13
TRANSNET SOC LTD FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 and 205 PORT OF DURBAN Contract Number: TCP CON/041/2011/005 Task Order Number: TOTCP001 Project Number: M2122830408 METHOD STATEMENT: ZAA 1370MS016 REV 00 EXTENSION OF SANDBANK 25 September 2012

TRANSNET SOC LTD 3) FOR THE 203 and 205 L...TRANSNET SOC LTD FEASIBILITY STUDY ... METHOD STATEMENT: ... Determined the extent of dredging at the toe of the existing sandbank, the

Embed Size (px)

Citation preview

 

 

 

 

 

 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 and 205 

PORT OF DURBAN 

 

Contract Number: TCP CON/041/2011/005 

Task Order Number: TO‐TCP‐001 

Project Number: M‐2122830‐408  

 

 

 

 

METHOD STATEMENT:  ZAA 1370‐MS‐016 REV 00 

EXTENSION OF SANDBANK 

 

25 September 2012 

 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012

REVISIONS 

REV  DATE  DESCRIPTION DESIGNED 

BY 

CHECKED 

BY 

APPROVED 

BY 

00  25 September 2012  Draft  CJE  JZ  JZ 

           

           

           

           

           

           

           

           

           

           

           

AUTHORISATION 

AUTHORISED BY  NAME  SIGNATURE  DATE 

DIRECTOR  J ZIETSMAN  

25 September 2012 

 

 

This document, including all design and information therein, is Confidential Intellectual Property of ZAA Engineering.  

Copyright and all other rights are reserved by ZAA Engineering.   

This document may only be used for its intended purpose. 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012

CONTENTS 

1.0  INTRODUCTION ....................................................................................................................................... 1 

2.0  SCOPE AND PURPOSE .............................................................................................................................. 2 

3.0  RESPONSIBILITIES .................................................................................................................................... 2 

3.1  Design .............................................................................................................................................................. 2 3.2  Approval .......................................................................................................................................................... 2 3.3  Execution ......................................................................................................................................................... 2 

4.0  SCOPE ...................................................................................................................................................... 3 

4.1  Drawings ......................................................................................................................................................... 3 4.2  Description ...................................................................................................................................................... 3 4.3  Quantities ........................................................................................................................................................ 3 

5.0  SEQUENCE ............................................................................................................................................... 3 

6.0  METHOD .................................................................................................................................................. 4 

7.0  ENVIRONMENTAL CONSIDERATIONS AND POLLUTION CONTROL ............................................................ 4 

7.1  General ............................................................................................................................................................ 4 7.2  Specific Measures ........................................................................................................................................... 4 

8.0  RISK ASSESSMENTS.................................................................................................................................. 5 

9.0  PROGRAMME .......................................................................................................................................... 5 

10.0  QA & QC .................................................................................................................................................. 5 

11.0  HEALTH AND SAFETY ............................................................................................................................... 5 

12.0  SPECIFICATIONS ....................................................................................................................................... 5 

13.0  DRAWINGS .............................................................................................................................................. 5 

14.0  RESOURCES AND EQUIPMENT ................................................................................................................. 5 

15.0  RECORDS ................................................................................................................................................. 5 

ANNEXURES ............................................................................................................................................................. 1 ANNEXURE 1 – DRAWINGS ....................................................................................................................................... 2 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012 

 Page | 1 

1.0 INTRODUCTION 

This  Method  Statement  is  prepared  as  part  of  the  Contract  awarded  to  ZAA  Engineering  Projects  and  Naval 

Architecture (Pty) Ltd, (ZAA), by TRANSNET SOC Ltd, for the Feasibility Study (FEL‐3) for the deepening of Berths 203 

– 205 in the Port of Durban. 

 

 

 

 

Left Port of Durban 

 

 

 

 

 

 

 

 

 

 

 

 

Below – Pier 2, Berths 203 to 205 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The Method Statement is one of a series that have been developed, and where necessary updated, to define at high 

level  the  responsibilities  and  the  procedures  that  must  be  implemented  by  ZAA,  Transnet  and  the  ultimate 

contractor to be appointed when the project proceeds to the FEL‐4 implementation stage. 

 

The methodologies will be subject to confirmation following the formal appointment of a contractor. 

