Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 2 of 55
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 3 of 55
Condition Compliance Status
No Description
* The Environmental Clearance is issued for the
following products
Penoxaline @ 150 MT / Month
Cartap @ 50 MT / Month
Metabromuron @ 50 MT / Month
Phosphamidon @ 150 MT / Month
Dichlorovos @ 200 MT / Month; and
Antracol / Mancozeb @ 500/800 MT /
Month
Environmental Clearance also contains the
following by-products
Hydrated Sodium Sulphate @ 737 MT /
Month
Sodium Sulphite Solution @ 298 MT /
Month
Sodium Bromide Solution @ 95 MT /
Month
Sodium Sulphate Solids @ 31 MT / Month
Liquefied Methyl Chloride @ 131 MT /
Month
30 % HCL @ 138 MT / Month
Complied.
Production details are attached for the period of January-
15 to June 2015.
We have obtained Consent to Operate (CC&A) renewed
with amendment for existing products and new solid &
liquid formulation products; vide GPCB CC&A # 55992
dated 31.07.2013 which is valid up to 12.05.2018 (copy
is attached as Annexure-1).
Condition Compliance Status
No. Description
SPECIFIC CONDITIONS
* The land area of the project is 1, 36,777 m2. Project does not involve forest land and displacement of people.
Water requirement is 951.1 kl / day. Solid waste in the form of ETP Sludge (30 MT / Month); Incinerator
Ash (4.5 MT / Month) and Inorganic Solids from Monocrotophos Plant (75.6 MT / Month); Solid Salts (82
MT / Month); and Salt from RO System will be disposed off in the secured landfill facility. NOC from
GPCB was obtained on 29.06.2002. Public Hearing was held on 16.01.2002
* MOEF accords Environmental Clearance to the project under provisions of EIA Notification dated
27.01.1994 as amended subsequently subject to compliance of various special and general conditions
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 4 of 55
1 Gaseous emissions (SO2, NOX, HCl, HC
and Cl2) and PM from various process units should conform to standards
prescribed by authorities. At no time, emissions to go beyond standards.
During failure of pollution control
systems, unit should not be restarted until measures are rectified to achieve
the efficiency
Complied.
-Monitoring done internally and through external agency.
-Reports are attached herewith for the period of January-15 to June
2015. -All parameters are within permissible limit. We have also
started --monitoring PM2.5 parameter for ambient air as per new
standards
Detailed analysis report is enclosed in Annexure –I & analysis
range is as follows
Flue Gas Stacks Emissions – Fuel Natural Gas
Parameter Range
SO2 6 -28 mg/nm3
Stack attached to Boilers
NOX 8 - 24 mg/nm3
Stack attached to Boilers
SPM 14 -89 PPM
Stack attached to Boilers
Process Stack Emissions
Parameter Range
HCl 3–6 mg/Nm3
In PCl3 Plant Stack attached to storage tank Caustic scrubber
Cl2 BDL mg/nm3
In PCl3 Plant Stack attached to Storage Tank Caustic scrubber
SPM 68 – 76 mg/nm3
Stack attached to Spray Dryer (SPD) of CaCl2 Plant wet scrubber
NH3 8 – 11 mg/nm3
CL2 2-4 mg/nm3
Stack attached to TMP Plant HCL Scrubber
PM 15 – 18 mg/nm3
Stack attached to Mancozeb Plant Spray Dryer Wet scrubber
PM 15 – 19 mg/nm3
Stack attached to Antracol Plant Spray Dryer Bag Filter
PM 12 – 18 mg/nm3
Stack attached to Formulation plant Bag filter
HCL - 2.9 – 11.2 mg/nm3
SO2 4.3 - 11.2 mg/nm3
NH3 10-18 mg/nm3
Stack attached to Flonicamide Plant Water scrubber & Caustic scrubber.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 5 of 55
2 Fugitive emissions in workplace
environment, product, raw material storage areas must be monitored. Flue
gas emissions should conform to standards prescribed by GPCB
Complied.
Fugitive emission monitoring at various locations are being carried out by our QA Department. Fugitive Emission Reports are attached
herewith for the period of January-15 to June 2015. Detailed analysis
report is enclosed in Annexure –I & analysis range is as follows
Fugitive Emissions
Parameter Range
Cl2 (TLV= 0.5 ppm) BDL
CS2 (TLV = 10 ppm) BDL – 3 ppm
NH3 (TLV=25 ppm) BDL – 7 ppm
3 Process emissions (SPM, HCl, SO2, Methyl Chloride and VOC) should be
scrubbed through caustic venturi scrubber and conform to standards.
Efficiency of scrubber to be improved and maintained as per best practicable
technology. VOC data to be monitored
and submitted to MOEF. Additional venturi scrubber for Mancozeb,
Penoxaline, Phosphamidon plant and a scrubber for Cartap plant to be installed
in addition to process scrubbers already installed in the unit
Complied.
Air pollution control systems are provided at various stacks.
VOC Monitoring is done through our QA Department by using handy PHOTOVAC monitoring kit.
The monitoring data is attached herewith in Annexure –I
4 As reflected in EIA / EMP Report,
effluent generation should not exceed 195 m3 / day. The waste streams to be
segregated into high and low pollution load streams. Effluent with high organic
load to be incinerated and dilute streams
like from R & D, washing, domestic, dilute streams from process and scrubber
blow down, to be given primary, secondary and tertiary treatment before
discharging into GIDC drain. Treated effluent to conform to standards. Non
toxic effluent to be diverted to RO plant
and re-cycled to minimize fresh water consumption
Complied.
Treated effluent is discharged to GIDC drain to final Effluent treatment plant, NCTL, Ankleshwar for further treatment & disposal to deep sea.
Details of quantity discharged are attached herewith.
Permeate from RO (Reverse Osmosis) System is taken to cooling tower
water make up. RO Permeate month wise details attached in Annexure
-I
5 Waste stream should be treated before taking into solar evaporation pond.
Solvent from effluent to be recovered
before discharging into solar evaporation pond. As reflected in EIA / EMP
Report, Company to install forced evaporation system for aqueous waste to
avoid discharge of effluent into solar
evaporation pond
Complied.
Company has discontinued Solar Evaporation ponds.
Forced Evaporation System is in operation. Details are attached for the
period January-15 to June 2015. in Annexure –I
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 6 of 55
6 Company to recover Methyl Chloride
(CH3CL) by installation of CH3CL recovery plant. Solvent recovery to be
improved and attempts to be made to achieve at least 90 % recovery wherever
possible. Rest solvent which can’t be
recovered, to be incineration. Action to be submitted to Ministry within 3
months
Complied.
Methyl Chloride Plant is in operation.
We have EDC solvent in Monocrotophos & having recovery of @ 98%
7 Company to upgrade existing
incinerator for incineration of hazardous
waste. Organic waste, solid waste generated, to be collected and
incinerated for total destruction. As reflected in EIA / EMP Report, solid
waste and ash obtained after incinerator should be stored in plant premises in a
pit with impervious flooring and
leachate collection system. Ash and sludge from ETP to be finally disposed
off in a TSDF of BEIL. Leachate to be sent to ETP for treatment
Complied.
Company has discontinued operation of Incinerator.
Company has taken membership of Common Incinerator at BEIL, Ankleshwar.
Details of incinerable waste send to BEIL, Ankleshwar is attached for
the period January-15 to June 2015, In Annexure -I
8 Destruction efficiency of incinerator to
be assessed by agency like CPCB and reported. Company to monitor VOCs
and data submitted to MOEF / CPCB / GPCB regularly
Not Applicable.
Company has discontinued operation of Incinerator. Company has membership of common facility BEIL, Ankleshwar.
9 As per CREP, bio assay test to be
replaced by Toxicity Factor Test Method developed by CPCB. TF=4 to
be achieved by December 2003 and TF=2 by July 2006. Action plan to be
submitted within 3 months
Complied.
TF factor monitoring results are attached for the period of January-15 to
June 2015..In Annexure -I.
10 Green belt in 0.2 hectors in addition to 3.66 hector to be provided to mitigate
the effect of fugitive emissions in the plant. Development of green belt along
the boundary wall, open space and
avenue roads to be improved in consultation with local DFO as per
CPCB guidelines
Complied
Total 150 Nos. of trees have been planted during period January-15 to
June 2015.
11 Company to adopt waste minimization
/ cleaner production techniques to
reduce pollution load and action plan to be submitted to Ministry within 3
months
Complied.
12 Company to undertake rain water
harvesting measures as per action plan
submitted to Ministry
Complied.
Rain water harvesting area = 3070 m2
Rain water is being used in cooling tower.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 7 of 55
13 Company to comply with
Environmental Protection measures and safeguards recommended in EIA /
EMA / RRA reports as well as recommendations of Public Hearing
panel
Complied.
An Environmental Cell is in operation, coordinating environmental protection activities. Full-fledged effluent treatment system with
primary, secondary and tertiary treatment is in operation. Treated effluent is monitored and given for further treatment and disposal to
NCTL. Proper scrubbers are in operation to control air pollution and
stack / ambient air monitoring is carried out regularly. Hazardous wastes generated are treated and disposed off. Monthly Reports are
submitted to GPCB.
We are operating plants with valid CC&A and complying to conditions.
CC&A # AWH 55992 dated 31.07.2013 which is valid up to 11.05.2018
B GENERAL CONDITIONS
1 Company to adhere to stipulations made by GPCB
Complied.
We are complying to various conditions given by GPCB in CC&A
We are submitting various Reports / Returns to GPCB on time. We have installed TOC/TN meter at ETP out let .TOC / TN data is
transmitted to GPCB XGN site on real-time basis.
2 No further expansion / modifications in the plant to be carried out without prior
approval of MOEF. In case of deviations / alterations in the project
proposals from those submitted, a fresh reference to be made to Ministry to
assess adequacy of conditions imposed
and add additional environmental protection measures required, if any
Complied
We are operating plants with valid CC&A and complying to conditions.
CC&A # AWH 55992 dated 31.07.2013 which is valid up to 11.05.2018
Copy attached as Annexure # 1
3 Company to comply with MSIHC Rules 2000. Prior approvals of Chief Inspector
of Factories, Chief Inspector of
Explosives, Fire Safety Inspectorate etc, to be obtained
Complied.
The unit is having various statutory licenses & approvals.
4 Company to comply with HWM Rules and authorization from GPCB to be
obtained
Complied
We are operating plants with valid CC&A and complying to conditions. CC&A # AWH 55992 dated 31.07.2013 which is valid up to 11.05.2018
5 Overall noise levels in and around plant area to be kept within the standards (85
dBA) by providing noise control
measures including acoustic hoods, silencers, enclosures etc, on all sources
of noise generation. Ambient noise levels to conform to standards i.e. 75
dBA (day time) and 70 dBA (night time)
Complied.
Noise level monitoring results at different location around Plants area
are attached for period January-June 15 in Annexure -I. The areas like
Compressor Room / Boiler where noise level is slightly higher, ear-muff is used by employees.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 8 of 55
6 Occupational health surveillance
program to be undertaken as regular exercise for all employees, specifically
for those engaged in handling hazardous substances. First aid facilities in OHC to
be strengthened and medical records of
each employees to be maintained
Regular medical checkup of each employee has been conducted.
Premedical employment and medical checkup was done for all new
joinees for the period of January-15 to June 2015..
7 A separate Environment Management
Cell with full-fledged laboratory to be set up to carry out the environmental
management and monitoring functions
Complied.
Water, Stack Monitoring, Bio Assay Test, Tf Factor Test, Ambient Air Monitoring, VOC monitoring, Solid Waste Analysis, Noise Level
Monitoring are carried out. Also, Environmental Audit is being carried out regularly.
8 Company to provide adequate funds for
recurring and non-recurring expenses to implement the conditions stipulated by
MOEF as well as state government
along with implementation schedule for all conditions stipulated. The funds
should not be diverted for any other purposes
Complied.
The funds are already provided as part of manufacturing activities and operation of ETP / Incinerator. Separate cost codes are also available.
9 Implementation of the project and
Environmental Action Plan to be monitored by MOEF, Regional Office at
Bhopal, GPCB / CPCB. A six monthly compliance report to be submitted to
monitoring agencies
Complied.
Half yearly compliance reports are being sent during first week of February and August every year to Ministry of Environment and Forests
Regional Office, Western Region, Bhopal.
10 Company to inform that public that project has been accorded
Environmental Clearance by Ministry and copies are available with GPCB and
may be seen at MOEF web site. This should be advertised within 7 days in
two local newspapers and copies to be
submitted to RO- GPCB
Complied.
Published in Gujarati and English newspapers; and copies submitted to
GPCB and MOEF.
11 Company to inform RO-GPCB as well
as Ministry, date of financial closure and final approval of the project by
concerned authorities and date of
commencing the land development work, if any
Complied.
- Ministry may revoke or suspend the clearance, if implementation of any of
the conditions is not satisfactory
Noted
All environmental parameters are being monitored and results are within limits
- Ministry reserves the right to stipulate additional conditions if required.
