32
COOP 3902 Louis W. Bray Construction Ltd. Subsurface Investigation into the Richmond Forcemain Repairs and Modifications Project Travis Smith 7226904 COOP 3902 Submission Date: January 10th, 2016

Travis_Smith_Work_Term_Report_F2016

Embed Size (px)

Citation preview

Page 1: Travis_Smith_Work_Term_Report_F2016

COOP 3902

Louis W. Bray Construction Ltd.

Subsurface Investigation into the Richmond Forcemain

Repairs and Modifications Project

Travis Smith

7226904

COOP 3902

Submission Date: January 10th, 2016

Page 2: Travis_Smith_Work_Term_Report_F2016

Abstract

This report is an investigation into the subsurface conditions for the Richmond Forcemain

Repairs and Modifications project which had many challenges. The project was situated in the

town of Richmond ON and involved the placement of roughly 1200m of sanitary forcemain

along the Jock River. One of the challenges of this project was the high groundwater table which

required a large amount of dewatering for the trench which extended up to 4.5 mbgl in some

areas. In order to remedy this issue, different dewatering techniques were analyzed to determine

the most advantageous method of dewatering.

Another challenge was the supports for the soil walls in these areas, where the height of the

trench posed a design challenge. This is analyzed in the following report and the proposal is to

stack two (2) 8’ x 16’ trench boxes one on top of the other to provide the required height.

Overall this report provides recommendations into the sizing and cost of the dewatering and soil

support systems required for this project.

Keywords: Subsurface Profile, Trench Dewatering, Soil Stability, Richmond Forcemain

Page 3: Travis_Smith_Work_Term_Report_F2016

TABLE OF CONTENTS

1. Introduction ..…….…………………………………..……………………. 4

2. Subsurface Profile ………………………..……………………………… 6

3. Trench Dewatering ………..……………………………………………... 8

4. Soil Excavation Support …………………………………………………. 15

5. Discussion ……………………………………………………………….. 28

6. Conclusions and Recommendations ……………………………………….. 29

7. References ………………………………………………………………. 31

8. Appendices .……………………………………………………………... 32

List of Tables

1. Table 1: Summary of Proposed and Anticipated Subsurface Elevations ……... 6

2. Table 2: Subsurface Profile Elevations …………………………………. 8

3. Table 3: Parameters for the calculation of radial flow from a water table aquifer 9

4. Table 4: Cost Estimate for the Sump Pumping Scenario …………………….. 13

5. Table 5: Cost Estimate for the Wellpoint System Scenario …………………. 15

6. Table 6: Technical Data for the In Situ Soils at Borehole F1 ……………….. 17

List of Figures

1. Figure 1: Braced cut analysis on trench box supports …………………. 19

2. Figure 2: Analysis of Vertical soil face …………………………………. 20

3. Figure 3: Shear Force and Bending Moment Diagrams for First Cut Section … 21

4. Figure 4: Shear force and Bending Moment Diagrams for Second Cut Section.. 23

Page 4: Travis_Smith_Work_Term_Report_F2016

1.0 Introduction

The objective of this investigation is to determine the dewatering, bracing, and pumping

requirements for one of the major projects that was tendered during the work term in the Fall of

2016. During the first half of the COOP work term with Louis W. Bray Construction Ltd., a

heavy civil contracting firm, I worked in the Estimating department. During this time, I worked

on various small projects, but spent the majority of my efforts focusing on the Richmond

Forcemain Repairs and Modifications project. It was during this time that I decided to pursue this

topic of subsurface investigation in order to provide my colleagues at the time with additional

technical information in order to put together an improved estimate.

The name of the project was Richmond Forcemain Repairs and Modifications and it

involved the installation of roughly 1200 linear meters of sanitary forcemain from the pumping

station in the town of Richmond, ON to the newly developed Lagoon cell several kilometers

away. The proposed pathway for the sanitary forcemain ran along the Jock River through the

town of Richmond, ON. The cost to construct this forcemain would prove to be difficult to

estimate due to high groundwater table levels in the installation location along the Jock River.

See Appendix B – Subsurface Profile to see the height of the groundwater table relative to the

surface. This high groundwater table could pose many difficulties during construction including

but not limited to: infiltration, basal heaving, soil collapse or failure which all have the potential

to injure the workers on the project. It is for this reason that estimators must know the variables

beforehand in order to prepare for any potential obstacles. In order to safely and effectively

install the sanitary forcemain, the contractor would a) support the soil using trench boxes or

approved equivalent up to the maximum excavation depth of 4.65m below ground level and b)

Page 5: Travis_Smith_Work_Term_Report_F2016

Dewater the trench area to ensure that workers have a safe and stable surface to install the PVC

sanitary forcemain.

The first part of this report deals with the subsurface profile of the soils present in situ.

With the raw data obtained from the Geotechnical investigation provided with the project

(Subsurface Investigation, 2016), the borehole logs can be analyzed and converted into a

subsurface profile drawing. This will aid not only in the parts following, but also for visual

confirmation of the soil stratification.

The second part of the investigation is concerned with the lowering the groundwater table

to the point that work can be done safely within the trench. To perform this, there are three

typical methods used for construction purposes: Sump pumping, wellpoint systems, and deep

well systems. Deep well systems are better suited for small areas and longer term construction

and were not considered in this report. The sump pumping method involves having multiple

large hydraulic submersible pumps which are stationed within the trenches. In this method the

water infiltrates into the trench, where it gathers in the sump area and is pumped out of the trench

into a collection area. The other method is a wellpoint system in which small wells are drilled on

both sides of the trench and water is pumped continuously through a network of pipes connecting

each well point.

The third part of the investigation is the analysis of the soil failure and the required

mitigation measures to support the soils. The most common way to support soils in a trench is

through the use of a P.Eng. certified trench box, which is a pre-manufactured box which prevents

Page 6: Travis_Smith_Work_Term_Report_F2016

the soil from collapse in an excavated area. Trench boxes are normally made of either steel or

aluminum sidewalls which are supported by multiple spreaders which transfer the forces from

one end of the trench to the other without buckling. The thickness and length of the trench box

are very important to ensure that the spreaders or sidewalls do not buckle and cause harm to the

workers within the trench box area. It is for this reason that in this report, the forces, stresses, and

other parameters will be calculated.