 

   

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012 

 Page | 2 

2.0 SCOPE AND PURPOSE 

This Method Statement defines the procedures to be adopted for the reclamation and extension of substantial areas 

of the sandbanks opposite the new construction work at Berths 203 to 205  

 

The purpose of this Method Statement is to define in advance the extent of the work, the division of responsibilities 

and the required modus operandi of all parties.  

 

The desired outcome  is thus to ensure that all operations for the preparation and placing of high quality reclaimed 

material for the extension of the sandbank is carried out safely and in a manner that disturbs the environment to the 

minimal  extent  possible. Measures  are  to  be  implemented  to  ensure  the work  is  done  in  accordance with  the 

specified environmental requirements, design and standards; to the required tolerances; in the correct sequence and 

to the required programme for the works. 

 

3.0 RESPONSIBILITIES 

3.1 Design 

It is the responsibility of the designer, ZAA Engineering Projects and Naval Architecture (Pty) Ltd, (ZAA) to carry out 

the following work in order to define the reclamation work required for the sandbank extension.  

 

ZAA will have  

Assessed the available and new geotechnical and survey data  

Established sources of sand from the offshore borrow site 

Determined the extent of reclamation and extension of the sandbank, as well as specifications  for 

the material and its placing 

Determined the extent of dredging at the toe of the existing sandbank, the bottom slope protection 

required and the required profiles of the extended surfaces 

Investigated the suitability of dredged material for stockpiling and later use for reclamation 

 

ZAA will further provide: 

Detail reclamation and extension drawings and quantities  

Specifications of the reclaim material – sources, properties and grading 

Instructions for placing 

Control and monitoring measures to minimize turbidity of the water column 

Construction sequence during placing 

QA / QC requirements and record keeping 

Tolerances and required surveys during and after placing to ensure that the requirements are met 

3.2 Approval 

It will be the responsibility of the client (TCP) to  

Approve all drawings and procedures to Approved for Construction (AFC) Stage 

Define borrow sites for sourcing reclaim material 

Obtain licenses and environmental approvals for dredging and placing of reclaimed material 

Appoint and negotiate details with the Contractor 

3.3 Execution 

It will be the responsibility of the Contractor to 

Review and accept or make proposals for the modification of all designs and procedures 

Provide his own detailed method statements  for execution, based on his own available resources, 

plant and internal procedures 

Produce, update and maintain his own detailed construction schedules for all phases of the works. 

Manage the contract 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012 

 Page | 3 

Take possession of the site 

Provide suitable plant – dredger and distribution systems plus additional facilities and equipment for 

placing of reclaim material 

Obtain suitable sources of material and provide samples for approval. 

Provide initial, progress and completion surveys to confirm compliance with design requirements as 

well as measurement for payment purposes. 

 

4.0 SCOPE 

4.1 Drawings 

The scope of work required is shown on the following drawings (attached as Annexure 1). 

 

1370‐DWG‐1700 Rev P02 – Berth 203 to 205 Deepening – Dredging ‐ General Layout Option 3G 

1370‐DWG‐1710 Rev P00 – Berth 203 to 205 Deepening – Dredging – Mooring Basin Layout Option 

3G 

1370‐DWG‐1711 Rev P00 – Berth 203 to 205 Deepening – Dredging – Sections Option 3G 

4.2 Description 

The drawings show dredging layout Option 3G, which defines a tapering basin opposite the new berths 203 to 205 as 

well as a deepened turning basin between the existing T‐jetty and Pier 1. The new basin will be deepened from  its 

current nominal depth of ‐12.8 m CDP to ‐16.5 m CDP. 

 

The tapered shape of the deepened basin permits a substantial extension of the sandbanks, which offsets the smaller 

areas that will be lost to the turning circle and the extension of Berth 205 into the existing crane area. 

 

The  sections  show  the  current  profile  of  the  sandbank,  which  has  been  found  to  have  a  natural  slope  of 

approximately 1:4. Its top is in the intertidal zone at a nominal elevation of 0.0 m CDP. It is thus exposed at low tide 

and  inundated at high tide. As shown  in the second section,  it  is the  intention of the reclamation and extension to 

replicate  the  natural  profiles.  Tidal  flows will  over  time modify  this  slightly  to  establish  a  fully  stable  extended 

surface. Being a contiguous extension rather than a new area, it is expected that the spread of ecological systems to 

the extended area will be relatively quick. 

