157
TRANSPORT AND ROAD RESEARCH LABORATORY Department of the Environment SUPPLEMENTARY REPORT 108 UC BUS ROUTE COSTING FOR PLANNING PURPOSES by Arthur Andersen & Co Any views expressed in this Report are not necessarily those of the Transport and Road Research ~boratory or of any other division, of the Department of the Environment. Prepared by Arthur Andersen & Co under contract to the Transport and Road Research Laboratory Special Research Branch Transport Operations Department Transport and Road Research Laboratory Crowthorne, Berkshire 1974

TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TRANSPORT AND ROAD RESEARCH LABORATORY

Department of the Environment

SUPPLEMENTARY REPORT 108 UC

BUS ROUTE COSTING FOR PLANNING PURPOSES

by

Arthur Andersen & Co

Any views expressed in this Report are not necessarily those of the Transport and Road Research ~boratory or of any other division, of the Department of the Environment.

Prepared by Arthur Andersen & Co under contract to the Transport and Road Research Laboratory

Special Research Branch Transport Operations Department

Transport and Road Research Laboratory Crowthorne, Berkshire

1974

Page 2: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

1. INTRODUCTION AND SUMMARY

Page

i.i Introduction 1.2 S1~mmary 1.3 Guide to reading the report

1 3 8

2. THE COST STRUCTURE

2.1 2.2 Form of the cost structure 2.3 Relation to other route costing work 2.4 Application to route costing 2.5 Management accounts for cost control

Requirements to be served by the cost structure

3. COMPONENTS OF THE COST STRUCTURE

Introduction Direct costs Variable overheads Fixed overheads Engineering costs - cleaning, maintenance and repairs

.3.1 3.2 3.3 3.4 3.5 servicing,

l l 14 18 18 19

20 20 23 28

33

4. THE CREW COST ELEMENT OF A BUS ROUTE COST

.

4.1 The need for the crew cost element to be related to time of day

4.2 Approach to estimating the crew cost element 4.3 The relationship between crew hours paid

for and bus hours operated 4.4 The direct cost of the crew hours required

to operate the total combination of bus hours required on a route

4.5 The direct cost of the crew hours associated with changes in the hours of bus service on a route in peak and offpeak periods

4.6 Interpretation of total and marginal direct crew costs

4.7 The direct cost of crew hours associated with blocks of service

4.8 Analysis of crew costs in MPTE 4.9 Consistency with other research 4.10 Conditions forapplication in MPTE 4.11 Application in other companies

DETERMINING ROUTE NET COSTS.

4o ho

h2

44

~h

hh

h5 48 51 55 55

/

5.1 General principles 5.2 Application to routes 5.3 Revenue estimation -methods application to MPTE 5.4 Cost determination - avoidable costs

57 6o 61 64

. PILOT APPLICATION IN MERSEYSIDE PASSENGER TRANSPORT EXECUTIVE

6.1 6.2 6.3

Objectives. Coverage of the pilot study Feasibility in the pilot study, and implications for general application

66 66

67

Page 3: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Ownership of the Transport Research Laboratory was transferred from the Department of Transport to a subsidiary of the Transport Research Foundation on 1 st April 1996.

This report has been reproduced by permission of the Controller of HMSO. Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.

Page 4: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

.

6.4 Results prepared for MPTE 6.5 Conclusions from the pilot study

EXAMPLES OF APPLICATION IN PARTICULAR PLANNING CONTEXTS

•8.

7.1 7.2

7.3

7.4

7.5

7.6 7.7

SOME

S~,mmary Effect of street closure and free travel off~eak on route i00

Estimating the net cost of providing service at some times of the week

Estimating the cost consequences of conversion to 0MO Cost consequences of alterationsto service frequency ~

Increasing fares during peak periods • Providing increased service in offpeak periods

FURTHER DE"qELOPMENTS OF BUS ROUTE COST INFORMATION

8.1 8.2 8.3

8.4

APPENDIX

APPENDIX

APPENDIX

Introduction Changes to evening service Stopping services short of the terminus (revenue effects)

Taking action in response to short-term trends

l: Participants in the study

2: Crew Costs: models andregression analyses

3: Definition of terms

ADDENDUM: Further analysis and application ofthe method

1. Introduction to Addendum 1.1 Purposes of tNis additional work • 1.2 Reasons for addendum format ' 1.3 Structure of the addendum

2. Addendum snmmary 2.1 Applicability of cost structure to other PTE's 2.2 Peak and offpeak crew costs: Selnea and

Greater Glasgow PTE 2.3 Weekday offpeak costs MPTE 2.4 Simplified method of analysis

. Peak 3.1 3.2 3.3

and offpeak crew costs Comparison between the three PTE's Method of analysis Conclusion

. Weekday offpeak costs in Merseyside PTE 4.i Analysis of buses' operation 4.2 Results of this analysis 4.3 Higher costs of evening duties

72 73 ̧

79

82

88

93

9 7 lOb 108

n o l l O

iii 112

113

l l b

121

28 "

128 128 128

Z29 • •

1 3 o ' 130

131 131 132

134 134 136 136

138 138 139 139

i

Page 5: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

ADDENDUM: APPENDIX i:

ADDENDUM: APPENDIX 2 :

Some relevant features of the union agreements in Selnec and Greater Glasgow PTEs

Estimating peak and offpeak crew costs in other companies

145

149

(C) CROWN COPYRIGHT 1974

Extracts from the text may be reproduced, except for commercial purposes, provided the source is acknowledged.

Page 6: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 1

INTRODUCTION AND SUMMARY

i.i Introduction This study was commissloned by the Transport and

Road Research Laboratory (TRRL) following a survey

of bus industry research requirements in 1971, and particular interest

expressed by Merseyside Passenger Transport Executive (MPTE) in

participating in the study.

The main part of the work commenced in November 1973, and

fieldwork in MPTE was essentially completed in March 1974. Brief

discussions were held with other bus companies in April 1974 to

determine the extent to which the principlesand methods developed

might be applicable to them.

Aims of the study The study's aims have been to establish principles

and methods for classifying and structuring the

total costs of bus companies so that the costs of individual services

can be determined, and so that estimates of the cost of changes to

services can be made, on a sound economic basis which Will in Principle ,

if not in exact detail, be applicable in most bus companies. It is

envisaged that the outcome of the study will be used:

(a) for attributing costs to routes, both in Merseyside and

elsewhere, to help determine the extent to which they are

(b~

making or losing money.

for budgeting and planning purposes, by MPTE Operational,

Planning and Financiai Management.

Page 7: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(c) in modelling the cost structure of bus companies for

research purposes.

Particular interest centered on the question of the

differences between the costs of changes to peak services, and to

offpeak services.

It was decided that our work should be initially quite

independent of the work of the National Bus Company (NBC), and of the

Chartered Institute of Public Finance and Accountancy (CIPFA) and similar

bodies Working onRoute Costing. The intention was to provide an

independent approach to Route Costing, and to concentrate particularly

on crew costs at different times of the day and week. This is an area

on-which NBC are themselves working by methods which are different from

ours, but which share a common aim of achieving greater accuracy in

accounting for an important element of bus company costs.

Our approach comes to conclusions very similar in the main

to NBC's in ~ those areas in which our aims were the same. We have

expanded on their results in differentiating further between peak and off-

peak costs, and we have taken a slightly different view on the treatment

of some engineering costs, to relate them more closely to the peak/offpeak

differences. We are now in close touch with them and other interested

parties in taking the work forward.

2

Page 8: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

1.2 Summary

Cost structure developed We have developed a structure of bus

company*costing which classifies each

operating cost of a bus company according to two criteria:

a) with which one of three measures of activity the cost is

most closely linked: bus hours operated; bus miles

operated; or number of buses operated at peak periods, and

b) the timescale over which changes to operations would result

in changes to costs: within a week or two; within a few

months; or only over a longer period and not as a direct

consequence of changes to individual services.

Following the classification of costs according to these

criteria, standard dnit costs are developed, per bus hour, bus mile,

and peak bus. For each measure Of activity (e.g. bus hour) a separate

unit cost is derived which applies over each of the three timescales.

These standard unit costs are then used to attribute total costs to

routes, and in estimating the costs of planned changes to services.

Basis for managementaccounts By defining categories of cost for

which standard unit costs can be

developed for planning and route costing purposes, the cost structure

would also provide a basis for management accounting systems which:

a) provide estimates for budgeting purposes, related

to the expected level of activity of the company and

its separate parts

* Whenever in this report we re fer to a bus " company", we mean any undertaking which runs bus services, acting as one operating unit - e.g., one NBC operating subsidiary, a PTE, or a municipal bus undertaking.

Page 9: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

b) allow actual costs to be compared with standard costs

c) structure costs as direct, variable overhead, and

fixed overhead, and allow detailed reporting of

the reasons for variances betweenactual and

standard costs, by responsibility.

Peak/offpeak differences We have found evidence that additional bus

hours operated in peak periods cost substan-

tially more per hour than additional off peak bus hours.

iThe crew cost per additional peak bus hour is approximately

constant, and independent of the existing level or • proportion of peak

working, at least over the wide range observed in MPTE.

The crew cost per additional offpeak hour is also approximately

constant and independent of the existing peak level of service.

We cannot yet say whether crew costs incurred by additions to

offpeak service are the same at all times of day. Evening service and

midday service may have different costs. We found that in existing

MPTE schedules, evening duties appear relatively more expensive (by i0-

20%) per bus hour than other non-spreadover duties. (See addendum.)

We are told that a significant increase in evening work (or

"late turns") would be unpopular in MPTE. We are also told that some

evening work must be included in the duty mix, in order to provide a

satisfactory rotation of types of duty. Although these factors are

not at present reflected formally in penalty payments to compensate

for the unpopularity of evening work, they do illustrate the general

point that costs cannot be extrapolated for changes which go beyond

the range within which the union agreement provides an acceptable

form of payment for unpopular or inconvenient working hours.

4

Page 10: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

We estimate that additional peak operation in MPTE would •

lead within a few months to cost increases of the order of • £4.70

per peak bus hour added, compared with an average cash fare revenue •

per peak bus hour of approximately £3.O0. Increases to offpeak

service would lead over the same time span to increases in cost

of the order of only £1.75 per offpeak bus hour, compared with the

average cash fare revenue*per offpeak bus hour of approximately

£2.75.

Reductions to service should lead to the same cost

reductions: about £4.70 per peak, and £1.75 per offpeak bus hour.

(Fixed costs are in all cases excluded from the figures given, which

are based on analysis of one week's operation in one MPTE garage.)

Part of the cost •difference between•peak and offpeak service • .

increases comes from the extra crew cost resulting from an increase

in spreadover working and penalty payments which increased scheduled •

peak working causes. The other part comes from the • need to provide • •

extra buses as peakservice levels are increased • , and the corresponding

increase in that part of engineering costs Which is associated with

each bus owned and operated, regardless of the amount of use it

receives.

The interpreter of these figures should bear in mind that cash fares in MPTE account for only about 87% of fare revenue. Other types of passengers are multi-trip and season ticket holders (accounting for the remaining 13% of fare revenue), who travel more in peak than offpeak periods, and old age pensioners, who can travel free in offpeak periods only.

5

Page 11: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Possible implications The figures indicate that at present, for the

one week's operation analysed at one MPTE

garage, revenue received from peak travellers is not covering the

costs of providing peak service, and that offpeak revenue is more than

covering costs. (In both cases, the costs referred to are costs

excluding fixed overheads.)

To the extent that wider considerations of public policy

make it desirable for fare revenue more closely to approximate to

the cost of providing services, this suggests two possibilities for

the bus operator to explore further:

m

n

Application to routes

stepsare required:

increasing offpeak service provided

charging higher fares during peak periods.

i•n order to apply Our methods to costing the

routes operated by a bus company, the following

(a) using Table 2.1' as a guide, classify each of the

company's costs according to their• relationship with

bus hours, bus miles, or peak buses operated, and

according to the timescale over which the costs

change following changes to service. Allow for any

cost increases anticipated in the period being planned.

(b) calculate bus hours, bus miles and peak buses for the

company as a whole, and for each route to be costed.

(c) if the mix of peak, offpeak and weekend work is similar

on all routes, and peak and offpeak crew cost differences

Page 12: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(d)

are not required, then calculate standard unit costs for

each timescale by dividing the cost in each classification

by the number of units of activity to which it relates-.

use the standard unit costs in conjunction with each

route's use of bus hours, bus miles and peak buses to

estimate the costs attributable to the route.

(e) if peak/offpeak cost differences are of fnterest, then a

more detailed analysis of crew costs will be necessary

The method by which we first •succeeded in doing this •

in MPTE is described in Chapter 4. The addendum

described a later development of a simpler method with

potentially wider application, which has beenpilot

tested in t hr~e PTEs. . .

Revenue analysis, the other• major aspect Of route cost and

revenue analysis, requires . the development of methods specific tO

each company's fare structure and systems of .fare collection. The

methods we applied in MPTE involved analysis of waybills for cash

fares, and a variety of special studies and surveys for other types

of revenue.

Examples of the application of these methods to some of

MPTE's services are given in this volume, showing summary information

for all routes operated from one garage, and detail information for

three routes. (Detail flor other routes was prepared for MPTE, but

is ~ot shown in this report.~

Examples are also given in Chapter 7 of the application

of route cost and revenue analysis methods to.a variety of bus

planning problems.

7

Page 13: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

1.9 Guide to reading the report Some readers will wish to inform

themselves in full about all

aspects of our study, and will wish to read the report straight through.

For those with more particular purposes, the following guide may prove

helpful.

Obtaining an overview of the work For those (e.g., senior bus company

managers) wishing to obtain quickly

an overview of the cost structure which we have developed, and how it

can be applied to bus route cost and revenue analysis, we suggest reading

Chapters 2, 5 and 6.

Chapter 2 outlines the cost structure we have developed,

and gives general Principles for its application in other bus

companies. The problem of costing peak operations imposes particular

requirements on the costing structure. We describe our view on peak

costing, and the way in which the structure responds to the

requirements. Table 2.1 summarises the results of our application

of the structure to the costs of MPTE's operations, and indicates

therelative sizes of main cost elements and the way in which we

have treated them.

Chapter 5 describes how the structure of costs is applied

to costing individual routes.

Chapter 6 gives examples of the sorts of information our

methods can provide. We applied the methods to the routes operated

out of one of MPTE's garages for one fairly typical week in late

1973. Tables 6.1 and 6.2 show respectively a cost and revenue summary

for all these routes, and details for one of the routes.

Page 14: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Applying the results in other companies For those wishing to find

out more about how to apply

the results in other bus companies, we suggest that they read Chapters

3 and 7 in addition to the Overview chapters 2, 5 and 6.

Chapter 3 gives more details of our treatment of cost

elements in the costing structure, and lists the cost elements which

we included in each celi of Table 2.1 for MPTE. It also discusses ~

considerations to be borne in mind when analysing engineeringc0sts

Chapter 7 illustrates some applications of the costing

methods and results to particular planning decisions.

Peak/offpeak crew cost differences We found in MPTE substantial

differences in the effective cost

of crew time per bus hour of operation for additions or reductions to

peak, offpeak and weekend services. Those who need to consider the

extent to which these results can be applied more generally should read ~

Chapter 4, Appendix 2, and the addendum.

Chapter 4 describes the results we obtained for MPTE:

consistently higher effective crew costsper bus hour of additions to

operation in peak periods, independent of the existing level and

proportion of peak operation over a wide range, and higher Costs also

~k

9

Page 15: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

at weekends. It also describes the conditions under which we expect

that the results can be validly applied.

Appendix 2 gives technical details of analyses we performed

to identify these cost differences, and the addendum describes a

simpler method of analysis.

Limitations of route costin~ methods Route cost and revenue analyses

of the type we have developed

are valuable for many planning decisions, but are not adequate for

some. Those who need to know about some types of decision for which

further analyses will be required should read Chapter 8.

l0

Page 16: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 2

THE COST STRUCTURE

2.1 Requirements to be served by the cost structure

cost structure needs to be:

In order to meet the aims

identified in Chapter l, the

a)

b)

c)

d)

closely related to the way in which changes in the activities involved in operating bus services lead to changes in the costs of operation in the medium term.

useful for broad planning purposes with a planning timescale of, say, three months to one or two years, and hence not dependent on particular day-to-day features of operations.

accurate, but not necessarily to a greater extent thanthe accuracy obtainable for crew costs, and consistent with the intended use for broad planning purposes.

simple, both for a bus company to develop, and to apply in practice. Simplicity is highly desirable, and to be aimed for so far as is consistent with the other needs.

In order to develop a cost structure which meets these

needs, we found it essential to consider first the cost differences

which exist between peak, offpeak (weekday), and weekend services.

Because the proportion of peak to offpeak and weekend work may vary

considerably between routes, and because peak working is significantly

more expensive than offpeak, these cost differences are important for

accurate route costing, and we could make little progress in route

costing until these issues had been addressed.

ll

Page 17: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Costing peak operations Two main elements make the costs of peak

and offpeak working different:

- the costs of providing buses

- the costs of providing crews

to meet any given mixture of peak and offpeak requirements.

Provision of buses There are a set of costs which we call "ownership"

costs* which arise because a bus is owned, almost

regardless of its usage. The total amount of these costs is determined

by the peak busrequirement, and will not be significantly affected by

offpeak usage. The need to own the bus arises because it has been

decided to provide a certain level of peak operation in response to

higher demand at certain times of day. Changes in the level of peak

provision of buses will lead to changes in total ownership costs, /

which are attributable therefore to peak period changes. Peak

addition of a bus incurs one extra unit of ownership cost; offpeak

addition of a bus adds nothing to the ownership cost, provided that

for the company as a whole the offpea k level of service remains below

that at the peaks.

Crew costs ~ The effective crew cost incurred to provide an extra hour's

operation during the peak period is very significantly

higher in MPTE than the effective crew cost of an extra offpeak bus

hour, mainly because extra work in the peak requires increased spread-

over working, and its associated penalty payments.

Once the decision has been taken to acquire or retain a bus for operational use, many types of cost are automatically incurred over the service lifetime of the bus. We define these as the "ownership" costs of the bus. They are those costs of owning and operating the bus which are not significantly affected by its usage. They comprise licensing, capital costs, and certain engineering costs. Because the number of buses owned and operated is a function of peak requirements~ the Company's total ownership costs (in the medium to long-termJ will vary in proportion to the number of buses operated at peak periods.

12

Page 18: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

We have developed a simple relationship between total weekday

crew costs and the amounts of peak and offpeak working, in such a form

that we can estimate not only total crew costs, but also the cost

effect of changes to peak or to offpeak working.

Another requirement of the crew costing method, not connected

with the peak/offpeak distinction, is that account must also be taken

of any major differences in rates of pay for different types of

operation (e.g., in MPTE, different premium rates apply for single-

deck and double-deck one-man driver/operators, and the extra cost of s

conductor on two-man buses must be allowed for).

13

Page 19: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

2.2 Form of the cost structure In the cost structure, we show the

costs which may be expected to

change over a timescale of three months to one or two years as a

result of changes made to the bus company's operations. Furthermore,

costs which change Over a shorter period than three months are

separately identified. This is done in order to assist management

with some shorter-term planning, and to help clarify the distinction

between short and medium term cost effects of changes.

