradles located

on the launch shaft before the start of the excavation work. These cradles are usually the platforms

that permit the site assembly of the TBMs where the machine will be at the start position.

The cradle for this project consists of H beams, stiffener plates, connected by bolts and fillet

welds. These steel structures are designed to withstand the heavy loads of the TBM parts during and

after assembly, this will be installed on top of the concrete base slab. Please refer to MS

DOC/SDC/MS/017 for details.

Page 11: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 11 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 1: The Cradle

Page 12: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 12 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 2: Cradle Elevation View

Figure 3: Cradle Plan View

Page 13: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 13 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 4: Cradle Front View and Details ii. Entrance

The Tunnel Entrance is designed to support the Tunnel face from possible water seepage and

collapse. The Entrance will serve as the seal of Entrance Portal to prevent ground water flow through

the gap between the shaft wall and TBM skin during the break-in on the sheet pile wall line. This will

also aid to stabilizing the proper alignment of Tunnel Boring Machine for entering the Tunnel drive.

For launch of the Grange Road to Orchard Boulevard junction, the tunnel entrance is located

adjacent to the strengthening wall and sheet pile at C2 launching shaft. Chainage for the North tunnel

Page 14: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 14 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

entrance is from CH-N-1016.62 to CH-N-1013.646 (2.97m width). The South tunnel entrance is from

CH-S-1028.2 to CH-S-1025.23 (2.97m width). Please refer to MS DOC/SDC/MS/015 for details.

Figure 5: The Completed Tunnel Entrance iii. Reaction Frame

The 1st Reaction Frame is designed to resist 16,000 kN of thrust force from Tunnel Boring

Machine during launching and initial driving stage. Reaction frame is considered as essential part of

the launch as this will aid to serve as the TBM during first stages of its advance.

The calculations for the item are provided by the Design Consultant that is engaged on

determining if the components to be used are sufficient enough to withstand the jacking force on the

thrust load induced by the TBM. Please refer to MS DOC/SDC/MS/015 for details.

Page 15: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 15 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 6: The 1st Reaction Frame iv. Temporary Segment Support

The Temporary Segment Support is designed primarily to support the TBM during the initial

stage of operation in installing segment ring.

The Structure is consists of H-beams 300x300x10x15, and steel plates connected by bolts and

nuts. This structure will be installed on each side of the Cradle.

Page 16: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 16 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 7: Temporary Segment Support Plan View

Page 17: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 17 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 8:

Page 18: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 18 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 9: v. Muck Pit and Tipping Frame

Muck pit is designed to an area suitable for collecting excavated materials during TBM

driving. Muck was removed by means of small muck car and transported to the muck pit ground

level. A muck pit of capacity 315m3 was constructed on this project beside the shaft wall at the

ground of each tunnel drive. An excavator will be used to load the excavated spoil inside the muck

pit onto dump truck for off-site disposal. However, Tipping Frame is a structure that will aid the

muck car to dispose the excavated material to the muck pit. This structure is consisting of

450x450 H-beam which is designed to hold the muck car and rotate it for disposal. The following

figures show the Plan and details of this structure and the operation procedure.

Page 19: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 19 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 10: Muck Pit Plan

Page 20: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 20 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 11: Tipping Frame with 11m3 Muck-skip

Figure 12: Plan and Details of Tipping Frame

Page 21: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 21 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 13: Tipping Frame Fabrication Drawing The following figures show the procedure during operation;

Figure 14

Page 22: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 22 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 15

Figure 16

Page 23: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 23 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 17 vi. 2nd Reaction Frame

The 2nd Reaction Frame is designed to resist 16,000 kN of thrust force from Tunnel Boring

Machine during launching and initial driving stage. Reaction frame is considered as essential part

of the launch as this will aid to serve as the TBM during first stages of its advance. As TBM

advances to the grouting area, the 2nd Reaction frame will be installed at the rear part of TBM.

This is to support the rear assembly of TBM in installing the segment ring.

2nd Reaction Frame will be installed in the following sequence of procedures:

Page 24: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 24 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

1. Installation of T1 to T7 half Segment

2. Installation of T8 to T9 Temporary Segment TBM advances as approaching the Grouting area

Figure 18

Figure 19

Page 25: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 25 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

3. Installation of 2nd Reaction Frame between T1 to T7 Before advancing to the Grouting area

4. From T10 Initial Driving to the Grouting area Will commenced.

Figure 20

Figure 21

Page 26: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 26 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

5. after the installation of P4 Segment Backfill Grouting on Grout area

6. The temporary Belt conveyor for initial driving Will be installed after the installation of P7 segment Figure 23

Figure 22

Page 27: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 27 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

7. The Rear part of 2nd Reaction Frame will then Removed from T1 to T7 and will be installed in Front

8. T8 to T13 Temporary Segment will then remove. Figure 25

Figure 24

Page 28: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 28 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

9. 2nd Reaction Frame will then installed between T1 and T6

10. 2nd Reaction Frame will then installed between T7 to T13

Figure 26

Figure 27

Page 29: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 29 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 29: The 2nd Reaction Frame

11. Installation of Locomotive Figure 28

Page 30: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 30 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 30 vii. Single Rail and Double Rail ( Y-Switch ) for TBM Operation

Single Rail and double rail with Y-switch are to be used during TBM main driving. Single Rail

will be installed after setting the back-up Gantry. Length of Y-switch should be determined first as

conformed to its design. However, the double rail approximately 100m length from tunnel

entrance up to the end of back-up Gantry.

Construction of these Single and double rail will reduce the cycle for TBM operation in

Page 31: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 31 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

transporting excavated muck.

Figure 31

Figure 32

Page 32: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 32 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 33

Figure 34: Y-Switch Rail Plan

Page 33: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 33 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 35: Elevation view of Y-Switch Rail C. Ancillary Facilities and Equipment

i. Backfill Plant

Backfill Plant is an ancillary facility for injection tail void grouting during TBM driving.

This consists of cement silo, bentonite tank, sodium silicate tank, mixer and etc. for feeding mixed

grout to Tunnel Boring Machine.

There will be electrical control panel for setting the figure of mix design. Mix design of tail void

grouting to be discussed and proposed on next section of this MS for SDC C2 project.

Figure 36 is shown the drawing of backfill plant which is to be used at SDC C2 project.

Page 34: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 34 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 36: Backfill Plant ii. Gantry Crane

Gantry Crane is main lifting equipment for TBM tunneling work. The crane is used for

disposal of excavated material, lowering the precast segment to Launching shaft, setting the TBM

backup trailers, general lifting work and etc. There will be a lot of activities.

The gantry crane for SDC C2 project is manufactured by BD Crane Tech Pte. Ltd., one of

the crane manufacturers in Singapore. The capacity is 35 ton of safe load and 60m runway on

site.

For reference, design drawing is attached as figure 37 and MS Gantry Crane Installation.

Page 35: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 35 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 37: Gantry Crane Design iii. Substation

Generally, Tunnel Boring Machine needs electric power supply for operation. 11kV high

voltage will be connected between Transformer on TBM and Substation. Also substation will be

provided low voltage as well for all electrical work on site. The detail will be provided. Please refer

to the figure 38 which is the flow chart of electric power on SDC C2 project.