 

The new dredged basin will be deepened  to  ‐16.5 m CDP at a 1:3 slope and scour protection  is  to be provided  to 

protect and stabilize the new toe of the sandbank. This will extend down the 1:3 slope and for 10 m along the new 

basin floor at ‐16.5 m CDP. In addition it will be lapped over the top of the slope at the current ‐12.8 m CDP level. 

4.3 Quantities 

The estimated quantity of sand to be dredged and placed is approximately 1,000,000 m3. Based on a single 2,700 m3 

TSD and with a bulking factor of 1.12 a nett deposition of about 1,800 m3 could be expected per dredged load. This 

requires some 550 loads at a cycle time of some 6 hours. Thus the maximum sand deposition rate will be of the order 

of 5,400 m3  / day which would  take at  least 6 months of uninterrupted work.  It  should be noted  that  the actual 

equipment available to and selected by the contractor may change these rates and durations significantly. 

 

5.0 SEQUENCE 

The major part of this work will be carried out during Phase 1 of the work, during which the basin and turning circle 

will be dredged to its new depth and the slope protection installed. Phase 1 also includes the construction of the new 

Berth 205 and the deepened basin and turning circle must be available for the  larger ships that will use Berth 205 

after it is commissioned. Extension of the sandbanks will progressively follow the dredging work. 

 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012 

 Page | 4 

6.0 METHOD 

The  following procedure provides a simplified, high‐level overview of  the Contractor’s process of  reclamation and 

extension  of  the  sandbanks.  Note  that  the methodology  for  basin  and  turning  circle  dredging  as well  as  slope 

protection is not covered by this document. 

Set up a  survey programme, determining  setting out points of  the area  to be  filled. This must be 

compared with previous surveys and the baseline agreed 

Conduct a video survey of the existing slopes for record purposes 

Set up pollution control measures – refer to Section 7 below 

Mobilise  and  commission  suitable  dredging  equipment, marine  operating  staff,  diving  crews  and 

support boats. The anticipated dredging equipment  is a Trailing Suction Dredger  (TSD),  fitted with 

discharge pumps and hoses from a bow coupling. 

Dredge clean reclaim material from designated and approved borrow site offshore 

Provide samples for confirmation of suitability of material 

Place  sandbags  along  the  line of  the new  toe of  the extended  sandbank  to  form  a  low  retaining 

structure. Bio‐degradable sandbags would be preferred. 

Pump the reclaim material behind the sandbag retaining structure in a sequence so that the area is 

filled evenly and rises  in  layers from below. This procedure will reduce entrainment of sand  in the 

water column and thus reduce turbidity. 

Monitor turbidity in the water column and adjust deposition rates as needed. 

Fill to the pre‐determined level, with periodic dives providing video records of the new profile. 

Conduct  interim  and  acceptance  surveys  for  confirmation  of  final  levels  achieved  and  for 

measurement of quantities. 

 

7.0 ENVIRONMENTAL CONSIDERATIONS AND POLLUTION CONTROL 

7.1 General 

Despite being  an  industrial  site  for many  years  and  thus being  in  a more or  less degraded  state  in  places,  good 

environmental Management  of  the  Port  of Durban  nevertheless  remains  an  absolute  priority.  All  aspects  of  the 

project will be subject  to detailed environmental scrutiny  into  the construction  related and  long  term operational 

effects on the environment, both locally and in the wider context of the Port and its surroundings, land and marine. 

In  particular  underwater  operations,  or  those  resulting  in  potential  spillage  of  material,  pose  substantial 

environmental challenges that have to be very carefully managed. 

ZAA will  identify at an early stage the potential Environmental Concerns resulting from placing the 

reclaim material, as well as mitigatory procedures.  

TCP will refer all  issues to the Environmental Consultants for resolution through the EIA / approval 

processes 

The Contractor will be required to set up operational and monitoring procedures to ensure that all 

environmental requirements are met. 

 

7.2 Specific Measures 

The following specific measures must be adopted to reduce pollution and turbidity to the absolute minimum. 

Grading of  the  sand  selected  for  reclaim and  sandbank extension  shall match  that of  the existing 

sandbank as closely as possible. The material shall be free of clay, organic matter or other detritus. 

Pumping shall be controllable  in rate so that  it can be slowed  if turbidity  levels rise.  It  is expected 

that pumping can be maximized over both high and low tide periods, but may have to be reduced as 

tidal  flows  in  both  directions  increase.  In  particular  turbidity  during  tidal  flows  away  from  the 

sandbank and towards the new basin must be strictly controlled to prevent sand flowing back  into 

the newly dredged areas. 

