77
SPEED POST ~mqw government of I ndia ~~~ Central Electricity Authority ~~~~ Western Regional Power Committee ~ -3, ~~ ~ 0lm't (~), ~ - 400 093 F-3, MIOe Area, Andheri (East), Mumbai - 400 093 ~ Phone: 022- 28221636; 28200194/95/96; ~ Fax: 022 - 28370193 Website: www.wrpc.gov.in E-mail: [email protected] ~ ~ .m g 9001-2008 ISO: 9001-2008 u gq~ 129cIT ~ ~I ~ ~/2015 - No. WRPC/29 th WRPC Mtg.lAS/20151 -$ 06' 7 "3 Date: -- w.rr ?[, fT 0, (~~cfi~) (As per enclosed list) ~ g m"'qlf ~ ~ ~ c£T 29 eft ~ c£T Gw.:f~~"1 Sub.: Agenda of the 29 th meeting of Western Regional Power Committee ~/Sir, ~ q;r cfi m~ 24 ~ 2015, 10:00 ~ c6r Aurangabad tr 0illilfV1~ ~ cmrIT m'q11 ~ ~ ~ c£T 29 eft ~ o;cf ~ ~ 23 ~ 2015, 10:00 ~ c6r 0i1'41fV1~ i'R cmrIT ~Gf)f.1cbl B~~FH ~ c£T ~ c£T Gf)14~~1~ ~I Please find enclosed herewith the Agenda of the 29 th meeting of Western Regional Power Committee to be held on 24th July 2015 at 10:00 hrs to be preceded by TCC meeting on 23 rd July 2014 at 10:00 hrs at Aurangabad for your needful. " ~Nours faithfully, (~ G: 2JGf)fll~1 S Taksande) ~ ~(m/Member Secretary Encl: As Above

u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

SPEED POST~mqw

government of India~~~

Central Electricity Authority~~~~

Western Regional Power Committee~ -3, ~~ ~ 0lm't (~), ~ - 400 093

F-3, MIOe Area, Andheri (East), Mumbai - 400 093~ Phone: 022- 28221636; 28200194/95/96; ~ Fax: 022 - 28370193

Website: www.wrpc.gov.in E-mail: [email protected]

~ ~ .m g 9001-2008ISO: 9001-2008

u gq~ 129cIT ~ ~I ~ ~/2015 -No. WRPC/29th WRPC Mtg.lAS/20151 -$ 06' 7 "3 Date:--w.rr ?[, fT 0,

(~~cfi~)(As per enclosed list)

~ g m"'qlf ~ ~ ~ c£T 29 eft ~ c£T Gw.:f~~"1Sub.: Agenda of the 29th meeting of Western Regional Power Committee

~/Sir,

~ q;r cfim~ 24 ~ 2015, 10:00 ~ c6r Aurangabad tr 0illilfV1~ ~ cmrIT m'q11 ~

~ ~ c£T 29 eft ~ o;cf ~ ~ 23 ~ 2015, 10:00 ~ c6r 0i1'41fV1~i'R cmrIT ~Gf)f.1cbl

B~~FH ~ c£T ~ c£T Gf)14~~1~ ~ I

Please find enclosed herewith the Agenda of the 29th meeting of Western Regional Power

Committee to be held on 24th July 2015 at 10:00 hrs to be preceded by TCC meeting on 23rd

July 2014 at 10:00 hrs at Aurangabad for your needful.

"~Nours faithfully,

(~ G: 2JGf)fll~1 S Taksande)

~ ~(m/Member Secretary

Encl: As Above

Page 2: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

2015-16

1 Chairman, WRPC/CSPCL, RAIPUR. 0755-27665872 Member (GO&D), CEA, New Delhi 011-261088343 Managing Director, CSPTCL,Raipur 0771-22411414 Managing Director, CSPDCL, Raipur. 0771-40665665 Managing Director, CSPGCL, Raipur. 0771-22417416 Chief Engineer (LD), SLDC, Raipur. 0771-25741747 Chairman, GSECL, Vadodara 0265-23402208 Managin Director, GSECL, Vadodara 0265-23447349 Managing Director, GETCO, Vadodara. 0265-2338152General 2337918

10 Managing Director,DAKSHIN Gujarat vij.companyLtd.Vadodara 0261-2574251

11 Chief Engineer (LD), SLDC, GETCO, Vadodara. 0265-2352019, 235646912 Managing Director, MPPTCL, Jabalpur 0761-266414113 Chairman & Managing Director, MPPGCL, Jabalpur. 0761-2665661

14 Chief Engineer-Commercial, Corporate office, MP PASCHIMKVVCom.Ltd, Indore. 0731-2423300

15 CE(LD), SLDC, MPPTCL, Jabalpur. 0761-2660015, 266434316 Chairman & Managing Director, MSETCL, Mumbai. 26595270 26595401 / 2659859517 Chairman & Managing Director, MSEGCL, Mumbai. 26471060, 2658140018 Chairman & Managing Director, MSEDCL, Mumbai. 2647867219 Chief Engineer (LD), SLDC, MSETCL, Kalwa. 2760176920 Chief Electrical Engineer, Electricity Dept., Goa 0832-242698621 Secretary(P), UT of Daman & Diu, Moti Daman. 0260-2230771,223008822 Secretary(P), UT of DNH, Silvassa. 0260-263022023 Director (Comml.), NTPC Ltd., New Delhi. 011-2436841724 Director (Operation), NPCIL, Mumbai. 25993318, 2599125825 Director (Operation), PGCIL, Gurgaon. 0124-257192226 Chief Executive Officer, NLDC, New Delhi. 011-2653690127 General Manager, POSOCO, WRLDC, Mumbai. 2820263028 Executive Director (O), Tata Power Company, Mumbai. 6665796629 Managing Director, RGPPL, Noida 0120-414891130 Chief Executive Director, NHDC Ltd, Bhopal. 0755-403000331 Executive Director, Torrent Power Generation, Surat 02621-66115132 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-2555717633 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-271918534 Director, Adani Enterprises.Ltd(Energy Trader),Ahmedabad35 CEO, Reliance Infrastructure Ltd, Borivali(W),Mumbai-9236 Director & CEO, JSW Energy Ltd.,New Delhi. 011-46032343/2618354637 Managing Director &CEO,Jindal Power Ltd.,Gurgaon. 011-2673915138 Excutive Directo & CEO,Coastal Gujarat Power Ltd,Kutch. 02838-66118138 Member Secretary, WRPC, Mumbai

List of members of WRPC

Page 3: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

List of members of TCC

1 Chairman, TCC & MANAGING DIRECTOR CSPGCL, RAIPUR0771-2241741

2 Chief Engineer (GM), CEA, New Delhi. 011-26109750

3 Chief Engineer(Comml.), CSPDCL, Raipur 0771-2574442

4 Executive Director(O&M:Gen), CSPGCL, Raipur 0771-2574425

5 Executive Director(Gen.), GSECL, Vadodara 0265-2338848

6 Superintending Engineer (R & C), GETCO, Vadodara. 0265-2353086 / 2337918

7 Chief Engineer(IT &C&R),Dakshin Guj.Vij.Co.Ltd,Surat. 0261-2574251

8 Executive Director (O&M-Gen), MPPGCL, Jabalpur. 0761-2664572

9Addl.C.E.(O),Corporate Office,MP PASCHIMKVVCom.L,Indore. 0731-2423300

10 Director(Operation),MSETCL,Mumbai. 26590383 / 26591254

11 Director (Operation), MSEGCL, Mumbai. 26478852

12 Director (Operation), MSEDCL, Mumbai. 26581465

13 Executive Engineer, DD, Nani Daman 0260-2250889

14 Executive Engineer, DNH, Silvassa 0260-2642338

15 Regional ED, NTPC Ltd., WRHQ-I, Mumbai. 28259364

16 Regional ED, NTPC Ltd., WRHQ-II, Raipur 0771- 2544550 / 2544513

17 Associated Director (Trans), NPCIL, Mumbai. 25991258/ 25563350

18 Executive Director, WRTS-I, PGCIL, Nagpur. 0712-2641471

19 Executive Director, WRTS-II, PGCIL, Vadodara. 0265-2488564

20 Vice President, Tata Power Company, Mumbai 66658012, 66687067

21 General Manager (Power), RGPPL, Ratnagiri 02359-241071

22 General Manager, ISP, NHDC Ltd, Indore 07323-284080

23 Executive Director (O&M), Torrent Power, Surat 02621-661151

24 Sr.VP(OTS) / AGM(BD), Adani P0wer Ltd., Ahmedabad 079-25557176

25 Sr.Vice President, ACB(India)Ltd., Gurgaon. 0124-2719185

26 Director, Adani Enterprises.Ltd(Energy Trader),Ahmedabad27 VP(O), Reliance Infrastructure Ltd, REMI,Andheri(E),Mumbai.28 Senior Vice President,JSW Energy Ltd., Ratnagiri, 02357-242508

29 President, Jindal Power Ltd., Chhattisgarh. 07767-281995.

30 Chief (O&M),Coastal Gujarat Power Ltd,Kutch. 02838-661181

1 CMD, MPPMCL Jabalpur. 0761-2664749, 2661245

2 Member (Power), NCA, Indore. 0731-2559888

Copy to1 Member Secretary, ERPC, Kolkata 033-24221802

2 Member Secretary, SRPC, Bengaluru 080-22259343

3 Member Secretary, NERPC, Shillong 0364-2520030

4 Member Secretary, NRPC, New Delhi 011-26868528, 26865206

Page 4: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

C O N T E N T S

ITEM NO. PARTICULARSPAGENO

ITEM NO.1CONFIRMATION OF THE MINUTES OF THE 28TH MEETING OF

WRP COMMITTEE 1

ITEM NO.2SYSTEM STRENGTHENING

3

ITEM NO.3UTILIZATION OF PUMPED STORAGE STATIONS IN PUMPING

MODE DURING OFF-PEAK HOURS6

ITEM NO.4

SCHEDULING OF SOLAR POWER THROUGH INTERSTATE

BILATERAL TRANSACTION 10

ITEM NO.5SCHEDULING OF 10 MW ALLOCATION OF POWER TO BARC

FACILITIES (TAPS 3 &4) FROM NPCIL TAPS 3&411

ITEM NO.6 FUNDING FROM PSDF 13

ITEM NO.7REVISION OF DSM ACCOUNTS AND PAYMENT OF INTEREST

THEREOF & STOA REVISIONS16

ITEM NO.8PROCUREMENT OF ERS SUBSTATION/SYSTEM OF

400/220/33KV19

ITEM NO.9A PROGRESS OF EMS / SCADA REPLACEMENT 20

ITEM NO.9B MASTER PLAN COMMUNICATION 21

ITEM NO.10UNIFIED REAL TIME DYNAMIC STATE MEASUREMENT

(URTDSM)22

ITEM NO.11TESTING OF SPS ENVISAGED FOR SR-NEW GRID

OPERATION AND 765 KV AGRA-GWALIOR LINES24

ITEM NO.12.1SPS FOR AGRA-GWALIOR – MOCK TESTING OF SPS

ENVISAGED FOR BACKING DOWN OF GENERATION IN WR26

ITEM NO.12.2 REVIEW OF SPS FOR CGPL MUNDRA 27

ITEM NO.12.3 ISLANDING SCHEMES FOR TAPS 1 & 2 AND TAPS 3 & 4 28

ITEM NO.13DEVIATION SETTLEMENT MECHANISM AND RELATEDMATTERS (FIRST AMENDMENT) REGULATIONS, 2014 DATED18TH DECEMBER’ 2014

29

ITEM NO.14 HON’BLE CERCS REGULATIONS 31

ITEM NO.15 READINESS OF SLDC AT GOA, OTHER SLDCS AND WRLDC 34

ITEM NO.16 DECLARATION OF TRANSMISSION ELEMENTS 35

Page 5: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

INTO COMMERCIAL OPERATION BY ISTS LICENCEES

ITEM NO.17 DECLARATION OF ISGS IN TO COMMERCIAL OPERATION 35

ITEM NO.18 GRANT OF MTOA AND LTOA BY POWERGRID 35

ITEM NO.19STATUS OF LETTER OF CREDIT(LC) OPENING AGAINST

DEVIATION CHARGES LIABILITY FOR 2015-1636

ITEM NO.20.1 STATUS OF DEVIATION CHARGES 37

ITEM NO.20.2 STATUS OF REACTIVE ENERGY CHARGES 38

ITEM NO.20.3 STATUS OF RECONCILIATION OF DEVIATION AND REC POOL

ACCOUNT FOR THE PERIOD JAN’15 TO MAR’1538

ITEM NO.20.4 INTEREST CALCULATION STATEMENT OF DEVIATION POOL

ACCOUNT FOR THE PERIOD FROM 1ST APR ’2015 TO 30TH

JUN’2015

39

ITEM NO.21PERFORMANCE OF WR GRID DURING FEBRUARY 2015 TO

JUNE 201541

ITEM NO.22

ANTICIPATED POWER SUPPLY POSITION IN WESTERN

REGION FOR THE PERIOD FROM JULY 2015 TO SEPTEMBER

2015

43

ITEM NO.23

STATUS OF COMPLETION OF 765/400 KV AND ABOVE ON

GOING TRANSMISSION SCHEMES BEING

EXECUTED/IMPLEMENTED BY TRANSMISSION AGENCIES

43

ITEM NO.24

STATUS OF COMPLETION OF 765/400 KV AND ABOVE ON

GOING TRANSMISSION SCHEMES BEING

EXECUTED/IMPLEMENTED BY TRANSMISSION AGENCIES

46

ITEM NO.25 WRPC MEMBERSHIP FOR RATTANINDIA POWER LIMITED 47

ITEM NO.26 ANY OTHER ITEM 48

ITEM NO.27 DATE AND VENUE OF NEXT WRPC MEETING 48

Page 6: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

ANNEXURES

ANNEXURE PARTICULARS

ANNEXURE -3REPORT ON PUMP MODE OPERATION OF KADANA HYDROUNITS

ANNEXURE - 15 STATUS OF PROGRESS OF SLDC’S & BACK-UP SLDC’S OF WRCONSTITUENTS /WRLDC

ANNEXURE. - 16 LIST OF TRANSMISSION ELEMENTS COMMISSIONED DURINGTHE PERIOD 08.01.2015 TO 06.05.2015

ANNEXURE - 18 THE LIST OF LTOAS/MTOAS RECEIVED FROM NLDC ANDAPPLICABLE FROM THE MONTH OF JUNE-15 FORCOMPUTATION OF RTA

ANNEXURE - 20DEVIATION CHARGES PAYABLE/RECEIVABLE BY WR ENTITIESTO WR DEVIATION POOL ACCOUNT FUND MAINTAINED BYWRLDC AS ON 07TH JULY 15

ANNEXURE – 20A PAYABLE/RECEIVABLE BY WR ENTITIES TO REACTIVE POOLACCOUNT FUND MAINTAINED BY WRLDC AS ON 07TH JULY ‘15

ANNEXURE-21.1(a) FREQUENCY PROFILE

ANNEXURE-21.1(b). DEMAND PROFILE

ANNEXURE- 21.2 VOLTAGE PROFILE

ANNEXURE-21.3 AULF STATUS

ANNEXURE-22 ANTICIPATED POWER SUPPLY POSITION

ANNEXURE- 25 WRPC MEMBERSHIP FOR RATTANINDIA POWER LTD.

