    2 Weeks Rolling Schedule (Waterline)

    From 25 July 09 TO 07 August 09

    Total Qty

    Cum.

    Last

    Week

    Actual

    This

    Week

    Cum.

    Till

    Date

    Plan

    Next 2

    Weeks

    Start Finish

    18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7

    LINE 1,2,3 Pipe Wrapping 324 RM 120 120 240 84 14/07/09 30/07/09

    Trial Strip Excavation 324 RM 40 20 06/07/09 03/08/09

    Excavation to Formation Level 324 RM 12 48 14/07/09 04/08/09

    Pipe Laying and Bedding 324 RM 12 48 21/07/09 05/08/09

    Location Activity Description

    Quantity Schedule July August

  • 7/27/2019 Two Weeks Rolling Schedule

    2/12

    2 Weeks Rolling Schedule

    From 25 July 09 TO 07 August 09

    LINE 1,2,3 Pipe Wrapping

    Trial Strip Excavation

    Excavation to Formation Level

    Pipe Laying and Bedding

    Location Activity Description

    Date : 23 July 2009

    Only 60 running meter are handed over

    Only 60 running meter are handed over

    Only 60 running meter are handed over

  • 7/27/2019 Two Weeks Rolling Schedule

    3/12

    2 Weeks Rolling Schedule (Waterline)

    From 01 August 09 TO 14 August 09

    Total Qty

    Cum.

    Last

    Week

    Actual

    This

    Week

    Cum.

    Till

    Date

    Plan

    Next 2

    Weeks

    Start Finish

    25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14

    LINE 1,2,3 Pipe Wrapping 324 RM 240 60 300 24 14/07/09 06/08/09

    Trial Strip Excavation 324 RM 40 10 50 10 06/07/09 06/08/09

    Excavation to Formation Level 324 RM 12 6 18 42 14/07/09 08/08/09

    Pipe Laying and Bedding 324 RM 12 12 48 21/07/09 12/08/09

    Location Activity Description

    Quantity Schedule July August

  • 7/27/2019 Two Weeks Rolling Schedule

    4/12

    2 Weeks Rolling Schedule

    From 01 August 09 TO 14 August 09

    LINE 1,2,3 Pipe Wrapping

    Trial Strip Excavation

    Excavation to Formation Level

    Pipe Laying and Bedding

    Location Activity Description

    Date : 30 July 2009

    Only 60 running meter are handed over

    Only 60 running meter are handed over

    Only 60 running meter are handed over

  • 7/27/2019 Two Weeks Rolling Schedule

    5/12

    2 Weeks Rolling Schedule (Waterline)

    From 08 August 09 TO 21 August 09

    Total Qty

    Cum.

    Last

    Week

    Actual

    This

    Week

    Cum.

    Till

    Date

    Plan

    Next 2

    Weeks

    Start Finish

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21

    LINE 1,2,3 Pipe Wrapping 324 RM 300 24 324 14/07/09 04/08/09

    Trial Strip Excavation 324 RM 50 10 60 06/07/09 06/08/09

    Excavation to Formation Level 324 RM 18 14 32 28 14/07/09 13/08/09

    Pipe Laying and Bedding 324 RM 12 20 32 28 21/07/09 13/08/09

    Backfilling 324 RM 18 18 36 03/08/06 27/08/09

    Location Activity Description

    Quantity Schedule August

  • 7/27/2019 Two Weeks Rolling Schedule

    6/12

    2 Weeks Rolling Schedule

    From 08 August 09 TO 21 August 09

    LINE 1,2,3 Pipe Wrapping

    Trial Strip Excavation

    Excavation to Formation Level

    Pipe Laying and Bedding

    Backfilling

    Location Activity Description

    Date : 06 August 2009

    Completed 324 meters

    Completed 60 meters

    Only 60 running meter are handed over

    Only 60 running meter are handed over

    Only 60 running meter are handed over

  • 7/27/2019 Two Weeks Rolling Schedule

    7/12

    2 Weeks Rolling Schedule (Waterline)

    From 15 August 09 TO 28 August 09

    Total Qty

    Cum.

    Last

    Week

    Actual

    This

    Week

    Cum.

