Page 1: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Thermo Design Engineering

Process Plants for the Energy IndustryDesign Fabrication Installation

Page 2: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

2

Page 3: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Thermo Design Engineering (TDE) is one of Canada’s leading engineering, project management and fabrication companies, specializing in process plants and equipment for the oil and natural gas industry. Founded in 1979, TDE’s philosophy has always been to engineer, design and fabricate process equipment and systems that meet or exceed our clients’ expectations. Our commitment to maintaining the highest level of product quality ensures that every project delivers maximum value to our clients.

TDE offers a full range of services, including:

Feasibility studies

Project management

Process design engineering

Equipment design

Procurement

Equipment fabrication

Joint venture engineering & fabrication management

Site construction

Supervision

Commissioning and start up

Personnel training

After sales service and parts supply

Building on ExcellenceThermo Design Engineering

Service and Quality

3

Page 4: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

At TDE, we pride ourselves in our ability to address our clients’ needs by providing sound, cost effective engineering solutions.

To that end, we have assembled a talented team of process plant engineers, technologists, designers and support staff to serve our clients. This multidisciplinary engineering team provides a comprehensive range of services, including process, mechanical, structural, electrical, instrumentation, and control systems.

Our engineering team utilizes an advanced computer network, state of the art software and other technology to ensure quality, cost effective and efficient work. TDE has also developed its own in-house software for process simulation, equipment sizing and equipment specification.

When required, TDE can offer engineering only services or technology sharing with joint venture project and fabrication management.

Thermo Design Engineering has delivered complete process plants and turnkey facilities to all areas of the world, including remote areas with harsh climates and areas with unique national codes and standards. TDE also provides a broad range of in-house services, including:

Turnkey Operations

Engineered products for oil and natural gas production facilities

Control system for 320 MMSCFD cryogenic plant utilized Siemens PLC with a TDE developed human machine interface using Win CC on Windows in Russian and English.

Qualified Personnel and Technology

Engineering Solutions

4

• Projectmanagement

• Completemulti-disciplineengineeringservices

• Procurementofmajorequipment

• Equipmentfabricationorjointventurefabricationmanagement

• Logisticscoordination

• Constructionmanagementandsupervision

• Plantcommissioningandstartupservices

Page 5: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Turkmenistan Grass Roots LPG recovery plant built for Intergaz in Turkmenistan. This cryogenic plant features molecular sieve dehydration, a Mafi-Trench Turbo Expander to chill the inlet gas to –77 °C (–106°F) to condense hydrocarbon liquids and LPG fractionation. TDE supplied all process modules, pipe

rack, utilities, control room and electrical systems. Construction and start up were completed with local workforce under TDE supervision. Commissioning and start up was completed by TDE.

This table outlines some of the technology tools TDE uses to design and manage processing plant engineering, procurement, fabrication, installation and start-up.

Process Engineering Aspentech Engineering Suite – Hysys, Shell & Tube Heat Exchanger Design, Flare Network SizingPromax Process Simulation SoftwareVendor supplied programsTDE developed programs

Mechanical/Structural EngineeringCompress pressure vessel design programCAESAR II piping stress analysis programRISA 2D / 3D structural steel stress analysisTDE developed programs

Engineered DrawingsAutoCAD – computer aided design softwareBentley Autoplant – 3D modeling of equipment and pipingPDMS – 3D modeling of equipment, structural and pipingTekla Structures – 3D modeling of structures

Instrumentation EngineeringISA I&V database (DesignIt)FLOWEL orifice softwareManufacturers’ software packagesTDE developed databases

Control Systems EngineeringPLC Programming – Allen-Bradley, Siemens, Schneider HMI Programming –Wonderware, CitectDCS Programming –Emerson Delta V, Yokagawa, ABBSIS Programming – Triconex, Hima, Emerson, ABB

Project ControlsMS ProjectsTimberline – accounting, purchasing & job cost softwareTimberline Precision EstimatingTDE proprietary estimating software

5

Page 6: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

TDE Oil and Gas Processing Units in Tuha Field, China, include a 300,000 m3/d LPG/NGL recovery plant fabricated in Canada and a 100,000 m3/d LPG/NGL recovery plant fabricated in China utilizing TDE design and TDE supplied components. Oil is processed in a 1,000,000 tonne /year oil stabilization plant designed by TDE and manufactured under a partnership of TDE and Daqing Energy.

