Transmission Pricing India

  • Upload
    kaynpti

  • View
    229

  • Download
    0

Embed Size (px)

Citation preview

  • 8/2/2019 Transmission Pricing India

    1/20

    TRANSMISSION PRICING

  • 8/2/2019 Transmission Pricing India

    2/20

    EVOLUTION OF

    TRANSMISSION PRICING

    Stage

    I

    Cost ofTransmissionclubbed withGenerationTariff

    Stage II

    Determinedon the basisof energydrawn

    (Usage Based)

    Stage III

    Determinedon the basisof MWentitlements

    (AccessBased)

    Stage IV

    HybridMethodologylike NodalBased.

    Upto 19911992-2002

    2002-2011

    2011onwards

  • 8/2/2019 Transmission Pricing India

    3/20

    EA-2003 AND NATIONAL

    ELECTRICITY PLAN

    EA-2003: Facilitate competitive markets

    Generation De-licensed

    Non-dDscriminatory open access

    Efficient, coordinated and economical development of ISTS

    Prior agreement with beneficiaries not a pre-condition for ISTSdevelopment

    CTU/STU should undertake network expansion after identifying therequirements in consultation with stakeholders and taking up theexecution after due regulatory approvals.

    Transmission tariff to be made sensitive to distance, direction andquantum of flow.

  • 8/2/2019 Transmission Pricing India

    4/20

    TARIFF POLICY ON

    TRANSMISSION PRICING

    Sensitive to distance, direction and quantum

    Sharing in proportion to utilization

    Facilitate planned development/augmentation

    Discourage non-optimal investment

    Prior agreement not pre-condition

    Apportionment of losses- distance and direction

    sensitive.

  • 8/2/2019 Transmission Pricing India

    5/20

    NEED FOR CHANGE IN

    PRICING FRAMEWORK

    Synchronous integration of Regions.

    Changes caused by law and policy.

    Open Access and Competitive Power Markets

    Pricing Inefficiencies.

    National Grid / Trans-regional Grid

    Changing Network utilization.

    Agreement of beneficiaries a challenge.

  • 8/2/2019 Transmission Pricing India

    6/20

    TYPESOF TARIFFS

    Postage stamp

    Contract Path Method

    MW-Mile

    Point of Connection

  • 8/2/2019 Transmission Pricing India

    7/20

    POSTAGE STAMP METHOD

    A postage stamp rate is a flat per kW charge for network access

    within a particular zone, based on average system costs. Postage

    stamp transmission tariffs allocate total system costs to consumers

    on the basis of load share/Energy share.

    This method results in higher costs above marginal costs because it

    incorporates historical fixed costs. The cost for transmitting power

    within the zone is independent of the transmission distance.

    A generator transmitting to a load in a different zone would have topay the postage stamp charges for the zone of origin and the zone

    of delivery, and also any intervening zones. This accumulation of

    zone access charges is often called pan-caking

  • 8/2/2019 Transmission Pricing India

    8/20

    POSTAGE STAMP METHOD

    The advantage of using this method is that it is easy to administer. It

    does not reflect marginal costs except in a special circumstance

    where all generators are at equal distances from load and where

    the load on each line is equal.

    In this method the total charge has been divided into two

    components

    Actual power Transmission charges

    Charges for transmission losses

  • 8/2/2019 Transmission Pricing India

    9/20

    THE MW-MILEMETHOD

    The MW-Mile method calculates the flow at each circuit

    caused by the generation/load pattern of each agent based

    on a power flow model. Costs are then allocated in proportion

    to ratio of power flow and circuit capacity.

    According to this method the embedded cost of transmission

    facility is allocated based on the changes in power flowcaused by a transaction in a transmission line and length of

    the line. This method is also called Line-by-Line method.

  • 8/2/2019 Transmission Pricing India

    10/20

    THE CONTRACT PATHMETHOD

    Sensitive to distance:

    The contract path shall be the shortest route formed by

    series of transmission lines capable of carrying contractedpower between the point of receipt to point of delivery in

    the wheeling system. Monthly transmission charges of this

    path would be payable in proportion to contracted power.

    Provides wrong economic signal, based on fictitious path,power flow on parallel path is ignored

  • 8/2/2019 Transmission Pricing India

    11/20

    POINTOF CONNECTION

    It is the latest transmission charge pricing methodology

    introduced for sharing of Inter State Transmission Systems (ISTS)

    charges and Losses among the Designated ISTS Customers (DICs)depending on their location and sensitive to their distances

    from load centers and generation and the direction of the node

    in the grid.

