Upload
hoanganh
View
219
Download
2
Embed Size (px)
Citation preview
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 and 205
PORT OF DURBAN
Contract Number: TCP CON/041/2011/005
Task Order Number: TO‐TCP‐001
Project Number: M‐2122830‐408
METHOD STATEMENT: ZAA 1370‐MS‐016 REV 00
EXTENSION OF SANDBANK
25 September 2012
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
REVISIONS
REV DATE DESCRIPTION DESIGNED
BY
CHECKED
BY
APPROVED
BY
00 25 September 2012 Draft CJE JZ JZ
AUTHORISATION
AUTHORISED BY NAME SIGNATURE DATE
DIRECTOR J ZIETSMAN
25 September 2012
This document, including all design and information therein, is Confidential Intellectual Property of ZAA Engineering.
Copyright and all other rights are reserved by ZAA Engineering.
This document may only be used for its intended purpose.
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
CONTENTS
1.0 INTRODUCTION ....................................................................................................................................... 1
2.0 SCOPE AND PURPOSE .............................................................................................................................. 2
3.0 RESPONSIBILITIES .................................................................................................................................... 2
3.1 Design .............................................................................................................................................................. 2 3.2 Approval .......................................................................................................................................................... 2 3.3 Execution ......................................................................................................................................................... 2
4.0 SCOPE ...................................................................................................................................................... 3
4.1 Drawings ......................................................................................................................................................... 3 4.2 Description ...................................................................................................................................................... 3 4.3 Quantities ........................................................................................................................................................ 3
5.0 SEQUENCE ............................................................................................................................................... 3
6.0 METHOD .................................................................................................................................................. 4
7.0 ENVIRONMENTAL CONSIDERATIONS AND POLLUTION CONTROL ............................................................ 4
7.1 General ............................................................................................................................................................ 4 7.2 Specific Measures ........................................................................................................................................... 4
8.0 RISK ASSESSMENTS.................................................................................................................................. 5
9.0 PROGRAMME .......................................................................................................................................... 5
10.0 QA & QC .................................................................................................................................................. 5
11.0 HEALTH AND SAFETY ............................................................................................................................... 5
12.0 SPECIFICATIONS ....................................................................................................................................... 5
13.0 DRAWINGS .............................................................................................................................................. 5
14.0 RESOURCES AND EQUIPMENT ................................................................................................................. 5
15.0 RECORDS ................................................................................................................................................. 5
ANNEXURES ............................................................................................................................................................. 1 ANNEXURE 1 – DRAWINGS ....................................................................................................................................... 2
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
Page | 1
1.0 INTRODUCTION
This Method Statement is prepared as part of the Contract awarded to ZAA Engineering Projects and Naval
Architecture (Pty) Ltd, (ZAA), by TRANSNET SOC Ltd, for the Feasibility Study (FEL‐3) for the deepening of Berths 203
– 205 in the Port of Durban.
Left Port of Durban
Below – Pier 2, Berths 203 to 205
The Method Statement is one of a series that have been developed, and where necessary updated, to define at high
level the responsibilities and the procedures that must be implemented by ZAA, Transnet and the ultimate
contractor to be appointed when the project proceeds to the FEL‐4 implementation stage.
The methodologies will be subject to confirmation following the formal appointment of a contractor.
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
Page | 2
2.0 SCOPE AND PURPOSE
This Method Statement defines the procedures to be adopted for the reclamation and extension of substantial areas
of the sandbanks opposite the new construction work at Berths 203 to 205
The purpose of this Method Statement is to define in advance the extent of the work, the division of responsibilities
and the required modus operandi of all parties.
The desired outcome is thus to ensure that all operations for the preparation and placing of high quality reclaimed
material for the extension of the sandbank is carried out safely and in a manner that disturbs the environment to the
minimal extent possible. Measures are to be implemented to ensure the work is done in accordance with the
specified environmental requirements, design and standards; to the required tolerances; in the correct sequence and
to the required programme for the works.
3.0 RESPONSIBILITIES
3.1 Design
It is the responsibility of the designer, ZAA Engineering Projects and Naval Architecture (Pty) Ltd, (ZAA) to carry out
the following work in order to define the reclamation work required for the sandbank extension.
ZAA will have
Assessed the available and new geotechnical and survey data
Established sources of sand from the offshore borrow site
Determined the extent of reclamation and extension of the sandbank, as well as specifications for
the material and its placing
Determined the extent of dredging at the toe of the existing sandbank, the bottom slope protection
required and the required profiles of the extended surfaces
Investigated the suitability of dredged material for stockpiling and later use for reclamation
ZAA will further provide:
Detail reclamation and extension drawings and quantities
Specifications of the reclaim material – sources, properties and grading
Instructions for placing
Control and monitoring measures to minimize turbidity of the water column
Construction sequence during placing
QA / QC requirements and record keeping
Tolerances and required surveys during and after placing to ensure that the requirements are met
3.2 Approval
It will be the responsibility of the client (TCP) to
Approve all drawings and procedures to Approved for Construction (AFC) Stage
Define borrow sites for sourcing reclaim material
Obtain licenses and environmental approvals for dredging and placing of reclaimed material
Appoint and negotiate details with the Contractor
3.3 Execution
It will be the responsibility of the Contractor to
Review and accept or make proposals for the modification of all designs and procedures
Provide his own detailed method statements for execution, based on his own available resources,
plant and internal procedures
Produce, update and maintain his own detailed construction schedules for all phases of the works.