China

Modularization and Transportation

Delivering the Product

TDE helped pioneer natural gas processing plant modularization and is now one of the world’s leading exporters of this expertise.

Modular design saves both time and money when compared to traditional on-site construction. TDE configures the processing equipment inside a quality controlled environment where manufacturing can take place quickly.

TDE ships the processing plant by truck, rail, ship, barge and air in sections or modules. Each module is designed to suit the mode of transportation by which it will be shipped. This helps to ensure on-time delivery anywhere in the world.

Once the modules reach their destination, they can be installed and commissioned in a matter of weeks. If the clients’ needs change in the future, the modular construction allows for relocation of the plant. TDE processing plants are operating in Canada, United States, Mexico, Brazil, Poland, Russia, Turkmenistan, Kazakhstan, Libya, Tunisia, Angola, Syria, Iran, Kuwait, India, Pakistan, Bangladesh, Indonesia and China.

6

Page 7: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Angola TDE supplied a LPG recovery plant to Chevron for installation in Cabinda, Angola. Supply included TDE packaged reciprocating gas compressor, gas chilling using mechanical refrigeration, LPG fractionation and associated utility systems.

Glycol Dehydration facility manufactured in TDE shops as modules complete with knock down stairway and platforms. Modules were shipped from Edmonton, Canada to Brazil and erected under TDE supervision.

Modular construction offers the advantage of custom design and fabrication to meet client specifications and regional shipping limits. Modules can be factory assembled and function tested at the TDE fabrication facility prior to disassembly and delivery to field location.

7

Page 8: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

TransportationDelivering the Product

TEG glycol contactor exiting TDE shop was trucked to a local rail siding and delivered by rail to Houston, Texas. The contactor with a wall thickness of 4 inches (102mm) and a shipping weight of 437,000 lbs (198,220 kg) was built to ASME Section VIII, Division 2 code and was installed on an offshore platform in the Gulf of Mexico.

Glycol dehydration vessels and process modules are packaged and ready for shipment from TDE’s yard. To satisfy the client’s stringent delivery schedule and first gas date, the equipment was shipped from Edmonton, Canada to Poland aboard a Russian Ilyushin-76TD cargo plane.

TDE recently supplied 2 identical 30 mmscfd refrigeration plants and amine plants to Birchcliff Energy for installation in British Columbia. TDE designed, fabricated, commissioned and started up the equipment. Birchcliff is so pleased with Thermo Design’s work that they recently orderd a third larger capacity set of equipment from TDE

British Columbia, Canada

8

Page 9: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Facilities/Manufacturing CapabilitiesRoom for Innovation

Libya

TDE has its design and manufacturing facilities in Edmonton located on 16 acres. Two office buildings hold the design staff, administration and corporate headquarters. Six shops contain the fabrication and assembly facilities. Each shop has multiple bridge cranes and all-terrain mobile cranes for assembly and yard work

• Mainofficebuildingis17,000squarefeet.Itholdsthe design staff and corporate headquarters.

• Additionaldesignofficesof17,000sqftholdadditional design staff

• Vessel fabrication shop is 27,300 square feet and has single vessel capacity of 250 tons and 20 feet diameter

• 1200 amps of continuous-feed multi-head submerged-arc automatic welding

• Pipe spooling shop is 8,200 square feet and has RotoWeld 2000 computer-controlled welding machine for fabrication of medium and large diameter pipe spooling

• Structural shop is 25,200 square feet. It is used for fabrication of vessel internals, vessel components, skids, pipe racks and structural components

• Assembly shop is 14,700 square feet. It is used for assembly of process skids and modules

• Sandblasting shop is 9,200 square feet.

• Paint shop is 9,400 square feet.

• Dedicated facility for electronic control panel assembly, programming and testing

• Yard space for completion of module pipe rack assembly and marshalling of completed products

• Heated ware house facility

Control panel testing: A dual redundant GE Fanuc PLC control system manufactured for offshore application is assembled and tested in TDE’s dedicated panel shop.

An exhaust steam condenser manufactured by TDE for Alstom Power. The condenser contains 7,228 stainless steel tubes and is 4 m in diameter and 11 m long. The condenser was installed on a turbine waste heat recovery application at Shell Canada’s Scotford Refinery and power generation plant.

