Transmission Pricing

Embed Size (px)

Citation preview

  • 7/27/2019 Transmission Pricing

    1/84

    TRANSMISSION PRICING

  • 7/27/2019 Transmission Pricing

    2/84

    Objectives of TransmissionPricing

    Suggest key objectives fortransmission pricing should be:

    Enabling competition for grid services

    where possible Enabling appropriate grid investment to

    proceed

    Providing incentives for the grid owner(and system operator) to minimise gridcosts

  • 7/27/2019 Transmission Pricing

    3/84

    Objectives of TransmissionPricing

    Enabling competition for grid services where possible Generators and loads can compete with grid services, for

    new grid investment, by either locational investmentdecisions or operating decisions (load management)

    Can achieve this by either pricing or grid investment approvalprocess

    If transmission pricing reflects long run marginal cost ofprovision of new transmission, and costs can be avoided byappropriate investments or operations by users, then users

    are likely to make efficient investment or operating decisions Examples - locational pricing, peak pricing

    Both difficult to get perfect in practice

  • 7/27/2019 Transmission Pricing

    4/84

    Objectives of TransmissionPricing

    Enabling appropriate grid investmentto proceed Costs of under investment can be higher than

    costs of over investment (if more difficult toquantify)

    Grid owner needs process to invest whereappropriate and reasonable assurance of ability

    to recover costs of investment May be appropriate to have some degree of risk

    sharing on investment decisions with grid users

  • 7/27/2019 Transmission Pricing

    5/84

  • 7/27/2019 Transmission Pricing

    6/84

    Pricing Methodology

    Previous sections have dealt with theobjective of transmission pricing

    This section deals with how this cost is

    recovered from grid users - Pricingmethodology

    Common approaches include:

    Post stamp pricing

    Locational pricing

    Peak charges

  • 7/27/2019 Transmission Pricing

    7/84

    Pricing Methodology

    Post stamp pricing

    All locations on grid pay same charge

    Adopted on basis that locational marginal

    pricing in energy market providesadequate locational signal and properlocational charges are very difficult tocalculate

    But considering development of locationalcharges as future development

  • 7/27/2019 Transmission Pricing

    8/84

    Pricing Methodology

    Locational pricing Attempts to signal long run marginal cost of new

    transmission investment

    Sends appropriate signal to allow load and generation to

    compete with transmission investment But difficult to calculate accurately, as grid usage can

    change over time

    Common practice is to have either regional locationalpricing or limited locational pricing

    Australia uses regional locational pricing Bases locational charge on last 12 months historic use of

    grid

  • 7/27/2019 Transmission Pricing

    9/84

    Pricing Methodology

    Locational pricing Many US jurisdictions, that dont have locational

    marginal pricing in energy market, use locationalpricing in transmission pricing

    Alternative is to have limited locational pricing

    That is where one primary beneficiary to a set ofassets (connection assets) can be identified thencharge those assets to beneficiary and postagestamp price rest.

  • 7/27/2019 Transmission Pricing

    10/84

    Pricing Methodology

    Peak charges Attempts to signal capacity value of grid

    Grid users contract for maximum guaranteed capacity

    Usage also includes charge for highest annual peak (or

    average of several peaks) Peak charges may be offset by contracted capacity

    Issues with whether peaks should be locational or systemwide

    As non-coincident peaks contribute differently to over all

    system capacity

  • 7/27/2019 Transmission Pricing

    11/84

    Nodal price determinationexamples

  • 7/27/2019 Transmission Pricing

    12/84

    Shadow Price, nodal price, LMP

    Shadow price of a constraint is the change in theoptimum value for the objective function when theconstraint is relaxed by 1 MWh (increase load by 1MW)

    3 Steps

    Optimise the objective function

    Re-optimizing the objective function with relaxedconstraint

    The difference between the two objective functionvalues is the shadow price of the constraint