Page 36: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 36 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 38: The flow chart of electric power on SDC C2 for Tunneling work.

iv. Cooling Water Tower and Water Silo

Tunnel Boring Machine is required cooling water for cooling down the temperature of

hydraulic parts and soil conditioning, grouting work. Water consumption volume (ton) will be about

9,000ton/month. Cooling water will be provided 25℃ ~ 29℃ temperature of water for tunneling

work.

v. Rolling Stock

The Rolling Stock is transportation for Tunneling work. This consists of Locomotive,

Muck skip, Segment car. The operation method on TBM initial driving or main driving will be

discussed on next section of this MS.

Page 37: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 37 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

1. Locomotive

For SDC C2 project, the locomotive is manufactured as diesel operation. The dimension is

6,800mm (L) x 1,200mm (W) x 1,850mm (H) with 750mm of rail gauge according to Tunnel

dimension and TBM backup trailers dimension. Manufacturer is SCHOMA LOKOMOTIVEN which

is one of locomotive manufacturer in Germany.

The figure 39 is shown the drawing of locomotive for SDC C2 project.

Figure 39

Page 38: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 38 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

2. Muck Skip

The purpose of Muck skip is disposal and transport excavated materials from tunnel to

surface. There are 6 nos. of muck skip which are 1 nos. of 13.5m3 muck skip for TBM initial

driving and 5 nos. of 11m3 muck skip for TBM main driving. All muck skip will be equipped spring

loaded brake system at each wheels (Called air brake system). The manufacturer is CNR

Lanzhou Locomotive Co., Ltd in China. Please refer to the company profile and supply track

record as Appendix A.

The table. 1 is shown the dimension and specification of muck skip and figure 40, 41 is

shown the drawing of muck skip which is to be used for SDC C2 project. Table. 1 : The specification of Muck skips Type Part Description 11m3 Dimension 7,000mm(L) x 1,230mm(W) x 2,100mm(H) Rail gauge 750mm Wheel base 3,500mm Wheel diameter 400mm Designed speed 25km/h Braking force 6kN per each wheel 13.5m3 Dimension 7,000mm(L) x 1,600mm(W) x 1,970mm(H) Rail gauge 750mm Wheel base 3,500mm Wheel diameter 400mm Designed speed 25km/h Braking force 6kN per each wheel

Page 39: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 39 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 40: 11m3 muck skip

Page 40: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 40 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 41: 13.5m3 muck skip 3. Segment Car

The main purpose of segment car is for transportation of the segment into Tunnel. Also it will

be used for transportation of materials, tunnel service pipes and TBM dismantling work.

Two (2) segment cars will be used for SDC C2 project. One of segment car is 15ton loading

capacity and the other is 30ton loading capacity as considered heavy load such as TBM

dismantling in the future. According to PUB (LTA) M&W specification, the segment car is equipped

spring loaded brake system at each wheel (Called air brake system). The manufacturer is CNR

Lanzhou Locomotive Co., Ltd in China as same with muck skip manufacturer. Please refer to

Page 41: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 41 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Table 2 for further specification. The figure 42 and 43 is shown the drawing of segment car which

is to be used for SDC C2 project. Table. 2 : The specification of Segment car Type Part Description

15 ton Dimension 3,756mm(L) x 1,230mm(W) x 530mm(H) Rail gauge 750mm Wheel base 2,000mm Wheel diameter 400mm Designed speed 25km/h Braking force 6kN per each wheel 3o ton Dimension 5,756mm(L) x 1,230mm(W) x 530mm(H) Rail gauge 750mm Wheel base 2,200mm Wheel diameter 400mm Designed speed 25km/h Braking force 6kN per each wheel

Page 42: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 42 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 42: 15ton Segment Car

Page 43: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 43 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 43: 30ton Segment Car vi. Tunnel Utilities

Tunnel Utilities consists of rail sleeper, hanger for various cables and pipes, tunnel walkway

and TBM backup trailer rail support. Those are supported for tunnel operation. The details are as

below.

1. Rail Sleeper

The purpose of rail sleeper is to support for Rolling stock operation which is related with

tunneling work. Rail sleeper is designed according to rail gauge distance of rolling stock, 38kg/m

rail dimension which is standard size in Singapore for SDC C2 project. Furthermore, it is all in one

type with TBM backup gantry rail support (Can be used as Tunnel walkway as well.) and hanger

Page 44: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 44 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

support of various cables and pipes. The figure 44 ~ 48 are shown the design drawings. This will

be fabricated on workshop and to be installed as 1.2m distance on invert of every segment ring.

38kg/m rail specification is attached for reference as figure 49 and 50. PE endorsement drawing

for Rail Sleeper will be submitted separately.

Figure 44: Rail Sleeper with Backup Gantry Rail Support in Tunnel.

Page 45: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 45 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 45: Rail Sleeper with Backup Gantry Rail Support Detail

Page 46: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 46 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 46: A part of Rail Sleeper with Backup Gantry Rail Support.

Figure 47: B part of Rail Sleeper with Backup Gantry Rail Support.

Page 47: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 47 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 48: Walkway and Hanger for Cables, Pipes in Tunnel.

Page 48: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 48 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 49: Dimension of 38kg/m Rail

Page 49: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 49 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Page 50: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 50 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 50: 38kg/m rail Standard Specification in Singapore. 2. Service Pipes and Cable Hanger

For Tunnel Boring Machine (TBM) operation, there are power cable, communication cable

and pipe lines. The purpose of hanger in tunnel is support for connection cables and pipes

between ancillary facilities and TBM.

The List of Service pipes and cables are mentioned below Table 3. Figure 51 is shown the

design of hanger for SDC C2.

Page 51: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 51 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Table. 3: List of Service pipes and cables in Tunnel Cable Pipe Communication Cable (Internet, Survey, etc) 1” size for Sodium Silicate (Backfill Grouting) Low Voltage Cable 2” size for Grouting (Backfill Grouting) 11kV High Voltage Cable 2” size for Bentonite (Face pressure) 2” size for Cleaning water 4” size for Compressed Air (2 Lines) 4” Cooling Water (2 Lines)(TBM operation) 4” Dewater (TBM operation)

Page 52: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 52 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 51: Hanger for cables and pipes 3. Backup Gantry Rail Support and Tunnel Walkway

TBM Backup gantries are equipped 4 set of double wheel. It is required to install the rail

support for advance with TBM. Also there is required safe walkway for workers, engineers, others

in Tunnel.

This support is designed for 2 purposes. One is support for Backup gantry rail, other is

walkway for tunnel worker after Backup gantry pass from this support.

Please refer to the figure 52 which is proposed design for SDC C2 project. PE endorsement

drawing will be submitted separately.

Page 53: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 53 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 52: Tunnel Walkway

Page 54: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 54 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

D. Operation i. Sequence of TBM Operation 1. Initial Driving

This method statement for S-975 HTM EPBM’s for Stamford Diversion Canal Contract 2

covers the safety and efficient operations and procedures that are related to the initial drive for the

two bored tunnels (North and South Bounds). Initial Drive is following completion of which will be

TBM and back-up rearrangement work. The method statement will also cover the preparation

work for Initial Drive, TBM and backup trailer setting, installation of temporary ring, TBM brake out

procedure, and EPB TBM initial drive excavation procedure, it has been written in this MS to

describe the safe working procedures as well.