    The need for this method was triggered due to the problemsconfronted in the application of the present Regional Postage

    Stamp Method which implied that all the users of a system in a

    region pay same price/MW of allotted transmission capacity.

  • 8/2/2019 Transmission Pricing India

    12/20

    COMPUTATION OF POC

    CHARGES

    Average YTC per circuit km (for each voltage level & conductor

    configuration) shall be used for computation of charges.

    PoC Charges to be computed for 5 blocks of month for peak and other

    the peak conditions

    Representative Blocks of Months

    April to June July to September

    October to November

    December to February

    March

  • 8/2/2019 Transmission Pricing India

    13/20

    COMPUTATION OF POC

    CHARGES

    Average YTC to be apportioned to peak and other than peak

    based on the no. of hours constituting these periods.

    50% recovery through Hybrid Methodology and 50% through

    Uniform Charge Sharing Mechanism(for first two years ).

    Loss Allocation Factor to be computed for each season using

    Hybrid Methodology

    50% losses through Hybrid Method and 50% through

    Uniform Loss Allocation Mechanism(for first two years)

  • 8/2/2019 Transmission Pricing India

    14/20

    COMPUTATION OF POC

    CHARGES

    Criteria for Zoning of nodes:

    Costs within the same range

    Geographically and electrically proximate

    Nodes with connectivity to Thermal Generators > 1500 MW or

    Hydro Generators > 500 MW to be taken as separate zone.

    Except NER states where entire region is to be taken as one zone.

    Zonal Charges : Weighted Average of Nodal Charges

  • 8/2/2019 Transmission Pricing India

    15/20

    COMPUTATION OF POC

    CHARGES

    Generating stations connected to ISTS network < 400KVwould be charged at zonal charges where physically located

    No transmission charges/losses for solar projects (for theentire useful life) commissioned within next 3 years.

    In the event of a Designated ISTS Customer failing to provideits requisition for demand or injection for an Application

    Period, the last demand or injection forecast supplied by theDIC and as adjusted by the Implementing Agency for LoadFlow Analysis shall be deemed to be Approved Withdrawalor Approved Injection

  • 8/2/2019 Transmission Pricing India

    16/20

    SPECIFIC CHARGES

    For deviation > 20% in any time block, the DIC shall be

    required to pay transmission charges for excess generation

    @ 25% above the zonal POC charges determined for zonewhere the Designated ISTS Customer is physically located

    Payment on account of additional charges for deviation bythe generator shall not be charged to its long term customer

    and shall be payable by the generator

  • 8/2/2019 Transmission Pricing India

    17/20

    INDIRECT METHODFOR

    HVDC COST ALLOCATION

    Compute Transmission Charges for all load and generators with all HVDC

    lines in service.

    Disconnect HVDC line and again compute new transmission charges for all

    loads and generators

    Compute difference between nodal charges with or without HVDC.

    Identify nodes which benefits with the presence of HVDC

    [Benefit = (old cost i.e. base case with injection) minus (new usage cost i.e. withlink disconnected)]

    In case benefit is ve, same to be collared to zero

    Allocate HVDC line cost to the identified nodes.

  • 8/2/2019 Transmission Pricing India

    18/20

    COMPARISONOFDIFFERENT

    METHODS IN TRANSMISSION PRICING

    Postage Stamp Method

    Positive: Simple, familiar, most widely used in developing market

    Negative : Insensitive to distance & direction

    Contract Path Methodology

    Positive: Sensitive to distance

    Negative: Provides wrong economic signal, based on fictitiouspath, power flow on parallel path is ignored

  • 8/2/2019 Transmission Pricing India

    19/20

    COMPARISONOFDIFFERENT

    METHODS IN TRANSMISSION PRICING

    Distance Based MW-Mile Methodology

    Positive: Simple, sensitive to distance

    Negative: Based on physical distance, not on actual power flow.

    Point tariff, Nodal Pricing or Locational Marginal Pricing (LMP)

    Positive: Provides economic signals, suitable for developed /

    saturated market

    Negative: Complex, not suitable for developing market, lossesforms the part of transmission pricing, based on MWhnot on MW.

  • 8/2/2019 Transmission Pricing India

    20/20