2.0 Subsurface Profile

Prior to the tendering of the project, City of Ottawa had a third party engineering firm on

site to do a preliminary subsurface investigation. This investigation included boreholes at various

locations along the proposed pathway which gave information such as the groundwater table

level, soil stratification, and the elevation of bedrock/auger refusal. It was with this information

that the following table was calculated. Table 5.1 of the subsurface investigation was titled

β€œSummary of Anticipated Excavation Conditions” which provided the borehole ID, Approx.

proposed inverts, and bedrock surface elevation. It was with this information and from that

obtained from the borehole logs that the following values were calculated.

Table 1: Summary of Proposed and Anticipated Subsurface Elevations

Borehole Distance (m) GL GWT

Approx. Prop.

600mm Invert Elev.

Bedrock Elev.

Depth of

GWT (m)

Depth of

Bedrock (m)

Depth of

Exc. (m)

Excavation within GWT

Excavation within

bedrock

F1 70 93.15 91.80 88.5 87.5 1.35 5.65 4.65 3.30 0.00

F2 80 91.76 91.45 89.2 89.0 0.31 2.76 2.56 2.25 0.00

F3 90 92.25 91.15 89.4 88.7 1.10 3.55 2.85 1.75 0.00

Page 7: Travis_Smith_Work_Term_Report_F2016

F4 130 93.10 91.65 90.2 88.8 1.45 4.30 2.90 1.45 0.00

F5 130 92.88 92.35 90.4 88.5 0.53 4.38 2.48 1.95 0.00

F6 80 93.34 91.20 90.5 90.8 2.14 2.54 2.84 0.70 0.30

F7 280 92.67 N/A 90.2 91.0 - 1.67 2.47 - 0.80

F8 - 90.97 90.80 88.9 89.0 0.17 1.97 2.07 1.90 0.10

Sample Calculations for Table 1:

π·π‘’π‘π‘‘β„Ž π‘œπ‘“ πΊπ‘Šπ‘‡ (π‘š) = 𝐺𝐿 βˆ’ πΊπ‘Šπ‘‡ = 93.15 βˆ’ 91.80 = 1.35π‘š

π·π‘’π‘π‘‘β„Ž π‘œπ‘“ π΅π‘’π‘‘π‘Ÿπ‘œπ‘π‘˜ (π‘š) = 𝐺𝐿 βˆ’ π΅π‘’π‘‘π‘Ÿπ‘œπ‘π‘˜ 𝐸𝑙𝑒𝑣. = 93.15 βˆ’ 87.5 = 5.65π‘š

π·π‘’π‘π‘‘β„Ž π‘œπ‘“ 𝐸π‘₯𝑐. (π‘š) = 𝐺𝐿 βˆ’ π΄π‘π‘π‘Ÿπ‘œπ‘₯. π‘ƒπ‘Ÿπ‘œπ‘ 600π‘šπ‘š πΌπ‘›π‘£π‘’π‘Ÿπ‘‘ 𝐸𝑙𝑒𝑣. = 93.15 βˆ’ 88.5 = 4.65π‘š

𝐸π‘₯π‘π‘Žπ‘£π‘Žπ‘‘π‘–π‘œπ‘› π‘€π‘–π‘‘β„Žπ‘–π‘› πΊπ‘Šπ‘‡ (π‘š) = π·π‘’π‘π‘‘β„Ž π‘œπ‘“ 𝐸π‘₯𝑐. βˆ’π·π‘’π‘π‘‘β„Ž π‘œπ‘“ πΊπ‘Šπ‘‡ = 4.65 βˆ’ 1.35 = 3.30π‘š

𝐸π‘₯π‘π‘Žπ‘£π‘Žπ‘‘π‘–π‘œπ‘› π‘€π‘–π‘‘β„Žπ‘–π‘› π‘π‘’π‘‘π‘Ÿπ‘œπ‘π‘˜ (π‘š) = π·π‘’π‘π‘‘β„Ž π‘œπ‘“ 𝐸π‘₯𝑐. βˆ’π·π‘’π‘π‘‘β„Ž π‘œπ‘“ π΅π‘’π‘‘π‘Ÿπ‘œπ‘π‘˜ = 4.65 βˆ’ 5.65

= 0π‘š

With the information gathered from Table 1 above, the estimator will be able to gather an

understanding of the types of excavation required which will increase dramatically based on the

excavation type. For excavation in sandy silty soils, an excavator with the required boom length

would be able to excavate down to the depths required. With the excavation into bedrock though,

a special attachment for the excavator, called a hoe ram, will be required to break up the rock.

Depending on the contract specifications as well, unsuitable material such as limestone rock may

have to be transported off site, with all costs being covered by the contractor. So having a table

like this allows the estimator to provide a better estimate of the anticipated cost for excavating

this trench.

By compiling the data from the borehole logs, the data could be shown as a subsurface profile

drawing (Attached in Appendix B). This drawing makes it clear the required excavation depths

Page 8: Travis_Smith_Work_Term_Report_F2016

as well as the soil stratification in each area. For example, in the area of boreholes F6 through F8

the depth of excavation will sink below the bedrock. This 360m stretch of trench will require the

use of a hoe ram or approved equivalent to break around 0.5m of bedrock. The subsurface profile

drawing was made using excel graphing software along with the data shown in Table 2 below;

Table 2: Subsurface Profile Elevations

Well X-Dist Topsoil/FILL Silty Clay Silt Silty Sand Glacial Till Bedrock

(meter

s) Top Bottom Top Bottom Top Bottom Top Bottom Top

Bottom

Top

F1 0 93.15 91.02 91.02 89.64 89.64 87.81 - - 87.81 87.48 87.50

F2 70 91.76 90.54 90.54 89.93 - - 89.93 89.02 - - 89.00

F3 150 92.25 91.80 91.80 90.42 90.42 89.20 - - 89.20 88.67 88.70

F4 240 93.10 92.49 - - 92.49 89.59 - - 89.59 88.83 88.80

F5 370 92.88 92.70 - - 92.70 91.05 - - 91.05 88.49 88.50

F6 500 93.34 91.51 - - - - 91.51 90.75 - - 90.80

F7 580 92.67 91.45 - - - - - - 91.45 90.95 91.00

F8 860 90.97 89.60 - - 89.60 89.04 - - - - 89.04

With the drawing shown in Appendix B, the soil stratification can be easily seen and analyzed by

the estimators as they see fit.