A. Launching the TBM Preparation work prior for Initial Driving

The following items/activities should be ready before launching the S-975 HTM EPBM’s for

Stamford Diversion Canal Contract 2 Launching Shaft:

� Setting up of TBM cradle and TBM Reaction Frame

� Back-up Trailer installation on shaft

� Grouting Plant installation

� 35 Ton Gantry Crane installation, including testing and commission

� Tunnel Survey system and TBM Guidance System

� Temporary Ventilation fan installation

� Installation of services (piping) to TBM

� Entrance Ring and packing / flapper installed

Page 55: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 55 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

� All relevant documentation and test certificates will have been established

� All Lifting gear available and certified

� All crew are well trained for their tasks

TBM Break out

Prior to TBM break out, the following items must be prepared;

� Temporary and permanent rings, including all segment accessories.

� Grouting plant fully operational with stock of cement, bentonite, sodium silicate, stabilizer

etc, with piping connected to the TBM.

� Compressed air procedures had been finalized and understood by the tunnel team.

� All necessary training for operator had been done and the operators well trained for their

task, the operators including;

o TBM operator

o Grouting Plant operator

o Segment erector operator

o Locomotive operator

� TBM parameter for the first 100m

� TBM excavation procedure including all documentation, quality control, test certificate, etc.

� All crew had been inducted for tunneling operation.

� All lifting lugs of TBM had been removed.

� Welding stopper at TBM body to prevent TBM rolling or toppling during initial breakout.

Page 56: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 56 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

� Emergency procedures and contingency plan in place and understood by all personnel.

� Emergency equipment materials in place, such as sand nag, wood, steel beam, and water

pump, etc.

� Other necessary preparations for break out.

EPB TBM initial Drive Excavation Procedure

EPB TBM initial drive excavation procedure will follow the TBM parameter for the first

100m from Grange road (nearby T218) to River Valley Road (nearby T220). However, the TBM

parameters may change depending on the actual ground condition. Other parameters such as

jack speed, thrust force, cutter toque, jack selection etc will be instructed by the Tunnel Engineer

or Tunnel Manager.

� Face pressure and excavated soil volume will be controlled and monitored to prevent over

excavation that may result in ground movement or settlement.

� Face pressure and excavated soil volume will be controlled by the TBM operator and

monitored by the Tunnel Engineer. The TBM operator will be following the instruction

sheet prepared by the Tunnel Manager.

� Initially and until it is practicable to set up the conveyor belt system, excavated soil will be

removed from the cutter chamber thru the screw conveyor and discharged into a muck

skip. The size of the muck skip will be decreased such that at first a full skip can be pushed

to the shaft bottom only by the workers.

� The full muck skip will be transported to the shaft bottom, hoisted up using the 35-ton

Page 57: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 57 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Gantry crane or mobile crane and emptied using the tipping frame inside the mucking pit.

� Backfill grout to fill the annulus between TBM over cutting and segment extrados is

batched on the surface and pumped a storage tank at the back up trailer. From the storage

tank the backfill grout material (liquid A and B) is pumped to the grout port. Procedure for

Backfill grouting will be submitted under MS for Backfill Grouting.

� TBM guidance system will be using IRIS and checked by Tunnel Surveyor and

Tunnel Engineer. TBM alignment will be controlled by the TBM operator.

� Segment selection (type and key position) will be done by the Tunnel Engineer who will

ensure that the segment selected follows the design tunnel alignment and has enough

clearance between segment extrados and TBM tail skin. Procedure for segment ring

building show under item (iv.) Segment Ring Building of TBM Operation.

� Tail Seal Grease. When the tail seals have passed over temporary ring No.13, they will

be automatically packed with grease by the “on-board” grease pumps. The volume of tail

seal grease injected will be limited to a value as required.

� Initial Grouting sequence. Once grease has been injected and the entrance packing

had been adjusted to the extrados of the segmental lining, the TBM will be advancing for

the last section of permanent ring No.1. Grout will be injected through the tail skin.

During grouting, the grout should also come out via bleed ports also installed in the

entrance concrete. The grouting process will continue until grout is flowing out from the

pipe located at the crown of the entrance concrete pacing. The volume of the grout used

per ring will be recorded and kept in the Backfill Grout Record Sheet. Where flow is

Page 58: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 58 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

restricted or there is undue pressure build up, the grout injection point will be changed

accordingly until all voids are full. Great care will be taken to ensure that the annulus has

been completely filled. If any leaks are discovered on striking the entrance packing.

It may be deemed necessary to drill and instigate secondary grouting.

� Ground Conditioning. Initially, we will only be injecting water/foam through the

ground conditioning ports. The rate will be adjusted to maintain optimum TBM operation.

Once the machine has passed through the sheet pile area, ground conditioning will be

injected to suit conditions. Foam may be used to reduce the stickiness. In any case, as the

initial drive progresses and ground conditioning agents are in use with regularity, polymer

injection will be controlled and monitored. It is actually very difficult to predict ground

conditioning parameter in advance of the tunneling work. The dosages and types of

materials will be adjusted until they give the soil conditions that are best suited.

� After completion of the Initial drives and after track and TBM rearrangement works, it will

now be possible to bring in a full train compliment of segment trolleys, Locomotive, 11m3

Muck skips. The ventilation ducting and other back-up utilities not previously connected

will already be connected to the TBM gantries.

Page 59: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 59 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

SUMMARY SEQUENCE OF INITIAL DRIVE;

Figure 53 Sequence 1

» Once the umbilical connected into back-up car and TBM Assembly completed, the Reaction

Frame will be installed, T1 to T7 install only half segment.

Page 60: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 60 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 54:

Figure 55:

Page 61: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 61 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Sequence 2,3

» TBM Pushing stop before touched Grouting area (Install T8 & T9), Install 2nd Reaction

Frame between T1 to T7.

Sequence 4

» From T10 Start Initial Driving into Grout Area. Prior TBM shoving the 2nd Reaction Frame should be

endorsed by PE for loading capacity.

Figure 56: Sequence 4

» From T10 Start Initial Driving tinto Grout Area. Prior TBM shoving the 2nd Reaction Frame should be

endorsed by PE for loading capacity.

From T10

Page 62: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 62 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 57: Sequence 5

» From P4 segment after start Backfill Grouting into Grout area.

Page 63: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 63 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 58: Sequence 5.1

» After Erection P7 segment Install Temporary Belt Conveyor for Initial Driving.

Figure 59:

Page 64: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 64 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Sequence 6.1

» Removal 2nd Reaction Frame between T1 to T7

Figure 60 Sequence 6.2

» Removal top position segments of the ring 6 nos. of temporary rings will be removed.

Access is mainly necessary to lower down and lift up the muckskips, segments and materials.