Company, in a time bound manner, will
implement the same
Noted
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 9 of 55
- The above conditions will be enforced
inter-alia under provisions of various acts and rules
Noted
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 10 of 55
STACK MONITORING REPORT (INTERNAL LAB ANALYSIS REPORT)
STACK MONITORING REPORT MONTH : JAN-2015
PESTICIDES AND PESTICIDE INTERMEDIATES PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20
mg/Nm3 5 mg/Nm3 30
mg/Nm3 50
mg/Nm3 20
mg/Nm3 100
mg/Nm3
TMP PLANT VENT OF 10.01.15 ------ 0.90 5.90 ------ ------ ------
1 SCRUBBER ATTACHED
TO R-901 AND R-902 20.01.15 ------ 2.00 11.00 ------ ------ ------
MANCOZEB PLANT(New) 04.01.15 ------ ------ ------ ------ 18.00 ------
2 WET SCRUBBER SPRAY
DRIER (Mojj) 21.01.15 ------ ------ ------ ------ 17.00 ------
MANCOZEB PLANT(Old) 04.01.15 ------ ------ ------ ------ 15.00 ------
3 SPD WET SCRUBBER
OUTLET ( L&T) 21.01.15 ------ ------ ------ ------ 16.00 ------
SPRAY DRIER SYSTEM 10.01.15 ------ ------ ------ ------ 16.00 ------
4 OF ANTRACOL PLANT
23.01.15 ------ ------ ------ ------ 19.00 ------
Formulation plant (ULALA) 11.01.15 ------ ------ ------ ------ 18.00 ------
5 Stack attached to VFBD
19.01.15 ------ ------ ------ ------ 16.00 ------
Formulation plant (ULALA) 11.01.15 ------ ------ ------ ------ 15.00 ------
6 Stack attached to ACM Mill
19.01.15 ------ ------ ------ ------ 12.00 ------
Sr. AREA IDENTIFICATION DATE OF HCL SO2 NH3
No. SAMPLING 20
mg/Nm3 40 mg/Nm3 30
mg/Nm3
Flonicamide Plant
scrubber, SO2 and HCL SO2 and HCL 17.01.15 11.20 7.90 ------ ------ ------ ------
1
06.01.15 7.40 9.10 ------ ------ ------ ------
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 11 of 55
Flonicamide Plant
Scrubber, Ammonia 17.01.15 ------ ------ 9.10 ------ ------ ------
2
06.01.15 ------ ------ 10.00 ------ ------ ------
OTHER CHEMICAL PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20 mg/m3 9 mg/m3 175
mg/m3 50
mg/Nm3 150
mg/m3 100
mg/Nm3
IN PCL3 PLANT STACK 10.01.15 2.60 BDL ------ ------ ------ ------
1 ATTACHED TO
STORAGE SCRUBBER 20.01.15 5.00 BDL ------ ------ ------ ------
SPRAY DRIER SYSTEM 07.01.15 ------ ------ ------ ------ 72.00 ------
2 OF CACL2 PLANT
23.01.15 ------ ------ ------ ------ 69.00 ------
STACK ATTACHED TO
3 BOILER B5 GT-3138 07.01.15 ------ ------ ------ 8.00 22.00 10.00
4 BOILER B6 GT-3476 12.01.15 ------ ------ ------ 11.00 17.00 13.00
5 BOILER B7 GT-3515 12.01.15 ------ ------ ------ 10.00 16.00 12.00
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT MONTH : FEB-2015
PESTICIDES AND PESTICIDE INTERMEDIATES PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20
mg/Nm3 5 mg/Nm3 30
mg/Nm3 50
mg/Nm3 20
mg/Nm3 100
mg/Nm3
TMP PLANT VENT OF 12.02.15 ------ 2.30 8.70 ------ ------ ------
1 SCRUBBER ATTACHED
TO R-901 AND R-902 23.02.15 ------ 1.80 9.80 ------ ------ ------
MANCOZEB PLANT(New) 09.02.15 ------ ------ ------ ------ 15.00 ------
2 WET SCRUBBER SPRAY
DRIER (Mojj) 17.02.15 ------ ------ ------ ------ 19.00 ------
MANCOZEB PLANT(Old) 09.02.15 ------ ------ ------ ------ 13.00 ------
3 SPD WET SCRUBBER
OUTLET ( L&T) 17.02.15 ------ ------ ------ ------ 16.00 ------
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 12 of 55
SPRAY DRIER SYSTEM 09.02.15 ------ ------ ------ ------ 15.00 ------
4 OF ANTRACOL PLANT
18.02.15 ------ ------ ------ ------ 18.00 ------
Formulation plant (ULALA) 12.02.15 ------ ------ ------ ------ 14.00 ------
5 Stack attached to VFBD
23.02.15 ------ ------ ------ ------ 17.00 ------
Formulation plant (ULALA) 12.02.15 ------ ------ ------ ------ 13.00 ------
6 Stack attached to ACM Mill
23.02.15 ------ ------ ------ ------ 14.00 ------
Sr. AREA IDENTIFICATION DATE OF HCL SO2 NH3
No. SAMPLING 20
mg/Nm3 40 mg/Nm3 30
mg/Nm3
Flonicamide Plant
scrubber, SO2 and HCL SO2 and HCL 12.02.15 9.70 6.20 ------ ------ ------ ------
1
21.02.15 10.20 7.80 ------ ------ ------ ------
Flonicamide Plant
Scrubber, Ammonia 12.02.15 ------ ------ 13.20 ------ ------ ------
2
21.02.15 ------ ------ 10.70 ------ ------ ------
OTHER CHEMICAL PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20 mg/m3 9 mg/m3 175
mg/m3 50
mg/Nm3 150
mg/m3 100
mg/Nm3
IN PCL3 PLANT STACK 12.02.15 3.10 BDL ------ ------ ------ ------
1 ATTACHED TO
STORAGE SCRUBBER 23.02.15 2.80 BDL ------ ------ ------ ------
SPRAY DRIER SYSTEM 16.02.15 ------ ------ ------ ------ 79.00 ------
2 OF CACL2 PLANT
23.02.15 ------ ------ ------ ------ 71.00 ------
STACK ATTACHED TO
3 BOILER B5 GT-3138 16.02.15 ------ ------ ------ 22.00 89.00 28.00
4 BOILER B6 GT-3476 16.02.15 ------ ------ ------ 8.00 16.00 10.00
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 13 of 55
5 BOILER B7 GT-3515 16.02.15 ------ ------ ------ 8.00 11.00 14.00
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT MONTH : MAR-2015
PESTICIDES AND PESTICIDE INTERMEDIATES PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20
mg/Nm3 5 mg/Nm3 30
mg/Nm3 50
mg/Nm3 20
mg/Nm3 100
mg/Nm3
TMP PLANT VENT OF 05.03.15 ------ 0.90 9.10 ------ ------ ------
1 SCRUBBER ATTACHED
TO R-901 AND R-902 18.03.15 ------ 1.50 7.30 ------ ------ ------
MANCOZEB PLANT(New) 16.03.15 ------ ------ ------ ------ 17.00 ------
2 WET SCRUBBER SPRAY
DRIER (Mojj) 18.03.15 ------ ------ ------ ------ 18.00 ------
MANCOZEB PLANT(Old) 16.03.15 ------ ------ ------ ------ 14.00 ------
3 SPD WET SCRUBBER
OUTLET ( L&T) 21.03.15 ------ ------ ------ ------ 16.00 ------
SPRAY DRIER SYSTEM 06.03.15 ------ ------ ------ ------ 19.00 ------
4 OF ANTRACOL PLANT
21.03.15 ------ ------ ------ ------ 15.00 ------
Formulation plant (ULALA) 03.03.15 ------ ------ ------ ------ 12.00 ------
5 Stack attached to VFBD
26.03.15 ------ ------ ------ ------ 14.00 ------
Formulation plant (ULALA) 03.03.15 ------ ------ ------ ------ 15.00 ------
6 Stack attached to ACM Mill
26.03.15 ------ ------ ------ ------ 13.00 ------
Sr. AREA IDENTIFICATION DATE OF HCL SO2 NH3
No. SAMPLING 20
mg/Nm3 40 mg/Nm3 30
mg/Nm3
Flonicamide Plant
scrubber, SO2 and HCL SO2 and HCL 04.03.15 6.50 7.10 ------ ------ ------ ------
1
17.03.15 7.30 9.80 ------ ------ ------ ------
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 14 of 55
Flonicamide Plant
Scrubber, Ammonia 04.03.15 ------ ------ 8.30 ------ ------ ------
2
20.03.15 ------ ------ 10.00 ------ ------ ------
OTHER CHEMICAL PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20 mg/m3 9 mg/m3 175
mg/m3 50
mg/Nm3 150
mg/m3 100
mg/Nm3
IN PCL3 PLANT STACK 05.03.15 2.60 BDL ------ ------ ------ ------
1 ATTACHED TO
STORAGE SCRUBBER 18.03.15 1.90 BDL ------ ------ ------ ------
SPRAY DRIER SYSTEM 05.03.15 ------ ------ ------ ------ 76.00 ------
2 OF CACL2 PLANT
17.03.15 ------ ------ ------ ------ 69.00 ------
STACK ATTACHED TO
3 BOILER B5 GT-3138 20.03.15 ------ ------ ------ 24.00 82.00 26.00
4 BOILER B6 GT-3476 21.03.15 ------ ------ ------ 11.00 15.00 9.00
5 BOILER B7 GT-3515 21.03.15 ------ ------ ------ 12.00 16.00 6.00
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT MONTH : APR-2015
PESTICIDES AND PESTICIDE INTERMEDIATES PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20
mg/Nm3 5 mg/Nm3 30
mg/Nm3 50
mg/Nm3 20
mg/Nm3 100
mg/Nm3
TMP PLANT VENT OF 09.04.15 ------ 1.70 8.10 ------ ------ ------
1 SCRUBBER ATTACHED
TO R-901 AND R-902 22.04.15 ------ 3.00 10.00 ------ ------ ------
MANCOZEB PLANT(New) 16.04.15 ------ ------ ------ ------ 18.00 ------
2 WET SCRUBBER SPRAY
DRIER (Mojj) 25.04.15 ------ ------ ------ ------ 16.00 ------
MANCOZEB PLANT(Old) 16.04.15 ------ ------ ------ ------ 15.00 ------
3 SPD WET SCRUBBER
OUTLET ( L&T) 25.04.15 ------ ------ ------ ------ 16.00 ------
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 15 of 55
SPRAY DRIER SYSTEM 08.04.15 ------ ------ ------ ------ 17.00 ------
4 OF ANTRACOL PLANT
27.04.15 ------ ------ ------ ------ 19.00 ------
Formulation plant (ULALA) 08.04.15 ------ ------ ------ ------ 14.00 ------
5 Stack attached to VFBD
24.04.15 ------ ------ ------ ------ 12.00 ------
Formulation plant (ULALA) 08.04.15 ------ ------ ------ ------ 17.00 ------
6 Stack attached to ACM Mill
24.04.15 ------ ------ ------ ------ 15.00 ------
Sr. AREA IDENTIFICATION DATE OF HCL SO2 NH3
No. SAMPLING 20
mg/Nm3 40 mg/Nm3 30
mg/Nm3
Flonicamide Plant
scrubber, SO2 and HCL SO2 and HCL 08.04.15 5.20 11.20 ------ ------ ------ ------
1
20.04.15 4.30 14.30 ------ ------ ------ ------
Flonicamide Plant
Scrubber, Ammonia 08.04.15 ------ ------ 8.70 ------ ------ ------
2
20.04.15 ------ ------ 15.00 ------ ------ ------
OTHER CHEMICAL PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20 mg/m3 9 mg/m3 175
mg/m3 50
mg/Nm3 150
mg/m3 100
mg/Nm3
IN PCL3 PLANT STACK 09.04.15 2.90 BDL ------ ------ ------ ------
1 ATTACHED TO
STORAGE SCRUBBER 22.04.15 5.00 BDL ------ ------ ------ ------
SPRAY DRIER SYSTEM 10.04.15 ------ ------ ------ ------ 77.00 ------
2 OF CACL2 PLANT
26.04.15 ------ ------ ------ ------ 69.00 ------
STACK ATTACHED TO
3 BOILER B5 GT-3138 15.04.15 ------ ------ ------ 20.00 88.00 25.00
4 BOILER B6 GT-3476 15.04.15 ------ ------ ------ 10.00 16.00 8.00
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 16 of 55
5 BOILER B7 GT-3515 15.04.15 ------ ------ ------ 12.00 18.00 10.00
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT MONTH : MAY-2015
PESTICIDES AND PESTICIDE INTERMEDIATES PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20
mg/Nm3 5 mg/Nm3 30
mg/Nm3 50
mg/Nm3 20
mg/Nm3 100
mg/Nm3
TMP PLANT VENT OF 08.05.15 ------ 1.30 7.20 ------ ------ ------
1 SCRUBBER ATTACHED
TO R-901 AND R-902 18.05.15 ------ 2.80 8.00 ------ ------ ------
MANCOZEB PLANT(New) 16.05.15 ------ ------ ------ ------ 18.00 ------
2 WET SCRUBBER SPRAY
DRIER (Mojj) 27.05.15 ------ ------ ------ ------ 16.00 ------
MANCOZEB PLANT(Old) 16.05.15 ------ ------ ------ ------ 17.00 ------
3 SPD WET SCRUBBER
OUTLET ( L&T) 27.05.15 ------ ------ ------ ------ 19.00 ------
SPRAY DRIER SYSTEM 14.05.15 ------ ------ ------ ------ 15.00 ------
4 OF ANTRACOL PLANT
21.05.15 ------ ------ ------ ------ 19.00 ------
Formulation plant (ULALA) 04.05.15 ------ ------ ------ ------ 13.00 ------
5 Stack attached to VFBD
20.05.15 ------ ------ ------ ------ 16.00 ------
Formulation plant (ULALA) 04.05.15 ------ ------ ------ ------ 15.00 ------
6 Stack attached to ACM Mill
20.05.15 ------ ------ ------ ------ 12.00 ------
Sr. AREA IDENTIFICATION DATE OF HCL SO2 NH3
No. SAMPLING 20
mg/Nm3 40 mg/Nm3 30
mg/Nm3
Flonicamide Plant Plant shut down
scrubber, SO2 and HCL SO2 and HCL 01.05.15 to 18.05.15 ------ ------ ------ ------ ------ ------
1
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 17 of 55
24.05.15 4.30 8.10 ------ ------ ------ ------
Flonicamide Plant Plant shut down
Scrubber, Ammonia 01.05.15 to 18.05.15 ------ ------ ------ ------ ------ ------
2
24.05.15 ------ ------ 6.10 ------ ------ ------
OTHER CHEMICAL PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20 mg/m3 9 mg/m3 175
mg/m3 50
mg/Nm3 150
mg/m3 100
mg/Nm3
IN PCL3 PLANT STACK 08.05.15 2.20 BDL ------ ------ ------ ------
1 ATTACHED TO
STORAGE SCRUBBER 18.05.15 4.00 BDL ------ ------ ------ ------
SPRAY DRIER SYSTEM 15.05.15 ------ ------ ------ ------ 87.00 ------
2 OF CACL2 PLANT
27.05.15 ------ ------ ------ ------ 70.00 ------
