Upload
others
View
5
Download
1
Embed Size (px)
Citation preview
Twenty Forth Annual
Willem C. Vis International Commercial Arbitration Moot
Vienna, Austria April 7-13, 2017
MEMORANDUM FOR CLAIMANT
On behalf of Against
Wright Ltd SantosD KG
232 Garrincha Street 77 Avenida O Rei
Oceanside, Equatoriana Cafucopa, Mediterraneo
CLAIMANT RESPONDENT
ALEXIA-NEFELI DOUMA • ILLIA CHERNOHORENKO • PENKA KOSTOVA
Memorandum for CLAIMANT
TABLE OF CONTENTS
INDEX OF ABBREVIATIONS ........................................................................................................................................... IV
INDEX OF STATUTES, RULES AND TREATIES .......................................................................................................... VI
INDEX OF AUTHORITIES ............................................................................................................................................... VII
INDEX OF COURT DECISIONS ........................................................................................................................................ XI
INDEX OF ARBITRAL AWARDS ................................................................................................................................... XII
STATEMENT OF FACTS ...................................................................................................................................................... 1
SUMMARY OF THE ARGUMENTS .................................................................................................................................... 4
ARGUMENTS ON THE PROCEDURAL ISSUES.............................................................................................................. 5
I. THE CLAIMANT’S CLAIMS ARE ADMISSIBLE. ................................................................................. 5
1. ‘Failure of negotiation’ did not take place on 1st April 2016, therefore, claims are admissible. ........... 5
1.1. Ambiguity in the time-bar clause must be resolved in favour of restrictive application. ...... 5
1.2. Claimant did not foreclose negotiation, or declare ‘failure of negotiation’ through the
email dated 1st April 2016. .................................................................................................................................... 6
1.3. Alternatively, negotiations failed not with the email dated 1st April 2016, but with
Respondent’s failure to reply to the same became apparent. .............................................................. 7
2. In arguendo, the DSA does not apply the sixty-day time-bar to compliance with technical requirement
of the CAM-CCBC Rules. ................................................................................................... 7
3. In any case, arbitration commenced within the prescribed time as there was substantial compliance with
Article 4.1 of the CAM-CCBC Rules. ................................................................................. 8
3.1. Arbitration commences where there is substantial compliance with technical requirements. ..... 8
3.2. Defect relating to power attorney was technical and curable. ....................................................................... 9
3.3. Non-payment of Registration Fee does not affect ‘commencement’ of arbitration under Article
4.1 of the CAM-CCBC Rules. ............................................................................................................................... 10
II. THE RESPONDENT’S REQUEST FOR SECURITY FOR COSTS SHOULD BE DISMISSED .............. 10
1. Special considerations apply to grant of security for costs, in view of the measure’s exceptional
nature. ................................................................................................................................. 11
2. The Respondent’s application for security for costs is precluded on grounds of consent and delay.
........................................................................................................................................... 11
3. The application must be dismissed since there has been no ‘fundamental change in
circumstances’. ...................................................................................................................... 12
4. Security of costs cannot be ordered as the Claimant does not suffer from an inability to satisfy an
award of costs, or an inadequacy of assets. ............................................................................. 13
4.1. Claimant’s inability to satisfy an adverse award for costs is relevant to deciding the
application, and not its alleged unwillingness. ........................................................................................ 13
4.2. Application cannot be decided in Respondent’s favour on the basis of the information
presented. ................................................................................................................................................................... 14
Memorandum for CLAIMANT
III
4.3. Claimant does not suffer from an inability to pay costs or lack of resources against which
an award may be enforced. ................................................................................................................................ 14
5. It would be unfair to grant security for costs, as the claims have substance and have been made in
good faith. ............................................................................................................................ 15
CONCLUSION ON PROCEDURAL ISSUES .................................................................................................................... 16
ARGUMENTS ON THE MERITS ..................................................................................................................................... 16
III. THE CLAIMANT IS ENTITLED TO USD 2,285,240 FOR THE FAN BLADES
BASED ON THE PRESENT EXCHANGE RATE ............................................................. 16
1. The parties agreed to the conversion of Claimant’s production cost on a flexible ‘cost-plus basis’
under the DSA ................................................................................................................... 16
1.1 The DSA must be interpreted through the parties’ common intention, which was not to
have any fixed exchange rate. ........................................................................................................................... 17
1.1A fixed exchange rate is incompatible with the common intention to calculate price on
a ‘cost-plus basis’ ................................................................................................................................. 17
1.1B. No previous practice between the parties relating to the application of a fixed
exchange rate. ...................................................................................................................................... 19
1.2. Additionally, and alternatively, the fixed exchange rate could not be read into the DSA by a
reasonable person .................................................................................................................................................. 20
2. The Addendum did not alter or amend any terms of the DSA. ............................................. 21
2.1. There was no intent as to the rights and obligations under the main DSA. ............................ 22
2.1A Neither parties intended to modify the main DSA through the Addendum. ......... 22
2.1B The Claimant specifically intended for the fixed-rate clause to apply only to sale
of clamps. ................................................................................................................................................ 23
2.2. Applying the ‘reasonable interpretation’ test, the written terms show that the fixed-rate
clause was limited to the Addendum. ........................................................................................................... 23
2.3. Applying the contra-preferentem rule, uncertainty in the interpretation and application
must be resolved in the Claimant’s favour. ................................................................................................ 25
IV. THE CLAIMANT IS ENTITLED TO USD 102,192.80 FOR THE FEES DEDUCTED BY
THE EQUATORIANA CENTRAL BANK. ......................................................................... 25
1. Respondent is liable to pay the levy under the DSA. ............................................................. 26
1.2 The levy under ML/2010C falls within the meaning of ‘bank charges’ ........................................ 26
2. Respondent is liable to pay the levy under the general legal framework. ................................... 27
2.1 Respondent has the obligation to take all necessary measures to effect full payment to the
Claimant under Art. 54 CISG ............................................................................................................................. 27
2.2 Respondent did not discharge its obligation for payment when the Central Bank deducted
the 0.5% levy before the funds reached Claimant’s financial institution. ................................... 28
CONCLUSION ON SUBSTANTIVE ISSUES ................................................................................................................... 29
REQUEST FOR RELIEF ..................................................................................................................................................... 31
Memorandum for CLAIMANT
IV
INDEX OF ABBREVIATIONS
AAA American Arbitration Association
Art./Arts. Article/Articles
CA Court of Appeal
CAM-CCBC Center for Arbitration and Mediation of the Chamber of Commerce
CISG United Nations Convention on Contracts for International Sale of
Goods, Vienna 1980
CLAIMANT Wright Ltd
Co. Company
Corp. Corporation
DSA Development and Sales Agreement, 1 August 2010
Ed.
EQD
Edition
Equatorianian Denar
EU European Union
EWHC England and Wales High Court of Justice
Exhibit/Ex.C [No.] CLAIMANT’s Exhibit [No.]
Exhibit/Ex.R [No.]
FIU
GBP
RESPONDENT’s Exhibit [No.]
Financial Investigation Unit
Great British Pound
i.e. Id est [that is]
ICC International Chamber of Commerce International Court of
Arbitration
Inc. Incorporated
LCIA The London Court of International Arbitration
Ltd Limited
No./Nos. Number/Numbers
p./pp. Page/Pages
para./paras. Paragraph/Paragraphs
PO No. 1 Procedural Order Number 1
PO No. 2 Procedural Order Number 2
Prof./Profs. Professor/Professors
Res. Answer Answer to Statement of Claim by RESPONDENT
RESPONDENT SantosD KG
Sec. Section
Memorandum for CLAIMANT
V
St. Cl. Statement of Claim by CLAIMANT
Swiss Rules Swiss Arbitration Rules 2012
The Parties CLAIMANT and RESPONDENT
The U.S. The United States of America
The UK The United Kingdom
UKHL The United Kingdom House of Lords
UNCITRAL United Nations Commission for the Unification of International
Trade Law
UNCITRAL Rules United Nations Commission for the Unification of International
Trade Law Arbitration Rules 2010
UNIDROIT Principles of International Commercial Contracts of 2004 of the
International Institute for the Unification of Private Law
USD United States Dollar
v. Versus [against]
Vol. Volume
Memorandum for CLAIMANT
VI
INDEX OF STATUTES, RULES AND TREATIES
Chartered Institute of Arbitrators Guidelines on Applications for Security for Costs (2015)
CIA Guidelines on Applications for Interim Measures (2016)
Convention on the Recognition and Enforcement of Foreign Arbitral Awards (New York
1958) (the “New York Convention”)
International Bar Association Rules on the Taking of Evidence in International Arbitration
(2010)
International Chamber of Commerce International Court of Arbitration Rules (2012)
Singapore International Arbitration Centre Arbitration Rules (2013)
United Nation Commission on International Trade Law Arbitration Rules (2010)
United Nation Commission on International Trade Law Model Law on International
Commercial Arbitration (1985)
United Nations Convention on Contracts for International Sale of Goods (Vienna 1980)
Memorandum for CLAIMANT
VII
INDEX OF AUTHORITIES
Cited as Sources Cited at para.
Blacks Law Dictionary Blacks Law Dictionary 1290
Bonell
Cf. Ole Lando
Bonell, M. J., The UNIDROIT Principles in Practice,
(2nd. Ed., Transnational Publishers, 2006).
Cf. Ole Lando and Hugh Beale eds., Principles of
European Contract Law: Parts I and II, Kluwer Law
International (2000)
Derains,Schwartz Yves Derains & Eric A. Schwartz, A Guide to the ICC
Rules of Arbitration, 2nd edn
The Hague: Kluwer Law International (2005), 57 and
43
DiMatteo DiMatteo, L. A. [et al.], International Sales Law: A
Critical Analysis of CISG Jurisprudence, Cambridge
University Press, 2006, at 154-156.
DiMatteo DiMatteo, L. A., International Contract & Sales Law,
Kluwer Law International (2009), at 214-224.
Friedland Paul D. Friedland, The Swiss Supreme Court Sets
Aside an ICC Award, Journal of International
Arbitration, (© Kluwer Law International;
Kluwer Law International 1996, Volume 13 Issue 1)
pp. 111 – 116, at page 112, 113
Fouchard John Savage; Emmanuel Gaillard; Fouchard Gaillard
Goldman, International Commercial Arbitration
Kluwer Law International (1999)
Memorandum for CLAIMANT
VIII
Gabriel
J. Waincymer
Gabriel, H. D., The Buyer's. Performance under the
CISG: Articles 53-60 Trends in the Decisions, 25 J.L.
& Commerce, at 273.
Jeff Waincymer , Procedure and Evidence in
International Arbitration, (© Kluwer Law
International; Kluwer Law International 2012) at page
224
Finkelstein/Casado
Filho/Straube
Frederico Jose Straube; Claudio Finkelstein; Napoleao
Casado Filho, The CAM-CCBC Arbitration Rules 2012
: A commentary (Eleven International Publishing 2016)
Richard Hyland CISG-AC Opinion no 3, Parol Evidence Rule, Plain
Meaning Rule, Contractual Merger Clause and the
CISG, 23 October 2004. Rapporteur: Professor,
Rutgers Law School, Camden, NJ, USA.
Kröll/Mistelis/
Viscasillas
John O. Honnold
Johan Erauw
Stefan Kröll; Loukas Mistelis; Pilar Perales Viscasillas
UN Convention on the International Sale of Goods
(CISG) Commentary
C. H. Beck (2011)
Uniform law for international sales under the 1980
United Nations convention / John O. Honnold ;
edited and updated by Harry M. Flechtner. [4th ed.]