Page 65: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 65 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 61 Sequence 6.3

» 2nd Reaction Frame Re-Install between T1 to T6

Figure 62

Page 66: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 66 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Sequence 6.4

» 2nd Reaction Frame Install between T7 to T13

Figure 63 Sequence 6.5

» Lower down Locomotive, When 2nd Reaction Frame will be installed. Prior TBM shoving the 2nd

Reaction Frame should be endorsed by PE for loading capacity. B. Umbilical Cable and Hose

• Electric Cables

A 200 m. long 11 kV trailing cable will be stored on a cable reel on the rear of the TBM back-up

gantry. As the tunneling progress the cable is fed out and hold to the right hand side wall of the tunnel

Page 67: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 67 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

at knee position with brackets.

When the TBM has progressed approximately 200 m; tunneling stops and the trailing cable is

disconnected from the cables along the tunnel isolation for high voltage switching.

A new cable is run from the previous cable to the rear of the back-up gantry. The trailing cable is

recovered, and rolled back onto the cable reel using the air motor, and the ends of the cables are

joined using couplers ready for tunneling to recommence.

The Umbilical Line Plan

Figure 64

Page 68: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 68 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Umbilical line has to be connected by prior start TBM excavation; Six (6) no’s. Cutter motor

cable should be connected each cutter motor.

Umbilical cable and hose are will be disconnect & moving position when dismantle of Temporary

Segment and Install 2nd Reaction Frame.

Lower down Locomotive and when 2nd Reaction Frame install after Umbilical line should be Re-

connection inside permanent ring.

SERVICES LAYOUT

• Intercom line : Communication lines.

• Ventilation pipe : For ventilation.

• High voltage line : Electricity supply for TBM operations.

• Low voltage line : For lighting inside tunnel.

• Spare pipe : Spare for the case Block.

• Backfill pipe A : Solution A for Backfilling (refer backfill Grouting)

• Backfill pipe B : Solution B for Backfilling (refer backfill grouting

grouting)

• Cooling Water line : TBM cooling system.

• Air supply line : Carry out the air for compressed air

• Drain water pipe : Removal of drain water

• Rail Sleeper : Support Rail for Locomotive or Rolling stocks

• Backup Gantry Support : Support Rail for moving Backup Trailers

• Pipe Rack : Hanging the Pipes

• Walkway Support : Put the walkway plate on it

• Cable Rack : All kinds Cable Hanging

Page 69: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 69 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

C. Erection of Temporary Segment

Temporary Ring Installation (Ring No.1)

Figure 65: 1. As pre decided that first key on the top (i.e. Key position K, right lead 40 look up or

overhang) place the segment on the feeder with the help of 35T Gantry crane.

2. Preparatory arrangement before ring build, weld 2 or more as per site requirement

Nos. 65x65mm square bar in TBM tail shield square bar use to give the clearance

from tail skin.

3. Mark the centre of TBM by survey team on the tail skin with respect to the thrust

frame to prevent the excessive roll of the ring.

4. Start to place the segment with help of erector correct positioning of the first plate A2,

with respect to survey centre line marked on the tail skin. It would be braced on the tail

skin with the help of four number stiffener plates 200×340x 20 and dowel bar (2 back of

the segment +2 front of the segment), stiffener numbers may be change as per the site

requirements.

Page 70: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 70 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

5. Install segment A3 adjacent to A1 with dowel bar circumferentially. For making

clearance between the segment and the tail skin would use wooden wedge.

6. In similar manner install A1 adjacent to A2.

7. Install segment C it with adjacent segment A1, support it with erector till L- bar

(200x340x 20) weld to the skin at the overhang edge.

8. In similar fashion as erected the segment A2, erect segment C it with adjacent

segment B, support it with erector till L-bar weld to the skin at the edge.

9. Check the gap between segment A2 and segment C, and then insert the key segment.

10. After completion of the ring check the bolts tightness and then cut off the stiffeners.

11. Fill the tail seal grease with manual/mechanical mechanical to the three rows of wire

brush.

12. Weld some stopper to the TBM outer shield with the cradle.

13. Before pushing of the complete ring no1 to thrust frame see all around the ring there

should not be any obstruction, then apply one jacks per segment at least (at the most

jacks) .which would just touch the front edge of the ring . Cut the stiffeners one by one.

Then apply the trust (hydraulic pressure adjustment to the lower side of pressure

would be done in consultation with HK team) slowly and uniformly to ring against to

the thrust frame.

Continue with the next ring building.

D. Rolling Stock Operation Plan

Rolling Stock is the general term covering all non powered rails mounted equipment

use in the tunnel, including muck cars, man rider, segment transport cars, material transport

flatcars, etc.

Page 71: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 71 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

The scope of this method Statement is to describe the methodology operation of the locomotive

train and Rolling stock within the tunnel and shaft. These rolling stock / locomotive are equipment for

use as transportation for all tunnel related materials aligns the bored tunnel. The Procedures are

outline to ensure the loco operations within the bored tunnel and shaft bottom are well carried out in a

safe way manner.

Figure 66

Page 72: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 72 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

2. Man Driving

Reinstall Raised Platform,

Rails

Relaunch all Rolling

Stocks, ventillation…. etc

into the Tunnels

Dismantle rails…etc &

cleaning

Cross Passage In-situ Lining (SCL)

Dismantle Shield

Machine &

Backup system

Ground

Improvement

Establishment of

Construction Plan

Casting of

1st Stage Concrete

Break Through

(Docking)

Construction of

Launching Shaft

Main Drive

Initial Drive

Design,

Fabrication

and Delivery of

Shield Machine

Erection of Back up

Facilities

above ground

Sub Station

Dismentle Temporary

Segments

and Back trussPreparation of

Main Drive

Preparation of

Initial Drive

Setting up Platform & Back

Truss

for Thrust Force

Erection of Shield Machine,

Site Testing &

Commisioning

Erection of Temporary

Segments

Page 73: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 73 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Excavation (TBM Advance)

The cutter head rotation speed and direction is set by the TBM Operator considering the

following:

• The TBM Operator selects the rotation of the cutter head as either clockwise or counter clockwise

as required for the actual roll status of the machine;

• The cutter head speed is increased from zero using the control knob and is adjusted if required,

dependant on ground conditions and cutter head torque. Generally speed between 1.0 and 2.5

revolutions per minute (rpm) will be used in soft ground and maximum speed (4.3 rpm) will be used

in rock conditions and slow speed in mix face;

• To change the head direction once started, the cutter head will first be stopped.

• The thrust rams are powered in four groups and in order to activate the thrust rams: Each group can

be driven at different pressures to facilitate steering without overloading the segmental lining;

• Steering can be achieved by applying greater pressure on particular group of thrust rams; and

• Each full stroke is nominally 1200 mm. however the rams will be extended in the range 600 - 1800

mm. to allow the key to be installed for the 1200 mm.

• Face pressure and excavated soil volume will be controlled and monitored by Tunnel Engineer.

TBM Operator will follow the “TBM Operation Instruction Sheet given by Tunnel Engineer;

• The calculation of “Face Pressure” will submit separately. However, face pressure applied may differ

depend on the actual ground condition, which is decided by Tunnel Manager; and

• Excavated soil volume will be controlled and compared to the theoretical soil volume and statistical

mean of excavated soil volume.

• The TBM Operator will advance the TBM within the guidelines of the “TBM Operation Instruction

Sheet for maximum advance rate, thrust, and contact force and machine torque. It is important for

settlement control that the TBM advance rate does not exceed the backfill grouting rate.