3.0 Trench Dewatering

In order to prepare an estimate for trench dewatering, the inflow must be calculated to

determine the pumping rate and sizing requirements. In order to perform this, an analytical

model will be used with several assumptions being made. For the trench proposed for the

Richmond Forcemain project, the trench with the highest cost will be considered in order to

determine the worst case scenario for cost. This means that the area of study will be from

Page 9: Travis_Smith_Work_Term_Report_F2016

borehole F1 through F2, an area of 100.0m. In this section of trench, the excavation depth is

lowest and coupled with a high groundwater level will have the highest cost for dewatering. The

two cases being analyzed are the sump pumping scenario and the wellpoint system. Both of these

methods will have a different kind of pumping requirement, which will be detailed further in the

coming sections.

For the calculation of infiltration into the trench, we will focus on the groundwater

infiltration for the sump pumping scenario. This will be completed using the equation for water

table flow from a line source to a drainage trench. The line source will be assumed roughly 1.5m

away from the trench on both sides. The equation used is shown below in Equation [1]: Equation

for water table flow from a line source to a drainage trench. For the design of the wellpoint

system, the wells will be installed 1.0m below the base of the excavation to prevent basal

heaving. The required drawdown at the point with the lowest excavation of 4.65 mbgl will

require the most pumping to dewater.

𝑄

π‘₯=

𝐾(𝐻2 βˆ’ β„Žπ‘€2 )

3.34 βˆ— 10βˆ’5𝐿 πΈπ‘žπ‘› [1]

Table 3: Parameters for the calculation of radial flow from a water table aquifer

Name Variable Value

Initial water table elevation from bedrock elevation H 4.3 m

Page 10: Travis_Smith_Work_Term_Report_F2016

Final water table elevation from bedrock elevation h 0.5 m

Radius of influence Ro 11.4 m

Aquifer permeability K 0.001 m/s

Sample Calculations for Table 3:

𝑅0 = 3000(𝐻 βˆ’ β„Ž)√𝐾 = 3000(4.30π‘š βˆ’ 0.50π‘š) βˆ— √0.001 π‘š/𝑠 = 360.5 π‘š

𝑄𝑀 (

0.001π‘šπ‘  βˆ— (4.3π‘š2 βˆ’ 0.5π‘š2)

3.34 βˆ— 10βˆ’5(1.5π‘š) ) βˆ— ((4.65π‘š + 1.0π‘š) βˆ— 2 𝑠𝑖𝑑𝑒𝑠)

𝑄𝑀 = 0.06870 π‘š3

𝑠= 5,935,680 𝐿/π‘‘π‘Žπ‘¦

Therefore the infiltration through the soil will be approximately 5,935,680 liters per day,

meaning that the sump pump will have to handle flows of this magnitude or higher. In order to

ensure that the calculations can be applied to the real life scenario, a factor of safety will be

applied to incorporate the unknown variables that cannot be taken into consideration such as

fissures, fractured bedrock, and pervious soils which may increase the water table flow.

π‘„π‘–π‘›π‘“π‘™π‘œπ‘€,π‘€π‘Žπ‘‘π‘’π‘Ÿ π‘‘π‘Žπ‘π‘™π‘’ π‘“π‘™π‘œπ‘€ = 5,935,680𝐿

π‘‘π‘Žπ‘¦ π‘₯ 1.3 𝐹𝑆 = 7,716,384 𝐿/π‘‘π‘Žπ‘¦

With this value of 7,716,384 L/day we can begin to investigate the pumping requirements for the

sump pumping activities. For this type of application, the pumps will be used to draw the water

out of the sump hole and into the collection basin. The type of pump chosen for this purpose is a

submersible hydraulic electric pump. The typical diesel trash pumps were not considered due to

Page 11: Travis_Smith_Work_Term_Report_F2016

the fact that they are not as efficient at pumping vertically out of sump holes. For the submersible

electric pumps, they were also preferred because multiple pumps can be run from one generator,

leading to less maintenance in fueling. Another benefit of the hydraulic pumps is that the oil used

to lubricate the machine parts can be swapped out for vegetable oil in order to be

environmentally conscious. This vegetable oil is greatly advantageous in the case of a priming

error, if the pump is not properly primed, it can backwash hydraulic fluid into the groundwater

potentially causing contaminants to enter the nearby private wells. Since the area in

consideration is near a river and close to residential developments, the submersible pumps will

be used to lessen the environmental impact on the surrounding area.

To determine the pump sizing, we will look at the pumping scenario. With a submersible

hydraulic pump, the pumps will be placed in designated sump holes within the trench itself.

Therefore the suction head will be zero and the only consideration is the discharge head from the

sump to the collection basin. In order to be consistent, we will assume the length of discharge is

5.0m vertically, and 30.0m horizontally to the collection basin. To calculate the required pump

head, the energy equation is applied.

Assumptions:

Assume that losses to are deemed negligible.

Velocity at point 1 is zero within the sump hole.

Velocity at point 2 is also zero within the collection basin.

