Upload
emil-sparks
View
217
Download
0
Embed Size (px)
Citation preview
Transmission Transparency Workshop
European Strategy and Environment
10 July 2008
2
NW Gas Regional Initiative
Regional Initiatives Started Spring 2006 Practical bottom up approach to reform Engage all stakeholders
North West Region Nine Members (+ Norway) Majority of European gas trade and consumption
Transparency One of three priority areas
1. Transparency 2. Capacity3. Investment
Objective: overcome barriers to gas trade between Member States on a non-discriminatory basis
3
Participating TSOs
Netherlands
United Kingdom
Germany Belgium
France Ireland
Sweden
Northern Ireland
Denmark
?
4
Context – original information shopping list
Gas Quality
Gas Balancing
Transmission Capacity
Gas Flows
Supply and Demand
Agreed as priority areas
Important issues for
future focus
To be delivered…
Gas Flows
Daily flow and interruptions
Daily prompt allocations
Daily aggregate day-ahead nominations
Historic gas flows
Transmission Capacity
Max technical capacity
Interruption probability
Daily commercial firm and interruptible capacity
focus on prioritised subset of information
5
Which interconnection points?
121 Interconnection Points
87 Public
34 Confidential (?)
Greater information transparency at “confidential” interconnection points?
EC Law: Less than three shippers; can request authorisation from NRAs not to publish information
3rd package amendment1 1
74
10 10
14
2
6
22
02
0
5
9
0 0
0
0
0
11
9
0
1
0
5
6
3
0
0
0
5
10
15
20
25
Num
ber o
f Inte
rcon
necti
on P
oint
s
publicly available confidential
IMPACT OF LESS THAN THREE SHIPPER RULE ON PROJECT
6
TSOs committed to milestones
7
Implementation schedule
Data Type% provided
in December 2007
% expected by May 2008
% expected by September
2008
% expected by December
2008 (C1) Max technical capacity
69 94 94 94
(C2) Interruption 31 50 81 88(C3) Daily commercial firm and interruptible capacity
56 75 88 94
(F1) Daily flow / aggregated Allocation
25 75 94 100
(F2) Daily prompt allocation information
81 88 88 94
(F3) Daily aggregate day-ahead nominations 13 31 63 75
(F4) Historic gas flow information database
44 63 100 100
Example: 25% of TSOs already provided aggregate daily flow and interruptions (F1), by December 2008 100% of TSOs should provide this info
8
Implementation progress: May 2008
MIXED PROGRESS: ON TRACK IN 3 BUT BEHIND SCHEDULE ON 4
9
Dec 2007 - planned im-plementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Max technical capacity (C1)
ALMOST ON TRACK: ONLY ONE TSO LEFT TO IMPLEMENT
Planned
Fluxys, BGE, Energinet.dk, Swedegas
Implemented
Fluxys, BGE, Energinet.dk
Delayed
Swedegas
10
Dec 2007 - planned im-plementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Probability of interruption (C2)
BEHIND SCHEDULE: 6 TSOs TO IMPLEMENT BY SEPTEMBER
Planned
Ontras, Energinet.dk, Swedegas
Implemented
E.ON
Delayed
Ontras, Energinet.dk Swedegas
11
Daily commercial firm and interruptible capacity (C3)
ROUGHLY ON TRACK: ONE TSO IMLPEMENTED EARLY ONE TSO FAILED
Dec 2007 - planned im-plementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Planned
Fluxys, BGE, Energinet.dk
Implemented
NG, BGE, Energinet.dk
Delayed
Fluxys
12
Daily flow/aggregated allocation (D+1) (F1)
BEHIND SCHEDULE: 4 TSOs TO IMPLEMENT BY SEPTEMBER; 3 BY DECEMBER
Dec 2007 - planned im-plementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Planned
E.ON, WINGAS, Ontras, Energinet.dk, BEB, DEP, Swedegas, GdF DT
Implemented
E.ON, BEB, DEP, GdF DT
Delayed
Fluxys, WINGAS, Ontras, Swedegas
13
Daily prompt allocation information (F2)
ON TRACK: ALL TSOs NOW REPORT TO PROVIDE THIS INFORMATION
Dec 2007 - planned im-plementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Svenska Kraftnät and E.ON now report that
they provide this information
14
Daily aggregate day ahead nominations (F3)
BEHIND SCHEDULE: 3 TSOs PROVIDE NO ANSWER ON IMPLEMENTATION
Dec 2007 - planned im-plementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Planned
WINGAS, Ontras, DEP
Implemented
E.ON
Delayed
WINGAS, Ontras, DEP
15
Historic gas flow database (F4)
ON TRACK: 5 TSOs STILL NEED TO IMPLEMENT THIS INFORMATION
Dec 2007 - planned implementation
June 2008 - monitored implementation
resulting change
-4
-2
0
2
4
6
8
10
12
14
16
in place May 2008 Sept 2008 Dec 2008 no answer
Num
ber
of
TS
Os
Planned
WINGAS, Ontras, BEB
Implemented
E.ON, DEP, WINGAS, BEB
Delayed
Ontras
16
TSOs that report new information release
TSOs that report full compliance already
17
Next Steps
Incorporate your feedback into the implementation report: feedback by 18 July
Publish the implementation report and press release: end of July 2008
Questionnaire for second progress report: October 2008
Publication of second progress report: November 2008
North-West Region Stakeholder Conference in London: 14 November
Deadline for implementation: 31 December 2008
Final project report/workshop: Early 2009
18
Key issues
Implementation accuracy1. At which interconnection points will the relevant data be
published?2. Are the definitions for each data type appropriate?3. Has there been any further progress since May?
User views4. Network user feedback on accessibility and usefulness of
the data5. Improvements to project management and reporting6. Any other key issues?
TSO feedback7. Reasons for delays in releasing new data8. Re-confirmation of implementation commitment
19
Risks to successful project?
How will we handle delays in project implementation? First implementation report and press release to be published
at the end of July Second and final implementation reports published in
November and early 2009 Updates at GRI Stakeholder(November 2008) and Madrid Fora
Escalation of concerns? National regulators to engage with TSOs Engage Programme Board in project implementation Timelines to be revised?
20
BIG THANK YOU TO ALL STAKEHOLDERS!
PROJECT WOULD NOT BE POSSIBLE WITHOUT POSITIVE AND ACTIVE PARTICIPATION OF ALL
THOSE INVOLVED
WANT POSITIVE OUTCOME FOR EVERYBODY
21