TDE designed and fabricated a 220 mmscfd glycol dehydration unit and refrigeration plant as well as a 28,000 bbls/d condensate stabilzation unit for Waha Oil in Libya at their Faregh II facility. TDE also assisted in the installation, commissioning and startup of the equipment.

9

Page 10: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Strong Client RelationshipsThe Core of Our Business

Turnkey Grass Roots Plants

The engineering, manufacturing and construction of a grass roots, turnkey plant requires a trusting relationship between the owner and their chosen engineering, procurement, fabrication (EPF) and construction company.

When the EPF and owner are thousands of miles apart and speak different languages, new challenges arise beyond the design and supply of process equipment. TDE has been able to meet these challenges and work with our clients around the world to meet their process plant needs. TDE can take responsibility for the entire process plant or enter joint venture agreements with our clients or their partners when this would maximize efficiency and economics.

At TDE, we are committed to quality and dedicated to satisfying our clients’ needs. As a result, we have forged long-term relationships with many of our clients.

OAO Yakutgazprom

When OAO “Yakutgazprom” decided to build a gas processing and LPG recovery plant in eastern Siberia to satisfy local needs, TDE was awarded the contract. During the subsequent 10 years, the plant has been expanded twice. Both times, TDE was the “Yakutgazprom” supplier of choice. We continue to service the plant and are working with “Yakutgazprom” in planning for their future needs.

PetroBras

Thermo Design recently designed and fabricated two gas processing plants for PetroBras in Brazil, a 90 MMSCFD turbo expander C3+ recovery plant and a 129 MMSCFD TEG dehydration plant. Thermo Design sent experienced senior staff to the job site for construction installation supervision of the modular units followed by commissioning, start up, performance testing and operator training. Working together with the customer, our staff ensured that both plants were completed and started quickly and smoothly.

Polish Oil & Gas Corporation

When Polish Oil & Gas Corporation (POGC) had to process sour gas and liquids in its Zielin Field, they decided to construct a gas processing plant – the first to be built by POGC in Poland. In 1995, TDE was selected to engineer, fabricate, install and start up the original plant. TDE subsequently completed an expansion project in 1999. TDE continues to provide parts, service and engineering support services to the Zielin plant and other gas producing fields for POGC.

TDE was awarded a contract with Karakudukmunai/Lukoil, in June 2007, to supply an Oil Processing Plant with a nominal inlet oil flow of 6,000 m3/day plus an Associated Gas Processing plant designed for a capacity of 15,600 Nm3/hr. The contract included: detailed design and fabrication of the Crude Oil and Gas Processing Plants; supervision of field assembly of the modular TDE supplied equipment; responsibility for commissioning, startup and operational performance test. The complete facility was operational in February 2009

Karakuduk

10

Page 11: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Russia Thermo Design was awarded a contract with ZAO Stimul, to expand the existing facilities of an Oil and Gas Processing Plant near the Orenburg Region of Russia. The scope of the project includes the design and supply of equipment to upgrade the existing train, and supply an additional train, each with the ability to process reservoir fluids to a maximum of 500,000 tonnes/year in product crude oil. In addition, the design services for the future phases of the plant expansion were to be completed, including one more processing train to bring the production of the plant to 1,500,000 tonnes/year. The project was completed in 2008

11

Yakutgazprom — The Yakutsk Gas Plant process, electrical and pipe rack modules were shipped from TDE and installed during the short Siberian summer. The equipment was designed and manufactured for Russia’s severe Siberian climate using proven northern Alberta technology.

Polish Oil & Gas Company — The Zielin Gas Plant includes wellhead facilities, condensate stabilization, amine unit, three stage ‘CLAUS’ sulphur recovery unit, refrigeration unit, LPG recovery, all required utilities and control systems.

PetroBras — TDE designed and fabricated a turbo expander package, glycol dehydration unit and a condensate stabilization unit for the Catu facility. TDE also supplied the necessary control system, supervised the equipment installation and commissioned and started up the equipment.

Page 12: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

OrenburgNeft

In 1992, TDE began its relationship with OrenburgNeft of Russia. OrenburgNeft faced the challenge of treating one million tonnes per year of crude oil at the unusually high pressure of 490 psig (4068 kPag) (vessel design pressure). OrenburgNeft wanted the crude to be preheated externally from the treaters and then electrostatically treated. TDE was there to provide the fabricated process modules, including free water knock out vessels, heaters, treaters, shell and tube heat exchangers, modular pipe rack, control room and SCADA-based control system. In addition, TDE was responsible for field construction and start up of the facility.