************************

Page 7: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Baart sarkarGovernment of India

kond`Iya ivaVut p`aiQakrNaCentral Electricity Authority

piScama xao~Iya ivaVut saimaitWESTERN REGIONAL POWER COMMITTEE

p xao iva sa kI idnaaMk 23 jaulaa[- evaM 24 jaulaa[- 2015 kaoAurangabad maoM Aayaaoijat kI jaanaovaalaI

29 vaI baOzk kI kaya-saUcaI

AGENDA NOTES OF 29th MEETING OF WRPCTO BE HELD ON 23rd & 24th JULY 2015

AT

AURANGABADHosted by

NPCILmauMba[-

MUMBAI

Page 8: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad1

AGENDA NOTES FOR THE 29th MEETING OF WESTERN REGIONALPOWER COMMITTEE TO BE HELD ON 24TH JULY 2015 (FRIDAY)

PRECEDED BY TCC MEETING ON 23RD JULY 2015(THURSDAY) ATAURANGABAD (MAHARASHTRA)

ITEM No.1: CONFIRMATION OF THE MINUTES OF THE 28TH MEETING OFWRP COMMITTEE

The minutes of 28TH meeting of WRP Committee held on 4TH March 2015 at

Udaipur were forwarded to the members vide letter No. WRPC/28th WRPC

Mtg./AS/2015/3176 dated 07.04.2015. Following comments have been

received.

A. AGM(AM), PGCIL vide letter dated 15.05.2015 requested for following

corrigendum in para 8 of Item no.5 at Page 12 of the minutes of the 28th

meeting of WRPC:

QUOTE:

“GM-PGCIL(HO), informed that in Southern Region, PGCIL had utilized 400kV

ERS substation and charged 220 kV system in cyclone affected areas and

loads of 100-150 MW were restored. Hence he opined that 400 kV ERS

substation is essential.”

UNQUOTE:

He requested for following replacements in place of above para:

“GM-PGCIL(HO), informed that subsequent to cyclone Hud-Hud in Southern

region, SRPC during its 26th meeting on 20.12.2014 had approved

procurement of one set of 400/220/33kV ERS Substation.”

B. GM(OS & Comml), WR-1 HQ, Mumbai vide Email dated 18.06.2014requested for insertion of following lines on page no13 in Item No. 13,TCC discussions point no2, 8th line in the MoM of 28th WRPCmeeting.

Quote:

2) “TCC discussed the documentation required for COD as per contractualobligations and regulatory provisons, as different cases had to provide

Page 9: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad2

different sets of documentation. From this point of view of COD, forgenerators under the purview of Section 62 (where the tariff is approvedby a Regulator) the COD shall be as per the provisions of Terms andConditions of Tariff 2014-19, if CERC has determined the tariff. It wasnoted that this includes cases like NTPC generators and alsogenerators like Torrent Power whose tariff is determined by CERC. Iftariff is determined by State Regulator (under Section 62), thenwhatever conditions of COD are mentioned by the Regulator, the sameshall be complied with. If it is not explicitly mentioned in such cases, it issuggested that it should follow the COD norms as given Terms andConditions of Tariff 2014-19.”

Unquote:

After insertion of request made by NTPC, the above quoted lines becomes asfollows:

2) “TCC discussed the documentation required for COD as per contractual

obligations and regulatory provisons, as different cases had to provide

different sets of documentation. From this point of view of COD, for

generators under the purview of Section 62 (where the tariff is approved by

a Regulator) the COD shall be as per the provisions of Terms and

Conditions of Tariff 2014-19, if CERC has determined the tariff. It was

noted that this includes cases like NTPC generators and also generators

like Torrent Power whose tariff is determined by CERC. As per theprevailing Tariff Regulations the requisite certificate is to besubmitted by the company to the respective RPC and RLDC, andno other document is required to be submitted, as this provisionwould not be applicable for NTPC and to the Generators under theperview of section 62 of IE act 2013. If tariff is determined by State

Regulator (under Section 62), then whatever conditions of COD are

mentioned by the Regulator, the same shall be complied with. If it is not

explicitly mentioned in such cases, it is suggested that it should follow the

COD norms as given Terms and Conditions of Tariff 2014-19.”

No other comments have been received. Committee may discuss abovecomments and confirm the minutes accordingly.

Page 10: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad3

ITEM NO 2 : SYSTEM STRENGTHENING

2.1Conversion of fixed Reactor to switchable Reactor;

During 28th WRPC/TCC meeting, PGCIL had proposed that fixed Line

Reactors installed in following lines be converted to switchable Line Reactors

so that they could be utilised as Bus Reactors when line is out, which may be

required to maintain Voltage profile. The list of such lines with reactors that

require to be converted to switchable line reactors are at the following

locations :

Sr.

No.

Line Name Length

(CKm)

Capacity Switchable(S)/

Fixed(F)

%

compensation

End1 End2 End1 End2

1 Bina-

Shujalpur-I

199.936 63 50 S F 103

2 Bina-

Shujalpur-II

199.936 63 50 S F 103

3 Bhadravati-

Dhariwal

18 63 - F 636

During 28th WRPC/TCC, it was recommended to convert the above fixed line

reactors as switchable reactors without any system study.

PGCIL may update the status.

2.2 Extension on 220 kV Network at GIS Navi Mumbai station

During 28th WRPC/TCC meeting, Member Secretary WRPC informed that

POWERGRID had communicated that 400 kV GIS at Navi Mumbai is likely to

be commissioned by the end of May, 2015, as the cable laying works are in full

swing and shall be completed before March 15. Further they requested

MSETCL to extend 220 kV grid from Navi Mumbai GIS station to their load

centers.

Page 11: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad4

Accordingly MSETCL was requested to indicate the progress for installation of

220 kV line from GIS Navi Mumbai.

During TCC Director, MSETCL enquired about the status of the incoming

source of 400 kV Vapi-Navi Mumbai at Navi Mumbai station. It was informed

by GM – PGCIL(HO) that 400 kV Vapi-Navi Mumbai line is not coming, and

this was already reported at Standing Committee meetings. With the line not

coming to Navi Mumbai, Director MSETCL informed that the substation was

not beneficial to Maharashtra system, as there is no source of input power to

Maharashtra grid. Hence laying 220 kV network from MSETCL system to Navi

Mumbai would only mean unnecessary congestion in Maharashtra system and

only charging of substation at Navi Mumbai.

Further with respect to LILO of 400 kV Lonikhand-Kalwa MSETCL line at Navi

Mumbai. ED-WR1, PGCIL informed that the cable work is in advanced stages

of completion, and the same would be ready by May end along with the

substation.

Director, MSETCL requested for relocation of the asset to more useful place

for better utilization of the same as the existing asset is not serving any useful

purpose to Maharashtra system. GM – PGCIL(HO) informed that these

projects have been executed after due approvals from competent authorities.

Further progress and problems faced have been reported at SCM. At this

stage it is not possible for them to consider any relocation of asset.

During the 28th WRPC Meeting, Executive Director, MSETCL explained

Maharashtra’s position with respect to relocation of asset, as already given

above, and requested to take the matter to CEA before taking a decision.

AGM-PGCIL(HO) explained that the non availability of 400 kV Vapi-Navi

Mumbai was informed to SCM. However at that time Navi Mumbai was not

discussed for relocation. A decision to relocate Navi Mumbai could have been

taken at that time itself, in that case, before award of any contract. However

since the project has since been in advance stage of completion, at this stage

it was not acceptable to relocate.

Page 12: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad5

She pointed out that relocation of an asset is much more costly than

establishing a new asset. There are experiences of Sasaram HVDC being

thought of relocation but that was not feasible and given up. However it may be

beneficial to replan the network in that area, so that the asset can be utilized.

Hence the substation should be allowed to be charged.

Regarding the issue of charging of the substation, Director, MSETCL stated

that since the asset is not beneficial at all, charging would unnecessary

commercially burden the Maharashtra consumer with no benefits. This could

not be permitted. If however there is benefit after re planning, the issue of

charging can be thought of. Hence matter requires discussion with CEA.

AGM-PGCIL(HO) explained that non charging of PGCIL asset, when it has

been created after due approvals cannot be acceptable to PGCIL. PGCIL

requested that the station be allowed to charge. But this was not acceptable to

Maharashtra, as there is no benefit to their system.

During the 28th WRPC meeting Chairperson, WRPC suggested to take up the

issue with CEA by MSETCL and PGCIL with respect to utilization of the

substation as well as charging.

MSETCL and PGCIL may update the status.

2.3 220 kV Extension feeders at 765/400 kV/220 kV sub-station atAurangbad.

During 28th WRPC/TCC meeting, Member Secretary WRPC informed that

POWERGRID’s 765/400/220 kV sub-station at Aurangabad was

commissioned in January, 2014 and in operation from the above date. The ICT

765/400 kV and also 400/220 kV is not operating since the last one year.

Further, there is no 220 kV network to cater the load of Aurangabad sub-

station to nearby load centres.

MSETCL was requested to make the construction of 220 kV lines at the

earliest so that the load can be catered through POWERGRID’s sub-station at

Aurangabad to different load centres in Maharashtra.

Page 13: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad6

Director, MSETCL informed that 220 kV Chitegaon-Shendra evacuation line at

Aurangabad shall be completed in about six months time.

MSETCL May update the status.

2.4 Readiness of Kudus sub-station :

During 28th WRPC/TCC meeting, Member Secretary WRPC informed that

MSETCL is constructing Kudus sub-station near Padghe. POWERGRID’s 765

kV/400 kV GIS Padghe sub-station is likely to be commissioned in

May/June,2015. The 400 kV line from Powergrid Padghe GIS station is likely to

be completed by the end of May, 2015. In order to evacuate power from

POWERGRID sub-station, MSETCL has to be kept ready the Kudus station

by May, 2015.

Director MSETCL informed that outgoing feeders at Kudus along with Kudus

substation is expected to be completed in about one year time (by June 2016).

MSETCL May update the status.

ITEM NO 3 : UTILIZATION OF PUMPED STORAGE STATIONS INPUMPING MODE DURING OFF-PEAK HOURS

Background: With growing self-sufficiency in the Western Regional grid, the

peak energy shortage in WR have reduced. However, it is observed that the

difference between the demand met during off-peak and peak hours has

increased. On normal days the difference is around 12000 MW which may

further increase during inclement weather / exceptional days. In order to

ensure balance between load and generation, the generation is required to be

backed down during off-peak hours and picked up during peaking hours. With

the pressure to maintain uninterrupted power supply to the customers along

with rising penetration of Renewable Energy Sources in the Grid, the need for

flexible generation (load-following, fast ramp-down, fast ramping up) would

accentuate further. These emerging challenges in grid operation call for

enhancing the flexibility of existing fleet of conventional generation and also

Page 14: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad7

exploit the available facilities for energy storage and spinning reserve in the

form of Pumped Storage hydro stations.

Operation of available capacity of Pumped Storage hydro plants in pumping

mode would provide the following advantages as elaborated in the CBIP

Publication No. 265 titled “Pumped Storage in India” (Nov 1997):

a) Would enable storage of electrical energy into potential energy during

off-peak hours for utilization during peak hours

b) Provides a dynamic load during off-peak hours and thus helps in

reducing difference between Maximum and Minimum Load in the

system

c) Limits the quantum of variation in despatch schedule of thermal

stations, thus would help in enhancing efficiency of thermal stations

d) Would provide spinning reserve in the grid due to its flexibility to quickly

change over from motoring mode to generation mode

e) Would help in voltage and power factor correction

f) Improved System Reliability

The CEA report on “Large Scale Grid Integration of Renewable Energy

Sources- Way Forward” issued in November 2013 also emphasizes the need

for exploitation of pumped storage hydro stations. The report lists various

existing and envisaged PSP schemes in all the States.