STACK ATTACHED TO
3 BOILER B5 GT-3138 20.05.15 ------ ------ ------ 17.00 19.00 16.00
4 BOILER B6 GT-3476 20.05.15 ------ ------ ------ 11.00 17.00 12.00
5 BOILER B7 GT-3515 20.05.15 ------ ------ ------ 13.00 16.00 10.00
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT MONTH : JUN-2015
PESTICIDES AND PESTICIDE INTERMEDIATES PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20
mg/Nm3 5 mg/Nm3 30
mg/Nm3 50
mg/Nm3 20
mg/Nm3 100
mg/Nm3
TMP PLANT VENT OF 08.06.15 ------ 1.60 8.30 ------ ------ ------
1 SCRUBBER ATTACHED
TO R-901 AND R-902 25.06.15 ------ 2.10 10.00 ------ ------ ------
MANCOZEB PLANT(New) 07.06.15 ------ ------ ------ ------ 17.00 ------
2 WET SCRUBBER SPRAY
DRIER (Mojj) 23.06.15 ------ ------ ------ ------ 14.00 ------
MANCOZEB PLANT(Old) 07.06.15 ------ ------ ------ ------ 18.00 ------
3 SPD WET SCRUBBER
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 18 of 55
OUTLET ( L&T) 23.06.15 ------ ------ ------ ------ 17.00 ------
SPRAY DRIER SYSTEM 13.06.15 ------ ------ ------ ------ 18.00 ------
4 OF ANTRACOL PLANT
24.06.15 ------ ------ ------ ------ 15.00 ------
Formulation plant (ULALA) 18.06.15 ------ ------ ------ ------ 12.00 ------
5 Stack attached to VFBD
23.06.15 ------ ------ ------ ------ 14.00 ------
Formulation plant (ULALA) 18.06.15 ------ ------ ------ ------ 17.00 ------
6 Stack attached to ACM Mill
23.06.15 ------ ------ ------ ------ 14.00 ------
Sr. AREA IDENTIFICATION DATE OF HCL SO2 NH3
No. SAMPLING 20
mg/Nm3 40 mg/Nm3 30
mg/Nm3
Flonicamide Plant
scrubber, SO2 and HCL SO2 and HCL 08.06.15 3.30 6.50 ------ ------ ------ ------
1
18.06.15 2.90 8.10 ------ ------ ------ ------
Flonicamide Plant
Scrubber, Ammonia 08.06.15 ------ ------ 7.80 ------ ------ ------
2
18.06.15 ------ ------ 5.60 ------ ------ ------
OTHER CHEMICAL PLANT :
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 20 mg/m3 9 mg/m3 175
mg/m3 50
mg/Nm3 150
mg/m3 100
mg/Nm3
IN PCL3 PLANT STACK 08.06.15 2.20 BDL ------ ------ ------ ------
1 ATTACHED TO
STORAGE SCRUBBER 25.06.15 3.00 BDL ------ ------ ------ ------
SPRAY DRIER SYSTEM 13.06.15 ------ ------ ------ ------ 76.00 ------
2 OF CACL2 PLANT
28.06.15 ------ ------ ------ ------ 82.00 ------
STACK ATTACHED TO
3 BOILER B5 GT-3138 08.06.15 ------ ------ ------ 13.00 20.00 8.00
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 19 of 55
4 BOILER B6 GT-3476 17.06.15 ------ ------ ------ 14.00 15.00 10.00
5 BOILER B7 GT-3515 08.06.15 ------ ------ ------ 15.00 22.00 12.00
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT (SIDDHI CONSULTANTS ANALYSIS REPORT)
MONTH: JAN 2015
PESTICIDES AND PESTICIDES INTERMEDIATES PLANT:
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20 mg/m3
5 mg/m3 30 mg/m3
50 mg/m3
20 mg/m3 100 mg/m3
TMP PLANT VENT OF
1 SCRUBBER ATTACHED 12.01.2015 2 11
TO R-901 AND R-902
MANCOZEB PLANT(OLD) 13.01.2015 15
2 WET SCRUBBER SPRAY
DRIER
MANCOZEB PLANT(NEW) 13.01.2015 18
3 SPD WET SCRUBBER
OUTLET
ANTRACOLPLANT (BAG FILTER)
13.01.2015
13
16
17
15
4
ANTRACOL PLANT (HOT AIR GENERATOR)
13.01.2015
5 IKI Plant (attached to water scrubber)
12.01.2015 10
6 Formulation Plant (attached to Bag Filter)
13.01.2015 18
OTHER CHEMICAL PLANT
Sr. AREA IDENTIFICATION DATE OF HCl CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 09 mg/m3
9 mg/m3 175 mg/m3
50 PPM 150 mg/m3
100 PPM
STACK ATTACHED TO
BOILER B5 GT-3138 12.01.2015 8 22 10
5
BOILER B6 GT-3476 12.01.2015 10 16 12
BOILER B7 GT-3515 12.01.2015 10 16 12
SPRAY DRYER SYSTEM OF CACL2 PLANT
13.01.2015
69
6
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 20 of 55
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20 mg/m3
5 mg/m3 30 mg/m3
50 mg/m3
20 mg/m3 100 mg/m3
IN PCL3 PLANT STACK ATTACHED TO
STORAGE SCRUBBER
7 12.01.2015 5 BDL
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT: (SIDDHI CONSULTANT ANALYSIS REPORT)
MONTH: FEB 2015 PESTICIDES AND PESTICIDES INTERMEDIATES PLANT:
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
TMP PLANT VENT OF
1 SCRUBBER ATTACHED 16.02.2015 3 10
TO R-901 AND R-902
MANCOZEB PLANT(OLD) 16.02.2015 18
2 WET SCRUBBER SPRAY
DRIER
MANCOZEB PLANT(NEW) 16.02.2015 16
3 SPD WET SCRUBBER
OUTLET
4
ANTRACOLPLANT (BAG FILTER) ANTRACOL PLANT (HOT AIR GENERATOR)
16.02.2015
8
19
16
10
17.02.2015
5 FORMULATION PLANT BAG FILTER
6
IKI Plant (attached to water scrubber)
17.02.2015 18
OTHER CHEMICAL PLANT
Sr. AREA IDENTIFICATION DATE OF HCl CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 09
mg/m3 9 mg/m3 175
mg/m3 50 PPM 150
mg/m3 100 PPM
STACK ATTACHED TO
BOILER B5 GT-3138 16.02.2015 22 89 28
6
BOILER B6 GT-3476 16.02.2015 10 18 12
BOILER B7 GT-3515 16.02.2015 8 14 11
SPRAY DRYER SYSTEM OF CACL2 PLANT
71
7 16.02.2015
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 21 of 55
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
IN PCL3 PLANT STACK ATTACHED TO STORAGE SCRUBBER
8 16.02.2015 4 BDL
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT :( SIDDHI GREEN EXCELLENCE P LTD ANALYSIS REPORT)
MONTH: MARCH 2015 PESTICIDES AND PESTICIDES INTERMEDIATES PLANT:
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
TMP PLANT VENT OF
1 SCRUBBER ATTACHED 20.03.2015 2 9
TO R-901 AND R-902
MANCOZEB PLANT(OLD)
2 WET SCRUBBER SPRAY
DRIER
MANCOZEB PLANT(NEW)
3 SPD WET SCRUBBER
OUTLET
ANTRACOLPLANT (BAG FILTER)
20.03.2015
9
16
18
12
4
ANTRACOL PLANT (HOT AIR GENERATOR) 20.03.2015
OTHER CHEMICAL PLANT
Sr. AREA IDENTIFICATION DATE OF HCl CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 09
mg/m3 9 mg/m3 175
mg/m3 50 PPM 150
mg/m3 100 PPM
STACK ATTACHED TO
BOILER B5 GT-3138 21.03.2015 24 82 26
5
BOILER B6 GT-3476 21.03.2015 12 16 6
BOILER B7 GT-3515 21.03.2015 12 16 6
SPRAY DRYER SYSTEM OF CACL2 PLANT
68 6 20.03.2015
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 22 of 55
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
IN PCL3 PLANT STACK ATTACHED TO STORAGE SCRUBBER
7 20.03.2015 6 BDL
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT: (SIDDHI GREEN EXCELLENCE P LTD ANALYSIS REPORT)
MONTH: APRIL 2015 PESTICIDES AND PESTICIDES INTERMEDIATES PLANT:
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
TMP PLANT VENT OF 14.04.2015 3 10
1 SCRUBBER ATTACHED
TO R-901 AND R-902
MANCOZEB PLANT(OLD) 15.04.2015 16
2 WET SCRUBBER SPRAY
DRIER
MANCOZEB PLANT(NEW)
3 SPD WET SCRUBBER
OUTLET
ANTRACOLPLANT (BAG FILTER)
4
ANTRACOL PLANT (HOT AIR GENERATOR)
5 IKI Plant (attached to water scrubber)
14.04.2015 15
OTHER CHEMICAL PLANT
Sr. AREA IDENTIFICATION DATE OF HCl CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 09
mg/m3 9 mg/m3 175
mg/m3 50 PPM 150
mg/m3 100 PPM
STACK ATTACHED TO
BOILER B5 GT-3138
5
BOILER B6 GT-3476 15.04.2015 10 16 8
BOILER B7 GT-3515 15.04.2015 12 18 10
SPRAY DRYER SYSTEM OF CACL2 PLANT
69 6 14.04.2015
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 23 of 55
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
IN PCL3 PLANT STACK ATTACHED TO STORAGE SCRUBBER
10.04.2015 5 BDL
7
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT: (SIDDHI GREEN EXCELLENCE P LTD ANALYSIS REPORT)
MONTH: MAY 2015 PESTICIDES AND PESTICIDES INTERMEDIATES PLANT:
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
TMP PLANT VENT OF
1 SCRUBBER ATTACHED 20.05.2015 4 8
TO R-901 AND R-902
MANCOZEB PLANT(OLD) 21.05.2015 15
2 WET SCRUBBER SPRAY
DRIER
MANCOZEB PLANT(NEW) 21.05.2015 17
3 SPD WET SCRUBBER
OUTLET
ANTRACOLPLANT (BAG FILTER)
21.05.2015
8
18
15
10
4
ANTRACOL PLANT (HOT AIR GENERATOR) 20.05.2015
5 FORMULATION PLANT BAG FILTER
6 IKI PLANT STACK ATTACHED TO WATER SCRUBBER
OTHER CHEMICAL PLANT
Sr. AREA IDENTIFICATION DATE OF HCl CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 09
mg/m3 9 mg/m3 175
mg/m3 50 PPM 150
mg/m3 100 PPM
STACK ATTACHED TO
BOILER B5 GT-3138 20.05.2015 21 82 24
5
BOILER B6 GT-3476 21.05.2015 12 17 11
BOILER B7 GT-3515 20.05.2015 13 16 10
SPRAY DRYER SYSTEM OF CACL2 PLANT
71
6 20.05.2015
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 24 of 55
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
IN PCL3 PLANT STACK ATTACHED TO STORAGE SCRUBBER
7 20.05.2015 4 BDL
ALL THE PARAMETERS ARE WITHIN THE LIMITS
STACK MONITORING REPORT: (SIDDHI GREEN EXCELLENCE P LTD ANALYSIS REPORT)
MONTH: JUNE 2015 PESTICIDES AND PESTICIDES INTERMEDIATES PLANT:
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
TMP PLANT VENT OF
1 SCRUBBER ATTACHED 08.06.2015 3 10
TO R-901 AND R-902
MANCOZEB PLANT(OLD) 08.06.2015 16
2 WET SCRUBBER SPRAY
DRIER
MANCOZEB PLANT(NEW)
3 SPD WET SCRUBBER
OUTLET
ANTRACOLPLANT (BAG FILTER)
08.06.2015
16
15
20
12 4
ANTRACOL PLANT (HOT AIR GENERATOR)
08.06.2015
5 FORMULATION PLANT BAG FILTER
6 IKI PLANT STACK ATTACHED TO WATER SCRUBBER
OTHER CHEMICAL PLANT
Sr. AREA IDENTIFICATION DATE OF HCl CHLORINE NH3 NOX SPM SO2
No. (STACK) SAMPLING 09
mg/m3 9 mg/m3 175
mg/m3 50 PPM 150
mg/m3 100 PPM
STACK ATTACHED TO
BOILER B5 GT-3138 09.06.2015 13 20 8
7
BOILER B6 GT-3476
BOILER B7 GT-3515 09.06.2015 15 22 12
SPRAY DRYER SYSTEM 09.06.2015 76
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 25 of 55
Sr. AREA IDENTIFICATION DATE OF HCL CHLORINE NH3 NOx SPM SO2
No. (STACK) SAMPLING 20
mg/m3 5 mg/m3 30
mg/m3 50
mg/m3 20
mg/m3 100
mg/m3
8 OF CACL2 PLANT
IN PCL3 PLANT STACK ATTACHED TO STORAGE SCRUBBER
9 08.06.2015 3 BDL
ALL THE PARAMETERS ARE WITHIN THE LIMITS
AMBIENT AIR MONITORING (OUR INTERNAL LAB ANALYSIS REPORTS)
AMBIENT AIR MONITORING REPORT
MONTH : JAN-2015
PM 2.5 PM 10 AMMONIA CL2 HCL NOX SO2
LIMITS --> 60 100 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
NEAR MAIN GATE 03.01.15 -- 72 BDL BDL 5 -- 3
NEAR MAIN GATE 06.01.15 49 75 5 BDL 3 4 --
NEAR MAIN GATE 09.01.15 -- 79 2 BDL BDL -- 5
NEAR MAIN GATE 12.01.15 41 84 3 BDL BDL 4 --
NEAR MAIN GATE 15.01.15 -- 74 BDL BDL 3 -- 3
NEAR MAIN GATE 17.01.15 52 72 BDL BDL BDL 5 --
NEAR MAIN GATE 19.01.15 -- 81 3 BDL 4 -- 3
NEAR MAIN GATE 23.01.15 47 78 3 BDL 4 3 --
NEAR MAIN GATE 25.01.15 -- 82 BDL BDL BDL -- 4
NEAR MAIN GATE 28.01.15 -- 76 4 BDL 3 4 --
Maximum 52 84 5 BDL 5 5 5
Minimum 41 72 BDL BDL BDL 3 3
Average 47 77 3 BDL 4 4 4
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : JAN-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H CACL2 PLANT 03.01.15 81 213 17 BDL 3 -- 17
B/H CACL2 PLANT 06.01.15 76 210 15 6 8 13 --
B/H CACL2 PLANT 09.01.15 67 187 19 4 8 -- 15
B/H CACL2 PLANT 12.01.15 85 193 23 BDL 6 16 --
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 26 of 55
B/H CACL2 PLANT 15.01.15 82 204 14 BDL 5 -- 14
B/H CACL2 PLANT 17.01.15 80 213 19 3 7 12 --
B/H CACL2 PLANT 19.01.15 67 209 12 2 9 -- 13
B/H CACL2 PLANT 23.01.15 71 201 14 5 5 13 --
B/H CACL2 PLANT 25.01.15 80 198 22 BDL 7 -- 14
B/H CACL2 PLANT 28.01.15 74 206 19 4 5 11 --
Maximum 85 213 23 6 9 16 17
Minimum 67 187 12 BDL 3 11 13
Average 76 203 17 4 6 13 15
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : JAN-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H BREQUATING PLANT 03.01.15 87 209 9 BDL BDL -- 16
B/H BREQUATING PLANT 06.01.15 84 203 8 5 8 13 --
B/H BREQUATING PLANT 09.01.15 72 189 7 2 3 -- 17
B/H BREQUATING PLANT 12.01.15 90 221 11 3 11 11 --
B/H BREQUATING PLANT 15.01.15 68 204 6 BDL 5 -- 15
B/H BREQUATING PLANT 17.01.15 87 207 9 BDL 5 14 --
B/H BREQUATING PLANT 19.01.15 82 196 10 4 BDL -- 14
B/H BREQUATING PLANT 23.01.15 79 201 12 3 7 16 --