Johan Erauw, CISG Articles 66-70: The Risk of Loss
and Passing It p. 203-215
80, 86
Lew/Mistelis/Kröll Julian D. M. Lew; Loukas A. Mistelis; Stefan Michael
Kröll, Comparative International Commercial
Arbitration
Kluwer Law International (2003) at page 224
Macdonald Macdonald, E., Bank Charges and the Core
Exemption: Office of Fair Trading v. Abbey National
Plc,
The Modern Law Review, 2008, at 994.
Memorandum for CLAIMANT
IX
Magnus Magnus, Ulrich, General Principles of UN-Sales Law,
Rabels Zeitschrift for Foreign and International Private
Law,
Volume 59, Issue 3-4, 1995, at 469-494.
Maskow Maskow, D., Article 54, Bianca, C.M. & Michael
Bonell. Commentary on the International Sales Law:
The 1980 Vienna Sales Convention (Milan: Guiffre,
1987), at 394-400.
Needham Michael J. Needham, Orders for Security for a Party's
Costs, 63 J.C.I. Arb. 122–29 (1997).
Osana-Gonzalez
Schlechtriem and
Schwenzer
Osana-Gonzalez, Buyer’s enabling steps to pay the
Price: Article CISG, 25 Journal of Law & Commerce
(2005-06), at 299-323.
Peter Schlechtriem; Ingeborg Schwenzer, Schlechtriem
& Schwenzer Commentary on The UN Convention on
The International Sale of Goods (CISG).]
Redfern/Hunter Nigel Blackaby; Constantine Partasides; Alan Redfern;
J. Martin Hunter, Redfern and Hunter on International
Arbitration
Kluwer Law International (6th ed., 2015)
105
Reid Greg Reid, Security for Costs in International
Arbitrations: Forget It?, New Law Journal, September
27, 2002 (Arbitration and ADR supplement) at 1427
Saidov Djakhongir Saidov, The Law of Damages in
International Sales : The CISG and Other International
Instruments,
Hart Publishing (2008), sec.2.1
Sevón L. Sevón L., Obligations of the Buyer under the Vienna
Convention on the International Sale of Goods,
Reproduced with permission from Suomalainen
Lakimiesten Yhdistys: -Tidskrift utgiven av Juridiska
Föreningen i Finland
[Finnish Law Society] 126 (1990), at 327-343
102
Memorandum for CLAIMANT
X
Gary Soo Gary Soo, Securing Costs in Hong Kong Arbitration, 3
Int'l Arb. L. Rev. 25 (2000) at page 25.
Tallon, D. Published in Galston & Smit ed., International Sales:
The United Nations Convention on Contracts for the
International Sale of Goods, Matthew Bender (1984),
Juris Publishing, Ch. 7, at 7-1 & 7-20.
UNCITRAL Model
Law Digest
United Nations Commission on International Trade
Law, UNCITRAL Secretariat, UNCITRAL 2012
Digest of Case Law on the Model Law on International
Commercial Arbitration
116
UNIDROIT
Principles
Commentary
Stefan Vogenauer
in: Commentary on the UNIDROIT Principles of
International Commercial Contracts (PICC)
Oxford University Press (2009)
121, 123
Veeder V Veeder, International Handbook on Commercial
Arbitration
Paulsson ed, (1997)
Waincymer Jeffrey Waincymer, Procedure and Evidence in
International Arbitration
Kluwer Law International (2012)
Weixa
Weixia Gu, Security for Costs in International
Commercial Arbitration, Journal of International
Arbitration, (© Kluwer Law International; Kluwer Law
International 2005, Volume 22 Issue 3) pp. 167 – 205,
at page 188;
Zeller Bruno Zeller “Determining the Contractual Intent of Parties
under the CISG and Common Law -- A Comparative
Analysis” Reproduced with permission of European Journal
of Law Reform (Kluwer) Vol. 4, No. 4 (2002) 629-643
Memorandum for CLAIMANT
XI
INDEX OF COURT DECISIONS
Hong Kong
China Shipping Co. v.
Whistler Charterers
China Ocean Shipping Co. Owners of the M/V Fu
Ning Hai v. Whistler International Charterers of the
M/V Fu Ning Hai (1999) H.C.C.T. No. 20, May 24,
1999, Findlay J.
The United Kingdom
Berkley C Villages v
Pullen
Berkeley Community Villages Ltd v Pullen, [2007]
EWHC 1330
Nobahar-Cookson v. Hut
Group
Nobahar-Cookson & Ors v The Hut Group Ltd
[2016] EWCA Civ 128
OFT v Abbey National
PLC
Office of Fair Trading v Abbey National plc and
Others [2009] UKSC 6, [2009] EWCA 116, [2008]
EWHC 875 (Comm)
Copée Lavalin v. Ken-
Ren Chemicals
S.A. Coppée Lavalin N.V. v. Ken-Ren Chemicals and
Fertilisers Ltd. [1995] 1 A.C. 38
The Sabrewing The Sabrewing [2008] 1 Lloyd's Rep 286 at para 16-
17
The Starsin Homburg Houtimport BV v Agrosin Private Ltd
[2004] 1 AC 715 at p.779
XY International v.
Société Z
2010 FOLIO
XY International, Inc. v. Société Z (ICC), reprinted
in 1997(2) ASA Bull. 363 cited as: XY Int’l, Inc. v.
Société Z (ICC)
High Court of Justice, Queen's Bench Division
(Commercial Court), Case No: 2010 FOLIO 849, 9
February 2011
Spain
MCC-Marble Ceramic
v Ceramica
See MCC-Marble Ceramic Center, Inc. v. Ceramica
Nuova D'Agostino S.p.A.; Spain 14 July 2010
Cáceres Court of Appeals (Rolls of rubber case)
Memorandum for CLAIMANT
XII
INDEX OF ARBITRAL AWARDS
International Centre for Settlement of Investment Disputes (ICSID)
ICSID Case No.
ARB/12/18, 25 January,
Valle Verde Sociedad Financiera S.L. v. Bolivarian
Republic of Venezuela (Decision on Provisional
Measures), ICSID Case No. ARB/12/18, 25 January
Tribunal of International Commercial Arbitration at the Russian Federation Chamber of
Commerce and Industry
CLOUT Case No. 142
Tribunal of International Commercial Arbitration at the
Russian Federation Chamber of Commerce and Industry,
Russian Federation, 17 October 1995 (Arbitral award No.
123/1992)
CLOUT case No. 215 SWITZERLAND Bezirksgericht [District Court] St.
Gallen 3 July 1997, available online at
<http://cisgw3.law.pace.edu/cases/970703s1.html>
CLOUT Case No. 222 CLOUT case No. 222 [UNITED STATES MCC-Marble
Ceramic Center v. Ceramica Nuova D'Agostino, [Federal
Appellate Court] [11th Circuit] 29 June 1998, available:
<http://cisgw3.law.pace.edu/cases/980629u1.html>
CLOUT Case No. 236 Landgericht Tübingen, Germany, 18 June 2003,
Internationales Handelsrecht, 2003,
CLOUT Case No. 268 GERMANY Bundesgerichtshof [Supreme Court] 11
December 1996, available online at
<http://cisgw3.law.pace.edu/cases/961211g1.html>
CLOUT Case No. 313
FRANCE Cour d'appel [Appellate Court] Grenoble 21
October 1999, available online at
<http://cisgw3.law.pace.edu/cases/991021f1.html>
International Chamber of Commerce International Court of Arbitration (ICC)
ICC XY International, Inc. v. Société Z (ICC), reprinted in
1997(2) ASA Bull. 363
96
ICC Case No.10032 ICC Case No. 10032 of November 1999 (Nos. 82–84)
Memorandum for CLAIMANT
XIII
ICC Award No.6228 ICC Award No.6228 (1990), ICC BULLETIN, Vol.8,
No.1
ICC Case No. 7197 ICC Arbitration Case No. 7197/1992
ICC Case No. 6784 ICC Case No. Veeder 1 (1997): 53
ICC Case No. 7074
ICC 8324/1995
ICC Case No. 7074 of 1996, published extracts in 8 ICC
Arb. Bull. 61 (No. 1, 1997)
ICC 8324/1995, published on the Internet at
http://www.unilex.info
Ad hoc Tribunal
Vekoma v Maran Coal Transport- en Handelsmaatschappij 'Vekoma' B.V. V.
Maran Coal Corporation, judgment of 17 August 1995,
ASA Bulletin 1996, 673
Memorandum for CLAIMANT
1
STATEMENT OF FACTS
1. The Parties to this dispute are Wright Ltd (“Wright”), the CLAIMANT, which is a highly-specialized
manufacturer of fan‐blades for jet engines in Equatoriana, and SantosD KG (“SantosD”), the
RESPONDENT, which is a medium sized manufacturer of jet engines from Mediterraneo. Both
CLAIMANT and RESPONDENT were subsidiaries of Engineering International SA (“Engineering”), a
company based in Oceania, operating in the engineering industry, more particularly in turbines. The
contractual relationship between the Parties dates back to two contracts, in 2003 and 2005, respectively.
Engineering International SA sold CLAIMANT on 1 August 2010 to Skymover, which later became
Wright Holding PLC, and RESPONDENT to SpeedRun, a Private Equity Fund on 3 August 2010. Wright
Holding PLC owns 88 % of CLAIMANT’s shares.
2. In 2010 CLAIMANT and RESPONDENT were in negotiations to jointly “develop” a new fan blade for
the next generation of RESPONDENT’s high‐spec jet engine, JE 76/TL14b. The fan blade was to be
based on CLAIMANT’s newest model of swept fan blade. The improved fan blade – TRF 192‐I, was
supposed to lead to a considerable noise reduction in RESPONDENT’s new engine. The improved fan
blade was to be developed jointly under the technical leadership of CLAIMANT.
3. RESPONDENT agreed to buy at least 2,000 of the swept fan blades in the first year, but the final
development and production costs for the new blades was not yet certain. RESPONDENT insisted on
fixing a maximum price to be paid, in order for it to be able to offer itself a price for the engine to Earhart
SP (“Earhart”), and parties agreed on a flexible price structure for the fan blade.
4. According to the Development and Sales Agreement (“DSA”) of 1 August 2010 RESPONDENT ordered
2,000 swept fan blades for a price per blade ranging between USD 9,975 to USD 13,125 based on an
estimate by CLAIMANT about the likely cost per blade to which a certain profit was to be added.
CLAIMANT estimated that the production costs per blade would be around EQD (Equatorianian Denars)
20,000 and in USD around USD 10,000. The exchange rate had largely remained the same for the last
three years fluctuating between USD 1 = EQD 2.00 and USD 1 = EQD 2.02.
5. At the same time, RESPONDENT had intended to purchase the same number of clamps from another
producer. Following the conclusion of the DSA, and in particular when it turned out that those clamps
from the other producer were not suitable, it became clear that RESPONDENT would have to purchase
the clamps from CLAIMANT.
6. Accordingly, an Addendum was added to the contract and signed by the parties on 26 October 2010. In the
Addendum the parties agreed that the price for the clamps would be calculated on a cost coverage basis.
Moreover, because of RESPONDENT’s insistence and deviation from the rules applicable to the price
calculation for the fan blades, the parties agreed on a fixed exchange rate for the cost of the clamps.