To enable route costing to be done, we find it necessary

first to understand the structure of operating costs for the bus

company as a whole. The company cost structure can be used to assist

other decisions in addition to route-related decisions - for example,

to help assess the merits of increasing offpeak working, or pricing

differentially for peak services. These aspects are taken up in

Chapter 7, together with examples of decisions related to specific

route s.

The cost structure has two aspects. In one aspect of the

structure, we classify costs according to the measure of activity to

which they are most closely linked.

In the other aspect, we classify costs by the timescale over

which changes to operations may be expected to work through into

changes in the corresponding costs.

Measures of activity For costing purposes, all bus services can be

characterised by three measures of activity:

* Definitions of each of the "measures" will be found in Appendix 3.

14

Page 20: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

- Bus hours operated - Bus miles operated

- Number of buses operated at the height of the peak period.

Within a bus company, we identify "pools" of cost which we take

to be non-overlapping, each of which then varies in size directly

with only one of these three measures. The cost of operating a

service then has three components, which add together: the bus-

hour-related component, the bus-mile-related component, and the

peak-bus-related component. Service changes which alter only one

component (e.g. adding extra layover time to bus hours) change only

the cost of that component. Service changes which affect more than

one component produce corresponding changes in the cost of each•

component affected.

In practice, we find it necessary to further divide the

bus hour component by time of day and week because different

effective crew costs per hour are observed in different periods

(in MPTE, into weekday (peak), weekday (offpeak), Saturday morning,

and other weekend hours).

i

Timescale of the cost impact of chan~es We also characterise costs according to the

timescale over which they may be expected to

change to a new level, following changes to operations, as:

- direct costs : change within a week or two

- variable overheads : change within a few months

fixed overheads costs which do not vary over a wide range of levels of operation, or which can only be changed in relatively large increments.

15

Page 21: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CD

0

oo:

P c~

0

~0 u~

. . . . i

0 0

o o ~ , _ ~ +~

, - 1 0 " . 1 " O U'~ o'~ " . t C~ O I ~ ¢

i

m o~ , ~

i~ ¢-t

~ ,~ ~ ~ o ,

0 ~ ~ .H ",~ 0 "~

' O ~ O r ~ ~ f ~

2, "g oo~

o o ~ ~ 4 ~ r ._)

!

! z

• • I °

. . . . . I •

0 ~ '-40 0 I ~> $

o . ~

~,~ o~ ~o

~0 ~

..~@~

,0~ ~

~ o

N m

. ~ , , ~

-g .~ ~ = . . . .

~ ~.~,'= . ~ - ~

N N g o

~ o . ~

~ ~ 0 0

I - • •

I ~D,--I

I •

I

i

i i z

o

I

|

~, .o

~1 .,- i x

o

,-4 ~

o

z

g o

u~

o

1:o

o

o o o

-o o

u'x

c,x

o ~

o

o g

o

o

o

-o

16

Page 22: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Cost classification matrix In Table 2.1 (to which reference should

be made in the rest of this chapter and

in Chapter 3) we have classified each of a bus company's major

operational cost elements into one of nine cells. Rows in the Table

correspond to the "measures of activity" classification• (hours/miles/

peak buses) and columns to the "timescale" classification (direct

costs/variable overhead/fixed overhead). Each cost of the bus company

is included once and only once in the table, so that all costs are

accounted for, and total company costs are represented completely.

Figures in the Table show the percentage of total costs accounted for

by each item, for the operation of one of MPTE's garages over one week

in late 1973.

Each cost element is classified into the appropriate ~ell

in the table by considering:

a)

•b)

with which measure of activity is the cost element most closely linked

over what timescale can the cost element be expected to settle to a new level.

The classification adopted in Table 2.1 represents our

best judgement at present as to the links between levels of activity

and consequent costs in general; but application of the classifi-

cation in particular companies may require some regrouping. We

would expect such regrouping to be guided by the considerations of

the previous paragraph.

17

Page 23: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

2.3 Relation to other route costing work The categories adopted

correspond in the main

with those adopted independently by the National Bus Company;

important differences are that we distinguish crew costs by time

period (peak, offpeak etc.), and we also treat some engineering

costs differently.

2.4 Application to route costing Two major steps are required for

route costing. First, a set of

standard unit costs are derived for each of the cells shown in Table

2.1. Costs of the company are sorted into the pools of cost

corresponding to bus hours, bus miles, peak buses; and into direct

COSTS, variable overheads, and fixed overheads. For planning purposes,

known or anticipated cost increases should be allowed for, and then

standard costs per unit of activity are calculated for the company as

a whole, or for selected cost centres only. (Crew costs require a

more complicated form of calculation, described in Chapter 4.)

Second, to apply these costs to services, each service's

use of resources is calculated: bus hours operated (by time of day

and week), bus miles operated, and peak bus requirement. These

resources are then costed at the relevant standard cost per unit, and

the total gives the cost of the service. Examples are given in

Chapters 6 and 7.

Revenue is estimated separately. We have not found it

possible to develop general methods for revenue analysis, but Chapter 5

describes the methods we were able to apply in MPTE.

18

Page 24: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

2.5 Management accounts for cost control Table 2.1 could also be

used as a basis for the

development of management accounts. These would serve two purposes

for route costing and planning, in addition to their other management

control information functions. They could be used:

a) to provide regularly the information necessary to update the standard unit costs needed for planning purposes

b) to check that actual cost changes following changes to service are being kept in line with those planned,i and as estimated by the route working system. This is particularly important for variable overheads.

Separate cost centres could be set up for sub-units of the company,

to enable cost variances to be more closely identified, The sub-

units must be such that both actual costs, and operating data, can

be collected relating to the same sub-units (e.g., garage)

19

Page 25: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 3

COMPONENTS OF THE COST STRUCTURE

3.1 Introduction In sections 3.2 to 3.4, each cost

classification cell of the costing matrix

(Table 2.1) is discussed in turn, column by column. Direct

costs are covered in section 3.2, variable overheads in .

section 3.3, and fixed overheads in section 3.4. For each cell,

we first specify the principles to be applied for classifying

costs into that cell, then list the cost elements we included

for MPTE. We go on where necessary to describe further the

cost elements in the cell, and give some examples, to help

clarify potential difficulties.

Section 3.5 describes in more detail some of the

assumptions made in placing engineering costs into the various

classifications.

3.2 Direct costs The direct costs are those costs of bus

operation which would change to a new

level within a week or two of changes being made to scheduled

operations. The direct costs related to each type of activity

are discussed in turn (refer to the first column of costs in

Table 2.1).

Bus hour related direct costs Any payments which are directly

linked with bus and crews' hours

of operation "on the road" are regarded as falling in this cell.

20

Page 26: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Included in this cell are:

Standard payment for a scheduled duty worked

Spreadover penalties

Other penalty payments applying to scheduled•hours worked - e.g. early start, late finish; night work; premiums for Saturday, Sunday and public • holiday working.

Payments for scheduled standby duty only

Premium payments for scheduled overtime •only • J

Any payments which are made "per man employed" rather

than as a function of hours worked,~ are not regarded as direct costs,

but as variable overheads. The premium part of payment for

unscheduled overtime is also regarded as a variable overhead,-• as •it

depends on the level of staff shortage for•the garage as a whole,

whereas scheduled overtime premium payments are specific to a duty

sheet.

A change in operations which • results in one or more crewmen • •

b e c o m i n g " s p a r e " w i l l s h i f t an e l e m e n t o f c o s t f r o m t h e " d i r e c t C o s t " • . ~ . " .

to the "variable overhead" column of Table 2.1, without immediately

c h a n g i n g t h e c o m p a n y ' s t o t a l p a y m e n t s f o r c r e w s . I t i s f o r r e a s o n s

such as this that it is important to have effective means of reporting

and controlling overhead costs, so that management steps can be taken •

to keep actual overhead unit costs close to those planned. If this

is not done, the unit costs will change, and tend to reduce the value

of the costing system.

Obtaining the total direct crew costs is fairly straight-

forward. It is based on an analysis of payroll records, and garage

logs of duties worked.

21

Page 27: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

In order to separate the direct crew cost effects of

changes to peak, offpeak, and weekend working (which as shown

later can vary over a range of nearly 2:1), and by type of

operation (SDOM0, DDOMO, 2-man crew) a more complex form of

analysis is required. This is described in Chapter 4t and in the

addendum.

Bus mile related direct costs

as falling in this cell.

Any costs which are directly linked

to bus miles operated are regarded

Included are costs of:

- Fuel for buses

- Fuel tax rebates (credits)

- Tyres for buses

- Any other payments determined by a per-mile rate (e.g., third party insurance and hire of buses)

If information is available from special studies or

for separate cost centres, it may be possible to establish

different fuel consumption and tyre wear costs by cost centre,

or at different times of day, or by type of terrain, or by

type of vehicle.

Peak bus related direct costs

peak buses operated.

No significant direct costs arise

as a function of the number of

Costs which are higher in peak periods as a function

of the number of peak buses operated are included elsewhere as

variable overheads.

22

Page 28: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

3.3 Variable overheads By "variable overheads" we mean those

costs of bus operation which would change

to a new level within a few months of changes being made to

scheduled operations, provided that management is aware of the

implications of the changes, and acts to ensure that those

overhead costs which can be reduced, are reduced (for service

cuts; and vice versa for service increases) in proportion to the

change in the relevant measure of the level of activity. Management

accounts systems should provide information which enable this

control to be exercised.

Bus hour related variable overheads Under this heading are included

all other payroll costs of crew

(i.e., all crew payroll costs not included as direct costs) and all ~

costs which are in the medium term linked to operating staff numbers,

which are in turn linked to bus hours.

Included are:

Crew

All NHI, graduated pension and superannuation costs

All bonuses paid as amounts per man or per week, or otherwise unrelated to dutyhours worked e.g., attendance bonus, long service bonus, OM0 savings bonus.

Payments for crew time : on holiday sick spare (but not on

scheduled standby) training any other time not on

working duty

The premium part of payment for rest day or other unscheduled overtime working

Redundancy or severance payments

Any other crew payroll costs which are not directly related to scheduled hours worked.

23

Page 29: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Crew supervision and training

Payroll costs of: traffic supervision : garage administration : training staff

Operating costs of training vehicles

Other

Uniforms

Staff bus

Miscellaneous

Scheduling variance

All items on this list except the last are fairly straight-

forward, both to identify, and to classify into this cell of the

table. All these items are likely to vary in the medium-term with

crew numbers employed, and hence with bus hours worked.

"Scheduling variance" is explained in more detail in

Chapter 4. Briefly, it relates to the difference between the actual

crew (direct) costs, and the "standard cost" computed for this

garage's mix of peak, offpeak, and weekend working, using the

coefficients of Table 4.1.

Bus mile related variable overheads In this cell are included all

costs which are found to be

most closely linked in the medium term with bus miles operated, but

which are not directly related to bus miles.

24

Page 30: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Included for MPTE are:

At garages

- Cost of materials consumed for:

. routine maintenance of buses

. cleaning buses

• servicing buses

At works

- Payroll (excluding supervision) and material costs for:

. unit changes

. unit reconditioning

• other major mechanical and electrical repairs

. accident repairs

Costs of cleaning, servicing and maintenance of vehicles

other than buses are fixed overheads, as far as route costing is

concerned, and are included under that heading.

Materials used in the annual certificate of fitness dock

(which in MPTE is performed in the main at garages) are not

significantly related to miles operated, and are not included here.

Engineering labour costs at garages were found to be much

more closely related to bus numbers than to miles operated: the

labour cost is largely for maintenance inspection, which is performed

regularly; and for cleaning and servicing, both also performed at set

intervals, rather ~ than as a function of usage. They are therefore

regarded as ownership costs, and treated as peak bus related variable

overheads (see following paragraphs).

25

Page 31: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Peak bus related variable overheads All the "ownership" costs of the

bus fleet are included in this

cell. Ownership costs are those costs which arise over the service

lifetime of the bus, because it is owned, but which are not

significantly affected by the usage it receives. The costs would no

longer be incurred for individual buses if they weresold, and

corresponding staff levels etc. altered in proportion.

Included for MPTE are costs of:

Bus depreciation

Bus licensing

Garage payroll costs (excluding engineering supervision and administration) of staff employed on cleaning, servicing, routine maintenance, and other maintenance and repair of buses done at garages.

Materials used at garage for annual certificate of fitness work.

Works engineering payroll (excluding supervision and administration) and material costs for:

bodywork reconditioning (except accident repairs)

annual (if done at works) and 7,13 year etc. DoE certi- fication work.

26

Page 32: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

As an approximation for the capital element of the cost of

owning a bus, depreciation is treated as a peak-bus related variable

overhead. More detailed information, if available, could be used for

a decision on disposal or acquisition of buses, either considering a

full discounted cash flow calculation or distinguishing between

classes of bus: older buses may be fully depreciated •already. Not

enough difference in cost is observed for new buses in MPTE between

single and double deck to make the distinction financially important

for planning.

Bus licensing costs are clearly proportional to the number

of peak buses operated, after allowing for operational reserves. Any

costs of buses owned, but not licensed, should be treated as fixed

overheads. These buses are not part of the operational fleet.

In MPTE, cleaning, servicing, and routine maintenance are

performed at garages, and the policy is to carry these out St regular

intervals. For MPTE, therefore, the payroll cost •of these operations:

forms part of the "ownership" costs of the bus. (See section 3.5 •for .•

a discussion of alternative ways of treating these costs.)

The remaining ownership costs arise out of functions which

are required at regular intervals, either legally or as a function of

the passage of time.

27

Page 33: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

3.4 Fixed overheads By fixed overheads, we mean costs which are

fixed over a period of at least a year, and

which fall into at least one of these categories:

costs which are not affected by changes to any

of the measures of level of activity (bus hours,

bus miles, or number of peak buses) over a wide

range of changes from the present situation

b) costs which can only be changed in relatively

large increments, and by considered management

decision.

External changes may affect fixed costs - changes in rent

and rates, for example - and known or prospective Changes must be

consideredin estimating future levels of fixed costs.

For management control purposes, and possibly in justifying

subsidies, it may be important to ensure that each operating unit (be

it a garage, a type of service, or a route) makes a proportionate

contribution towards paying these fixed overheads.

The means of determining a "proportionate contribution"

must in essence be somewhat arbitrary - by definition, fixed

overheads do not vary in the medium term with any of the measures of

level of activity. One criterion for making the apportionment is to

28

Page 34: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

take a view about the likely long-term relationship between

fixed overheads and the overall "size" of the undertaking.

We favour pro-rating most fixed overheads on the

basis of bus hours, on the hypothesis that bus hours are the

principal determinant of crew numbers, and most overheads will

in the long term be approximately proportional to crew numbers.

(A study* in 1•969/70 showed no apparent scale economies in bus

transport in Britain for "management and general expenses",

and tends to support this view.)

Some fixed overheads however are more closely related

to bus numbers - garage size, and hence rates (and rent, if paid),

depreciation of garage buildings and equipment, and engineering

• supervision, both at garages and at central works. These are

therefore pro-rated on •the basis of peak bus numbers.

It is important to emphasise again that since fixed

overheads by definition do not change as a function of changes to

levels of activity (in the medium term), they should not be

included when costing changes to activity levels, unless the

changes are so large as to cause a significant increment in

"fixed" costs (e.g., opening or closing a whole garage). The use

of "fixed overhead cost per unit of activity" is confined t•0 two

purposes:

a) determining which services are contributing less

than a proportionate share towards covering fixed

overheads.

*Lee, N. and I. Steedman "Economies of Scale in Bus Transport: Britain" J. of Transport Economics and Policy. Vol. IV, no 1. January, 1970.

29

Page 35: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

b) determining the subsidy required to cover the

direct, variable overhead and fixed overhead

costs of operation of particular services.

In connection with the last point, it should be noted that

we do not wish to prejudge the question of whether a subsidy should,

or should not, coven a contribution to fixed overhead.

In Merseyside PTE, responsibility for fixed overheads

arises at three levels, corresponding to MPTE's organisational

structure. We have distinguished these levels in Tsble 2.1, for

clarity, but not all bus companies will have this distinction.

Bus hour related fixed overheads. In this cell are included all costs

which meet the criteria for being

treated as fixed costs, and which may be expected in the long term

to vary in general with the number of operating staff employed, and

hence most closely with bus hours operated.

Included for MPTE are:

At g a r age

"#r

Meat, light and power

Miscellaneous administration costs (excluding engineering supervision and administration payrolls)

3O

Page 36: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

At division

- Administration payroll

- .Divisional Inspectors" payroll

- Welfare and medical benefits (a divisional • •

responsibility• in MPTE) L ~

Executlve-wide A!i headquarters costs.except non-busdepreclationp

-and englneeringmanagement. (BUsdepreclatlon is

a variable overhead for route Costing purposes, and other

deprec'iation is treated as:a peak bus related fixed overheads).

Included for MFTE are:

- Executive, managerial, and administrative payrolls Incurred by H.Q.

- Heat, light and power for H.Q, fsnctlons

- General supplies, and bought-ln services

• - Publicity materials and bought in services

- All other:H.Q, costs except as noted above

- Loan interest (loans are for non-specific p u r p o s e s .) . ~ '

• - ' O p e r a t i n g c o s t s o f . a l l n o n ' b u s v e h i c l e s . . . "

Peak bus related fixed overheads In this cell areInclude d al!i ~

. . . . costs which •meet the criteria for

being treated as fixed costs, and which may be expected in the long

term to vary in•general with the number of buses owned and operated,

and hence with the•number of-buses in use at the peak.

Included for MPTE are:

At garage

- Rates (and rent if paid)

Engineering supervision and administration payrolls (including. stores clerks, storemen, etc.)

31

Page 37: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Executive-wide

. Non-bus depreciation

- Central works management and administration

- Chlef Technical Officer and his section.

• . . ... . .

J

32

Page 38: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

3.5 Engineering costs - cleaning, servicing, maintenance and repairs The central difficulty

in attributing ~

engineering costs to the operation of particular services arises from

a lack of knowledge about the relationship between "usage" of buses

(however measured) and engineering cost components.

We have had to make certain assumptions in our treatment

of engineering costs in order to separate out costs which may be

expected to behave differently with changes in levels of activity,

It was not possible to obtain information within the scope of this

study which would enable the validity of all the assumptions to be

tested (although some were). The assumptions we made aredescrlbed

in this section, so that readers may Judge for themseives the ~

reasonableness of the untested assumptions~ and In order to provlde

a framework for further development of e~ngineering costing systems

for planning purposes. ~

Classification of englneering costs We have classified the types

of Costs involved aCCOrding

to the way in which the need for them is determined. We divide

engineering costs (i.e. costs Of all operations which in MPTE

are the responsibility of the engineering function - cleaning,

servicing, maintenance and repairs into two major groups:

x

33

Page 39: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

those which arise as a function of elapsed time, given that a bus is owned (bus "ownership" costs)

those which arise as a function of the usage a bus receives.

Within the first group, (elapsed time related) the operation giving

rise to a cost may be:

legally required at regular intervals (annual, 7,13 year etc. certificate of fitness work)

required at regular intervals for operational reasons (daily servicing ~- refuelling, topping up with oil, water etc., tyre and other inspection checks)

occasioned by the passage of time (repairs to bodywork for damage due to deterioration, corrosion etc.)