B/H BREQUATING PLANT 25.01.15 85 207 8 BDL 7 -- 16
B/H BREQUATING PLANT 28.01.15 76 178 6 5 9 14 --
Maximum 90 221 12 5 11 16 17
Minimum 68 178 6 BDL BDL 11 14
Average 81 202 9 4 7 14 16
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : FEB-2015
PM 2.5 PM 10 AMMONIA CL2 HCL NOX SO2
LIMITS --> 60 100 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
NEAR MAIN GATE 02.02.15 -- 71 BDL BDL 3 2 --
NEAR MAIN GATE 05.02.15 -- 81 3 BDL BDL -- 4
NEAR MAIN GATE 07.02.15 43 78 4 BDL BDL 3 --
NEAR MAIN GATE 10.02.15 -- 69 BDL BDL 5 -- 4
NEAR MAIN GATE 13.02.15 48 83 BDL BDL 3 4 --
NEAR MAIN GATE 17.02.15 -- 80 5 BDL BDL -- 5
NEAR MAIN GATE 20.02.15 52 72 2 BDL BDL 5 --
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 27 of 55
NEAR MAIN GATE 22.02.15 -- 76 4 BDL 4 -- 3
NEAR MAIN GATE 24.02.15 47 89 3 BDL 2 2 --
NEAR MAIN GATE 26.02.15 -- 85 3 BDL 3 -- 4
Maximum 52 89 5 BDL 5 5 5
Minimum 43 69 BDL BDL BDL 2 3
Average 48 78 3 BDL 3 3 4
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : FEB-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H CACL2 PLANT 02.02.15 69 176 15 BDL 7 13 --
B/H CACL2 PLANT 05.02.15 76 190 10 4 9 -- 12
B/H CACL2 PLANT 07.02.15 81 182 12 4 12 15 --
B/H CACL2 PLANT 10.02.15 72 207 13 BDL 7 -- 18
B/H CACL2 PLANT 13.02.15 87 202 9 3 9 11 --
B/H CACL2 PLANT 17.02.15 80 192 7 6 10 -- 14
B/H CACL2 PLANT 20.02.15 76 178 14 3 14 17 --
B/H CACL2 PLANT 22.02.15 74 181 12 BDL 12 -- 19
B/H CACL2 PLANT 24.02.15 79 187 11 4 10 12 --
B/H CACL2 PLANT 26.02.15 81 172 10 3 8 -- 16
Maximum 87 207 15 6 14 17 19
Minimum 69 172 7 BDL 7 11 12
Average 78 187 11 4 10 14 16
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : FEB-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H BREQUATING PLANT 02.02.15 73 207 7 4 4 9 --
B/H BREQUATING PLANT 05.02.15 81 198 11 BDL BDL -- 12
B/H BREQUATING PLANT 07.02.15 75 214 12 6 7 11 --
B/H BREQUATING PLANT 10.02.15 70 203 5 3 4 -- 15
B/H BREQUATING PLANT 13.02.15 80 197 8 4 5 13 --
B/H BREQUATING PLANT 17.02.15 83 188 7 BDL BDL -- 11
B/H BREQUATING PLANT 20.02.15 72 184 7 3 9 13 --
B/H BREQUATING PLANT 22.02.15 78 199 10 BDL 3 -- 12
B/H BREQUATING PLANT 24.02.15 70 192 9 3 7 11 --
B/H BREQUATING PLANT 26.02.15 81 202 6 BDL BDL -- 13
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 28 of 55
Maximum 83 214 12 6 9 13 15
Minimum 70 184 5 BDL BDL 9 11
Average 76 198 8 4 6 11 13
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : MAR-2015
PM 2.5 PM 10 AMMONIA CL2 HCL NOX SO2
LIMITS --> 60 100 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
NEAR MAIN GATE 03.03.15 -- 76 3 BDL BDL -- 4
NEAR MAIN GATE 06.03.15 46 81 5 BDL 2 5 --
NEAR MAIN GATE 09.03.15 -- 89 BDL BDL BDL -- 3
NEAR MAIN GATE 11.03.15 -- 72 2 BDL 4 3 --
NEAR MAIN GATE 16.03.15 39 74 3 BDL BDL -- 4
NEAR MAIN GATE 18.03.15 -- 81 BDL BDL 5 3 --
NEAR MAIN GATE 20.03.15 53 89 BDL BDL BDL -- 3
NEAR MAIN GATE 22.03.15 -- 93 3 BDL 3 5 --
NEAR MAIN GATE 24.03.15 42 78 3 BDL 2 -- 3
NEAR MAIN GATE 27.03.15 -- 76 BDL BDL BDL 4 --
Maximum 53 93 5 BDL 5 5 4
Minimum 39 72 BDL BDL BDL 3 3
Average 45 81 3 BDL 3 4 3
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : APR-2015
PM 2.5 PM 10 AMMONIA CL2 HCL NOX SO2
LIMITS --> 60 100 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
NEAR MAIN GATE 04.04.15 43 78 3 BDL BDL 4 --
NEAR MAIN GATE 07.04.15 -- 71 2 BDL 4 -- 3
NEAR MAIN GATE 10.04.15 49 83 BDL BDL 3 6 --
NEAR MAIN GATE 12.04.15 -- 88 2 BDL BDL -- 4
NEAR MAIN GATE 15.04.15 -- 76 BDL BDL 4 3 --
NEAR MAIN GATE 18.04.15 37 90 BDL BDL BDL -- 3
NEAR MAIN GATE 22.04.15 51 81 4 BDL 2 4 --
NEAR MAIN GATE 24.04.15 -- 85 BDL BDL BDL -- 2
NEAR MAIN GATE 26.04.15 -- 78 2 BDL 3 4 --
NEAR MAIN GATE 28.04.15 -- 76 BDL BDL BDL -- 4
Maximum 51 90 4 BDL 4 6 4
Minimum 37 71 BDL BDL BDL 3 2
Average 45 81 3 BDL 3 4 3
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 29 of 55
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : APR-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H CACL2 PLANT 04.04.15 86 213 9 2 10 20 --
B/H CACL2 PLANT 07.04.15 70 204 7 BDL 7 -- 16
B/H CACL2 PLANT 10.04.15 73 186 12 4 13 15 --
B/H CACL2 PLANT 12.04.15 76 190 10 3 6 -- 14
B/H CACL2 PLANT 15.04.15 83 183 7 BDL 5 17 --
B/H CACL2 PLANT 18.04.15 81 195 14 2 9 -- 19
B/H CACL2 PLANT 22.04.15 90 208 8 3 11 13 --
B/H CACL2 PLANT 24.04.15 87 202 10 BDL 13 -- 13
B/H CACL2 PLANT 26.04.15 78 185 12 2 7 12 --
B/H CACL2 PLANT 28.04.15 83 181 9 3 6 -- 12
Maximum 90 213 14 4 13 20 19
Minimum 70 181 7 BDL 5 12 12
Average 81 195 10 3 9 15 15
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : APR-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H BREQUATING PLANT 04.04.15 88 203 7 6 4 14 --
B/H BREQUATING PLANT 07.04.15 67 206 9 BDL 8 -- 16
B/H BREQUATING PLANT 10.04.15 78 176 10 4 3 9 --
B/H BREQUATING PLANT 12.04.15 80 172 4 3 2 -- 14
B/H BREQUATING PLANT 15.04.15 75 183 6 BDL BDL 11 --
B/H BREQUATING PLANT 18.04.15 72 193 9 2 6 -- 19
B/H BREQUATING PLANT 22.04.15 89 209 6 3 5 13 --
B/H BREQUATING PLANT 24.04.15 81 169 8 BDL BDL -- 12
B/H BREQUATING PLANT 26.04.15 73 201 6 3 5 10 --
B/H BREQUATING PLANT 28.04.15 76 193 4 4 3 -- 16
Maximum 89 209 10 6 8 14 19
Minimum 67 169 4 BDL BDL 9 12
Average 78 191 7 4 5 11 15
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 30 of 55
AMBIENT AIR MONITORING REPORT
MONTH : MAY-2015
PM 2.5 PM 10 AMMONIA CL2 HCL NOX SO2
LIMITS --> 60 100 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
NEAR MAIN GATE 02.05.15 41 86 BDL BDL BDL 3 --
NEAR MAIN GATE 05.05.15 -- 79 2 BDL 3 -- 4
NEAR MAIN GATE 08.05.15 -- 72 BDL BDL BDL 5 --
NEAR MAIN GATE 11.05.15 48 82 3 BDL 3 -- 3
NEAR MAIN GATE 14.05.15 -- 85 BDL BDL BDL 3 --
NEAR MAIN GATE 16.05.15 52 89 BDL BDL 2 -- 2
NEAR MAIN GATE 19.05.15 -- 76 3 BDL BDL 2 --
NEAR MAIN GATE 23.05.15 46 84 3 BDL BDL -- 4
NEAR MAIN GATE 26.05.15 -- 81 BDL BDL 3 4 --
NEAR MAIN GATE 29.05.15 -- 85 BDL BDL BDL -- 3
Maximum 52 89 3 BDL 3 5 4
Minimum 41 72 BDL BDL BDL 2 2
Average 47 82 3 BDL 3 3 3
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : MAY-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H CACL2 PLANT 02.05.15 89 207 15 2.00 12 16 --
B/H CACL2 PLANT 05.05.15 72 201 9 BDL 9 -- 14
B/H CACL2 PLANT 08.05.15 71 210 7 BDL 13 18 --
B/H CACL2 PLANT 11.05.15 78 190 11 2.00 8 -- 18
B/H CACL2 PLANT 14.05.15 81 217 14 BDL 11 14 --
B/H CACL2 PLANT 16.05.15 91 210 17 BDL 14 -- 11
B/H CACL2 PLANT 19.05.15 86 192 12 2.00 8 12 --
B/H CACL2 PLANT 23.05.15 83 198 14 3.00 11 -- 15
B/H CACL2 PLANT 26.05.15 79 186 9 BDL 10 13 --
B/H CACL2 PLANT 29.05.15 84 203 11 BDL 13 -- 10
Maximum 91 217 17 3 14 18 18
Minimum 71 186 7 BDL 8 12 10
Average 81 201 12 2 11 15 14
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 31 of 55
AMBIENT AIR MONITORING REPORT
MONTH : MAY-2015
PM 10 SPM AMMONIA CL2 HCL NOX SO2
LIMITS --> 100 500 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
B/H BREQUATING PLANT 02.05.15 82 181 9 3.00 2 14 --
B/H BREQUATING PLANT 05.05.15 76 202 6 BDL 5 -- 13
B/H BREQUATING PLANT 08.05.15 70 194 7 BDL 4 10 --
B/H BREQUATING PLANT 11.05.15 90 162 7 4.00 3 -- 16
B/H BREQUATING PLANT 14.05.15 80 171 5 2.00 7 17 --
B/H BREQUATING PLANT 16.05.15 83 175 6 2.00 2 -- 12
B/H BREQUATING PLANT 19.05.15 74 206 8 BDL 3 12 --
B/H BREQUATING PLANT 23.05.15 81 189 7 BDL 4 -- 14
B/H BREQUATING PLANT 26.05.15 86 188 5 BDL 6 11 --
B/H BREQUATING PLANT 29.05.15 79 195 7 BDL 4 -- 12
Maximum 90 206 9 4 7 17 16
Minimum 70 162 5 BDL BDL 10 12
Average 80 186 7 3 4 13 13
%Deviation Nil Nil Nil Nil Nil Nil Nil
All the parameters are within the limits
AMBIENT AIR MONITORING REPORT
MONTH : JUN-2015
PM 2.5 PM 10 AMMONIA CL2 HCL NOX SO2
LIMITS --> 60 100 400 100 200 80 80
Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3 Microg/m3
LOCATION DATE
NEAR MAIN GATE 02.06.15 54 87 BDL BDL 2 4 --
NEAR MAIN GATE 05.06.15 -- 76 BDL BDL BDL -- 3
NEAR MAIN GATE 08.06.15 -- 83 3 BDL 3 3 --
NEAR MAIN GATE 12.06.15 46 81 2 BDL BDL -- 4
NEAR MAIN GATE 15.06.15 -- 85 BDL BDL 2 2 --
NEAR MAIN GATE 18.06.15 50 76 2 BDL 3 -- 2
NEAR MAIN GATE 21.06.15 -- 80 BDL BDL BDL 5 --
NEAR MAIN GATE 24.06.15 42 71 BDL BDL 2 -- 3
NEAR MAIN GATE 26.06.15 -- 69 2 BDL BDL 3 --
NEAR MAIN GATE 29.06.15 -- 86 BDL BDL BDL -- 4
Maximum 54 87 3 BDL 3 5 4
AMBIENT AIR ANALYSIS REPORT (BY SIDDHI CONSULTANTS)
JAN TO JUNE 2015
MONTH LOCATION DATE OF
PM 10 PM 2.5
SOx NOx HCL CL2 NH3 H.C. H2S
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 32 of 55
SAMPLING
100 µg /m
3
60 µg /m
3
80 µg /m
3
80 µg /m
3
200 µg
/m3
100 µg
/m3
400 µg
/m3
160 µg
/m3
500 µg
/m3
JAN 2015 Near TMP / Boiler area
12.01.15 76 29 19 21 14 10 12 BDL BDL
FEB 2015 Near TMP / Boiler area
17.02.15 77 28 20 22 15 12 10 BDL BDL
MAR 2015 Near TMP / Boiler area
20.03.15 72 29 22 25 14 10 8 BDL BDL
APR 2015 Near TMP / Boiler area
14.04.15 70 30 24 28 12 8 10 BDL BDL
MAY2015 Near TMP / Boiler area
20.05.15 75 32 24 27 13 9 12 BDL BDL
JUNE 2015 Near TMP / Boiler area
08.06.15 72 30 22 28 18 6 11 BDL BDL
TREATED EFFLUENT ANALYSIS REPORT
(OUR INTERNAL LAB ANALYSIS REPORTS)
TREATED EFFLUENT WATER ANALYSIS REPORT
MONTH : JAN-2015
DATE PH TEMP. TSS TDS BOD COD AMMONI- Phos- D.O. Chlori- Sulph- Oil & Phen- Sulphi- Cyani-
CAL-N phates des ates Grease Olic des des
G.P.C.B. 5.50 to 40°C 100 2100 30 100 5 4 600 1000 10 1 0.5 0.2
LIMITS 8.50 MAX. mg/l mg/l mg/l mg/l 50 mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
01.01.15 7.65 30 27 1510 9 60 BDL 2.1 5.1
02.01.15 8.07 31 27 1680 8 56 7 2.0 5.1
03.01.15 7.91 30 28 1610 8 52 8 2.4 5.2
04.01.15 7.91 30 28 1540 9 56 BDL 2.6 5.1
05.01.15 7.77 29 27 1570 10 68 BDL 2.5 5.3
06.01.15 8.37 29 28 1490 7 48 BDL 2.2 5.3
07.01.15 8.15 30 39 1750 10 68 BDL 2.8 5.2 560 910 1 BDL BDL BDL
08.01.15 8.31 29 29 1690 9 56 BDL 2.6 5.2
09.01.15 8.17 29 28 1670 10 72 16 2.2 5.1
10.01.15 8.33 29 26 1840 9 64 15 1.8 5.1
11.01.15 8.04 29 28 1900 14 96 BDL 2.0 5.2
12.01.15 7.95 30 27 1920 14 92 18 2.4 5.2
13.01.15 7.85 29 27 1830 8 60 19 3.0 5.3
14.01.15 7.75 30 30 1590 14 92 21 2.9 5.1 540 670 1 BDL BDL BDL
15.01.15 7.76 28 28 1650 12 88 BDL 2.6 5.2
16.01.15 7.75 29 27 1770 8 64 BDL 3.0 5.3
17.01.15 7.87 29 27 1610 12 84 BDL 3.4 5.3
18.01.15 7.94 29 28 1620 14 88 BDL 3.8 5.2
19.01.15 8.07 30 29 1790 12 80 BDL 4.1 5.2
20.01.15 7.73 30 29 1690 13 84 BDL 3.6 5.1
21.01.15 7.79 29 28 1690 12 80 BDL 3.3 5.1 420 880 BDL BDL BDL BDL
22.01.15 7.37 29 29 1630 9 72 7 2.1 5.2
23.01.15 7.59 30 28 1570 8 72 BDL 2.3 5.3
24.01.15 7.87 29 27 1650 14 84 BDL 2.2 5.2
25.01.15 7.68 29 28 1590 10 76 BDL 1.8 5.1
26.01.15 7.39 30 25 1710 12 84 BDL 1.6 5.3
27.01.15 7.41 29 27 1790 8 60 BDL 1.9 5.2
28.01.15 8.15 29 27 1790 9 72 BDL 2.0 5.2 457 840 BDL BDL BDL BDL
29.01.15 7.51 31 28 1690 10 76 BDL 2.1 5.1
30.01.15 7.58 31 30 1730 12 88 BDL 2.0 5.1
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 33 of 55
31.01.15 8.10 30 29 1890 10 72 BDL 2.2 5.1
PARAM- PH TEMP. TSS TDS BOD COD AMMONI- PHOSP- D.O. CHLOR- SULP- Oil & Phen- Sulphi- Cyani-
ETER CAL N HATES IDES HATES Grease Olic des des
AVG 7.86 30 28 1692 10 73 14 2.5 5.2 494 825 0.50 BDL BDL BDL
RANGE (MIN-MAX)
7.37 28 25 1490 7 48 BDL 1.6 5.1 420 670 BDL BDL BDL BDL
8.37 31 39 1920 14 96 21 4.1 5.3 560 910 1 BDL BDL BDL
DATE Colour (pt/co)
Total Chromium
Copper Nickel Zinc Lead Fluorides Mercury Arsenic Cadmium Selenium Boron Total Resi.