• As the stroke proceeds the TBM Operator will monitor the discharged estimated excavation volume

Page 74: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 74 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

from bulk scanner or muck skip counting, face pressure, the grout intake, grout pressure and the

actual and predicted positions are calculated using the IRIS and details provided on the monitor in

the Operator‘s cabin.

• Once the TBM has completed the advance and with the thrust cylinder pumps still running, the

advance and cutter head rotation is stopped and control passed over to the Erector Operator.

• The displaceable main drive allows accurate loading on the cutter head and face to be determined

(contact force). If the cutter head strikes an obstruction, the main bearing is protected by hydraulic

interlocks. A face inspection would be carried out in the event of an obstruction being encountered.

A. Backup Gantry Setting Plan

Backup Gantry Setting plan is the safety and efficient operations and procedures that are related

to the Main drive for the two bored tunnels (North and South Bounds).

Initial Drive is following setting Backup Gantry near the cut & cover tunnel and surface of available

area. When S-975 HTM EPBM’s TBM machine reaches approximately 96m which will be TBM and

back-up need to rearrangement work from entrance to Cutter Head. Approximately 96m all of Backup

Gantry (6 no’s) can set tunnel inside.

The method statement will also cover the preparation work for Main Drive Backup trailer setting.

The main worksite and staging area for the tunneling back-up facilities on the ground will be

located near the cut and cover tunnel, utilizing the area to set-up equipment/machineries, plants, and

staging areas for the tunneling works as here under described as follows;

Figure 67

Page 75: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 75 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 68

Figure 69

Page 76: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 76 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 70 B. Rolling Stock Operation Plan

Rolling Stock is the general term covering all non powered rails mounted equipment use in the

tunnel, including muck cars, man rider, segment transport cars, material transport flatcars, etc.

The scope of this method Statement is to describe the methodology operation of the locomotive

train and Rolling stock within the tunnel and shaft. These rolling stock / locomotive are equipment for

use as transportation for all tunnel related materials aligns the bored tunnel. The Procedures are

outline to ensure the loco operations within the bored tunnel and shaft bottom are well carried out in a

safe way manner.

Page 77: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 77 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 71 ii. Soil Conditioning

The soil conditioning agent will be injected to cutter face, excavation chamber and screw

conveyor as well. The injection rate will be controlled subject to ground condition in order to stabilize

the face pressure and to improve the fluidity and water tightness. In order to maintain a stable

chamber pressure, excavated material should be a homogenous mix of coarse and fine particles,

improving overall plasticity of the material. Required physical properties of an excavated material are

achieved through conditioning it with foam, polymer, bentonite or simply water, creating a paste like

consistency. Proportions of foam constituents are selected depending on actual type and gradation of

excavated material as well as expected ground pressure. Additional benefits of ground conditioning

include reduced water permeability of conditioned ground as well as reduced stickiness and clogging

of the materials, facilitating efficient mining. Appendix B shows the Face pressure for North and South

alignment. During mining the following should be monitored and adjustments made as required.

• TBM parameters; i.e. Face pressure, thrust speed, cutter torque and thrust force

• TBM position

• Excavated material flow and condition

• Volume of excavated materials

• Grout pressure and volume

Page 78: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 78 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

• Overall TBM Behaviour

Soil condition Foam agent (MAK Foam)

: Please refer the Material Submission ~ DOC/SDC/MAT/009

iii. Backfill Grouting

Generally, Backfill Grouting is main activity for TBM tunneling work. Basic principle of TBM

tunneling work is shown the drawing as figure ( 72 ).

Figure 72 As shown figure 72 , Backfill grout will be injected through grouting injection port in TBM tail skin.

The purpose of backfill grouting is filling the gap between TBM O.D (ø5, 290mm) and Segment O.D

(ø5, 000mm).

Page 79: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 79 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

For getting sufficient strength of grout, high quality of grout materials are to be used for SDC C2

project and compressive strength test will be carried out on site once a day.

Material submission of grout materials will be submitted after trial mix under PUB/CPG

supervision.

The requirement for backfill grout mix is as follows.

Bleeding <5%

Gel Time(After mixing with accelerator 4~15 sec

Before the next shove commence >50kPa as M&W Specification 16.2.13

29 days compressive strength >2MPa as M&W Specification 16.2.13

The proposal mix design for grout material is shown as figure Table 4. Test report will be submitted

separately.

Table 4: Mix Design for Backfill Grout.

Page 80: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 80 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

The minimum, maximum and Grouting pressure will be submitted on TBM instruction sheet by

Tunnel Manager.

iv. Segment Ring Building

One complete ring consisting of six (6) number segments is transported to the TBM by the train,

stacked in pairs on segment car. Hydraulic lifting arms on the segment handler will lift the segments

from the segment car in pairs and position on the segment handler. The vacuum pad crane will then

be used to lift the top segment in each pair and arrange them individually in the segment handling

area. The segments can be selected in any order required for the ring build sequence.

The segments will be delivered and stacking should be in manner as shown in Figure 73.

Figure 73

Page 81: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 81 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

a) The temporary will be lowered down to the launch shaft by using 35-ton gantry crane or mobile

crane and proprietary lifting device. The segment will then be transported to the segment feeder

device. Refer to figure (74 and 75).

b) The reaction frame will be marked with the correct internal and external diameter of the ring. By

using wedges and jacks in addition to the roundness retainer, the correct shape and level of the

rings can be ensured. Once in position, angle bar or other proprietary steel section will be welded

to shove frame to keep the ring in position. Holes may be burnt in the shove frame in positions

that tally with the bolt pockets of the segments. Bolts can then be used to secure the ring. This will

be confirmed at site if appropriate or not.

c) Tail seal grease will be applied manually at the TBM tail seal brush.

d) A total 13 no’s of temporary rings will be installed for each of Bounds tunnels.

e) For the temporary rings, segment that has minor non-conformances will be used; these segments

are able to be used for TBM launching purpose – i.e. the segments are structurally sound. They

may or may not be coated. Gasket or packing will not be installed for temporary rings.

f) For the permanent rings, only accepted segments will be used complete with coating, EDPM

gasket and packing; these segments prior to use should have been checked and accepted.

g) The temporary rings will be lowered down to the shaft onto a segment car by using the 35 ton

gantry crane or mobile crane and certified lifting device. The segments are unloading to the

segment feeder where it available and brought into the segment erection area. The ring will be

installed inside the TBM by using the TBM erector.

h) The ring level and roll will be checked; and during erection, the segment will be secured to

prevent rolling and other movement. The segment will be drilled into the joint of the 2 segment

into steel plate to prevent moving when retracting the rams.

i) Once ring erection is completed, the ring will be pushed slowly toward the reaction frame by thrust

Page 82: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 82 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

jacks. C-channels will be welded at the reaction frame as support and guide during pushing the

segment to the reaction frame.

j) Once the ring is in position, wire rope with turnbuckle will be put around the segment extrados to

secure its shape during TBM excavation. TBM turnbuckle will be used remove any slack in the

wire rope.

k) The process will be repeated until all temporary rings are constructed. During each shove for ring

outside the ground, Tunnel Supervisor / Engineer will observe the ring condition, support, TBM

position and attitude with respect to tunnel eye opening; TBM will be closely monitored especially

when the tail skin passes beyond the end of cradle.

l) Every temporary ring will be checked as to the level and chainage to ensure the correct

positioning of the first permanent ring.