Manage the contract
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
Page | 3
Take possession of the site
Provide suitable plant – dredger and distribution systems plus additional facilities and equipment for
placing of reclaim material
Obtain suitable sources of material and provide samples for approval.
Provide initial, progress and completion surveys to confirm compliance with design requirements as
well as measurement for payment purposes.
4.0 SCOPE
4.1 Drawings
The scope of work required is shown on the following drawings (attached as Annexure 1).
1370‐DWG‐1700 Rev P02 – Berth 203 to 205 Deepening – Dredging ‐ General Layout Option 3G
1370‐DWG‐1710 Rev P00 – Berth 203 to 205 Deepening – Dredging – Mooring Basin Layout Option
3G
1370‐DWG‐1711 Rev P00 – Berth 203 to 205 Deepening – Dredging – Sections Option 3G
4.2 Description
The drawings show dredging layout Option 3G, which defines a tapering basin opposite the new berths 203 to 205 as
well as a deepened turning basin between the existing T‐jetty and Pier 1. The new basin will be deepened from its
current nominal depth of ‐12.8 m CDP to ‐16.5 m CDP.
The tapered shape of the deepened basin permits a substantial extension of the sandbanks, which offsets the smaller
areas that will be lost to the turning circle and the extension of Berth 205 into the existing crane area.
The sections show the current profile of the sandbank, which has been found to have a natural slope of
approximately 1:4. Its top is in the intertidal zone at a nominal elevation of 0.0 m CDP. It is thus exposed at low tide
and inundated at high tide. As shown in the second section, it is the intention of the reclamation and extension to
replicate the natural profiles. Tidal flows will over time modify this slightly to establish a fully stable extended
surface. Being a contiguous extension rather than a new area, it is expected that the spread of ecological systems to
the extended area will be relatively quick.
The new dredged basin will be deepened to ‐16.5 m CDP at a 1:3 slope and scour protection is to be provided to
protect and stabilize the new toe of the sandbank. This will extend down the 1:3 slope and for 10 m along the new
basin floor at ‐16.5 m CDP. In addition it will be lapped over the top of the slope at the current ‐12.8 m CDP level.
4.3 Quantities
The estimated quantity of sand to be dredged and placed is approximately 1,000,000 m3. Based on a single 2,700 m3
TSD and with a bulking factor of 1.12 a nett deposition of about 1,800 m3 could be expected per dredged load. This
requires some 550 loads at a cycle time of some 6 hours. Thus the maximum sand deposition rate will be of the order
of 5,400 m3 / day which would take at least 6 months of uninterrupted work. It should be noted that the actual
equipment available to and selected by the contractor may change these rates and durations significantly.
5.0 SEQUENCE
The major part of this work will be carried out during Phase 1 of the work, during which the basin and turning circle
will be dredged to its new depth and the slope protection installed. Phase 1 also includes the construction of the new
Berth 205 and the deepened basin and turning circle must be available for the larger ships that will use Berth 205
after it is commissioned. Extension of the sandbanks will progressively follow the dredging work.
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
Page | 4
6.0 METHOD
The following procedure provides a simplified, high‐level overview of the Contractor’s process of reclamation and
extension of the sandbanks. Note that the methodology for basin and turning circle dredging as well as slope
protection is not covered by this document.
Set up a survey programme, determining setting out points of the area to be filled. This must be
compared with previous surveys and the baseline agreed
Conduct a video survey of the existing slopes for record purposes
Set up pollution control measures – refer to Section 7 below
Mobilise and commission suitable dredging equipment, marine operating staff, diving crews and
support boats. The anticipated dredging equipment is a Trailing Suction Dredger (TSD), fitted with
discharge pumps and hoses from a bow coupling.
Dredge clean reclaim material from designated and approved borrow site offshore
Provide samples for confirmation of suitability of material
Place sandbags along the line of the new toe of the extended sandbank to form a low retaining
structure. Bio‐degradable sandbags would be preferred.
Pump the reclaim material behind the sandbag retaining structure in a sequence so that the area is
filled evenly and rises in layers from below. This procedure will reduce entrainment of sand in the
water column and thus reduce turbidity.
Monitor turbidity in the water column and adjust deposition rates as needed.
Fill to the pre‐determined level, with periodic dives providing video records of the new profile.
Conduct interim and acceptance surveys for confirmation of final levels achieved and for
measurement of quantities.