Memorandum for CLAIMANT
2
7. CLAIMANT delivered the fan blades and the clamps on 14 January 2015 to RESPONDENT as per
contract and attached invoices for both goods. RESPONDENT accepted delivery and after inspection
confirmed that the swept fan blades – model TRF 192‐I, and the clamps were in conformity with the
contract.
8. Due to a mistake by CLAIMANT’s accounting department, the invoice for the fan blades attached during
delivery was inaccurate. Instead of the due amount of USD 22,723,800 under Section 4 of the DSA, the
invoice was only for USD 20,438,560. Mr. Lee, the person responsible for creating the invoice, had first
prepared the invoice for the clamps using the fixed exchange rate as under the addendum. When he then
prepared the invoice for the fan blades, he applied the same fixed exchange rate, overlooking that for the
price calculation for the fan blades the current exchange rate was to be applied.
9. RESPONDENT paid the amount invoiced and informed CLAIMANT about the payments made. On 15
January 2015, Mr. Cyril Lindbergh, RESPONDENT’s Chief Financial Officer, emailed Ms. Amelia
Beinhorn, the COO of CLAIMANT, that he had effected payment of USD 20,438,560 and USD
183,343.28 to the CLAIMANT’s account at the Equatoriana National Bank for the fan blades and clamps,
respectively.
10. Immediately after receiving the email, Ms. Beinhorn contacted Mr. Lindbergh to clarify the mistake and to
point out that on the basis of the formula agreed upon in the contract the costs per fan blade was USD
10,941.90, resulting in an overall purchase price of USD 22,723,800. RESPONDENT in computing the
price and making the transfer had applied the wrong exchange rate. It assumed that the fixed exchange rate
relevant for the clamps produced under the Addendum was also applicable to the fan blades. It is
uncontested that CLAIMANT incurred costs in the amount of EQD 19,586 per fan blade. Based on the
correct exchange rate at the time of production, the costs per blade in USD were 10,941.90 and not USD
9,744.28 as assumed by REPONDENT based on the wrong exchange rate also included in our invoice.
11. On 29 January 2015, USD 20,336,367.20 was credited to CLAIMANT’s account at the Equatoriana
National Bank. On 9 February 2015, Ms. Beinhorn notified Mr. Lindbergh via e-mail that CLAIMANT
was demanding the outstanding payment of USD 2,387,432.80 by 4 March 2015. However, in his reply
dated 10 February 2015, Mr. Lindbergh denied that any additional purchase price payment was due. He
reiterated RESPONDENT’S view, that the costs per fan blade was only USD 9,744.28 insisting again on
the application of the fixed exchange rate set out in the Addendum to the DSA, for converting the cost
incurred by CLAIMANT in EQD into USD.
12. Ms. Beinhorn’s inquiry with the Equatoriana National Bank revealed that the bank had investigated the
payment for money laundering under Regulation ML/2010C. A 0.5% levy was deducted from the
funds transferred by Respondent as per Section 12 of the Regulation.
Memorandum for CLAIMANT
3
13. In line with the requirements in Section 21, CLAIMANT tried to resolve the dispute amicably.
CLAIMANT made several offers combining a reduction in the sales prices for the 2,000 fan blades directly
covered by the DSA with a firm commitment for further fan blades to be delivered within the next five
years. RESPONDENT, however, insisted on a cost of USD 9,744.28 per fan blade. Mr. Lindbergh stated
that RESPONDENT was not aware of any reason why USD 102,192.80 had been deducted from the USD
20,438,560 they had transferred.
14. CLAIMANT submitted its Request for Arbitration at the Center for Arbitration and Mediation of the
Chamber of Commerce Brazil-Canada (“CAM-CCBC”) on 31 May 2016, requesting payment by
RESPONDENT under the Contract. RESPONDENT submitted his Answer to the Statement of Claim
on 24 June 2016.
Memorandum for CLAIMANT
4
SUMMARY OF THE ARGUMENTS
1. Claimant submits that its recourse to arbitration is allowed and that its claim is admissible. The
Request for Arbitration was filed within the sixty-day period. The ‘failure of negotiation’ did not
take place on 1st April 2016 contrary to Respondent’s assertion. The sixty-day time-bar under
Section 21 of the DSA applies specifically to the ‘initiation of arbitration’ and not to the
‘commencement of arbitration’ as defined under Article 4 of the CAM-CCBC Rules. Assuming
arguendo that the time-bar clause requires ‘commencement’ within sixty-days from the failure of
negotiations, Claimant’s request still constitutes a valid commencement of arbitration because the
failure of negotiations occurred on 31 May 2016.
2. Furthermore, Respondent’s request for security for costs should be dismissed. Art. 8 of the
CAM-CCBC Rules provides that “[u]nless the parties have otherwise agreed, the Arbitral
Tribunal can grant provisional measures, both injunctive and anticipatory” in accordance with
international arbitration. Claimant does not suffer from an inability to satisfy an adverse order for
costs, or a lack of resources against which such an order could be enforced. The balance of
convenience is in favour of the Claimant as its claims have been made in good faith and prima
facie have merit.
3. Claimant is entitled to USD 2,285,240 for the blades under the current exchange rate. According
to Art. 8 (1) and (2) CISG, Claimant maintains that during negotiations for the DSA, the parties
agreed on a ‘cost + basis’ or a cost plus profit price scheme in Section 4 DSA, where they fixed the
minimum and maximum price in USD. Despite the parties’ agreement on payment in USD,
Claimant was supposed to receive the respective equivalent amount in EQD upon payment.
Concomitantly, the cost of USD 102,192.80 is to be borne by Respondent.
4. The Addendum did not modify the main Agreement, as the intention of the parties was clearly
not to alter the DSA provisions. Claimant was made to believe that the Addendum’s purpose was
limited to the sale of clamps. Based on Arts. 4.1 and 4.2 UNIDROIT mirroring Art. 8 (1) & (2)
CISG on contractual interpretation, Respondent’s concealed intention to fix the exchange rate
cannot be considered. Applying the contra-preferentum rule, uncertainty in the interpretation must
be resolved in the Claimant’s favour.
5. Last but not least, Claimant requests USD 102,192.80 for the fees deducted by the Equatoriana
Central Bank. According to Arts. 53 and 54 CISG, Claimant is entitled to the full price of
payment under the DSA, whereas Respondent must take all steps in complying with such
formalities as may be required under the contract or any laws so as to effect payment.
Accordingly, the levy under Regulation ML/2010C is a bank charge contemplated under the
DSA.
Memorandum for CLAIMANT
5
ARGUMENTS ON THE PROCEDURAL ISSUES
I. THE CLAIMANT’S CLAIMS ARE ADMISSIBLE.
1. The Respondent has raised an objection to the admissibility of the claims, on the ground that
they have been submitted beyond the time limit provided under Section 21 of the DSA [Ans.
Resp. p. 26, para. 11-15]. This objection should be rejected, as: Firstly, the claims were made within
the sixty-day period, as the ‘failure of negotiation’ did not take place on 1st April 2016, contrary to
the Respondent’s assertion (1). Secondly, the sixty-day time bar under Section 21 of the DSA
applies not to ‘commencement of arbitration’ as defined under Article 4 of the CAM-CCBC
Rules, but instead to ‘initiation of arbitration.’ Through its request for arbitration dated 31st May
2016, the Claimant initiated arbitration within time, whether or not it commenced arbitration
under Article 4.1 of the CAM-CCBC Rules (2). Finally, assuming arguendo that the time-bar
clause required ‘commencement’ under CAM-CCBC Rules within sixty-days, the Claimant’s 31st
May 2016 request was a valid commencement of arbitration (3).
1. ‘Failure of negotiation’ did not take place on 1st April 2016, therefore, claims are
admissible.
2. Section 21 of the DSA provides that “each party has the right to initiate arbitration proceedings
within sixty days after the failure of the negotiation”. The application of this provision depends
on when the Tribunal deems the “failure of negotiation” to have taken place. In making this
determination, the Tribunal must resolve issues of interpretation in favour of restricting the
application of the time-bar provision (1.1). In line with this approach, the Tribunal must hold
that either: (a) ‘failure of the negotiation’ did not take place until the filing of request for
arbitration, as there was no express foreclosure of negotiations or ‘failure of the negotiation’, nor
was there any mutual agreement to that effect (1.2); or (b) ‘failure of the negotiation’ did not take
place when Claimant sent the email on 1st April 2016, but took place when it became clear that
the Respondent would not reply to the said email (1.31.2). In both cases, the effect would be that
the claims are admissible, irrespective of the date of commencement of arbitration.
1.1. Ambiguity in the time-bar clause must be resolved in favour of restrictive
application.
3. Contractual provisions that serve the limited purpose of restricting a party’s rights under the
contract should be interpreted narrowly [Nobahar-Cookson & Ors v The Hut Group Ltd]. This is
especially true for time-bar clauses [The Starsin, para.144; The Sabrewing, para 16,17]. The High
Court of Justice in the United Kingdom (UK) has held that where a time-bar clause can be
applied in two alternate ways, the court should choose the application that extends the period of
Memorandum for CLAIMANT
6
limitation [2010 FOLIO, p. 849]. This decision was rendered in the context of an arbitration
agreement, which contained a time-bar clause.
4. In the present case, Section 21 of the DSA contains an exclusion clause or a time-bar clause. This
time bar clause states that right to initiate arbitration must be exercised within sixty-days of the
‘failure of the negotiation’. The clause does not define what this failure is, how it takes place or
when it takes place. There are arguably multiple answers to these questions. From amongst these
answers, the Tribunal must choose the ones that limit the effect of the time-bar.
5. Therefore, as long as the Tribunal finds that the interpretation proposed by the Claimant is
reasonable and is not against the terms or the contract, or the intent of the parties, the Tribunal
should adopt the same.
1.2. Claimant did not foreclose negotiation, or declare ‘failure of negotiation’
through the email dated 1st April 2016.
6. Due to the absence of guidance in the DSA as to when the deemed ‘failure of negotiation’ takes
place, the parties may validly have different understandings of the same. Since the interpretation
of this phrase affects the parties’ right to arbitration, an interpretation should be adopted which
makes the ‘failure of arbitration’ objectively determinable. This is in line with the argument
presented above (1.1).
7. Failure of negotiation cannot be objectively determined in the absence of an statement from one
of the parties that there has been a “failure of negotiation; or a clear mutual understanding
between the parties to that effect. This is the standard that the Tribunal should adopt. This view
is in line with decision of the Tribunal in the Vakoma v. Maran case, in which a similar arbitration
agreement was at issue [Vekoma v Maran Coal, p. 673]. The arbitration agreement in that case
provided that arbitration may be initiated within thirty days after the parties agreed that dispute
cannot be resolved through negotiation [Friedland, p. 112]. The Tribunal held that there must be
an unequivocal agreement between the parties that negotiations had failed, even though there
were clear circumstances from which a common understanding to this effect could have been
inferred [Friedland, p. 113].
8. In this case, through email dated 1st April 2016, the Claimant did not foreclose negotiations
between the parties. To the contrary it specifically stated that it “remain[ed] open for any
meaningful negotiations” [Ex. R.3, page 29]. The email even contemplated a future settlement,
stating that “from now on the costs incurred for [Claimant’s] lawyer must be part of any
settlement reached.” By stating that it had instructed its lawyer to prepare for initiation of
arbitration, the Claimant cannot be said to have barred the option of negotiation. Stating the
Memorandum for CLAIMANT
7
possibility of litigation is a legitimate and commonly used tool in negotiation. That ipso facto does
not indicate an unwillingness to negotiate.
