Upload
burerey
View
222
Download
0
Embed Size (px)
Citation preview
7/27/2019 Two Weeks Rolling Schedule
1/12
2 Weeks Rolling Schedule (Waterline)
From 25 July 09 TO 07 August 09
Total Qty
Cum.
Last
Week
Actual
This
Week
Cum.
Till
Date
Plan
Next 2
Weeks
Start Finish
18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7
LINE 1,2,3 Pipe Wrapping 324 RM 120 120 240 84 14/07/09 30/07/09
Trial Strip Excavation 324 RM 40 20 06/07/09 03/08/09
Excavation to Formation Level 324 RM 12 48 14/07/09 04/08/09
Pipe Laying and Bedding 324 RM 12 48 21/07/09 05/08/09
Location Activity Description
Quantity Schedule July August
7/27/2019 Two Weeks Rolling Schedule
2/12
2 Weeks Rolling Schedule
From 25 July 09 TO 07 August 09
LINE 1,2,3 Pipe Wrapping
Trial Strip Excavation
Excavation to Formation Level
Pipe Laying and Bedding
Location Activity Description
Date : 23 July 2009
Only 60 running meter are handed over
Only 60 running meter are handed over
Only 60 running meter are handed over
7/27/2019 Two Weeks Rolling Schedule
3/12
2 Weeks Rolling Schedule (Waterline)
From 01 August 09 TO 14 August 09
Total Qty
Cum.
Last
Week
Actual
This
Week
Cum.
Till
Date
Plan
Next 2
Weeks
Start Finish
25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14
LINE 1,2,3 Pipe Wrapping 324 RM 240 60 300 24 14/07/09 06/08/09
Trial Strip Excavation 324 RM 40 10 50 10 06/07/09 06/08/09
Excavation to Formation Level 324 RM 12 6 18 42 14/07/09 08/08/09
Pipe Laying and Bedding 324 RM 12 12 48 21/07/09 12/08/09
Location Activity Description
Quantity Schedule July August
7/27/2019 Two Weeks Rolling Schedule
4/12
2 Weeks Rolling Schedule
From 01 August 09 TO 14 August 09
LINE 1,2,3 Pipe Wrapping
Trial Strip Excavation
Excavation to Formation Level
Pipe Laying and Bedding
Location Activity Description
Date : 30 July 2009
Only 60 running meter are handed over
Only 60 running meter are handed over
Only 60 running meter are handed over
7/27/2019 Two Weeks Rolling Schedule
5/12
2 Weeks Rolling Schedule (Waterline)
From 08 August 09 TO 21 August 09
Total Qty
Cum.
Last
Week
Actual
This
Week
Cum.
Till
Date
Plan
Next 2
Weeks
Start Finish
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
LINE 1,2,3 Pipe Wrapping 324 RM 300 24 324 14/07/09 04/08/09
Trial Strip Excavation 324 RM 50 10 60 06/07/09 06/08/09
Excavation to Formation Level 324 RM 18 14 32 28 14/07/09 13/08/09
Pipe Laying and Bedding 324 RM 12 20 32 28 21/07/09 13/08/09
Backfilling 324 RM 18 18 36 03/08/06 27/08/09
Location Activity Description
Quantity Schedule August
7/27/2019 Two Weeks Rolling Schedule
6/12
2 Weeks Rolling Schedule
From 08 August 09 TO 21 August 09
LINE 1,2,3 Pipe Wrapping
Trial Strip Excavation
Excavation to Formation Level
Pipe Laying and Bedding
Backfilling
Location Activity Description
Date : 06 August 2009
Completed 324 meters
Completed 60 meters
Only 60 running meter are handed over
Only 60 running meter are handed over
Only 60 running meter are handed over
7/27/2019 Two Weeks Rolling Schedule
7/12
2 Weeks Rolling Schedule (Waterline)
From 15 August 09 TO 28 August 09
Total Qty
Cum.
Last
Week
Actual
This
Week
Cum.
Till
Date
Plan
Next 2
Weeks
Start Finish
8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
LINE 1,2,3 Pipe Wrapping 324 RM 324 324 14/07/09 04/08/09
Near E14 Trial Strip Excavation 324 RM 60 60 06/07/09 06/08/09
Excavation to Formation Level 324 RM 32 30 62 14/07/09 12/08/09
Pipe Laying and Bedding 324 RM 32 28 60 21/07/09 13/08/09
Backfilling 324 RM 18 12 30 30 03/08/06 27/08/09
LINE 1,2,3 Pipe Wrapping 65 RM 65 15/08/09 17/08/09
Near E12 Trial Strip Excavation 65 RM 20 17/08/09 07/09/09
Excavation to Formation Level 65 RM 10 22/08/09 14/09/09
LINE 15 Pipe Wrapping 56 RM 56 18/08/09 20/08/09
Near E11 Trial Strip Excavation 56 RM 10 22/08/09 17/09/09
Location Activity Description
Quantity Schedule August
7/27/2019 Two Weeks Rolling Schedule
8/12
2 Weeks Rolling Schedule
From 15 August 09 TO 28 August 09
LINE 1,2,3 Pipe Wrapping
Near E14 Tria l Strip Excavation
Excavation to Formation Level
Pipe Laying and Bedding
Backfilling
LINE 1,2,3 Pipe Wrapping
Near E12 Tria l Strip Excavation
Excavation to Formation Level
LINE 15 Pipe Wrapping
Near E11 Tria l Strip Excavation
Location Activity Description
Date : 13 August 2009
Completed 324 meters
Completed 60 meters
Completed 62 meters
Completed 60 meters
Only 60 running meter are handed over
For 65m pipe length available
For 65m pipe length available
For 56m pipe length available
7/27/2019 Two Weeks Rolling Schedule
9/12
2 Weeks Rolling Schedule (Waterline)
From 22 August 09 TO 04 September 09
Total Qty
Cum.
