Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
- Technical Standards and
Specifications -
Technical Standards and Specifications
Training on technical standards and specifications:
• content of NRS 097 series,
• the wiring code and wiring standards,
• SANS 10142-1-X (currently under development),
• the SA Renewable Power Plant (RPP) Grid Code and
• other appropriate ranges of standards including
international standards (e.g. IEC).
Overview: Technical Standards
3
Loads
Off and on Earth leakage
=≈
M
M
Solar Load
Control
Municipal Network
1
2
3 4
15
6
7
8 9
10 11
13
14
PE/PEN
12
5
Overview: Technical Standards
• South African Documents
– NRS 097
– SANS 10142-1-X
– RPP Grid Code
– NRS 052 / SANS 959
– NRS 048
• International Documents
– IEC 62109: Safety of power converters for use in
photovoltaic power systems
NRS 097-1
Part 1: Distribution standard for the interconnection of embedded
generation
– To be based on Eskom standard
– (Document number: 240_61268576)
• Still not developed
• >100kVA
• SA Grid Code for Renewable Power Plants (RPP Grid Code)
– Eskom document contains more than the minimum
requirements in the RPP Grid Code
NRS 097-2• Grid interconnection of embedded generation
• Part 2: Small-scale embedded generation
• The specification sets out the technical requirements for the utility interface, the embedded generator and/or system and the utility distribution network with respect to embedded generation. The specification applies to embedded generators and or embedded generator systems smaller than or equal to 1000 kVA connected to low-voltage networks.
– Section 1: Utility interface
– Section 2: Embedded generator requirements. (To be developed in the future.)
– Section 3: Utility framework.
– Section 4: Procedures for implementation and application. (To be developed in the future.)
NRS 097-2-1
• Grid interconnection of embedded generation
• Part 2: Small-scale embedded generation
• Section 1: Utility interface– Technical requirements for a generator to connect to the utility
network
– Not an inverter specification
“Device Independent”
– Not a generator specification
Interface Document
– Describe the requirements at the utility interface
Overview: NRS 097-2-1
• Interface
9
Loads
Off and on Earth leakage
=≈
M
M
Solar Load
Control
Municipal Network
1
2
3 4
15
6
7
8 9
10 11
13
14
12
5
NRS 097-2-1
• Connected to LV (<1 kV)
• Edition 1 <100 kVA
• Edition 2 <1000 kVA
• Several changes
– Aligns with RPP Grid Code as far as possible
– Influenced by international developments
NRS 097-2-1 / RPP Grid Code
• Size and balancing information
– Category A1: 0 – 13,8 kVA
– Category A2: >13,8 kVA – <100 kVA
• Central disconnection
– Category A3: 100 kVA – <1 MVA
• Controllability (4.1.1.15)
• Ramp-up after abnormal conditions
11
NRS 097-2-1
• Equivalent International Documents
– IEC 61727
– IEEE 1547
– EN 50438
– VDE-AR-4105
– G83 / G59
NRS 097-2-1
• Three clauses:
4.1 Utility compatibility
4.2 Safety and protection
4.3 Metering
4.4 UPS with embedded generation
13
NRS 097-2-1
• Clause 4.4 removed for Edition 2:
– 4.1.1.13 Any UPS/generating device that operates in parallel
with the grid may only connect to the grid when it complies fully
with the requirements of this part of NRS 097. This includes UPS
configurations with or without EG.
• NOTE The requirement is applicable irrespective of the duration of
parallel operation.
14
NRS 097-2-1: Utility Compatibility
• General Clauses:
– general requirements
– sets the basic parameters
– basic system compatibility
– power quality compatibility
– type approval
– size allowed
– utility approval
– fault level
– Installation requirements
• Ref SANS 10142-1 and -1-2
• Maximum DC voltage - 1000 V (1500 V)
15
NRS 097-2-1: Utility Compatibility
• In accordance with SANS 10142-1 and/or 10142-1-2, all generators
shall be wired permanently.
• Standby-generators are covered by SANS 10142-1.
– Change-over switch
16
NRS 097-2-1
• Summarise as:
– What to expect?
– What is allowed?
– What to do?
17
=≈
=≈
=≈
CONTROL
What to Expect?
• Voltage
– South African LV range
– Check connection
• Frequency
– 50 Hz ±2%
– RPP Grid Code ride-through requirements
18
=≈
What to Expect?
• Power Quality
– Take note of NRS 048-2 compatibility levels
– Generator must be able to withstand these levels
continuously
– Protect itself should levels exceed these
19
=≈
What to Expect?
• EMC / Mains signalling
– Fail-safe
20
=≈
What to Expect?
• Fault Level
• Short-circuit ratio
– Documentation and nameplate
– Design
– Type testing
21
=≈
NRS 097-2-1: Utility Compatibility
• Reference Source Impedance and Short-Circuit Levels
– IEC 60725: 0,4 + j0,25 Ω
– Annex C (p41):
– Z_source = 1,05 + j 0,32 Ω
– I_SC = 210 A
– S_SC = 146 kVA (three-phase)
• NOTE Use with caution, based on published international
values and simulations only.