The status of pumped storage hydro capacity in Western Region is as under:

Station Capacity State

PumpedStoragecommissioned

Capability ofworking inpumpingmode

Whether beingoperated inpumping mode

Availability ofTelemetry

1Paithon(Jayakwadi)

1x12 Maharashtra Yes Yes

No

No

2 Ujjaini 1x12 Maharashtra Yes Yes No

3 Bhivpuri 1x90 Maharashtra Yes No No

4 Bhira 1x150 Maharashtra Yes Yes No No

5 Ghatghar 2x125 Maharashtra Yes Yes Yes No

6 SardarSarovar 6x200 Gujarat No Tail race

reservoir No Yes

Page 15: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad8

Station Capacity State

PumpedStoragecommissioned

Capability ofworking inpumpingmode

Whether beingoperated inpumping mode

Availability ofTelemetry

(Garudeshwar) to becompleted :Target-18months

7 Kadana-I 2x60 Gujarat Yes Yes No No

8 Kadana-II 2x60 Gujarat Yes Yes No No

Envisaged PSP schemes:Maharashtra:Koyna left bank (2x40 MW), Malsej Ghat (700 MW) and Humbarli

400 MW)

Madhya Pradesh: Mara (1100 MW) and Binauda (2250 MW) : No information

from MP whether these project exist as indicated in 468th OCC.

Apart from utilization of the existing stations in pumping mode there is a need

to expedite the commissioning of envisaged PSP schemes in the region.

28th WRPC/TCC Discussion:

During the discussion, CE,SLDC,GETCO pointed out that they are following

the matter at Kadana HPS and vibration problems are being faced when the

same was operated earlier in PSP. The matter has been taken up with their

Genco. Also telemetry facility is available. They shall report the progress in

OCC.

The detailed report for exploration PSP of KHPS submitted by Gujarat is

attached at Annexure -3

In case of Bhivpuri, Head(PSCC),TPC pointed that they are not having

pumped storage. In case of Bhira, the plant operates for more than 10 hrs in

generator mode. Hence even if water is pumped back it can be utilised in off

peak hours only. There are commercial mechanisms also that requires to be

addressed. Also water levels are quite sufficient and they feel PSP at Bhira is

not needed..

Page 16: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad9

In case of Maharashtra, CE,SLDC,Kalwa informed that Paithon and Ghatghar

are being operated in Pumped storage mode. Regarding PSP at Ujni facility

exists, but due to commercial reasons it is not operated in PSP mode.

In case of SSP, Member, NCA informed that Garudeshwar reservoir is being

constructed in about 18 months time. With that the SSP RBPH machines can

be operated in Pumped storage mode. However this being a shared project,

the beneficiaries shall have to agree on the usage of pumped storage mode of

operation. Initially all had agreed for PSP operation, however MP later on

backed out due to commercial reasons. Presently in principle Gujarat has

agreed. But MP and Maharashtra have expressed certain reservations. These

matter is being discussed in NCA forum.

Director(Comml) MPPMCL informed that commercial problems are envisaged

due to PSP for which MP had backed out.

Director(Opn), MSEDCL informed that the commercial implications of PSP at

SSP is not known. Hence they cannot comment in this forum. However they

are willing to discuss the issue and have a relook on the situation, if need be.

MS WRPC pointed out that commercial aspects of pumping cannot be studied

in isolation, but also requires to be studied along with necessary DSM charges

paid by the utility at the time of pumping. It would certainly reduce the DSM

charges along with capping in off peak hours, nullifying the commercial impact

of pumping up the water. It may be even be economical to use PSP in off peak

hours. Hence commercial aspects of such operation should be studied

CE,SLDC GETCO stated that commercial issues and sharing of charges of

PSP in Gujarat Discoms were discussed internally and the mechansism of

how it could be shared may be also brought the notice of all when PSP is

studied in detail.

Page 17: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad10

Member Secretary, WRPC suggested that NCA may list all the difficulties

mentioned and bring out a White Paper and discuss the same in a separate

meeting. Similarly commercial aspects of PSP may also be discussed in that

meeting for all the above units with PSP feasibility.

Subsequently the matter was discussed in 56th PSC of NCA wherein it was

intimated by SSCAC that the probable completion date for work of

Garudeshwar reservoir is 03.11.2017 and PSS will be operational probably

in Janury-2018. It was agreed that a white paper on the PSS operation at

SSP will be finalised after taking into account various possible situations

which may arise in real time and will be discussed in the next PSC of

NCA. After incorporating the comments and view on the paper the same shall

be forwarded to WRPC.

NCA may update the status & Committee may discuss the same.

ITEM No.4: SCHEDULING OF SOLAR POWER THROUGH INTERSTATEBILATERAL TRANSACTION

4.1. Back ground: In the 69th CCM CE SLDC Gujarat had informed that the

Inter state bilateral transaction for sale of power from M/s. Jaydeep Cotton

Fiber Pvt. Ltd. (JCFPL) to Goa under Short Term Open Access has

commenced from 28.08.2014 and elaborated the various issues w.r.t

scheduling of solar power in their letter Gujsldc/SCH/F-12/132 and suggested

replacing Schedule with actual generation.

The Committee felt that the scheduling on the above suggestion of

SLDC Gujarat can only be done if Hon’ble CERC gives directions aligned

with the suggestion

4.2. CE SLDC Gujarat vide their letter GETCO/SLDC/4501 dated

23.05.2015 informed that the Interstate bilateral transaction for sale of power

from M/s Jaydeep cotton fibre Pvt Ltd (JCFPL) to Goa is through NVVN, and

prior to scheduling of the said power under STOA WRLDC has conveyed to

Gujarat SLDC as under for M/s JCFPL

Page 18: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad11

1. No POC charges and losses for solar power for CTU system.

2. If there is no UI/DSM for solar generation in the state of Gujarat, the

same may be taken care at their end.

3. WRLDC shall not carry out any post facto revision by making SG=AG.

Two more solar generators M/s Gujarat State ElectricityLtd and M/s Gujarat Power Corporation Ltd, both having10MW installed capacity of Solar Power have commenced thesale of solar power under Inter State Bilateral transaction toGRIDCO, Odhisa through SECI wef 24.3.15. In total three solarplants are selling about 20-22 MW p o we r under InterstateBilateral Transaction. In f u t u r e number of solar and windgenerators may come up for such transactions. Since thecommercial mechanism under RRF is suspended, theimpl icat ions for DSM charges on the State due to deviation cannotbe settled. Hence, the actual generation be treated as schedules for suchgenerators.

The above was discussed again in the 70th CCM, since SLDCs arereceiving application for solar power inter-State transactions. The sub-Committee felt that in view of suspension of the commercial mechanismunder RRF regulations and the provisions of the CERC regulations invogue, it would not be possible to post facto revise the schedules to theactual generation in case of the solar power plants and therefore theStates may take up the matter with CERC for further directions.

TCC/WRPC members may like to discuss.

ITEM No.5: SCHEDULING OF 10 MW ALLOCATION OF POWER TOBARC FACILITIES (TAPS 3 &4) FROM NPCIL TAPS 3&4.

WRLDC vide letter WRLDC/MO-II/1797/2015/310 dated 08.04.2015 &

27.01.2015 have informed that BARC facilities have disconnected from

MSEDCL system. Since, BARC facility is no more a consumer of

MSEDCL, therefore WRLDC vide above letters have requested to convene

a meeting to resolve the issues involved in scheduling of power from TAPS-

3&4 to BARC facilities. Accordingly a meeting to resolve issues involved in

Page 19: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad12

scheduling of 10MW allocation of power to BARC facilities (TAPS-3&4)

from NPCIL TAPS 3 & 4, was held on 28.04.2015 at WRPC Mumbai.

The issues discussed were as follows;

1. Allocation of 10MW was made from NPCIL TAPS 3 & 4 to BARC facilities

(TAPS-3&4) vide letter. WRPC/Comml-I/3/Alloc/2014/7872 dated

22.08.2014 to be effective w.e.f. 00:00hrs of 23.08.2014, as per MoP letter

No.3/44/2014-OM dated 20.08.2014.

2. Scheduling of BARC facilities commenced w.e.f. 00:00hrs of 23.08.2014,

treating BARC facilities as embedded entity of Maharashtra.

3. Disconnection of BARC facility from MSEDCL : As per NPCIL letter dtd

15.01.2015, they had disconnected the supply from MSEDCL w.e.f.

17.10.2014. However MSEDCL, representative informed that they would

confirm whether BARC Facilities supply from MSEDCL has been

permanently disconnected and they do not have any objection treating

BARC facilities as regional entity.

4. Status of BARC scheduling : It was informed that since scheduling of

BARC Facility is being done as an embedded entity of Maharashtra, the

DSM and other liabilities are with Maharashtra and would continue with

Maharashtra till it is treated as embedded entity.

GM WRLDC informed that BARC is being treated as an embedded entity

and invited suggestions, whether to continue treating BARC as embedded

entity or start treating BARC facilities as regional entity in light of above

communication received from BARC facilities.

5. BARC facilities representative informed that they have not applied for

open access with MSEDCL and MSETCL. SLDC MSETCL, Kalwa

representative informed that for treating BARC facility as embedded entity

of Maharashtra, BARC Facility has to take open access of

MSETCL/MSEDCL system for wheeling power from TAPS-3&4 to BARC

Facility through MSEDCL/MSETCL system. It was suggested that

MSEDCL, Maharashtra STU and BARC Facilities would resolve the open

access issue on priority.

Page 20: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad13

6. If BARC facility desires to be treated as regional entity, BARC facility would

have to approach CTU for multi party agreement between BARC Facility,

CTU, TAPS 3&4 & TAPS 1&2 and to get MSEDCL/MSETCL NoC for the

above connectivity, since one entity can not have dual connectivity with

CTU and STU simultaneously.

7. Till the above at point 6 is resolved BARC Facility would be treated as

embedded entity of Maharashtra. After completion of the above at point 7,

BARC facility would inform WRLDC and complete all the formalities with

WRLDC required for becoming a regional entity. Thereafter the scheduling

of BARC facility as regional entity would commence at a convenient date.

8. In that case, BARC Facility would be treated as buyer and DSM would be

applicable to BARC facility from the above date as per the methodology of

scheduling adopted for buyers and beneficiaries of the nuclear stations.

In line with the above discussions BARC Facility was requested to take

appropriate action at the earliest and communicate the status. However

BARC facility has not reverted on the above issue and BARC facility is

being treated as an embedded entity of Maharashtra for scheduling and

DSM accounting purpose.

TCC/WRPC members may like to discuss.

ITEM No. 6 : FUNDING FROM PSDF

CERC vide notification No.L-1/148/2014/CERC dated 9.6.2014 have notified

CERC (PSDF) Regulation 2014. As per these regulations the PSDF shall be

maintained and operated through the Public Account of India.

(1) PSDF shall be utilized for the following purposes:

(a) Transmission systems of strategic importance based on operational

feedback by Load Despatch Centres for relieving congestion in inter-

State transmission system (ISTS) and intra-State Transmission

Systems which are incidental to the ISTS.

Page 21: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad14

(b) Installation of shunt capacitors, series compensators and other reactive

energy generators including reactive energy absorption and dynamic

reactive support like static VaR compensator (SVC) and static

synchronous compensator (STATCOM) for improvement voltage profile

in the Grid.

(c) Installation of special protection schemes, pilot and demonstrative

projects, standard protection schemes and for setting right the

discrepancies identified in the protection audits on regional basis.

(d) Renovation and Modernization (R&M) of transmission system for

relieving congestion.

(e) Any other scheme/project in furtherance of the above objectives such

as technical studies, capacity building, installation of Phasor

Measurement Unit (PMU) etc.

(2) PSDF shall also be utilized for the projects proposed by distribution utilities

in the above areas which are incidental to inter-state transmission system

and have a bearing on grid safety and security, provided that these projects

are not covered under any other scheme of the Government of India, such

as Restructured Accelerated Power Development & Reforms Programme

(RAPDRP), Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY) /

National Electricity Fund (NEF) etc.

(3) The private sector projects shall not be eligible for assistance from PSDF.

(4) Prioritization shall be done mainly on the criteria of the schemes (i)

addressing grid security concerns; (ii) being of national importance; (iii)

being in the order of National / Multi Utility/Regional/State importance; (iv)

being inter-state in nature.

(5) The Procedure for Application, Screening, Appraisal, Monitoring, Sanction

etc. of PSDF is mentioned in the regulations.

Proposals of projects for funding through PSDF are being received by WRPC

Secretariat from constituents for recommending these projects to the Appraisal

Committee in Format A5.

Page 22: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad15

The proposals received and recommended by the Secretariat to the AppraisalCommittee are as follows;

Sr.No. Name of project Organisation

1 ADMS SLDC GETCO

2 Load Forecasting SLDC GETCO

3 Fault current limiter SLDC GETCO

4 Implementation of integratedsystem for availability based tariff,open access & MIS for SLDC,MPPTCL, Jabalpur.

SLDC MPPTCL

Since the above projects were of the nature of introduction to new technology

and help in enhancing the grid security, they were recommended by the

Secretariat to the Appraisal Committee in FormatA5.

Some more utilities have approached the WRPC Secretariat for

recommendation of their projects to the Appraisal Committee and are given

below

Sr.No. Name of project Organisation

1 A Pilot Project on establishment ofInteroperability among Process Bus compatibleIEDs of Different OEMs

GETCO

2 Wind generation forecasting project of Gujarat GETCO

3 Dynamic Reactive Power Compensation forimprovement of voltage profile in the Grid

MADHYA

GUJARAT VIJ

COMPANY LTD.

4 Compliance of protection audit observation andreplacement/renovation/up gradation ofprotection system and switchyard equipmentsof EHV Substations under Chhattisgarh StatePower Transmission Company Limited(CSPTCL) at various EHV Substationsfunctioning under CSPTCL.