Chlorine
Hexav. Chromium
Insecticide/ Pesticides
G.P.C.B. 100 2 2 3 5 0.1 1.5 0.01 0.2 2 0.05 2 1 0.1 Absent
LIMITS Units mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
Findings 5 BDL BDL BDL 0.01 BDL BDL BDL BDL BDL BDL BDL 0.20 BDL BDL
Note : All parameters are within the limit.
BIOASSAY TEST:--- Toxicity factor test study being carried out.Total 10 experiments conducted and observed Tf<2 after 48 hrs.
TREATED EFFLUENT WATER ANALYSIS REPORT
MONTH :FEB-2015
DATE PH TEMP. TSS TDS BOD COD AMMONI- Phos- D.O. Chlori- Sulph- Oil & Phen- Sulphi- Cyani-
CAL-N phates des ates Grease Olic des des
G.P.C.B. 5.50 to 40°C 100 2100 30 100 5 4 600 1000 10 1 0.5 0.2
LIMITS 8.50 MAX. mg/l mg/l mg/l mg/l 50 mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
01.02.15 7.84 30 27 1480 12 80 BDL 2.6 5.1
02.02.15 7.89 29 29 1510 10 76 BDL 2.8 5.3
03.02.15 7.81 29 29 1670 12 84 7 2.1 5.3
04.02.15 7.90 29 28 1320 8 68 7 2.7 5.2
05.02.15 7.64 29 26 1410 14 88 6 3.2 5.2
06.02.15 7.81 30 29 1480 14 91 4 3.4 5.3
07.02.15 7.94 30 28 1610 12 82 9 2.9 5.2 520 740 1 BDL BDL BDL
08.02.15 7.83 30 28 1650 10 72 7 3.0 5.2
09.02.15 7.51 31 27 1610 8 60 7 2.7 5.3
10.02.15 7.57 29 28 1760 12 88 11 2.1 5.1
11.02.15 7.41 29 27 1820 8 64 12 2.5 5.1
12.02.15 7.27 30 28 1740 12 80 7 3.3 5.2
13.02.15 7.71 27 28 1570 10 76 9 2.8 5.2
14.02.15 7.20 29 26 1660 12 88 10 2.6 5.3 508 710 1 BDL BDL BDL
15.02.15 7.32 30 26 1680 10 72 7 2.4 5.2
16.02.15 7.19 30 24 1600 8 66 4 2.2 5.3
17.02.15 7.00 30 26 1430 14 84 11 3.0 5.3
18.02.15 6.92 31 30 1670 14 88 8 3.3 5.3
19.02.15 7.10 31 28 1550 12 80 7 3.8 5.2
20.02.15 Discahrge NIL
21.02.15 Discahrge NIL
22.02.15 Discahrge NIL
23.02.15 6.98 31 28 1570 10 72 8 2.3 5.2 420 690 1 BDL BDL BDL
24.02.15 7.01 30 30 1630 12 80 9 2.2 5.2
25.02.15 7.28 32 26 1790 10 76 8 1.9 5.4
26.02.15 7.02 32 28 1720 12 84 11 2.5 5.1
27.02.15 7.58 31 29 1810 14 96 11 3.0 5.1
28.02.15 7.14 31 28 1870 16 96 14 3.1 5.1 510 880 BDL BDL BDL BDL
PARAM- PH TEMP. TSS TDS BOD COD AMMONI- PHOSP- D.O. CHLOR- SULP- Oil & Phen- Sulphi- Cyani-
ETER CAL N HATES IDES HATES Grease Olic des des
AVG 7.43 30 28 1624 11 80 8 2.7 5.2 490 755 0.75 BDL BDL BDL
RANGE (MIN-MAX) 6.92 27 24 1320 8 60 BDL 1.9 5.1 420 690 BDL BDL BDL BDL
7.94 32 30 1870 16 96 14 3.8 5.4 520 880 1 BDL BDL BDL
DATE Colour (pt/co)
Total Chromium
Copper Nickel Zinc Lead Fluorides Mercury Arsenic Cadmium Selenium Boron Total Resi.
Chlorine
Hexav. Chromium
Insecticide/ Pesticides
G.P.C.B. 100 2 2 3 5 0.1 1.5 0.01 0.2 2 0.05 2 1 0.1 Absent
LIMITS Units mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
Findings 5 BDL BDL BDL 0.01 BDL BDL BDL BDL BDL BDL BDL 0.20 BDL BDL
Note : All parameters are within the limit.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 34 of 55
BIOASSAY TEST:--- Toxicity factor test study being carried out.Total 10 experiments conducted and observed Tf<2 after 48 hrs.
TREATED EFFLUENT WATER ANALYSIS REPORT
MONTH : MAR-2015
DATE PH TEMP. TSS TDS BOD COD AMMONI- Phos- D.O. Chlori- Sulph- Oil & Phen- Sulphi- Cyani-
CAL-N phates des ates Grease Olic des des
G.P.C.B. 5.50 to 40°C 100 2100 30 100 5 4 600 1000 10 1 0.5 0.2
LIMITS 8.50 MAX. mg/l mg/l mg/l mg/l 50 mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
01.03.15 7.00 30 28 1440 14 92 14 2.8 5.1
02.03.15 7.10 30 26 1680 12 84 12 3.1 5.2
03.03.15 7.27 31 28 1910 14 92 10 3.2 5.1
04.03.15 7.00 31 30 1880 14 92 12 3.2 5.1
05.03.15 7.20 31 29 1840 16 92 6 3.5 5.1
06.03.15 7.40 31 28 1770 10 68 5 2.9 5.1
07.03.15 7.26 31 29 1810 14 92 6 2.2 5.1 430 872 BDL BDL BDL BDL
08.03.15 7.20 30 30 1780 16 96 4 2.0 5.1
09.03.15 7.47 31 29 1670 14 92 4 3.1 5.2
10.03.15 7.54 31 30 1750 18 96 BDL 3.5 5.2
11.03.15 7.26 30 30 1680 18 96 3 3.9 5.1
12.03.15 Discahrge NIL
13.03.15 Discahrge NIL
14.03.15 Discahrge NIL
15.03.15 Discahrge NIL
16.03.15 7.30 30 26 1470 10 80 BDL 3.8 5.2 410 590 1 BDL BDL BDL
17.03.15 7.31 30 28 1540 14 92 BDL 3.4 5.2
18.03.15 7.25 30 28 1610 18 96 4 3.6 5.2
19.03.15 7.26 29 26 1680 16 96 11 2.9 5.1
20.03.15 7.04 29 28 1590 14 92 14 2.2 5.2
21.03.15 7.16 30 25 1660 16 96 11 2.4 5.3 512 762 BDL BDL BDL BDL
22.03.15 7.00 30 25 1570 14 88 12 3.0 5.2
23.03.15 7.30 30 28 1790 12 84 7 3.1 5.2
24.03.15 7.49 31 26 1630 12 84 8 3.1 5.2
25.03.15 7.59 31 26 1730 8 56 4 3.5 5.2
26.03.15 7.46 31 28 1740 14 92 8 3.2 5.1
27.03.15 7.21 30 26 1490 18 96 9 2.6 5.1
28.03.15 7.32 31 27 1540 16 96 7 2.2 5.2 482 630 BDL BDL BDL BDL
29.03.15 7.39 31 26 1600 14 92 7 2.1 5.1
30.03.15 7.48 30 27 1530 12 88 8 2.1 5.2
31.03.15 7.68 31 28 1510 18 96 7 2.4 5.2
PARAM- PH TEMP. TSS TDS BOD COD AMMONI- PHOSP- D.O. CHLOR- SULP- Oil & Phen- Sulphi- Cyani-
ETER CAL N HATES IDES HATES Grease Olic des des
AVG 7.29 30 28 1663 14 89 8 2.9 5.2 459 714 0.25 BDL BDL BDL
RANGE (MIN-MAX) 7.00 29 25 1440 8 56 BDL 2.0 5.1 410 590 BDL BDL BDL BDL
7.68 31 30 1910 18 96 14 3.9 5.3 512 872 1 BDL BDL BDL
DATE Colour (pt/co)
Total Chromium
Copper Nickel Zinc Lead Fluorides Mercury Arsenic Cadmium Selenium Boron Total Resi.
Chlorine
Hexav. Chromium
Insecticide/ Pesticides
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 35 of 55
G.P.C.B. 100 2 2 3 5 0.1 1.5 0.01 0.2 2 0.05 2 1 0.1 Absent
LIMITS Units mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
Findings 5 BDL BDL BDL 0.02 BDL BDL BDL BDL BDL BDL BDL 0.40 BDL BDL
Note : All parameters are within the limit.
BIOASSAY TEST:--- Toxicity factor test study being carried out.Total 10 experiments conducted and observed Tf<2 after 48 hrs.
TREATED EFFLUENT WATER ANALYSIS REPORT
MONTH : APR-2015
DATE PH TEMP. TSS TDS BOD COD AMMONI- Phos- D.O. Chlori- Sulph- Oil & Phen- Sulphi- Cyani-
CAL-N phates des ates Grease Olic des des
G.P.C.B. 5.50 to 40°C 100 2100 30 100 5 4 600 1000 10 1 0.5 0.2
LIMITS 8.50 MAX. mg/l mg/l mg/l mg/l 50 mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
01.04.15 7.75 30 28 1380 16 88 5 2.2 5.1
02.04.15 7.86 31 30 1470 18 96 4 2.7 5.2
03.04.15 7.66 31 31 1680 16 92 5 3.2
5.1
04.04.15 7.71 31 28 1660 14 92 5 3.2
5.2
05.04.15 7.70 31 28 1640 14 88 5 3.3 5.1
06.04.15 7.25 31 30 1630 12 80 5 3.8 5.2
07.04.15 7.49 31 28 1640 12 84 5 4.1 5.2 508 780 BAL BDL BDL BDL
08.04.15 7.26 31 28 1640 14 88 11 4.0 5.2
09.04.15 7.35 31 30 1600 20 96 17 3.9 5.2
10.04.15 7.20 31 30 1890 14 88 18 3.4 5.1
11.04.15 7.15 31 32 1820 16 92 BDL 2.8 5.2
12.04.15 7.53 32 30 1880 18 92 11 2.2 5.1
13.04.15 7.40 31 26 1760 18 96 11 1.8 5.2
14.04.15 7.00 31 28 1740 14 92 14 1.8 5.1 470 890 BDL BDL BDL BDL
15.04.15 7.00 31 30 1820 18 96 11 2.1 5.1
16.04.15 7.01 32 26 1680 16 88 13 1.9 5.0
17.04.15 6.74 31 34 1690 14 84 9 2.4 5.0
18.04.15 6.84 31 34 1920 16 92 11 2.3 5.1
19.04.15 6.85 32 32 1760 20 96 7 2.2 5.0
20.04.15 7.00 32 30 1610 16 88 13 2.0 5.1
21.04.15 7.18 32 32 1620 16 88 6 1.6 5.1 484 780 1 BDL BDL BDL
22.04.15 7.41 32 30 1690 18 92 4 1.9 5.1
23.04.15 7.24 31 31 1740 18 96 7 2.0 5.1
24.04.15 7.30 31 30 1660 18 92 8 2.2 5.1
25.04.15 7.50 30 31 1690 16 92 11 2.6 5.1
26.04.15 7.40 31 28 1810 16 88 12 2.8 5.0
27.04.15 7.68 31 30 1840 16 92 12 3.0 5.0
28.04.15 7.50 31 32 1780 14 84 14 3.2 5.1 520 890 BDL BDL BDL BDL
29.04.15 7.65 31 28 1760 16 88 21 2.9 5.1
30.04.15 7.10 31 26 1810 16 92 22 2.6 5.1
PARAM- PH TEMP. TSS TDS BOD COD AMMONI- PHOSP- D.O. CHLOR- SULP- Oil & Phen- Sulphi- Cyani-
ETER CAL N HATES IDES HATES Grease Olic des des
AVG 7.32 31 30 1710 16 90 10 2.7 5.1 496 835 0.25 BDL BDL BDL
RANGE (MIN-MAX) 6.74 30 26 1380 12 80 BDL 1.6 5.0 470 780 BDL BDL BDL BDL
7.86 32 34 1920 20 96 22 4.1 5.2 520 890 1 BDL BDL BDL
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 36 of 55
DATE Colour (pt/co)
Total Chromium
Copper Nickel Zinc Lead Fluorides Mercury Arsenic Cadmium Selenium Boron Total Resi.