Floating containment curtains extending well into the water will be required to restrict movement of 

the more turbid water until it has settled. 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    September 2012 

 Page | 5 

 

8.0 RISK ASSESSMENTS 

Risk assessments will be carried out on all aspects of the work as defined in more detail in Method Statement 1370 – 

MS – 003. 

 

9.0 PROGRAMME 

Suitable programming will be  required  for all aspects of  the work as defined  in more detail  in Method Statement 

1370 – MS – 003. 

 

10.0 QA & QC 

Suitable QA & QC  procedures will  be  required  for  all  aspects  of  the work  as  defined  in more  detail  in Method 

Statement 1370 – MS – 003. 

 

11.0 HEALTH AND SAFETY 

The Contractor will be  responsible  for  the  implementation of a  comprehensive Health and Safety 

programme 

 

12.0 SPECIFICATIONS 

As part of  the design premise, ZAA will define all General Specifications and Codes of Practice  for 

reclamation and extension 

Additional  detailed  Specifications  will  be  provided  where  necessary  or  as  a  result  of  Field 

Engineering Queries (FEQ) 

 

13.0 DRAWINGS 

ZAA will produce all necessary AFC Drawings 

The  Contractor will  produce  survey  data  and  drawings  of  initial,  interim  and  final  stages  of  the 

reclaim material placement. 

 

14.0 RESOURCES AND EQUIPMENT 

The Contractor will be  responsible  for  the provision, establishment, operation, maintenance,  and 

disestablishment of suitable and reliable equipment for dredging, transport, placing and testing. 

The  contractor will  further  be  responsible  for  any  other  equipment  required  for  the  placing  of 

reclaim material, as well as  for management,  scheduling,  staff,  sub‐contractors, power and  fuels, 

interfacing with Port Operations and managing vessel traffic. 

 

15.0 RECORDS 

The Contractor will be responsible for producing all ‘As built’ survey drawings 

The Contractor shall maintain all QA / QC records 

 

   

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    Annexures   September 2012 

 Page | 1 

ANNEXURES 

TRANSNET SOC LTD 

FEASIBILITY STUDY (FEL 3) FOR THE DEEPENING OF BERTHS 203 AND 205 

PORT OF DURBAN 

 

EXTENSION OF SANDBANK 

 ZAA 1370 | MS | 016 Rev 00    Annexures   September 2012 

 Page | 2 

ANNEXURE 1 – DRAWINGS 

1370‐DWG‐1700 Rev P02 – Berth 203 to 205 Deepening – Dredging ‐ General Layout Option 3G 

1370‐DWG‐1710 Rev P00 – Berth 203 to 205 Deepening – Dredging – Mooring Basin Layout Option 3G 

1370‐DWG‐1711 Rev P00 – Berth 203 to 205 Deepening – Dredging – Sections Option 3G 

 

 

29°52'S

31°02'E

THE POINT

E

S

P

LA

N

A

D

E

C

H

A

N

N

E

L

2

0

5

2'

31°E

2' 3' 4'

52'

S

A

N

D

B

A

N

K

P

I

E

R

N

o

1

P

IE

R

N

o

2

M

U

L

T

I

-

P

U

R

P

O

S

E

T

E

R

M

I

N

A

L

2

0

4

2

0

3

T

J

E

T

T

Y

1'

5' 6' 7' 8'

31°E

2' 3' 4'

1'

5' 6' 7' 8'

L

O

T

1

0

1370-DWG-1700- P02

EMAIL : [email protected]

PO Box 26546

Tel: +2721 791 9100

HOUT BAY 7872 HOUT BAY 7806

Fax: +2721 790 4470

31 Melkhout Crescent

www.zaaepna.com

1370-DWG-1710 REV P00

EMAIL : [email protected]

PO Box 26546

Tel: +2721 791 9100

HOUT BAY 7872 HOUT BAY 7806

Fax: +2721 790 4470

31 Melkhout Crescent

www.zaaepna.com

1370-DWG-1711 REV P00

EMAIL : [email protected]

PO Box 26546

Tel: +2721 791 9100

HOUT BAY 7872 HOUT BAY 7806

Fax: +2721 790 4470

31 Melkhout Crescent

www.zaaepna.com