    Till

    Date

    Plan

    Next 2

    Weeks

    Start Finish

    8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28

    LINE 1,2,3 Pipe Wrapping 324 RM 324 324 14/07/09 04/08/09

    Near E14 Trial Strip Excavation 324 RM 60 60 06/07/09 06/08/09

    Excavation to Formation Level 324 RM 32 30 62 14/07/09 12/08/09

    Pipe Laying and Bedding 324 RM 32 28 60 21/07/09 13/08/09

    Backfilling 324 RM 18 12 30 30 03/08/06 27/08/09

    LINE 1,2,3 Pipe Wrapping 65 RM 65 15/08/09 17/08/09

    Near E12 Trial Strip Excavation 65 RM 20 17/08/09 07/09/09

    Excavation to Formation Level 65 RM 10 22/08/09 14/09/09

    LINE 15 Pipe Wrapping 56 RM 56 18/08/09 20/08/09

    Near E11 Trial Strip Excavation 56 RM 10 22/08/09 17/09/09

    Location Activity Description

    Quantity Schedule August

  • 7/27/2019 Two Weeks Rolling Schedule

    8/12

    2 Weeks Rolling Schedule

    From 15 August 09 TO 28 August 09

    LINE 1,2,3 Pipe Wrapping

    Near E14 Tria l Strip Excavation

    Excavation to Formation Level

    Pipe Laying and Bedding

    Backfilling

    LINE 1,2,3 Pipe Wrapping

    Near E12 Tria l Strip Excavation

    Excavation to Formation Level

    LINE 15 Pipe Wrapping

    Near E11 Tria l Strip Excavation

    Location Activity Description

    Date : 13 August 2009

    Completed 324 meters

    Completed 60 meters

    Completed 62 meters

    Completed 60 meters

    Only 60 running meter are handed over

    For 65m pipe length available

    For 65m pipe length available

    For 56m pipe length available

  • 7/27/2019 Two Weeks Rolling Schedule

    9/12

    2 Weeks Rolling Schedule (Waterline)

    From 22 August 09 TO 04 September 09

    Total Qty

    Cum.

    Last

    Week

    Actual

    This

    Week

    Cum.

    Till

    Date

    Plan

    Next 2

    Weeks

    Start Finish

    15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4

    LINE 1,2,3 Pipe Wrapping 324 RM 324 324 14/07/09 04/08/09

    Near E14 Trial Strip Excavation 324 RM 60 8 68 50 06/07/09 15/08/09

    Excavation to Formation Level 324 RM 62 6 68 50 14/07/09 27/08/09

    Pipe Laying and Bedding 324 RM 62 6 68 48 21/07/09 31/08/09

    Backfilling 324 RM 30 30 60 48 03/08/06 03/09/09

    LINE 1,2,3 Pipe Wrapping 65 RM 65 22/08/09 24/08/09

    Near Proposed Sewer MH 58 Trial Strip Excavation 65 RM 30 29/08/09 07/09/09 Subject to SSBD handover of site

    Excavation to Formation Level 65 RM 10 01/09/09 10/09/09 Subject to SSBD handover of site

    LINE 15 Pipe Wrapping 56 RM 56 18/08/09 20/08/09

    Near E11 Trial Strip Excavation 56 RM 30 29/08/09 17/09/09 Subject to SSBD handover of site

    Location Activity Description

    Quantity Schedule August September

  • 7/27/2019 Two Weeks Rolling Schedule

    10/12

    2 Weeks Rolling Schedule (Waterli

    From 22 August 09 TO 04 September 09

    LINE 1,2,3 Pipe Wrapping

    Near E14 Trial Strip Excavation

    Excavation to Formation Level

    Pipe Laying and Bedding

    Backfilling

    LINE 1,2,3 Pipe Wrapping

    Near Proposed Sewer MH 58 Trial Strip Excavation

    Excavation to Formation Level

    LINE 15 Pipe Wrapping

    Near E11 Trial Strip Excavation

    Location Activity Description

    Date : 20 August 2009

    Completed 324 meters

    Additional 50m will be handover

    Additional 50m will be handover

    Additional 50m will be handover

    Subject to SSBD handover of pipes

    For 65m pipe length available

    For 65m pipe length available

    Subject to SSBD handover of pipes

    For 56m pipe length available

  • 7/27/2019 Two Weeks Rolling Schedule

    11/12

    2 Weeks Rolling Schedule (Waterline)

    From 29 August 09 TO 11 September 09

    Total Qty

    Cum.

    Last

    Week

    Actual

    This

    Week

    Cum.

    Till

    Date

    Plan

    Next 2

    Weeks

    Start Finish

    22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11

    LINE 1,2,3 Pipe Wrapping 324 RM 324 324 14/07/09 04/08/09

    Near E14 Trial Strip Excavation 324 RM 68 39 107 30 06/07/09 31/08/09

    Excavation to Formation Level 324 RM 68 39 107 30 14/07/09 01/09/09

    Pipe Laying and Bedding 324 RM 68 36 104 30 21/07/09 03/09/09

    Backfilling 324 RM 60 15 75 48 03/08/06 17/09/09

    LINE 1,2,3 Pipe Wrapping 65 RM 65 29/08/09 31/08/09

    Near Proposed Sewer MH 58 Trial Strip Excavation 65 RM 30 05/09/09 14/09/09 Subject to SSBD handover of site

    Excavation to Formation Level 65 RM 10 01/09/09 17/09/09 Subject to SSBD handover of site

    LINE 15 Pipe Wrapping 56 RM 56 01/09/09 03/09/09

    Near E11 Trial Strip Excavation 56 RM 30 05/09/09 17/09/09 Subject to SSBD handover of site

    Location Activity Description

    Quantity Schedule August September

  • 7/27/2019 Two Weeks Rolling Schedule

    12/12

    2 Weeks Rolling Schedule (Waterli

    From 29 August 09 TO 11 September 09

    LINE 1,2,3 Pipe Wrapping

    Near E14 Trial Strip Excavation

    Excavation to Formation Level

    Pipe Laying and Bedding

    Backfilling

    LINE 1,2,3 Pipe Wrapping

    Near Proposed Sewer MH 58 Trial Strip Excavation

    Excavation to Formation Level

    LINE 15 Pipe Wrapping

    Near E11 Trial Strip Excavation

    Location Activity Description

    Date : 27 August 2009

    Completed 324 meters

    Subject to SSBD handover of pipes

    For 65m pipe length available

    For 65m pipe length available

    Subject to SSBD handover of pipes

    For 56m pipe length available