14
September 13, 2016 THE ROAD TO HARBOR BRIDGE: Achieving Environmental Clearance on a Major Project for the State of Texas October 11, 2016

THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

THE ROAD TO HARBOR BRIDGE:Achieving Environmental Clearance on

a Major Project for the State of Texas

October 11, 2016

Page 2: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Richard O’Connell

Associate General Counsel

Christopher Amy,

Environmental Specialist

Page 3: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

US 181 Harbor Bridge Project

3

Constructed 1956-1959

Replacing the existing US 181

Harbor Bridge and

approaches over the Corpus

Christi Ship Channel.

2005-2007 Project Scoping

2010 FHWA determined EIS

developed under SAFETEA-LU

Procedures

2011 Published NOI to

prepare EIS

FHWA the lead Federal agency

with TxDOT as the joint lead

agency for the project

EPA, HUD & USCG were

Cooperating AgenciesCourtesy of Corpus Christi Caller Times

Page 4: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

US 181 Harbor Bridge Project

4

Page 5: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Harbor Bridge Public Involvement

5

Public Hearing Store Front Meetings

Page 6: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Developing Harbor Bridge Mitigation

6

Page 7: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Developing Harbor Bridge Mitigation

7

TxDOT and FHWA Commitments to

the Neighborhood

Implement Recreational

Enhancements

– Implement park mitigation

– Construct hike & bike trails

Noise Mitigation

Host Job Fairs

Provide Information on Workforce

Support

Develop Northside Neighborhood

Livability Plan

– Develop Historical Record of

neighborhoods

– Identify neighborhood needs and ideas

Page 8: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

The FEIS was published in November 2014

In March of 2015, FHWA received a complaint under Title VI of the Civil Rights Act

US 181 Harbor Bridge FEIS

Page 9: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

US 181 Harbor Bridge FEIS

Page 10: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

ROD signed January 8, 2016

Record of Decision

Page 11: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Voluntary Resolution Agreement

11

Page 12: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Voluntary Resolution Agreement

12

Page 13: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Community Advisory Board (CAB)

Meetings Monthly

• Where: (Oveal Williams Senior Center)

• First Meeting was held May 12th

Meetings will be professionally facilitated;

Open to the public;

• Citizens provide input during the public comment period

TxDOT responsibilities

– Collaborate with CAC on implementation of Agreements:

• Voluntary Acquisition

• Relocation Benefits

• Voluntary Restrictive Covenant

• Tenant relocation at D.N. Leathers

• 4(f) mitigation for T.C. Ayers and H.J. Williams Parks

– Document Meetings with CAB for update to FHWA

13

Page 14: THE ROAD TO HARBOR BRIDGE · September 13, 2016 US 181 Harbor Bridge Project 3 Constructed 1956-1959 Replacing the existing US 181 Harbor Bridge and approaches over the Corpus

September 13, 2016

Lessons Learned

14