CSPTCL

Page 23: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad16

Many more projects would be identified by various utilities for funding through

PSDF and therefore it is proposed to form a Committee at the regional level to

recommend the projects proposed by utilities. This Committee would go

through the proposals and identify the projects which are in line with the PSDF

regulations. For recommending these projects to the appraisal Committee.

The Committee may comprise of MS WRPC, GM WRLDC, ED/CE (STU) from

the constituents, ED POWERGRID, ED NTPC.

TCC/WRPC members may like to discuss.

ITEM NO. 7 REVISION OF DSM ACCOUNTS AND PAYMENT OFINTEREST THEREOF & STOA REVISIONS :

A) Revision of DSM Accounts and payment of interest thereof : ACBIL

vide their letter ACBIL/WRPC/14-15/1948 DATED 24.03.2015 have intimated

that the DSM account for the week 04.11.13 to 10.11.13 was revised due to

inadvertent error in calculating the injection of ACBIL and the DSM account for

the week 23.06.2014 to 29.06.2014 was revised due to erroneous CT ratio for

Bilaspur substation.

For both the DSM accounts WRLDC raised invoices on ACBIL based on the

original account and later raised revised invoices based on revised DSM

accounts. ACBIL did not make the payments as per original invoice citing that

the revised accounts/revised invoices were issued prior to due date of payment

of the original account. Further WRLDC vide their memos dated 02.05.2014

and 06.01.2014 raised invoices for interest payment against nonpayment of

dues as per original accounts. The interest is not payable by ACBIL as the

DSM accounts were corrected before the due date for payment and needs to

be written back.

The matter was discussed in the 70th CCM and WRLDC representative

informed that the interest for outstanding amounts of pool members in the

original account is calculated after the due date of the original account. Any

subsequent revision of the original account will have a new due date, therefore

Page 24: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad17

till this new due date, the interest is calculated for the pool members who have

out standing amount from the due date of the original account.

If the accounts are revised within the due date of the original account, the

sufferer pool member has to bear the interest on the out standing amount till

the due date of the revised account. Therefore they unnecessarily have to pay

the interest on the out standing amount and this adversely affects the cash

flow of small pool members due to errors non attributable to them in the

account.

WRLDC was of the view that pool members should confirm their injection/drawl

is correct and errors if any should be brought to their notice by Monday, since

the meter data is uploaded on their web site by Friday, so that the errors can

be rectified and revised data can be furnished by them to WRPC for preparing

the accounts.

Not withstanding the above the sub-Committee suggested that if the accounts

due to the above errors are revised within 5days of issuing the original account

the original a/c be suspended or the interest liability of all the pool members be

calculated as per the outstanding amount as per the revised a/c after the due

date of the revised account.

Since as per the regulations, the data for DSM account is to be furnishedby WRLDC by Friday & WRPC based on this data has to issue the DSMA/c on Tuesday. Suspension of A/cs as suggested means delayedissuance of the A/cs as per regulations. Further the pool member wouldsuffer in case of errors in a/cs which are beyond their control.

Followings are recommended;1) If the a/c is revised within the due date of the original a/c due toerrors beyond the control of pool members, the amount payable by poolmembers shall be as per the revised a/c and the due date shall be as perthe revised a/c.2) If the a/c is revised after the due date of the original a/c due toerrors beyond the control of pool members, a mechanism should beformulated such that the interest be receivable by the pool members who

Page 25: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad18

have paid excess amounts as per the original a/c than the amountspayable by such pool members as per the revised a/c.

TCC/WRPC may discuss and guide in this matter.

B) STOA revisions : ACBIL vide their above letter have intimated that the

plants of ACBIL have been granted connectivity through 400kV D/C dedicated

transmission line from ACBIL generating station switchyard to 765/400 KV

PGCIL substation Bilaspur.

The LTOA/Connectivity for the plants is as under:

1. Grant of open access for 270 MW vide PGCIL letter dated 16.03.2009

2. Grant of open access for 50 MW vide PGCIL letter dated 16.03.2009 and

27.12.2013

3. Grant of open access for 2x30 MW vide PGCIL letter dated 13.06.2013

ACBIL is scheduling the gross power from all the units under common UI pool

account and WRLDC works out the deviation w.r.t declared capacity of all units

taken together.

M/s ACBIL & SCPL applied to WRLDC for revision of STOA schedule for the

1x50 MW unit of SCPL from 24.73 MW to 0 MW due to forced outage on

27.03.2014 vide application no N23280A. WRLDC POSOCO vide their mail

dated 27.03.2014 replied that the STOA revision cannot be implemented

because the plant capacity is 50 MW and in further communications WRLDC

cited CERC provision of IEGC 2010 according to which, in case of forced

outage only generator having capacity of more than 100 MW shall only be

allowed for revision in declared capacity/schedule through concerned

SLDC/RLDC.

Therefore ACBIL is requesting to permit revision of schedule in case of forced

outage irrespective of size of generating unit as combined connectivity has

been given at Bilaspur substation.

In the 70th CCM ACBIL representative informed that the entire ACBIL & SCPL

complex is treated as a single pool member having installed capacity of more

than 100MW and therefore the revision of STOA schedule should have been

Page 26: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad19

allowed due to forced outage. WRLDC representative re-iterated that the

generator is having less than 100MW capacity therefore the STOA can not be

revised as per the above stated IEGC provision. ACBIL did not accept the

above clarification of WRLDC.

Since ACBIL as a pool member & generator has a capacity greater than100MW, whether the tripping of 50MW is eligible for STOA revisions ornot requires guidance of TCC/WRPC.

TCC/WRPC members may like to discuss.

ITEM NO 8: PROCUREMENT OF ERS SUBSTATION/SYSTEM OF400/220/33KV

POWERGRID proposed for procurement of Emergency restoration System for

Substation at 400/220/33kV level to meet the contingency arising out of natural

calamities like earthquake, flood, cyclone etc. WRPC agreed in principle and

suggested discussion in technical committee meeting to examine the proposal.

Recently, cyclones of the scale of Phailin in Odhisha and Hudhud in Vizag

caused enormous damage to Power transmission infrastructure in the respective

regions which triggered revisiting the requirement of ERS Substation at

400/220/33kV level. Matter was again discussed in TCC meeting of 28th WRPC

held on 3rd March, 2015 where TCC members agreed to the suggestion of MS,

WRPC that the earlier view taken by WRPC about three to four years ago on the

ERS substation can be relooked under the present changed scenario.

During CCM meeting held on 4.06.2015 it was recommended that the proposal

for ERS s/s be discussed first in OCC for technical details and tentative cost

estimate. So that recommendations of OCC could be put up to ensuing

TCC/WRPC ensuing meeting.

In 472nd OCC meeting held on 10.06.2015 at Ahmadabad representative from

POWERGRID, WRTS – 1, Nagpur made a presentation in brief about techno-

commercial details. Mobile substations are useful for meeting the contingencies

imposed by natural disasters like cyclone and earthquake which cause extensive

damage to the power supply network. Other than natural disasters there is

Page 27: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad20

application of mobile substation in cases of terrorist attacks on the power system

assets and for temporary augmentation / reinforcement of existing power supply

network like in case of organization of big national / international level events.

Mobile substations are critical for ensuring reliability in power system network in

case of contingencies beyond the control of power system operator / system

owner.

During the meeting CE, SLDC GETCO opined that above project may involve

significant commercial involvement, therefore it would be better if is funded

through PSDF fund and minimize the burden on beneficiaries. Also, participation

of DISCOMs is essential before making any decision on procurement of the

same.

Member Secretary, WRPC suggested the by procurement of such type of mobile

Sub-station the interruption of supply hrs may be reduced.

He further informed POWERGRID to come up with more techno-economical

details in upcoming TCC/WRPC meeting regarding finalizing the modalities

involved in the procurement of mobile substations for Western Region.

Present status of availability of ERS also about pooling/utilization strategies about

existing ERS constituent wise is given below:

One ERS is available with MSETCL, no ERS is available with Gujarat, one ERS

available with MP, two 400 kV ERS available with Chattishgarh at Bhilai/Raipur,

PGCIL have four set of ERS system viz 765kV at Seoni, 400 kV at Raipur, 400

kV Dehgam, Itarsi and one at 400kV & one at 500kV level total two ERS

available with Adani.

PGCIL may give the brief details on above & WRPC/TCC may discuss thesame.

ITEM NO 9 :

A. PROGRESS OF EMS / SCADA REPLACEMENTIn the 16th Project Review Meeting of SCDA/EMS held on 6th July, 2015,

WRLDC informed that GE SCADA LTSA would expire on 13.10.2015. and

Page 28: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad21

requested to complete Alstom SCADA commissioning and testing by

30.09.2015. The site readiness has been reviewed specially for the following

location :

a) Bhopal SLDC / Sub-LDC

b) Indore sub LDC

c) Goa (Madgaon) SLDC

d) Bhilai back up SLDC

After detailed deliberation with PGCIL, It was agreed that extra efforts may be

made to complete the above sites including communication requirement by

15.08.2015. In case of extreme emergency delay, alternate arrangement for

temporary deployment of new SCADA will be made to facilitate migration to

New system.

PGCIL, Alstom and Members agreed the same.

TCC/WRPC members may like to note.

B. MASTER PLAN COMMUNICATION

In the 16th Project Review Meeting of SCDA/EMS held on 6th July’2015,

PGCIL requested for repeater station for Master Plan communication at

following location:

a) Pichore 132 kV for Bina-Gwalior link

b) Bijawar 132 kV for Champa – Kurukshetra line

c) Sihora 132 kV for Champa –Kurukshetra line

Requirement of repeater at above location was discussed and considering the

Grid operational requirement, the same was agreed. MP requested to provide

terminal equipment in place of repeater station whenever required. PGCIL

informed that they will explore and include as per convenience.

Representative from MP informed that the same may be taken up with MP

STU and SLDC will extend necessary assistance.

TCC/WRPC members may like to discuss.

Page 29: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad22

ITEM NO. 10 : UNIFIED REAL TIME DYNAMIC STATE MEASUREMENT(URTDSM)

10.1 : REPORTING OF DATA TO STATE SLDCS

The matter of non reporting of central sector PMUs data to SLDCs was taken

up by SLDCs in URTDSM project review meetings held at WRLDC Mumbai on

13-12-2014 and 09-01-2015 in which it was principally agreed that PMUs data

of all stations falling under geographical area of the State is required to be

arranged in real time to the PDC of that SLDC. Further, representative of

LD&C POWERGRID informed that technical feasibility for additional

reporting/routing of data from Central sector PMUs need to be worked out

considering the capability of hardware and software, especially historian sizing,

storing capacity, duration etc. and assured that they shall revert back during

the next meeting.

The above was emphasised in the 28th WRPC meeting by the beneficiaries

and SLDCs. The above requirement, along with necessary hardware and

software required was in principle accepted by WRPC and PGCIL was

requested to work out the details of hardware and software requirement and

discuss the same in detail with WR constituents in the ensuing URTDSM

meeting. GM – PGCIL(HO) agreed to examine and implement the same.

In the 4th URTDSM meeting held on 6th July’2015, as per the directives of

WRPC in the 28th WRPC meeting. PGCIL representative informed that they

have worked out the hardware and associated requirement and confirmed that

original configuration is adequate to the meet the above data flow.

Requirement of enhanced capacity in view of above has been worked out by

PGCIL which will be implemented in the 2nd phase.

TCC/WRPC members may like to note.

10.2: URTDSM technical requirement:In the 4th URTDSM meeting during the presentation on 7th July’2015 by IIT-B,

PGCIL to a query clarified that one terminal at WRPC would be made available

Page 30: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad23

and PMU data would also be available at this terminal for analysis by the

protection group of WRPC.

IIT-B gave a presentation on the analytics being developed under this project.

The analytics envisaged in the project includes On line State Estimation,

Estimation of line parameters, vulnerability analysis of relays for load

encroachment and power swings, CT/PT calibrations and Zone-III adaptive

protection.

To a query of representatives present as to whether metering core or

protection core is wired up for PMUs, IIT-B representative replied as per

POWERGRID proposal metering core is being wired up for PMU.

It was in general felt that the choice of instrumentation transformers cores

should be based on the applications/analytics being developed for the project

and for all protection purpose analytics it would always be advisable to use the

protection core of the instrument transformers since under heavy power swings

and faults persisting in Z-II/Z-III timings the metering cores would saturate and

the analytics developed for protection purpose would not give desired results.

Therefore for specialized protection analytics PMUs of protection class are

required to be wired up in PS class CT/PT cores.

Since POWERGRID was responsible for providing input they assured to

consider the above suggestion and would revert back.

TCC/WRPC members may like to note.

10.3: URTDSM Manpower requirement

In the 4th URTDSM meeting held on 6th July’2015, PGCIL has informed that

scheduled Program Development System ( PDS) is to be delivered during

August 1st week. The Committee discussed the requirement of dedicated

manpower for PMU technology development and deployment in SLDCs. GM,

WRLDC informed that PMU technology has immense potential in Grid

operation for improvement in system efficiency and reliability. So dedicated

Page 31: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad24

man power will ensure engagement of the Engineers from all control centres

towards adoption of new technology and achieve desired benefits.

After detailed deliberation the URTDSM Committee recommended for

dedicated man power of 2-3 persons in each control centres to be provided

respective utility (SLDC/RLDC/….).

TCC/WRPC members may like to discuss and approve.

10.4: URTDSM space requirement

In the 4th URTDSM meeting held on 6th July’2015, PGCIL informed the

schedule for delivery of URTDSM project materials and requested constituents

to arrange necessary space at all control centers for which constituents

agreed.

TCC/WRPC members may like to discuss and approve.

