Upload
kaynpti
View
229
Download
0
Embed Size (px)
Citation preview
8/2/2019 Transmission Pricing India
1/20
TRANSMISSION PRICING
8/2/2019 Transmission Pricing India
2/20
EVOLUTION OF
TRANSMISSION PRICING
Stage
I
Cost ofTransmissionclubbed withGenerationTariff
Stage II
Determinedon the basisof energydrawn
(Usage Based)
Stage III
Determinedon the basisof MWentitlements
(AccessBased)
Stage IV
HybridMethodologylike NodalBased.
Upto 19911992-2002
2002-2011
2011onwards
8/2/2019 Transmission Pricing India
3/20
EA-2003 AND NATIONAL
ELECTRICITY PLAN
EA-2003: Facilitate competitive markets
Generation De-licensed
Non-dDscriminatory open access
Efficient, coordinated and economical development of ISTS
Prior agreement with beneficiaries not a pre-condition for ISTSdevelopment
CTU/STU should undertake network expansion after identifying therequirements in consultation with stakeholders and taking up theexecution after due regulatory approvals.
Transmission tariff to be made sensitive to distance, direction andquantum of flow.
8/2/2019 Transmission Pricing India
4/20
TARIFF POLICY ON
TRANSMISSION PRICING
Sensitive to distance, direction and quantum
Sharing in proportion to utilization
Facilitate planned development/augmentation
Discourage non-optimal investment
Prior agreement not pre-condition
Apportionment of losses- distance and direction
sensitive.
8/2/2019 Transmission Pricing India
5/20
NEED FOR CHANGE IN
PRICING FRAMEWORK
Synchronous integration of Regions.
Changes caused by law and policy.
Open Access and Competitive Power Markets
Pricing Inefficiencies.
National Grid / Trans-regional Grid
Changing Network utilization.
Agreement of beneficiaries a challenge.
8/2/2019 Transmission Pricing India
6/20
TYPESOF TARIFFS
Postage stamp
Contract Path Method
MW-Mile
Point of Connection
8/2/2019 Transmission Pricing India
7/20
POSTAGE STAMP METHOD
A postage stamp rate is a flat per kW charge for network access
within a particular zone, based on average system costs. Postage
stamp transmission tariffs allocate total system costs to consumers
on the basis of load share/Energy share.
This method results in higher costs above marginal costs because it
incorporates historical fixed costs. The cost for transmitting power
within the zone is independent of the transmission distance.
A generator transmitting to a load in a different zone would have topay the postage stamp charges for the zone of origin and the zone
of delivery, and also any intervening zones. This accumulation of
zone access charges is often called pan-caking
8/2/2019 Transmission Pricing India
8/20
POSTAGE STAMP METHOD
The advantage of using this method is that it is easy to administer. It
does not reflect marginal costs except in a special circumstance
where all generators are at equal distances from load and where
the load on each line is equal.
In this method the total charge has been divided into two
components
Actual power Transmission charges
Charges for transmission losses
8/2/2019 Transmission Pricing India
9/20
THE MW-MILEMETHOD
The MW-Mile method calculates the flow at each circuit
caused by the generation/load pattern of each agent based
on a power flow model. Costs are then allocated in proportion
to ratio of power flow and circuit capacity.
According to this method the embedded cost of transmission
facility is allocated based on the changes in power flowcaused by a transaction in a transmission line and length of
the line. This method is also called Line-by-Line method.
8/2/2019 Transmission Pricing India
10/20
THE CONTRACT PATHMETHOD
Sensitive to distance:
The contract path shall be the shortest route formed by
series of transmission lines capable of carrying contractedpower between the point of receipt to point of delivery in
the wheeling system. Monthly transmission charges of this
path would be payable in proportion to contracted power.
Provides wrong economic signal, based on fictitious path,power flow on parallel path is ignored
8/2/2019 Transmission Pricing India
11/20
POINTOF CONNECTION
It is the latest transmission charge pricing methodology
introduced for sharing of Inter State Transmission Systems (ISTS)
charges and Losses among the Designated ISTS Customers (DICs)depending on their location and sensitive to their distances
from load centers and generation and the direction of the node
in the grid.