Chlorine
Hexav. Chromium
Insecticide/ Pesticides
G.P.C.B. 100 2 2 3 5 0.1 1.5 0.01 0.2 2 0.05 2 1 0.1 Absent
LIMITS Units mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
Findings 5 BDL BDL BDL 0.02 BDL BDL BDL BDL BDL BDL BDL 0.20 BDL BDL
Note : All parameters are within the limit.
BIOASSAY TEST:--- Toxicity factor test study being carried out.Total 10 experiments conducted and observed Tf<2 after 48 hrs.
TREATED EFFLUENT WATER ANALYSIS REPORT
MONTH : MAY-2015
DATE PH TEMP. TSS TDS BOD COD AMMONI- Phos- D.O. Chlori- Sulph- Oil & Phen- Sulphi- Cyani-
CAL-N phates des ates Grease Olic des des
G.P.C.B. 5.50 to 40°C 100 2100 30 100 5 4 600 1000 10 1 0.5 0.2
LIMITS 8.50 MAX. mg/l mg/l mg/l mg/l 50 mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
01.05.15 7.40 30 30 1740 14 88 19 3.3 5.1
02.05.15 7.60 31 32 1820 14 84 17 3.8 5.1
03.05.15 7.28 31 28 1680 16 84 17 4.1 5.1
04.05.15 7.51 32 30 1690 12 76 14 4.0 5.1
05.05.15 7.40 32 28 1880 14 80 13 3.9 5.1
06.05.15 7.56 31 30 1760 16 88 10 3.4 5.0
07.05.15 7.39 31 29 1610 17 92 16 3.2 5.1 552 710 1 BDL BDL BDL
08.05.15 7.45 31 28 1620 14 84 13 3.7 5.1
09.05.15 7.41 32 28 1800 12 80 10 2.9 5.1
10.05.15 Discahrge NIL
11.05.15 Discahrge NIL
12.05.15 Discahrge NIL
13.05.15 Discahrge NIL
14.05.15 7.39 32 30 1640 16 88 32 2.4 5.1 512 818 BDL BDL BDL BDL
15.05.15 7.52 32 28 1630 16 92 17 2.3 5.1
16.05.15 7.83 32 22 1640 8 68 14 2.2 5.1
17.05.15 7.31 33 24 1640 12 80 29 2.0 5.2
18.05.15 7.45 32 28 1600 8 64 11 1.6 5.2
19.05.15 7.28 33 28 1890 6 44 11 1.9 5.2
20.05.15 7.02 33 24 1820 8 60 8 2.0 5.2
21.05.15 7.79 31 20 1820 4 44 5 2.2 5.2 484 780 1 BDL BDL BDL
22.05.15 7.62 33 20 1680 6 48 11 1.8 5.3
23.05.15 7.69 32 20 1690 7 44 8 1.8 5.3
24.05.15 7.41 32 22 1890 8 52 7 2.1 5.2
25.05.15 Discahrge NIL
26.05.15 7.47 33 26 1470 8 60 6 2.6 5.0
27.05.15 7.51 33 26 1680 12 80 2 2.8 5.1
28.05.15 7.11 32 26 1660 14 88 2 3.0 5.1 496 832 BDL BDL BDL BDL
29.05.15 7.50 32 30 1640 14 88 22 3.2 5.1
30.05.15 7.80 32 29 1630 12 76 14 2.9 5.1
31.05.15 7.33 32 30 1680 14 80 17 3.1 5.2
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 37 of 55
PARAM- PH TEMP. TSS TDS BOD COD AMMONI- PHOSP- D.O. CHLOR- SULP- Oil & Phen- Sulphi- Cyani-
ETER CAL N HATES IDES HATES Grease Olic des des
AVG 7.46 32 27 1704 12 74 13 2.8 5.1 511 785 0.25 BDL BDL BDL
RANGE (MIN-MAX) 7.02 30 20 1470 4 44 BDL 1.6 5.0 484 710 BDL BDL BDL BDL
7.83 33 32 1890 17 92 32 4.1 5.3 552 832 1 BDL BDL BDL
DATE Colour (pt/co)
Total Chromium
Copper Nickel Zinc Lead Fluorides Mercury Arsenic Cadmium Selenium Boron Total Resi.
Chlorine
Hexav. Chromium
Insecticide/ Pesticides
G.P.C.B. 100 2 2 3 5 0.1 1.5 0.01 0.2 2 0.05 2 1 0.1 Absent
LIMITS Units mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
Findings 5 BDL BDL BDL 0.02 BDL BDL BDL BDL BDL BDL BDL 0.30 BDL BDL
Note : All parameters are within the limit.
BIOASSAY TEST:--- Toxicity factor test study being carried out.Total 10 experiments conducted and observed Tf<2 after 48 hrs.
TREATED EFFLUENT WATER ANALYSIS REPORT
MONTH : JUN-2015
DATE PH TEMP. TSS TDS BOD COD AMMONI- Phos- D.O. Chlori- Sulph- Oil & Phen- Sulphi- Cyani-
CAL-N phates des ates Grease Olic des des
G.P.C.B. 5.50 to 40°C 100 2100 30 100 5 4 600 1000 10 1 0.5 0.2
LIMITS 8.50 MAX. mg/l mg/l mg/l mg/l 50 mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
01.06.15 7.75 32 32 1680 14 92 17 2.4 5.1
02.06.15 7.70 32 32 1890 16 96 18 2.3 5.1
03.06.15 7.49 32 26 1660 4 32 4 2.2 5.1
04.06.15 7.88 32 28 1910 14 92 14 1.8 5.1
05.06.15 8.09 32 26 1980 6 56 14 2.0 5.2
06.06.15 7.63 32 28 1720 14 88 25 1.9 5.2
07.06.15 7.70 32 26 1660 12 52 7 2.6 5.1 490 810 1 BDL BDL BDL
08.06.15 7.91 32 28 1600 11 52 10 2.6 5.1
09.06.15 7.80 32 29 1930 14 76 22 2.0 5.1
10.06.15 7.87 31 30 1880 15 84 32 2.2 5.1
11.06.15 7.82 31 28 1790 16 88 36 3.0
4.9
12.06.15 7.54 31 29 1760 16 88 25 2.8
5.0
13.06.15 7.41 31 30 1740 15 80 21 3.1 5.0
14.06.15 7.39 30 32 1800 16 88 35 2.7 5.1 524 786 1 BDL BDL BDL
15.06.15 7.27 30 30 1860 10 80 33 3.0 5.1
16.06.15 7.30 30 28 1720 12 84 36 2.2 5.2
17.06.15 7.20 30 28 1790 14 72 8 3.3 5.1
18.06.15 7.30 29 29 1610 14 72 4 3.2 5.0
19.06.15 7.00 29 28 1800 14 76 5 3.5 5.1
20.06.15 7.00 29 29 1740 16 84 16 2.8 5.0
21.06.15 7.00 30 29 1620 18 92 14 2.3 5.1 481 798 BDL BDL BDL BDL
22.06.15 7.30 30 28 1940 18 96 12 2.6 5.1
23.06.15 6.90 29 29 1840 16 96 12 2.9 5.1
24.06.15 6.95 29 28 1690 12 88 16 2.1 5.1
25.06.15 7.30 30 29 1740 16 92 16 1.9 5.0
26.06.15 7.00 29 29 1860 18 96 16 2.4 5.0
27.06.15 7.00 29 28 1710 16 96 11 2.3 5.1
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 38 of 55
28.06.15 7.00 29 28 1790 14 88 BDL 2.2 5.0 503 890 BDL BDL BDL BDL
29.06.15 7.00 29 29 1830 14 84 BDL 2.2 5.1
30.06.15 7.16 30 28 1700 16 92 10 2.4 5.1
PARAM- PH TEMP. TSS TDS BOD COD AMMONI- PHOSP- D.O. CHLOR- SULP- Oil & Phen- Sulphi- Cyani-
ETER CAL N HATES IDES HATES Grease Olic des des
AVG 7.39 30 29 1775 14 82 17 2.5 5.1 499 821 0.50 BDL BDL BDL
RANGE (MIN-MAX) 6.90 29 26 1600 4 32 BDL 1.8 4.9 481 786 BDL BDL BDL BDL
8.09 32 32 1980 18 96 36 3.5 5.2 524 890 1 BDL BDL BDL
DATE Colour (pt/co)
Total Chromium
Copper Nickel Zinc Lead Fluorides Mercury Arsenic Cadmium Selenium Boron Total Resi.
Chlorine
Hexav. Chromium
Insecticide/ Pesticides
G.P.C.B. 100 2 2 3 5 0.1 1.5 0.01 0.2 2 0.05 2 1 0.1 Absent
LIMITS Units mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l mg/l
Findings 5 BDL BDL BDL 0.02 BDL BDL BDL BDL BDL BDL BDL 0.20 BDL BDL
Note : All parameters are within the limit.
BIOASSAY TEST:--- Toxicity factor test study being carried out.Total 10 experiments conducted and observed Tf<2 after 48 hrs.
TOXICITY FACTOR
(OUR INTERNAL LAB ANALYSIS REPORTS)
TOXICITY FACTOR MONTH: Jan- 2015
DATE Parts of Ratio of Dilution FISH FISH ANALYSIS OF FIISH AFTER HRS. TOXICITY
OF Dilution Waste Factor (T) TYPE NO. FINAL OUTLET 2 HRS 6 HRS 24 HRS 48 HRS FACTOR
EXP. Water Water Tf Tobe To test PH COD Added Water PPM To one (by Part of Volume) Waste Water (by volume)
01.01.15 1 1:2 2 ZEBRA 5 7.65 60 5 5 5 5 Tf =2
03.01.15 1 1:2 2 ZEBRA 5 7.91 52 5 5 5 5 Tf =2
06.01.15 1 1:2 2 ZEBRA 5 8.37 48 5 5 5 5 Tf =2
09.01.15 1 1:2 2 ZEBRA 5 8.17 72 5 5 5 5 Tf =2
12.01.15 1 1:2 2 ZEBRA 5 7.95 92 5 5 5 5 Tf =2
16.01.15 1 1:2 2 ZEBRA 5 7.75 64 5 5 5 5 Tf =2
18.01.15 1 1:2 2 ZEBRA 5 7.94 88 5 5 5 5 Tf =2
21.01.15 1 1:2 2 ZEBRA 5 7.79 80 5 5 5 5 Tf =2
25.01.15 1 1:2 2 ZEBRA 5 7.68 76 5 5 5 5 Tf =2
27.01.15 1 1:2 2 ZEBRA 5 7.41 60 5 5 5 5 Tf =2
Remark : All parameter passes as per requirement.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 39 of 55
TOXICITY FACTOR MONTH: FEB- 201
DATE Parts of Ratio of Dilution FISH FISH ANALYSIS OF FIISH AFTER HRS. TOXICITY
OF Dilution Waste Factor (T) TYPE NO. FINAL OUTLET 2 HRS 6 HRS 24 HRS 48 HRS FACTOR
EXP. Water Water Tf
Tobe To test PH COD
Added Water PPM
To one (by
Part of Volume)
Waste
Water
(by volume)
01.02.15 1 1:2 2 ZEBRA 5 7.84 80 5 5 5 5 Tf =2
03.02.15 1 1:2 2 ZEBRA 5 7.81 84 5 5 5 5 Tf =2
06.02.15 1 1:2 2 ZEBRA 5 7.81 91 5 5 5 5 Tf =2
08.02.15 1 1:2 2 ZEBRA 5 7.83 72 5 5 5 5 Tf =2
11.02.15 1 1:2 2 ZEBRA 5 7.41 64 5 5 5 5 Tf =2
13.02.15 1 1:2 2 ZEBRA 5 7.71 76 5 5 5 5 Tf =2
16.02.15 1 1:2 2 ZEBRA 5 7.19 66 5 5 5 5 Tf =2
18.02.15 1 1:2 2 ZEBRA 5 6.92 88 5 5 5 5 Tf =2
25.02.15 1 1:2 2 ZEBRA 5 7.28 76 5 5 5 5 Tf =2
28.02.15 1 1:2 2 ZEBRA 5 7.14 96 5 5 5 5 Tf =2
Remark : All parameter passes as per requirement.
TOXICITY FACTOR MONTH: March- 2015
DATE Parts of Ratio of Dilution FISH FISH ANALYSIS OF FIISH AFTER HRS. TOXICITY
OF Dilution Waste Factor (T) TYPE NO. FINAL OUTLET 2 HRS 6 HRS 24 HRS 48 HRS FACTOR
EXP. Water Water Tf
Tobe To test PH COD
Added Water PPM
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 40 of 55
To one (by
Part of Volume)
Waste
Water
(by volume)
02.03.15 1 1:2 2 ZEBRA 5 7.10 84 5 5 5 5 Tf =2
05.03.15 1 1:2 2 ZEBRA 5 7.20 92 5 5 5 5 Tf =2
08.03.15 1 1:2 2 ZEBRA 5 7.20 96 5 5 5 5 Tf =2
11.03.15 1 1:2 2 ZEBRA 5 7.26 96 5 5 5 5 Tf =2
16.03.15 1 1:2 2 ZEBRA 5 7.30 80 5 5 5 5 Tf =2
20.03.15 1 1:2 2 ZEBRA 5 7.04 92 5 5 5 5 Tf =2
23.03.15 1 1:2 2 ZEBRA 5 7.30 84 5 5 5 5 Tf =2
25.03.15 1 1:2 2 ZEBRA 5 7.59 56 5 5 5 5 Tf =2
27.03.15 1 1:2 2 ZEBRA 5 7.21 96 5 5 5 5 Tf =2
30.03.15 1 1:2 2 ZEBRA 5 7.48 88 5 5 5 5 Tf =2
Remark : All parameter passes as per requirement.