As a result of this success, TDE was awarded the contract to engineer, fabricate, install, commission and start up a 220 MMSCFD (2.2 billion m3/year) grass roots turnkey gas processing plant. The TDE supplied gas processing plant included:

• Inletgashandling

• Gasturbinedriveninletgascompressors

• Propanerefrigerationloopcompletewithgasturbinedriven centrifugal compressors

• Liquidhydrocarbonrecoveryequipment

• LPGfractionationplant

In addition, TDE supplied the plant utility systems, including:

• 10megawattsofgasturbineelectricpowergenerationwith 6000V and 660 V switch gear

• Lowandhighpressuresteamgenerationutilizingwaste heat recovery boilers and fired boilers

• Plantair&andnitrogengenerationfacilitieswithstorage

TDE also supplied, programmed and commissioned the plant DCS (distributed control system) and ESD PLC (emergency shutdown programmable logic controllers).

Our cooperation with OrenburgNeft included the preparation of an engineering study for an oil stabilization plant and mini refinery to be installed on the site of the Zaikinskoye Gas Processing Plant.

Tyumen Neft Company (TNK) of Russia subsequently purchased OrenburgNeft. TDE continues to service our past projects and is working with TNK to explore new opportunities for the supply of oil and gas production equipment.

12

Zaikinskoye Gas Processing Plant under construction

Russia

Page 13: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Quality ControlDoing it Right

From the frigid waters of the Atlantic Ocean off Canada’s East Coast to the tropical waters of the Gulf of Mexico or South China Sea, TDE has supplied equipment for fixed shallow water platforms and floating production, storage and offloading vessels (FPSO).

Offshore applications require sound engineering and rigorous quality control during manufacturing. TDE has answered this challenge.

Total Quality Management System

TDE employs a Total Quality Management System. Our Quality Control System is registered with the American Society for Mechanical Engineers (ASME), the National Board of Boilers and Pressure Vessel Inspectors (NBBI), and the Alberta Boilers Safety Association (ABSA). TDE also holds Certificates of Authorization that allow us to operate in the following specialty areas:

• Designandfabricationofpressurevessels (ASME Div. I and Div. II) and heat exchangers

• Fabricationofpowerboilers,directandindirectheating coils

• Pressurepipingfabrication

• Pressurevesselrepairsandalterationstoexistingpressure equipment

• Conductperformancequalificationtestingofweldersand machine operators

13

Indonesia

The Petro-Canada Terra Nova Floating Production

Storage and Offloading (FPSO) vessel sailing to its

location 350 kilometers east of Newfoundland, Canada.

TDE manufactured glycol regeneration modules

assembled in TDE yard. The system regenerated 65 USGPM of TEG to 99 wt%

using an electric reboiler and stripping column. The

modules were manufactured to withstand the harsh Atlantic environment and wave action

experienced on the FPSO.

TDE supplied a 470 MMSCFD natural gas TEG dehydration facility to Mobil Oil Indonesia. The facility included two parallel trains of gas processing and glycol regeneration. All engineering was completed by TDE and fabrication was completed in Canada and Indonesia to satisfy local content requirements. Commissioning and start up included TDE personnel.

Page 14: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Project ProfilesPEMEX AKAL-GC Offshore Platform, Gulf of Mexico

Combisa EPC-22 PEMEX Offshore Platform, Gulf of Mexico

Owner — PEMEX of Mexico

Operator — Westcoast Energy of Canada

Process Equipment supplied by TDE —

EPC — Halliburton KBR (formerly Brown & Root Energy Services)

Owner — PEMEX of Mexico

Process Equipment supplied by TDE —

Sour Gas TEG Dehydration Facility processing 250 MMSCFD of natural gas

Gas Compression Suction, Interstage and Discharge Scrubbers

Flare Knockout Vessel

Sour Gas TEG Dehydration Facility processing 664 MMSCFD of natural gas. Glycol regenerated in twin train stacked process modules

Sour Produced Water Treatment Facility processing 300 USGPM of water

Gas Compression Scrubbers

14

Page 15: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Shanul, Iran Lukoil Komi LKA, Russia

15

Thermo Design was awarded a contract, in December 2004, to supply a 20,000 bbls/d condensate stabilization plant and plant utilities packages which included heat medium system,cooling water and fire water systems. The project was completed in December 2006.