Last
Week
Actual
This
Week
Cum.
Till
Date
Plan
Next 2
Weeks
Start Finish
15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
LINE 1,2,3 Pipe Wrapping 324 RM 324 324 14/07/09 04/08/09
Near E14 Trial Strip Excavation 324 RM 60 8 68 50 06/07/09 15/08/09
Excavation to Formation Level 324 RM 62 6 68 50 14/07/09 27/08/09
Pipe Laying and Bedding 324 RM 62 6 68 48 21/07/09 31/08/09
Backfilling 324 RM 30 30 60 48 03/08/06 03/09/09
LINE 1,2,3 Pipe Wrapping 65 RM 65 22/08/09 24/08/09
Near Proposed Sewer MH 58 Trial Strip Excavation 65 RM 30 29/08/09 07/09/09 Subject to SSBD handover of site
Excavation to Formation Level 65 RM 10 01/09/09 10/09/09 Subject to SSBD handover of site
LINE 15 Pipe Wrapping 56 RM 56 18/08/09 20/08/09
Near E11 Trial Strip Excavation 56 RM 30 29/08/09 17/09/09 Subject to SSBD handover of site
Location Activity Description
Quantity Schedule August September
7/27/2019 Two Weeks Rolling Schedule
10/12
2 Weeks Rolling Schedule (Waterli
From 22 August 09 TO 04 September 09
LINE 1,2,3 Pipe Wrapping
Near E14 Trial Strip Excavation
Excavation to Formation Level
Pipe Laying and Bedding
Backfilling
LINE 1,2,3 Pipe Wrapping
Near Proposed Sewer MH 58 Trial Strip Excavation
Excavation to Formation Level
LINE 15 Pipe Wrapping
Near E11 Trial Strip Excavation
Location Activity Description
Date : 20 August 2009
Completed 324 meters
Additional 50m will be handover
Additional 50m will be handover
Additional 50m will be handover
Subject to SSBD handover of pipes
For 65m pipe length available
For 65m pipe length available
Subject to SSBD handover of pipes
For 56m pipe length available
7/27/2019 Two Weeks Rolling Schedule
11/12
2 Weeks Rolling Schedule (Waterline)
From 29 August 09 TO 11 September 09
Total Qty
Cum.
Last
Week
Actual
This
Week
Cum.
Till
Date
Plan
Next 2
Weeks
Start Finish
22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11
LINE 1,2,3 Pipe Wrapping 324 RM 324 324 14/07/09 04/08/09
Near E14 Trial Strip Excavation 324 RM 68 39 107 30 06/07/09 31/08/09
Excavation to Formation Level 324 RM 68 39 107 30 14/07/09 01/09/09
Pipe Laying and Bedding 324 RM 68 36 104 30 21/07/09 03/09/09
Backfilling 324 RM 60 15 75 48 03/08/06 17/09/09
LINE 1,2,3 Pipe Wrapping 65 RM 65 29/08/09 31/08/09
Near Proposed Sewer MH 58 Trial Strip Excavation 65 RM 30 05/09/09 14/09/09 Subject to SSBD handover of site
Excavation to Formation Level 65 RM 10 01/09/09 17/09/09 Subject to SSBD handover of site
LINE 15 Pipe Wrapping 56 RM 56 01/09/09 03/09/09
Near E11 Trial Strip Excavation 56 RM 30 05/09/09 17/09/09 Subject to SSBD handover of site
Location Activity Description
Quantity Schedule August September
7/27/2019 Two Weeks Rolling Schedule
12/12
2 Weeks Rolling Schedule (Waterli
From 29 August 09 TO 11 September 09
LINE 1,2,3 Pipe Wrapping
Near E14 Trial Strip Excavation
Excavation to Formation Level
Pipe Laying and Bedding
Backfilling
LINE 1,2,3 Pipe Wrapping
Near Proposed Sewer MH 58 Trial Strip Excavation
Excavation to Formation Level
LINE 15 Pipe Wrapping
Near E11 Trial Strip Excavation
Location Activity Description
Date : 27 August 2009
Completed 324 meters
Subject to SSBD handover of pipes
For 65m pipe length available
For 65m pipe length available
Subject to SSBD handover of pipes
For 56m pipe length available