TOXICITY FACTOR MONTH: April- 2015
DATE Parts of Ratio of Dilution FISH FISH ANALYSIS OF FIISH AFTER HRS. TOXICITY
OF Dilution Waste Factor (T) TYPE NO. FINAL OUTLET 2 HRS 6 HRS 24 HRS 48 HRS FACTOR
EXP. Water Water Tf
Tobe To test PH COD
Added Water PPM
To one (by
Part of Volume)
Waste
Water
(by volume)
02.04.15 1 1:2 2 ZEBRA 5 7.86 96 5 5 5 5 Tf =2
05.04.15 1 1:2 2 ZEBRA 5 7.70 88 5 5 5 5 Tf =2
08.04.15 1 1:2 2 ZEBRA 5 7.26 88 5 5 5 5 Tf =2
11.04.15 1 1:2 2 ZEBRA 5 7.15 92 5 5 5 5 Tf =2
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 41 of 55
14.04.15 1 1:2 2 ZEBRA 5 7.00 92 5 5 5 5 Tf =2
17.04.15 1 1:2 2 ZEBRA 5 6.74 84 5 5 5 5 Tf =2
20.04.15 1 1:2 2 ZEBRA 5 6.85 96 5 5 5 5 Tf =2
23.04.15 1 1:2 2 ZEBRA 5 7.24 96 5 5 5 5 Tf =2
25.04.15 1 1:2 2 ZEBRA 5 7.50 92 5 5 5 5 Tf =2
28.04.15 1 1:2 2 ZEBRA 5 7.50 84 5 5 5 5 Tf =2
Remark : All parameter passes as per requirement.
TOXICITY FACTOR MONTH: May- 2015
DATE Parts of Ratio of Dilution FISH FISH ANALYSIS OF FIISH AFTER HRS. TOXICITY
OF Dilution Waste Factor (T) TYPE NO. FINAL OUTLET 2 HRS 6 HRS 24 HRS 48 HRS FACTOR
EXP. Water Water Tf
Tobe To test PH COD
Added Water PPM
To one (by
Part of Volume)
Waste
Water
(by volume)
01.05.15 1 1:2 2 ZEBRA 5 7.40 88 5 5 5 5 Tf =2
04.05.15 1 1:2 2 ZEBRA 5 7.51 76 5 5 5 5 Tf =2
07.05.15 1 1:2 2 ZEBRA 5 7.39 92 5 5 5 5 Tf =2
09.05.15 1 1:2 2 ZEBRA 5 7.41 80 5 5 5 5 Tf =2
14.05.15 1 1:2 2 ZEBRA 5 7.39 88 5 5 5 5 Tf =2
17.05.15 1 1:2 2 ZEBRA 5 7.31 80 5 5 5 5 Tf =2
20.05.15 1 1:2 2 ZEBRA 5 7.02 60 5 5 5 5 Tf =2
23.05.15 1 1:2 2 ZEBRA 5 7.69 44 5 5 5 5 Tf =2
26.05.15 1 1:2 2 ZEBRA 5 7.47 60 5 5 5 5 Tf =2
29.05.15 1 1:2 2 ZEBRA 5 7.50 88 5 5 5 5 Tf =2
Remark : All parameter passes as per requirement.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 42 of 55
TOXICITY FACTOR MONTH: June- 2015
DATE Parts of Ratio of Dilution FISH FISH ANALYSIS OF FIISH AFTER HRS. TOXICITY
OF Dilution Waste Factor (T) TYPE NO. FINAL OUTLET 2 HRS 6 HRS 24 HRS 48 HRS FACTOR
EXP. Water Water Tf
Tobe To test PH COD
Added Water PPM
To one (by
Part of Volume)
Waste
Water
(by volume)
01.06.15 1 1:2 2 ZEBRA 5 7.75 92 5 5 5 5 Tf =2
04.06.15 1 1:2 2 ZEBRA 5 7.88 92 5 5 5 5 Tf =2
07.06.15 1 1:2 2 ZEBRA 5 7.70 52 5 5 5 5 Tf =2
10.06.15 1 1:2 2 ZEBRA 5 7.87 84 5 5 5 5 Tf =2
13.06.15 1 1:2 2 ZEBRA 5 7.41 80 5 5 5 5 Tf =2
16.06.15 1 1:2 2 ZEBRA 5 7.27 80 5 5 5 5 Tf =2
18.06.15 1 1:2 2 ZEBRA 5 7.30 72 5 5 5 5 Tf =2
21.06.15 1 1:2 2 ZEBRA 5 7.00 92 5 5 5 5 Tf =2
24.06.15 1 1:2 2 ZEBRA 5 6.95 88 5 5 5 5 Tf =2
28.06.15 1 1:2 2 ZEBRA 5 7.00 88 5 5 5 5 Tf =2
Remark : All parameter passes as per requirement.
NOISE MONITORING REPORT (OUR INTERNAL LAB ANALYSIS REPORTS)
SOUND LEVEL MONITORING
REPORT : ( AMBIENT)
JAN-2015
SR.NO. LOCATIONS OF MONITORING SOUND LEVEL SOUND LEVEL
DAY TIME NIGHT TIME
Time : 6 AM to 10
PM Time : 10 PM to 6
AM
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 43 of 55
( AMBIENT) Limit : 75 DBA Limit : 70 DBA
Date : 17.01.2015 Date : 26.01.2015
Time : 14.30 hrs. Time : 00.15
1 MAIN GATE 68.2 52.4
2 WORK SHOP (ENGG.) 67.5 46.7
3 MANCOZEB SOLID 71.3 68.5
4 MANCOZEB LIQUID 71.6 67.9
5 ANTRACOL PLANT 67.8 65.7
6 ELECTRICAL DEPARTMENT 65.2 64.7
7 BOILER HOUSE 71.3 69.1
8 TMP PLANT 70.1 68.0
9 MCP PLANT 68.2 65.6
10 AMMONIA RECOVERY PLANT 71.5 67.9
11 CACL2 PLANT 72.3 68.5
12 ETP PLANT 71.5 67.1
13 Q.A.LAB 61.3 58.2
14 R&D LAB 65.6 60.4
15 FLONICAMID(ULALA) 70.6 68.1
15 IKI-220 PLANT 71.3 68.7
Remarks : All Parameters passes as per requirements.
SOUND LEVEL MONITORING REPORT :
( AMBIENT) FEB-2015
SR.NO. LOCATIONS OF MONITORING SOUND LEVEL SOUND LEVEL
DAY TIME NIGHT TIME
Time : 6 AM to 10 PM
Time : 10 PM to 6 AM
( AMBIENT) Limit : 75 DBA Limit : 70 DBA
Date : 19.02.2015 Date : 24.02.2015
Time : 16.00 hrs. Time : 01.15
1 MAIN GATE 66.9 57.4
2 WORK SHOP (ENGG.) 68.5 48.3
3 MANCOZEB SOLID 68.3 66.7
4 MANCOZEB LIQUID 67.8 66.3
5 ANTRACOL PLANT 72.7 68.1
6 ELECTRICAL DEPARTMENT 67.9 64.3
7 BOILER HOUSE 71.8 69.0
8 TMP PLANT 70.1 67.7
9 MCP PLANT 71.7 68.4
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 44 of 55
10 AMMONIA RECOVERY PLANT 70.7 67.9
11 CACL2 PLANT 71.1 67.6
12 ETP PLANT 70.9 67.3
13 Q.A.LAB 66.2 62.1
14 R&D LAB 69.1 63.4
15 FLONICAMID(ULALA) 67.9 66.3
15 IKI-220 PLANT 71.9 68.5
Remarks : All Parameters passes as per requirements.
SOUND LEVEL MONITORING REPORT :
( AMBIENT) MAR-2015
SR.NO. LOCATIONS OF MONITORING SOUND LEVEL SOUND LEVEL
DAY TIME NIGHT TIME
Time : 6 AM to 10
PM Time : 10 PM to 6
AM
( AMBIENT) Limit : 75 DBA Limit : 70 DBA
Date : 20.03.2015 Date : 23.03.2015
Time : 15.30 hrs. Time : 02.00
1 MAIN GATE 69.2 55.3
2 WORK SHOP (ENGG.) 73.6 46.1
3 MANCOZEB SOLID 65.2 62.1
4 MANCOZEB LIQUID 68.4 62.3
5 ANTRACOL PLANT 71.9 68.4
6 ELECTRICAL DEPARTMENT 60.5 56.3
7 BOILER HOUSE 72.0 68.9
8 TMP PLANT 70.9 68.3
9 MCP PLANT 71.3 67.1
10 AMMONIA RECOVERY PLANT 72.1 67.7
11 CACL2 PLANT 70.2 68.2
12 ETP PLANT 72.9 67.5
13 Q.A.LAB 65.6 57.3
14 R&D LAB 69.8 62.4
15 FLONICAMID(ULALA) 65.7 62.7
16 IKI-220 PLANT 72.3 68.9
Remarks : All Parameters passes as per requirements.
SOUND LEVEL MONITORING REPORT :
( AMBIENT) APR-2015
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 45 of 55
SR.NO. LOCATIONS OF MONITORING SOUND LEVEL SOUND LEVEL
DAY TIME NIGHT TIME
Time : 6 AM to 10
PM Time : 10 PM to 6
AM
( AMBIENT) Limit : 75 DBA Limit : 70 DBA
Date : 21.04.2015 Date : 24.04.2015
Time : 14.00 hrs. Time : 01.15
1 MAIN GATE 71.2 52.70
2 WORK SHOP (ENGG.) 72.9 48.10
3 MANCOZEB SOLID 72.0 68.30
4 MANCOZEB LIQUID 69.8 65.10
5 ANTRACOL PLANT 72.8 68.70
6 ELECTRICAL DEPARTMENT 65.2 52.30
7 BOILER HOUSE 72.8 68.50
8 TMP PLANT 71.5 67.60
9 MCP PLANT 72.0 67.30
10 AMMONIA RECOVERY PLANT 71.6 67.50
11 CACL2 PLANT 70.6 66.80
12 ETP PLANT 72.5 67.10
13 Q.A.LAB 67.3 53.60
14 R&D LAB 70.4 60.70
15 FLONICAMID(ULALA) 69.0 65.10
16 IKI-220 PLANT 71.4 68.50
Remarks : All Parameters passes as per requirements.
SOUND LEVEL MONITORING REPORT :
( AMBIENT) MAY-2015
SR.NO. LOCATIONS OF MONITORING SOUND LEVEL SOUND LEVEL
DAY TIME NIGHT TIME
Time : 6 AM to 10
PM Time : 10 PM to 6
AM
( AMBIENT) Limit : 75 DBA Limit : 70 DBA
Date : 20.05.2015 Date : 26.05.2015
Time : 17.00 hrs. Time : 02.45
1 MAIN GATE 69.3 56.3
2 WORK SHOP (ENGG.) 67.4 50.6
3 MANCOZEB SOLID 71.9 68.1
4 MANCOZEB LIQUID 69.3 67.3
5 ANTRACOL PLANT 72.2 68.0
6 ELECTRICAL DEPARTMENT 65.8 54.6
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 46 of 55
7 BOILER HOUSE 72.4 69.1
8 TMP PLANT 71.8 68.0
9 MCP PLANT 71.7 67.1
10 AMMONIA RECOVERY PLANT 72.0 68.3
11 CACL2 PLANT 71.3 66.5
12 ETP PLANT 72.1 66.8
13 Q.A.LAB 65.8 51.3
14 R&D LAB 70.6 62.7
15 FLONICAMID(ULALA) 71.8 67.7
16 IKI-220 PLANT 71.9 68.2
Remarks : All Parameters passes as per requirements.
SOUND LEVEL MONITORING REPORT : ( AMBIENT)
JUN-2015
SR.NO. LOCATIONS OF MONITORING SOUND LEVEL SOUND LEVEL
DAY TIME NIGHT TIME
Time : 6 AM to 10
PM Time : 10 PM to 6
AM
( AMBIENT) Limit : 75 DBA Limit : 70 DBA
Date : 16.06.2015 Date : 26.06.2015
Time : 16.00 hrs. Time : 02.45
1 MAIN GATE 64.1 49.8
2 WORK SHOP (ENGG.) 62.1 48.4
3 MANCOZEB SOLID 72.3 67.6
4 MANCOZEB LIQUID 69.8 67.4
5 ANTRACOL PLANT 72.7 68.3
6 ELECTRICAL DEPARTMENT 67.3 56.7
7 BOILER HOUSE 72.2 69.2
8 TMP PLANT 71.5 67.8
9 MCP PLANT 71.8 67.5
10 AMMONIA RECOVERY PLANT 71.6 68.0
11 CACL2 PLANT 72.4 67.8
12 ETP PLANT 70.6 65.1
13 Q.A.LAB 62.1 52.6
14 R&D LAB 72.4 58.4
15 FLONICAMID(ULALA) 72.1 67.3
16 IKI-220 PLANT 72.3 67.9
Remarks : All Parameters passes as per requirements.
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 47 of 55
FUGITIVE EMISSIONS REPORT (OUR INTERNAL LAB ANALYSIS REPORTS)
FUGITIVE EMISSIONS REPORT ( Form no:37)
MONTH : JAN-2015
SR. PLANT AREA Date : 10.01.2015
Date : 28.01.2015
NO. IDENTIFICATION Time : 14.30 Hrs. Time : 16.00 Hrs.
1.A MCP
PLANT Near Chlorine tonner area
CHLORINE TLV = 0.5 ppm
BDL BDL
2.A AMMONIA
PLANT
RVDF Gfloor Area
AMMONIA TLV=25 PPM
5.00 7.00
2.B High way side(Near boundry) BDL BDL
2.C Behind Cacl2 plant 2.00 1.00
3.A
MANCOZEB PLANT
During Cs2 Tanker unloading
CARBON DISULPHIDE TLV=10 PPM
BDL BDL
3.B Near ST-702A BDL BDL
3.C Near D-14 Tank BDL BDL
3.D Near P-14 Tank BDL BDL
3.E Mancozeb Packing Area 2.00 1.00
3.F Mancozeb Storage Godown BDL BDL
Remark : All parameter passes as per requirement.
FUGITIVE EMISSIONS REPORT ( Form no:37)
MONTH : FEB-2015
SR. PLANT AREA Date : 13.02.2015
Date : 23.02.2015
NO. IDENTIFICATION Time : 16.15 Hrs. Time : 11.15 Hrs.
1.A MCP
PLANT Near Chlorine tonner area
CHLORINE TLV = 0.5 ppm
BDL BDL
2.A AMMONIA
PLANT
RVDF Gfloor Area
AMMONIA TLV=25 PPM
3.00 2.00
2.B High way side(Near boundry) BDL BDL
2.C Behind Cacl2 plant 1.00 2.00
3.A
MANCOZEB PLANT
During Cs2 Tanker unloading
CARBON DISULPHIDE TLV=10 PPM
BDL BDL
3.B Near ST-702A BDL BDL
3.C Near D-14 Tank BDL BDL
3.D Near P-14 Tank BDL BDL
3.E Mancozeb Packing Area 2.00 1.00
3.F Mancozeb Storage Godown BDL BDL
Remark : All parameter passes as per requirement.