22
NRS 097-2-1: Utility Compatibility
25
0
0.05
0.1
0.15
0.2
0.25
0.3
0.35
0.4
0.45
0.5
0 50 100 150 200 250 300 350 400 450 500
FA
UL
T L
EV
EL
[K
A]
LV LINE LENGTH [M]
125kVA 25mm2 (1ph FL [kA]) 315kVA 400mm2 (1ph FL [kA]) 210A
What Allowed?
• Inject current - not voltage
– Voltage control (future requirements) may lead to instability
• Synchronise
• Operate within trip limits
• No islanding
– Out of phase reclosing
26
=≈
What Allowed?
• QOS contributions
– Flicker (p13)
• Short-term flicker severity limit Pst = 0,35
• Long-term flicker severity limit Plt = 0,30
– 3% Voltage change limit
– Utility to manage by appropriate planning
27
=≈
What Allowed?
• QOS contributions
– Voltage unbalance (p13 to 14)
• 4.6 kVA difference between phases limit
• Three-phase generators: 0.2% limit
• Grid Code limits difference between phases
– 4.6 kVA (any size up to 1 MVA)
28
=≈
What Allowed?
• QOS contributions
– Harmonics and waveform distortion (p15)
– IEC 61727
• IEEE 1547
• IEEE 519
– Up to the 60th
29
=≈
NRS 097-2-1: Utility Compatibility
• p15
• Also refers to NRS 048-4
30
Harmonic order (h) h<11 11≤h<17 17≤h<23 23≤h<35 35≤h
Percentage of rated current
(Odd harmonics)
4,0 2,0 1,5 0,6 0,3
Percentage of rated current
(Even harmonics)
1,0 0,5 0,38 0,15 0,08
Percentage of rated current
(Inter-harmonics)
0,1 0,25 0,19 0,08 0,03
Total Demand Distortion = 5%
NOTE 1 Even harmonics are limited to 25 % of the odd harmonic limits
NOTE 2 Inter-harmonic are limited to 25 % of the odd harmonic limits and adjusted for the 200
Hz band measurement required by IEC 61000-4-7, except for the lower frequencies where the
flicker contribution is more likely.
NOTE 3 Total Demand Distortion = Total Harmonic Distortion
Harmonic Examples
-400
-300
-200
-100
0
100
200
300
400
0.000 0.005 0.010 0.015 0.020
Harmonic Voltage
31
Harmonic Current Examples
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
10000
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
5
2016/05/07 00:00 2016/05/07 04:48 2016/05/07 09:36 2016/05/07 14:24 2016/05/07 19:12 2016/05/08 00:00 2016/05/08 04:48 2016/05/08 09:36 2016/05/08 14:24
3rd Harmonic Current as Percentage of Maximum Fundamental
I_1 I_2 I_3 P_TOTAL
33
10 minute values
Harmonic Current Examples
-1000
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
2016/05/07 00:00 2016/05/07 04:48 2016/05/07 09:36 2016/05/07 14:24 2016/05/07 19:12 2016/05/08 00:00 2016/05/08 04:48 2016/05/08 09:36 2016/05/08 14:24
11th Harmonic Current as Percentage of Maximum Fundamental
I_1 I_2 I_3 P_TOTAL
35
What Allowed?
• QOS contributions
– DC injection (p14)
– 1-minute average d.c. current injected ≤ 0,5 % of
rated a.c. output current
• under any operating condition.
36
=≈
What Allowed?
• Power factor
• Power factor requirements updated
– A1 and A2 pf > 0.98
– A3 pf > 0.95
– (If required, specifics may be requested)
37
=≈
What Allowed?
• EMC / Mains signalling
– IEC 62578 (to be removed)
• May require filtering (e.g. separate transformer)
– SANS/IEC 50065-1
• 3 kHz to 148,5 kHz
• Unintentional
• To start at 30 kHz (WG recommendation)
38
=≈
What Allowed?
• EMC / Mains signalling
– SANS 211 (CISPR11)
• From 148,5 kHz (not 150 kHz)
• Class B Group 1
• Radiated and Conducted (unintentional)
39
=≈
What Allowed?
• EMC / Mains signalling
– Existing and new PLC-based communication systems
have preference
• SSEG to fix if and when problems arise
40
=≈
What to DO?
• Safety
– SANS/IEC 62109-1 and IEC 62109-2
• Ensure Anti-islanding
• Redundancy
41
=≈
CONTROL
What to DO?