Within the second group (usage related) there are costs of operations

which are:

directly related to the usage the bus has received (maintenance and repair materials; costs of "unit changes" when major units - mainly transmission and suspension components - are exchanged; the cost of reconditioning exchanged units; and accident damage repairs).

indirectly related to usage, via engineering policy decisions which might change if there were a major change in the level or mix of measures of activity (examples include cleaning, for which MPTE's policy is to clean 3 times per week plus an internal "soap wash" every two weeks; and the labour cost component of routine maintenance - buses are examined and maintenance work is done as necessary, every two weeks).

This classification is illustrated in Table 3.1.

34

Page 40: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 3.1

CLASSIFICATION OF ENGINEERING COSTS

Attribution of cost based on:

Incurring of cost depends on:

ELAPSED TIME:

Legally required

Operationally necessary

Passage of time

USAGE:

Subject to management•policy (performed at regular intervals

Subject to need

OWNERSHIP COSTS

peak buses

Labour and materials costs of DoE certificate of fitness (every 1,7,13 etc. years)

daily servicing

bodywork reconditioning (excluding accident repairs)

cleaning

routine maintenance (labour only)

USAGE-RELATED COSTS

bus hours bus miles

engineering materials used at garages for routine work

unit changes

unit repairs and reconditioning

accident repairs

35

Page 41: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Attribution of engineering costs - principles We classify all of the first

group of costs (elapsed time

dependent) as ownership costs. They are therefore attributed to

services on the basis of peak buses used.

Costs which are incurred because of usage, but which

arise in ways not subject to management policy, are attributed

on the basis of bus miles operated.

The difficulty i n principle arises with the middle group

of costs in Table 3.1 - those which may indirectly be related to

usage, but which at present arise as a function of elapsed time

because of management policy which requires cleaning, and routine

maintenance at garages, to be performed at regular intervals.

Should they be treated as ownership costs, and therefore attributed

on a peak bus basis, or should they be attributed on the basis of

bus miles operated? The alternative we have adopted is shown by

the location given in the table to each cost element: possible

alternatives are indicated by dotted lines and question marks.

We have taken the view that in MPTE at least, these costs

should be classified as ownership costs, and hence attributed on a

peak bus basis. We say this because our discussions with management

36

Page 42: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

lead us to believe that there will continue to be reasons in MPTE for

performing maintenance inspections and cleaning operations at regular

intervals (even though the interval migh t chang@ if significant

changes in usage took place). This means that a bus, once owned, will

be subjected to regular inspection and maintenance, and as we have

argued before, the requirement for ownership arises from peak demand.

An alternative view could be adopted in other companies,

depending on their cleaning and maintenance policy, although our

discussions with three other companies have not indicated a need to

alter our view for their mode of operations.

Attribution of engineering costs - practical difficulties Cost records are not kept in

summary form in MPTE in a

manner which enables the cost elements of Table 3.1 to be directly

and separately identified. In order to estimate these costs, we made

assumptions based in part on analyses we performed, and in part on

discussions with engineering management. We now describe these

assumotions.

Routine cleaning, servicing and maintenance costs Costs of labour for routine

maintenance at garages vary most

closely with number of buses operated at peak periods; our analysis

of cost data by garage indicated a generally linear increase in cost

with the number of buses (because these activities are performed, by

policy, at regular intervals), but with a substantial fixed cost

37

Page 43: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

component (effectively the engineering supervision and

administration costs at each garage). We used the results

of our analysis to estimate the fixed cost element (shown in

Table 2.1 as a garage level, peak bus based, fixed overhead),

and treated the remainder of the actual garage engineering

labour costs as peak bus based variable overhead.

Engineering materials used at garages are most closely

related to bus miles operated by that garage; our analyses

again showed a linear increase in cost (but this time varying

not number of buses) with a significant fixed with bus miles,

element per garage. We have estimated the amount of the fixed

element from the analyses, and assumed that it is related in the

main to the materials required at garages for the annual

certificate of fitness work performed there.

Other engineering costs We have had to estimate the costs of

each other engineering activity from

the total costs incurred at the works coupled with judgements

by senior engineering personnel about the fraction of those costs

which relate to each of the remaining cost elements shown in

Table 3.1. We supplemented these judgements where possible by

brief ad hoc analyses. This was rendered necessary by limitations

on the time available to us within the scope of the study, but

we do not believe that is has introduced any serious errors in

the resulting unit costs derived from Table 2.1.

38

Page 44: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The accounts do show separately the costs of engineering

management and administrative costs at the works, and we have used

those figures for Table 2.1, in the peak bus based, fixed overhead

cell.

39

Page 45: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 4

THE CREW COST ELEMENT OF A BUS ROUTE COST

4.1 The need for the crew cost element to be related to time of day Crew payroll forms an

important part of bus

company costs -- about 37% of the total in MPTE, and 52% of costs

excluding fixed overhead. Costs which are directly affected by

schedule changes (direct crew costs) constitute 27% of MPTE's total

costs and 38% of costs excluding fixed overheads (see Table 2.1.).

Direct crew costs vary significantly between schedules having the

same content of bus hours worked, depending on the proportion of

peak, offpeak and weekend work in the schedule. Different routes

can have significantly different relative amounts of work in the

different time periods of weekday peak and offpeak, and weekend.

Accurate route costing should therefore take account of

the amounts of working in each time period.

4.2 Approach to estimating the crew cost element The NBC cost

system which

allocates bus crew costs to routes on a time basis for each type of

operation by cost centres does not specifically differentiate between

'peak' and 'offpeak' NBC recognised that this was an area requiring

f~rther research to enable the initial system to be further refined in

due course. A line of approach NBC is testing is that of costing

various alternative sets of schedules using crew computer scheduling

4O

Page 46: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

techniques. The behaviour of costs under various alternative levels

and lengths of 'peak' is analysed to test the changing crew costs at

each cost centre brought about by the changes in schedules, and from

this to see whether a relationship can be established and a cost

model developed.

We have taken an approach which is different from NBC's.

Our approach depends on statistical analysis of data relating to

existing schedules, and also avoids, in general, the need for the

scheduling of proposed changes in order to determine their effect on cost.

The approach depends on being able to know how a change in

the number of bus hours in a period of the day affects, on average,

the number of crew hours that have to be paid for.

To discover whether there is a statistical relationship

between crew hours paid for and bus hours operated which is present

after the various procedures of the schedules have been worked through,

we need data to be available which covers a wide range of mixtures of

work in different periods of the day. Furthermore, we need the different

mixtures of work to have been performed by different groups of men, all

subject to the same union agreement, but without rotation of the

mixtures of work through any of the groups of men. This last requirement

is necessary because otherwise the paid crew hours associated with a

particular profile of bus working through the day would be likely to

result from a group of men accepting the rough with the smooth.

41

Page 47: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

In MPTE, the necessary data was found by analysing different

duty sheets. A duty sheet in MPTE defines a set of crew duties,

worked in turn by the same group of men. There were 63 weekday duty

sheets in operation at the time of our analyses. Esch duty sheet

typically contains 20 to 40 duties. A "duty" is one day's work for

one man. These gave us a wide range of mixes of work in peak and off-

peak periods, and the necessary conditions for the analysis were

fulfilled. The details of the analysis are set out later in this

chapter after the main argument has been presented, but at this stage,

suffice it to say that a relationship was found between on the one side,

crew hours paid for and on the other side, bus hours operated in the

peak period and in the offpeak period.

We now describe the relationship; the costing information

that it gives, and the practical advantages of the form of the

information.

4.3 The relationship between crew hours paid for and bus hours operated Duty sheets in operation

at one time for the whole

of the MPTE were analysed. Their activity was separated into what

took place in peak and in offpeak periods.

The peak periods were 0700 to 0930 and 1600 to 1830, Mondays

to Fridays. They represented periods during which the most buses were

on the road for MPTE as a whole. The rest of the day was taken as being

offpeak. No distinction was made between the morning, mid-day and

evening effpeaks. Weekends were treated separately for Saturday morning

(up to 1300) and other weekend hours.

~2

Page 48: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The range of peak/offpeak profiles was wide; duty sheets

ranged from having an approximately equal number of buses operating

in the offpeak and peak periods up to there being over ten times as

many buses operating in the peak as in the o£fpeak. Over this wide

range, we found that (to within about 5%) the total crew hours paid

for a weekday duty sheet could be represented as a weighted sum of

the bus hours operated by the duties of the duty sheet in the peak

periods and in the offpeak periods.

Thus we have, where A and B are constants estimated in the

analysis, the number of crew hours paid is approximately equal to

A x (bus hours operated in peak periods) + B x (bus hours operated

in offpeak period).

This linear relationship with the same A and the same B is

true for the activity on each weekday duty sheet. Furthermore, since

the relationship is deduced from duty sheets which cover a wide range

of peak to offpeak ratios with a variety of combinations of routes,

the relationship may be taken to hold for individual routes.

4.4 The direct cost of the crew hours required For each type of to operate the total combination of bus hours required on a route operation (DDOMO,

SDOMO, two-man crew) there is a different, but constant, cost per crew

hour paid. This is applied to the crew hours paid to operate the

combination of peak and offpeak bus hours incurred by the route; and

hence the direct crew cost of the route is calculated-. Thus the direct

crew cost of the route as a whole is obtained. This answers one question

relating to route costing - what is the direct cost of a bus route as

43

Page 49: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

a whole in the general context of the other routes? (that is, without

attempting to pursue the details of fitting the one route with the

schedules for other routes, but making a general allowance for the

fit which works overall).

4.5 The direct cost of the crew hours From the observed associated with changes in the hours of bus service on a route in peak and relationship described offpeak periods

in section 4.3, we obtain

the costs of making marginal changes in the peak or in the offpeak service.

For the addition or subtraction of a bus hour in the peak periods,

keeping the rest of the service the same, we have that the paid crew

hours changes up or down by an amount A. For the addition or subtraction

of each bus hour in the offpeak, keeping the service in the peak unchanged,

the paid crew hours change up or down by an amount B. Hence the direct

crew costs of marginal changes to service in the peak or offpeak are

obtained.

4.6 Interpretation of total and marginal direct crew costs

with care.

This information must

clearly be interpreted

It can only be applied with confidence to changes which come

within the range of observation on which the relationship of 4.3 is

based.

a) In MPTE, the observations do not include duty sheets where service in the peak period dips below that provided in the adjacent offpeak periods, and the relationship could not therefore be applied in general to routes

operated from such duty sheets.

~4

Page 50: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

b)

c)

d)

e)

The various changes to routes which are being evaluated must not be so large as to change significantly the timing of "peak periods" for the company as a whole: i.e., those periods during which most buses are in service.

Nor must they be so large or so unpopular as to require amendment to the union agreement in operation.

The level of detail of the information is appropriate for general planning purposes in MPTE, but could be inaccurate for small changes to routes, which might be able to take advantage of particular marginal amounts of crew time available in the existing schedules, or made possible by alterations to only a few duties. (Such small changes can, and should, be separately costed, by detailed calculation of changes to crew hours paid for the affected duties.)

Finally, if the changes being considered would substan- tially change the relative levels of offpeak service in the early morning, mid-day, and evening offpeak periods, then the present form of the relationship, which treats all those periods as the same, might not apply.

4.7 The direct cost of crew hours associated with blocks of service We are doubtful as to

whether the planning

and control of bus routes or research into the provision of bus service,

do indeed require answers to queations such as "How should the total

crew cost be split into an all-day component and a component for the

excess peaks?" or "What are the crew costs of the service offered in

the offpeak and in the peak periods?"

45

Page 51: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

However, if needed, these can be computed from the paid

crew hours relationship.

Excess peak service Number of buses in service /

All day service

Time of day

The cost of the excess peak service can be calculated as (A x bus

hours operated in the excess peaks), because successive removal of

bus hours from the peaks reduces crew costs by A per bus hour.

The cost of all day service can be calculated by subtraction

from the total crew cost.

Equal additions of bus hours between the peaks only, or in

the evening only, will change the profile of service through the day,

and may have different effects on total crew costs, but this we have

not so far investigated.

Peak vs. offpeak costs Service through the day can also be regarded

as consisting of the two components "peak"

and "offpeak" service.

46

Page 52: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Peak service

~ ~ ~ Off peak service

~-- Time of day

The cost of the offpeak service assuming that the peak

service stays constant can be calculated as (B x bus hours operated

in offpeak periods), because successive additions of offpeak bus

hours from zero increases crew cost by B per bus hour added.

The cost of the peak service is then (A x bus hours

operated in the peak periods), by subtraction of the offpeak cost

from the total.

An apparent anomaly should be noticed, which indeed throws

doubt on the usefulness of calculating total costs of blocks of

service. The anomaly arises if the offpeak service is increased

to the point where it operates at the same level throughout the day

as the existing peak service. Although service is at a constant level

through the day, the cost is now apparently higher at certain times:

in the former "peak" periods, costed at A per bus hour, vs. B per bus

hour at other times. However, even if service is level during the

day, provision of service in one period of the day may have a

discontinuous effect on total cost. (If the "day" were one shift long,

the crew hours paid for would be nearly equal to the bus hours. If

47

Page 53: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

the "day" were to be one shift plus one hour long, the total cost

would jump. To which hour in the day should the jump in cost be

allocated, or should it be spread evenly?)

Taking the "extra" cost into the peak period in the special

case when the peak and offpeak levels of service happen to be equal

at least has the virtue of consistency and continuity with the normal

situation when the peak is higher.

Having now described the relationship, its uses for route

costing, and some of the caveats necessary in interpretation, we

describe now how our results were derived in MPTE.

4.8 Analysis of crew costs in MPTE We established the relationship

between total direct crew costs

and bus hours operated in each time period (weekday peak and offpeak,

Saturday morning, Saturday afternoon and Sunday) by a two step process.

The first step establishe~ the simple relationship already

described between crew hours paid, peak bus hours operated, and Offpeak

bus hours operated (for weekdays), and a similar relationship for

weekends.

The second step calculated the direct crew cost per crew

hour paid, for each type of operation (DDOMO, SDOM0, two-man crew).

The first step To accomplish the first step, we performed linear

regression analyses of MPTE's duty sheets, to relate the scheduled

crew hours paid for the duties on the duty sheet to the bus hours

48

Page 54: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

operated in each time period by all duties on the duty sheet.

analyses were made for weekdays and for weekends.

Separate

The scheduled crew hours paid were calculated for each duty

using rules taken from the union operating agreement and payroll

calculation, and totalled for each duty sheet.

Some small pieces of duty are scheduled to be worked as

overtime. These were counted in "crew hours paid" at the appropriate

rate (i.e, 50% extra paid hours for overtime, and subject to certain

minimum payments).

No full duties are scheduled to be worked as overtime:

only standard rates (and penalties) were included for all full duties.

Rest day work is unscheduled, voluntary, and a function of

the (variable) level of staff shortage at each garage. The premium

part of payment for rest day work is treated as a variable overhead

for the garage, not in this part of the calculation.

Figures for bus hours operated were derived by calculating

the number of buses provided by the duty sheet in each quarter hour of

the day (using a time diagram of the duties worked), and totalling for

each duty sheet by time period.

The second step In the second step, we calculated the cost of each

crew hour paid.

Separate calculations were required for each type of operation,

and to reconcile scheduled crew hours paid as calculated from the duty

49

Page 55: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

sheets with actual hours paid, as shown on the payroll. Differences

between the scheduled and actual hours paid arise because of:

- service cuts

- unscheduled overtime and rest day working

- time spent: on holiday

sick

spare (but not on scheduled standby)

training

any other time not on working duty

We reconciled these differences using duty sheets, the payroll cost

summaries for the particular week studied, and logs maintained at

the garage showing the work done by each man at the garage during

the week, and used as input to the payroll calculation.

Other payroll costs were calculated for inclusion in the

bus hour related, variable overheads cell of Table 2.1, by reference

to the payroll summary and the reconciliation calculations~

Results A summary of the results is presented in Table 4.1, which

shows our estimates of the direct crew cost of a bus hour

of operation in each time period for each type of operation.

Tables 4.2 and 4.3 show separately the results of the first

and second step in the analyses just described.

These results should be applied subject to the general

caveats described in section 4.6 and specific conditions for MPTE

described in section 4.9.

50

Page 56: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Accuracy of estimation scheduling variance The number of crew hours paid

was estimated by a simple

calculation, multiplying the bus hours in each time period by the

corresponding coefficient from Table 4.2. This estimate was compared

with the actual scheduled crew hours as calculated directly for each

duty sheet. The estimates were accurate to within 10% in all cases,

and within 5% in most.

Scheduling variance is the term we use to describe the

cost of this difference between actual and estimated crew hours paid.

Favourable variances result if the hours required by the duty sheet

to be paid for are less than the "standard hours"estimated from the

coefficients of Tsble 4.2, and vice-versa. The variance is shown in

Table 2.1 in the "variable overheads, bus hour related" cell.

4.9 Consistency with other research The numerical values we have

obtained reflect the partiCular

union agreement in MPTE, and the nature of MPTE's services and

scheduling practices. However, the results we have obtained do confirm

evidence from other research studies that the crew costs of additions

to peak period service can be substantially higher than the costs of

additions to weekday offpeak service.

London Transport Executive. A Crew cost Model for Buses, Operational Research Report R178, December 1971, and Egerton, Mark. "Statistical Analysis of Platform Labour Costs". Unpublished paper, Ministry of Transport, July 1969.

51

Page 57: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

5"2

rO ~ I i-~ [=.I

I:~ CO Z 0 " ~ : ~ ~:~ 0 0

E-~ b-~ H

0 ~.~ ~=I

~ _~ 0

E-~ l~l O 0 09 r-~ o a:~ r.o

O Z

~Zl ~ H

O E-~

c~

~ c ~

0~

c~

°

I

O ~

0

H

o

I--I E~

,J

e~

e~

(:0 e~

r- I

e~ e ~

,.-I

b - b -

J

b-- -.4-

0 x

C'q

",.0 b -

0

e~

D-

O

C~

P~ c~

0

G" 100

0

0 0 x

o

b-- O0

d

0 0

r- I

0

,'cl

O~

',.0

,,D

~0

O0

~0

Rg

(L)

..~ 0

Ch 0

II II

C~ 0 ~

I ~ II If

O

",.1" II

e~ 0

r- I

0

,--I

r- I

E~

!

I"0

0 (D

cd 0

cd

0 E'~

0

C~

"cl

O)

.,~ P~

(D (D

0

O'J

CO 0 0

0

~C~

o "

b~O

-r l

0

I

e~

0

0

o

b~O

-r-I ~ . . ~

eJ

O 0

~ 0

0 , - ~ o o

0

, , +~ ,-~ cd

~) ,'cl ~ - ~

cd

0

b o b .

m"c~

m O

o

~ A 0

0

Page 58: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 4.2

CREW HOURS PAID PER BUS HOUR.

BY TIME OF DAY AND WEEK

Figures are derived from the schedules in operation in

w e e k 48, 1973, i n MPTE

DAY OF WEEK

Weekday (Monday to Friday)

Weekend**

CREW HOURS PAID TIME OF DAY PER BUS HOUR*

Peak 2.0

Off peak 1.1

Saturday up to 1 p.m. 1.3

Other weekend 2.O

Notes

Figures are quoted to the nearest tenth of an hour, ms they are subject to residualstatistical uncertainty of the order of 10%. In our calculations, three significant figures were used to ensure that total hours paid were reproduced accurately.