The contract included the following Thermo Design supplied equipment and services:

• DetailedDesign(process,mechanical,electrical,civil,instrumentation and control) and fabrication of the condensate stabilization plant and plant utilities packages

• FireDetectionandMonitoringSystems&FireFightingFacilities

• InterconnectingPiperackandUndergroundPiping–Design, supply of Raw Materials and supervision of installation

• DCS,ESDandF&GControlSystemsforAllNewUnits

• DesignofEquipmentFoundations&ConcretePiles

• UtilitySubstationandProcessSubstationSwitchgearandMCC Equipment

• DCandACUPSsystems

• SiteConstructionSupervision

• Pre-Commissioning/Commissioning

• CustomerTraining,StartupandPerformanceTest

Thermo Design was awarded a contract, in March 2008,to supply a Heavy Crude Oil and Heat Medium Heating Plant designed for the Russian arctic. The contract also included supply of a heat medium system. The project was completed in late 2009.

The contract includes the following Thermo Design supplied equipment and services:

• DetailedDesignandfabricationoftheCrudeOilHeatingand Heat Medium Units.

• SupervisionoffieldassemblyofthemodularThermoDesign supplied equipment.

• Responsibilityforcommissioning,startupandoperationalperformance test.

Thermo Design was awarded a contract, in December 2003, to supply LPG Recovery Plant with a nominal inlet gas flow of 3,000,000 m3/day @ 80 barg and 55°C. The Plant consists of two (2) identical parallel trains with 3,000,000 m3/day capacity each, built and delivered on a “turn-key” project basis. The project was completed in 2006 with ongoing operations support thru 2007.

The contract included the following Thermo Design supplied equipment and services:

• DetailedDesign(process,mechanical,electrical,instrumentation and control) and fabrication of the LPG Recovery Plant.

• Shoptestingofallequipmentandsystempriortoshipping.

• SitecivilworksandfieldassemblyofthemodularThermoDesign supplied equipment.

• Responsibilityforcommissioning,startupandoperationalperformance test.

Bagadja, Turkmenistan

Page 16: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

ExpertisePackaged Processing Facilities

Component and Custom Fabrication

Liquified Petroleum Gas (LPG) Recovery / Dewpoint Control UnitsHydrocarbon Dewpoint Control / LPG Recovery: Joule-Thompson Expansion (Auto-Refrigeration)Silica Gel AdsorptionMechanical Refrigeration (Propane, Ammonia)Lean Oil AdsorptionDeep Cut (Cryogenic) LPG Recovery:Turbo Expander ProcessesEthane ExtractionCascade Refrigeration

Liquids Fractionation & DistillationProduct Fractionation – Deethanization, LPG, NGL ProductsProduct Stabilization

Gas Sweetening Units (H2S, CO2, Mercaptan Removal)Amine Absorption (Selective & Non-Selective)Fixed Bed (Molecular Sieve, Iron Sponge, etc.)Caustic SweeteningLPG/NGL Sweetening

Sulphur Recovery UnitsClaus and SuperClaus UnitsProTherm (Chelate) Process

Gas Compression SystemsElectric Motor or Engine Drive Reciprocating, Centrifugal, Screw, Rotary Vane, DiaphragmRefrigeration Compressor PackagesGas Booster Compressor PackagesAcid Gas Injection Compressor PackagesVapour Recovery Packages

Gas Dehydration UnitsEthylene/Diethylene Glycol Injection Diethylene/Triethylene Glycol AbsorptionDrizo Dehydration UnitsMolecular Sieve Adsorption

Custom Pressure Vessel Fabrication

Custom Exchanger Fabrication to TEMA Specifications

Custom Module Fabrication

Piping Systems

Repair and Refit Work

Specialized Alloy Welding (Low Temperature / Stainless / Exotic Metals)

Structural Assemblies

Thermo Design is committed to supplying comprehensive oil processing products with the best technology available. To meet our customers needs in heavy oil and bitumen processing Thermo Design has combined our expertise with ProSep Technologies design and fabricate horizontal flow treaters for heavy oil and bitumen production.