• Automatic disconnection for abnormal conditions:
– network voltage or frequency out-of-bounds conditions
– loss-of-grid conditions
– d.c. current injection threshold exceeded (per phase)
– and residual d.c. current (phase and neutral currents
summated)
42
=≈
CONTROL
NRS 097-2-1: Safety and protection
• Overvoltage, under-voltage and frequency (including
voltage-ride-through)
• Sub-categories A1 and A2
– RPP Grid Code may override
• Sub-category A3 - RPP Grid Code applies
– Same as Category B
• Network and System control need not intervene
43
NRS 097-2-1: Safety and protection
• Sub-category A1 and A2: Safety disconnect requirements
• Abnormal Voltages
Voltage range
(at point of connection)
Maximum trip time
S
V < 50 % 0,2 s
50 % ≤ V < 85 % 10 s
85 % ≤ V ≤ 110 % Continuous operation
110 % < V < 115 % 40 s
115% ≤ V < 120% 2 s
120 % ≤ V 0,16 s
NOTE If multi-voltage control settings are not possible, the more
stringent trip time should be implemented, e.g. 2 s between 110%
and 120% of voltage.
NRS 097-2-1: Safety and protection
• Category A: Safety disconnect requirements
• Abnormal Frequency
f < 47 HzDisconnect
0,2 s
f > 50.5 HzInstantaneous
output power ->
PM
f > 50.5 HzReduce/ increase
linearly as a
function of PM
f > 50.5 HzSA: 50% droop
f > 51,5 Hz > 4sTrip within 0,5 s
NRS 097-2-1: Safety and protection
4.2.2.3.4 Relaxation for non-controllable generators
• Randomly disconnect between 50,5 Hz and 51.5 Hz
• 0,1 Hz steps
• Uniform distribution per manufacturer
What to DO?
• Automatic disconnection for abnormal conditions:
– network voltage or frequency out-of-bounds conditions
– loss-of-grid conditions
– d.c. current injection threshold exceeded (per phase)
– and residual d.c. current (phase and neutral currents
summated)
47
=≈
CONTROL
Anti-Islanding-Additional
• What is an island?
– Section of network
– Disconnected from main grid
– Generation continues to supply load
• Implies - balance between generation and load
• NOTE: loss-of-grid and anti-island used interchangeably
48
NRS 097-2-1: Safety and protection
4.2.2.4 Prevention of islanding
• Cease to energise the network within 2 s
• NOTE Prevention of islanding measures is only considered on the
embedded generator side, i.e. no utility installed anti-islanding
measures are considered.
– Utility to consider ARC settings!
NRS 097-2-1: Safety and protection
4.2.2.4 Prevention of islanding
• Passive methods
– Three-phase voltage detection and shall be verified by an AC
voltage source.
– Not be the sole method to detect an island condition.
• At least one active island detection method implemented
– Needs interaction with EG
– IEC 62116: Anti-islanding test
What to DO?
• Automatic disconnection for abnormal conditions:
– network voltage or frequency out-of-bounds conditions
– loss-of-grid conditions
– d.c. current injection threshold exceeded (per
phase)
– and residual d.c. current (phase and neutral
currents summated)
51
=≈
CONTROL
What to DO?
• Ensure synchronisation (p18)
– Network voltage stable for 60s
– Ramp up at 10% per minute OR
– Random reconnection from 1 to 10 minutes
• Only automatic synchronisation allowed
52
=≈
CONTROL
What to DO?
• Dip ride-through (X1-type dips)
• OR
• Category B and C curve (A3)
53
=≈
CONTROL
NRS 097-2-1: Safety and protection
• Voltage ride-through: Sub-category A1 and A2
54
NRS 097-2-1: Safety and protection
130%
125%
120%
115%
110%
100%
95%
90%
85%
80%
75%
70%
65%
60%
55%
50%
45%
40%
35%
30%
25%
20%
15%
10%
5%
0%
X1
Y
Disconnect 10s
150 600 3000 ms
Disconnect 0.16s
Disconnect 2.0s
Disconnect 40s
Disconnect 0.2s
55
20s
110%
120%
150 600 3000 ms
40%
0%
60%
Y
Z1
SX1
X2
Z2
T
70%
80%
90%
Area A
Area B
Area C
Area D
NRS 097-2-1: Safety and protection
• Ride-through requirements (Also RPP Grid Code)
– Category A3
– Same as category B (and C excluding Area D)
What to DO?
• Power factor control (> 100 kVA)
• Capability required
57
=≈
CONTROL
NRS 097-2-1: Utility Compatibility
4.1.11 Power factor
• Controllable EG
– Towards unity at PoC
• Utility may request characteristic curve
– Default is unity
58
NRS 097-2-1: Utility Compatibility
• Power factor control
• Often requires capacitors
• Separate vs. integrated
• May need detuning
– Harmonics
– Switching transients
• Discussion and agreement between EG owner and utility
59
NRS 097-2-1: Safety and protection
• Disconnection device
• Compulsory
– Integrated or stand-alone
• Stand-alone may be suitable, e.g.:
– All EG installations larger than 30 kVA shall have a central
disconnection device.
– For customers' own load in isolated operation.
• Operate under all network conditions
– E.g. future fault level
– EG Owner responsibility
• Power quality immunity
– over voltages, harmonics etc.