The following figures show the sequence of Ring Building:

Figure 74

Initial Driving Main Driving

Page 83: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 83 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 75 Figure 76 1. The 1st Ring segment Installation The segment will be transported by segment car.

Initial Driving Main Driving

Page 84: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 84 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 77 Figure 78 Figure 79

2. The 1st Ring segment Installation The segment will lift using dowel pin.

3. The 1st Ring segment Installation The segment will be set to its position

4. The 1st Ring segment Installation The dowel pin will be inserted to the dowel socket.

Page 85: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 85 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 80

Figure 81 Figure 82

5. The 2nd Ring segment Installation The dowel pin will served as the connection of each segment 6. The 2nd Ring segment Installation The segment will be pushed by Thrust jack to connect and tightened. 7. The cycle of installation will continue by inserting dowel pin into dowel socket for the next segment ring

Page 86: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 86 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 83

Figure 84

Figure 85: The Completed Ring Segment

Page 87: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 87 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

v. Cutter Head Intervention

1. CHI on Planned Location

The Stamford Diversion Canal Contract 2 has two alignments, the North and South alignment.

The Tunnels are to be driven approximately 1,000 m long using Earth Pressure Balance (EPB) shield

with external diameter and internal diameters of 5.3m and 4.5m. Cutter head interventions will be

planned in advance whenever possible to ensure that the cutter head is located in stable ground

conditions in order to enable the entry of personnel. Planned interventions are generally intended for

inspections of the cutter head prior to tunneling beneath critical structures such as roads and

buildings along the route to see the actual ground condition as well as through difficult ground

conditions; planned replacement of cutting tools, or for removal of obstruction inside the cutter head

chamber.

The cutter head / cutting wheel are part of the TBM. Inspecting the cutter head / cutting wheel

and its excavation tools is therefore necessary to prevent major damage on the cutter head / cutter

wheel. Appendix C shows the Planned Cutterhead Interventions.

Table 5 : Planned Interventions for the South Alignment drive No. Chainage (m) Nearest borehole Distance from nearest building (m) Pressure, half face (bar) Pressure, full face (bar) Comments 1 105.0 BH4-2d 23 0.75 1.00 2 284.5 BH4-2a 35 0.96 1.21 Access shaft 2 3 425 BH4-3g 27 0.84 1.09 4 556 NBH-12 24 0.83 1.08 Maintenance shaft 5 720 BH4-3a 11 0.57 0.82 6 872 NBH-6 53 0.48 0.73 Access shaft 4

Page 88: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 88 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Table 6 : Planned Interventions for the North Alignment drive No. Chainage (m) Nearest borehole Distance from nearest building (m) Pressure, half face (bar) Pressure, full face (bar) Comments 1 90.0 BH4-2d 15.8 0.73 0.98 2 228.5 NBH-16 12.5 1.04 1.29 Access shaft 1 3 375 BH4-2c 15 0.86 1.1 4 471 NBH-13 15.5 0.81 1.06 5 591.4 NBH-11 11 0.82 1.07 Maintenance shaft 6 690.0 BH4-3a 14 0.59 0.84 7 815 NBH-7 47 0.51 0.76 Access shaft 3 2. Cutter Head Entry

In the event where TBM advancement is becoming unexpectedly difficult such as cutter head

torque increase/decrease or thrust force increase with low advance and penetration rates, and if the

wear detectors mounted on the cutter head indicate that the cutting tools are worn down, the

unplanned Intervention are required. TBM may encounter obstructions such as construction waste,

boulders or piles, etc. The Unplanned Intervention will be required a Cutter Head Entry permit to be

accomplished by the project concerned personnel.

3. Scope of Work

There are possibilities that man-made obstructions could be encountered during tunneling fill

material. These obstructions may include construction waste, abandoned road pavement layer and

shallow foundations. The obstruction may become trapped on the cutter head or damage to cutter

head. Removing the obstructions or change the cutting tools covers the scope of work of Cutter head

Intervention.

Page 89: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 89 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

A. Replacement of Cutting Tools

During TBM operation, the cutting tools of TBM Cutter head will be monitored as to different

circumstances. Replacement of cutting tools may be necessary when the wear detectors mounted on

the cutter head indicates that the cutting tools need to be replaced. The TBM will be stopping on the

stoppage location defined in Cutter head Intervention Plan or as the case may be to Unplanned

Intervention. The ground condition will be checked by competent person before the replacement of

cutting tools.

B. Inspection of Geological Condition

Anticipated ground conditions for tunneling have been assessed based on the GIBR. The

tunneling will be encountering the weathered granite G(VI). Mixed soil conditions, consisting of a

mixed face of the G(VI) and fill layer are anticipated locally on all drives.

Table 7 : General ground conditions anticipated along the route of the SDC tunnel, North Alignment,

based on the GIBR. Chainge from (m) Chainage to (m) Anticipated Ground Conditions at Tunnel Face N-0 N-50 G(VI)<0.5D cover to Fill layer N-50 N-160 0.5D<G(VI)<1D cover to Fill layer N-160 N-330 G(VI)>1D cover to Fill layer N-330 N-710 0.5D<G(VI)<1D cover to Fill layer N-710 N-1018 G(VI)<0.5D cover to Fill layer Table 8 : General ground conditions anticipated along the route of the SDC tunnel, South Alignment,

based on the GIBR.

Page 90: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 90 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Chainge from (m) Chainage to (m) Anticipated Ground Conditions at Tunnel Face S-0 S-50 G(VI)<0.5D cover to Fill layer S-50 S-160 0.5D<G(VI)<1D cover to Fill layer S-160 S-340 G(VI)>1D cover to Fill layer S-340 S-730 0.5D<G(VI)<1D cover to Fill layer S-730 S-1029 G(VI)<0.5D cover to Fill layer A variable thickness of fill soils is shown above the tunnel in the GIBR. According to the tables,

the G(VI) that is just over the tunnel crown or could be present over the face locally is shown in some

areas of Chainage 600, 700, and 900. Those chainages are represented by borehole BH4-3c, BH4-3d,

and BH4-3e for chainage 600, 770, and 900, respectively. However, site investigation report of BH4-

3e provides>3m cover of G(VI) over the tunnel crown that is different with what is shown on the soil

profile drawings. The long section of GIBR soil profile is attached in Appendix D.

C. Re – launching the TBM after cutter head intervention

Once the Cutter head Intervention work has completed, TBM will be advancing slowly and fill-up

soil in the chamber and the air will be discharged slowly for balancing the face pressure.

vi. TBM Operation for Control the Face Pressure

Controlling the face pressures to the limits will depend on the skill of the operator and the

effectiveness with which the soil conditioning is adjusted to suit the varying conditions along the

alignment.