β€˜Head loss in the 4” discharge hose was determined by assuming that the discharge would

be roughly 900 GPM and using the pump curve relating the head loss per 100ft section of

Page 12: Travis_Smith_Work_Term_Report_F2016

discharge hose. For 900 GPM, the estimate for head loss is roughly 10.5 ft loss per 100ft

section of pipe.’ (Water Flow through Hoses – Pressure Loss, 2016)

𝑃1

πœŒπ‘”+

𝑉12

2𝑔+ 𝑧1 + β„Žπ‘ =

𝑃2

πœŒπ‘”+

𝑉22

2𝑔+ 𝑧2 + β„Žπ‘‘ + β„Žπ‘™

β„Žπ‘ = (𝑧1 βˆ’ 𝑧2) + β„Žπ‘™

β„Žπ‘ = (βˆ’5.0π‘š βˆ’ 0.0π‘š) + (10.5𝑓𝑑

100π‘“π‘‘βˆ— 100𝑓𝑑 βˆ—

0.3048π‘š

𝑓𝑑)

β„Žπ‘ = 8.2 π‘š = 26.9 𝑓𝑑

For our initial calculations, we will assume that the pump has a diameter of 4”. β€˜The pump that

will be used is a Thompson 4” Hydraulic Submersible Pump Heads (HST) pump. With this

pump and the required pump head of 26.9 feet, we can refer to the pump curve to determine the

discharge. Referring to the pump curve for the 40 HST pump, the discharge will be 1150 GPM

or 6,268,636 L/day. Assuming that the pump operates at roughly 80% efficiency, the expected

discharge for the 4” submersible pump will be 920 GPM or 5,015,909 L/day.’ (Hydraulic

Submersible Pump Heads (HST), 2016)

In order to dewater the trench, the pumps will need to not only handle the daily infiltration of

groundwater, they will need to drawdown the water table in order to allow for the construction of

the forcemain. It is for this reason that I proposed placing two (2) 4” hydraulic submersible

pumps spaced one at 1/3 and one at 2/3 of the total length of the trench.

To place an estimate on the cost of the sump pumping, we will consider the time frame of one

month. In order to simplify the estimate, some elements such as mobilization/demobilization,

security, and additional engineering costs were not included.

Page 13: Travis_Smith_Work_Term_Report_F2016

Table 4: Cost Estimate for the Sump Pumping Scenario

Item Qty Unit Unit Price Unit Cost ($/month)

4" Hydraulic Submersible Electric Pump 2 ea $2,300.00 $4,600.00

4" Discharge Hose 60 m $3.33 $200.04

600V Generator 1 ea $2,400.00 $2,400.00

Fuel for generator 3800 L/month $0.80 $3,040.00

Enviro-tank Collection Basin 1 ea $20,000.00 $20,000.00

Labour for fueling 80 hr/month $35.00 $2,800.00

Total $33,040.04

Therefore, the cost estimate for the pumping equipment alone will be approximately $33,040 per

month, not including the aforementioned items above.

In the second scenario, the inflow will be considered as radial flow from a water table aquifer.

The formula used to find the flow into the trench will be found using Eqn [2]: Equation for radial

flow from a water table aquifer.

𝑄𝑀 =πœ‹πΎ(𝐻2 βˆ’ β„Žπ‘€

2 )

ln(π‘…π‘œ

π‘Ÿπ‘€)

πΈπ‘žπ‘› [2]

Sample Calculations:

𝑅0 = 3000(𝐻 βˆ’ β„Ž)√𝐾 = 3000(5.30π‘š βˆ’ 0.50π‘š) βˆ— √0.001π‘š

𝑠= 455.4 π‘š

Page 14: Travis_Smith_Work_Term_Report_F2016

π‘Ÿπ‘€ = 4 𝑖𝑛 = 0.1016 π‘š

𝑄𝑀 =πœ‹ (

0.001π‘šπ‘  ) ((5.30π‘š)2 βˆ’ (0.50π‘š)2)

ln (455.4π‘š

0.1016π‘š)

π‘„π‘Š = 0.01040π‘š3

𝑠= 898,764.5 𝐿/π‘‘π‘Žπ‘¦

Therefore the infiltration through the soil will be approximately 898,764 liters per day, meaning

that the well point system will have to handle flows of this magnitude or higher. In order to

ensure that the calculations can be applied to the real life scenario, a factor of safety will be

applied to incorporate the unknown variables that cannot be taken into consideration such as

fissures, fractured bedrock, and pervious soils which may increase the water table flow.

π‘„π‘–π‘›π‘“π‘™π‘œπ‘€,π‘€π‘Žπ‘‘π‘’π‘Ÿ π‘‘π‘Žπ‘π‘™π‘’ π‘“π‘™π‘œπ‘€ = 898,764.5𝐿

π‘‘π‘Žπ‘¦ π‘₯ 1.3 𝐹𝑆 = 1,168,393 𝐿/π‘‘π‘Žπ‘¦

β€˜From the quote received attached as Appendix C, from one of the dewatering companies

bidding on this project, we have the following empirical information. The configuration of

wellpoints is different from that of regular pumps. Wellpoints typically have many drilled well

holes which are interconnected by tubing and eventually to pumps which are spread evenly

among the drilled well points. The wellpoints are placed 1.0m apart and are drilled 5.0m in

depth. For the proposed wellpoint system, the wellpoints will be placed along a 1000m stretch on

both sides, totaling 2000m of dewatering. Each pump will dewater roughly 250m of pipe.

Therefore the number of pumps required to dewater will be eight (8) pumps.

Page 15: Travis_Smith_Work_Term_Report_F2016

Table 5: Cost Estimate for the Wellpoint System Scenario

Item Qty Unit Unit Price Unit Cost ($/month)

Wellpoint pump (Fuel included) 8 ea 4400 35200

Envirotank 1 ea 2200 2200

Total 37400

Therefore comparing the costs of the two scenarios, the cost will be higher on a monthly basis

for the wellpoint scenario. This is due to the fact that each well must be drilled individually

which requires more time and material costs. The advantage to the wellpoint system is that it is

able to draw down the water table to the point that the soil becomes unsaturated. This

unsaturated soil causes the soil to retain more of its internal shear strength and applies less active

pressure stress on the excavated soil face, leading to less support required. This will be

investigated further in the next section.

4.0 Soil Excavation Support

In the Richmond Forcemain project, the health and safety will be the largest concern and

focus for the workers on site. The open cut excavation proposed for the sanitary forcemain will

be of utmost importance. It is for this reason that the stability of the soil and the type of bracing

will be analyzed to ensure they can safely handle the loads imposed by the soil. For this

application of open cut excavation, the types of soil failure possible would be toppling due to the

granular nature of the fill and sandy materials. Another possible source of failure could be sliding

which is due to the high groundwater table causing the soil to be saturated and prone to sliding.