ITEM NO. 11: TESTING OF SPS ENVISAGED FOR SR-NEW GRIDOPERATION AND 765 KV AGRA-GWALIOR LINES

11.1 : SPS ENVISAGED FOR SR-NEW GRID OPERATION :

Back ground: As per NLDC’s letter dated 11.04.2014, the backing down quantum for

generators in WR were finalized for various security threats after NEW – SR

synchronization with 765kV Raichur-Sholapur Ckt-I. The matter was further deliberated in

the 26th WRPC meeting held on 21.06.2014 and decided that as and when the signals are

extended to the newer generators, the quantum of backing down of the already

participating generators will be reduced on prorata basis. NLDC vide letter dated 07th July

2014 communicated modification in SPS in view of commercial operation of 765kV

Raichur-Solapur ckt-II. The same was circulated to all the concerned for necessary action.

Status: In the 123rd PCM, PGCIL was requested to extend the signal to Lanco at the

earliest and requested all newly participating generating stations to complete the wiring for

necessary action at their end. It was also decided that mock testing of the modified SPS

Page 32: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad25

may be done by WRLDC after completion of signal extension and wiring at all generating

stations.

WRLDC representative intimated that mock testing of SPS for 765kV Raichur – Solapur

D/C was done in December 2014 and signal for generation backdown was received at all

envisaged generating stations i.e. KSK, JPL, JPL Extension, NSPCL, BALCO, KWPCL and

DB Power.

11.2: Tripping of 765 kV Raichur – Solapur D/C on 24.05.2015: On 24.05.2015 at

around 19:13 Hrs 400 kV Chittor – Tiruvalem – I & II tripped. Subsequently at 19:19 Hrs,

HVDC Talcher – Kolar pole I & II tripped on valve cooling problem and thus the power flow

on each circuit of 765 kV Solapur – Raichur D/C touched around 1573 MWs and these line

tripped from Raichur end. It was followed by tripping of around 1750 MWs generation and

1000 MWs load shedding in SR.

In the 125th PCM, WRLDC representative intimated that during the above occurrence,

power swings were observed as seen from the PMU data of Solapur and Raichur. He

further informed that it is suspected that the lines have tripped from Raichur end due to

crossing of 1000MW for 10 secs. However the tripping of the D/C should have been

blocked when both ckts are in service. The tripping at WR end (i.e. Sholapur end) is

blocked and it needs to investigate whether the tripping for above condition is blocked at

Raichur end. This has been taken up with POWERGRID.

Committee felt that during the above occurrence, the load shedding in SR envisagedfor HVDC Thalcher-Kolar SPS might have acted correctly. However during theoccurrence generators at Meenakshi(150MW), SDS TPS (800MW), RaichurTPS(210MW) and Ramagundam-Bhadrawati Pole 1 was out of service. This led toincrease in loading on Raichur-Sholapur lines, but the load shedding in SR was notadequate (due to combined effects of HVDC Thalchar-Kolar tripping and Generationtrippings in SR). Further it is suspected that SPS settings as per NLDC letter dated07.07.2014 is not revised at Raichur end(i.e. blocking of tripping for O/L when bothckts are in service). This led to tripping of the lines from Raichur end. . Committeerequested WRLDC to take up the matter with NLDC / SRLDC / ERLDC. Further, theloads to be shed identified for Thalchar-Kolar SPS & Raichur-Sholapur SPS shouldbe independent of each other.

Page 33: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad26

11.3: Tripping of 765 kV Raichur – Solapur D/C on 31.05.2015: In the 125th PCM,WRLDC representative intimated that at 16:59 hrs, 765 KV Raichur-Solapur-II tripped on

B-phase fault .At 17:00 hrs, 765 KV Raichur-Solapur-I tripped on Y-phase fault. A/R

attempted for both circuit but due to persisting fault, the lines tripped.

765 KV Raichur-Solapur-I was charged from Raichur end at 17:42 hrs and synchronized at

Solapur at 19:00 hrs. During synchronization, SPS operated and generation backing down

took place at NSPCL ( 25 MW ), JPL ( 70 MW ), KSK (40 MW ). 765 KV Raichur-Solapur-II

was restored at 19:25 hrs. At the time of synchronisation large power swings were

observed and the magnitude of Power swing was more than 3000 MW on this occasion,

which caused SPS operation.

The large power swings were observed due to improper synchronisation of the NEW & SR

grids. As seen from the PMU data, the synchronization was done at an angular difference

was around 115 degrees.

The PCM felt that angular difference estimated/assessed during the synchronizationby WRLDC may not be around 115 degrees, since synchronization at such anangular difference would have resulted power flows of the magnitude of phase tophase faults. However there was some problem during synchronization whichneeds to be brought out by studying the incidence in great depth by central agencylike NLDC/CEA.

Subsequently considering the seriousness of the above events, WRPC vide letterdated 17.06.2015 took up the issue with CEA. NLDC have published a report on theabove events and a copy is available at WRPC web-site..

TCC/WRPC members may like to discuss/note.

ITEM NO. 12:

12.1 SPS FOR AGRA-GWALIOR – MOCK TESTING OF SPS ENVISAGED FORBACKING DOWN OF GENERATION IN WR

Background: An SPS has been implemented for 765kV Bina – Gwalior – Agra D/C,

wherein when sudden reduction in import by NR on Agra-Gwalior I & II ckts by more than or

Page 34: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad27

equal to 1500 MWs, 500 MWs generation back down in WR (KSTPS NTPC– 120 MWs,

VSTPS NTPC – 200 MWs & CGPL – 180 MWs) and load shedding in NR would take place.

The mock testing of SPS for 765 kV Bina – Gwalior – Agra D/C was proposed by NRPC on

24.12.2014. The mock testing of the SPS was unsuccessful and in the 124th PCM, PGCIL

representative intimated that the signals were sent to generating stations directly from Agra

S/s, under PGCIL - NR.

The mock testing of the SPS was again carried out on 30.04.2015 and the receipt of

signals at all the generating stations in WR was confirmed.

In the meeting held on 23.06.2015 at CEA New Delhi for revision of SPS settings of 765kV

Bina-Gwalior-Agra lines, it was decided that the SPS setting for triggering Load Shedding in

NR be revised from existing 1250MW to 1400MW for each circuit (i.e. 2500MW to 2800MW

for D/C). Increase in flow limit for SPS would allow import by NR upto 1400MW on each

ckt. However ATC/TTC would not be changed. This settings would be observed for some

time before revising upward and also in the light of ensuing commissioning of 765 kV

Gwalior-Jaipur Circuit.

TCC/WRPC members may like to note.

12.2: Review of SPS for CGPL Mundra:

In view of commissioning of 400 kV Bhachau – Versana D/C the SPS was under review.

Based on the studies carried out by WRLDC in consultation with SLDC GETCO, CGPL and

WRPC the

Revised SPS agreed is as follows;

Sl. No. SPS triggering condition Actions required Comments

i) If export is more than3300MW and one cktof CGPL-BhachauD/C trips

Backing down automaticallyto bring down thegeneration to 3100MW.

1.One line trips and export isbetween 3300 to 3500MWthen runback of unit 40only.

2.Two lines trip and export isbetween 3300 to 3500MWthen trip unit 40.

ii) If export is more than3300MW and ifCGPL-Chorania orCGPL-Halvad or oneckt of CGPL-Jetpur

Backing down automaticallyto bring down thegeneration to 3300MW.

Page 35: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad28

D/C trips3.One line trips and export is

more than 3500MW thenrunback of unit 40 andother selected unit.

4.Two lines trip and export ismore than 3500MW, thentrip Unit 40 and runback inother selected unit.

iii) In case of D/C trippingof CGPL-Bachhau,CGPL-Chorania orCGPL-Jetpur

Trip one unit immediately.Unit running at maximumgeneration to be selectedfor tripping to get full800MW reductionimmediately to take care ofsystem stability.

Iv In case of D/C trippingof Bachhau-Ranchopura

Backing down automaticallyto bring down thegeneration to 3300MW.

CGPL vide letter dated 18.05.2015 have intimated that the above logics have beenimplemented at CGPL Mundra since 08.05.2015.

TCC/WRPC members may like to note.

12.3: Islanding schemes for TAPS 1 & 2 and TAPS 3 & 4:

In the 124th & 125th PCM meeting, it was proposed that TAPS 1 & 2 generation be islanded

with Bhilad load and TAPS 3 & 4 be islanded with load of Boisar (MSETCL). In the 124 th

PCM, Committee reviewed the proposal and opined that units of TAPS 1 & 2 are very old

and fine control of generation is not possible. The governors of TAPS 1 & 2 are such that

the generation can either be 160 or 100 MWs. Further the radial loads at Bhilad are

variable and fine control of loads may not be possible. Therefore islanding TAPS 1 & 2 with

Bhilad load may not survive for long and even if it survives, while restoring the grid it may

be very difficult to synchronize this island with grid as both load and generation of the

island are not controllable.

Further it was felt that as the generation of TAPS 3 & 4 can be controlled, it would be better

to form an island with generation of TAPS 1, 2, 3 & 4 and loads of Bhilad and Boisar.

Committee requested TAPS 1 & 2 to take up the above proposal with higher authorities and

revert back to the PCM forum with its proposal.

TAPS 1 & 2 representative intimated that the above proposal was discussed in depth with

higher authorities. It was felt that TAPS 1, 2, 3 & 4 together as island have multiple

Page 36: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad29

combinations (All Units are running, TAPS 1 under shutdown etc..,) , it would be very

difficult to implement the logic for the same.

Committee decided to drop the proposal for islanding of TAPS 1 & 2 and islandingscheme for TAPS 3&4 be formulated and requested WRLDC to prepare a draftscheme and put up the same in the next PCM.

TCC/WRPC members may like to note.

ITEM NO. 13 : DEVIATION SETTLEMENT MECHANISM AND RELATEDMATTERS (FIRST AMENDMENT) REGULATIONS, 2014 DATED 18TH

DECEMBER’ 2014Background:

In the 28th WRPC meeting MD, MSETCL pointed out that the bigger states like

Maharashtra, MP, Gujarat etc face a lot of practical difficulties in restricting the

deviations as per the provisions of the DSM regulations and amendments thereto.

However the representations with the Hon’ble CERC have been made on individual

basis (as only MP has approached the Commission). He further suggested that if

difficulties are experienced in implementing the restrictions of deviations as per

DSM regulations during operation by almost all the States of the region, then as a

region it is necessary to represent the case and also point out acceptable solutions

before the Commission or appropriate redressal forum. He pointed out the following

difficulties are being faced by Maharashtra and other States in restricting deviations

within limits:

1) Impact of Renewable Energy: The renewable energy particularly wind faces

a lot of uncertainties. The quantum of wind has gone up in Maharashtra. These

variations are far above 150 MW limits prescribed. The RRF mechanism is

suspended. In these conditions, the State is unnecessarily burdened with DSM

penalties.

2) Failure of Communication links: In January 2015, there were instances

when the major communication links failed. Under these conditions, the State was

asked to back down generation. With frequency being low, the DSM penalties were

very high, as it turned out from the energy meter readings that the State was not

actually underdrawing as seen from the SCADA in absence of links, but was

Page 37: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad30

overdrawing. There should be provisions in the DSM to mitigate penalties in such

cases where state is asked by WRLDC to backdown and links are not fully present.

3) Need for Redundancy in links: There is a need to increase the redundancy

in communication links in a phased manner so that the above point does not repeat

and cause financial implications.

4) Too small margins: Apart from the RRF factor, the margin for deviation of

150 MW for States with demands ranging from 10000 to 20000MW and central

shares around 4000 MW is too small to be within limit and seriously requires to be

enhanced.

5) Infirm power: New generating units under infirm power also cause

deviations.

WRPC in the 28th meeting accepted the suggestions of MD MSETCL and

recommended for formation a group comprising of representatives from all states

and study the problems faced during the DSM regime and suggest the solutions in

the next WRPC meeting. It is necessary to represent the case as a region and also

point out acceptable solutions. It was decided that the Scope of the Group would be

to study the operational challenges mentioned above and other related issues if

any, which are commonly affecting the states in WR and suggest acceptable

solutions and put up to the next WRPC meeting so that the matter may be put up to

the Commission as a Region, if required.

It was decided that the group shall be as follows:

1) All CE, State SLDCs

2) NTPC

3) All CE, Discom / Holding company if required

4) Any other member as required during discussions

CE, SLDC MSETCL shall be convenor.

A meeting was convened by CE SLDC Maharashtra at SLDC Kalwa on 22.04.2015.

CE SLDC may give presentation on the outcome of the meeting.

TCC/WRPC members may like to discuss.

Page 38: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad31

ITEM NO.14: HON’BLE CERCS REGULATIONS:

14.1: THIRD AMENDMENT OF OPEN ACCESS REGULATION 2015 DT.12TH

MAY 2015

Hon’ble CERC has notified 3rd amendment of Open Access Regulation 2015 dt

12th May 2015. Brief on the amendment is as follows.

Amendment of Regulation 2 of principle regulation

State Load Despatch Centre Operating Charges (SLDC operating charges) shall

include the fees for scheduling, system operation, collection and disbursement of

charges in respect of short term open access transactions for inter-State

transmission of electricity. The operating charges collected by the State Load

Despatch Centre for short term open access transactions shall be in addition to

fees and charges , specified by the respective State Commission. The SLDC

operating charges as may be decided by the Commission in accordance with this

regulation shall be applicable to the inter-State short term customers only if the

operating charges have not been notified by the respective State Commission

Amendment of Regulation 8 of Principle Regulation

While making application to the RLDC/SLDC for obtaining concurrence for

bilateral transactions (except for intra-day transaction/contingency transactions),

an affidavit in the format prescribed in the Detailed Procedure, duly notarized,

shall be submitted, along with the application, declaring that:

(i) There is a valid contract with the concerned persons for the sale or purchase,

as the case may be, of power under the proposed transaction for which

concurrence is applied for, and;

(ii) There is no other contract for sale or purchase, as the case may be, of the

same power as mentioned in (i) above.