1. Face Pressure Information

The ground losses can be controlled by applying the sufficient face pressure, injection of the

thick bentonite slurry using system installed on the TBM, simultaneous tail void grouting suing the

system installed on the TBM. With the use of the slurry injection system and good control of tail void

grouting the volume of the ground loss can be reduced significantly. The value of the volume loss also

depends on the workmanship. Appendix E and Appendix F shows the summary of Face Pressure

Page 91: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 91 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

information.

2. The measure of Shallow Overburden

The recommended face pressure for the residual soil of Bukit Timah Granite is 0.4 to 0.6 of the

total overburden pressure. It could be reduce to free air when undrained shear strength is reach to

100 kPa at the depth of the 20m below ground surface. This face pressure is only for the case of the

full face of the residual soil of Bukit Timah Granite.

A. Sink Hole

Sink Hole occurs when the excavated volume of soil is bigger than the calculated design

volume. This occurs in unstable ground condition such as sand, gravel, sandy soil of low viscous force.

Figure 86

Page 92: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 92 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

The Flow Chart illustrates that during Tunnel operation, the TBM operator must carefully followed the

TBM instruction sheet. The parameters that should be checked are the following:

1. Torque

2. R.P.M.

3. Trust Jack Force

4. Thrust Speed

5. Face Pressure

Excavated Muck volume must be monitored, in the event that the muck volume is bigger than

the calculated volume the TBM operator must inform the Engineer and watchman to check the

surface condition to prepare for necessary safety procedures if possible Sinkhole is found.

TBM Drive Maintenance Face Pressure Continue Drive Finish Drive Segment Erection Preparation TBM Drive

TBM Operator must follow TBM Operation Instruction Sheet • Torque • R.P.M. • Thrust Force • Thrust Speed

1. If excavated Muck volume is bigger inform the Engineer in charge 2. If possible Sinkhole is found: • Inform TBM operator • Inform Tunnel Manager 1. If excavated Muck volume is bigger inform the Engineer in charge 2. If possible Sinkhole is found: • Inform TBM operator • Inform Tunnel Manager

Page 93: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 93 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

B. Blow out

Blow out occurs when the pressure at the crown exceeds the total overburden pressure, the

ground may rapture leading to a blow out of the compressed air. This causes a severe risk to the

safety of those working in the compressed air and to the public at the surface. For this project the

residual soil and fill material will be encountered with same permeability at the face and above the

tunnel crown the risk of heave due to compressed air is impossible. However, the risk of the pressure

blow-out for both semi and open modes are investigated. The factor of safety against blow-out was

checked for the case where the excavation chamber is emptied to invert level. The factor of safety is

less than 1.2 for the chainages below. Therefore full emptied of the chamber is not recommended and

the cutterhead intervention should be performed in the semi-EPB mode.

Table 9 : The locations where the full face intervention is not recommended Tunnel North Bound From N-10.0 to N-30.0; and From N-730.0 to N-990.0 South Bound From S-10.0 to S-30.0; and From S-800.0 to S-980.0

Figure 87

Page 94: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 94 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

• Torque should be maintained in any geological condition.

• R.P.M. should be maintained for each ground condition, when approaching weak

ground R.P.M. is 1-1.5.

• Initial & Main Driving R.P.M. is 1-3.5.

• If R.P.M. is increases or decreases, ground relaxation should increased.

• R.P.M. must be checked for each ground condition.

• Thrust jack force should be control to maintain Face pressure.

Page 95: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 95 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

• Thrust force can be increased, in case of high Torque.

• Thrust speed should be increased, when Thrust force is high.

• Face Pressure should be inspected when decreases gradually C. Heaving

The pressure required to cause unacceptable ground heave is effectively the pressure required

to lift the overburden block of ground. This pressure is equal to the in-situ stress at the tunnel level

plus a value based on the strength of the ground loss. If the maximum face pressure is kept at or

below the total vertical overburden pressure, there should be no risk of excessive heave in ground

surface during construction of the tunnel.

For the below locations the minimum grout pressure to ensure effective grouting was greater

than the pressure required to heave the ground surface. To avoid the excessive heave, the maximum

grout pressure was reduced to 85% of the total overburden plus the pressure needed to overcome the

shear strength of the ground considering a factor of safety of 1.2. Table 10 : Chainage of shallow depth tunnels with risk of excessive heave due to high grout pressure Tunnel Chainage North Bound From N-10.0 to N-160.0; and From N-340.0 to N-1008.0 South Bound From S-10.0 to S-160.0; and From S-350.0 to S-1019.0

Page 96: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 96 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Figure 88

Page 97: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 97 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

• Torque should be maintained in any geological condition.

• R.P.M. should be maintained for each ground condition. When approaching weak ground,

docking R.P.M. should only at 1-1.5.

• Initial and Main Driving R.P.M. 1-3.5.

• Thrust force should be maintained for Face Pressure.

• Thrust force can be increased, in case of high Torque.

Page 98: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 98 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

• Thrust speed can be decreased when Torque reaches high.

• Face Pressure should be inspected when gradually increases. 3. Operation Method

The operation methods are preliminary based on existing soil investigation. The Operation

method includes the following: Part Description Target Face Pressure All the time Controlling TBM advance rate, B/F Grouting Monitoring (24 Hrs.) TBM Parameter, Surface Visual check Muck Condition, Volume 2nd Grouting Immediately (After pass through) Proper usage for soil condition Foam, Polymer, Bentonite A. Settlement Monitoring

The target volume loss figures of calculations are shown in Table below: Tunnel Chainage Volume Losss From To North Alignment 0+000 1+018 0.7% South Alignment 0+000 1+029 0.7% These target volume loss figures have been used as a basis for the rate and grouting pressure

calculations. However, these calculations are for short term settlement when tunneling EPB mode only.

There are number of potential causes of settlement which are not directly related to the face pressure

used and which therefore cannot be directly controlled with the face pressure. These include:

1. Consolidation settlement due to dissipation of excess pore pressures generated during tunneling,

leakage into the tunnel or bleeding of the tail void grout.

Page 99: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 99 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

2. Settlement associated with interventions.

3. Settlement due to boulders, pieces of rock or other obstructions being trapped in or rolled around

the cutter head, and causing damage to the ground in and above the face of the tunnel.

4. The construction of the cross-passage, maintenance shaft, and access shaft.

Settlements due to these causes are excluded from the calculated target volume loss, and will

be additive to the volume loss. While these potential sources of additional settlement are not directly

related to the face pressure used, in most case (excluding leakage into the tunnel and bleeding of the

grout) the use of the calculated target face pressure will help to minimize the risk of and/ or magnitude

of settlement due to these potential additional sources. Appendix G shows the Settlement based on

Surfer analysis.

B. TBM Parameter

The parameters that must be observed for TBM operation are the following:

• Torque

• R.P.M.

• Thrust Jack Force

• Thrust Speed

C. Emergency Response

In the event that it is necessary to contact Emergency Services to report on emergency, the

person is to follow the instructions on the Emergency Reporting Instructions. These instructions are to

be posted at the surface and tunnels.

All accidents/incidents are to be reported to the Project Manager of TS and LTA.

Page 100: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 100 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

• The internal telephone network provides the primary means of communication in an

emergency.

• Telephones are maintained at the surface and tunnel underground.

• Emergency response from underground is achieved by the provision of emergency lines

direct to telephones in the main office area.