For the design significance of excavating and backfilling, the factor of safety applied will

be 1.3, a typical value for non-critical structures. In order to apply this factor of safety, the trench

Page 16: Travis_Smith_Work_Term_Report_F2016

boxes will be designed to ensure they meet and exceed the forces and stresses exerted by the cut

soil.

For this stability analysis, due to the nature of the work, it will be considered short-term

stability analysis. This means that total stress analysis will be applied, and pore water pressure

will be assumed zero as it does not have time to develop and will be constantly changing.

In order to analyze the soil, several assumptions will need to be made in order to apply

equations to the real scenario. The analysis will be conducted on the deepest part of the trench,

which is the 4.65m deep open cut excavation. According to the borehole log for this point, we

have the soil stratification and groundwater level which will allow us to analyze the probable

forces and stresses. The analysis and design will focus on one of the possible cases, where the

groundwater table is at 1.16m below ground level as per the borehole logs and the soils present

are as per the borehole logs as well. The groundwater table was raised 0.24m from the reported

value since the work will be done in the springtime and groundwater levels will be higher than

when the measurements were taken.

β€˜Now the parameters for the soils ca be determined. Since certain values that are required

were not found through the borehole logs or subsequent analysis, assumptions and

generalizations will need to be made in order to quantify and apply values to the soils. A

commonly used website titled geotechinfo.data was used to correlate the values and type of soils

found to an approximate value for the unit weight and internal friction angle of the soils. The unit

weights for the soil are empirical values determined using the tables of an online resource. For

Page 17: Travis_Smith_Work_Term_Report_F2016

example, referring to the table titled β€œTypical Values of Soil Index Properties” we can determine

that for a stiff silty clay the dry unit weight would be approximately 140 lb/ft3 and the saturated

unit weight would be 80 lb/ft3.’ (Soil Unit Weight, 2017).

β€˜For the angle of internal friction, a table was also referred to β€œTypical values of soil

friction angle for different soils according to USCS” in order to get an estimate of the typical

friction angles for the soils present.’ (Soil friction angle, 2017)

Table 6 below shows the technical data compiled for the soils in situ in the location of

borehole F1.

Table 6: Technical Data for the In Situ Soils at Borehole F1

Soil Type Start

Elevation (m)

Final Elevation

(m)

Thickness (m)

Dry Unit Weight

(kg/m^3)

Saturated Unit

Weight (kg/m^3)

Friction angle, Ο† (Β°)

Undrained Cohesion, Cu

(kN/m^3)

Granular Fill 93.15 91.02 2.13 1842 849 30 0

Stiff, grey brown Silty Clay 91.02 89.64 1.38 2243 1281 27 35

Very loose, grey Silt 89.64 88.5 1.14 1297 817 25 0

β€˜For the soil analysis, the technique used to calculate the required supports for braced

cuts was used. This allows for the calculation of the forces on the struts or spreaders of the trench

boxes. This method also allows for the calculation of the maximum bending moment which will

be exerted on the trench box walls or panels. Since the method of analyzing braced cuts usually

involves trenches that are 6m deep with no groundwater table, the analysis will be exceeding

what has been previously been analyzed using this method. This method was chosen due to the

information it provides which will be critical for the design of the trench box.

Page 18: Travis_Smith_Work_Term_Report_F2016

To begin with the design of the supports for the open cut excavation, the cost of the setup

needs to be taken into consideration. The use of soldier beams or sheet piles are very expensive

for short term construction such as underground sewer work and are not considered for long

stretches of trench. The preferred method for construction is the use of trench boxes which are

dragged along by the excavator and provide a moving work area where the forces and stresses of

the soil are supported by the trench box. For this application, the requirement is to support the

soil to a depth of 4.65m, which is very challenging for a trench box setup. Manufacturers do not

provide trench boxes with heights greater than 10’ or 3.05m due to economical and functional

constraints. It is for this reason that I have proposed to have a setup of two (2) 8’ or 2.438m high

trench boxes stacked one on top of the other for this difficult portion of the trench. This will

provide a 4.8m soil support height and will allow for the re-use of the trench boxes in the other

areas of the open cut trench along the proposed forcemain pathway. This will provide savings in

that the trench box provider will not be charging for multiple mobilization and demobilization

costs and it will also be easier for the contractor to track the costs of the boxes under one

grouping. β€˜(Chapter 7: Sheet Pile Walls and Braced Cuts, 2016)

β€˜As previously discussed, the height for the trench boxes will be 2.438m (8’) in height, but the

other dimensions can be interchanged in order to incorporate for the conditions present in situ.

The variables that will be determined are the length of the trench box (16” to 28”), the thickness

of the panels or walls (4” to 8”), and the inside width of the spreaders or struts (24” to 144”).’

(Trench Protection, 2017)

Page 19: Travis_Smith_Work_Term_Report_F2016

Figure 1 - Braced cut analysis on trench box supports

β€˜As seen above in Figure 1 above, the parameters have been given and the analysis can begin. In

order to determine the active earth pressure exerted on the trench panels, we must assign an

apparent lateral earth pressure diagram. This diagram is dependent on the type of soil, for the

stiff silty clay layer;

𝛾𝐻

𝑐𝑒=

(22.43π‘˜π‘”π‘š3)(1.38π‘š)

35 π‘˜π‘/π‘š3= 0.88 < 4 => 𝑆𝑇𝐼𝐹𝐹 πΆπΏπ΄π‘Œ

Since the granular fill and loose silt have trace clay components, the entire soil envelope will be

treated as a stiff clay for the apparent lateral earth pressure envelope in order to simplify

calculations. For this type of soil envelope, the active earth pressure can have a factor between

Page 20: Travis_Smith_Work_Term_Report_F2016

0.2 and 0.4, the 0.4 value was chosen for design purposes in order to provide a better support

system.

Now the analysis of the section can begin, this is initiated by rotating the vertical subsurface into

something that can be analyzed like a beam. This was performed and is shown in Figure 2 below.