60
NRS 097-2-1: Safety and protection
• Reliability of Disconnection Device:
• Fail SAFE:
– A failure within the disconnection device shall lead to disconnection
of the generator from the utility supply and indication of the failure
condition.
– A single failure within the disconnection switching unit shall not lead
to failure to disconnect. Failures with one common cause shall be
taken into account and addressed through adequate redundancy.
– The disconnection device shall disconnect the generator from the
network by means of two series connected robust automated load
disconnect switches.
– Both switches shall be electromechanical switches.
– Each electromechanical switch shall disconnect the embedded
generator on the neutral and the live wire(s).
61
NRS 097-2-1: Safety and protection
• The fault current breaking capacity of each disconnecting switch
shall be appropriately sized for the application.
• Any programmable parameters of the disconnection switching unit
shall be protected from interference by third-parties, i.e. password
protected or access physically sealed.
• The network and system grid protection voltage and frequency relay
for the central disconnection device will be type-tested and certified
on its own (stand-alone tested).
62
NRS 097-2-1: Safety and protection
DGSL• Dead Grid Safety Lock
• Dr Hendri Geldenhyus
– Dr Johan Beukes
63
NRS 097-2-1: Safety and protection
4.2.3 Emergency personnel safety
• No requirements for emergency personnel safety (e.g. fire brigade)
existed at the time of publication. It is expected that such issues will
be dealt with in other documents, e.g. OHS Act, SANS 10142-1.
NRS 097-2-1: Safety and protection
4.2.4 Response to utility recovery
• Always synchronise (cfg. 4.1.12)
• Stable voltage and frequency: 60s
• Non-controllable generators
– Select reconnection time: 1 min to 10 min
– No more than 2% within 10s
• Controllable generators
– Reconnect at 1 min
– Ramp up at 10% per minute
NRS 097-2-1: Safety and protection
4.2.5 Isolation
• In line with SANS 10142-1 (as amended), each energy source should have its own, appropriately rated, isolation device.
• Maintenance of EG
– Note internal requirements not covered by NRS 097-2-1
• SANS 10142-1/-1-2 developments will supersede
• Rated appropriately in accordance with SANS 60947-2
• For dedicated suppplies
– A similar disconnection device
– Lockable and accessible by utility
– Utility owned
How to earth a generator
NRS 097-2-1: Safety and protection
4.2.6 Earthing
• To be finalised for SANS 10142-1-2
– Floating DC preferred
• B.3.2 Earth electrode
• B.3.2.1 All alternative systems shall have an own earth electrode connected to the consumer’s earth terminal and shall comply with 7.12.3.1.1 in SANS 10142-1:2012.
• B.3.2.2 Embedded generators need not have their own earth electrode in accordance with SANS 101421, but an own earth electrode is preferred.
69
DC: TN-S
TN-S d.c. systemFloating d.c.Protective earth
L+
L-
PE
Source(s) Installation
TN-S
NRS 097-2-1: Safety and protection
• Earth leakage:
• As per IEC 62109-2
• RCD that can detect smooth dc (without zero crossings)
– Avoid nuisance tripping (i.e. higher leakage currents)
• RCD type B according to IEC/TR 60755, amendment 2
• Unless dc can be prevented completely
– E.g. transformer between dc and ac
NRS 097-2-1: Safety and protection
4.2.7 Short-circuit protection
• In accordance with SANS 10142-1 and SANS 10142-1-2.
• Supply EG short-circuit characteristics to utility
NRS 097-2-1: Safety and protection
4.2.8 Maximum short-circuit contribution
• In order to limit the fault level changes in low voltage networks and
allow coordination of fault levels with the utility, no generator will
exceed the following fault level contribution:
a) for synchronous generators: 8 times the rated current;
b) for asynchronous generators: 6 times the rated current; and
c) for generators with inverters: 1 times the rated current.
• Check short-circuit ratings of all equipment
– Note potential impact on adjacent customers
NRS 097-2-1: Safety and protection
4.2.9 Labelling
• SANS 1186-1
• Upstream DBs
-
-
NRS 097-2-1: Safety and protection
4.2.10 Robustness requirements
• According to 4.2.2.1, all SSEG shall comply with safety
requirements in accordance with SANS/IEC 62109-1 and
IEC 62109-2.
• NOTE This section will be expanded in future revisions.