While making application to the SLDC for obtaining no objection or prior standing

clearance in case of collective transactions , the affidavit shall also include the

declaration that there is no other contract for sale or purchase, as the case may

Page 39: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad32

be, of the same power for which no objection or prior standing clearance is applied

for.

Amendment of Regulation 17 of Principle Regulation

Operating charges at the rate of `1000/-,per day or part of the day for each

bilateral transaction for each of the Regional Load Despatch Centre involved and

at the rate of `1000/- per day or part of the day for each State Load Despatch

Centre involved shall be payable by the applicant.

In case of collective transaction, operating charges shall be payable by the power

exchange at the rate of `2000/- per day to the National Load Despatch Centre for

each State involved and `1000/-per day for the State Load Despatch Centre

involved for each point of transaction.”

14.2: CERC (Sharing of Inter State Transmission Charges & Losses)-3rdAmendment Regulations, 2015, dt 1st April 2015

Hon’ble CERC has notified 3rd amendment regulations of Sharing of Interstate

Transmission Charges & losses dated 01.04.2015

Brief on the Amendment is given below

1. Terms deleted from all sections of the Regulation:

Peak and Off peak hours scenarios.

Network Truncation

Uniform Charging method

2. Application period ie ‘period of application of these charges’ is now for

3months duration. (eg. Apr-Jun, July –Sep, Oct-Dec, Jan-Mar.)

3. Approved injection (MW)-( for an Application Period) is now defined as the

maximum injection made during the corresponding application period for the last

3yrs.

4. Approved withdrawal (MW)(for an Application Period) is now defined as the

actual peak met during corresponding application period of last 3yrs.

5. DIC :(User of any segment of ISTS viz generator, STU/SEB, Load) Now it also

includes any intra state entity who has obtained MTOA or LTA to ISTS and are

connected to either STU or ISTS or both .

Page 40: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad33

6. In addition to injection/withdrawal PoC, two more new charges have been

introduced.

(1) HVDC Charges and

(2) Reliability Support Charge

7. Additional norms are defined for data submission to Implementing Agency (IA)

Nodal generation data (forecast based) by the DICs (for an application

period)Forecast demand data by the DICs (for an application period)For a given

application period the IA would compute the Approved Injection / Withdrawal

based on last 3 yrs. actual fig. & same will be validated by the VC Difference b/w

the fig. given by the DIC & those computed by IA have to be explained reasonably

by the DIC Mis-declaration by a DIC ( beyond +/- 20% ) for 2 consecutive quarters

– Treated as Gaming & to be reported to CERC.

8. ‘Network truncation’ is no more allowed and Hybrid methodology shall be

applied by the IA on the Basic network to determine Transmission charges

(Injection & Withdrawal PoC rate) and Loss allocation factor (LAF).

9. There shall be 9 slab rates for PoC rate (in Rs./MW/Month) as well as PoC

Loss (in %).

10.Recovery of transmission (YTC) based on both Hybrid and Uniform charges

stands amended.

Recovery of YTC will now be done in 3 parts PoC Charges ( Calculated based on

hybrid methodology) Reliability support charges ( RSC to recover 10% of YTC)

HVDC charges 10% of YTC shall be through Reliability Support Charge sharing

methodology. This charge shall be determined separately and shall not mixed with

Zonal PoC rates.

11.Now onwards losses also shall be apportioned to each DIC through Hybrid

methodology only.

Earlier 50% was through Hybrid and 50% through uniform loss allocation

mechanism Now there will be 9 slabs of Loss ( 4 steps above & 4 steps below the

average loss %) Step size = 0.25 % ( Min Loss = 0%)Slabs to be reviewed by

CERC after 2 years.

Page 41: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad34

Any ISGS connected to 400kV ISTS system ( including those connected to ISTS

& STU) shall be treated as a separate Zone.

12.Merchant Power Plant: New definition introduced Whose tariff is neither

determined as per sec-62 or sec-63 of the Act & who sells entire capacity in the

open market. For Merchant power plants connected to ISTS with zero LTA or part

LTA, injection considered in Base case or LTA which ever is higher shall be

considered to arrive at PoC injection rate.

13. In case commissioning (CoD) of a generating unit is delayed, the generator

shall be liable to pay withdrawal charges corresponding to the LTA granted &

withdrawal charges shall be @ average withdrawal PoC rate of the target region.

14.Before CoD & Commencement of LTA when a Generating station draws start-

up power or injects infirm power its liable to payWithdrawal PoC charge for drawal

of start-up power (as per actual quantum of W/D) Injection PoC charge for infirm

injection (as per actual quantum of injection. )(The amount collected through this

shall be adjusted against YTC for next application period)

WRP Committee may like to note.

14.3 Hon’ble CERC has issued the following Regulations14.3.1Hon’ble CERC issued fifth amendment on “ Grant of Connectivity, Long

term Access and MTOA in inter state transmission and related matters”

Regulation 2015 , dt.15th May 2015.

14.3.2 Hon’ble CERC issued Notification on “ Fees and Chrages of RLDCs and

other related matters” for the control period 2014-2019, dt. 18th May 2015

TCC/WRPC members may like to discuss.

ITEM NO 15 : READINESS OF SLDC AT GOA, OTHER SLDCs AND WRLDC

During 28th WRPC meeting it was decided that the status of progress of SLDC’s &Back-up SLDC’s of WR constituents /WRLDC would be regularly monitored inmonthly OCC meeting.

Page 42: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad35

Accordingly the OCC monitored every month & as per 472nd OCC the presentstatus of progress of SLDC’s & Back-up SLDC’s of WR constituents /WRLDCattached at Annexure –15.Respective utilities may update the status & WRP Committee may like todiscuss.

ITEM NO 16 DECLARATION OF TRANSMISSION ELEMENTSINTO COMMERCIAL OPERATION BY ISTS LICENCEES.

The list of transmission elements commissioned during the period 08.01.2015 to06.05.2015 as conveyed by PGCIL is enclosed at Annexure 16.

WRP Committee may like to discuss/note.

ITEM NO 17. DECLARATION OF ISGS IN TO COMMERCIAL OPERATIONWRLDC have informed the status of units under commercial operation in WesternRegion from Feb15-May15 as follows;

SLNO

STATIONNAME

UNITNO/CAPACIT

Y

Date wefcommenceme

nt ofCommissionin

g activities

Date ofSyn. Of

GT

Date ofCoD

1SASANUMPP 6-660MW NA 02.12.14 27.03.15

2JAYPEENIGRI 2-600MW NA 11.02.15 21.02.15

3 MB POWER 1-600MW 25.02.15 19.03.15 20.05.15

4MCCPL(ACBIL) 1-300MW 23.03.15 17.04.15

5JHABUAPOWER LTD 1-600MW

28.04.156 JPL STAGE 2 4-600MW NA 26.03.15

ITEM NO. 18: GRANT OF MTOA AND LTOA BY POWERGRID.

The list of LTOAs/MTOAs received from NLDC and applicable from the month ofJune-15 for computation of RTA is enclosed at Annexure-18.

TCC/WRPC members may like to note.

Page 43: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad36

ITEM NO 19 STATUS OF LETTER OF CREDIT(LC) OPENING AGAINSTDEVIATION CHARGES LIABILITY FOR 2015-16.

WRLDC have intimated the details of LC to be opened by WR entities for the FY

2015-16 and the status is given below.

SlNo.

WR Entity who haveto open LC

No ofweeks inwhich UIpayable

Averagepayable

weekly UI(Rs in lakhs)

LCAmount(Rs inlakhs)

Remark

1 CSPDCL 45 265 292

2 MP PowerManagement Co. Ltd. 25 185 204

Previous LC of Rs164 lakhs is valid

upto 30.06.15

3 MSLDC UI Settlementaccount 31 582 641

4 Goa 46 134 147 OPENED LC ON26.06.15

5 D&D 28 87 95Previous LC of Rs 53

lakhs is valid upto02.02.16

6 D&NH 38 40 44

7 JPL 29 267 293

8 LANCO 7 18 20

9 ACBIL 40 51 56Previous LC of Rs 66

lakhs is valid upto04.08.15

10 RGPPL 52 36 40 OPENED LC ON18.05.15

11 BALCO 49 44 48

12 CGPL UMPPMUNDRA 8 16

17

13 DCPP JSPL 35 38 41

Page 44: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad37

14 Essar Power MP Ltd 51 68 1217

15KSK 13 43

47Previous LC of Rs 26

lakhs is valid upto25.08.15

16 Vandana Vidhyut ltd 52 31 506

17 EMCO 15 1618 OPENED LC ON

18.05.15

18 KORBA WESTPOWER Corp. LTD 51 43

47

19 DB POWER 49 68 75

20 JAYPEE NIGRI 30 49 54

21 Essar STEEL LTD 31 62 68

22 GMRCHHATTISGARH 42 11

12

23 Dhariwal InfrastructureLtd. 28 5

5

24 RKM POWERGEN 15 9 10

TCC/WRPC members may like to note.

ITEM NO 20:

20.1 STATUS OF DEVIATION CHARGESDeviation charges Payable/Receivable by WR entities to WR Deviation pool

account fund maintained by WRLDC as on 07th July 15 is enclosed at

Annexure-20.

Major Default by Entities towards Deviation charges –Payable

1. Essar Power MP Ltd- Rs 22.00 crs

2. Vandana Vidyut Ltd- Rs 8.45 crs

3. ACBIL - Rs 4.07 crs

4. Jhabua Power- Rs 1.58 crs

5. KWPCL- Rs 1.91 crs

TCC/WRPC members may like to note.

Page 45: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad38

20.2 STATUS OF REACTIVE ENERGY CHARGES

Payable/Receivable by WR entities to Reactive pool account fund maintained

by WRLDC as on 07th July ‘15 is enclosed at Annexure-20A.

TCC/WRPC members may like to note.

20.3 :STATUS OF RECONCILIATION OF DEVIATION AND REC POOLACCOUNT FOR THE PERIOD JAN’15 TO MAR’15.

WRLDC vide letter dated 10.04.2015, have intimated that WRLDC has sent

the signed reconciliation statement for the period Jan’15 to Mar’15 to all

Deviation/REC pool members as on 1th Apr ‘2015 . All the details of

payments/receipts of Deviation charges and REC during Jan’15 to Mar’15 are

also uploaded on WRLDC website (www.wrldc.com/commercial/Pool

Reconciliation). The following members are yet to send back the signed

reconciled statement to WRLDC for the period mentioned above.

DSM Pool Members REC Pool members

1 GETCO LTD. 1 CSPDCL

2 MSLDC UI Settlement account 2MP Power Management Co.Ltd.

3 Goa 3 GETCO LTD.

4 D&D 4 MSEDCL

5 JINDAL POWER LIMITED 5 Goa

6 HVDC Vin. 6 D&D

7 HVDC Bha.

8 Lanco Amarkantak Power Ltd

9 BALCO

10 CGPL UMPP MUNDRA

11 DCPP JSPL

12 Essar Power MP Ltd

13 SASAN Power limited

Page 46: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad39

14 KSK Mahanadi

15 Vandana Vidyut Ltd

16 EMCO Energy ltd.

17KORBA WEST POWER Corp.LTD

18 JAYPEE NIGRI TPP

19 DGEN (Torrent Energy Limited)

20 GMR Chhattisgarh Energy ltd

21 Dhariwal Infrastructure Ltd.

WRLDC have requested all the above entities to reconcile at their end and

send the signed statement to WRLDC at the earliest.

TCC/WRPC members may like to note.

20.4: INTEREST CALCULATION STATEMENT OF DEVIATION POOLACCOUNT FOR THE PERIOD FROM 1ST APR ’2015 TO 30TH

JUN’2015The summary of interest payable/receivable for Deviation pool account as on

01.07.15 is as given below.

ConstituentNet interest payable/ receivable

(in Rs.)

CSPDCL 0

MP Power Management Co. Ltd. 16,497

GETCO LTD. -10,510

MSLDC UI Settlement account 66,577

Goa 1,41,043

D&D 3,48,407

D&NH 1,169

NTPC 1,308

JINDAL POWER LIMITED 4,327

HVDC Vin. 148

Page 47: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad40

HVDC Bha. 0

Lanco Amarkantak Power Ltd 0

NSPCL 0

ACBIL 21,22,318

RGPPL 811

BALCO 4,29,266

CGPL UMPP MUNDRA 7,076

DCPP JSPL 0

Essar Power MP Ltd 3,06,43,541

SASAN Power Limited -21,649

KSK Mahanadi 8,02,292

Vandana Vidyut Ltd 1,01,68,324

EMCO Energy ltd. 27,550

Korba West Power Co.Ltd 1,42,908

D. B.Power 2,250

Jaypee Nigrie TPP 9,68,726

Essar Steel India Ltd 6,67,023

DGEN (Torrent Energy Limited) 2,429

GMR Chhattisgarh Energy Ltd 7,42,409

Dhariwal Infrastructure Ltd. 60,129

RKM POWERGRN Pvt Ltd. 9,078

MB POWER LTD 5,419

JHABUA POWER LTD 33,282

Note: +ve indicates payable by the constituent and –ve indicates receivable bythe constituent

TCC/WRPC members may like to note.