FUGITIVE EMISSIONS REPORT ( Form no:37)
MONTH : MAR-2015
SR. PLANT AREA Date : 10.03.2015 Date : 26.03.15
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 48 of 55
NO. IDENTIFICATION Time : 15.30 Hrs. Time : 16.15 Hrs.
1.A MCP
PLANT Near Chlorine tonner area
CHLORINE TLV = 0.5 ppm
BDL BDL
2.A AMMONIA
PLANT
RVDF Gfloor Area
AMMONIA TLV=25 PPM
3 2
2.B High way side(Near boundry) BDL BDL
2.C Behind Cacl2 plant 2 2
3.A
MANCOZEB PLANT
During Cs2 Tanker unloading
CARBON DISULPHIDE TLV=10 PPM
BDL BDL
3.B Near ST-702A BDL BDL
3.C Near D-14 Tank BDL BDL
3.D Near P-14 Tank BDL BDL
3.E Mancozeb Packing Area 2 3
3.F Mancozeb Storage Godown BDL BDL
Remark : All parameter passes as per requirement.
FUGITIVE EMISSIONS REPORT ( Form no:37)
MONTH : APR-2015
SR. PLANT AREA Date : 09.04.2015
Date : 24.04.2015
NO. IDENTIFICATION Time : 16.00 Hrs. Time : 15.15 Hrs.
1.A MCP
PLANT Near Chlorine tonner area
CHLORINE TLV = 0.5 ppm
BDL BDL
2.A AMMONIA
PLANT
RVDF Gfloor Area
AMMONIA TLV=25 PPM
3 3
2.B High way side(Near boundry) BDL BDL
2.C Behind Cacl2 plant 1 BDL
3.A
MANCOZEB PLANT
During Cs2 Tanker unloading
CARBON DISULPHIDE TLV=10 PPM
BDL BDL
3.B Near ST-702A BDL BDL
3.C Near D-14 Tank BDL BDL
3.D Near P-14 Tank BDL BDL
3.E Mancozeb Packing Area 2 1
3.F Mancozeb Storage Godown BDL 1
Remark : All parameter passes as per requirement.
FUGITIVE EMISSIONS REPORT ( Form no:37)
MONTH : MAY-2015
SR. PLANT AREA Date : 12.05.2015
Date : 25.05.2015
NO. IDENTIFICATION Time : 11.30 Hrs. Time : 16.00 Hrs.
1.A MCP
PLANT Near Chlorine tonner area
CHLORINE TLV = 0.5 ppm
BDL BDL
2.A AMMONIA
PLANT
RVDF Gfloor Area
AMMONIA TLV=25 PPM
4 2
2.B High way side(Near boundry) BDL BDL
2.C Behind Cacl2 plant 1 2
3.A MANCOZEB During Cs2 Tanker unloading CARBON BDL BDL
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 49 of 55
3.B PLANT Near ST-702A DISULPHIDE TLV=10 PPM
BDL BDL
3.C Near D-14 Tank BDL BDL
3.D Near P-14 Tank BDL BDL
3.E Mancozeb Packing Area 2 1
3.F Mancozeb Storage Godown BDL BDL
Remark : All parameter passes as per requirement.
FUGITIVE EMISSIONS REPORT ( Form no:37)
MONTH : JUN-2015
SR. PLANT AREA Date : 09.06.15 Date :22.06.15
NO. IDENTIFICATION Time : 10.45 Hrs.
Time : 16.00 Hrs.
1.A MCP
PLANT Near Chlorine tonner area
CHLORINE TLV = 0.5 ppm
BDL BDL
2.A AMMONIA
PLANT
RVDF Gfloor Area
AMMONIA TLV=25 PPM
3.00 5.00
2.B High way side(Near boundry) BDL BDL
2.C Behind Cacl2 plant 2.00 3.00
3.A
MANCOZEB PLANT
During Cs2 Tanker unloading
CARBON DISULPHIDE TLV=10 PPM
BDL BDL
3.B Near ST-702A BDL BDL
3.C Near D-14 Tank BDL BDL
3.D Near P-14 Tank BDL BDL
3.E Mancozeb Packing Area 2.00 1.00
3.F Mancozeb Storage Godown BDL BDL
Remark : All parameter passes as per requirement.
VOC Monitoring Data
Subject Total VOC monitoring analysis data.
Date of Monitoring 26.03.2015
Time 14.15 hrs to 16.00 hrs
Location Different Plant & Location at UPL-1
Instrument used On line digital VOC monitoring Instrument of UNIT-02
Instrument operation Operated by Mr. H.J.Patel (Q.A)
Sr.no. Location Parameter Remarks Remarks
1 TMP Plant - Drum filling area Total VOC BDL
2 TMP Plant - Ground floor area Total VOC BDL
3 TMP Plant - First floor area Total VOC BDL
4 TMP Plant - Near Solvent Storage Tank Total VOC BDL
5 MCP Plant – Ground floor back side Total VOC BDL
6 MCP Plant - Ground floor , Centre Total VOC 1 ppb
7 MCP Plant - First floor , Centre Total VOC 2 ppb
8 MCP Plant - Second floor , Centre Total VOC BDL
9 ETP Plant - Near Aer-2 & Aer-3 area Total VOC BDL
10 ETP Plant - Haz.Drum storage area Total VOC BDL
11 Drum storage area, Behind ETP Plant Total VOC BDL
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 50 of 55
12 Raw material Drum storage area - Pond site Total VOC BDL
13 Pilot plant - Ground floor area Total VOC 3 ppb
14 Pilot plant - First floor area Total VOC BDL
15 Pilot plant - Second floor area, Total VOC 2 ppb
16 Pilot plant - Ground floor area, Methanol Feeding pump Total VOC 2 ppb
17 FG storage godown Total VOC BDL
18 Drum storage area- Opposite FG godown, near parking Total VOC BDL
19 Main gate Total VOC BDL
20 On Road, Near Boiler Total VOC BDL
21 On Road, Between Antracol plant & Electrical Dept. Total VOC BDL
22 R & D Lab Total VOC BDL
23 Q.A.Lab Total VOC BDL
24 MaxPro Lab Total VOC BDL
VOC Monitoring Data
Subject Total VOC monitoring analysis data.
Date of Monitoring 29.06.2015
Time 16.15 hrs to 17.45 hrs
Location Different Plant & Location at UPL-1
Instrument used On line digital VOC monitoring Instrument of UNIT-02
Instrument operation Operated by Mr. H.J.Patel (Q.A)
Sr.no. Location Parameter Remarks Remarks
1 TMP Plant - Drum filling area Total VOC BDL
2 TMP Plant - Ground floor area Total VOC BDL
3 TMP Plant - First floor area Total VOC BDL
4 TMP Plant - Near Solvent Storage Tank Total VOC BDL
5 MCP Plant – Ground floor back side Total VOC 2 ppb
6 MCP Plant - Ground floor , Centre Total VOC 1 ppb
7 MCP Plant - First floor , Centre Total VOC BDL
8 MCP Plant - Second floor , Centre Total VOC BDL
9 ETP Plant - Near Aer-2 & Aer-3 area Total VOC BDL
10 ETP Plant - Haz.Drum storage area Total VOC BDL
11 Drum storage area, Behind ETP Plant Total VOC 3 ppb
12 Raw material Drum storage area - Pond site Total VOC BDL
13 Pilot plant - Ground floor area Total VOC 5 ppb
14 Pilot plant - First floor area Total VOC 3 ppb
15 Pilot plant - Second floor area, Total VOC 3 ppb
16 Pilot plant - Ground floor area, Methanol Feeding pump Total VOC BDL
17 FG storage godown Total VOC BDL
18 Drum storage area- Opposite FG godown, near parking Total VOC BDL
19 Main gate Total VOC BDL
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 51 of 55
20 On Road, Near Boiler Total VOC BDL
21 On Road, Between Antracol plant & Electrical Dept. Total VOC BDL
22 R & D Lab Total VOC BDL
23 Q.A.Lab Total VOC BDL
24 MaxPro Lab Total VOC BDL
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 52 of 55
PRODUCTION DETAILS
BY-PRODUCTS DETAILS
PESTICIDE FORMULATION PRODUCTS
Month PRODUCTION (MT)
Monocr Otophos
Dichl
Orovos
Man cozeb
Antr acol
Zineb
Tri-Methyl
Phosphite
Tri-ethyl
Phosphite
IKI
(Flocinamid)
(SF10) Sulfosulfuran
Tebuc onazo
le
Acifluorfen
Tech. (Fen-04 )
ZIRAM
Jan 15 191.4 188 618.9 0 23.2 988.61 42.56 16.098 0 0 0 0 Feb 15 287 257 640.8 0 0 1087.3 31.92 35.005 0 0 40 0 Mar 15 450.2 208 531.9 13.5 104 1082.2 35.79 46.582 0 0 1.726 0 April'15 313.393 215 556.8 0 71.6 1101.7 18.05 21.196 0 0 43.3 0
May.’15 302.395 204 559.4 0 89.2 1118.07 0 0.568 0 0 23.5 0
June’15 119.83 183.7 496.23 0 121.2 1119.33 0 17.647 7.2 0 0 0
Month PRODUCTION (MT)
CACL2 FUSED
CACL2 SOL. 30%
AMMONIUM SOL. 20%
NH4CL
Solid
SODIUM SULPHAT
E POWDER
SODIUM BISULP
HITE 20% SOL.
HCl 30%
MECL GAS
NaHS Solutio
n
METHANOL- BY PRODU
CT
Jan 15 600 3150.8 808.19 20 0 26.11 35.04 69 0 0
Feb 15 529.29 2743.06 606.63 25 0 31.93 0 51.11 0 0
Mar 15 602.71 2545.47 650.22 25 0 28.94 14.71 61.28 0 0
April'15 517.05 2860.117 670.83 59.86 0.535 0 18.44 60.96 0 0
May.’15 480 1827.961 497.26 97.35 0 32.45 20.19 58.8 0 0
June’15 638.6 3088.66 945.63 252.69 0.33 27.2 0 41.4 0 0
Month PRODUCTION (MT)
Acifluorfen (Fen-04 )
Formulation
Mancozeb Formulation
Flocinamid (IKI) formulation
MCP (PHOSKILL) FORMULATION
Dichlorovas Formulation
Jan 15 81 239.95 16.491 NIL 0 Feb 15 80 333.04 35.64 333.65 0 Mar 15 62.4 499 26.815 462.671 0 April'15 60.1 544.16 29.496 399.507 0
May.’15 41.6 221.14 41.112 496.165 0
June’15 146.6 309.5 31.422 479.32 0
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 53 of 55
DETAILS OF GIDC WATER CONSUMPTION & TREATED EFFLUENT DISCHARGED TO FETP, NCTL, ANKLESHWAR (INDUSTRIAL + DOMESTIC)
MONTH WATER CONSUMPTION TREATED EFFLUENT DISCHARGE QUANTITY TO FETP, NCTL,
ANKLESHAWR
ALL QUANTITY IN KL/MONTH
Jan 15 21955 8170
Feb 15 21955 6492
Mar 15 28761
7295
April'15 30704 8668
May.’15 25417 7542
June’15 25417 7588
DETAILS OF TREATMENT FOR HIGH TDS EFFLUENT WASTE WATER IN EVAPORATION SYSTEM AND PERMEATE GENERATION FROM WATER RECYCLING SYSTEM (RO)
MONTH
FORCED EVAPORATION SYSTEM: High TDS (NaCl) from Plants and from RO system in KL
(Feed Qty)
REUSABLE PERMEATE GENERATED FROM RO PLANT
–KL
Jan 15 929.00 2097
Feb 15 912.50 1746
Mar 15 817.00 2007
April'15 834.50 1968
May.’15 917.50 1868
June’15 889.50 1427
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 54 of 55
DETAILS OF INCINERABLE WASTE - MT
MONTH
OPENING STOCK (MT)
GENERATION CONTAMINATED PLASTIC &
OTHER WASTE
DISPOSAL
(Total Sent to BEIL)
CLOSING STOCK
ORGANIC AQUEOUS
Jan 15 35.68 16.65 9.12 0 0.00 61.45
Feb 15 61.45 12.85 14.56 0 54.82 34.0400
Mar 15 34.04 27.46 20.11 0 45.97 35.64
April'15 35.64 86.44 69.72 6.92 176.7 22.02
May.’15 22.02 36.23 49.67 0 81.37 26.55
June’15 26.55 22.01 57.99 0 83.78 22.77
DETAILS OF SOLID WASTE ( LANDFILLING)
MONTH OPENING STOCK
GENERATION SOLID DISPOSAL TO BEIL (ETP SLUDE + SALT)*
CLOSING STOCK
ETP SALT TOTAL (ETP SLUDGE+ SALT)
ALL FIGURES IN MT/ MONTH
Jan 15 20.331 27.92 138.33 166.25 167.75 18.831
Feb 15 18.831 29.47 136.28 165.75 167.94 16.641
Mar 15 16.641 28.29 137.36 165.65 161.17 21.121
April'15 21.121 28.5 138.8 167.3 167.64 20.781
May.’15 20.781 29.59 136.11 165.70 165.49 20.991
June’15 20.991 29.0 132.00 161.00 163.31 18.681
Compliance Report for the conditions in the Environmental Clearance # J.11011/117/2002-IA.II dated 17.07.2003 & Environmental Clearance # J.11011/407/2006-IA.II (I) dated 04.04.2007
issued by Ministry of Environment and Forests, New Delhi for expansion of pesticide unit by United Phosphorus Ltd., Unit # 01, Ankleshwar, Gujarat
Period from January 2015-June 2015
Page 55 of 55
TOTAL LANDFILL WASTE DETAILS –MT
MONTH (ETP SLUDGE + SALT)* DCP SLUDGE** NON-RECYCLABLE PLASTIC WASTE/INSULATION
WASTE
TOTAL
Jan 15 167.75 1365.12 24.98 1557.9
Feb 15 167.94 820.53 11.33 999.80
Mar 15 161.17 950.71 18.67
1130.55
April'15 167.64 1081.84 35.79 1285.27
May.’15 165.49 748.60 23.43 937.52
June’15 163.31 801.68 14.21 979.2
DETAILS OF DCP SLUDGE (BY-PRODUCT / SOLD AS SOIL CONDITIONER)
MONTH OPENING STOCK (MT)
GENERATION (MT)
DISPATCH (MT) CLOSING STOCK (MT) PARTY* BEIL**
Jan 15 343.526 2400 811.5 1365.12 566.906
Feb 15 566.906 1100 421.25 820.53 425.126
Mar 15 425.126 1050 91.35 950.71 433.066
April'15 433.066 1250 251.41 1081.84 349.816
May.’15 349.816 1000 273.57 748.6 327.646
June’15 327.646 1000 278.57 801.68 247.396
(*) Sold as Soil Conditioner to below given end user:
1) SHREE CHARBHUJA AGRO FERTILIZER