Utility Staff Safety: MV
• MV Process
• Open
• Isolate
• Test
• Earth
– Both sides
• Work
75
Utility Staff Safety: LV
• LV Process
• Open
• Isolate
• Test
• Earth
– Not possible
• DGSL
• Work
76
Disconnecting Device Layout
Contactor 1 Contactor 2
Auxiliary Relay
The DD comprises of:
Auxiliary Relay: Double pole NO contacts
Contactor 1 and 2: NO contacts to break all phases and Neutral. Single auxiliary NC contact
Source: Dr Hendri Geldenhuys (Eskom)
NRS 097-2-1: Metering
• Meter remains property of utility
• Metering will comply to SANS 474/NRS 057 and SANS
473/NRS 071
• Smart meters: NRS 049
78
NRS 097-2-1: Metering
• Signage may also be required for metering (meter readers)
NRS 097-2-1: Metering
• Single quadrant meter (standard meter)
• Recommended upgrade to four quadrant
• Note confusion on use of “Nett metering”
80
kWhkWh
EG L
U
~
DB
Net
meter
NRS 097-2-1: Metering
• Two or four quadrant meter
• Two options
81
kWhkWh
EG L
U
~
DB
kWhkWh
Consumption
meter
Embedded
generation
meter
kWhkWh
EG L
U
~
DB
kWhkWh
Net
meter
Embedded
generation
meter
NRS 097-2-1 Summary
• Interface document
• Device independent
4.1 Utility compatibility
4.2 Safety and protection
4.3 Metering
82
NRS 097-2-2• Embedded generator requirements
– Type testing - proving compliance to NRS 097-2-1
• Draft
• References to IEEE 1547.1
• Testing houses in SA – None
• SABS - no facilities
• Processing and compliance monitoring
• Database
83
NRS 097-2-3
• Simplified utility connection criteria for low-voltage connected generators
• For use by utilities
– Customers can establish what would be easy to connect, e.g. smaller than 25% of ADMD/Breaker size
– Maximum size as a function of cable parameters and distance from transformer
• Flowchart to consider connection without detailed studies
• When SSEG connection request complies with simplified checks, can be connected
– Allows for larger SSEG connections, pending detailed studies by utility
• Principle of fairness
– 30% of 50% of customers can be accommodated
NRS 097-2-3
• Type-test certified to NRS 097-2-1.
• Simplified connection: limited to 350 kVA.
• The maximum permissible generation size of an individual LV
customer is dependent on:
– the type of LV network, i.e. shared or dedicated.
– the customer’s notified maximum demand (NMD) (i.e. circuit-
breaker rating).
• Additional requirements linked to the size of the MV/LV transformer
and maximum loading of the associated MV feeder are discussed
this section of NRS 097-2.
89
NRS 097-2-3
• The LV fault level at the customer point of supply should be greater
than 210 A.
– NOTE Details of the selection of the 210 A fault level is
discussed in annex C of NRS 097-2-1:Ed2.
• If the criteria in this standard are not met -> more detailed studies
are required.
• Utilities may modify the criteria, or add additional criteria, to meet
their specific requirements considering their network characteristics.
90
NRS 097-2-3: Basis for the calculations
NOTE 1 The proposed criteria in this section of NRS 097-2 have been
guided by
– the approaches used in other countries and utilities, as informed
by work within Cigre, and specifically Cigre working group C6.24.
The intention is to adopt best practice as already applied in other
utilities that have considerable experience with LV connected
generators; and
– the application of specific technical criteria on models that
represent typical South African LV networks.
• NOTE 2 It is intended that the criteria will be enhanced and revised
as more detailed studies are performed in the future and that the
industry can learn from the application of these criteria.
91
NRS 097-2-3
• The technical limits that constrain the amount of generation are as follows
a) thermal ratings of equipment (lines, cables and transformers) may not be
exceeded;
b) LV voltage regulation should be within the limits specified in NRS 048-2 (LV
voltages at the customer point of supply should be within ± 10 %);
c) the maximum change in LV voltage (due to voltage drop/rise in the MV/LV
transformer and LV feeders) due to embedded generators is limited to 3 %.
– This is a common international practice where the generation is
variable.
– From a voltage change perspective, it does not matter how much of the
generation is consumed locally or fed back into the network.
d) islanding on the utility network is not allowed;
e) the fault level at the customer point of supply should be greater than 210 A,
or the minimum fault level at which the generator is rated.
92
NRS 097-2-3
• The application of the limits given in 4.6.2 resulted in the following proposed
criteria:
a) Voltage rise on LV feeders should be limited to a maximum of 1 %. This
value is informed by the NRS 048 voltage limits, MV voltage control
practices and the MV/LV transformer voltage ratio and tap settings (see
table 4).
b) Voltage rise across the MV/LV transformer should be limited such that the
NRS 048-2 voltage limits are not exceeded (see table 5). The maximum
generation connected to a MV/LV transformer is limited to 75 % of the
transformer rating understanding that this may result in overvoltage
problems on LV feeders where there is further voltage rise. The 75 % limit is
hence high but in reality the net flow through the transformer into the MV
network is expected to be significantly less due to the customer loads. A 75
% limit will also ensure that the transformer will not be overloaded during
periods of maximum generation and minimum loading.