  • 7/27/2019 Transmission Pricing

    13/84

    Case 1: one node market,energy price

    110

    0

    G1:Energy

    $50/MW

    Dispatch G1 100MW energy. G2 100MW reserve

    Shadow price calculation

    Step 1: Total cost: 100 x $50 + 100 x $10 = $6000

    Step 2: increase load by 1 MW and total cost becomes 101 x $50 +

    101 x $10 = $6060 Step 3: LMP (energy) = $6060 $6000 = $60

    0

    110

    Energy (MW)

    Reserve (MW)

    Load =100

    G1 G2

    G2: Reserve$10/MW

    Assuming N-1 security

    requirement

  • 7/27/2019 Transmission Pricing

    14/84

    Case 2: one node market,reserve price

    120

    0

    G1: Energy

    $50/MW

    Dispatch G1 100MW energy. G2 100MW reserve

    Shadow price calculation

    Step 1: Total cost: 100 x $50 + 100 x $10 = $6000

    Step 2: relax reserve requirement by 1 MW and total cost becomes100 x $50 + 99 x $10 = $5990

    Step 3: LMP (reserve) = $6000 $5990 = $10

    0

    120

    Energy (MW)

    Reserve (MW)

    Load =100

    G1 G2

    G2: Reserve

    $10/MW

    Assuming N-1 securityrequirement

  • 7/27/2019 Transmission Pricing

    15/84

    2 Node Models Assumptions

    Two nodes, A and B

    Load is 80MW at Node B

    Generation is available as follows:

    A1 offers 50MW @ $50/MWh

    A2 offers 60MW @ $100/MWh B1 offers 50MW @ $150/MWh

  • 7/27/2019 Transmission Pricing

    16/84

    Case 3: 2 Nodes, No Losses, NoConstraints

    A BA1: 50MW

    @ $50/MWh

    A2: 60MW

    @ $100/MWh

    B1: 50MW

    @ $150/MWh

    Load =

    80MW

    Dispatch A1: 50MW, A2: 30MW

    Nodal prices A: $100/MWh, B: $100/MWh

    Generators Paid - $8,000

    Purchasers Pay - $ 8,000

  • 7/27/2019 Transmission Pricing

    17/84

    Case 4: 2 Nodes, Losses, NoConstraints

    A B

    A1: 50MW @$50/MWh

    A2: 60MW @$100/MWh

    B1: 50MW @$150/MWh

    Load = 80MW

    Average loss = 5%, marginal loss = 10%

    Dispatch A1: 50MW, A2: 34MW

    Nodal prices A: $100/MWh, B: $110/MWh

    Generators Paid: $8400 ($100 x 84)

    Buyers Pay: $ 8,800 ($110 x 80) Loss Rental: $ 400

  • 7/27/2019 Transmission Pricing

    18/84

    Case 5: 2 Nodes, No Losses,Constraints

    A B

    A1: 50MW

    @ $50/MWh

    A2: 60MW

    @ $100/MWh

    B1: 50MW

    @ $150/MWh

    Load = 80MW

    Dispatch A1: 50MW, A2: 10MW, B1: 20MW

    Nodal prices A: $100/MWh, B: $150/MWh

    Generators Paid: $9,000 ($100 x 60 + $150 x 20)

    Purchasers Pay: $12,000 ($150 x 80)

    Constraint Excess: $3,000 (or $50/MWh x 60MWh) Try the same exercise, if B1 offers $200/MWh

    Limit 60MW

  • 7/27/2019 Transmission Pricing

    19/84

    Case 6: 2 Nodes, Shadow Price ofConstraint

    A B

    A1: 50MW

    @ $50/MWh

    A2: 60MW @$100/MWh

    B1: 50MW @$150/MWh

    Load =

    100MW Relax constraint by 1MW Dispatch A1: 50MW, A2: 11MW, B1: 39MW

    Nodal prices A: $100/MWh, B: $150/MWh

    Pay generators now - $11,950

    Previously paid to generators $ 12,000

    Shadow price of constraint = $50 (What is the relationship with theprevious example?)