A horizontal flow treater offers several advantages over a conventional upflow treater in heavy oil applications. As the process fluid flows through the vessel and the water droplets suspended in the oil phase coalesce into larger droplets until they reach the a critical diameter where Stokes’ Law applies. Stokes Law defines the terminal settling velocity of a particle as it falls through a fluid. In a horizontal flow treater the settling velocity is perpendicular to the process flow velocity whereas the upflow treater design has a process flow velocity that opposes the settling velocity as defined in Stokes Law. The result is that if the parameters in Stokes Law are fixed, a horizontal flow regime can remove a smaller droplet size then a conventional upflow treater, which results in a more efficient system.

A horizontal flow treater uses a vertical electrostatic grid system. As the oil phase progresses through the vessel it can be exposed to several stages of electrostatic fields of varying potentials. Built-in adjustability allows these fields to match the water content remaining in the oil phase, thus ensuring complete dehydration.

One further advantage is the ability to incorporate mechanical coalescers in combination with the electrostatic grids. These coalescers can be placed in the process stream to provide either bulk or polished coalescence which further enhances the dehydration capability of the treater.

Fired HeatersDirect Fired Cabin Type FurnacesFiretube Heaters – Direct and Indirect FiredSalt Bath HeatersReconcentrators / ReboilersLine Heaters and Wellhead HeatersHelical coil direct fired heaters

Crude Oil ProcessingLight and heavy crude oil processingElectrostatic and mechanical dehydrators and desaltersFree water knockouts (FWKO)Production manifolds and separatorsMobile automated test separatorsMini-refineries/topping plants

Water TreatmentBoiler Feed Water Treatment and Condensate Collection SystemsProduced Water Treatment (Solids, Oil and H2S Removal)Produced Water Injection

Specialty Plants & FacilitiesBiomass ConversionSmall-Scale Petrochemical PlantsSmall Scale LNG Facilities

Plant Utility SystemsElectric Power Generation and Distribution FacilitiesNitrogen Generation and Storage FacilitiesInstrument Air SystemsProduct Storage, Loading and Unloading Facilities

Heavy Oil Processing

16

Page 17: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Nitrogen generation and storage/instrument air facility

Condensate stabilization reboiler heat exchangers

Molecular sieve dehydration

Claus unit reaction furnace

TDE packaged Mafi-Trench turboexpander

17

CERTIFICATES OF AUTHORIzATION

Association of Professional Engineers, Geologists, and Geophysicists of Alberta (APPEGA) Permit to Practice Engineering #2800

ASME – ‘U’ - 22145, ‘UM’ – 29162, ‘U2’ – 31217 Pressure Vessel Manufacturing

National Board of Boiler & Pressure Vessel Inspectors

Gosgortechnadzor of Russian Federation OOMT – No. 017809/10 (Oil & Gas Facilities)

GOST Standards of Russian Federation – No. 4026833 (Oil & Gas Facilities)

Canadian Welding Bureau (CWB)

UDT (Poland) UC-291/3 import of Pressure Vessels

CBPVI (China) import of Pressure Vessels

REGISTERED PROGRAMS

Quality Control Program (ABSA) – AQP-1104(S)

Pressure Welders Qualification Program (ABSA) – AOQP-7027

Pressure Piping (ANSI) – B31.1, B31.3, B31.5

Repair & Alteration of Pressure Vessels (ABSA)

FABRICATION CODES & STANDARDS APPLIED

ASME Section VIII Div. 1 and 2 – Boiler & Pressure Vessel Codes

ASME Section IV Heating Boilers

ANSI – B31.1, B31.3, B31.5 Pressure Piping

Canadian Standards Association CSA B51

TEMA Heat Exchangers

API – American Petroleum Institute

National Association of Corrosion Engineers

NACE MR-0175-99

AWS – American Welding Society

Russian National Standards

Polish National Standards

Other standards as required for projects

INSPECTION & TESTING STANDARDS

American Society for Non Destructive Testing SNT-TC-1A

Canadian General Standards Board (CGSB)

American Welding Society AWS-QC1-96

Non Destructive Examination

Radiographic and Ultrasonic Testing

Magnetic Particle Inspection

Dye Penetrant Inspection

Brinnell Hardness

Quality at a Glance

Crude oil electrostatic treaters

TDE packaged Nuovo Pignone hydrogen compressor

Ten Megawatt power generation and distribution plant

Page 18: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Thermo Design Engineering Ltd. (TDE) believes an effective Health, Safety & Environment Policy is essential to our business operation and is fully committed to this policy through the cooperation of senior management and employees at all levels.