A few weekend "extra" duties are scheduled to be performed as overtime. For these duties, the weekend coefficients shown should be increased by the 50% overtime premium paid in MPTE.

53

Page 59: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 4.3

DIRECT COST PER CREW HOUR PAID,

BY TYPE OF OPERATION

TYPE OF OPERATION

Double deck, one-man operated

Single deck, one-man operated

Two-man crew (driver and conductor)

DIRECT C0,gT PER CREW HOUR PAID

P e n c e 69

67

117

Note that the costs shown are only those defined as direct costs in Chapter 3, and represent only a part of total crew payroll costs.

54

Page 60: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

d i r %C:.t- czr,@w ea~ e%~q.~..f" t.rQu~t %s, ~a:n,~ o~r~o p, qs %dr clh:a.;n~g %s.,j~,t~e.j %b,e:~, [.sag~j!,~c!t, ~$o~ sth~ej j

general caveats desc'ribed in section 4.6, and the follo.:ow:i-n,:g:~tm,ojr:e~oai ¢'~Jxo

specific assumptions which must be checked before applying the results

of Table 4.1 in MPTE. We assume that: . . . . . . , , . , . [ [0 ~ 3 2_!: J.[.;d ~.3.3 £ ; :~ . :e"z .'.= ' ~ _ , . , : . ~ i E ~ . . . . . . .,~. 3 d ~ .J_L:~s. ~ t : o : . ,

~-,: ~-~.[ :r~g Ga,} ~uSc~ed, ul, ers nqonti:n~'e~ to i-us ~.j-the _,s,ame-, a.~.l~roach ,to Grew-~ ~.. ~ ~, .~ .,q s

=s~qhed, uli.ng,p ~:and ~c, ont-inue ~,~to iapplM ..~th.e~ ,=s, ame ~p, roq~edu~e,s: .. ~ ,* ;

and rules in the construction of schedules, . w : . i , ~ h / %b, e u % , ; - f , ; e . , T c , . - ,

the same efficiency in the use of crew time as at present.

(b) Any changes to wage rates and other payroll cost elements,

and the extent of unscheduled overtime working, sickness,

and holidays are allowed for, and used to adjust Tables 4.i

and 2.1 before use.

(c) The location of relief points on new routes is not such as

to cause a significant amount of wasted crew time resulting

from a particularly awkward fit of journey times into crew

duties (this effect does not seem to be important on

existing routes).

4.11 Application in other companies The basic cost structure of

Chapter 2 can be applied in

principle to all bus companies. Crew costs can be analysed by a

method either similar to that used in MPTE, or by a simpler method

under development, but this method of analysis will not apply in

companies with a union agreement which consolidates spreadover pay

into the basic rate.

In those undertakings, increases in peak working would

55<'

Page 61: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(usually) be accommodated by more spreadover working; up to a point,

this might not increase cost per peak bus hour. Beyond that point,

the consolidated rate would need to be increased to compensate for the

extra inconvenience.

A rough estimate of the resulting increase in total crew

costs could be made using MPTE's results, but it can only be an

approximation, as the effective rate will change in jumps in undertakings

with a consolidated agreement, following renegotiations of the

consolidated rate.

56

Page 62: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 5

DETERMINING ROUTE NET COSTS

5.1 General principles By the net cost of operating aroute

we mean the difference between the costs

which are attributable to operating the route, and the revenue which

is attributable to its operation. The value of knowing the net cost

of a route is that the effect on the financial position of the

company of operating this route can be determined, and the extent to

which it would need subsidy to break even can also be established.

Costs The costs attributable to the operation of a route are of

two sorts: its avoidable costs, and an apportionment of

fixed overheads. The avoidable costs are those which could be

avoided if the operation of the route were to cease, and corresponding

adjustments were made to crew schedules, crew numbers and traffic

supervisory staff, number of buses owned, engineering staff numbers

etc. Avoidable costs correspond generally to direct costs and

variable overheads, as defined in Chapters 2 and 3.

The apportionment of fixed overheads was discussed in

section 3.4. These costs would not be avoided if the route ceased

operating, and are not relevant when considering possible changes to

a route. They are merely useful for the two purposes given in

section 3.4: determining if a route is making a proportionate

contribution to the recovery of a company's fixed overhead in total,

57

Page 63: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

and possibly in connection with the question of the amount of

subsidy required to break even, if a subsidy is being considered

on a route-by-route basis.

Revenues The revenue attributable to the operation of a route

can have more than one component.

The first group of components consists of the revenue

actually collected from passengers travelling on the route. Even

this seemingly straightforward part of the revenue is becoming

harder to determine, as company revenue is increasingly received from

sources other than cash fares collected at the time of boarding.

Use of a route by season ticket and multi-ride ticket holders,

concessionary travellers (old age pensioners, schoolchildren, police

on duty, etc.) can only be satisfactorily estimated by special surveys.

Even cash revenue attribution to routes, based on analysis of waybills,

is time-consuming and expensive to perform on a regular basis, and the

introduction of fareboxes and other forms of cash revenue collection

pose their own problems of route analysis of receipts. Our study

was not intended to address these problems in any depth, and we have

not done so, except insofar as was necessary to analyse revenue for

the routes we studied in detail.

A second group of components of the revenue attributable

to a route consists of the revenue which would be gained or lost on

related routes if this route were to cease operating. This group of

58

Page 64: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

components will be important principally on routes which are being

considered for service alterations. Gains could occur on parallel

alternative routes if passengers switch to those routes instead.

Revenue could be lost if journeys which were made partly on this

route, and partly on connecting routes, could no longsr be made.

As a starting point, experienced judgment should be applied

to the route in question if changes are being considered, to see if

this component of revenue is likely to be important. If it is, then

special ad hoc studies may be required, or judgment -- applied to

such route revenue information as is available -- may provide

sufficiently accurate answers for the particular decision being made.

59

Page 65: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

5.2 Application to routes

borne in mind when determining route net costs.

steps may be summarised as:

(a)

(b)

Section 5.1 described the general

principles and considerations to be

In practice, the

Determine the revenue attributable to the operation of the route.

Determine the costs attributable to the operation of the route.

Attributing revenue Systems of fare collection vary so much

between companies that we have not found it

possible to make general recommendations for attributing revenue to

routes. Section 5.3 describes what we did in MPTE, and illustrates

some of the practical requirements involved.

Attributing cost Section 5.4 describes the determination of

avoidable costs for a route. Section 3.4, in

Chapter 3, has already covered the attribution of fixed overhead.

6O

Page 66: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

5.3 Revenue estimation - methods applicable to MPTE MPTE stage

carriage revenue

comes from four main sources: cash fares, multi-trip tickets (Bus

Economy Tickets, or BETs), schoolchildren's passes paid for by the

school authorities, and concessionary travel, which is paid for in

part directly by individual local authorities, and partly by the

general rate precept, which also covers any operating deficit. Minor

additional income is received from season tickets and other sources.

Cash Fares We analysed cash fare revenue for all the routes operated

from one garage for one week, by manual extraction of

information from MPTE's usual form of waybill. This process required

a substantial initial effort to determine which journeys in each crew

duty are worked on each route -- information which was available by

analysis of existing records, but not summarised in a useful form.

The preparation and maintenance of such a master file relating journeys,

bus "boards", and crew duties is an essential step in the routine

analysis of cash revenue by route and time of day and week.

We did not attempt to assess the secondary component of cash

revenue attributable to each route by virtue of its relations with

other routes.

Bus Economy Tickets These tickets are issued from many locations in

the city including agents (tobacconists, newsagents,

travel agents etc.) as well as from MPTE garages and public information

points. They are valid for journeys on any route, up to the fare

61

Page 67: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

value printed on the ticket. Each ticket is valid for ten trips,

and is cancelled one trip at a time by a machine on the bus. The

tickets are sold at a discount of 20% off face value. For the

purposes of this project, MPTE hoped to mount a special survey of the

use of these tickets on the selected routes, counting the cancelled

clippings collected on each bus, and analysing them by value, route,

and time of day. However, the results were not available in time to

include them, and hence an approximate allocation of BET revenue

to routes has been made.

Schoolchildren's passes These do not account for a very high

proportion of revenue, so an arbitrary

allocation of this revenue was made to routes in proportion to the

bus hours operated during the times of day in wh~h the majority of

schoolchildren travel. ~ Further detail if required could be obtained

from an analysis of the school name and pupil's address information

on each pass, either at the time of issue, or when expired passes are

returned at the end of term.

Concessionary travel ~ The use of routes by old age pensioners and

other concessionary travellers was analysed by

MPTE staff from a survey mounted in early January. Each concessionary

traveller was issued at the time with a zero-value ticket, and special

records were kept of the number of tickets issued by each crew.

Another method, which has been used by London Transport, and may be

used in the future by other companies including MPTE, is to use a

home-based interview survey of a sample of concessionary pass holders.

62

Page 68: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

It may provide more, and more reliable, information at about the

same or lower costs.

The revenue to be attributed to a Journey made by concessionary

travellers presents special difficulty, because they do not pay on the

basis of the number or length of journeys made. We have therefore

confined ourselves to estimating the number of journeys made on each

route by concessionary travellers. For many purposes, this is

sufficient information. For other purposes, an average value per

journey can be assigned, based on the total number of journeys made,

and the revenue which would have been obtained had they paid the

corresponding regular fare.

63

Page 69: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

5 . 4 Cost +de~t~e~in~tib~ . " " . . . . "' "~ . . . . . . ' , _ a v o ~ d a b t ~ e ~ c o s t ~ e ' ~ T h e ~ a , v b i d : a ~ i e Z ~ o . ~ t s ~ . : o f ~ • ,

operating:,,.a Cro6,t:,ec~re thes~d

costs which could be avoided if operation on that route were to cease.

F o r a r o u t e w h o s e o p e r a t i o n c a n b e c o n s i d e r e d i n d e p e n d e n t l y , t h e

avoidable costs correspond directly to our definition of direct costs

p l u s v a r i a b l e o v e r h e a d s . T h e a v o i d a b l e c o s t s f o r s u c h a r o u t e a r e

thus estimated b~ calculating its use of bus hours, bus miles, and

peak buses, and applying the appropriate unit costs derived from "/~'- ' ,~ 3 . ~ . ~ "r " ~ ' ~ ' : e v ~ f "~ ~ t ~ . ~ J ; . ~ , " , . ~ . 1 ¢ . ~ - . , ~ . . ~ . ( t ~ ' : ; , ~ , ",] , .~ .~O~L , ; ~ . . ,

e a n d 4 . 1 , e x c l u d i n g a l l t h e f i x e d c o s t e l e m e n t s i n T a b l e

9 " ' U n d ' ~ r Ts p ' ,~ 'dT'a l ' ~ c ' i ~ g ~ m S ' ~ a ' f i c e ' s '~ ~ ~o t ~ h ~ ( f -a c t o r s ' , m a y fl'e @d 't~6 b e ~. ~ i

taken into account. ," ~ - ~,3 -'3 '' "~t ~ ~,I~(~ ~. j ..' ~',j

Just as, for revenue, there may be secondary effects on

other routes, so there may be related cost consequences on other routes

if one route ceases operation. Cancellation of service on one route

may require that additional substitute service be provided on other

routes, either to cope with increased traffic, or to provide an

acceptable alternative-standard of service.

"Fixed" overheads may become avoidable in some circumstances.

For example, the cessation of service on one route might allow a whole

garage to be closed. A potential example of this exists in MPTE.

Spare capacity is available at one garage. Another nearby garage is

also kept operating, but it is small, and costly to run. It cannot

now be closed because its buses cannot all be accommodated within the

spare capacity available. Should some of its services be cancelled,

~64

Page 70: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

however, the remainiHg buses could be transferred to the nearby ~

larger garage with spare capacity, and the small garage could then

be closed and its fixed costs avoided.

65

Page 71: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 6

PILOT APPLICATION IN THE MERSEYSIDE PASSENGER

TRANSPORT EXECUTIVE

6.1 Objectives The objectives of our pilot application of route

costing in MPTE were twofold:

a)

b)

to ensure that any principles and methods we proposed passed the test of being feasible in at least one practical situation

to obtain results which would be of direct use to MPTE operating, planning and financial management.

6.2 Coverage of the pilot study We needed to study a sufficient

number of services to ensure, so

far as possible, that our methods would apply acceptably well to

services having different sizes of peak and offpeak working, different

numbers of buses at peak periods, and offering different types of

service to the public.

We also wanted to keep the amount of data analysis to the

minimum necessary to achieve the objectives.

With these considerations in mind, we selected all the

services operated out of one medium-sized MPTE garage, which provides

service on a mixture of route types, including suburb to suburb,

(routes 66, 88), suburb to city centre (routes 4,5,85,86,87), and a

"Cityride" shoppers' service (route lO0) on a short loop route in the

centre of Liverpool.

66

Page 72: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The garage chosen had little interaction with other garages'

services~ although it does provide some service on other garage routes,

and receives in return some service from ocher garages on its "own"

routes, mainly in peak periods. Service on each of its own routes is

provided from up to four different duty sheets.

Our reason for choosing a whole garage for analysis was

that it offers advantages in data collection and in ensuriug accuracy.

Much existing information is already summarised by garage, and can be

used either directly, or to check totals etc. arrived at by other

means.

One full week's operation was analysed for this garage.

This was the necessary minimum time to which much of•the important

• summary information available was related (e.g. payroll) and also,

we believed, the shortest period over which revenue could be meaning-•

fully analysed because of the likelihood of substantial variability in

the pattern of takings between routes and between days. Our findings

fully supported this initial belief.

6.3 Feasibility in the pilot study, and implications for ~eneral application It proved possible in the

pilot study to achieve the

cost and revenue analyses we had been aiming for.

67

Page 73: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The main steps were :

a)

b)

c)

d)

e)

to analyse crew duty sheets for the whole of MPTE to derive the direct crew cost coefficients described in Chapter 4.

to structure andanalyse costs into the format of Table 2.1, in order to derive unit costs of operation per bus hour, bus mile and peak bus t distinguishing direct costs, variable overheads and fixed overheads. This was done for one week's operation in the pilot garage. Some overheads were pro-rated from management accounts figures for the whole Executive.

to calculate each route's Use of bus hours and bus miles by time of day, and its peak bus requirement, for all routes operated from the pilot garage.

to calculate route costs by combining a), b), and c) for each route operated from the pilot garage.

to analyse revenue by route.

Three types of effort were involved in each step:

i)

ii)

iii)

Work such as would be required initially to design the system.

Work such as would be required initially in setting up an ongoing system - compilation of basic data and its analysis.

Work such as would be required in an ongoing system.

With the assistance of MPTE staff, it was found to be possible in the

period of the pilot to perform all these steps.

Initial work to design the system We spent sufficient time on this

aspect of the pilot work only to

ensure that it would be feasible to complete our pilot analyses with

the resources available to us. We developed manual methods of data

compilation and analysis which worked acceptably well on a pilot

68

Page 74: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

scale, but we were not aiming to design a system which would be most

efficient in routine use.

The larger the scale of application, the more effort it is

worth putting into system design to make it as efficient, practical,

and useful as is feasible. Our pilot results give some indications

of the type of analysis which has proved possible, but more extensive

design work would be needed before launching on full-scale implemen-

tati on.

Implications for setting up systems Set up effort depends to a great

extent on the complexity of route

service structure in the bus company, on the amount of initial analysis

required to establish peak, offpeak, and weekend crew costs, and on the

ease with which existing cost records can be structured into a table

like Table 2.1.

In all cases, it will be necessary to set up a file relating

bus journeys, crew duties, and each bus's work during the day in order

to be able to calculate each route's use of bus hours, bus miles and

peak buses and to attribute cash revenue to routes, by time period.

The file will be simple if the provision of service on routes is simply

related to duties. In MPTE, as in some other undertakings, this was not

the case for a substantial proportion of crew duties, for which detailed

analysis of the work on different routes was required, journey by journey.

The file can be compiled manually in the first instance, as we compiled

it. A computer system which allows the file to be generated from

computer-stored schedules data would increase the accuracy and speed of

preparation and updating of the file.

69

Page 75: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Establishing crew costs by time of day requires a second

substantial set up effort. The method we oniginally used in MPTE may be

applicable in some other companies, but we have developed a simpler method

of analysis, which we believe will apply for the analysis of peak and

offpeak crew costs in most bus companies with unconsolidated union

agreements.

A third set up requirement is the preparation of an overall

cost structure like Table 2.1, which requires the classification of

expenses as direct costs, variable overheads, and fixed overheads, and

according to the type of activity to which they are most closely related

(bus hours, bus miles, or peak buses).

This Table must be built up from records for the company as a

whole for some overhead costs, but can be compiled for parts of the

company only for other costs.

Our principal difficulty in compiling Table 2.1 for the pilot

garage arose for the engineering costs, for which records were not kept

in a form suitable for easy use in developing Table 2.1. This difficulty

was discussed in section 3.5.

The system requirement is for a clearer separation in the

recording of engineering costs, into the headings shown in the cells

of Table 2.1:

m

cleaning and maintenance materials used at garages

major maintenance (excluding bodywork)

accident repairs

cleaning, servicing and garage maintenance payroll, excluding supervision and admin. payrolls

other major maintenance

engineering supervision and administration.

70

Page 76: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Implications for ongoing systems As a rough indication of the scale

of effort that might be required in

an ongoing system, we estimate that a section of 6-8 clerical staff

could prepare quarterly route cost and revenue reports like those

shown later in Tables 6.1 and 6.2, using manual methods such as those

we developed for the pilot, and applying them to the routes served by

MPTE's 1400 buses. We do not recommend manual methods for long-term

use except in small companies, but they could provide a useful interim

step prior to computer system development.

We would expect that a high proportion of the effort would

be devoted to revenue analysis. Cash revenue analysis needs either a

complete analysis of waybills for a whole week or more, each time the

analysis is done, or will require great care in sampling techniques

based on extensive prior research, if applied more selectively to

certain days or journeys only. We found very considerable variations

in cash revenue, both between days on the same route, and in the

pattern of revenue takings through the week on different routes. No

consistency of pattern could be established on the basis of our one-

week analysis.

It would be desirable for accuracy of analysis of other

revenue by surveys, etc., to build into the survey design a means of

analysing non-cash-fare passenger journeys by time of day and week.

71

Page 77: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

6.4 Results prepared for MPTE The main management planning reports

which we have prepared as a result

of the pilot application in MPTE are illustrated in Tables 6.1 and

6.2 at the end of this chapter. They are respectively a summary of

route cost and revenue for the whole garage studied, and a detailed

report for each route. The unit costs and the revenues used were

those applicable to the one week of operation of the pilot garage which

we studied in most detail.

Route 86 is used for illustration of the format of the

detailed report: similar reports were prepared for each other route,

and are included in a report submitted to MPTE. Two of them are also shown in

Chapter 7.

It is envisaged tha~ these reports would be prepared several

times per year, one summary like Table 6.1 for each of MPTE's garages,

and one detailed report like Table 6.2 for each route •or special service.

Interpretation of the information shown on the reports is described in

a series of notes following the two tables.