    Limit 60MW

  • 7/27/2019 Transmission Pricing

    20/84

    Case 7: 2 Nodes, Losses andConstraints

    A B

    A1: 50MW @$50/MWh

    A2: 60MW

    @ $100/MWh

    B1: 50MW

    @ $150/MWh

    Load = 80MW

    Average loss = 5%, marginal loss = 10%

    Dispatch A1: 50MW, A2: 13MW, B1: 20MW

    Nodal prices A: $100/MWh, B: $150/MWh

    Generators Paid - $9,300 ($100 x 63 + $150 x 20)

    Purchasers Pay - $12,000 ($150 x 80)

    Constraint Excess - $2,700 (can we separate the loss from congestionrentals?)

    Limit 60MW

  • 7/27/2019 Transmission Pricing

    21/84

    Case 8: 2 Nodes, Co-optimisation

    Assume that reserves are available at $10/MW fromthird parties

    N-1 reserve requirement

    Generator B1 now offers 50MW @ $101/MW/h(instead of $150 as in previous examples)

    If not co-optimised SO will dispatch A1 for 50MWand A2 for 30MW, nodal price is $100 at both A andB, as previously shown

    Generators paid $8,000, reserve providers paid$500, total cost $8,500

    Co-optimisation changes dispatch

  • 7/27/2019 Transmission Pricing

    22/84

    Co-optimisation

    A B

    A1: 50MW

    @ $50/MWh

    A2: 60MW

    @ $100/MWh

    B1: 50MW

    @ $101/MWh

    Load = 80MW

    Dispatch A1: 27MW, A2: 27MW, B1: 26MW

    Nodal prices A: $101/MWh, B: $101/MWh

    Generators Paid - $8,080

    Reserve payment - $270

    Total cost - $8,350

  • 7/27/2019 Transmission Pricing

    23/84

    Case 9: Reserves DeterminingDispatch

    Station Reserve OfferMW $ MW $

    H1 300 10 250 20

    HMC1 250 11 150 16

    C1 200 11 100 10D 100 15 100 5E 100 25 100 3

    Assumption: Load 200 MW and all other stations small and won't set riskTotal Cost of Energy and Reserve To Meet 200MW

    Energy Reserve Total

    H1 200*10 = 2,000 100*3+100*5 = 800 2,800

    HMC1+H1 100*10+100*11 =2,100

    =100*3 = 300 2,400

    Dispatch stations HMC1 and C1 ahead of H1 as lower overall cost

    Energy and reserve offers

    Energy Offer

  • 7/27/2019 Transmission Pricing

    24/84

    Case 10: 3 Nodes Example 1

    LMP Example Base Case No Congestion:

    Load = 50

    MWh

    Capacity60MW

    G1 offersEnergy -

    10MW @$10/MWh

    Reserve -40 MW @$10/MWh

    Capacity60MW

    G2 offersEnergy -

    60MW @$250 /MWh

    Reserve -10 MW @$250/MWh

    G1 LOAD

    G3

    G2

    Capacity60MW

    G3 offersEnergy -

    60MW @600/MWh

  • 7/27/2019 Transmission Pricing

    25/84

    3 Nodes Example 1 LMPbase case, no congestion

    The least cost dispatch schedule for meeting 50MWh load is$10,500, with the following dispatch schedule

    Energy: 10 MWh from G1 at $10/MWh and 40MWh from G2 at$250/MWh

    Reserve: 40 MWh from G1 at $10/MWh.

    The least cost dispatch schedule for meeting 51 MWh load is$11,000, with the following dispatch schedule.

    Energy: 10 MWh from G1 at $10/MWh and 41MWh from G2 at $250/MWh

    Reserve: 40 MWh from G1 at $10/MWh and 1 MWh at $250/MWh

    The energy price for the 50 MWh load is $500 /MWh, calculated asthe difference between the total delivered cost for 51 MWh and thatfor 50 MWh. The price compromises the marginal generation cost of$250 /MWh and marginal reserve cost of $250/MWh.