Figure 2 - Analysis of Vertical soil face

Analysis from the surface to point B

𝑅1 =1

2βˆ— 1.16π‘š βˆ— 0.4 βˆ— 18.42

π‘˜π‘”

π‘š3βˆ— 4.65π‘š = 19.87

π‘˜π‘

π‘š

𝑅2 = 0.865π‘š βˆ— 0.4 βˆ— 8.49π‘˜π‘”

π‘š3 βˆ— 4.65π‘š = 13.66 π‘˜π‘

π‘š

𝑅3 =1

2βˆ— 1000

π‘˜π‘”

π‘š3βˆ— 9.81

π‘š

𝑠2βˆ— (0.865π‘š)2 = 3.67

π‘˜π‘

π‘š

Page 21: Travis_Smith_Work_Term_Report_F2016

βˆ‘ 𝑀𝐴 = 0; ( 2

3βˆ— 1.16π‘š βˆ’ 0.275π‘š)(19.87

π‘˜π‘

π‘š) + (1.16π‘š +

1

2βˆ— 0.865π‘š

βˆ’ 0.275π‘š)(13.66π‘˜π‘

π‘š) + (1.16π‘š +

2

3βˆ— 0.865π‘š βˆ’ 0.275π‘š)(3.67

π‘˜π‘

π‘š) βˆ’ 1.75π‘š

βˆ— 𝐡1 = 0

∴ π‘©πŸ = πŸπŸ—. πŸŽπŸŽπ’Œπ‘΅

π’Ž

βˆ‘ 𝐹𝑦 = 0; 𝐴 + 19.00π‘˜π‘

π‘šβˆ’ 19.87

π‘˜π‘

π‘šβˆ’ 13.66

π‘˜π‘

π‘šβˆ’ 3.67

π‘˜π‘

π‘š

∴ 𝑨 = πŸπŸ–. πŸπŸŽπ’Œπ‘΅

π’Ž

Figure 3: Shear Force and Bending Moment Diagrams for First Cut Section

0 = 13.49 βˆ’34.26

2βˆ— 𝑋1

∴ π‘ΏπŸ = 𝟏. πŸπŸπ’Ž

Page 22: Travis_Smith_Work_Term_Report_F2016

From the shear force diagram, the corresponding moments were determined;

𝐴1 = (1

3) βˆ— 0.275π‘š βˆ— βˆ’4.71

π‘˜π‘

π‘š= βˆ’0.43

π‘˜π‘

π‘š2

𝐴2 = (2

3) βˆ— 0.787π‘š βˆ— 13.49

π‘˜π‘

π‘š= 7.08

π‘˜π‘

π‘š2

𝐴3 = (1

3) βˆ— (1.75π‘š βˆ’ 0.787π‘š) βˆ— 19.00

π‘˜π‘

π‘š= βˆ’6.10

π‘˜π‘

π‘š2

Analysis from point B to the bottom of the trench

𝑅1 = 1.465π‘š βˆ— 0.4 βˆ— 22.43π‘˜π‘”

π‘š3βˆ— 4.65π‘š = 61.12

π‘˜π‘

π‘š

𝑅2 = 1.16π‘š βˆ— (1

2) βˆ— 0.4 βˆ— 12.97

π‘˜π‘”

π‘š3βˆ— 4.65π‘š = 13.99

π‘˜π‘

π‘š

𝑅3 = 0.865π‘š βˆ—1000π‘˜π‘”

π‘š3βˆ— 9.81

π‘š

𝑠2βˆ— 2.625π‘š = 22.29

π‘˜π‘

π‘š

𝑅4 = (1

2) βˆ— 2.625π‘š βˆ— 1000

π‘˜π‘”

π‘š3βˆ— 9.81

π‘š

𝑠2βˆ— 2.625π‘š = 34.13

π‘˜π‘

π‘š

βˆ‘ 𝑀𝐡 = 0; (1.465

2βˆ— 61.12) βˆ’ 0.875 βˆ— 𝐢 + (

2.625

2βˆ— 22.29) + ((

2

3) βˆ— 2.625 βˆ— 34.13)

+ ((1.465 + (1

3) βˆ— 1.16) βˆ— 13.99) = 0

∴ π‘ͺ = πŸπŸ–πŸ. πŸ’πŸ•π’Œπ‘΅

π’Ž

βˆ‘ 𝐹𝑦 = 0; 𝐡2 + 182.47 βˆ’ 69.5 βˆ’ 13.99 βˆ’ 22.29 βˆ’ 34.13 = 0

∴ π‘©πŸ = πŸ’πŸ. πŸ“πŸ”π’Œπ‘΅

π’Ž (↓)

Page 23: Travis_Smith_Work_Term_Report_F2016

Figure 4: Shear force and Bending Moment Diagrams for Second Cut Section

Struts/Spreaders:

Let the length of the spreaders, s, be 84” or 2.13m

𝑃(𝐴) = 𝐴 βˆ— 𝑠 = 18.00π‘˜π‘

π‘šβˆ— 2.13π‘š = 38.34 π‘˜π‘

𝑃(𝐡) = (𝐡1 + 𝐡2) βˆ— 𝑠 = (19.00 βˆ’ 42.56) βˆ— 2.13π‘š = βˆ’50.18 π‘˜π‘

𝑃(𝐢) = 𝐢 βˆ— 𝑠 = 182.47π‘˜π‘

π‘šβˆ— 2.13π‘š = 388.66 π‘˜π‘

Walls/Panels:

From the bending moment diagram, we can determine the maximum positive and negative

bending moments.

π‘€π‘šπ‘Žπ‘₯,βˆ’β€²π‘£π‘’ = βˆ’58.36π‘˜π‘

π‘š2

Page 24: Travis_Smith_Work_Term_Report_F2016

π‘€π‘šπ‘Žπ‘₯,+′𝑣𝑒 = 21.88π‘˜π‘

π‘š2

Now we can begin to design the trench box, but first the factor of safety must be applied to all of

the calculated values.