The need for this method was triggered due to the problemsconfronted in the application of the present Regional Postage
Stamp Method which implied that all the users of a system in a
region pay same price/MW of allotted transmission capacity.
8/2/2019 Transmission Pricing India
12/20
COMPUTATION OF POC
CHARGES
Average YTC per circuit km (for each voltage level & conductor
configuration) shall be used for computation of charges.
PoC Charges to be computed for 5 blocks of month for peak and other
the peak conditions
Representative Blocks of Months
April to June July to September
October to November
December to February
March
8/2/2019 Transmission Pricing India
13/20
COMPUTATION OF POC
CHARGES
Average YTC to be apportioned to peak and other than peak
based on the no. of hours constituting these periods.
50% recovery through Hybrid Methodology and 50% through
Uniform Charge Sharing Mechanism(for first two years ).
Loss Allocation Factor to be computed for each season using
Hybrid Methodology
50% losses through Hybrid Method and 50% through
Uniform Loss Allocation Mechanism(for first two years)
8/2/2019 Transmission Pricing India
14/20
COMPUTATION OF POC
CHARGES
Criteria for Zoning of nodes:
Costs within the same range
Geographically and electrically proximate
Nodes with connectivity to Thermal Generators > 1500 MW or
Hydro Generators > 500 MW to be taken as separate zone.
Except NER states where entire region is to be taken as one zone.
Zonal Charges : Weighted Average of Nodal Charges
8/2/2019 Transmission Pricing India
15/20
COMPUTATION OF POC
CHARGES
Generating stations connected to ISTS network < 400KVwould be charged at zonal charges where physically located
No transmission charges/losses for solar projects (for theentire useful life) commissioned within next 3 years.
In the event of a Designated ISTS Customer failing to provideits requisition for demand or injection for an Application
Period, the last demand or injection forecast supplied by theDIC and as adjusted by the Implementing Agency for LoadFlow Analysis shall be deemed to be Approved Withdrawalor Approved Injection
8/2/2019 Transmission Pricing India
16/20
SPECIFIC CHARGES
For deviation > 20% in any time block, the DIC shall be
required to pay transmission charges for excess generation
@ 25% above the zonal POC charges determined for zonewhere the Designated ISTS Customer is physically located
Payment on account of additional charges for deviation bythe generator shall not be charged to its long term customer
and shall be payable by the generator
8/2/2019 Transmission Pricing India
17/20
INDIRECT METHODFOR
HVDC COST ALLOCATION
Compute Transmission Charges for all load and generators with all HVDC
lines in service.
Disconnect HVDC line and again compute new transmission charges for all
loads and generators
Compute difference between nodal charges with or without HVDC.
Identify nodes which benefits with the presence of HVDC
[Benefit = (old cost i.e. base case with injection) minus (new usage cost i.e. withlink disconnected)]
In case benefit is ve, same to be collared to zero
Allocate HVDC line cost to the identified nodes.
8/2/2019 Transmission Pricing India
18/20
COMPARISONOFDIFFERENT
METHODS IN TRANSMISSION PRICING
Postage Stamp Method
Positive: Simple, familiar, most widely used in developing market
Negative : Insensitive to distance & direction
Contract Path Methodology
Positive: Sensitive to distance
Negative: Provides wrong economic signal, based on fictitiouspath, power flow on parallel path is ignored
8/2/2019 Transmission Pricing India
19/20
COMPARISONOFDIFFERENT
METHODS IN TRANSMISSION PRICING
Distance Based MW-Mile Methodology
Positive: Simple, sensitive to distance
Negative: Based on physical distance, not on actual power flow.
Point tariff, Nodal Pricing or Locational Marginal Pricing (LMP)
Positive: Provides economic signals, suitable for developed /
saturated market
Negative: Complex, not suitable for developing market, lossesforms the part of transmission pricing, based on MWhnot on MW.
8/2/2019 Transmission Pricing India
20/20