Particular attention should be paid to columns (P) and (Q)

of the reports. Column (Q) -- fare revenue contribution to fixed

overheads per bus hour of operation -- is in our view the best single-

figure financial yardstick to apply to a service's operation, and

should be used in preference to the traditional "revenue pence per

mile" figure, wherever possible.

Note that no allowance has been made on the revenue or

contribution columns for the carriage of 0APs, which is free offpeak.

72

Page 78: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Some of the uses which can be made of reports of this type

and of our costing methods are illustrated later, in Chapter 7.

A number of other special reports were prepared, and are also

contained in the report to MPTE. The discussion in section 6.3 was based in

part on these other reports, particularly the comments on the

variability of cash revenue. The reports were mainly of detailed

interest to MPTE, but the following general observation can be made.

Losses at some times of the week The route detail reports show that

all routes at the garage whose

operations we analysed make losses at peak periods, not even making a

positive contribution towards fixed costs (except for one route

operating only one bus), and all routes except two made losses on

Sunday.

The losses ranged from £0.45 to £3.70 per peak bus hour,

before fixed overhead attribution, and totalled about 22% of present

peak farerevenue or 7% of weekly total revenue. For further details,

see section 7.6.

Sunday losses range from £0.07 to £1.26 per bus hour, before

fixed overhead allocation, but the overall loss on Sunday is small

because of the one busy, profitable route, 86.

6.5. Conclusions from the pilot study Judgment of the potential

usefulness of the types of

results which we have achieved in the pilot can perhaps best be made

after reading Chapter 7, which describes some potential uses of the

results. Our own belief is that they offer considerable promise for

improved bus company planning.

73

Page 79: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

v |

|

v

e ~ v

• : , : ,

0 ¢*) n • I I

m m ~

v. :~ O | • ~.*

I u

e

0

~ : °

c:; ~:* vl

0

e : o I

- -4

|

I--I i

e

; l : ~ l v e

O m

| |

I II

. 4 "

e u

e ~

i : l a l ILl

|

: . . . . . . . . s , . N :

| I

| e . . ; n u - - - - ° , o . . . . . . .

t s

N ~ ~, ~. =o ~ ~ ~ .~ .~ ~ ~ . r . .

l r l It • , , . -

.~ : ~ --. ,

: ~ N Z e # I

u

r ~ n

- U

u

;/)it J I q T ~ m '-~* II ~ N ~ I e . m

Im I

m l ~ o

u

T S

I n

I-- u

~ g

m u

u

N m

t m m

| II a

, ~

r a

~ u

i . ~ u ~ U

(1)

0

> .

0

< 0 0

0 , 0

C~ ' . . )

o

0

0

C~

0

z

',,0

C ~

Z LTJ ;>

O CJ

0 c~

< c~ <

74

Page 80: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 6.1

(A): Routes covered

The numbered routes are public stage carriage services. "BSS" refers to a service provided under a recurring contract to carry passengers from British Rail's station to the cross-channel ferry. "Sch/Univ" are school and University special services, mainly for carrying school and University students to and from playing fields on sports days. Football services are run from various points in the city to the local teams' grounds when they are playing, and special cash fares are charged on these services.

"Non-garage" lines on the report summarise iuterworking with other garages, and provide the reconciling items to agree the totals by route to the garage's grand total. The "out" line refers to service provided, and revenue collected, by this garage working on others' routes, and the "in" line to the reverse situation. Negative amounts, or losses, in the contribution and net revenue columns are shown in parentheses; since the losses on the "in" line belong to other garages, they are shown with a minus sign preceding them, and go to reduce this garage's loss.

(B) to (F): Revenue

The set of "revenue" columns analyse route revenue. Cash fare revenue is shown in column (B), by route. It was obtained as described in Chapter 5, by analysis of waybills, and is still the dominant form of revenue.

Column (C) shows an estimate of revenue from BETs (Bus Economy Tickets), based on an approximate allocation. Travellers Ticket revenue was ignored in the pilot application (it is less than 1% of total revenue).

routes. Column (D) shows an attribution of scholars' revenue to

Column (E) shows miscellaneous fare revenue-- in th~s instance, for the BSS contract and ~chool and University services only.

Total fares are shown in the next column (F), which is a total of columns (B) to (E).

75

Page 81: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(Notes to Table 6.1~ continued)

(G), (H): Passengers carried

These next two columns show an estimate of the number of passengers carried ou each route, obtained for 0APs from a special zero-value ticket issue survey, and for other passengers by dividing total revenue by an assumed average fare per passenger. These two numbers provide a means of assessing the relative and absolute importance of concessionary vs. other travellers on each route.

(I) to (M): Cost

This second set of columns shows the components of the direct costs and variable overheads on each route. All figures are in £s.

Direct costs related to bus hours are shownin column (I); those related to bus miles in column (J).

Columns (K), (L) ana (M) show variable overheads related to bus hours, bus miles, andpeak buses respectively.

(N) to (Q): Contribution

These columns show revenue less direct cost and Variable' overhead, respectively for cash revenue only (columns (N), (0)) and taking all fare revenue into account (columns (P), (Q)).

Column (N) = (B) - (I) -.(J) - (K) - (L) -(M)

C o l u m n ( p ) = ( F ) - ( I ) - ( J ) - ( K ) - ( L ) ' - (M)

Columns (P) and (Q) are arguably the most important columns in this report, and in Table 6.2. Column (P) shows the net contribution (or loss) to fixed overheads which would be given up within a few months if this service ceased to operate. Column (Q) is the best single-figure financial "index of merit" of a route we have been able to devise.

(R): Fixed overhead allocation

This figure indicates the amount of contribution which should be expected from each service in proportion to its use of bus hours and peak buses in accordance with the allocation of Table 2.1.

(S), (T): Net revenue

These columns show fare revenue contribution less fixed overhead allocation, both in £, and £ per bus hour. (Column (S) = (P) - (R)).

76

Page 82: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

1

I I

~ e

!

e

r

~ e

i

l e

~ l

0

v l

- J

I n e

|

r

O l I ~ .

U J I ~

X : . g :

~ m

n ~ o I

: >~ :~.,

n ~

( I I ~ :

: ~ . J

~ m

I-.- w .

I,,,) I I Z: ILl

I'-- •

!

I

. . . . " ~ ~ , ,~ ~ o :

{.~ I I 0,. I , ~

u~

e ~ m

• N

l : o a •

, < 0

~- % It:

I •

I - I

r c. ~ :

~ I 0 I

r I r I ; , | •

c .

I / I I-~ I { , I

~ e ,,It a e e

| •

i i ! • i |

0 ;

~ r~ i ~ ~ e ~ 0 ! 0

I I

I

r ~ I I

I !

~ , . ~ ,

r

0 I

I I

0 0 0

I I I I I

I r I

0 ~ - - I

I 0 1

I •

! I I r N

, , ; ."

.:, .-. , , ~ , , ~ = I I I ~ n

' • '2; I[ I I

o , , ." | |

• I I I

', ' I :

I I I .~I" II I I I N

I I I ~ I • I II ~ I I I I I I

• I I I I I

., . I o i I e

e ~ i e I

I , , ,

$ I I

$

I I I I

° : n

" I • | •

R

~ m

O m

I . ' ~ n e ~ n ! ,41 m

g ;

o

o

.< ©

o

e . .

o Z

©

Z 0

©

.< [.-,

z

[--.

8

??

Page 83: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 6.2

(A): Period

Shows the period of the week to which the line refers.

Weekday: 0200 Monday to 2400 Friday, Saturday 0001 to 0200.

Peak: 0700 to 0930, 1600 to 1830 0ffpeak: All other times

Weekend:

Saturday: Sunday:

0200 Saturday to 0200 Sunday. 0200 Sund~y to 0200 Monday.

(B) to (Q): Revenue r cost, contribution

As for Table 6.1

(U): Percent service cuts

This column shows the extent to which services scheduled were not run, for whatever reason, in the period being analysed. It is expressed as a Percentage of scheduled bus hours which were dropped.

(V), (W), (X): Scheduled bus hours, miles, buses

These columns show (V) the bus hours (to the nearest whole hour), and (W) thousands of bus miles (to the nearest 100 miles) scheduled for one week's operation in each time period; and (X) the average number of buses in service during each period, to the nearest whole bus.

78

Page 84: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 7

EXAMPLES OF APPLICATION IN PARTICULAR

PLANNING CONTEXTS

7.1 Summary In this Chapter we give examples of the ways in which

the cost and revenue analyses could be used in a

variety of possible planning decisions*:

a)

b)

c)

d)

e)

f)

To estimate the revenue and cost consequences of changes to the "Cityride" route following the closure of a city-centre street for pedestrianisation, and the council's decision to provide free service on the route during offpeak hours (section 7.2).

To estimate the net cost of providing service at some times of the week on one route (section 7.3).

To estimate the cost consequences of conversion of a route to 0M0 (section 7.4).

To estimate the cost consequences of altering service frequency on a route (section 7.5).

To assist in a discussion of the value of increasing fares at peak periods (section 7.6).

To assist in a discussion of the value of inmreasing service in offpeak periods (section 7.7).

Within each of these sections we first briefly describe

the planning problem, then illustrate, by a table, the route costing

information which can be used to assist the planning decision. In

several cases the table takes the form of a Costing Worksheet (see

Table 7.1), a worksheet on which the unit costs described in Chapters 2

and 4 are set out in a form suitable for calculations based on bus

hour, bus mile and peak bus data.

* The broader implications of planning decisions are not, of course, discussed in this report.

79

Page 85: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The effects of operational changes on hours, miles and peak

buses operated have to be calculated separately; a note following

the table indicates considerations to be borne in mind in each case,

but details of those calculations are outside the scope of this

report.

The unit costs shown on the worksheet are then applied to the

operational changes shown in column (A)of the worksheet. Columns are

provided for separate calculation of direct costs, variable overheads,

and fixed overhead allocation. As described in section 3.4, the use of

the latter is confined ~o two purposes:

a) determining whether a route is contributing to overheads in proportion to its use of bus hours and peak buses

b) in determining the amount of subsidy required to achieve the required level of contribution.

We have not illustrated these uses here; they are simple to apply

for these purposes.

80

Page 86: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

il

v

E-+ ~-.-,

+ o

r ~ O

• I:::l

° ~

"~ o o ~

a ~

, l : u

0 ~

N

0 H

0

+

11

IJ

II

n

,,<

II

0

o~ I il il o ~ ~

o , ~ ~

• il • 0

S S ,...; ,-; ' o '

I

I I

g o o

II ~ IIII

o

II n

n n

I i u i i i i

,.,-I

Q,I

i/ iI °

0

s

8 1

Page 87: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

7.2 Effect of street closure and free travel offpeak on route lO0 Early in 1974 the local

authority closed a busy

central shopping street to traffic to make it into a pedestrian area.

Many bus routes were affected by this closure and had to be re-routed.

The Cityride' service (route lO0) was most significantly affected,

providing as it does a service in both directions round a loop in

central Liverpool, which was considerably lengthened and diverted

round other one-way streets when Church Street was pedestrianised.

Subsequently, the local authority requested MPTE to provide

the service free to passengers, outside peak periods.

The questions at issue were: what was the cost of these

changes, what was the revenue loss, and what was the net cost?

Cost Table 7.2 shows the calculations required for costing this

change, by applying the unit cost coefficients to the changes

in operations. We estimate by this means an additional cost (direct

cost plus variable overhead) of approximately £4,400 p.a., compared

with a corresponding cost before the change of about £19,000 p.a. --

a 23% increase.

82

Page 88: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

m .m m m

m

M r ~

~,~,,

+ O f f

° ° ° ;I P4 P.I 0 .

° ° ;I - n I i • 0 .

¢~" I ~ [ - t II

• :21:: ~ II

0 0 ~ I!

• I~s., II r ~ < 1

II @

, " "+ ~I

11 ~) O} II m m II ~ QI II @ (b

p, " " , ; , o o ,

II Ii

m: ~'I i i

m+ I |

°1 ii

~ ~ ' , = a m l

,," . ~ , - o l i c , ~ o !

ii

O 0 ~ . ~D C '~ 0 u"~_

0 ~ 0 t ' ~

00, ~,~ ~D C ~"

o ~

,~1 o , ~1 ~

o ~ ~ ~ ~ o

(%1 I I

c~ o .-, ,-; '

I !

l

! I I

I

: I ! !

i

)

n (0 Ii ~:~ fl

0

o l

o ~ o x

( 0 .

~ .

. n fl n

n

~ .gg

I n . e : n u

n u 0 n n

! n

1 " ! i! n

i i ~ I | n Ii H I|

o ~ o ~

, -0

xO

0 3 . n

(*3 .

¢Q n II

:=:: . n

o

o

ii ° • i - I

QQ

0 ,.~

0

os

I:::

P, o

,,i[3

,P.

o

III

4 ) r - I

4 ) tO

0

0

P)

I-+

o~

f-i o

o l,...l r - I 0

:>r+ I ' 4

"I"4

P~ ,.i-I

0+

+.,+ o I:I

+- u ' J v

S~

Page 89: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.2

1. To convert this week's figures to an annual equivalent,

a multiplier of 52 weeks per year was assumed. This possibly

understates annual costs since extra crew costs are incurred

at holiday times through higher rates on public holidays and

more overtime in the summer holiday period. More detailed

investigation could suggest a more accurate multiplier.

2. Hours, miles and peak bus data were calculated from

the revised duty sheets following the change. Earlier, but

less accurate, estimates could be made, using the proposed

bus running timetable, with an estimated allowance for time

required by crews and buses for out of service travelling

between the garage and the start of the route; and vice

versa.

3. The service is provided by single-deck OMO buses

(includiug some extra peak working) so the SDOMO crew rates

in column (B) are used.

4. Fixed overhead allocation is not relevant to this

calculation, so columns (D), (G), and (I) of the worksheet

are not used.

8~

Page 90: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Revenue Loss Table 7.3 shows revenue and costs on route 1OO in

week 48, 1973, before the change was made. ~/e calculate

the loss of revenue offpeak as £346 for this one week, or about

£18,000 p.a. The assumptions made in the calculations are noted

following the Table. It should be noted in particular that we do not

know at this stage-the possible inaccuracy in the £1'8,O700 estimate

which could result~ from week-to-week fluctuations In revenue. Regular

preparation of the" revenue data would permit this to be done.

Net~:cost Su$~ject to th~ caveats shown above, theinet ciost of the

.... r o u t e lO0 c h a n g e s was t h u s a b o G t £ 2 2 , 0 0 0 . T h i s fian be ; - •

compared with ~ the small net annual contribution of route IOO before

ther changes of_ about" £ 3 0 0 p.a.

\ • . .

i• ..

£

J

r

A

i

85

Page 91: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

#

3 c(

w

o z ~

~- a~ - .

~ m

: = = . o | • = i

e I • I

= "=:

0

ocu i w •

0 0 0

0 0 0

: 5 ' ~ " i i i ..-,-~ e ~,II i i ~l.i i

_,~, le ~,i.. o I

~ I l : l I

gi i'i i Jd l e

i ~,/i o e : g : :

~ n ~.~

> - : ~

> u :=

0 ~ e

0 ! e ! 0 ! I |

I I

i i $ e i - i i

~o. le z I I e n I l l

i i i ~ i l , - m o l

u I c I I I

~ , - ~ e e • I i I

~u o . . . . . . : = ,

. ~1 o o 1o1 i ~Z I I I

i • m I I i u

,," a' z : r . i ' " ~ I I ~" , I ~1 i e I

, ~."-. . ~ I ~ i i~ . i i

u _- : I

~ I : : )

I I •

0 • g 0 •

0 0 0 0

~- o ~ ~

I I •

Z

, : ,~:

l I in

I • I

I " t • , ! : : i

• I ~"o I | i I I ii ,, : , .

• , , : .

I e u

I I u

• t •

• e i

I I m I I u

e l s

O | |

| • o 0 u

I e a I i o • | e •

= o : o ! , o . ' .

e | m e e u

l e ~ I | •

o e I ~ 1 1 i ! i u

c~

o

o

>

0

r - .

c~

o

o z

o

o

"8

E E

86

Page 92: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.3

1. From this Table, one can see that of the total fare

revenue of £371 for the week, only £25 was collected during

the weekday peak periods. An abolition of the offpeak fare

would therefore directly have lost revenue of approximately

£346 in this week.

2. Scaling up by a factor of 52 weeks per year, and

assuming that week 48 is representative of the year, this

would imply an annual loss of revenue at fare levels

current in December 1973 of approximately £18,000. (This

may slightly overstate the revenue loss, since revenue is

lower on public holidays and in holiday periods.)

3. Some caveats are necessary. We do not as yet have

any detailed information by route on week-to-week variability

of revenue, so that we cannot say how accurate this scaled-

up £18,000 estimate is likely to prove. Also, the "BET

and Traveller ticket" revenue is only an approximate allocation;

this allocation scales up to about £700 of the annual loss of

revenue.

4. Regular preparation of the detail cost and revenue

report would allow the variability to be assessed, and

surveys of the actual use of BETs would improve the

estimate of their use by route.

87

Page 93: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

7.3 Estimating the net cost of providing service at some times of the week Sunday services on

all but two of

MPTE's routes at this garage lose money - fare revenue contribution

to fixed overheads ranges from a profit of £0.94 per bus hour on

Sunday to a loss of £1.26 per hour (see Table 7.4).

This section considers the question of estimating the net

cost of providing service on the route (route 87) with the

largest loss. The section illustrates the principles described in

Chapter 5.

Table 7.5 shows detailed route cost and revenue data for

route 87. A straight scaling up of the (negative) contribution from

Sunday service would indicate an annual loss of about £3,300; however,

it is at this point that the interaction between routes must be

considered. Routes 86 and 87 provide service on partially overlapping

routes, so that estimation of the net cost of route 87 service must

allow for the revenue that would be transferred to route 86 if route 87

were partially or completely withdrawn.

After taking this into account, a better estimate of the

net cost of route 87 Sunday service £3,900 is reached, as described

in the notes to Table 7.5.

88

Page 94: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 7. 4

SUNDAY SERVICE: FARE REVENUE CONTRIBUTION

BY ROUTE

Route

4

5

66

85

86

87

88

I00"

_ _ _ c _ o _ n _ t _ r _ ~ k u _ t _ ~ o _ ~ - _ ( _ ~ _ o s s )

Z/week £/bus hour

(52) (o.93)

(25) (0.61)

(3) (o.o7)

(35) (o.6o)

119 0.94

(63) (I .26)

6 0.43

Basic service frequency

(rains. interval)

3O

30

30

2O

15

3O

6o

* No Sunday service

Sources: Route detail reports and published timetable.

89

Page 95: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

g, q~

g

) . .

=°,o

O C , . I . . l .~l

Q m I

: : ) l l ~ 0 :

~ : , 0 :

m ~ i i c ) 0 • =c I

~. ,,. : ~. :

: :

:

e w e i i m : i

o c u o =

u n z i l~l

I ~,. I .al I l&l I

m x:

n e m |

~o

0 o o

~ : ~ : .0 , |

• • e

d " ~ ' t

= ; : e e ; l

| e

I~ la -J I e ~ •

.Jll • • I

; ; " ° : , , . . . . . ' ~:n~ m = --', • t e > . . : : , : ,

~ : ~ " ~ ~. : ~ :

~ 1 ~ . ~ ~ : ~- ,

o e l ~ e e e IV l I e

0e ~ . ~ e l , - • : : . ~ : ~= : : ~ 1 = , n ~ 1 , 1 1 1 1

L ° , : ~ 1

e I

l i= •

i

u

u

m

l e e

: I

~ : ~ : : ~- : ¢ e

~ , : ~ _~ : :~ :

~ : : :

~ : : ~ : ~ : z • .i I

( . ~ s ! I I t

o • ~ : ~ : .~ , sa.