93
NRS 097-2-3
c) The individual customer limit of 75 % of NMD on dedicated LV
feeders is informed by the MV/LV transformer limit of 75 %. This
approach provides customers with equitable access to the
available generation capacity as limited by the MV/LV transformer
rating. It will also ensure that service cables will not be overloaded
under conditions of maximum generation and low loading.
d) The dedicated LV feeder minimum size is based on a maximum
voltage rise of 1 % (figure 3 and figure 4). The 1 % value is in
accordance with table 4.
94
NRS 097-2-3
e) The individual customer limit of 25 % of NMD on shared LV feeders is
informed by an analysis of typical LV feeder designs whereby the
individual generator size was scaled as a function of the design ADMD
and the generation penetration level (percentage of customers that
install a generator).
a) The voltage rise and change in voltage were calculated
assuming that the installed generation is reasonably
balanced.
b) An individual limit of 25 % of NMD will typically support a
penetration level of 30 % to 50 %, which is considered a
reasonable and acceptable compromise between
restricting individual generator sizes versus restricting
penetration levels.
c) It shall be noted that a primary limitation is the maximum
voltage change of 3 %.95
NRS 097-2-3
f) The total generation connected to a MV feeder is limited to 15 % of
the MV feeder maximum loading.
a) This value is informed by practices in the United
States and Europe, and is based on the ratio of
maximum to minimum feeder loading for typical
consumer load profiles.
b) A limit of 15 % will ensure a low probability of reverse
power flow into the MV feeder source, thereby
preventing voltage rise in the MV feeder and reducing
the possibility of an island for operation of MV
switches and protection.
96
NRS 097-2-3
• Calculation of maximum LV voltage rise
• Calculation of maximum generation connected to a
MV/LV transformer
• Worst-case scenario simulations
– High load - high EG generation
– High load - no EG generation
– Low load - high EG generation
– Low load - no EG generation
97
NRS 097-2-3
• Table 1 — Maximum individual generation limit in a
shared LV (400 V/230 V) feeder
99
Number of
phases
Service circuit-
breaker size
NMD
[kVA]
Maximum individual
generation limit
[kVA]
1 20 A 4,6 1,2
1 60 A 13,8 3,68
1 80 A 18,4 4,6
3 60 A and 80 A 41,4 13,8 (4,6 per phase)
NRS 097-2-3
• Figure 3: Dedicated LV feeder maximum generator sizes as a function of
PVC copper cable size and distance
– 1% voltage rise
• Also figure 4: aluminium cable
• Tables 2 and 3 – look-up tables for these figures
101
0
50
100
150
200
250
300
350
400
450
0 50 100 150 200 250 300 350 400 450 500
Ge
n (
kW)
Distance (metres)
(Pf=1)
300 Cu PVC
240 Cu PVC
185 Cu PVC
150 Cu PVC
120 Cu PVC
95 Cu PVC
70 Cu PVC
50 Cu PVC
25 Cu PVC
NRS 097-2-3
4.5 Simplified connection criteria
• Flowchart
103
Research
• Master's student
– Emmanuel Namanya
– Proff Gaunt and Herman
• Thesis: “Voltage Calculation on Low Voltage
Feeders with Distributed Generation”
– May 2014
• NRS 034 (Herman Beta method)
106
Research
80
85
90
95
100
105
110
115
120
0 100 200 300 400 500 600
Vo
ltag
e [%
]
Distance [m]
Voltage Profile
Base Case
107
10%
10%
Research
80
85
90
95
100
105
110
115
120
0 100 200 300 400 500 600
Vo
ltag
e [%
]
Distance [m]
Voltage Profile
Base Case
Base +5%
108
15%
5%
Research
111
0 10 20 30 40 50 60 70 80 90
100
% EG/NMD (Approximate)
Research: Summary
• Recommendation:
– 30% of ADMD (not NMD)
– Approximately15% of NMD
112
NRS 097-2-3 Summary
• Simplified Connection Criteria
• Flowchart
• Basic checks
– Customer size
– Thermal loading of feeder
– Fault level > 210 A
• Total installed capacity as percentage of:
– MV/LV Transformer size
– MV Feeder loading
– Network loading (HV/MV substation)
• If not meet - detailed studies
113
NRS 097-2-3
• What if the connection request does not meet the
requirements?