TDE strives to maintain and continuously improve high standards of health, safety and environmental practice throughout all its operations. TDE is committed to create a working environment in which accidents will not occur, and in which employees, contractors and the public will not be exposed to safety or health hazards. It is also our aim to minimize the impact of our operations on the environment.

We aim to provide and maintain safe and healthy working conditions, equipment and systems of work for all our employees and to provide them with the necessary information, instruction, equipment and training to achieve this. Appropriate preventative and protective measures are, and will continue to be, implemented following the identification of work and related hazards and assessment of the risks associated with them.

This Health, Safety and Environment policy has been endorsed by senior management, who take prime responsibility for providing the necessary resources to ensure it's objectives are achieved. All employees and contractors of TDE must acknowledge their responsibility for protection of Health, Safety and Environment by making it the top priority in all aspects of their work.

Policy StatementOccupational Health and Safety

Certificates & RecognitionTDE has been a partner with WCB since 1996, obtaining the following certificates

Partners in Injury

Reducation Program (P.I.R)

Certificate of Recognition (C.O.R.)

TrainingTDE is committed to providing all employees with training to help develop the necessary skills to conduct pre-use inspections, the selection and limitations, the required specific hazard controls, the basic mechanical and the maintenance requirements of the equipment, tool or material used on the job.

TDE conducts job specific training to ensure that each employee can do the job and knows how to do it right.

Training is conducted at orientation, safety meetings, when an employee is assigned new or different work, when an employee is moved to a new site or location, when a new process or material is introduced or after an incident and, is reviewed at regularly scheduled intervals.

We strongly believe that training is the right path to take to improve the quality and effectiveness of the OHSE program at TDE.

18

Jim Montgomery, P.Eng TDE President

Page 19: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

Client List

Alstom Power, Canada, Sweden, France

Braskem, Brazil

Brown & Root (Halliburton), U.S.A.

Caltex Pacific, Indonesia

CCR/Sakhalin, Russia

Chart Energy & Chemicals, U.S.A.

China National Offshore Oil Corporation (CNOOC)

Constructora De Equipos De Compresion S.A. de C.V., Mexico

Daqing Energy Resource Technical Exploitation Company, Peoples’ Republic of China

Dragon Oil, Turkmenistan

EnergoBaltic, Poland

Energy Equity, Indonesia

Energy World, Hong Kong

Exspan, Indonesia

Falcon Oil & Gas Ltd., Romania

Iranian Central Oilfield Company, Iran

Iranian Offshore Oil Company, Iran

Irasco, Iran

Karakudukmunai, Kazakhstan

Kirishineftechimexport, Turkmenistan

Kuwait Oil Company, Kuwait

Lukoil Overseas, Kasakhstan

McDermott International, Inc., U.S.A.

Mobil Oil, Indonesia

National Iranian Gas Company, Iran

North Abu QIR, Egypt

Nuovo Pignone, Italy

Occidental International Petroleum, U.S.A.

Oil Industries Engineering & Construction, Iran

Oil India, India

OOO Monolit, Russia

Orenburgneft, Russia

PBG S.A., Poland

Pemex, Mexico

Perenco, Tunisia

Petrobras, Brazil

PetroChina Changqing Oilfield Co., Peoples’ Republic of China

Petrofac International Ltd, United Kingdom

PGNiG S.A., Poland

Polish Oil & Gas Company, Poland

Pokrovka, Russia

ProSep Technologies, U.S.A.

Sinopec Sichuan, China

Societé Nationale Des Hydrocarbures, Cameroon

SONANGOL, Angola

Sonatrach, Algeria

SRB Suedrohrbau GmbH, Germany

Stimul (Division of Gazprom), Russia

Syrian Petroleum Company, Syria

Titas Gas, Bangledesh

TNK BP Orenburgneft, Russia

Turkmengas, Turkmenistan

TurkmenNeft, Turkmenistan

UCH Power Company, Pakistan

Uzenmunaigaz, Kazakhstan

Vareyeganneft, Russia

Waha Oil Company, Libya

Yakutgasprom, Siberia

Yuzhkazneftegaz, Kazakhstan

International Clients

Canadian Oil & Gas / Petro-Chemical Industry ClientsAgrium Inc.