° o : - : : * ~ e e t

I • I • I I I

0 0 0 ~ ' -

0 0 0

2, : . . : : , , : I I I •

,, : ; = . . . .

; ; ; - : e I , , : ,',

°

o

• |

• • l ~ n

I i o ~ l I • I u

. : =

e e •

e i

e e • i I I i I I I H

I I I B

I ~ m | I •

| e I n • I I • • e I a

o o .o: :;:

e i i I

I t i ~ m

I • •

I I I T I

~ U

,..M c~

o

o

~g

.< o o t ~

e-.

o

c~

0

z

o

z

©

o

.o

;--4

o ~o

E .E

o

90

Page 96: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.5

1. Revenue Total Sunday fare revenue was £55 in week 48,

or about £2,900 p.a. Since much of the route

of the 87 bus is common with that of the 86 we need to

consider the interaction of the two routes. Not all of the

revenue on route 87 would be lost, as some passengers could

use ~he 86 instead. Assume that 25% of existing route 87

passengers would travel instead by route 86, to give a net

estimated revenue loss of about £2,200 p.a. (75% of £2,900).

Iu practice, traffic staff should be able to assist

in making this judgment, based on their experience. We have

taken 25% for illustration of the principle that route

interactions must be considered.

2. Cost The avoidable costs (see Chapter 5) of Sunday

service are in this case quite straightforwardly

the direct cost and variable overhe~.d components of the

route cost for Sunday, a total of £118 per week, or about

£6,100 p.a.

Since SUnday buses are rarely full, no extra capacity

is likely to be needed on route 86 (the 25% switch of route

87 Sunday passengers to route 86 0nly adds about 3% to the

number of route 86 passengers, as can be seen from the

91

Page 97: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(Notes to Table 7.5 continued)

existing figure of 1,O00 Sunday passengers shown for route

87, compared with the corresponding figure of 8,000 Sunday

passengers on route 86 obtained from its detail report, shoWn

earlier as Table 6.2.

3. Net saving The net saving after a few months is

estimated at £3,900 p.a., cost savings

of £6,100 being partially offset by fare revenue loss of

£2,200. Achievement of these savings would depend on

management taking action to ensure that variable overheads*

are correspondingly reduced following the service cut.

The variable overhead component is an important part (31%)

of the savings; in particular, if rest day working and

operating staff numbers were not reduced promptly, only a

part of the savings would be achieved.

mainly other staff payroll costs (NHI, graduated pension, etc.), rest day overtime premium, supervision and training, maintenance materials, major overhaul and accident repair costs -- see Table 2.1.

92

Page 98: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

7.4 Estimating the cost consequences of conversion to OMO There are three principal

stages required in performing

this calculation. In the first, the effect of slower boarding on the

running speed of the route must be calculated. In the second, this

slowdown must be translated into a new timetable, and its changed

requirements calculated for bus hours, bus miles, and peak buses. In

the third, the costs of these changed requirements are calculated.

Table 7.6 illustrates the third stage, the calculation of

the cost saving (excluding revenue effects) for a hypothetical

conversion of one route to OMO -- hypothetical, because all MPTE

services at this garage are already OMO.

The operational changes resulting from the switch are

illustrative only. We believe they are reasonable although they are

not based on real data. The notes to the Table indicate how they

might be calculated (the first two stages of calculation discussed

above) in a practical case. Thus the conversion savings indicated of

~329 per week on direct costs plus variable overheads should not be

considered as an indicator of real cost savings.

93

Page 99: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

qMO aJ .(:o'[8':evs(.)o t~ " ",~

] 8

v ~

~ 0 < ~

O

~ ~ O

O ~

O O ~ ~ j . ~

~ X

N

O H

v ~

9

x , <

0

] I

"21 O I

I ~ O , ~ I

v

,'-4 ,-4 v v v

I I I

,-1 , - I

• - - °

,4 6 6 ,4

r~ o c~

,-4

U3 .

N ',:

, - I v

em

i 0 i c ~

" il o

• I I 6

• I

I

I

I I

I

I . - . 1 ~

I ~ )

I I I I 4

ii ~ I1

• r t

~J

hO

¢1

°

0

ff 0

,--4

C

]

0 "< ~-I

,-4

r~

~rj v

9 4

Page 100: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.6

1. Slowdown of service Detailed calculation of the slowdown

likely to be experienced on OMO

conversion is outside the scope of this study. In brief, it

must consider the fare collection system and its effect on

boarding time per passenger, the "dead time" per stop, the

number of stops on the route, and the number of passengers

boarding and alighting.

Although we are not concerned with estimating it here,

it should also be noted that revenue changes can be expected

following conversion.

2. Estimating operational changes The effect of the slow-

down on bus hours, bus

miles and peak buses is very strongly influenced by the relation

between the frequency of service and the length of the basic

journey time between end points on the route.

A small increase in journey time resulting from OMO

conversion can often be accommodated by reducing the layover

time, and no extra bus hours, bus miles, or peak buses are then

required. The only cost changes are then those of the higher

rate paid to 0MO driver/operators, less the savings from

eliminating the conductor, plus the other operating cost

differences between OM0 and two-man buses, if any.

To accommodate a larger increase in journey time, or on

a service with only a small existing layover allowance,

either an alteration to the frequency of service, or an

95

Page 101: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(Notes to Table 7.6, continued)

additional bus and crew (or sometimes both) will be

required.

3. Assumptions used We have assumed that the peak service

requires 10% more bus hours because

of the slowdown, and ¼ of an extra bus in the peak hours. We

also assume that a part of peak service will still be provided

by two-man buses.

We have assumed a requirement for an additional 5% of

bus hours of f peak (weekdays), when passenger numbers are

smaller than during peaks and the influence on boarding

times is less, rising to 15% on Saturdays but dropping to

only 2% on Sunday.

We assume that additional mileage amounts to 200 miles

per week, from the extra ¼ peak bus.

4. Calculations Column (E) shows the net direct cost

effect of the increase in SDOM0 work,

offset by a greater reduction in two-man work -- for example,

the entry for weekday peak is calculated as:

(198 hrs. x £1.33/hour) minus (177 hrs. x £2.34/hour) = £151 saving, shown as (151).

Total savings are estimated at £329 per week on direct costs

plus variable overheads.

96

Page 102: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

m

7.5 Cost consequences of alterations to service frequency In the case of a change to

off peak frequency which is

uniformly applied throughout the day, an approximate estimate of the

cost change resulting from the change in service frequency is obtained

by taking the existing offpeak costs from the route detail report

(e.g. Table 7.3), and multiplying by the ratio between the new

frequency and the old, both expressed in buses per hour. This is

illustrated in Table 7.7 for route 100.

A more accurate estimate can be made by comparing new and

old timetables to calculate offpeak bus hours and bus miles, •using

a standard allowance for the bus hours required in addition to "wheel

turning time" for layover and for travelling out of service between

the garage and the route. The hours and miles are then costed as

usual. Table 7.8 shows an example of this calculation (based on a

different route from the example of Table 7.7).

Peak changes Changes to peak frequency are more difficult to cost,

since the relation between peak frequency and peak

buses required is not always simple, and inaccuracies in calculating

peak bus requirements can have a considerable effect on cost estimates.

Proposals for a revised bus timetable should be worked out, to

calculate the peak bus requirement, and the bus hours and bus miles

to be operated in the peak period. These are then costed as usual.

An example is given in Table 7.9 and is described in the notes to the

Table. The example illustrates the considerable importance of the

"peak bus" cost component of the change.

97 i•

Page 103: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 7.7

COSTING OFFPEAK FREQUENCY CHANGES: SIMPLE APPROXIMATE METHOD

This example is hypothetical, but illustrated by reference

to the route I00 data previously shown in Table 7.3.

Cost of existing off-peak (weekday) service

- related to bus hours

- related to bus miles

Direct Variable Costs Overhead

£ 68 £44

19 23

£ 87 £67

Total £~54

Proposed new service interval lO minutes = 6 buses / hr.

Current service interval 15 minutes = 4 buses / hr.

Estimated cost of new offpeak service

= £154 x 6/4 = £231 per week

Cost increase £ 77 per week (50%)

Notes

I. This method works because the only costs of offpeak

service are those related to bus miles and bus hours,

both of which are approximately proportional to the bus

frequency.

2. The method will be least accurate for services where:

the journey length is long compared with the duty length.

98

Page 104: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(Table 7.7 continued)

the access time out-of-service between garage and route is significant.

service is infrequent, and the relation between journey length and service interval is awkward giving rise to disproportionate layover times either before or after the change.

99

Page 105: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

il

v

~ 0 ~

~ * o

O ~

0

~ 0

0 ~

o O ~

O ~

0

;I 0

ii

u

I i

0

v ~ o

°1 ~ o

0

~ o

J J

o o o o

~ u

3 g

~ o ~

, j J ,...:,

I I

~ o ,'-4 0

• I

I !

I !

I

,, ,-, ~. I 0

I

I I I I

• I

I , ~ ~ 1 "t" m

I I I I !

I

!

I

o o

o o

o

o

m

i

g

g

o

cd 0

ff

0

*&

I00

Page 106: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.8

I. Offpeak frequency is assumed to be 20 minutes during the

day (between morning and evening peaks) and every 30 minutes

in the evening, to be changed to every 15 minutes during the

daytime, leaving evening service unchanged.

2. From these changes, bus hours and bus miles are

recalculated for the new service, to derive the figures

shown in Column (A).

3. We assume the crew costs of off peak service to be the

same at all weekday offpeak times, as we have at present

no quantitative evidence to the contrary.

4. Overall cost increases by £183 per week, compared

with existingcosts (excluding fixed overhead) of £577 per

week for offpeak service*- a cost increase of 32% for a

service frequency increase of about 24%. The simple

method of Table 7.7 applied to the daytime frequency

increase would estimate the cost increase as only about

£137, pro-rata to the frequency increase. It ignores

the interaction between journey length, service interval,

layover time and duty length, which is an awkward one in this

particular example.

5. This example is for a different route from that of Table 7.7;

the two results should not be compared directly.

*Derived from the route detail report (not shown here).

i01

Page 107: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

ii

H u

~ )) ,,

_ Ii I I • + 0 1 ;

~ 4 . ~.

N

O

O

o

°

u

n

. . g P~l

21 u

" 21 u O

, , , 0 v v

~0 v

~ ~ o ~

v

r 4

{ x z

o o o o

u

, - I v v

. ~ ~ ~ o

i - -4 ~XZ

I

I

i , -- I I 1 "~ I I xO Ox ~--I , - I u

i [ - , , i i

m

o

I 1

o • I I

o •

• !

I I

J

I

I ! I

0, ~. ~ ~

m i

i

¢

I

~ N ~ u m w

A

cO

O

g -O

g

X

ff .r4

~o r 4

a~

*g

r ~

:102

Page 108: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.9

1. Frequency of DDOMO peak service is being reduced

from every 10 minutes to every 12 minutes (from 6 to 5

buses/hr).

2. Peak buses can be reduced from 13 to IO, because of

a better fit in the schedules allowing more than the

pr0-rata reduction (which would be 2 buses).

3. Overall saving is estimated at £267 per week, or 20%

of the existing cost of £1,360, for a frequency reduction

of 16.7%. The bulk of the saving comes from the

reduction in the number of peak buses required.

103

Page 109: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

7.6 Increasing fares during peak periods All MPTE stage carriage

services from the garage

whose operations we analysed lose money* at peak periods, except for

one service (route 88) which only uses one bus. Table 7.10 shows

revenue and contribution, by route, for the peak periods.

If peak costs, excluding fixed overheads, are to be covered,

then additional revenue of about £1,200 per week would be needed at

this garage. This is equivalent to 22% of current peak fare revenue,

or 7% of the week's total fare revenue.

Notes after the Table indicate some of the factors that

would have to be borne in mind by the bus operator if this extra

revenue were to be generated by higher fares in peak periods, rather

than by other means.

One alternative to higher fares could be a subsidy to cover

losses on peak operations. The figures given here illustrate the size

of loss being made, and could form a basis for negotiation if a

subsidy is considered.

* i.e., contribution to fixed overheads is negative; direct costs plus variable overheads exceed total peak fare revenue.

104

Page 110: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 7 .I0

PEAK PERIODS CONTRIBUTION TO FIXED OVERHEADS

BY ROUTE

(Week 48,1973)

Route

4

5

66

85

86

87

88

I00-

Fare Revenue

Contribution (loss)

E/peak bus hour £ £

601 (227) (I ,33)

759 (186) (0.93)

552 (239) (I .46)

911 (174) (0.75)

2,032 (196) (0.45)

548 (89) (0.66)

200 30 0.73

25 (137) (3.70)

5,628 (1,218) (0.85)

A high proportion of route lO0's peak operation is out of service running between garage and route service, since route lO0 is primarily a daytime only shoppers'"Cityride" offpeak service. We believe that this accounts to a large extent for the high loss per bus hour.

Source: Route detail reports.

105

Page 111: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Notes to Table 7.10

Factors to be considered in connection with means of

recovering peak losses include basic choices of where additional peak

revenue should be raised - from higher peak fares, cross-subsidization

from other time periods, government subsidy or other source. Many

important issues are involved, beyond the scope of our study, but we

can comment on some relevant points mif higher peak fares are thought

to be an appropriate way of obtaining additional revenue.

.

.

.

Loss of passengers

Research results I indicate that the percentage loss of passengers following a fare increase is less than the percentage increase in fare, so that overall, total revenue is increased by higher fares. This is particularly true for peak period travel.

Indications I are that ~ passenger loss could be (very approximately) of the order of 0.2% for each 1% increase in fare - towards the lower end of the range of demand elasticities deduced from studies of travel

behavi our.

Traffic congestion

Any significant switch from buses to cars in peak periods could increase traffic congestion. However, bus fares are not generally a very significant factor in the choice of mode for the journey to work 2 and few passengers would switch to cars as a result of higher fares. Poor service is a much more common reason given by car drivers for not choosing public transport.

Lonser-term effects

Fare increases are unpopular, and increases at peak periods affect people with little choice but to pay them (that is one reason why overall revenue increases). If fare increases are not accompanied by improvements in comfort and reliability, the public's image of the bus company may be adversely affected, possibly causing undesirable long-term effects. Local authorities may also be influenced unfavourably in their attitude towards the bus company.

106

Page 112: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

(Notes to Table 7.10, continued)

4. Method of collection

References

Effective means would need to be devised to make clear to passengers and bus crews just when the peak fare must be paid. Alternatives include charging according to: the actual time of boarding the bus; the scheduled time at which the'bus should have passed the particular stop at which the bus was boarded; • the scheduled time of arrival of the bus at major destination points (effectively peak fares on certain bus journeys); and so on.

Different fare levels between peak and off-peak have already been tried in a number of companies,3 but in some cases have been dropped because of practical difficulties.

For the reader's convenience, references are quoted from

one publication: "Proceedings of a Symposium on Public

Transport Fare Structure," held at the Transport and Road Research

Laboratory in November 1973 (Supplementary Report 37 UC). The

conclusions described are often based also on other research studies,

to which further reference is given.

I. Smith, M.G. and P.T. Mclntosh. "Fares Elasticity:

Interpretation and Estimation." See especially pp. 29,

32.

2. Kemp, M.A. "Reduced Fare and Free-fare Urban Transit

Services - Some Cases Studies." See especially pp 38, 45.

3. For example, London Country Bus services~ Alder Valley

Services, Eastern Counties Omnibus Co Ltd., Midland Red Omnibus

Co Ltd, and Western Welsh Omnibus Co Ltd.

107

Page 113: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

7.7 Providing increased service in offpeak periods Advantages from increasing

offpeak services can be

suggested, based on the route detail reports such as Tables 6.2 and

7.3. At the garage analysed in MPTE, all offpeak services (except on

Sunday) make positive contributions to fixed overheads, and in general,

higher contributions per bus hour are achieved on the more frequent

services (see Table 7.11).

The positive contribution made by offpeak services is

achieved even without making any allowance for the benefits from

services provided free to old-age pensioners, and other concessionary

travellers.

Although it is not to be expected that more offpeak bus hours

provided will continue to attract the same additional revenue per hour

as the existing average, more offpeak service may (up to a point)

obtain more contribution in total, and in any event provides improved

levels of service to many people with limited alternative modes of

travel, at relatively low additional cost to the bus operator.

108

Page 114: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

TABLE 7.11

0FFPEAK (WEEKDAY) CONTRIBUTION TO FIXED OVERHEADS

BY ROUTE

(Week 48, 1973)

Route

4

5

66

85

86

87

88

I00

Fare Revenue*

£

Contribution*

£/offpeak bus hr.

Basic service** interval (minutes)

558 134 0.57 24

626 159 0.61 24

580 136 0.57 30

834 262 0.88 20

3,334 1,951 2.73 ~ 8

572 126 0.54 20"

316 172 2 .07 60

282 128 I .29 15

7,102 3,068

Notes

Excludes any allowance for carrying concessionary travellers, who travel free of f peak.

Daytime, between the peaks. Early morning and evening service is sometimes less frequent.

Sources: Route detail reports and published timetable.

109

Page 115: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

CHAPTER 8

SOME FURTHER DEVELOPMENTS OF BUS ROUTE

COST INFORMATION

8.1 Introduction There are some bus route planning and control

decisions which require cost and revenue inform-

ation with a type of detail which is different from that which has

been the subject of this report. Three such decision problems and

their implications for information needs are discussed in this

Chapter.

8.2 Changes to evening service The methods we have applied in

MPTE do not give sufficient

information to enable either the revenue or the cost consequences of

changes to evening service to be estimated with precision.

Revenue To obtain an estimate of evening revenue by route, more

detailed analyses of waybills could be made for cash revenue,

and surveys of other sorts of passengers (especially of 0AP's) could

distinguish "evening" as a time period for analysis.

Cost Our methods will give an approximate cost for evening service,

subject to an important qualification described below. By

calculating bus hours and bus miles involved in evening service, in

the usual way, and applying direct and variable overhead unit costs,

these costs can be estimated for either an existing evening service or

Ii0

Page 116: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

a proposed change. The "offpeak" crew cost should be used.

Caution The important qualification is that we do not know at this

stage whether evening work can be regarded as having the

same effective crew cost as other offpeak work. It is true that no

special payments are made for evening work, but we are told that (a)

some must be included in the mix of work and (b) it is Unpopular.

This means that significant changes to evening work may not be possible

without renegotiation and possibly the introduction of additional

penalty payments of some sort. Under these circumstances, no confident

estimate can now be made of the new crew costs.

8.3 Stopping services short of the terminus (revenue effects) The smallest unit of service

for which we obtained revenue

figures was a single journey of one bus travelling one way along its

route.