• A few slides on guidelines for planning processes
• And other aspects to keep in mind
114
General Impact Study
• Loadflow
– Thermal ratings
– Voltage regulation
• Voltage transients
– EG rejection
• Short-circuit studies
– Equipment ratings
– Protection coordination
115
General Impact Study
• Calculation of maximum generation connected to a MV/LV transformer
– Calculation of maximum LV voltage rise
– Calculation of maximum thermal loadings
– Note impact of dc currents
• Worst-case scenario simulations
– High load - high EG generation
– High load - no EG generation
– Low load - high EG generation
– Low load - no EG generation
116
Thermal Ratings
• Thermal ratings
– Typical Urban network
– Maximum load limited by thermal ratings
– Rather than voltage drop
• Loadflow
• Minimum load vs
• Maximum generation
• Reverse power flow possible
– e.g. Weekend mid-day
117
Generation
Load
Max
MinMaxMin
Thermal Ratings
• Thermal ratings
– Depending on location of EG
– Load growth
– Feeder conductor
• Reducing conductor sizes
– Evaluate all corners
• Thermal ratings for:
– Lines
– Cables
– Transformers
118
Generation
Load
Max
MinMaxMin
Data Requirements
• All cable/lines in the modelled area:
– types (conductors)
– length
• Substation transformer
– rating, short circuit impedance, tap changer range,
voltage setpoint
• MV/LV transformers
– including the actual winding ratio/position of off-load
tap changer
119
Data Requirements
• Maximum power output of all SSEG
• Load characteristics
– Profile
– Power factor
120
Protection Impacts
• Increased fault levels
• Reduced reach
• Sympathetic tripping
• Reclosing onto island
• Fuse-saving
121
Increased Fault Levels
• NRS 097-2-1: Ed2
• 4.2.8 Maximum short-circuit contribution
• No generator will exceed the following fault level contribution:
a) for synchronous generators: 8 times the rated current;
b) for asynchronous generators: 6 times the rated current; and
c) for generators with inverters: 1 times the rated current.
• Confirm short-circuit rating from test certificate
• Check short-circuit ratings of all equipment
– Note potential impact on adjacent customers
122
Reduced feeder breaker reach
• Generator also contributes to fault current
• Impedance to end of feeder
• Check feeder breaker settings vs. short-circuit
contribution
123
G
Sympathetic Tripping
• Healthy feeder trip
• Due to fault on adjacent feeder
• EG with high short-circuit current contribution
• Multiple feeders
• Breaker 2 has faster trip
characteristic than breaker 1
• Check breaker trip characteristics
124
G
1 2
Reclosing Onto Island
NRS 097-2-1: Ed2
4.2.2.4.4 An islanding condition shall cause the embedded
generator to cease to energize the utility network within 2 s,
irrespective of connected loads or other embedded
generators.
• ARC times for network in question to be checked
• Minimum ARC time > 2s
125
Fuse-Saving
• Fuse-saving philosophy:
– Feeder breaker first trip very fast
– Delay after first or second reclose to allow fuse to
operate
• EG result in increase in fault current
– Depends on type, size and number of EG
• Fuse may operate quicker
• Lack of coordination
• Need to re-evaluate coordination
126
Summary: Protection Impacts
• Increased fault levels
– Confirm short-circuit rating from test certificate
– Check short-circuit ratings of all equipment
• Note potential impact on adjacent customers
• Reduced reach
– Check feeder breaker settings vs. short-circuit contribution
• Sympathetic tripping
– Check breaker trip characteristics
• Reclosing onto island
– Minimum ARC time > 2s
• Fuse-saving
– Need to re-evaluate coordination
127
NRS 097-2-4
• Procedures for implementation and application
– To be developed
• Application forms and processes
• Database requirements
– keeping track of installations
128
NRS 097-2-4
• Some considerations (from NRS 097-2-1)
• ANNEX A:
• NOTE The customer is advised to contact the utility to discuss potential further connection requirements.
• A.1 The following requirements shall be specified in tender invitations and in each order or contract:
– whether all power quality parameters shall be measured at the POC
• A.2 The following requirements shall be agreed upon between the customer and the utility:
a) whether the EG shall be type approved
b) whether the EG may control the voltage
c) the power factor limits
129
Subtleties
• Renewable Power Producers
– Point of Connection
• Embedded Generators
– Generator terminals
– Point of Connection
• Safety aspects
NRS 097-2-4
• Significant work to be done
• AMEU / SALGA has put together resource pack
131
Compulsory Standards
• Department of Labour
– Determined by Minister
• OHS Act
• Electricity Installation Regulations
• SANS 10142-1
132
Compulsory Standards
133
SANS 10142-1Clause 7.12
• 7.12.1.1 Subclause 7.12 applies to an installation that incorporates alternative supplies intended to supply, either continuously or occasionally, all or part of the installation with the following supply arrangements: Amdt 6
• a) supply to an installation or part of an installation which is not connected to the main supply of a supplier; Amdt 6
• b) supply to an installation or part of an installation as an alternative to the main supply of a supplier; and Amdt 6
• c) appropriate combinations of the above.
• NOTE 1 Requirements of the supplier should be ascertained before a generating set is installed in an installation connected to the main supply of a supplier.
• NOTE 2 This part of SANS 10142 does not cover the supply to an installation that functions in parallel with the main supply (co-generation). Amdt 6
134
SANS 10142-1
Clause 7.12
• 7.12.1.2 Subclause 7.12 covers, but is not limited to, the following:
• a) generating sets that consist of a combination of an internal
combustion engine or a turbine, and an alternator or a d.c.
generator;
• b) rotary UPS systems (uninterruptible power systems) that consist
of a combination of an electric motor and an alternator, with
batteries as a standby power source for the electric motor, or with
an internal combustion engine or turbine as a standby power source
for the alternator; and
• c) static UPS systems that consist of static inverters with batteries
as the standby power source (with or without bypass facilities).