𝑃𝐴,π‘Žπ‘™π‘™π‘œπ‘€π‘Žπ‘π‘™π‘’ = 38.34 π‘˜π‘ βˆ— 1.13 = 43.3 π‘˜π‘

𝑃𝐡,π‘Žπ‘™π‘™π‘œπ‘€π‘Žπ‘π‘™π‘’ = βˆ’50.18 π‘˜π‘ βˆ— 1.13 = βˆ’56.7 π‘˜π‘

𝑃𝐢,π‘Žπ‘™π‘™π‘œπ‘€π‘Žπ‘π‘™π‘’ = 388.36 π‘˜π‘ βˆ— 1.13 = 438.8 π‘˜π‘

π‘€π‘šπ‘Žπ‘₯,βˆ’β€²π‘£π‘’,π‘Žπ‘™π‘™π‘œπ‘€π‘Žπ‘π‘™π‘’ = βˆ’58.36π‘˜π‘

π‘š2βˆ— 1.13 = βˆ’65.9 π‘˜π‘/π‘š2

π‘€π‘šπ‘Žπ‘₯,+′𝑣𝑒,π‘Žπ‘™π‘™π‘œπ‘€π‘Žπ‘π‘™π‘’ = 21.88π‘˜π‘

π‘š2βˆ— 1.13 = 24.7 π‘˜π‘/π‘š2

Looking at the maximum bending moments of -65.9 kN/m2 and 24.7 kN/m2, the

thickness of the wall will be determined which can sustain these factored values. β€˜In order to

determine the require thickness of the steel panel or wall, we will apply an analysis called elastic

moment resistance. This formula was chosen in place of the yield moment resistance since we

want the designed wall to be able to sustain the loads and moments without bending or yielding

which may compromise the integrity and safety of the structure.’ (Flexural Members (Beams),

2016)

Elastic moment resistance:

πœŽπ‘šπ‘Žπ‘₯ =𝑀π‘₯ βˆ— π‘¦π‘šπ‘Žπ‘₯

𝐼π‘₯

𝐼π‘₯ =π‘β„Ž3

12=

(𝑑)(2.625π‘š)3

12= 1.5075 βˆ— 𝑑 π‘š3

Page 25: Travis_Smith_Work_Term_Report_F2016

π‘¦π‘šπ‘Žπ‘₯ =2.625π‘š

2= 1.3125π‘š

πœŽπ‘šπ‘Žπ‘₯ = 400π‘₯103π‘˜π‘

π‘š2=

(βˆ’65.9π‘˜π‘π‘š2) (1.3125π‘š)

1.5075 𝑑 π‘š3

603π‘₯103 π‘˜π‘π‘š βˆ— 𝑑 = 86.49 π‘˜π‘/π‘š

𝑑 = 143π‘₯10βˆ’6π‘š = 0.143 π‘šπ‘š

Since the required value for the thickness of the wall is quite low, the recommendation is to rent

a 6” thick double walled panel. This is due to the fact that often calculations are not enough to

model the in situ soil. In order to keep safety the priority during construction, a 6” thick panel

would be preferred.

The final step in the design of the trench box will be to determine the required area of the

spreader required to support the axial forces which are transferred from the walls to the

spreaders. In order to calculate this, the maximum axial force of 438.8 kN will be used for the

calculations. β€˜The method of analysis will be to investigate the possible modes of failure for ideal

compression members. This means that we will determine the required pipe width for three (3)

cases of failure: Yielding, Local Buckling, and Global Buckling. The inside width or inside

diameter of the spreader will 0.2187m (8”) as per the suppliers limitations. For walls that are 6”

or 8” thick, the spreaders required have a minimum thickness of 0.2187m (8”).’(Compression

Members, 2016)

Yielding:

𝐢 = 𝐴 βˆ— 𝐹𝑦

Page 26: Travis_Smith_Work_Term_Report_F2016

𝐢 = 438.8 π‘˜π‘ = 𝐴 βˆ— 400 π‘€π‘ƒπ‘Ž

𝐴 = 1.097 βˆ— 10βˆ’3 π‘š2

Global Buckling:

π‘ƒπ‘π‘Ÿ =πœ‹2𝐸𝐼

𝑙2

π‘ƒπ‘π‘Ÿ = 438.8 π‘˜π‘ = πœ‹2 βˆ— (200 βˆ— 109 𝑁

π‘š2)(πœ‹

64 βˆ— (𝐷4 βˆ’ 𝑑4))

(2.13π‘š)2

1.99π‘₯103 π‘˜π‘ βˆ— π‘š2 = 96.895π‘₯109𝑁/π‘š2(𝐷4 βˆ’ 𝑑4)

𝐷4 βˆ’ 𝑑4 = 1.99π‘₯103 π‘˜π‘ βˆ— π‘š2

96.895π‘₯106 π‘˜π‘π‘š2

= 20.537π‘₯10βˆ’6 π‘š4

Local Buckling:

For circular hollow sections:

𝐷

𝑑<

23,000

𝐹𝑦

𝐷

𝑑 <

23,000

400 π‘€π‘ƒπ‘Ž= 57.5

With these restricting equations, we can determine the required thickness and width of the

spreader that meets the requirement for possible modes of failure. The process is iterative and

involves the use of the suppliers provided sizes, i.e 24”, 30”, 36”, etc… for the inside width of

the spreader. The first value chosen was an inside width of 48”, a value roughly in the middle of

the choices.

Case 1: Spreader with 0.2187m (8”) thickness and 1.312m (48”) inside diameter

Page 27: Travis_Smith_Work_Term_Report_F2016

Yielding Check

π΄π‘π‘Ÿπ‘œπ‘£ =πœ‹

4(𝐷2 βˆ’ 𝑑2) =

πœ‹

4((1.5307π‘š)2 βˆ’ (1.312π‘š)2) = 0.488 π‘š2

π΄π‘π‘Ÿπ‘œπ‘£ = 488.2 π‘₯10βˆ’3π‘š2 > π΄π‘Ÿπ‘’π‘ž = 1.097π‘₯10βˆ’3 π‘š2 𝐺𝑂𝑂𝐷.

Global Buckling Check

𝐷4 βˆ’ 𝑑4 > 20.537π‘₯10βˆ’6 π‘š4

(1.5307π‘š)4 βˆ’ (1.312π‘š)4 = 2.52 π‘š4 > 20.537π‘₯10βˆ’6π‘š4 𝐺𝑂𝑂𝐷.

Local Buckling Check

𝐷

𝑑=

1.5307π‘š

0.2187π‘š= 6.99 < 57.5 𝐺𝑂𝑂𝐷.