No analysis is therefore possible on this basis of the

revenue effect of stopping the ServiCe short of its present destination,

because we have no data on the numbers of passengers carried at

different stops along the route.

Much more detailed record keeping on board the bus, or

special bus loading surveys, would be needed to provide firm data for

estimating revenue loss from stopping a service short.

lll

Page 117: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

8.4 Taking action in response to short-term trends The cost and revenue reports which

were shown in Tables 6.1 and 6.2

are not intended to be used for monitoring short-term trends in either

revenue or cost and relating them to routes. The effort required iu

the reports' preparation, involving as it does detailed analysis in

accordance with the often complex interrelationships between duties

and routes, is significant.

To the extent that more frequent information would be of

value for management, more economical, but perhaps less route-specific,

methods of analysis should be sought.

For example, revenue could be simply monitored in MPTE by

totalling the cash revenue takings of crews who have worked during the

day on one set of duties. These correspond approximately to routes in

most instances so that significant changes in takings by duty sheet

would quickly direct attention to the need for further investigation,

and limit it to one or a few routes.

The monitoring of short-term changes in costs could serv e

two purposes related to route costing:

a)

b)

to make it possible for management to ensure that variable overheads are changed appropriatelY in response to service changes, and

to provide revised estimates of the unit costs required for planning purposes.

Additionally, the figures could beused to direct attention to

significant changes requiring management action.

112

Page 118: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

APPENDIX 1

PARTICIPANTS IN THE STUDY

STEERING COMMITTEE

Department of the Environment

Dr. F.V. Webster

Mr. J.K. Welsby

Mr. T.M. Coburn

Dr. P.H. Bly

Mr. D.R.C. Hepburn

Transport and Road Research Laboratory

Headquarters

Transport and Road Research Laboratory

Transport and Road Research Laboratory

Transport and Road Research Laboratory

Merseyside Passenger Transport Executive

Mr. B.B.P. Kinsman Financial Manager

National Bus Company

Mr. A. Beetham Group Executive, Planning

PROJECT TEAM

Arthur Andersen & Co.

Mr. D.R. Kaye

Dr. J.W. McClenahan

Mr. D.R. Holman

Mr. R. Sturman

Partner

Project Manager

Consultant

Consultant

Merseyside Passenger Transport Executive

Mr. J. Bidewell Management Accountant (Liaison Officer)

Miss M. Ewing

M i s s M. M c N a l l y

113

Page 119: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

APPENDIX 2

CREW COSTS: MODELS AND REGRESSION ANALYSES

I Aims of the analyses As described in Chapter 4, we were aiming

to establish coefficients A and B for

weekdays, such that we could describe the number of crew hours needed

to pay for any given duty sheet's mix of peak and offpeak bus hours

as:

Crew hours paid

= A x peak bus hours

+ B x offpeak bus hours

withacceptably small discrepancies between the crew hours paid as

calculated from this equation on the one hand, and as derived from the

scheduled payments made for the duties on the duty sheet, on the

other hand.

A similar relationship was sought for weekend work (extra

is paid for Saturday afternoon and Sunday work) of the form:

Crew hours paid (weekend)

= C x Saturday morning bus hours

+ D x other weekend bus hours.

2. Models With this aim in mind, we could choose between several

different regression models in our attempts to fit the

observed data.

1!4

Page 120: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

For economy of notation in describing the models, we write:

PAIDHOURS

PEAK

0FFPEAK

TOTAL

= Drew hours paid

= Peak bus hours; i.e. bus hours • operated in weekday peak periods

= Offpeak bus hours; i.e. bus hours operated on weekdays, outside peak periods.

= Total weekday bus hours; i.e. peak plus offpeak bus hours.

Straightforward estimation by a regression model which uses

directly the hours paid and bus hours operated would use the model:

PAIDHOURS = AlxPEAK + Blx0FFPEAK + C1 + E1 (1)

Transformations of this model can be made, to improve the

statistical properties of the error terms, and to minimise the effects

of correlation between the PEAK and 0FFPEAK variables. These

transformations include : •

PAIDHOURS 0FFPEAK

PAiDHOURS PEAK

PAIDHOURS TOTAL

PEAK = A2x----- + B2 + E2

OFFPEAK

A3 + B ̂ OFFPEAK = 3 x P-E~--K + E 3

• PEAK + 0FFPEAK = A4XTOTA L B4x •TOTAL * E4

( 2 )

( 3 )

(4)

In addition, non-linear terms in any of the three bus hour variables

could be added.

In these equations, the A and B coefficients of each under-

lying model are distinguished by s suffix (A1, A2,..., etc.). The "E"

terms (El, E2,..., etc.) denote the residual differences between the

model assumed, and actual observations: the distribution of error

terms and errors in the coefficients will be different for each model.

1i5

Page 121: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

For weekend work, the following model was used:

PAID HOURS = C + DxOTHER WEEKEND + E5 (5) SATURDAY A.M. SATURDAY A.M.

3. Results obtained The costs and coefficients of Tables 4.1 to 4.3

were based on results from models (2) and (5).

Separate regressions were performed for duty sheets representing

"block timetables" and those representing "extra duties". The former

consist predominantly of work on one or a few routes, each duty

msually working on only one route. The latter contain duties working

on several routes , mostly during peak periods.

The results from the two sets of duty sheets were not very

different (see Table A1), but we noted that the extra-duty sheet

coefficients wer~ somewhat higher both for peak and for offpeak work:

this distinction seemed worth preserving in the costing. We have

done this in all calculations of route cost and for Table 4.1, but

Table 4.2 showed only a weighted average approximation, for simplicity

of exposition.

Figures A1 and A2 show graphs of the fit of model (2) to the

two sets of data. When plotted, some points overlapped, so the number

of points appearing on the graphs is slightly smaller than the number

of observations.

i16

Page 122: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Separate analyses of each of MPTE's three operating

divisions showed no significant differences between divisions.

L

Trials of model (I) showed that the constant term ci was

not significant, and since its presence would have complicated the

c o s t i n g p r o c e d u r e s , model (1) was n o t a d o p t e d .

Model (3) was not pursued. Our understanding of the way

in which a higher proportion of peak working leads to more spreadover

duties, and hence higher payments, indicated that it was less suitable

as a model of the underlying process.

Model (4) has the drawback that the estimation of the error

of A4 is more difficult It was not used in this exercise, although

we are considering itJin connection with a simpler method of analysis

based on individual duties.

Residual analyses The distribution of residuals from model (2)

showed no marked deviation from normality,

and was uniform Over the range of variation of peak/offpeak rstlos.

There was no evidence of non-linearity in the relationship, over a

rang e of ratios of peak to offpeak bus hours from 0.4~I to over 4:I.

Residuals were mostly less than 5% of the value of crew

hours paid.

lit

Page 123: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

~ TABLE. AI

COEFFICIENTS OF CREW HOURS PAID PER BUS HOUR

(Figures in parentheses show the standard errors of the coefficients)

Weekday Block Timetables Extra Duty Sheets

.96 2.12 A. Peak (~.ll)_ (0.09)

B. Offpeak 1.03 (0.07)

1.15 (o. 34)

Weekend All Duty Sheets

C. Saturday before 1300 I .34 (o.i~)

D. Remainder of weekend 1.96 (0.09)

118

Page 124: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

0 .(Z

o

2 0 ¢-

3"50

3.25

3-00

2"75

2"50

2"25

2"00

1"75

1"50

1"25

0 I

0

/

y=-.

/7" 0.2 0"4 0.6 0"8

Peak bus hours /Of fpeak bus hours

P

! ' 0 1"2

Fig. A1 BLOCK TIMETABLES, CREW HOURSPAID/OFFPEAK BUS HOURS V.S. PEAK/OFFPEAK RATIO

119

Page 125: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

co

O t -

co r~

¢0

CZ

o

¢o Q.

O ¢-

C)

20

18

16

14

12

10

8

/. 4

2

~ O N

/- y w

qP A J

0 2 4 6 8 10

Peak bus hours / Offpeak bus hours

12

Fig. A2 E X T R A D U T Y SHEETS: CREW HOURS PAID/OFFPEAK BUS HOURS V.S. P E A K / O F F P E A K RATIO

! 2 0

Page 126: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

APPENDIX 3

DEFINITIONS OF TERMS

i. Bus hours, bus miles and peak buses "Bus hours" are those hours during

which a bus is crewed and out of the

garage. "Bus hours" include time spent driving between the garage

and the starting point of route service, and layover time.

"Bus miles" are the miles covered by the bus during its

bus hours of operation, as defined above.

Bus hours and bus miles can both be subdivided by the

time period during which they are operated.

"Peak buses" are the number of buses required for service

during the period for which the bus company's requirement for buses is

at its height. For MPTE, there is an hour in the morning peak (0745

to 0845) and an hour in the evening peak (1645 to 1745) for which this

requirement is within 1% if its absolute maximum. We define the average

peak bus requirement as the number of bus hours operated during this

period, divided by the length of the period. In this way, services

3 which require a bus for only (say) ~ hour of the 2 hour period are

charged only with 3/8 of a "peak bus": the remaining 5/8 of a "peak

bus" will be charged to some other service, which uses the bus during

the remainder of the 2 hour period.

121

Page 127: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The usage of bus hours, bus miles and peak buses can be

calculated for a route, duty sheet, garage, or any other subdivision

of the bus company's operation, or for its operations in total, as

is appropriate.

2. Paid hours Scheduled paid hours are the hours for which a bus

company schedules to pay its crews, assuming no

rest day working and no service cuts. The paid hours are a function

of the union agreement. In the case of a company with an unconsolidated

union agreement, the scheduled paid hours may be calculated for each

duty from the agreement and the duty sheets. Actual paid hours take

account of understaffing and service cuts, to reach the actual number

of hours paid for each category of staff.

3. Summary of MPTE Operating Agreement (as effective at ist December 1973)

Basic Rates

Crew Driver Crew Conductor SDOMO Driver/Operator DDOMO Driver/Operator

Hourly Rate (units)

1.00 0.98 approx. 1.20 1.25

Notes:

1.

2.

3.

Rates vary by approx. 1% dependent on length of service.

Basic PAYMENT is for 8 hr. day regardless of hours worked.

Basic WORK may be any period up to 8 hours 24 mins. but must average no more than 40 hours over 5 day week - any duty shorter than 7 hours 45 mins. counts as 7 hours 45 mins. for averaging.

122

Page 128: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Penalty Rates (as a fraction of basic rate)

Saturday Working after 1300 Sunday Working Public Hols. (excl. Good Friday

and Christmas Day) Good Friday and Christmas Day Night Duty (Cbmmence post 2200;

Finish pre 0800) (Not cumulative for O/T etc.)

Early Morning Duty (pre 0530) Delay Time (Breakdown, fog etc.) Spreadover Duties (i.e. duties

exceeding 8 hours 24 mins. in overall length):

First ½ hr. or part thereof of the excess

Each further ½ hr. or part thereof

Note - 0nly the highest penalty rate applies: are not compounded.

Overtime

All overtime worked (rounded to ½ hr. above)

Minimum Payments (Gross)

No break between duty & overtime As above but if finish time later

than 2400 Call out - pre 1159 Call out - post 1200 Rest Day - no work performed Rest Day work performed

Attendance Bonus

Paid unless late, on vacation, sick etc. (paid weekly)

Service Payment

Payment depends on length of service Minimum (over 6 months) Maximum (over 20 years) (paid half-

yearly)

they

Hourly Rate (units)

1.50 1.50

1.50 2.00

1.25

1.00

1.50

Fixed Payment

0.25 hr.

0.50 hr. 0.25 hr.

1 00 hr.

2. O0 hr s. 4.00 hrs. 3.00 hrs. 4 • O0 hr s. 8.00 hrs.

55p/week

50p/week

150p/week

123

Page 129: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

4. Duties, duty sheets and duty rosters in MPTE A "duty" is a day's work for a bus

crew. Scheduled overtime of less

than a full day's work is a "duty piece" and may be usually attached

to a full duty to be worked with it. Any part of a duty (e.g., half

of a spreadover duty) may also be called a "duty piece".

Duties are collected together into "duty sheets". Separate

duty sheets are prepared for weekdays, for Saturdays, and for Sundays.

Duties on a "block timetable" duty sheet work generally on one route,

or a few routes. Duties on "extra" duty sheets provide additional

service to a variety of routes, mainly to cover peak work requirements.

Duty sheets for weekday, Saturday and Sunday for each route

group are linked together to form directly the "duty roster". Each

crew works on successive days a duty with a number one higher on the

duty sheet, taking the weekday, Saturday, or Sunday sheet as appropriate.

Days off are allocated so as to provide fewer crews on Saturday and

Sunday, since these duty sheets require fewer men thsn the weekday

sheets to which they are linked.

5. Bus running boards A bus running board is one day's work for

a bus. It links together journeys on routes:

some running boards provide for operation on only one route, others may

cover several routes. Running boards may be classified into one of

four types (on weekdays) :

m all day, from early morning to late evening

124

Page 130: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

daytime only, from just before the start of the morning peak, to just after the evening peak

peak only, providing work mainly in peak periods

miscellaneous.

The last category includes a few special types of board,

such as (to give one example) those on a route where service is not

provided in the early morning or in the evening, and where each board

corresponds to one duty only.

. Apportionment of layover and dead time ("out of service working")

I. 0nly true out of service working is counted in "bus hours"

i.e. standby duties and off-duty pieces of split shifts are

omitted from bus hours (but not from "hours paid").

2. Where only one route has been worked in a duty piece, all

out of service working is allocated to that route.

3. Where out of service working is at an end of a duty piece,

that out of service working is allocated to the route worked

adjacent to the end of the duty.

4. Where out of service working occurs between two segments of

work on the same route, the out of service work is allocated to

tha~t route.

5. Where out of service working occurs between two segments of

work on different routes any apportionment is by nature arbitrary.

].25

Page 131: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

The following rules were used in MPTE.

a) If the period of out of service working is an even number of busquarter-hours,* the period was divided by 2 and apportioned equally to the two routes.

b) If the period of out of service working is an odd number of bus quarter-hours, the period has been split so that the route where the segment of working contains the larger proportion of peak working (or if neither contains any peak working the segment which begins or ends closest to the peak periods) was charged with the odd quarter hour, and the remainder was allocated equally between the routes.

In a system which calculates to the nearest minute, the out

of service bus hours can be allocated between routes in proportion to

the bus hours worked on each route during the duty.

7. Types of fare collected

I. Cash Money collected by the conductor or driver/operator

at the time of travel.

2. B.E.T. (Bus Economy Ticket) Purchased from an agency before

travel and valid for l0 journeys although costing

the equivalent of 8 times the single fare. Cancelled by machine

on the bus.

3. Scholar's Pass Fixed sum collected from Local Education

Authority. Valid for schooldays only,

and only at specified times.

All our bus hour calculations were rounded to the nearest quarter hour.

126

Page 132: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

4. Scholar's Permit Fixed sum collected from Local Education

Authority. Validity as for Scholar's

Pass. Allows scholars over fifteen living within three miles

of their place of study to travel at half fare.

5. OAP Passes Issued free to OAP's for unlimited travel

offpeak.

6. TraVellers' Tickets Issued by MPTE offices for fixed sums

dependent on duration of validity (one

week or one month). Valid at all times on all bus, train and

ferry services within the MPTE boundaries.

127

Page 133: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

ADDENDUM

FURTHER ANALYSIS AND APPLICATION OF THE METHOD

i. INTRODUCTION

1.1 Purposes of this additional work The work reported in this

addendum had four

purposes:

a)

b)

c)

d)

to give increased confidence that the structure of the costing system developed for MPTE could be applied in other companies;

to attempt to replicate our findings on crew costs in two other PTEs;

to attempt to identify differences in weekday offpeak crew costs at different offpeak times of day, in MPTE;

to develop methods of analysing weekday peak and offpeak crew costs which will be simpler to apply than the method described in the main report.

1.2 Reasons for addendum format All of these purposes except

the first were identified by

the Steering Committee at a late stage in the study, when the main

report structure was basically complete. The central theme of the

main report - development of an overall cost structure and the

identification of major differences between peak and offpeak crew

costs - is not affected by the results of these further

investigations, and it therefore seemed more appropriate to report

them in the form of an addendum.

Because fulfilment of the second purpose b) required

analysis of data from the two PTEs visited, it was felt appropriate

by the Steering Committee to include also our other findings from

our visits to these PTEs in the addendum, responding to purpose a).

128

Page 134: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

r

1.3 Structure of the addendum Section 2 of the addendum

summarises the extent to which

the purposes of the additional work were fulfilled.

The achievement of the first purpose is covered in the

summary. Sections 3 and 4 expand on the Summary for the purposes b)

and c) respectively, and Appendix 2 describes the simpler method of

analysis which we have developed in response to purpose d).

r

129

Page 135: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

2. ADDENDUM SUMMARY

2.1 Applicability of cost structure to other PTEs Based on our analysis of

schedules data provided by

Greater Glasgow and Selnec* PTEs we were able to confirm our

Merseyside finding of consistently higher crew costs in weekday

peak periods, and hence the need for the cost structure to

recognise different effective crew costs in peak and offpeak periods.

Our discussions with officers in these PTEs indicated

no reason to expect that other aspects of our cost structure

would be difficult in principle to apply to their operations.

On two specific issues which had given us concern in

Steering Committee discussions, the treatment of some engineering

costs, and the problems of allocating the costs of duties worked

on several routes to the routes concerned, the two PTEs had similar

practices to those in use in MPTE:

a)

b)

Cleaning, servicing and routine maintenance are performed on an elapsed time basis in all three PTEs.

Both Glasgow and Selnec have route structures which also exhibit the pattern of one duty working on several routes which we found in MPTE, and which led us to our method of finding standard unit costs per bus hour of different types in order to apportion the costs of dutyrosters to routes.

Fewer duty sheets/rosters are operated in the other PTE's

than in Merseyside. The crew cost analysis method we used in MPTE

which depended on the availability of data from a large number (63)

Now Greater Manchester Transport

130

Page 136: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

of rosters would therefore be more difficult (or impossible) to

apply and interpret in these other PTEs.

We have taken account of this observation in the

development of the simpler method of crew cost analysis reported

in this addendum.

2.2 Peak and offpeak crew costs: Selnec and Greater Glasgow PTE Analysis of existing weekday

duty sheets in Selnec and

Greater Glasgow indicates an effective rate of about two crew hours

paid per bus hour in peak periods, versus about one crew hour paid per

bus hour offpeak. This result is similar to what we obtained in

MPTE.

2.3 Weekday offpeak costs: MPTE We found indications in MPTE

that evening work may incur

somewhat higher costs than other weekday offpeak work (about

10-20%), mainly because fewer bus hours seem to be scheduled in

evening duties than in other non-spreadover duties. However,

this finding cannot necessarily be taken at face value. There

may be some(possibly informal)interaction between the lengths

of day and evening duties which would be upset if evening duties

were changed, so that the present (apparently different) costs

of evening duties are not necessarily attributable solely to

evening work.

131

Page 137: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

We did not find any evidence in existing duty schedules

that particularly high utilization of 'hours paid for' is actually

being achieved for the operation of buses during daytime hours

only, as the Steering Committee had suggested might be the case.