9. Thus, objective ‘failure of negotiation’ did not take place prior to the Claimant’s request for
arbitration. As a result, the limitation period in Section 21 of the DSA was not triggered, making
the claims admissible.
1.3. Alternatively, negotiations failed not with the email dated 1st April 2016, but
with Respondent’s failure to reply to the same became apparent.
10. Under Section 21 of the DSA, the parties were obliged to amicably settle their disputes through
negotiations in good faith. The obligation of ‘good faith’ is an obligation of “faithfulness to
agreed common purpose and consistency with the justified expectations of the other party”
[Berkley C Villages v Pullen]. In the present case, the common purpose of the parties was to
solve their difference amicably through earnest negotiations, and to prevent disputes from
reaching the stage of arbitration.
11. The Respondent was not discharged from this obligation by Claimant’s email dated 1st April
2016. Through the email dated 1st April 2016, the Claimant stated that amicable settlement was
not “presently possible”, at that point in time. This presumption was based on the Respondent’s
inflexibility to the various offers that the Claimant made in the meeting on 31st March 2016 [Ex.
R3, page 29]. It was the obligation of the Respondent to reply to the said email at the very least,
since failure to do so is contrary to the common purpose of trying to prevent arbitration of the
differences. The Claimant would also be justified in expecting a reply to the said email, either
confirming that no settlement would be possible or indicating a basis for settlement.
12. The Claimant cannot be punished for relying on this expectation. Therefore, the Tribunal should
hold that the ‘failure of the negotiation’ took place when it became clear that no reply would be
forthcoming from the Respondent. It would be safe to assume that it took the Claimant at least
more than a week to become certain that the Respondent would not reply to the Claimant’s email
sent on 1st April 2016. On that basis, ‘failure of the negotiation’ would have taken place after 8th
April 2016, which would bring even the rectifications in the Request to Arbitration (done on 7th
June, 2016) within the sixty-day limitation period. Therefore, employing this approach, it can be
seen that the Claimant’s claims are not time-barred and are admissible.
2. In arguendo, the DSA does not apply the sixty-day time-bar to compliance with
technical requirement of the CAM-CCBC Rules.
13. Section 21 of the DSA reads, “each party has the right to initiate arbitration proceedings within
sixty days after the failure of the negotiation”. This clause does not refer to the ‘Commencement
Memorandum for CLAIMANT
8
of Arbitration’ as defined in Article 4 of the CAM-CCBC Rules. Therefore, the Tribunal cannot
apply the contractual time-bar to the concept of ‘commencement of arbitration’, particularly as it
is defined in the CAM-CCBC Rules. This is because there is no contractual language or intention
to that effect.
14. The ‘term’ initiation should instead be interpreted to mean, the clear notification by any of the
parties of their intention to settle the dispute through arbitration. This is in line with the general
purpose of limitation clauses, which is to limit the time a party has to decide its course of action,
so that the counter-party can accordingly make its own decisions.
15. In the present case, the Claimant certainly ‘initiated’ arbitration within the sixty-day time period,
whether or not it ‘commenced arbitration’ under the CAM-CCBC Rules, as discussed in
argument (3.) hereinafter. Therefore, the claims are admissible.
3. In any case, arbitration commenced within the prescribed time as there was
substantial compliance with Article 4.1 of the CAM-CCBC Rules.
16. Assuming arguendo, that the sixty-day time limitation applied to ‘commencement of arbitration’,
the requirement was complied with as the ‘Request for Arbitration’ dated 31st May 2016 validly
‘commenced arbitration’. Here, the Claimant will show that under international practice,
‘commencement of arbitration’ is not delayed by technical defects, as long as there has been
substantial compliance with the requirements of the arbitration institutions (3.1). The Claimant
will then show that the defect relating to power of attorney in the Claimant’s request, was
technical in nature and did not affect the date on which the arbitration commenced (3.2). Finally,
the Claimant will show that the error in depositing inadequate Registration Fee does not form
part of the ‘Request for Arbitration’ and was in any case curable (3.3).
3.1. Arbitration commences where there is substantial compliance with technical
requirements.
17. The claims should not be held inadmissible on grounds of technical non-compliance with Article
4.1 of the CAM-CCBC Rules. In deciding the consequences of the defects in the notice to
commence arbitration, the “test should be whether the respondent is prejudiced other than
through losing the right to succeed on technical arguments” [Waincymer, p. 224]. The Tribunal
should not declare the claims inadmissible, unless due to the non-compliance the “[R]espondent
is truly unable to identify the nature of the claims” [Derains & Schwartz, p. 57].
18. The international practice is that where information has been given about the initiation of
arbitration, “non-fulfilment of additional requirements will not prevent the valid commencement
of an arbitration.” [Lew/Mistelis/Kroll, p. 519 ]. In ICC Case No. 6784, the Tribunal held that the
Memorandum for CLAIMANT
9
elements of the request for arbitration are pre-conditions to the admissibility of the Claims [ICC
Case No. 6784]. This is because the purpose of the concept of ‘commencement of arbitration’ is
to determine when the Claimant clearly notified the other party or arbitral institution, of its
intention to arbitrate the matter.
19. In the present case, the Claimant’s notice to CAM-CCBC served the purpose of announcing the
Claimant’s intent to invoke arbitration, and the nature and basis of its claim. No prejudice was
caused to the Respondent because of the defective power of attorney, or the deficient
Registration Fee, both of which have been additionally dealt with below. Therefore, in view of
substantial compliance with Article 4.1 of the CAM-CCBC Rules, the date of commencement is
31st May.
3.2. Defect relating to power attorney was technical and curable.
20. Power of attorney is “an instrument granting someone authority to act as agent or attorney-in-
fact for the grantor” [Black’s Law Dictionary, p. 1290]. Power of attorneys are submitted to
arbitration institutions to show that a representative is acting on the instructions of a party. For
this reason, some arbitration tribunals and institutions, including the ICC, do not require the
submission of a power of attorney at the time of commencement of arbitration [ICC Rules on
Arbitration, Art.4]. In fact, the Arbitral Tribunal in ICC Case No. 6228 held that a request for
arbitration need even be signed for it validly commence arbitration [ICC Award No. 6228]
Therefore, it is reasonable to say that Article 4.1 of the CAM-CCBC Rules requires the
submission of a Power of Attorney, not as a precondition to the admissibility of claims, but as a
formality for determining the authority of the person acting on behalf of the Claimant.
21. The power of attorney first submitted to CAM-CCBC was defective so far as it was not from the
Claimant (Wright Ltd), but from Claimant’s parent company (Wright Holding PLC). However, it
nonetheless established that in commencing the arbitration Mr. Horace Fasttrack had not acted
without proper instruction. The Claimant thereafter ratified the commencement of arbitration, by
providing Mr. Fasttrack an appropriate power of attorney, which the Claimant was entitled to do
under Article 2.2.9 of the UNIDROIT Principles. The effect of this ratification is that Mr.
Fasttrack will be deemed to have commenced the arbitration with proper authority. This
retrospectively removes any defect in the Request for Arbitration filed on 31st May, 2016.
22. Therefore, the 31st May 2016 ‘commencement of arbitration’ is not affected by the originally
defective power of attorney, and the claims are therefore within time.
Memorandum for CLAIMANT
10
3.3. Non-payment of Registration Fee does not affect ‘commencement’ of arbitration
under Article 4.1 of the CAM-CCBC Rules.
23. Under Article 4 of the CAM-CCBC Rules, ‘commencement of the arbitration’ takes place when
the Claimant sends notice to CAM-CCBC of its claim, in accordance with Article 4.1. Under
Article 4.2, “[T]he party [commencing arbitration] will attach proof of payment of the Registration Fee together
with the notice”. Article 4.2 does not provide what the contents of the notice should be, but only
requires that ‘proof of payment’ be attached to the notice. The actual content of the ‘notice’ is
provided by Article 4.1. Thus, the Claimant’s failure to attach proof of full payment does not
impact the date of ‘commencement’ of arbitration.
24. This rationale is consistent with ICC practice relating to Article 4 of ICC Rules of Arbitration,
which is similar to Article 4 of the CAM-CCBC Rules. Article 4(3) of the ICC Rules provides the
information which forms part of the ‘request’ which commences arbitration; and Article 4(4)
provides that, “[t]ogether with the Request… the claimant shall make payment of the filing fee”. The ICC
Secretariat has always construed the requirements for a valid request under Article 4(3), without
regard to the receipt of any payment [Schwartz and Derains, p. 43].
25. Since, Registration Fee is not a part of the Notice/’Request for Arbitration’ which commences
arbitration, any deficiency in Registration Fee has no bearing on the admissibility of the claims in
the present case.
II. THE RESPONDENT’S REQUEST FOR SECURITY FOR COSTS SHOULD BE DISMISSED
26. The Respondent has requested the tribunal to order an interim measure, in the form of security
for costs from the Claimant [Request, page 46]. The Tribunal is a creature of Section 21 of the DSA
which provides that “[T]he arbitration shall be conducted under the Rules of the Centre for Arbitration and
Mediation of the Chamber of Commerce Brazil-Canada and in line with international arbitration practice”.
27. Under the CAM-CCBC Rules, Article 8 provides that “[u]nless the parties have otherwise agreed, the
Arbitral Tribunal can grant provisional measures, both injunctive and anticipatory.” However, the CAM-
CCBC Rules do not provide any guidance as to the scope and exercise of this power. In
accordance with the DSA, the Tribunal must therefore exercise the power ‘in line with
international arbitration’.
28. In accordance with the international arbitration practice, security for costs can be granted in rare
and exceptional cases, only on an assessment of certain special factors (1). Applying these criteria
to the present case, the Respondent’s application for security must be dismissed, since: Claimant
Memorandum for CLAIMANT
11
cannot pray for security of costs contrary to the implied agreement of the parties not to ask for
such security; and in view of its waiver of its right to ask for such security (2); the Respondent’s
application does not meet the threshold requirement of disclosing a fundamental change in the
circumstances of the Claimant after signing of the arbitration agreement and the terms of
reference (3); the Claimant did not suffer from an inability to satisfy an adverse order for costs,
or a lack of resources against which such an order could be enforced (4); The balance of
convenience is in favour of the Claimant as its claims have been made in good faith and prima
facie have merit (5).
1. Special considerations apply to grant of security for costs, in view of the measure’s
exceptional nature.
29. In international arbitration practice, security for costs is viewed as a special kind of interim
measure, which should only be granted in highly exceptional circumstance [ICC Case No. 10032,
p. 366]. Even the literature relating to international arbitration is unanimous on the point that
security for costs should be rarely be used and is to be generally avoided [Veeder]. The criteria that
usually applied to interim measures, are not to be similarly applied to security for costs
[Redfern/Hunter]. Security for costs is the only type of interim measure for which the Chartered
Institute of Arbitrators released a separate ‘Guidelines for Applications for Security for Costs’
[Chartered Institute of Arbitrators Guidelines on Applications for Security for Costs].
30. Thus, the Tribunal should approach the application for security of costs, with a general
disinclination to decide the same in favor of the Respondent. It should base its decision not on
the usual factors ordinarily considered for granting interim measures. Instead, its decision should
be based on the exceptional considerations hereinafter discussed, in line with international
practice.