  • 7/27/2019 Transmission Pricing

    26/84

    Case 11: 3 Nodes Example 2:with congestion

    Capacity60MW

    G1 offersEnergy -

    10MW @$10 /MWReserve -

    40 MW @$10 /MW

    Capacityde-rated to40MW

    G2 offersEnergy -

    60MW @$250 /MWhReserve -

    10 MW @$250 /MW

    G1 LOAD

    G3

    G2

    Capacity60MW

    G3 offersEnergy -

    60MW @$600 /MW

  • 7/27/2019 Transmission Pricing

    27/84

    3 Nodes Example 2 - continued

    The least cost dispatch schedule for meeting the 50MWh loadremains at $10,500, with the following dispatch schedule

    Energy: 10 MWh from G1 at $10/MWh and 40MWh from G2 at$250/MWh

    Reserve: 40 MWh from G1 at $10 /MWh.

    However, to meet the 51 MWh load, G3 will be required togenerate 1 MW to meet the 51st MW, because the transmissioncapacity for G2-Load is fully utilised and constrained. The leastcost dispatch schedule for meeting 51 MWh load is $11,100,with the following dispatch schedule.

    Energy: 10 MWh from G1 at $10/MWh, 40MWh from G2, and 1

    MWh from G3 at $600 /MWh Reserve: 40 MWh from G1 at $10/MWh

  • 7/27/2019 Transmission Pricing

    28/84

    3 Nodes Example 2 - continued

    The energy price for 50 MWh load is $600/MWh, calculated asthe difference between the total delivered cost for 51 MWh andthat for 50 MWh. The price reflects marginal generation cost of$600 /MWh.

    Note that marginal reserve price is $0 /MWh as no change in

    reserve cost for dispatch of 51st

    MWh.

  • 7/27/2019 Transmission Pricing

    29/84

  • 7/27/2019 Transmission Pricing

    30/84

  • 7/27/2019 Transmission Pricing

    31/84

    Agenda

    Case 1 Physical Withholding Capacity Case 2 Economic Withholding Case 3 - Congestion - Islanded Load Case 4 - Controlling Congestion

    Case 5 - Market Power in Voltage Support Case 6 - Market Power in Frequency Keeping Case 7 - Controlling Dispatch via Reserve Pricing Case 8 Strategies Used by Traders in California

    Case 9 Regulation in Singapore

  • 7/27/2019 Transmission Pricing

    32/84

  • 7/27/2019 Transmission Pricing

    33/84

  • 7/27/2019 Transmission Pricing

    34/84

  • 7/27/2019 Transmission Pricing

    35/84

    Case 1 Physical withholding

  • 7/27/2019 Transmission Pricing

    36/84

    Case 1 Physical withholdingcapacity continued (IPP D

    withholds capacity)unit MW

    offeredOfferprice

    Dispatched MW

    Revenue

    IPP A G1 100 0 100 $50,000

    IPP B G2 300 10 300 $150,000

    IPP C G3 300 25 300 $150,000

    IPP D G4 200 30 200 $100,000

    IPP D G5 90 40 90 $45,000

    IPP D G6 200 500 10 $5,000

    Clearing price 500 1000

    IPP Ds revenue = $150,000

  • 7/27/2019 Transmission Pricing

    37/84

  • 7/27/2019 Transmission Pricing

    38/84

  • 7/27/2019 Transmission Pricing

    39/84

    Case 1 Physical withholdingCapacity Contd

    Winners and Losers Analysis Winners

    All generators

    Dont need to collude if all have same incentive

    Losers

    Purchasers

  • 7/27/2019 Transmission Pricing

    40/84

  • 7/27/2019 Transmission Pricing

    41/84

  • 7/27/2019 Transmission Pricing

    42/84

  • 7/27/2019 Transmission Pricing

    43/84

    Case 3 - Congestion and PriceIslanded Load

    Consider situation below where congestionmeans only one generator able to supplymarginal load

    Load -

    100MW Line Capacity 90 MW

    Rest ofSystem

    Clearing

    Price $30

    Gen A

    50MW@

    $900

  • 7/27/2019 Transmission Pricing

    44/84

    Case 3 - Congestion and PriceIslanded Load Contd

    islanded load needs local generator to meet marginaldemand

    If demand elasticity unable to relieve congestion then localgenerator assured of dispatch regardless of price