Page 48: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad41

ITEM NO.21: PERFORMANCE OF WR GRID DURING FEBRUARY 2015 TOJUNE 2015

21.1 SYSTEM PERFORMANCE

Frequency:During months of February 2015, March 2015, April 2015, May 2015 & June

2015 the grid operated in the IEGC frequency range of 49.9 Hz to 50.05 Hz for

60.15 %, 58.47 %, 60.20%, 64.74 % and 65.01 % of time respectively. The

frequencies below 49.9 Hz were from 12.30 % to 17.77 % of time during

February 2015 to June 2015. In higher frequency regime, system frequency

remained above 50.05 Hz from 19.44 % to 27.55 % of time during February

2015 to June 2015. The monthly average frequency was 50.00 Hz in February

2015 , 49.98 Hz in March 2015, 49.99 Hz in April 2015, 49.98 Hz in May 2015

& 50.00 Hz in June 2015.

The detail of frequency profile for the months of during February 2015 to June

2015 is placed at Annexure-21.1(a).

Demand :

The maximum unrestricted demand of Western Region was in the range of

42600 MW to 43580 MW(Ex Bus) in during February 2015 to June 2015. The

region faced capacity shortage in the range of 200 MW to 725 MW (peak

deficit of 0.50 to 2.00 %) respectively during these months. The details of

unrestricted peak demand, demand met and energy requirement and

availability are as furnished at Annexure-21.1 (b).

21.2 Voltage Profile

Overall voltage profile had been satisfactory during the period under review.

However, instances of high voltages beyond the IEGC specified operating

range were observed at some of the EHV sub-stations in the region. Higher

voltages in the range of 421 kV to 440 kV were noted at Indore, Itarsi, Karad,

Dhule, Kasor, Bhilai, Jetpur, Bina, Gwalior, Nagda and Khandwa substations.

Page 49: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad42

To contain high voltages WRLDC resorted to opening of lightly loaded EHV

lines on certain days. The detail of voltages at important 400 kV and 765 kV

sub-stations during the period of during February 2015 to June 2015 is placed

at Annexure- 21.2. In order to control incidences of high voltages during low

load periods, installation of reactors at following locations as planned by

various utilities is in the process as per following schedule:

S.No.

400 kVSub/stn.

Size(MVAR)

Implementingagency

Expected commissioningdate

1 Nanded 125 MVAR MSETCL June – 2016

2 Sholapur 125 MVAR MSETCL June – 2016

3 Kolhapur 125 MVAR MSETCL June – 2016

4 Akola 125 MVAR MSETCL June – 2016

*5 Nagda 125 MVAR MPPTCL July – 2015

6 Bhopal 80 MVAR MPPTCL July – 2015

7 ISP 125 MVAR NHDC December 2015

8 Line reactorat Nagda-ISPline at Nagdaend

50MVAR MPPTCL July 2015

11 Satpura 50 MVAR MPPGCL April-2016

12 Sasan Busreactor

240 MVAR RELIANCE Commissioned on 23rd May-2015

*50 MVAR existing bus reactor to be shifted to Nagda-ISP line as linereactor after commissioning of 125 MVAr reactor at Nagda.

*50 MVAR existing bus reactor to be shifted to Nagda-ISP line as linereactor.

WRP Committee may like to update/note as above.

Page 50: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad43

21.3 AUFLS Performance.

The month-wise details relating to performance of AUFLS scheme in Western

Region during the period during February 2015 to June 2015 in terms of

quantum of load relief obtained and number of occasions the UFR operated is

at Annexure-21.3.

WRP Committee may like to note as above.

ITEM No. 22: ANTICIPATED POWER SUPPLY POSITION IN WESTERNREGION FOR THE PERIOD FROM JULY 2015 TOSEPTEMBER 2015

The anticipated power supply position in the region for the period from July

2015 to September 2015 is at Annexure-22. The period under consideration is

monsoon season. The anticipated regional demand is likely to vary between

43500 MW to 45500 MW and the capacity surplus will be around 5.0 - 6.0 %.

In terms of energy, the unrestricted requirement is expected to range from

27200 MUs to 27500 MUs with regional energy surplus of around 2.0 % to 5.5

%.

WRP Committee may like to note as above.

ITEM No. 23 STATUS OF COMPLETION OF 765/400 KV AND ABOVE ONGOING TRANSMISSION SCHEMES BEING EXECUTED/IMPLEMENTEDBY TRANSMISSION AGENCIES.

The updated status on various ongoing transmission schemes for the year

2015-16 as per the current information available is as follows : -

S.No.

Name of the Line TargetCompletion

Date

Remarks

POWERGRID

1 400 kV Navsari – Kudus D/C Line July -15 ROW problem

2 765 kV Gwalior - Jaipur line (1st Ckt)S/C

July-15

Page 51: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad44

3 765 kV Dharamjaygarh - JabalpurPooling Station D/C line

July-15

4 765 kV Wardha –Nizamabad-Hyderabad D/C

March-16

5 765 kV Narendra-Kolhapur D/C Dec-15

6 400 kV Aurangabad - Boisar line D/Cline

Nov -2015

7 765 kV Aurangabad (PG) - Padghe(PG) D/C

Sept-2015

8 800kV DC Champa – KurukshetraBipole

Sept 2015

9 765 kV Aurangabad- Solapur D/Cline

Oct- 2015

10 LILO of both circuits of Aurangabad –Pune 400 kV D/c line at Pune765/400 kV GIS

July -15

11 400 kV Parli-Pune(Sikarapur) LILO atSikarapur

Commissioned on24.02.2015

12 765 kV Raipur – Champa Commissioned on28.05.2015

13 765 kV Indore-Vadodara Commissioned on05.06.2015

CHHATTISHGARH

1 LILO of 400 kV Korba west-Khedamara at Marwa

July - 2015

2 400 kV DCDS Raipur(Raita)-Jagdalpur(DCDS)

July 2015

3 220 kV DCDS lines Chhuri to Mopka(Bilaspur), (DCDS)

July- 2015

4 LILO of 220 kV Raigarh-Budipadar at400 kV PGCIL S/s Raigarh

August -2015

5 LILO of 220 Korba (E)- Bishrampurline at 220 kV Churri S/s

Commissioned on01/05/2015.

Page 52: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad45

GUJARAT

1 400 kV D/C Mundra-Zerda line No. 1 Sept -2015

2 400 kV D/C Mundra-Zerda line No. 2 Sept -2015

3 400 kV D/C Vadinar-Amreli line Sept -2015

4 400kV APL-Hadala LILO to Halvad Sept -2015

5 400 kV D/C Amreli-Kasor line(Part-1) Sept -2015

6 400 kV Charanka- Veloda Sept -2015

MADHYA PRADESH

1Satpura TPH-Ashta 400KV DCDSLine

1st ckt commissioned on30th March 2015.

2nd ckt – expected byJuly 2015.

MAHARASHTRA(STU)

1 400KV D/C line from Koradi-(II) toWardha S/S(PG) D/C

July - 2015

2 LILO of 400 kV Chandrapur-Parli atNanded Dec-15

3 2x1500 MVA 765/400 kV, ICTs atEktuni Dec -15

4 400 kV Bableshwar-Kudus D/C(Quad) July -16

5 765 kV Akola(II)-Ektuni -2 ( To becharge at 400kV at Tapthithanda) July 2015

6 400kV IEPL-Warora July 2015

GUJARAT (IPTC route) by WRTransmission (Guj) Pvt. Ltd

1 400 kV Rajgarh(PG)-Karamsad(GETCO) D/C

July 2015

STERLITE (JTCL)

1 765 kV Dhramjaygarh - Jabalpur (JTCL)D/C line

Sept -2015 Severe ROW Problem

Page 53: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad46

2 765 kV Jabalpur - Bina (JTCL) S/c Sept -2015 Severe ROW Problem

STERLITE (BDTCL)

1 765 kV Vadodara - Dhule (BDTCL) S/C Charged on 12th June2015.

2 765 kV Bhopal- Jabalpur Charged on 8th June2015.

3765kV Bhopal – Jabalpur

Charged on 8th June

2015.

WRP Committee may like to note as above.

ITEM No.24 COMMISSIONING OF NEW GENERATING UNITS INWESTERN REGION AND THE CAPACITY EXPECTED TOBE COMMISSIONED DURING THE CURRENT YEAR 2015-16.

The status regarding Generating units, commissioned /expected to be

commissioned during the current year 2015-16 according the available

information is as below:

Name of the Power Projects Unit No. Capacity(MW)

Date of Commissioning/Schedule Date

GUJARAT

SIKKA TPS EXT 1 250 Sep-15

SIKKA TPS EXT 2 250 Dec-15

CHHATTISGARH

Marwa 1 500 July 2015

2 500 July 2015

MAHARASHTRA

CHANDRAPUR 9 500 September 2016

KORADI 9 660 August 2015

KORADI 10 660 March -2016

PARLI 8 250 December 2015

Page 54: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad47

MADHYA PRADESH

M/s Jhabua Power, Seoni 1 600 July – 2015

Moser Bear (Hindustan power) 2 600 December 2015

Essar Power MP Ltd(Mahan) 2 600 July -2015

CENTRAL SECTOR/IPP

VINDYACHAL 13 500 OCT -2015

KSK 2 600 Sept – 2015

KSK 5 600 December – 2015

SASAN 6 600 COD on 27.03.2015

ACBIL(Maruti) 1 300 Commissioned on17.04.2015

RKM 1 350 August-2015

RKM 2 350 Sept 2015

RKM 3 350 Dec 2015

WRP Committee may like to note as above.

ITEM.NO.25: WRPC MEMBERSHIP FOR RATTANINDIA POWER LIMITED

RattanIndia Power Limited vide letter RPL/WRPC/15-16/006 dated 09th April,

2015(copy enclosed at Annexure-25) have requested for inclusion of

RattanIndia Power Limited as a member of WRPC.

Government of India, under the provision of Section 2 (55) of the Electricity Act

2003 vide its resolution F. No.23/1/2004-R&R dated 25th May 2005,

amendment dated 29th Nov.2005 and subsequent amendment dated 9th May

2008 has established the WRPC. As per the resolution, a representative from

every generating company which has established a generating station more

than 1000MW in Western Region shall qualify to become member of WRPC.

The RattanIndia Power Ltd(RPL), , Maharashtra successfully commissioned

the 5 units of generating capacity 270 MW each at Amaravati and one unit of

capacity 270 MW at Nasik(total 1620MW) w.e.f. 13.03.2015.

Page 55: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Agenda notes of 29th meeting of WRPC to be held on 24.07.2015 at Aurangabad48

Accordingly, RattanIndia Power Ltd(RPL). may be included as a

member of WRPC representing the Generating companies with more than

1000 MW generation capacity from the year 2015-16 onwards.

TCC/WRPC members may like to given their consent for insertion ofRattanIndia Ltd. On WRPC membership for the year 2015-16 onwards.

ITEM No. 26: ANY OTHER ITEM

ITEM No. 27: DATE AND VENUE OF NEXT WRPC MEETING

***********

Page 56: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

ANNEXURE

Page 57: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Page 1 of 3

Annexure -3

Report on pump mode operation of Kadana Hydro units

In 467th OCC meeting of WRPC held on 16.01.15 at WRPC, Mumbai, it was decided that

SLDC-Gujarat would update latest status regarding capability of pump mode operation of

hydro units of Kadana Hydro plant (4 x 60 MW). Also, the General Manager, WRLDC vide

letter No. WRLDC/SO/137 dated 05.02.15 informed that CEA report titled “Large Scale

Grid Integration of Renewable Energy Sources - Way Forward” issued in Nov-13 says

that 4 x 60 MW units of Kadana Hydro plant Stage - 1 & 2 in Gujarat are capable of

operating in pumped storage mode. The report indicates that the facility is presently not

working and it recommends as under:

“The vibration problem in Kadana PSP (240 MW) also needs to be resolved”

Presently, the installed capacity of wind generation is 3500 MW. Many times, it is

observed that the wind generation during night hours remains on higher side and the

system demand remains on lower side. In such conditions, there is a heavy under drawl

during night hours which is penalized under recent Deviation Settlement regulation of

Hon’ble CERC. Also, the system faces high voltage issues many times. It leads to tripping

of 400 KV lines connected to Wanakbori Thermal Power Station. The generation schedule

from Kadana Hydro units is based on irrigation requirement. During peak hous in winter

and summer season, the KHPS generation is limited to only one unit. In such conditions,

the costly gas generation has been scheduled in open cycle for meeting peak demand.

Looking to all these, the capability of pump mode operation will play vital role in power

system operation.

To know updated status and to explore feasibility of Kadana units in pump mode

operation, Shri. D. B. Joshi, SE (OP), SLDC, Shri. B. M. Shah, DE, SLDC and Shri K. G.

Patel, DE, Corporate Office, GSECL visited Kadana Hydro plant on 21.02.15. The team

verified past records of pump mode operation also. The chronological summaries of past

records are as under:

A meeting was held on 30.08.03 with M/s. BHEL representative. In the meeting, it was

decided that M/s. BHEL would send the team to ensure readiness of all the units for pump

mode operation. If required, they would call experts from M/s. SKODA for overall

Page 58: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Page 2 of 3

supervision. Also, M/s. BHEL would identify the spares requirement. They would check

and ensure control, instrumentation and protection requirement. Thereafter,

commissioning of the pump mode operation would be carried out. Accordingly, the joint

inspection of all four units had been carried out in the month of Sept-03. They had listed

out further works to be carried out before commissioning of pump mode operation.

Various works / activities had been performed jointly by the team of M/s. BHEL, M/s.

SKODA and GEB between 20.02.04 and 08.04.04. They had updated the status

regarding commissioning and operational status of pump mode operation to GEB

management on 09.04.04.