2. The Respondent’s application for security for costs is precluded on grounds of
consent and delay.
31. The Tribunal must first consider, whether the parties have by expressly or impliedly agreed that
neither should apply for security of costs [Gary Soo, p. 25]. In the S.A. Coppee Lavalin N.V. v. Ken-
Ren Chemicals case, Lord Mustill stated that in deciding security for costs applications in
arbitration, “[t]he first step must therefore be to identify, so far as is possible, the kind of arbitral
procedure which the parties have envisaged” [Coppée Lavalin N.V. v. Ken-Ren Chemicals and
Fertilisers Ltd ]. In applying this approach, it is to be considered that parties to arbitrations rarely
expressly agree on details such as security for costs. Therefore, the appropriate application of the
Ken-Ren approach would be, as per the view of the Court of First Instance of Hong Kong – to
“consider the kind of arbitral process that the parties had contemplated and whether it was
Memorandum for CLAIMANT
12
inconsistent with that process to make an order for security” [China Shipping Co. v. Whistler
Charterers].
32. In this case, the parties have expressly contemplated and made provisions for costs in the Terms
of Reference [Terms of Reference, page 41]. They have agreed that: (a) Tribunal shall have the power
to award costs [Terms of Reference, page 43, clause 12.3] and, (b) that parties shall bear their own costs
for the duration of the arbitration proceedings [Terms of Reference, page 43, clause 12.4]. The parties
did not contemplate the provision of security for costs for either party. The parties’ intention was
for each party to bear the burden of its own costs only during the arbitration process. Ordering
the Claimant to provide security for costs would place an additional burden on the Claimant,
which would defeat the agreed process contemplated by the parties.
33. Moreover, the Respondent waived its right to pray for security of costs by making a delayed
application for the same [Waincymer, p. 650]. This view is supported by the Chartered Institute of
Arbitrator’s commentary on its ‘Guidelines for Applications for Security for Costs’, which
provides that such applications must be made at the first possible instance [Guidelines, 10].
34. In this case, the delay cannot be justified on the ground of subsequent new information. This is
because the supposedly new information does not prove a substantial deterioration of the
Claimant’s financial condition, or the Claimant’s inability to satisfy an award for costs.
3. The application must be dismissed since there has been no ‘fundamental change
in circumstances’.
35. In international arbitration practice, unless a party can show that there has been a ‘fundamental
change of circumstances’ in the financial position of the opposite party since the parties entered
into the arbitration agreement, applications for security for are not entertained [Weixia]. The
party requesting security for costs must prove the emergence of exceptional circumstances
warranting security, which did not earlier exist [ICC Case No. 10032]. The rationale for this
requirement is that a party should not be able to raise those facts as a defense, which it knew
when it entered into agreement with the counter-party [ICC Case No. 7074].
36. In this case, the Claimant’s audited accounts for the years 2009, 2010, and 2015, were publicly
available in April of the years 2010, 2011 and 2016 [PO 2, Page 58, Clarification 28]. This means
that the financial position of the Claimant was in public domain, at the time when DSA was first
signed on 1st August 2016, as well as when the parties signed the Terms of Reference of the
present arbitration on 22nd August 2016.
37. In view of the publicly accessible information, the Respondent must demonstrate that there has
been a fundamental deterioration in the financial position of the Claimant since the time when
Memorandum for CLAIMANT
13
the DSA was entered. The Respondent has failed to aver or demonstrate this. The correct
position is that there has been no fundamental change in the financial position of the Claimant
that warrants a consideration of the Respondent’s application [PO 2, Page 58].
38. The Respondent has pleaded that it has only recently learned that an arbitration award for USD
2,500,000 was passed against the Claimant in January 2016 [Request, page 46]. However, this
information does not indicate that the said award has fundamentally deteriorated the financial
condition of the Claimant, such that it will be unable to comply with adverse award for costs.
Additionally, the said award is yet to be enforced against the Claimant. It may not even impact
the financials of the Claimant in any way, in view of the Claimant’s asserted set-off against the
award [Letter, page 49].
39. Therefore, since the Respondent has failed to show fundamental deterioration in the financial
condition of the Claimant, its application for security of costs deserves to be dismissed without
further consideration.
4. Security of costs cannot be ordered as the Claimant does not suffer from an
inability to satisfy an award of costs, or an inadequacy of assets.
40. Security for costs can only be granted where the claimant is unable to satisfy an adverse award of
costs, and not where the respondent alleges an unwillingness to pay an adverse award of costs
(4.1). This inability to pay, and the lack of resources against which award may be enforced, must
be proven by the Respondent. The Respondent is required to show more than a mere probability
of inability to pay, by reference to a credible testimony from a source familiar with the Claimant’s
financial position. The information presented by the Respondent does not meet these
requirements and therefore the application must fail (4.2). Finally, the Claimant’s financial
statements indicate that there no irreparable harm will be caused to the Respondent if security for
costs is not granted. Therefore, in the absence of such harm, security for costs cannot be granted
(4.3)
4.1. Claimant’s inability to satisfy an adverse award for costs is relevant to deciding
the application, and not its alleged unwillingness.
41. The purpose of granting security for costs is to enable shifting of costs to take place from the
losing party to the winning party, at the conclusion of the arbitration [CIA Guidelines on
Applications for Security for Costs]. It is a measure to protect against the possibility of a party not
being able to recover the awarded costs of arbitration, due to a lack of resources of the opposite
party [Reid, p. 1427].
42. For this reason, the CIA Guidelines - which provide guidance on how to decide applications for
Memorandum for CLAIMANT
14
security for costs, in line with international practice – provide in Article 3 that a claimant’s ability
to satisfy an award, and availability of its assets for enforcement are relevant for deciding an
application for security for costs. The CIA Guidelines do not at any point consider the claimant’s
intention to comply with an adverse costs award as a relevant factor.
43. Thus, all averments relating to intent of the Claimant should be disregarded in determining this
issue. The only factor relevant is whether in light of the Claimant’s ability to pay, and availability
of its resources for enforcement, an order for security ought to be made.
4.2. Application cannot be decided in Respondent’s favour on the basis of the
information presented.
44. Since the Claimant asserts that the Respondent asserts that Claimant will be unable to pay costs
in the case of an adverse order, the burden of proving this assertion is on the Respondent. In
view of the exception nature of a measure granting security for costs, a high standard of proof is
required for the Tribunal to exercise its discretion in favour of the requesting party. In order to
succeed on its application for security for costs, the requesting party must satisfy the following
conditions: (a) “It must provide credible testimony from sources having knowledge of the
claimant's financial affairs, relevant and persuasive documents including, the annual accounts and
statutory returns of the claimant”; and (b) “[s]uch testimony must, by itself, give rise to a reason
to believe that the claimant will be unable to pay the respondent's costs if successful in the
defence; and (c) “[t]he respondent must demonstrate that the claimant will be unable to pay, not
a probability of the same”[Gu, 188; Needham, 122–129].
45. In this case, the Respondent’s request for security of costs is entirely based on conjecture and a
news article published in ‘Carioca Business News’ [Exhibit R6, page 47]. This news article is not a
credible testimony; is not from a source having knowledge of the Claimant’s financial affairs or
its financial documents; and fails to demonstrate with certainty that the Claimant will be unable
to pay the Respondent’s costs. Similarly, by stating that the Claimant has suffered an adverse
award of USD 2,500,000, the Respondent does not prove what he is required to.
46. Therefore, the Respondent’s application is insubstantial and hopelessly inadequate, and deserves
to be dismissed for want of proof or basis.
4.3. Claimant does not suffer from an inability to pay costs or lack of resources
against which an award may be enforced.
47. The Claimant’s financial statements for at least three years – 2009, 2010 and 2015, have been
publicly available. All three financial statements indicate that the Claimant’s total assets are far in
excess of its liabilities. The value of the Claimant’s assets far exceeds the Respondent’s arbitration
Memorandum for CLAIMANT
15
costs estimated at USD 200,000. Even accounting for a possible enforcement of the adverse
USD 2,500,000 award, the Claimant’s assets more than sufficient to secure the Respondent the
cost of arbitration. An award for costs will be enforceable in Equitoriana, jurisdiction of the
Claimant, since it is a signatory to the New York Convention 1958, and the Respondent does not
plead otherwise [PO2, page 60, clarification 35]. Thus, there is no harm that may result to the
Respondent, if the Tribunal does not order security for costs, which will not adequately be
repaired by an award for costs at a subsequent stage [CIA Guidelines on Applications for Interim
Measures, Art. 2(1)(iii)].
48. Therefore, since there no urgency for the grant of security for costs, the Respondent’s application
must be dismissed [ICSID Case No. ARB/12/18]. In view of the Claimant’s ability to satisfy an
adverse award for costs, there is no ground for the Tribunal to grant the Respondent’s
application.
5. It would be unfair to grant security for costs, as the claims have substance and
have been made in good faith.
49. A factor for consideration in determining applications for security of costs is the substance of the
claims advanced. The Tribunal must consider whether claims have been made in a good faith
[CIA Guidelines, 5- 6]. As noted in the Working Group Report “the idea of a guarantee for costs
being required was often associated with the claim being apparently frivolous” [Report – 9/502].
The suggested need to provide security for costs arises out of a policy goal to prevent frivolous
or nuisance litigation [Waincymer, page 641].
50. In this case, the Claimant’s claims are neither frivolous, nor made in bad faith. The claims, as
discussed in issues III. and IV. below, disclose genuine disputes between the parties relating to
law and facts. The claims advanced are substantial and are likely to succeed on merits. With
respect to issue III., it is to be seen that the Claimant’s case is supported by the literal text of the
Addendum and the DSA, as well as by clear conduct and intent of the parties. With respect to
issue IV., the default position of the law under CISG read with the UNIDROIT Principles,
makes the buyer (Respondent) liable for incurring all costs associated with transfer of full price to
the seller (Claimant). The contract too expressly provides that the Respondent is liable to bear
bank charges.
51. This shows that the Claimant has a strong prima facie case, and therefore the balance of
convenience lies in favor of not order the Claimant to provide security for costs.
Memorandum for CLAIMANT
16
CONCLUSION ON PROCEDURAL ISSUES
52. Claimant’s submission of the present dispute to arbitration is admissible since the ‘failure of
negotiation’ did not occur on 1st April 2016, contrary to Respondent’s assertion. We argue that
the sixty-day time-bar under Section 21 DSA applies not to ‘commencement of arbitration’ as
defined under Article 4 of the CAM-CCBC Rules, but, instead, to ‘initiation of arbitration’.
Therefore, Claimant has brought a valid arbitration commencement before the CAM-CCBC
Tribunal.
53. Respondent’s request for security for costs is unsound as it contravenes Art. 8 CAM-CCBC
Rules, which provides that “[u]nless the parties have otherwise agreed, the Arbitral Tribunal can
grant provisional measures, both injunctive and anticipatory.” Respondent has breached the
principle of good faith, whereas Claimant did not suffer from an inability to satisfy an adverse
order for costs, or a lack of resources against which such an order could be enforced.