    Local generator Gen A has local market power

    Load -

    100MW Line Capacity 90 MW

    Rest of

    System

    Clearing

    Price $30

    Gen A

    50MW

    @

    $900

    Case 3 - Congestion and Price

  • 7/27/2019 Transmission Pricing

    45/84

    Case 3 - Congestion and PriceIslanded Load Contd (elastic

    demand )

    MW Price (US$) Dispatched Q $ amount

    Inelastic demand 90 $5,000 90

    Elastic demand 5 $100 0

    Elastic demand 5 $10 0

    Gen A offer 50 $500 0

    Rest offer 90 $30 90 $2,700

    Load -100MW Line Capacity 90 MW

    Rest of System

    Clearing Price

    $30

    Gen A

    50MW @

    $900

  • 7/27/2019 Transmission Pricing

    46/84

  • 7/27/2019 Transmission Pricing

    47/84

    C 3 C

  • 7/27/2019 Transmission Pricing

    48/84

    Case 3 - Congestion and PriceIslanded Load Contd

    Conclusions Contd If nodal price then local load exposed completely to Generator

    A market power

    If nodal pricing then all generators in price islanded region

    benefit so limited incentive to compete for dispatch (specialcase of with holding capacity)

    Nodal price sends strong investment signal for newtransmission or competing generation

  • 7/27/2019 Transmission Pricing

    49/84

  • 7/27/2019 Transmission Pricing

    50/84

  • 7/27/2019 Transmission Pricing

    51/84

    C 4 C t lli C ti

  • 7/27/2019 Transmission Pricing

    52/84

    Case 4 - Controlling CongestionContd

    Consider configuration below, where the samecompany owns generators A and B For an n-1 security criteria the SO would rate the lines A, B and C and 600

    MW.

  • 7/27/2019 Transmission Pricing

    53/84

    C 4 C t lli

  • 7/27/2019 Transmission Pricing

    54/84

    Case 4 - ControllingCongestion Contd

    Assumption: Ignoring losses and ignoring flows bus C A - B

    Gen A offers 200 MW @ $5 and 200MW@ $15

    Gen B offers 300 MW @ $100

    Line flows and dispatched amounts and cleared prices (Assuming Nodal

    Pricing) would be approximately as below Line C is operating at its constraint limit

    Case 4 Controlling Congestion

  • 7/27/2019 Transmission Pricing

    55/84

    Case 4 - Controlling CongestionContd

    Load - 1000MW @

    $10

    Generator A

    200 MW @

    $10

    Rest of

    System - 800

    MW @ $10Generator B

    0 MW

    @$10Line C 600 MW

    Line A 400 MW

    Line B 400

    MW

    Bus

    C

    Bus BBus A

  • 7/27/2019 Transmission Pricing

    56/84

  • 7/27/2019 Transmission Pricing

    57/84

    Case 4 Controlling Congestion

  • 7/27/2019 Transmission Pricing

    58/84

    Case 4 - Controlling CongestionContd

    Load - 1000MW @

    $100

    Generator A

    300 MW @

    $10

    Rest of

    System - 700

    MW @ $10Generator B

    100 MW

    @$100Line C 600 MW

    Line A 300 MW

    Line B 300

    MW

    Bus

    C

    Bus BBus A

  • 7/27/2019 Transmission Pricing

    59/84

    C 4 C t lli

  • 7/27/2019 Transmission Pricing

    60/84

    Case 4 - ControllingCongestion

    Conclusions The owner of Generators A and B can structure offers on

    Generator A so as to maximise total returns by forcing line C intoconstraint.

    They are thus able to control a Price Islanded Load situation.

    The generator financial gain is largely independent of pricingsystem adopted, i.e. Nodal, System Marginal Price, or Pay asyou bid. (Slightly higher if generator constrained on to manage

    congestion sets SMP).