This case meets all of the required elements, but in order to minimize the cost of the system, we

will attempt to provide a system that is within reasonable cost but with a smaller size which will

have a lower rental cost.

Case 2: Spreader with 0.2187m (8”) thickness and 0.656m (24”) inside diameter

Yielding Check

π΄π‘π‘Ÿπ‘œπ‘£ =πœ‹

4(𝐷2 βˆ’ 𝑑2) =

πœ‹

4((0.8748π‘š)2 βˆ’ (0.656π‘š)2) = 263.0π‘₯10βˆ’3 π‘š2

π΄π‘π‘Ÿπ‘œπ‘£ = 263.0 π‘₯10βˆ’3π‘š2 > π΄π‘Ÿπ‘’π‘ž = 1.097π‘₯10βˆ’3 π‘š2 𝐺𝑂𝑂𝐷.

Global Buckling Check

𝐷4 βˆ’ 𝑑4 > 20.537π‘₯10βˆ’6 π‘š4

(0.8748π‘š)4 βˆ’ (0.656π‘š)4 = 400.4π‘₯10βˆ’3 π‘š4 > 20.537π‘₯10βˆ’6π‘š4 𝐺𝑂𝑂𝐷.

Local Buckling Check

Page 28: Travis_Smith_Work_Term_Report_F2016

𝐷

𝑑=

0.656π‘š

0.2187π‘š= 2.999 < 57.5 𝐺𝑂𝑂𝐷.

This size of spreader meets the requirements and has the lowest price. Therefore for this design,

the spreaders chosen will be 0.2187m (8”) in thickness, and will have an inside diameter of

0.656m (24”).

5.0 Discussion

The analysis conducted went into great detail into the theoretical and practical sides of

construction. In Section 2.0: Subsurface Profile, the borehole logs and geotechnical investigation

performed by a third party were investigated to determine and produce a cross section of the soil

stratification. It is worth noting that after the soil profile was completed, the was an addendum to

the tender that raised the invert elevation of the forcemain in certain sections to reduce the

amount of excavation in the bedrock. Without the information extracted from the borehole logs,

the owners would not have noticed the extra cost of excavating and removing rock in these areas.

Aside from that, the depths and thicknesses of the layers of soils were also determined and

shown in Table 2: Subsurface Profile Elevations and were used in the other sections of this

report.

In the second part of the report, Section 3.0: Trench Dewatering the methods of trench

dewatering were analyzed. It was determined that cost of the well point dewatering system

would exceed that of the sump pumping, yet the decision for which system would be chosen was

not clear. In my professional opinion, the use of wellpoints for dewatering would provide a more

dependable option. One reason for this method would be that it would be easier to increase the

Page 29: Travis_Smith_Work_Term_Report_F2016

pumping rate by adding additional pumps or larger pumps if there are unforeseen circumstances

such as fissures or porous rock which increase infiltration. The wellpoint system as well will

provide a more stable working surface where the groundwater table will be lowered below the

trench. With a groundwater table below the trench, there will be less concern of soil failure due

to saturation and also less concern with basal heaving at the bottom of the trench. It is the

recommendation of this report to subcontract the dewatering portion of the contract to a

dewatering company who specializes in the use of wellpoints and will be able to provide the

required equipment.

In the final part of the report, Section 4.0: Soil Support System, the excavated soil face

was analyzed in order to determine the required supports. The proposed support system for the

trench, due to the short term of construction, was recommended to be trench boxes. Trench boxes

provide a temporary support which can be moved along with the excavation as it progresses.

During the analysis the forces and stresses were calculated leading to the following

recommendations. For the trench box walls or panels, it was recommended that the contractor

rent a 6” double wall panel. For the spreaders bars or struts, the recommendation is to rent

spreaders with an 0.2187m (8”) thickness and 0.656m (24”) inside width. With these

components, the excavator would be able to move the trench boxes along as the forcemain is

installed, reducing the cost compared to other support methods.

6.0 Conclusions

Despite the many challenges that are present on this project, it is my opinion that with this

additional information the estimators will be able to provide a more accurate estimate. With this

Page 30: Travis_Smith_Work_Term_Report_F2016

report in combination with the subsurface investigation provided by Houle Chevrier Engineering

Ltd., the estimator can request directly for the information on the required equipment and

materials rather than having to pay for separate analysis.

Page 31: Travis_Smith_Work_Term_Report_F2016

7.0 References

1. β€œSubsurface Investigation”, Richmond Forcemain Repairs and Modifications, Ottawa,

Ontario. Houle Chevrier Engineering Ltd. April 1, 2016.

2. Draft Permit to Take Water 5028-AAVHUN

3. β€œCategory 3 Permit to Take Water Application Package”, Richmond Forcemain

Upgrades, Ottawa, Ontario. Houle Chevrier Engineering Ltd. April 8, 2016.

4. β€œHydraulic Submersible Pump Heads (HST).” Thompson Pump, December 27, 2016,

https://www.thompsonpump.com/Hydraulic-Submersible-Pump-Heads--HST--10-181.html.

5. β€œWater Flow through Hoses – Pressure Loss” The Engineering ToolBox, December 28,

2016, http://www.engineeringtoolbox.com/water-pressure-loss-hose-d_1525.html.

6. β€œSoil Unit Weight” Geotechnical Info.com, January 2, 2017,

http://www.geotechnicalinfo.com/soil_unit_weight.html.

7. β€œSoil friction angle” Geotechnical Info.com, January 2, 2017,

http://www.geotechdata.info/parameter/angle-of-friction.html.

8. Dimitrova, Rozalina. β€œChapter 7: Sheet Pile Walls and Braced Cuts” University of

Ottawa, Summer 2016.

9. β€œTrench Protection” CAT The Rental Store, January 3, 2017,

http://www.catrents.ca/Products/Equipment/Rental_Equipment/_downloads/2014_Trencher.pdf.

10. β€œFlexural Members (Beams)” CVG3147-Structural Steel Design I, 2016

11. β€œCompression Members” CVG3147-Structural Steel Design I, 2016

Page 32: Travis_Smith_Work_Term_Report_F2016

8.0 Appendices

Appendix A – Conceptual Model for Groundwater Lowering System

Appendix B – Subsurface Profile