***
ARGUMENTS ON THE MERITS
III. THE CLAIMANT IS ENTITLED TO USD 2,285,240 FOR THE FAN
BLADES BASED ON THE PRESENT EXCHANGE RATE
54. Claimant will establish that it is entitled to the amount of USD 2,285,240 as payment for the TRF
192-I fan blades purchased by the Respondent under the DSA. Claimant submits that the parties
agreed to the conversion of Claimant’s production cost on a flexible cost-plus basis under the
DSA (1.) The DSA must be interpreted in light of the parties’ common intention, which was not
to apply any fixed exchange rate to the total purchase price. (1.1) Furthermore, applying a fixed
exchange rate would be incompatible with the common intention of the parties to calculate price
on a cost-plus basis. (1.1A) Claimant also argues that there is no previous practice between the
parties relating to the application of a fixed exchange rate. (1.1B) In any case, the fixed exchange
rate could not be read into the DSA using the standards of a reasonable person (1.2) Lastly, the
Addendum did not alter or amend any terms of the DSA. (2.)
1. The parties agreed to the conversion of Claimant’s production cost on a
flexible ‘cost-plus basis’ under the DSA
55. The DSA is the parties’ agreement that deals with the terms of the sale of the two thousand
(2000) TRF 192-I swept fan blades. Under the DSA, the parties agreed that the purchase price is
calculated on a cost-plus basis in accordance with the formula set forth by the parties. In
negotiating the DSA, the parties did not fix any exchange rate for the conversion of Claimant’s
Memorandum for CLAIMANT
17
productions costs from EQD to USD. Claimant will show that there was a common intention
not to apply any fixed exchange rate to the DSA. (1.1) Alternatively, a reasonable person in
Claimant’s position would not read a fixed exchange rate into the DSA. (1.2)
1.1 The DSA must be interpreted through the parties’ common intention,
which was not to have any fixed exchange rate.
56. In Section 20 of the DSA, the parties agreed on the application of CISG, Article 8(1) of which
provides that “statements made by and other conduct are to be interpreted according to his
intent where the other party knew or could not have been unaware what that intent was.” “[I]t is .
. . undisputed that [Article 8 CISG] also regulates the interpretation of the contract.” [Schlechtriem/
Schwenzer].
57. Article 8 (1) of CISG “is built on the subjective approach” [J.O. Honald]. The parties’ intention
could be gleaned from “negotiations, established practices between the parties, usages, and any
subsequent conduct of the parties” [Article 8(3) CISG; See Art. 5:102 PECL]. In relation to this,
Article 4.1 of the UNIDROIT Principles, provides that the “contract shall be interpreted
according to the common intention of the parties”. Accordingly, the parties’ statements, conduct,
and consequently the provisions of the contract, should be interpreted according to the parties’
intention, which depends on, inter alia, their negotiations, practices, and usages. [See MCC-Marble
Ceramic Center, Inc. v. Ceramica Nuova D'Agostino].
58. Claimant maintains that during negotiations for the DSA, the parties did not intend to apply a
fixed exchange rate for the conversion of EQD to USD. The application of a fixed exchange rate
is incompatible with the common intention to calculate the purchase price on a cost-plus basis
under the DSA. (1.1A) Neither has there been previous practice between the parties as to the
application of a fixed exchange rate that would lead to a common intention of that sort. (1.1B)
1.1A fixed exchange rate is incompatible with the common intention to calculate
price on a ‘cost-plus basis’
59. As will be established by Claimant below, the parties intended to secure the Claimant's actual cost
plus profit subject to certain amount caps (a). Providing for a fixed exchange rate would defeat
the said intention. (b) Verily, a flexible exchange rate would not be incompatible with
Respondent’s concern for currency fluctuation concern considering that the parties provided for
a price upper limit in the DSA. (c)
(a) Parties intended to secure the Claimant’s actual cost plus profit
subject to certain amount caps
60. Respondent does not deny that during the negotiations the parties agreed that the production
costs for the fan blades would be incurred in EQD [Page 8, Notes, The Problem/Summary Notes of 1
Memorandum for CLAIMANT
18
May 2010]. Moreover, in its Answer, Respondent admitted that “…due to the uncertain costs for
the development of a new fan blade CLAIMANT could not submit to a fixed price yet. Finally,
an agreement was reached to agree on a price range with different costs and profit elements.”
61. The intention to calculate production costs in EQD was determined by the expenses Claimant
would suffer such as the cost of labour, which is paid in EQD [Request, page 7, para 22]. Claimant
intended to recover its full expenses and make some profit by way of the price per fan blade in
EQD. Respondent clearly understood this intention and did not object to it. [Ex. R5, page 31,
para 1] Therefore, the parties had agreed that final payment consists of two steps: first, Claimant
defines the price in EQD; and second, Respondent pays the equivalent price in USD.
62. Subsequently, the parties agreed on a ‘cost-plus basis’ price scheme in Section 4 of the DSA, in
which they fixed a minimum and maximum price in USD. [DSA, page 10] Since the Claimant
intended to cover all its expenses and make profit in EQD, despite the parties’ agreement for
payment in USD, the Claimant was supposed to receive the relevant equivalent payment in USD
at the time of payment.
63. As outlined by Brunno Zeller “[i]f a party knows or ought to know the intent of the other party,
Article 8(1) is applicable” [Zeller (2009)]. Considering that Respondent knew Claimant’s intention
to cover its production costs in EQD, the rule in Article 8(1) CISG clearly applies. Thus, it
should be stated that there was a common intention to secure Claimants actual costs plus profit
under Section 4 of the DSA.
(b) A fixed exchange rate would defeat the parties’ intention to secure
the Claimant’s actual cost plus profit
64. The Claimant’s intention to get the relevant equivalent of cost plus profit in USD, which was
clearly understood and recognized by the Respondent, excludes the possibility of finding that the
parties intended to fix a currency rate at the time of the conclusion of the contract.
65. Procedural Order No. 1 states that “[b]oth Parties agree that the cost statements in Equatorian
EQD which have been submitted by CLAIMANT and which formed the basis for both Parties’
cost submission are correct” [PO 1, page 52] Respondent in its Answer acknowledged that
“CLAIMANT’s production cost [per fan blade] amount to EQD 19,586” [Ibid].
66. If we multiply the actual cost of the fan blades in EQD and the number of fan blades ordered,
the total amount would be EQD 39,172,000 (EQD 19,586 x 2000 fan blades). It this amount that
Claimant intended to get and was recognized by the Respondent.
67. However, the Claimant only received EQD 36,585,022.40 (USD 20,438,560 x EQD 1.79 (the
current currency rate)). Thus, Respondent only paid EQD 18,292.51 per fan blade (EQD
36,585,022.40 / 2000 fan blades). It is clear from the foregoing computation that the application
Memorandum for CLAIMANT
19
of a fixed exchange rate contradicts the parties’ intention to cover Claimant’s actual costs under
the cost plus profit scheme.
(c) Flexible exchange rate not incompatible with Respondent’s
currency fluctuation concern in view of the price upper limit in
Section 4 of the DSA
68. In its Answer the Request for Arbitration, Respondent referred to a discussion in 2009 wherein
SantosD KG should be “de‐risked” through the reduction of currency risk in existing contracts.
In Respondent’s point of view, the de-risking also applied to its newly concluded contracts then.
[Answer, page 24, para 9]
69. Respondent’s view is untenable. In addressing the matter of de-risking, Respondent’s CEO
proposed two options: “EITHER agreeing on fixed exchange rates, where the contracts provide
for floating rates, OR by finding other hedging strategies which reduces [Respondent’s] exposure
to currency risks” [Ex. R1, page 27]. Thus, for future contracts, the Respondent was
recommended to fix the exchange rate or find other “hedging strategies”.
70. Ultimately, the Respondent, in its contract for TRF 192-I fan blades with Claimant, chose the
second option - “other hedging strategies.” Respondent adopted the maximum price condition in
Section 4 of the DSA under the cost plus basis method. Respondent did not incorporate another
de-risking measure such as a fixed exchange rate or the fixed-rate clause that it now forces on
Claimant.
1.1B. No previous practice between the parties relating to the application of a
fixed exchange rate.
71. Respondent alleges that in previous co‐operations parties did not explicitly regulate the exchange
rate because they were both subsidiaries of the same company [Answer, page 24, para 8]. Allegedly,
it was the exchange rate at the time of contracting that had been used for the conversion of the
cost elements, which was in favour of Respondent [Answer, page 24, para 10]. Respondent is, thus,
trying to prove the existence of previous practice between the parties by referring to an alleged
allocation of risk for currency exchange rate to the Claimant in two previous contracts.
72. Respondent’s contention is unmeritorious. Claimant invites the Tribunal’s attention to the
following factual circumstances:
73. First, Engineering International SA, as the parties’ parent company, had pursued a tax
optimization scheme. It wanted to obtain a more favorable tax regime in Mediterraneo by
applying the most profitable exchange rate for Respondent. Hence, the application of a fixed
exchange rate involving Respondent’s contracts depended on whether or not the fixed exchange
rate would be profitable for Engineering International SA.
Memorandum for CLAIMANT
20
74. Second, the fixed exchange rate clause in the two previous contracts (TRF-155-II and TRF-163-
I) was not negotiated between the parties. [PO2, par. 5, p. 54] In fact, in the TRF-163-I contract
there was no difference in the exchange rate. [Ibid.]
75. According to Article 9 of the CISG “the parties are bound by any usage to which they have
agreed and by any practices which they have established between themselves.” Article 8 (3) also
provides that previous practices can prove the parties’ intention. There is no definition of what
constitutes as “practices.” However, Ole Lando defines it as “previous conduct to a particular
transaction or a particular kind of transaction between the parties that may be regarded as a
common understanding” [Cf. Ole Lando (2000)].
76. Claimant submits that abovementioned circumstances could not have led to a ‘common
understanding’ to de-risk Respondent through allocation of currency risk to Claimant. Clearly,
the parties have never used the ‘fixed exchange rate’ as a method of risk allocation between
themselves. The primary reason for the application of the exchange rate at the time of agreement
was for the tax optimization of Engineering International SA and not to de-risk Respondent.
Since the application of the fixed exchange rate at the time of contract formation was a measure
of tax optimization, Respondent’s reference to the previous contracts as evidence of the parties’
intention to allocate the currency rate risk to Claimant is, therefore, irrelevant.
1.2. Additionally, and alternatively, the fixed exchange rate could not be read into the
DSA by a reasonable person
77. In case the Tribunal does not find a common intention of the parties to apply a flexible exchange
rate in the DSA, the Tribunal should employ an objective or reasonable interpretation [See case
ICC 8324/1995].
78. Thus, “[w]here it is not possible to use the subjective intent standard in article 8(1) to interpret a
party's statements or conduct, one must resort to ‘a more objective analysis’ as provided for by
article 8(2), which should allow the courts to determine ‘a presumptive’ or ‘normative’
intent.”[UNIDRTOIT Digest]. As stated in Article 8 (2) of the CISG “[s]tatements . . . or conduct
of a party are to be interpreted according to the understandings that a reasonable person of the
same kind as the other party would have had in same circumstances”. This provision refers to
the rule of interpretation according to the “objective meaning”.
79. Courts have found that absent any relevant circumstance or practice between the parties at the
time the conclusion of the contract, the buyer's intention to be bound as well as the precise terms
of the contract may be deduced from the buyer's statements and conduct according to the
understanding that a reasonable person of the same kind as the seller would have had in the same
circumstances [See CLOUT case No. 215; CLOUT case No. 877].
Memorandum for CLAIMANT
21
80. In rejecting a claim, the Russian Supreme Court held that “the change in the internal rate of a
national currency against US dollars is a party's domestic affair”. The risk of currency rate
flotation “passes at the time of the valid conclusion of the agreement” [Johan Erauw, p. 203-2015].