  • 7/27/2019 Transmission Pricing

    61/84

    Case 4 Controlling Congestion

  • 7/27/2019 Transmission Pricing

    62/84

    Case 4 - Controlling CongestionReal Life Examples

    N Z - Tokaanu - Whakamaru Constraint

    Genesis own both generator able to controlconstraint (Tokaanu) and generator that benefits

    most from constraint binding (Huntly)

    Cases 5 and 6 Market Power in

  • 7/27/2019 Transmission Pricing

    63/84

    Cases 5 and 6 - Market Power inAncillary Services

    The previous examples have been of situations where generatorscan create a degree of Market Power in energy

    This relied on demand inelasticity to price, could be due tocongestion or, in some cases a portfolio generators ability to controlcongestion

    Ancillary Services Market Power is an extension of the samesituation

  • 7/27/2019 Transmission Pricing

    64/84

    Case 5 Voltage Support Market

  • 7/27/2019 Transmission Pricing

    65/84

    Case 5 - Voltage Support MarketPower

    Voltage support requirements tend to be fairly localisedas losses very high

    Voltage support market thus very regionalised withlimited competition within region

    Not a problem is vertically integrated transmission andgeneration companies as internal supply was cost based

    Becomes an issue for price based markets if supplierhas market power in region

    Case 5 Voltage Support Market

  • 7/27/2019 Transmission Pricing

    66/84

    Case 5 - Voltage Support MarketPower

    Conclusions Voltage support requirements are fixed by security criteria

    (System Operator has little or no ability to respond to price)

    High VAR losses can create regions of Market Power for voltagesupport providers

    Generators can exploit by offering very high prices for voltagesupport

    Restrained only by new investment costs and time frames

    Voltage support investment usually relatively low cost and shortlead time so opportunity limited

    System Operator may have limited ability (or incentive) to controlcosts if security standards prescriptive and costs passed through

  • 7/27/2019 Transmission Pricing

    67/84

  • 7/27/2019 Transmission Pricing

    68/84

  • 7/27/2019 Transmission Pricing

    69/84

  • 7/27/2019 Transmission Pricing

    70/84

    Case 6 - Frequency Keeping

  • 7/27/2019 Transmission Pricing

    71/84

    Case 6 - Frequency KeepingMarket Power - Conclusions

    Frequency keeping issue unique to NZ but equivalentswill exist in other jurisdictions where resources requiredfor secure system operation split off into competitivegeneration assets

    Frequency keeping requirement set by securitystandards, hence one sided market

    Owner of frequency keeping asset has natural monopolyand price only limited by legislation or fear of legislation

  • 7/27/2019 Transmission Pricing

    72/84

    Case 6 - Frequency Keeping

  • 7/27/2019 Transmission Pricing

    73/84

    q y p gMarket Power Real Life

    Examples Mighty River Power

    Annual frequency keeping costs went from $9M to $24M over 3years (1999 - 2001).

    System Operator able to control to some extent by betterdispatch matching of load and generation in real time

  • 7/27/2019 Transmission Pricing

    74/84

  • 7/27/2019 Transmission Pricing

    75/84

  • 7/27/2019 Transmission Pricing

    76/84

  • 7/27/2019 Transmission Pricing

    77/84

  • 7/27/2019 Transmission Pricing

    78/84

  • 7/27/2019 Transmission Pricing

    79/84

  • 7/27/2019 Transmission Pricing

    80/84

  • 7/27/2019 Transmission Pricing

    81/84

  • 7/27/2019 Transmission Pricing

    82/84

    Case 8: strategies used by traders

  • 7/27/2019 Transmission Pricing

    83/84

    Case 8: strategies used by tradersin California continued

    Inc-ing Load Artificially increase the load on the schedule submitted to ISO

    (generation and load must balance)

    In real time, Enron sends the generation it scheduled, but does not takeas much load as scheduled

    Say, it was scheduled to generate 1000MW, but only took 500MW.Enron made a net contribution to the grid of 500 MW

    ISO pays Enron 500 x the DEC price

    Case 8: strategies used by traders

  • 7/27/2019 Transmission Pricing

    84/84

    Case 8: strategies used by tradersin California continued

    Duke Energy Made $10 million in 1 week by

    creating congestion in path 26,and subsequently paid to relievethe congestion (at the time, withinthe Southern zone, no intra-zonalcongestion charge)

    ISO subsequently created Path26, and the zone is subject tozonal price difference, thuseliminating this gaming

    opportunity