Alberta Energy Company

Alberta Gas Ethylene

Alberta Mobile Air

Alberta Natural Gas

Alberta Research Council

Amerada Minerals

AMEC Americas

Amoco Petroleum

Atcor

Atlas Copco

Bankeno Resources

B.P. Exploration Canada

Bechtel Canada Limited

Birchcliff Energy Ltd

Bluerange Resources

Bonanza Resources

Britannia Industries

BS&B Canada

Burlington Resources

Cabre Exploration

Canadian Hunter Exploration

Canadian Midstream Services

Canadian Occidental Petroleum

Canadian Superior Oil

Centra Gas

Chevron Canada Resources

Chieftain International

Co-Enerco

Colt Engineering

Columbia Natural Gas

Compton Petroleum

Concise Design

Corridor Resources

Coseka Resources

Crestar Energy

CS Resources

CU Gas

Czar Resources

Darsi Engineering

Dekalb Petroleum

Delta Catalytic

Denison Mines

Discovery West Corp.

Dome Petroleum

D.P.H. Engineering

Electric Power Research Institute

EnCana

Encor

Energy Spectrum

Equinox Engineering

Esso Chemical Canada

Esso Resources Canada

Fluor / Daniel

Francanca Oil & Gas

Gardiner Oil & Gas

General American Oils

GPT Engineering

Gulf Resources

Home Oil

Hood Engineering

Husky Energy

ICG

IMV Projects

Inland Natural Gas

International Atlantis Resources

International Colin Energy

Keyspan Energy

Kinetic Projects

Ladd Exploration

Laforge

Lloydminster Gas Company

Longview Resource Management

Luscar Ltd.

MacDonald Engineering Projects

Merland Explorations

Mission Oil & Gas

MLC Oil & Gas

Mobil Oil Canada

Mohawk Oil

Morgan Hydrocarbons

Morrison Petroleum

New Gateway Oil and Minerals

Newalta

Norcen Energy

NovaCor / Novalta

Novagas Clearinghouse

Numac Oil & Gas

O’Rourke Engineering

Oakwood Petroleum

Ocelot Industries

Omega Hydrocarbons

OPC Engineering

Oriole Energy

Pacific Cassiar

PanCanadian Petroleum

Pengrowth Energy

Petro Canada

PetroFina

Pioneer Natural Resources

Poco Petroleums

Probe Exploration

Quadron Resources

Quantel Engineering

Quasar Petroleum

Ranchmens Resources

Ranger Oil Canada

Renaissance Resources

Roan Resources

RTM Engineering

Ryerson Oil & Gas

Sabine Canada

Saratoga Processing

SaskOil Corporation

Sceptre Resources

Scion Engineering

Shell Canada Resources

Shell Scotford Refinery

Signalta Resources

Simon-Carves of Canada

SNC-Lavalin

Solaris Management Consultants

Star Oil and Gas

Sulpetro

Suncor Energy

Sundance Oil Canada

Swinarton Engineering

Syncrude Canada Ltd.

Talisman Energy

Tartan Engineering

Texas Pacific Oil Canada

Tri-Dyne Projects

Trysol Canada Ltd.

Tuxtla Engineering

Ultramar Canada

Voyager Petroleum

Wainoco

Wascana Energy

Westcoast Energy

Western Decalta Petroleum

Weyerhauser Canada

19

Page 20: Thermo Design Engineering - omni-es.com Brochure.pdf · CAESAR II piping stress analysis program ... Bentley Autoplant – 3D modeling of equipment and piping PDMS – 3D modeling

www.thermodesign.com

e-mail: [email protected]

Engineering Offices and Manufacturing HeadquartersThermo Design Engineering Ltd. 1424 – 70th Avenue Box 5557 SECSC Edmonton, Alberta T6P 1P5

Telephone: (780) 440-6064 Facsimile: (780) 440-1657 E-mail: [email protected]

Canadian Sales Office#300, 400 5th Avenue SW Calgary, Alberta T2P 0L6 Telephone: (403) 269-3724 Facsimile: (403) 266-4849 E-mail: [email protected]

Sales Offices in:China Eastern Europe Iran Russia Turkmenistan India Bangladesh Indonesia Brazil Mexico

International Marketing ArmTDE Overseas Ltd. Suite 401 Karyatis Building #8 Athos Street Nicosia, Cyprus, 1087

or

Post Office Box 26646 Nicosia, Cyprus, 1646 Telephone: (357) 02-318326 Facsimile: (357) 02-317484