GMH
Template: Testing
Design Profile For:
Copyright © 2009-2010 BCM Institute and GMH. All Right Reserved.
GMH
Template: Testing
Copyright © 2009-2010 BCM Institute and GMH. All Right Reserved.
GMH
Template: Testing
STAFF CALL TREE EXERCISE REPORT
Date of Test: 02/07/201C
By Whom
Name of BUC: ATIF
% of Staff contacted in 10 Minutes TRemediai Action to be carried out
NameofBLUTD
SUCCESS CRITERIA: 50
Name of Staff Member
to contact
Ram
Yupar
Contact
Made
Yes
Yes
Contact Time
3:05pm
3:10pm
Member COULD
Attend
YES/NO
Estimated Time to
get
to Alternate Site
CommGnt/Remedial Action
IMPORTANT
If anyone does not make contact with someone on their call list, they then must take the responsibility for ensuring that the message reaches those people who the uncontactable member of staff would have called.
This Exercise Report should be signed off by the BUC and Manager and copied. One copy should be retained in the BU BCP testing file and the other copy
sent to the Business Porjtinuity Manager.
Line Manager: Atif. Date: 04 July 2010
3
Copyright © 2009-2010 BCM Institute and GMH. All Right Reserved.
Signed:
Template: Testing
WALK-THROUGH EXERCISE REPORT
Business Unit (BU): ITD-01
Date of Test: 02 July 2010
Name of Controller: Josephine Lim
Name of BUC:
Success Criteria: There should be no disagreement
between BUC
and Controller as to whether trie RTO would have been met.
Stage 1 - Immediate Response
Section and
Task Nos.
> Upon receiving call from our security guard and after verification from the
organization BCIVl Coordinator (GM), the damage accessment team (GM, OPS
Manager, HR Manager, IT Manager) (DAT) will proceed to the disaster site.
> Upon arrival at the disaster site, the DAT will access the damage & formulate
response/ emergency evaluation.
> If the extent of damage is greater than the acceptable losses, organization
BCM coordinator will activate the BC plan.
> If the extent of damage is lesser than the acceptable losses, we will salvage
the operation.
Stage 2 - Recovery and Resumption
ITD-01
ITD-02
ITD-03
> Upon activation of the BC Plan, the individual BU Heads will try to acquire the
grab list items.
> All those ALT BU Reps will proceed to the alternate site and initiate the
checklist and recovery procedures, while the other CS will work remotely at
home.
> Enable user access to backup server in only Inquiry mode with in an hour.
> Start verification of database at backup site for last log file applied.
^ Enable application for operations within 6 hours.
> Enable backups on backup server.
> Enable backup email server as primary mail server with on 2 hours.
> Start verification of mailbox store at backup site for last log file applied.
> Update DNS for backup server to be primary exchange server with in 1 hour.
)> Vefiry network resources.
> Arrange transportation of grab-desk to backup site within 2 hours.
> In case of missing grab-disk. Enable restoration fll backup then differential
backup.
> Start verification files and folders.
> Update user scripts for new folder locations at backup server.
Copyright © 2009-2010 BCM Institute and GMH. All Right Reserved.
Template: Testing
Stage 3 - Restoration
Section and
Task Nos.
> SAGE/SQL,E-mail Server, Network Drives
Stage 4 - Return Home or Re-Locate to New Building
> Check and verify all data, server, email & folders are restored.
> Re-commence normal mode of operations.
Types of Challenge or Enquiry
You mention that Checking Section Supervisor will do do they know and who is their alternate?
The plan says that you, the BUC will recover a box from off-site, how will the BCC contact you if events change?
You need computer application available with 3 terminals within 2 hours, have IT. agreed they can do that?
The essential printed forms, you say you do not need a supply held off-site, you will get them from printers, HOW?
Do you have an out-of-hours number for the archive contractor, this is needed to get this box at a weekend.
You say nothing about what you would do about unprocessed customer hard-copy instructions, still in the building.
The plan says "Bill Lim will take his lap-top computer home and work from there" Where is the lap-top now?
In order to meet your RTO, Sandra Tay must be at the office in 2 hours. How will she do that at 2.00 am?