135
SANS 10142-1
• NOTES:
• SANS 10142-1 still applies to balance of installation
• SANS 10142-1 does have a section on DC installations
– Possibly require more for PV installations
– May be addressed in future by another part of SANS
10142
136
Safety Concerns• Installation deficiencies
– Installation of utility-accessible lock-out breaker (where feasible)
– Such a breaker is not feasible in shared networks
– Dead Grid Safety Lock
– DC fed back into network (possible failure modes of the inverter)
– DC vs. AC breakers and associated derating
• Anti-islanding
– Failure to disconnect when the network is de-energised
– Test for voltage before work commences will safeguard LV personnel
• Re-connection while maintenance in progress (DGSL)
– Failure of the inverter to detect that the network is not energised
– Remains a risk (in shared networks) until LV networks can be earthed
– Earthing at LV requires redesign of LV networks (e.g. providing earthing terminals etc.)
• LV Maintenance Process
– Need to measure after disconnection
– Most voltmeters measure either DC or AC
• Australia – rumours of several PV installations that caused fires at residential homes
• Emergency Personnel, e.g. firefighting
137
2019/03/28
SANS 10142-1-X
• SANS 10142-1-2 has to be read in conjunction with SANS 10142-1 and complied with in full on the balance of the installation.
• SANS 10142-1-2 deal with the installation from the Point of Supply to the embedded generator terminals.
• Proposals indicate that SANS 10142-1-2 will deal with:
– Lightning
– Cable selection
– DC protection
– DC Earthing
138
SANS 10142-1-2
139
Loads
Off and on Earth leakage
=
≈
M
Scope of SANS 10142-1-2:
From EG terminals to POCM
Includes additional DC
where applicable
Neighbours
M
Lightning /
Surge protection
Earthing
Functional Earthing
• A functional earth connection serves a purpose other
than electrical safety, and may carry current as part of
normal operation.• - E.g. IT equipment, telecoms.
• IEC 60364-5-54: 2007: Low voltage electrical installation –
Part 5-54: Selection and erection of electrical equipment:
Earthing arrangement and protective bonding conductors
140
Earthing of Frames
• Frames to be earthed
• Class II insulation (double)
• PID
– Potential Induced Degradation
– Especially thin-film
– Earthing of DC negative pole
– Inverter manufacturer approval
– Need to disable earth fault detection
141
SANS 10142-1-2: Safety and protection
SANS 10142-1-2
• First letter: relationship of the source of energy to earth:
– T:one or more parts are connected direct to earth; and
– I: all live parts are isolated from earth or one point is connected to earth through impedance.
• Second letter: exposed conductive parts of the Consumer's installation to earth:
– T: exposed conductive parts of Installation connected direct to earth,
– independently of the earthing of any point of the source of energy; and
– N: exposed conductive parts of the Installation are connected direct to the source earth,
– (AC) usually the transformer neutral point.
• Arrangement of the neutral and protective conductors:
– C: supply and installation: single conductor;
– S: supply and installation: separate conductors;
– C-S: the neutral and protective functions on the incoming supply are combined in a single conductor and in the Consumer's Electrical Installation are serviced by separate conductors.
Earth Fault Detection
148
• IET CoP (Code of Practice)
Earth fault monitoring
149
Inverter Ground-Fault Detection “Blind Spot” and Mitigation Methods, Greg Ball et al, Solar America Board for Codes and Standards
• Fused GFDI not recommended• Ground Fault Detector and Interruptor
Cable selection
• The maximum voltage value (VDC-max) shall be calculated as follows:
– Voltage (VDC_max) = VOC_STC x 1.15
• The continuous or maximum current, Imax, is defined as 1.25 multiplied by Isc of the string.
– Current (IDC_max) = ISC_STC x 1.25
• Earthing cabling: the same rating!
150
Earthing wiring
• 6 mm2 minimum
• From SANS 10142-1
151
SANS 10142-1-2: Summary
1. Regulatory requirements
2. Embedded generator certification
3. Protection
1. Over current protection
2. RCD for personal protection requirements.
3. RCDs for DC leakage and DC earthing protection
4. Earthing of Neutrals and Protective earthing requirements
5. “Embedded” metering
1. Not covered
6. Isolation and Disconnection
1. Utility accessible isolator
2. Fireman switch for generator output (not required)
3. DGSL
152
SANS 10142-1-2: Summary
7.Monitoring and control
1.There might be requirements related to utility or third party
monitoring and control of the EG.
8.Interlocking protection
9.Islanding operation (refer back to SANS 10142-1)
10.Certification tests
1.Anti islanding
2.Synchronisation
3.Neutral to protective earth insulation test
11.EG-COC
1.Capacity approval limits
2.Proforma COC
12.Registered person(s)
153
Technical Standards and Specifications
Questions?
155