7.0 ENVIRONMENTAL CONSIDERATIONS AND POLLUTION CONTROL
7.1 General
Despite being an industrial site for many years and thus being in a more or less degraded state in places, good
environmental Management of the Port of Durban nevertheless remains an absolute priority. All aspects of the
project will be subject to detailed environmental scrutiny into the construction related and long term operational
effects on the environment, both locally and in the wider context of the Port and its surroundings, land and marine.
In particular underwater operations, or those resulting in potential spillage of material, pose substantial
environmental challenges that have to be very carefully managed.
ZAA will identify at an early stage the potential Environmental Concerns resulting from placing the
reclaim material, as well as mitigatory procedures.
TCP will refer all issues to the Environmental Consultants for resolution through the EIA / approval
processes
The Contractor will be required to set up operational and monitoring procedures to ensure that all
environmental requirements are met.
7.2 Specific Measures
The following specific measures must be adopted to reduce pollution and turbidity to the absolute minimum.
Grading of the sand selected for reclaim and sandbank extension shall match that of the existing
sandbank as closely as possible. The material shall be free of clay, organic matter or other detritus.
Pumping shall be controllable in rate so that it can be slowed if turbidity levels rise. It is expected
that pumping can be maximized over both high and low tide periods, but may have to be reduced as
tidal flows in both directions increase. In particular turbidity during tidal flows away from the
sandbank and towards the new basin must be strictly controlled to prevent sand flowing back into
the newly dredged areas.
Floating containment curtains extending well into the water will be required to restrict movement of
the more turbid water until it has settled.
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 September 2012
Page | 5
8.0 RISK ASSESSMENTS
Risk assessments will be carried out on all aspects of the work as defined in more detail in Method Statement 1370 –
MS – 003.
9.0 PROGRAMME
Suitable programming will be required for all aspects of the work as defined in more detail in Method Statement
1370 – MS – 003.
10.0 QA & QC
Suitable QA & QC procedures will be required for all aspects of the work as defined in more detail in Method
Statement 1370 – MS – 003.
11.0 HEALTH AND SAFETY
The Contractor will be responsible for the implementation of a comprehensive Health and Safety
programme
12.0 SPECIFICATIONS
As part of the design premise, ZAA will define all General Specifications and Codes of Practice for
reclamation and extension
Additional detailed Specifications will be provided where necessary or as a result of Field
Engineering Queries (FEQ)
13.0 DRAWINGS
ZAA will produce all necessary AFC Drawings
The Contractor will produce survey data and drawings of initial, interim and final stages of the
reclaim material placement.
14.0 RESOURCES AND EQUIPMENT
The Contractor will be responsible for the provision, establishment, operation, maintenance, and
disestablishment of suitable and reliable equipment for dredging, transport, placing and testing.
The contractor will further be responsible for any other equipment required for the placing of
reclaim material, as well as for management, scheduling, staff, sub‐contractors, power and fuels,
interfacing with Port Operations and managing vessel traffic.
15.0 RECORDS
The Contractor will be responsible for producing all ‘As built’ survey drawings
The Contractor shall maintain all QA / QC records
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 Annexures September 2012
Page | 1
ANNEXURES
TRANSNET SOC LTD
FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205
PORT OF DURBAN
EXTENSION OF SANDBANK
ZAA 1370 | MS | 016 Rev 00 Annexures September 2012
Page | 2
ANNEXURE 1 – DRAWINGS
1370‐DWG‐1700 Rev P02 – Berth 203 to 205 Deepening – Dredging ‐ General Layout Option 3G
1370‐DWG‐1710 Rev P00 – Berth 203 to 205 Deepening – Dredging – Mooring Basin Layout Option 3G
1370‐DWG‐1711 Rev P00 – Berth 203 to 205 Deepening – Dredging – Sections Option 3G
29°52'S
31°02'E
THE POINT
E
S
P
LA
N
A
D
E
C
H
A
N
N
E
L
2
0
5
2'
31°E
2' 3' 4'
52'
S
A
N
D
B
A
N
K
P
I
E
R
N
o
1
P
IE
R
N
o
2
M
U
L
T
I
-
P
U
R
P
O
S
E
T
E
R
M
I
N
A
L
2
0
4
2
0
3
T
J
E
T
T
Y
1'
5' 6' 7' 8'
31°E
2' 3' 4'
1'
5' 6' 7' 8'
L
O
T
1
0
1370-DWG-1700- P02
EMAIL : [email protected]
PO Box 26546
Tel: +2721 791 9100
HOUT BAY 7872 HOUT BAY 7806
Fax: +2721 790 4470
31 Melkhout Crescent
www.zaaepna.com
1370-DWG-1710 REV P00
EMAIL : [email protected]
PO Box 26546
Tel: +2721 791 9100
HOUT BAY 7872 HOUT BAY 7806
Fax: +2721 790 4470
31 Melkhout Crescent
www.zaaepna.com
1370-DWG-1711 REV P00
EMAIL : [email protected]
PO Box 26546
Tel: +2721 791 9100
HOUT BAY 7872 HOUT BAY 7806
Fax: +2721 790 4470
31 Melkhout Crescent
www.zaaepna.com