81. As a corporation engaged in international sales of goods, Respondent should have been aware of
the fluctuating currency rate. Yet, Respondent failed to negotiate a fixed-rate in the DSA. There
is no clause in the DSA that provides for a fixed exchange rate. As established earlier,
Respondent did not incorporate a “fixed-rate” clause but incorporated another “de-risk” measure
– the “maximum price” clause [Section 4 of the DSA, page 10].
82. The Respondent tries to brush off its fatal error on the matter by claiming that it “forgot to add
an express provision as to the exchange rate” [Answer, page 24] to the DSA. Considering
Respondent’s own actions or inaction, Claimant cannot be expected to not have any reasonable
expectations in applying a flexible exchange rate in determining the purchase price of the fan
blades. The application of a flexible exchange rate in computing the price for the fan blades
under the DSA is a reasonable act of supplying an appropriate term under the circumstances.
“Where the parties to a contract have not agreed with respect to a term which is important for a
determination of their rights and duties, a term which is appropriate in the circumstances shall be
supplied.” [Art. 4.8 UNIDROIT Principles] In view of the foregoing, the Tribunal should apply
“the rate at the time of payment and not at the time of billing.” [CRCICA Case No. 21/1990].
2. The Addendum did not alter or amend any terms of the DSA.
83. The Respondent has claimed that a fixed rate should be applied to the determination of the price
in the DSA, based on a clause contained in the Addendum. The Addendum was signed by the
parties on 26th October 2010 to enable sale of clamps to the Respondent.
84. The Claimant will show that the clause contained in the Addendum did not fix the exchange rate
for calculating the cost and price of the fan blades in the DSA. Firstly, in view of the Parties’
intentions, the Addendum cannot be held to have altered the terms of the DSA (2.1). Secondly,
even applying the ‘reasonable person’ standard to interpretation of the Addendum’s text and
circumstances shows that the fixed exchange rate clause was not to be applied to the main DSA
(2.2). Thirdly, lack of clarity relating to the fixed-rate clause must be resolved against the
Respondent, since the terms of the Addendum were supplied by it. Thus, it must be held that the
fixed-rate clause regulated only the sale of clamps (2.3).
Memorandum for CLAIMANT
22
2.1. There was no intent as to the rights and obligations under the main DSA.
85. In accordance with Article 8(1) of the CISG and Articles 4.1 and 4.2 of the UNIDROIT
Principles, the terms of the Addendum are to be interpreted in accordance with the intention of
the parties. In discerning this intent, the Tribunal must consider all relevant circumstances
including the negotiations between the parties [Article 8(3) of CISG]. The analogous Article 4.3
of the UNIDROIT Principles enumerates in greater detail these relevant circumstances and
mentions “the nature and purpose of the contract” as being one. In this case, the negotiations of
the parties and the nature and purpose of the Addendum, both prove that neither party intended
to alter or affect any of the terms, rights or obligations under the DSA, through the conclusion of
the Addendum (1.1A). The Claimant in fact clearly intended for the fixed-rate clause to only
apply to the sale of clamps, and the Addendum should be applied in line with this intent (1.1B).
2.1A Neither parties intended to modify the main DSA through the
Addendum.
86. When the Parties signed the DSA, the Respondent intended to purchase only fan blades from the
Claimant. After the Parties signed the DSA, on 21st October, 2010 the Respondent expressed its
intention to purchase clamps from the Claimant. The Respondent proposed that for ease of
transaction, the parties execute an Addendum to the DSA rather than creating a separate
contract. Through its email dated 22nd October 2010, the Respondent proposed the terms of the
Addendum. It was in this context that the Claimant accepted the proposed terms of the
Addendum, after which the Agreement was signed on 26th October 2016.
87. These circumstances show that in the context of their discussions relating to the Addendums,
neither party expressed any intention or desire to amend the obligations contained in the DSA.
Neither Party suggested that the Addendum should affect the sale of the fan blades in any way.
The only reference that was made to the DSA, was in the context of the ease, which the DSA
would provide as a document in conclusion of the agreement for sale. The Respondent made no
statement that it wished to fix the exchange rate for the main DSA as well.
88. Moreover, the purpose of the Addendum was plainly to provide for sale of clamps. In its email
dated 22nd October 2016, the Respondent stated that “the easiest way to regulate the purchase of
the clamps is to sign an addendum to our Development and Sales Agreement and not to enter
into a separate contract for the clamps.” This is the only statement made with respect to the
purpose of the Addendum, and in view of its purpose it cannot be interpreted as affecting or
altering the original DSA in any way.
Memorandum for CLAIMANT
23
2.1B The Claimant specifically intended for the fixed-rate clause to apply only
to sale of clamps.
89. The Claimant’s intent very clearly was for the fixed-rate clause to apply to the clamps only. Prior
to agreeing to the proposed terms of the Addendum, Mrs. Amelia Beinhorn specifically verified
whether the Claimant could agree to a fixed exchange rate for the clamps [Ex. C. 9, page 50]
which shows that the Claimant clearly understood the fixed-rate clause to apply only to the sale
of clamps. This intent is relevant for the interpretation of the fixed-rate clause because Article
8(1) instructs that statements and other conduct of a party are to be interpreted according to its
intent as long as the other party “knew or could not have been unaware” of that intent. The plain
language used in the CISG sets a mandate as to a party's subjective intent as long as its
counterparty was aware of that intent" [CLOUT case No. 222] or could not have been unaware of it
[CLOUT case No. 215].
90. The Respondent could not have been unaware of the intent of the Claimant. The Respondent
could not have concluded that the Claimant would implicitly agree, without negotiation, to
applying the fixed-rate clause to the sale of the fan blades. This is because applying the fixed-
exchange rate to the main DSA would have significant repercussions on the price of the main
DSA. A fixed-rate of conversion for fan blades would also have displaced the previous intention
of the parties, which was for the Claimant to receive its actual costs plus profit. In previous
negotiations relating to the conclusion of the DSA, the Claimant had accepted only the risk that
production costs might not be recoverable if they exceeded a particular threshold. Subject to this
risk, the Claimant was always intended to receive actual costs. The Claimant would not implicitly
accept the further risk of not recovering its costs in the event of unfavorable currency
fluctuation.
91. Thus, the Tribunal must hold that the fixed-rate clause does not apply to the sale of fan blades,
but only applies to the sale of clamps.
2.2. Applying the ‘reasonable interpretation’ test, the written terms show that the
fixed-rate clause was limited to the Addendum.
92. Article 8(2) of the CISG provides for an objective interpretation of a contract, where no
common intention is discernible. In such an interpretation, special importance is to be given to
its text of the agreement [CISG-AC Opinion no 3]. The parties’ intent is to be gathered and
understood from the terms of the agreement itself [Honnold, (1999)].
93. In textually interpreting a contract, the fundamental principle codified in Article 4.4 of the
UNIDROIT Principles needs to be applied. Article 4.4 provides that, “[T]erms and expressions
Memorandum for CLAIMANT
24
shall be interpreted in the light of the whole contract or statement in which they appear.” Thus,
the terms of the Addendum must be interpreted in the context of the whole document in which
they appear. By doing so, it becomes clear that the fixed-rate clause was to apply only to the
Addendum and not to the main DSA.
94. In this case, there are two agreements between the Parties, which are intentionally placed in a
single document – the main DSA for sale of fan blades and the Addendum for sale of clamps. In
the text of the DSA, as well as in the Addendum, whenever reference is made to the DSA, the
word “Agreement” (with capital ‘A’) has been used. Reference may be made to Section 2(3) of
the DSA, where the Respondent agreed to purchase “2,000 fan blades under this Agreement”. In
Section 20 of the DSA, the Parties provide that “[t]his Agreement” is to be governed by CISG
and the UNIDROIT Principles. Section 21 of the DSA is particularly important as it uses the
words “Agreement” and “agreement” both – in the first instance to refer to the DSA and in the
second instance to connote the ordinary meaning of the word. Thus, there is an established
usage/practice under Article 8(3), to the effect that references to the DSA in written contract are
to be made using the word “Agreement”. It is important (but not critical), to note that Mr. Cyril
Lindberg, who signed both the DSA and the Addendum on behalf of the Respondent, would
have been aware of this convention.
95. In the text of the Addendum as well, “Agreement” and “agreement” both have been used. The
second paragraph of the Addendum incorporates the terms of the DSA into the Addendum,
using the following words - “Other terms as per main Agreement”. Thus, agreement with a
capital ‘a’ was used to refer to the DSA, in line with the settled convention of the document. On
the other hand, the immediately following paragraph provides “The exchange rate for the
agreement is fixed to US$ 1= EQD 2.01.” In this clause, the Respondent has conspicuously
chosen to use the word “agreement” (with a small ‘a’). By using the word “agreement”, the clause
was clearly intended to apply to the Addendum, and not to the DSA, which has been constantly
referred to as “Agreement” in the DSA and the Addendum. It is axiomatic but important to
restate here that the Addendum is an agreement between the Parties, whatever name it may be
called by.
96. Thus, it is clear from an overall interpretation of the Addendum that the fixed-exchange rate
clause is only to be applied to the Addendum and not to the DSA. Since the fixed-rate clause
does not apply to the DSA, a flexible rate must be applied to the calculation of the costs in the
DSA. Consequently, the Claimant becomes entitled to amount claimed herein.
Memorandum for CLAIMANT
25
2.3. Applying the contra-preferentem rule, uncertainty in the interpretation and
application must be resolved in the Claimant’s favour.
97. Art. 4.6 UNIDROIT Principles provides that “if contract terms supplied by one party are
unclear, an interpretation against that party is preferred”. This principle is referred to as the
contra-proferentem rule. It is a general long-standing contractual interpretative technique that any
ambiguous rule is interpreted against the party that drafted it [ICC Case No. 8261; UK High Court
of Justice No. 2004 Folio 272]. This is because the party drafting any terms has the economic and
informational resources necessary to foresee and specify contingencies and, therefore to write the
terms to contain those risks.
98. In the present case, the terms of the Addendum were proposed by the Respondent through its
email dated 22nd August 2010 [Ex.R2, page 28]. The proposed terms were verbatim incorporated
into the Addendum. If the Respondent intended for the fixed-rate clause in the Addendum to
apply to the sale of fan blades under DSA, there was no difficulty in clarifying the text of the
Addendum to reflect that intention. However, instead of clearly specifying this result, the text of
the Addendum in fact appears to be designed to give the impression that the fixed-rate clause
does not apply to the main DSA. Thus, the fixed-rate clause was intentionally kept vague and
uncertain.
99. In this situation, the Respondent should be made to bear the consequence of the avoidable
uncertainty in the Addendum. The Tribunal should therefore adopt the interpretation that the
Addendum only governed the sale of clamps and the fixed rate clause does not affect the
obligations in the DSA.
IV. THE CLAIMANT IS ENTITLED TO USD 102,192.80 FOR THE FEES
DEDUCTED BY THE EQUATORIANA CENTRAL BANK.
100. This issue relates to the fees of USD 102,192.80 which was deducted from the partial payment
made by the Respondent to the Claimant. The Respondent has denied its obligation to pay the
Claimant this amount. The Claimant will herein show that it in accordance with Section 4(3) of
the DSA, it is the cost of USD 102,192.80 to be borne by Respondent and Claimant is entitled to
receive the same (1). Assuming arguendo, that the Respondent’s liability to pay this amount does
not arise under the DSA, it nonetheless arises under the substantive law (CISG and UNIDROIT
Principles) made applicable to the DSA (2). Accordingly, the Tribunal should hold that the
Claimant is entitled to recover the amount deducted by the Equatoriana Central Bank.