• A person appointed as a Tunnel Safety Supervisor will be in attendance on the tunnel at all

times.

Page 101: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 101 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Page 102: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 102 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Page 103: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 103 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

E. Maintenance of TBM

i. Joint Plan of High Voltage Cable

A 200 m. long 11 kV trailing cable will be stored on a cable reel on the rear of the TBM back-up

gantry. As the tunneling progress the cable is fed out and hold to the right hand side wall of the tunnel

at knee position with brackets. When the TBM has progressed approximately 200 m, tunneling stops

and the trailing cable is disconnected from the cables along the tunnel, isolation for high voltage

switching and a new cable is run from the previous cable to the rear of the back-up gantry.

The trailing cable is recovered, and rolled back onto the cable reel using the air motor, and

the ends of the cables are joined using couplers ready for tunneling to recommence.

ii. Extension Plan of Ventilation Duct for Tunnel

While excavation is stopped during the ring build cycle or even Excavation time. It is possible

to extend exchange the ventilation duct canister. All materials and equipment is stored on the TBM

backup gantry, having been transported to the TBM on flat car pushed by locomotive. Typically

delivered and installed during maintenance shift.

For ventilation within tunnel, forced-air supply method will be used; that provides fresh air into

tunnel with ventilation pump installed on the ground above the vertical pit (launch Shaft).

It shall be noted that the below computations and analyses for the ventilation system shown

hereunder are for sample computation for one tunnel only.

Page 104: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 104 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

A) Installed FAN Specification

Flux Q = 200m3/min

Wind Pressure p = 200mmAq

Model : Blower Type, TFB-22M, 3550rpm, 44KW

Operation Type : Both automatic and manual

Duct in tunnel : 1 row of Ventilation tube (Φ1000mm)

B) Calculation of Necessary Volume of Ventilation

Necessary Volume of Ventilation per 1 worker in tunnel = 3 m3/min

Q = 15 * 3m3/min = 45 m3/min

In-addition, the usage of diesel locomotive will require an additional air circulation of another 25%

of the normal ventilation requirement.

i.e; the flow rate required = 45 x 1.25

= 56.25 m3 / min

Page 105: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 105 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

But the effect of diesel locomotive won’t be disturbing the workers at the TBM, as the air

circulation will be as shown below and locomotive will be working at the rear part of the backup

system; refer to below sketch.

Since the locomotive will be located at the rear part of the backup system throughout the

operation, the outward flow of air will remove the effect of smoke away from the working area at the

TBM.

Figure 89

Calculation of Necessary Wind Volume of Fan

m = β * (L/100) m : Wind Loss Ratio,

β : Wind Loss Coefficient=0.015,

L : Duct Length=1000m

Qf : Necessary Wind Volume of Fan,

Q : Necessary Volume of Ventilation =45 m3/min)

m = 0.015 * (1100/100)

= 0.165

Page 106: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 106 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Qf = Q/(1-m)

= 45 m3/min ÷ (1-0.165)

= 53.89 m3/min

Calculation of Necessary Wind Pressure of Fan

ν : Wind Velocity in Tunnel m/sec

Q : Necessary Volume of Ventilation =45 m3/min

r : Duct Radius=0.5m,

h : Loss due to Duct Pressure =mmAg

λ : Duct Friction Coefficient=0.025,

L : Duct Length=1100m

γ : Air Gravity=1.2kg/m3

g : Acceleration of Gravity=9.8m/sec²

hf : Necessary Wind Pressure of Fan mmAg

m : Wind Loss Ratio =0.294 ν = Q / (15 * π * r²)

= 45/ (15 * π *0.5²)

= 3.82 m/sec

Page 107: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 107 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

h = (λ * L * ν² * γ) / (r * g)

= (0.025 * 1100 * 3.82² * 1.2) / (0.5*9.8)

= 98.28 mmAg

hf = h/(1-m) = 98.28/(1 - 0.165)

= 105.11 mmAq

∴ 200mmAq > 105.11 mmAq - - - - - O.K

Ventilation System Details

However, there should be some emergency ventilation during man to access the front of the

shield machine; the ventilation system used will be the same as for the temporary shaft:

a) Multi-gas detection meters will be installed at intervals.

b) Oxygen mask & cylinder harness – will be kept in adequate numbers as stand -by for

emergency rescue.

c) Ventilator blower (compressor or motor) located topside as shown in Figure 90.

d) Ventilating blow tubes – canvas/plastic foldable circular tubes of about 800mm diameter. It is

connected to the ventilator blowers on ground level, and run down vertically to the shaft base.

e) The ventilation system will be in continuous operation in the launch shaft & tunnel.

The installation of duct shown in Figure 90.

Page 108: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 108 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

Ventilator Ø800mm iii. Service Pipes

While excavation is stopped during the ring build cycle. It is possible to extend service pipes,

rails, electric cable and exchange the ventilation duct canister. All materials and equipment is stored

on the TBM backup gantry, having been transported to the TBM on flat car pushed by locomotive.

Services, other than pipes and rail, are typically delivered and installed during maintenance shift.

It is intended that pipe joints will be staggered to minimize the number of service changes at a

particular time. Services are extended by shutting the nearest valves either side of the pipe to be

extended carefully bleeding of the air or water by slowly opening the bleed valve on the end of the

back-up gantry/ hoses, then disconnecting the hose and inserting a new pipe.

The rail track can be laid using the overhead crane at the front of the first back-up gantry. The

rail will be installed to a standard to minimize maintenance and risk of the derailments. Rail gauge

750mm. and tolerance is -3mm. to +15 mm.

Figure 90: Vent Duct placement

Page 109: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 109 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX A

CNR LANZHOU LOCOMOTIVE CO.LTD. COMPANY

PROFILE AND SUPPLY TRACK RECORD

Page 110: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 110 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX B

FACE PRESSURE NORTH AND SOUTH ALIGNMENT

Page 111: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 111 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX C

CUTTERHEAD INTERVENTION LOCATION ALONG THE

TUNNELS

Page 112: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 112 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX D

GEOLOGICAL PROFILE ALONG THE TUNNELS BASED ON

GIBR

Page 113: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 113 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX E

SUMMARY OF KEY PRESSURE FOR SOUTH AND NORTH

ALIGNMENT

Page 114: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 114 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX F

SETTLEMENT BASED ON THE SURFER ANALYSIS

Page 115: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 115 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX G

RISK ASSESSMENT

Page 116: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 116 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX H

SAFE WORK PROCEDURES

Page 117: TBM Operation for Tunneling Work (Final).pdf

METHOD STATEMENT

TBM OPERATION

FOR TUNNELING WORK

Doc. No.: DOC/SDC/MS/019

Rev. No. : -

Est. date: OCT 2015 Pages: 117 of 117

SDC-C2

CONSTRUCTION OF STAMFORD DIVERSION CANAL CONTRACT 2 – GRANGE ROAD TO RIVER VALLEY ROAD

APPENDIX I

SAMPLE OF TBM OPERATION FORM

TBM Operation Instruction Sheet

Cutterhead Entry

Backfill Grouting

Backfill Grout Testing Record

Inspection of Segment Ring

Ring Building Protocol

Ring Inspection Sheet

Muck Skip Volume Record