We cannot, however, entirely rule out the possibility that

particularly effective use of crew time might be possible for daytime-

only buses. If it occurred, this would allow the addition of offpeak

bus hours between the peaks at very low extra cost over and above

the existing payment for the same bus, operated only during the

peaks.

2.4 Simplified method of analysis Our analysis of crew costs

for Selnec and Glasgow PTEs

was successfully performed on individual duties, not (as in our

original MPTE analyses) on whole duty sheets. This opens the

possibility of extending the crew cost analysis method for

differentiating peak and offpeak crew costs to the operations of

small as well as large companies, or to companies like Selnec and

Greater Glasgow PTEs which operate larger rosters, and hence have

fewer of them on which to base analysis.

We believe that the simple method can be applied with

a degree of confidence which is considerably enhanced by our earlier

method's success, and vice-versa.

132

Page 138: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

We envisage that it would be applied to as much of the

company's operations as it is desired to cost. Before using the

results of the simpler method to calculate the different crew costs of

peak and offpeak work, it is important to check that the conditions

of Chapter 4 for validity of the results are fulfilled. In particular,

it would be dangerous to base results on the study of individual

duties without checking-

a)

b)

c)

that the results are compiled for sets of duties worked by a group of men who usually work those duties between them;

that analysis of different groups shows reasonable consistency in the peak and offpeak coefficients between groups,• and that the average mixture of peak and offpeak work is sufficiently different between groups to give confidence that the coefficients deduced from the analysis would be valid for significant changes to the mix in any one group;

that the system of penalty payments for spreadover working has not been consolidated or partially consolidated to the extent that peak/offpeak mix changes could not be implemented without changes to the form of payment and/or the union agreement. This will be particularly important to check if the system of spreadover payment is very different from that which was found in the three PTEs studied.

133

Page 139: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

3. PEAK AND OFFPEAK CREW COSTS

3.1 Comparison between the three PTEs Table I shows the coefficients we estimate

for the hours paid per bus hour in each of

the three PTEs. The results indicate a perhaps surprisingly close

correspondence, with the peak coefficient roughly twice the offpeak

in all cases, except for Glasgow's Partick garage for which the

number of duties, and the range in the proportion of peak working,

are too limited to allow satisfactory estimation of a peak

coefficient.

The results are obviously dependent in each company on

both the nature of the union operating agreements, which determin~

the amount paid for duties worked, and on the amount and timing of

peak working, which in conjunction with scheduling practice gives

rise to the duties themselves. Some relevant features of the

union agreements in Selnec and Greater Glasgow are summarised in

Appendix 1.

We have not attempted to relate differences in

coefficients to characteristics of the peaking pattern and the

union agreements, on the basis of such a small sample, but this

might be a suitable subject for further research based on a

wider range of observations.

134

Page 140: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

o2 +~

0 ~o

0

,%

2 m

m

g m

~ . ~

%

g .,-i

÷~

E3

O3

O3

03

0

g~

0~

w~ oo

o

~v

:: -,-4 0

"~=o ~ v

o ~

r~ ~-~0

0 0" , ' 4

0 0

~; o

A

o g ~ ~. % ~ ~; ~ ~ .2 o o

. g o g ~ ~ ~ ~ o 0 =-¢

,-.4 0 0 0 ,..4

o ~ ~ ~

d d d

¢q

,.¢:;

0 ~ !

=o

0

"g "2 0

E E

.,.4

°,-4

o *~

¢0

• . 0 4-~

o • r,O

. , q +~

,%

.,.-I

q) °,.-i o3 ~ ~

~ v . ' 4 ~

o l

~ 2 • ,4 ~'1

,...1

m ~

~ g 0 ,% = ,%

. + *

135

Page 141: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

3.2 Method of analysis Figures 1 to 4 show graphically the

observations from which the coefficients

for Selnec and Greater Glasgow were deduced. The underlying model

assumed is:

crew hours paid

total bus hours operated = (A - B)xpeak bus hours

total bus hours + B + residual

This model was applied to the observations to estimate (A - B) and B.

The coefficients A and B have the same meaning as those described in

Chapter 4 of the main report: they are respectively the crew hours

paid per peak bus hour and per offpeak bus hour: i.e.,

crew hours paid = A x peak bus hours + B x offpeak bus hours

The graphs for Selnec and Greater Glasgow PTEs show the way in which

the amount paid per bus hour for a duty increases with the

proportion of peak working, and the tendency for high proportions

of peak work to be associated with more spreadover working.

3.3 Conclusion The similarity of results between PTEs and their

similarity also to LTEs and MoT results* give

increased confidence in the validity of our MPTE findings. However,

the three companies in which the methods of analysis have been

applied are somewhat similar: all are PTEs, all operate mainly stage

carriage services in urban areas, and all have union agreements

permitting spreadover working subject to penalty payment.

* referenced in the main report at the end of Chapter 4.

136

Page 142: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

We expect that the simple method of analysing peak and

offpeak crew costs, based on analysis of individual duties, can be

applied in most companies with unconsolidated union agreements.

However, only further application in a wider variety of companies can

establish the wider generality of the results.

137

Page 143: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

4. WEEKDAY OFFPEAK COSTS IN MERSEYSIDE PTE

4.1 Analysis of buses' operation It was suggested by members

of the Steering Committee that

the effective crew cost per bus hour might differ not only between

peak, offpeak and weekend work, but also at different weekday offpeak

periods of the day. In particular it was suggested that a bus

operated "daytime-only" from before the morning peak to just after

the evening peak (but not throughout the evening) might make

particularly economical use of the time available from two full

crew duties. If this were the case, then additional offpeak work

between the peaks could be obtained very cheaply by converting

the operation of a bus working at present only in the peaks, into

a full daytime-only bus operating as just described. Substantial

additional bus hours would be obtained at relatively low cost, by

replacing payment for one (expensive) spreadover duty by payment for

two (relatively cheap) ordinary duties.

In order to examine this question, we analysed the staffing

of bus running boards at the pilot garage. That is to say, we drew

time diagrams (see Figure 5 as an example) showing the operation of

each bus, the duties which covered that bus's operation, and the

"excess" amount paid for its operation.

The "excess" amount paid is the difference 0etween crew

hours paid and bus hours operated, for the operation of eac~ bus

running board.

138

Page 144: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

If the hypothesis were correct then the "excess" amounts

of payment per bus should be lower for daMtime-onlY buses than for

peak-only buses.

4.2 Results of this analysis We found no evidence at the pilot

garage that the suggested economies

are being achieved in practice in existing MPTE schedules.

The average peak-only bus provides 5.5 bus hours* at •an

average excess of 3.0 hours paid per bus.

The four existing daytime-only buses, staffed by two full

duties, provide i 13~ bus hours each, for an average excess of 2.9

hours per bus. Five other daytime-only buses are run, staffed by

a mixture of ordinary and spreadover duties,• which incur a slightly

higher average excess of 3.1 hoUrs. ....

Conversion from peak-only to daytime-only would therefore

provide an extra 7¼ bus hours, but at an additional cost of 7.9 [

hours paid (payment for one whole additional duty, less the saving

in excess hours of O.1 hour). This is not significantly different

from the offpeak cost previously derived.

4.3 Higher costs of evening duties We have analysed two of MPTE's

duty sheets in the same way

as was done for Selnec and Greater Glasgow PTEs - i.e.,by plotting

"crew hours paid per bus hour" versus the "ratio of peak to total bus

hours" .

* For operations in both peaks. Several boards only run in one peak, and have been excluded from these calculations.

139

Page 145: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

These analyses (see Figures 6 and 7) show an apparently

higher cost per crew hour £or evening duties; about 10-20% higher

than that for offpeak work as a whole deduced from our former

method of analysis. However, as described in the Summar~ this

result cannot necessarily be taken at face value.

Page 146: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

0

.D

0 ).,-

" 0

Q..

0 t -

O

(/)

3 0 ¢.-

(/)

" 0

O.

0 t -

O

2-0

1"8

1-6

1"4

1"2

1.0

0 0

2"0

1"8

1-6

1"4

1"2

1"0

0 0

SELNEC "C" ROTA (2- MAN)

I

DUTY TYPE !

• Ordinary

O Spreadover

• C

• og • " j Y I

0

0 0 0

O

0

Io

0.1 0"2 0"3 0"4 0"5

Peak bus hours /Total bus hours

0"6

ADDENDUM Fig.1

SELNEC

" O " ROTA (O.M.O.) I

DUTY TYPE

• Ordinary

0 Spreadover

• OoC~ ~

0"7

0-1 0"2 0"3 0"4 0"5

Peak bus hours / Total bus hours

0.6 0 .7

A D D E N D U M F ig .2

141

Page 147: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

0 e -

(13

0 r "

r . . )

P 0 e -

e-J

~o

0 .

.-s 0 e -

P ¢.)

2"0

1-8

1"6

1"4

1-2

1-0 I I I I I I

0 o

2-0

1.8

1.6

1-4

1"2

GR~T~R ~'~SGOW PAI~TICK (O.1~.O.)

I I

I DUTY TYPE

• Ordinary

O Spread over

O •

• e . o 9 • . - - - , • v U

0"1

a O

0"2 0"3 0'4 0-5

Peak bus hours / Total bus hours

0-6 0-7

A D D E N D U M F i g . 3

GRE~TER G'A~GOW GARTCRAIG (2 ' MAN)

I I

1.0 !

I I I I I

0 ' 0 0"1

• DUTY T Y P E

• Ordinary

O Spread over |

)

0 ~ • •

CI 0 _.,

J

I •

O J

0"2 0"3 0"4 0"5

Peak bus hours /Total bus hours

0-6 0-7

A D D E N D U M F i g . 4

1 4 2

Page 148: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

0

X W 0 . . ~

0

0

0

X

0

_.1

Z 0 V

LU

i:~ ,o

E

~_ 1"- 0') ~ 0

UJ

i - " C~ - J ..J

I I I ill " I. ' I ° I ' II II ii~irJli~Jiiiiii • , . 0 ° • .

• ~ i i i . . ~ . : ! . ! i I i i l e . ,

I i ' " " i;I i.i Jii I II, I! I! ~ , ~ J . . . . !"! .!i! "~ g . ~ ,o .o ~ ~ ~ ~ ® ~ ® ~ , o o ,.. - ~ ~ ~ ~ . , - , ~ ,,-; .o o ,,. o. , - . . o ® ~ ,,-, ,-, - . .

' . . ,

g

O"

0

- ~1~ ....... ~I ~L~ ',,0

I i

n~

m

o - -

c,,,~ o).

,o .o

,o

.o .o

m

"6

I : : .

Z

1 4 3

Page 149: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

0 ¢-

. 0

Q .

0 t -

c)

0

. 0

"10

C). (/)

. 0 t -

O

2-0

1 - 8

1-6

1.4

1"2

1-0

M'ERSEYSI I~E 85 DUTY SHEET

f I Least squares regression line

.°S excluding evening duties

D

DUTY TYPE

A

- - A J l 0

0

n

z~'

Through (daytime) •

Evening

Spreadover

Extra Duty

Overtime

• I : -I

0 0"2 0"4 0"6 0-8 1"0

Peak bus hours/Total bus hours

1-2

A D D E N D U M F i g . 6

2-0

1"8

I-6

| i

MERSEY, SI DE

86/87 DUTY SHEET

"Least squares re clression line - excluding evening duties

1-4 . J , '

~ e , A • • A • • A 9 _

1-2

A

D U T Y T Y P E

• Through (daytime)

1:0 i i i i i i

0 0

f 0 • Evening

0 Spreadover

n Extra Duty

z~ Overtime

I I

0 2 0 4 0 6 0-8 1-0 1"2

Peak bus hours/Total bus hours

A D D E N D U M F ig .7

144

Page 150: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

ADDENDUM APPENDIX I

SOME RELEVANT FEATURES OF THE UNION AGREEMENTS

IN SELNEC AND GREATER GLASGOW PTEs

SELNEC

Basic payment 8 hours per duty worked; 40-hour week.

Maximum hours worked in a duty: 8¼ hours.

Spreadover duties For duties with spreadover in excess of

9h 06m, 0.2 hours is paid at basic rate for

every 12 minutes or part of 12 minutes in excess of 9h 06m;

maximum 13h.

To start and finish between 0600 and 2000.

Travelling time: now consolidated into the basic rate.

Sign on/sign off allowance: varies according to location

and type of relief. Could range

in theory from a minimum of 15 minutes for an ordinary duty

relieving on the road at both ends of the duty, using a farebox,

to a maximum of 69 minutes for a spreadover duty relieving

entirely at the depot, for an OMO driver using a ticket machine.

* Based on our interpretation of the operating agreement in force from October 1973, with later amendments as described to us on our visit.

145

Page 151: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

GREATER GLASGOW

Types of duty All duties worked in Greater Glasgow PTE are called

"split" duties - that is, there is an (unpaid) meal

break in the middle of every duty.

Spreadover duties are those for which the time between

first starting and finally finishing work during the day exceeds

nine hours and six minutes.

Normal duties The standard work week is five days of eight hours

each. These are paid regardless of the actual hours

worked. Duties must average eight hours or less, and cannot exceed

eight hours fifteen minutes in "weight". The weight of the duty

corresponds to MPTE's definition of "hours worked" - i.e. the time

between sign on and sign off, less lhe unpaid meal b~eak, less any

interval between pieces of duty.

Premium rates Extra is paid for overtime, spreadover working,

Saturday afternoon after 1.O0 p.m., and all day

on Sunday. Former payments for early start, late finish, and

travelling time have been consolidated into the basic rate.

146

Page 152: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

S~readover payments Spreadover is paid for if it is in excess of

nine hours s~x minutes, and must not exceed

twelve hours and thirty minutes. Spreadover time in excess of nine

hours and six minutes is paid for according to the following scale:

Up to 24 minutes

Every additional 12 minutes or part of 12 minutes

0.2 hours

0.2 hours additional

Up to a maximum of 3 hours 24 minutes (12 h 30m overall spread) 3.2 hours extra

Saturday after 1300 For any duties started before 1.00 p.m.

a 50% extra for that part of the duty after

1.O0 p.m. is paid, rounded to the nearest tenth of an hour.

For duty started after 1.O0 p.m. four hours extra is paid, or

50% for a duty piece which is less than a full day's work~

Sunday A four hour allowance is paid extra for any full Sunday duty. I

Overtime: scheduled Very little scheduled overtime is workedln small•

pieces. However, "red days" are included in the

duty roster, and are worked (voluntarily) at overtime rates. They

average approximately one day in every eigh t duties. The basic

additional payment for overtime is 50%. However, the details of its

application are somewhat complicated.

Page 153: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

Overtime: unscheduled, and method of payment Unscheduled overtime can

be worked either as rest

days, or in addition to other duties. It is subject to a minimum

payment for two hours work plus 50% overtime penalty - i.e., a minimum

of three hours has to be paid for.

On weekdays any full duty worked as overtime pays twelve

hours (eight hours normal plus 50% overtime premium). Any duty

piece less than a full day's work has a 50% penalty added, rounded

to the nearest tenth of an hour, subject to the minimum payment for

two hours basic plus overtime premium.

On Saturdays, for a duty worked entirely after 1 p.m.

as overtime, a four-hour penalty is paid. For a Saturday worked

as a rest day double time applies, and is applied to the eight hours

normal duty plus four-hour premium for Saturday afternoon working

(equals 12 hours) plus 12 hour penalty for Saturday rest day working -

i.e., 24 hours is paid for a full Saturday duty worked as a rest day.

On Sundays, overtime is paid at 50% rate. A full duty pays

eight hours basic, plus four hours Sunday allowances, plus 50% of 12

hours (i.e.,six hours) as overtime penalty - i.e., 18 hours is paid

for a full Sunday duty worked as a rest day.

Page 154: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

ADDENDUM APPENDIX 2

ESTIMATING PEAK AND OFFPEAK CREW

COSTS IN OTHER COMPANIES

This appendix describes a method which can be applied in any

company which has an "unconsolidated,' union agreement -- i.e., one

in which different men are paid according to the duties they

actually work, and where there is a significant element of extra

allowance for spreadover working to cover peak periods of

operation.

First, define the "peak" period for the company as a

whole, or for smaller parts of it if these have significantly

different peak periods. A working definition of the peak period

is the period during •which the number of bhses in service exceeds

the midday number by at least half the amount by which the peak

number exceeds the midday number. (See Figure 8.)

Second, group together the scheduled duties which are

worked on weekdays by the same group of men under the same agreement.

Third, for each of these groups, calculate for each duty:

a) the number of crew hours paid (or the duty- related pay, if this is calculated directly);

b) the bus hours operated in the peak period, as previously defined;

c) the totsl bus hours operated;

d) the two quantities

C = crew hours paid (or duty-related pay) per (total) bus hour = (a) ~ (c)

P = proportion of peak bus hours to total : (b)

Fourth, draw a graph for each group of duties, plotting

vertically, and P horizontally, one point for each duty.

149

Page 155: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

G) ._o P

C: . m

::3 J ~

, D

E Z /

a.m. peak period

/ Equal

J

Time of day

p.m. peak period ,,= =,J

\

A D D E N D U M Fig .8 DEFINING THE PEAK PERIODS

150

Page 156: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

i.

Fifth, examine the resulting graph. If the points tend

t o form a s t r a i g h t l i n e , , t e n d i n g u p w a r d s t o t h e r i g h t , . t h e n t h e r e

exists a simple relationship between crew hours paid and bus hours

operated in peak and offpeak periods. The way of estimating the

r e l a t i o n s h i p i s d e s c r i b e d i n l a t e r s t e p s . I f t h e s t r a i g h t - l i n e

trend is not found, more complicated analysis will be required

than can be described here. . -

To . e s t i m a t e t h e c o e f f i c i e n t s C o r r e s p o n d i n g t o t h e p e a k

and offpeak coefficients 0f Table 4.2 (or of Table 4.1, if duty-

related pay is calculateddirectly), proceed as follows:

EITHER :

Draw a line by eye which best fits the collection of points;

OR :

Perform a simple linear regression analysis of the relation between C and ~, and plot the resulting line on the graph.

The value of C where the line crosses the vertical axis

gives the offpeak coefficient.

To find the peak coefficient , draw a vertical line at ~ = I

(i.e., where peak bus hours = 100% of total bus hours) to meet the

line through the points. The value of C where these lines cross

gives the peak coefficient.

See Figure 9 for these steps.

Before the results can be appliedwith confidence, it is

important to check that the condition s for validity described in

Chapter 4 of the main report, Vol. I, are adequately fulfilled, and

that the checks described in this addendum, (Summar~ section 2.4)

have been made.

7

Page 157: TRANSPORT AND ROAD RESEARCH LABORATORY BUS ROUTE … · lead within a few months to cost increases of the order of • £4.70 per peak bus hour added, compared with an average cash

C

¢ -

a ~

t -

Value of C • • J l . . . . • m I

= peak co e'tticient . " J ~ _ . _ Line f i t t e d ~ ~ • ~ . ' ; through points

. i • o .,,,,,, , ' ' '~ • I

• I O J o • . I I

• • l Vertical line

I

Value of C I

= offpeak coefficient I I I I

I I ~ P

0 1

Peak bus hours/Total bus hours

ADDENDUM Fig. 9 DETERMINING THE PEAK AND OFFPEAK COEFFICIENTS

Printed in England by the Transport and Road Research Laboratory

152