Memorandum for CLAIMANT
26
1. Respondent is liable to pay the levy under the DSA.
1.1 Bank charges are to be borne by the Respondent under Section 4(3) of the
DSA.
101. The parties agreed that Respondent would bear all the costs related to the transfer of money for
the payment of the goods under the contract. Section 4(3) of the DSA is clear that the “[t]he
bank charges for the transfer of the amount are to be borne by the BUYER.” [Exhibit C2, at 10].
It is an obligation that the parties expressly stated in their contract.
102. Parties have unlimited authority to regulate their relationship [Art.6 CISG; Magnus in Rabels
Zeitscrhrift, Vol. 3-4]. Hence, the fundamental rule is that contract stipulations are binding on the
parties [Magnus Zeitschrift, ibid]. According to Article 1.3 of the UNIDROIT Principles, “[a] contract
validly entered into is binding upon the parties”. This principle is also known as “pacta sunt servanta”
[UNIDROIT COMMENTARY], which means parties should comply with its contractual
obligations in good faith. Therefore, from the clear terms of Section 4(3) of the DSA,
Respondent is obliged to fulfil its duty to pay bank charges.
1.2 The levy under ML/2010C falls within the meaning of ‘bank charges’
103. Respondent argues that the levy under ML/2010C is not part of ordinary bank charges for
payments [Answer, p. 26, par. 18]. Claimant submits that the 0.5% levy under ML/2010C made by
the Equatoriana Central Bank on the amount transferred by Respondent is a bank charge
contemplated by the DSA.
104. “Bank charges” are those charges payable to the bank for services it supplied to the customer [See
Office of Fair Trading v. Abbey National PLC]. Bank charges may include those charges that are
levied on defined events or circumstances, and not merely a price or remuneration and not
payments in exchange for services. [See Macdonald, p. 994-997]
105. In this case, the levy made by the Central Bank was triggered by the Financial Investigation Unit’s
(FIU) investigation of Respondent’s fund transfer exceeding USD 2 million. The transfer of the
amount above the threshold triggered the imposition of the levy. The terms in the contract
should be interpreted so as to give effect to all of the terms rather than deprive some of them of
effect [Art. 4.5, UNIDROIT Principles; See Art. 5:106 PECL]. As such, the levy charge must be
borne by Respondent.
106. It must be emphasized that in two previous transactions, Claimant bore the levy charges due to
the fact that there was no contractual stipulation specifying who bears the bank transfer costs,
unlike in this case. [Problem, pp. 55-56, pars. 8-9.] In the present DSA, the parties clearly intended
Memorandum for CLAIMANT
27
for Respondent to bear the transaction costs. Section 4(3) of the DSA is clear that Respondent
should bear all transfer costs relating to the payment of the purchase price including the levy.
Respondent’s claim is baseless and cannot prevail over a clear contractual duty.
2. Respondent is liable to pay the levy under the general legal framework.
107. Article 53 of the CISG lays down the primary obligation of the buyer in an international sales
contract for the payment of the contract price [See Gabriel, p. 273]. “The buyer must pay the price
for the goods . . . as required by the contract and [the] Convention” [Art. 53 CISG]. It is generally
accepted that the UNIDROIT Principles of International Commercial Contracts are a “means of
interpreting and supplementing” the CISG (Art.7.1 and 7.2 CISG) [Eiselen, S., 323-370, fn. 180;
Preamble, CISG]. Also, as explicitly provided in Section 20 of the DSA as to the “CHOICE OF
LAW” agreed upon by the parties, the UNIDROIT Principles apply as to issues not dealt with by
the CISG.
108. Under Article 6.1.11 of the UNIDROIT Principles, the party required to perform an obligation
shall bear the costs of performance of that obligation [See Gabriel, p. 274]. Such costs may include
“transportation costs in delivering goods, bank commission in making a monetary transfer, fees
to be paid when applying for a permission, etc.” [Bonell UNIDROIT Principles Commentary, p. 305].
Respondent has the specific duty to pay bank charges involved in the transfer of funds for the
payment of the purchase price under the DSA. This duty is explicit in Section 4, par. 3 of the
DSA and there can be no other result than to effect full payment to Claimant by including
payment of transactional costs such as bank levy or charges.
2.1 Respondent has the obligation to take all necessary measures to effect full
payment to the Claimant under Art. 54 CISG
109. Assuming that the Tribunal finds that the levy imposed by the FIU under ML/2010C does not
fall under the term “bank charges”, Respondent is, nevertheless, required to perform enabling
steps to pay the full price to Claimant.
110. Art. 54 CISG states that the Buyer’s obligation to pay the price “includes taking such steps and
complying with such formalities as maybe required under the contract or any laws or regulations
to enable payment to be made.” Art. 54 deals with the Buyer’s obligation to comply with both
commercial and administrative requirements and formalities to enable payment.
111. Commercial requirements include the opening of letters of credit, posting security or
performance bonds, obtaining bank guarantees, or the acceptance of bills of exchange. [Osuna-
Gonzales, p. 302; Secretariat Commentary] Administrative requirements, on the other hand, involve
the buyer’s compliance with “a statute, or with a governmental or administrative ordinance, such
Memorandum for CLAIMANT
28
as applying for authorization to purchase foreign currency or transfer funds abroad.” [Osuna-
Gonzales, p. 304] There are instances, however, wherein the commercial requirements may
intersect with the administrative requirements to effect payment such as “the requirement of
exchange control regulations in force in the country where the place of payment lies.” [Jahn, p.
15]
112. The buyer is obliged to comply with the foreign exchange regulations that govern the country
where it must transfer the funds so as to effect payment. The buyer assumes the obligation to
examine any laws and regulations pursuant to his transaction, either local or international, which
could affect payment [Maskow, pp. 394-200].
113. For both commercial and administrative requirements, the enabling steps “must . . . lead to a
seller being able to collect the amount that he is due, and in some cases, it should allow a seller to
collect even if the buyer defaults with his duty to effect payment directly.” [Osuna-Gonzales, p. 313]
There must be a good faith effort on the buyer’s part to satisfy the requirements of the contract.
[DiMatteo, p. 95] If the buyer merely sends instructions to the bank to transfer funds to the seller,
it fails to take all measures necessary to ensure payment is made to the seller [CLOUT Case No.
142]. What is important is that the enabling steps must lead to the seller obtaining payment for
the goods sold to the buyer [Dulces Luisi, S.A. de C.V. v. Seoul Int'l Co.]
114. In the present case, Respondent did not make any good faith effort to comply with its obligation
to pay the full purchase price to Claimant. The adoption of ML/2010C was reported by the press
in Mediterraneo [PO No. 2, para ]. Respondent, as buyer, had the duty to investigate what the
requirements for compliance with the Regulation were. Despite notice of the deduction of the
levy from the payment transferred [Claimant’s Exhibit C6, p. 15], Respondent still refused to
comply with its obligations to the detriment of the Claimant. 2. Clearly, Respondent has the
obligation to take all necessary measures to effect full payment to the Claimant.
2.2 Respondent did not discharge its obligation for payment when the Central
Bank deducted the 0.5% levy before the funds reached Claimant’s financial
institution.
115. Payment may be performed in any form as perceived in the ordinary course of business at the
place of payment such as cash, check, banker's draft, a bill of exchange, credit card or any other
form, entailing electronic means of payment [CLOUT Cases No. 142 & 236; Art. 6.1.7,
UNIDROIT Principles]. The methods of payment under the UNIDROIT Principles complement
the buyer's obligation to comply with the contractual requirements or formalities to enable
payment to be made Art. 54 CISG [Osuna-Gonzalez, at 299-323].
Memorandum for CLAIMANT
29
116. Article 6.1.8(2) UNIDROIT Principles provides that “[i]n case of payment by a transfer, the
obligation of the obligor is discharged when the transfer to the obligee’s financial institution
becomes effective.” A buyer is considered “discharged of his obligation” when the beneficiary's
bank accepts a payment order for the beneficiary. Otherwise, the buyer does not cease to be
legally liable [CLOUT Case No. 104].
117. Under the Equatoriana Central Bank’s banking mechanism, it is only after the FIU gives the
clearance for the transfer that the amount would be credited to the relevant bank account in the
respective commercial bank. Hence, in this case, the levy or bank charge was already imposed on
the funds transferred before it reached Claimant’s bank – the Equatoriana National Bank [PO No
2, page 56, para 10-11]; Exhibit C8]. It follows then that Respondent’s obligation to effect payment
was not discharged when an amount less than the agreed purchase amount was credited to
Claimant’s bank account.
118. Indeed, the buyer may be exempted from liability if it proves that the failure to perform was due
to an impediment beyond its control and that it could not have reasonably been expected to take
the impediment into account at the time of the conclusion of the contract or to have avoided or
overcome it or its consequences. [Art. 79(1) CISG] However, in the present case, Respondent
failed to show how the non-payment of the full purchase price to Claimant’s bank account due to
the imposition of the levy charge was beyond its control. A party cannot be exempted from
complying with its obligations for the sole reason that performance has become unforeseeably
more difficult [DiMatteo, p. 160]. It is arguable that the levy charge only made compliance with the
obligation difficult for Respondent; it did not render the obligation impossible.
CONCLUSION ON SUBSTANTIVE ISSUES
119. Claimant is entitled to USD 2,285,240 for the blades under the current exchange rate under the
DSA balance, where the parties agreed upon a cost plus basis price scheme fixing minimum and
maximum price in USD. Despite the parties’ agreement on payment in USD, Claimant was
supposed to receive the respective equivalent amount in EQD upon payment. Concomitantly,
the cost of USD 102,192.80 is to be borne by Respondent.
120. Claimant submits that the Addendum did not modify by any means the main Agreement (DSA).
Respondent’s concealed intent cannot be inferred, since Claimant was led to believe that the
Addendum’s limited purpose was for the sale of clamps. Since Respondent proposed the
Addendum, which was attached verbatim to the DSA, any issue of ambiguity is brought against
them, under the contra proferentem rule.
121. Last but not least, Claimant requests USD 102,192.80 for the fees deducted by the Equatoriana
Central bank. Arts. 53 and 54 CISG outline, inter alia, the obligations of the Buyer, who shall take
Memorandum for CLAIMANT
30
all steps in conformity with the duties they have undertaken. It flows artlessly that Respondent
must act accordingly so as to secure effective payment.
Memorandum for CLAIMANT
31
REQUEST FOR RELIEF
CLAIMANT respectfully requests the Tribunal find that:
1. Their request for Arbitration be admissible and in conformity with Art. 4 of the CAM-CCBC
Rules.
2. RESPONDENT’s request for security for costs be unsound and therefore ought to be
dismissed.
3. They are entitled to USD 2,285,240 for the blades under the current exchange rate.
4. The cost of USD 102,192.80 is to be borne by RESPONDENT.
5. The Addendum did not modify the main Agreement.
6. CLAIMANT is entitled to USD 102,192.80 as fees deducted by the Equatoriana Central
bank.
7. RESPONDENT shall bear the costs of the arbitral proceedings.
London, 8 December 2016
Counsel for CLAIMANT
Illia Chernohorenko Alexia-Nefeli Douma
_________________ _________________
Penka Kostova
_________________