In their observation, it was mentioned that the trial of all four machines under pump mode

operation was taken. Unit No. 3 & 4 tripped on turbine guide bearing temperature high. In

the meeting, GEB requested M/s. BHEL to intimate the vibration limit for operation of

pump mode. Also, it was noted that acceptance of commissioning of pump mode

operation would be considered successful after seven Nos. of successful trials through

auto sequence from control room. At least one trial should be more than 05 hours and

rest for minimum 03 hours of continuous run. It was also mentioned that it is desirable to

maintain TRC level between 78 meters to 81.5 meters. It was mentioned that there was a

considerable heating of reactors and therefore, enclosure works need to be done. There

was structural vibration observed in all units at the generator floor and to be got analyzed

at appropriate level. Also, it was mentioned that the reliability and consistency of safe

operation in pump mode was yet to be established and high level of vibration in pump

mode operation was to be rectified for prolonged use in safe condition.

On 24.06.04, the Officer on Special Duty at KHPS reported that they may run pump mode

operation of any unit at any time without support of M/s. BHEL. As per the record of pump

mode operation of all four units, the maximum vibration horizontal at turbine guide bearing

for Unit No. 3 was on higher side. M/s. BHEL had recommended that maximum 50 micron

vibration shall be allowed at bearing (Horizontal).

On 07.03.06, the Engineer-In-Charge, KHPS informed that there are certain constraints /

limitations in operating units on pump mode.

Vibrations of the order of 12 to 15 microns are observed at power dam during

pump mode operation of Unit No. 1 & 2.

Page 59: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Page 3 of 3

Unit No. 3 tripped frequently on rotor earth fault. Also, 6 Nos. of slip rings insulated

bolts were found puncture.

When the machine was running in pump mode, initially, 16000 Amp eddy current in

reactor was developed and it was to be controlled as per the guidelines of SKODA

engineers.

Since October - 2005, no unit of KHPS was operated on pump mode. Hence, it is utmost

necessary to carry out inspection of units one by one in presence of OEM to put pump

mode operation at KHPS in service. The recommendations of OEM regarding spares /

modifications / rectifications shall be taken into account to reestablish pump mode

operation. Also, study shall be carried out to access allowable vibration limit of Dam

structure as well as vibration (horizontal) at turbine guide bearing of each unit. The matter

shall be taken up with the irrigation authority to maintain down stream reservoir level

situated at Dolatpur. The comprehensive proposal shall be placed in PSDF by GSECL

Corporate Office. If requires.

It was discussed during 468th OCC meeting of WRPC held on 16.02.15 that 2 x 125 MW

units at Ghatghar Hydro power station in Maharashtra are capable of operating in pump

mode and are being operated in pump mode. Therefore, it is suggested that a team of

experts from GSECL shall visit Ghatghar HPS and have a detailed deliberation with the

authorities there so that they can explore the feasibilities of sustainable operation of

KHPS units on pump mode at the earliest.

Page 60: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy
ms wrpc
Text Box
ANNEXURE - 15
Page 61: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Sl. No. Asset Project DOCO1 400kV D/C Bachau (PG) - Versana (GETCO) along with associated bays. WRSS-XIII 08.01.2015

2 420kV, 125MVAr Bus Reactor alongwith associated bay at Parli Substation. Installation of Reactors(Part-II) in WesternRegion

10.01.2015

3 400kV, 1*80 MVAR Bus Reactor along with associated bays at 400/220kV GISMagarwada (new) SS.

GIS Magarwada 11.01.2015

4 400KV, 1*80 MVAR (3 Ph) Line reactor as Bus Reactor along with associated bay at400 KV Boisar Substation (For 400 KV D/C (Quad) Aurangabad-Boisar ckt-I line ascontingency arrangement)

TRANSMISSION SYSTEM STRENGTHENING INWESTERN PART OF WR FOR IPP GENERATION

PROJECTS IN CHATTISGARH11.01.2015

5 3*80MVAR Line reactor alongwith line bay ( under interim contingency) as BusReactor at Satna SS (for 765kV S/C Vindhyachal pooling station -Satna Ckt-2Transmission line).

Rihand-III and Vindhyachal-IV 14.01.2015

7 Installation of 1x315MVA, 400/220kV ICT-III at Bhadrawati HVDC Back-to-Back stationInstallation of Transformer &Procurement ofSpare Converter Transformer for B'wati HVDC

BTB Station19.03.2015

82 Nos 220 KV line bays at 400/220 KV Pirana Substation (for 220 KV Barajadi ckt#1 &2 Transmission line of GETCO).

AUGMENTATION OF TRANSFORMER ANDBAYS IN WESTERN REGION 21.03.2015

9 765 KV, 3*80 MVAR Bus Reactor at Bina Substation with associated bays TRANSMISSION SYSTEM FOR PHASE-IGENERATION PROJECTS IN ORISSA (PART-C)

01.04.2015

10

1. 765/400 kV Vindhyachal pooling station (New) including 3 x 500 MVA ICT # 2

2. 765 kV S/C Vindhyachal pooling station - Satna ckt#1 Transmission line andassociated bays at Vindhyachal pooling station along with 3 x 80 MVAr switchable linereactor. (Line Reactor at Satna substation already commissioned as Bus reactor w.e.f13/11/2014 under interim contingency, is now restored as line reactor).

3. 765 kV S/C Sasan – Vindhyachal pooling station Transmission line along withassociated bays at Vindhyachal pooling station and at Sasan Reliance.

4. Associated line bays at Vindhyachal pooling station for one ckt. of 400 kV D/C Sasan- Vindhyachal pooling station Transmission line (TL portion commissioned earlier w.e.f.01/01/2013 under interim contingency).

Rihand-III and Vindhyachal-IV 02.04.2015

11765 KV, 240 MVAR Bus Reactor-I at 765 KV Jabalpur Pooling Substation withassociated bays

TRANSMISSION SYSTEM FOR PHASE-IGENERATION PROJECTS IN ORISSA (PART-B)” 06.05.2015

12Wardha -Aurangabad 765kV Second D/c Line alongwith 2 nos.3x110MVArSwitchable Line Reactor at Wardha end & 1 nos. 3x80MVAr Line Reactors atAurangabad end & associated bays.

1.04.2015

131 No.3X80MVAr 765kV Wardha-Aurangabad Line Reactor of Circuit 4 atAurangabad end. 19.04.2015

Solapur-Pune(GIS) 765kV S/C Line along with associated bays & 240MVArSwitchable Line Reactor at Pune(GIS)(New)LILO of Parli -Pune 400kV D/c Line alongwith associated bays & 2X50MVArLine reactors at Pune(GIS)(new)New 765/400kV GIS Sub-station (New) at Pune765/400kV, 1500MVA ICT-I at Pune (GIS) (New)765/400kV, 1500MVA ICT-II at Pune (GIS) (New)765kV, 240MVAr Bus Reactor at Pune(GIS) (New )

Assets commissioned during 08.01.2015-06.05.2015

System-Strengthening in Wardha-AurangabadCorridor for IPP Generation Projects inChhattisgarh (IPP-G)

14 Krishnapatnam UMPP - Part-B 06.03.2015

• 400 kV Navsari – Magarwada Ckt. 2 - Part *• 400 kV Magarwada – Kala Ckt. 2 **• 400 kV Vapi - Kala Ckt. 2 - Part***

*400 kV Navsari – Magarwada Ckt. 2 (Total length commissioned : 20.084 Kms)

a) Part of One Circuit of M/C portion of 400 kV D/C Vapi-Kudus (WRSS#V) from AP18/0 – AP 23B/0 (4.20 Kms.)b) Part of 400 kV D/C LILO (M/C) portion (MAGARWADA Project) from AP 23B/0 toMagarwada GIS Gantry (15.884 Kms.) along with Navsari 2 bay at MAGARWADA GISSS.

**400 kV Magarwada – Kala Ckt. 2 (Total length commissioned : 53.331 Kms)

a) Part of 400 kV D/C LILO (M/C) portion (MAGARWADA Project) from AP 23B/0 toMagarwada GIS Gantry (15.884 Kms.) along with Kala Ckt. 2 bay at MAGARWADA GISSS.b) Part of One Circuit of M/C portion of 400kV D/C Vapi-Kudus (WRSS#V) from AP23B/0 – AP 38/0 (14.96 Kms.)c) Part of 400 kV D/C portion of Navsari – Boisar (Mundra project) from AP 38/0 to AP43B/0 (11.193 kms)d) Part of one circuit of M/C portion of 400 kV D/C Navsari – Boisar (Mundra project)from AP 43B/0 to AP 45A/0 (2.28 Kms)e) Part of 400 kV D/C LILO (M/C) portion (KALA Project) from AP 45A/0 to Kala GISGantry (9.014 Kms.) along with Magarwada Ckt.2 bay at KALA GIS SS

***400 kV Vapi – Kala Ckt.2 (Total length commissioned: 41.647 Kms):a) Part of One Circuit of M/C portion of 400 kV D/C Vapi-Kudus (WRSS#V) from AP18/0 – AP 38/0 (19.16 Kms.)b) Part of 400 kV D/C portion of Vapi – Kudus (WRSS#V) from AP 38/0 to AP 43B/0(11.193 kms)c) Part of one circuit of M/C portion of 400 kV D/C Navsari - Boisar (Mundra Project)from AP 43B/0 to AP 45A/0 (2.28 Kms)d) Part of 400kV D/C LILO (M/C) portion (KALA Project) from AP 45A/0 to Kala GISGantry (9.014 Kms.) along with Vapi Ckt.2 bay at KALA GIS

WRSS V, MUNDRA, ESTABLISHMENT OF400/220 kV GIS S/S AT KALA IN UT DNH &

ESTABLISHMENT OF 400/220 kV GIS S/S ATMAGARWADA IN UT DD

01.03.20156

ANNEXURE 16

Page 62: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

S. No. Name of LTA Customer (Injecting utility) Generator/Load/Trader

Region Quantumof LTAgranted

LTA withtied upbeneficiaries

Name of thebeneficiaries

Whetherapplicableduring the

month

Remarks

NR ER WR NER SR TOTAL

1 ACB Limited Generator WR 243 200 Gujarat - - 43 - - 43 Yes2 Adani Power Limited Generator WR 342 0 NA 342 - - - - 342 Yes3 Adani Power Limited Generator WR 1495 1495 APL (Haryana). POC

charges payable byAPL, see remarks

- - - - - 0 Yes Based on CERC order dated 29/07/2013,for APL Mundra TPS stage #3 to HaryanaLTA, the APL would pay for the LTA of 1495MW at both Mundra TPS stage#3 injectionPOC rate as well as Haryana with drawlPOC rates.

4 Adani Power Limited Generator WR 200 0 NA - - 200 200 Yes5 ADHPL Generator NR 192 0 NA 192 - - - - 192 Yes6 BRPL (DVC Power) Load NR 100 100 BRPL - - - - - 0 Yes7 BRPL (DVC Power) Load ER 31 31 BRPL - - - - - 0 Yes8 BYPL (DVC Mejia U#7) Load NR 119.19 119.19 BYPL - - - - - 0 Yes9 BYPL (DVC Mejia U#8) Load NR 119.19 119.19 BYPL - - - - - 0 Yes Since BYPL is not making payment of

transmission charges, DVC is to be billedfor this quantum w.e.f. 01.09.2013. DVCwas informed by POWERGRID vide letterdtd 11.07.2013.

10 BYPL (DVC Power) Load NR 63 63 BYPL - - - - - 0 Yes11 BYPL (DVC Power) Load ER 19 19 BYPL - - - - - 0 Yes12 DD (NSPCL) Load WR 70 70 DD - - - - - 0 Yes13 DNH (NSPCL) Load WR 100 100 DNH - - - - - 0 Yes14 DVC (DVC Durgapur U#2) Generator ER 100 100 PSPCL - - - - - 0 Yes15 DVC (DVC Koderma U#1) Generator ER 50 50 Haryana - - - - - 0 Yes16 DVC (DVC Mejia U#7) Load ER 12.5 12.5 DVC - - - - - 0 Yes17 DVC (DVC Mejia U#8) Load ER 12.5 12.5 DVC - - - - - 0 Yes18 DVC (MPL U#1) Load ER 140.5 140.5 DVC - - - - - 0 Yes19 DVC (MPL U#2) Load ER 140.5 140.5 DVC - - - - - 0 Yes20 EMCO Energy Limited Generator WR 520 400 EMCO(MSEDCL) &

EMCO (DNH)PoC Charges payable

by EMCO, SeeRemarks

- - 120 - - 120 Yes 1. LTA commencement w.e.f. 10.12.2012as per CERC Order dtd 21.02.14 in Pet.127/MP/2013. (2) LTA of 200MW was tiedup with MSEDCL by EMCO w.e.f.17.03.2014, however the transmissioncharges for this 200MW shall be payableby EMCO. (3) LTA of 200 MW was tiedup with DNH by EMCO, commenced w.e.f07.07.2014 as per WRLDC letter, howeverthe transmission charges for this200MW shall be payable by EMCO

21 Haryana (DVC Mejia U#7) Load NR 50 50 Haryana - - - - - 0 Yes22 Haryana (DVC Mejia U#8) Load NR 50 50 Haryana - - - - - 0 Yes23 Haryana (PPCL) Load NR 140 140 Haryana - - - - - 0 Yes24 Himachal Sorang Generator NR 100 0 NA 100 - - - - 100 Yes25 HPSEB(BASPA) Load NR 300 300 HPSEB - - - - - 0 Yes

200 Haryana CTU vide Letter drd 29.04.14 (Copyenclosed), indicated no objection foroperationalizing 200MW to Haryana fromLTA of 704 MW of JPVL, w.e.f 01.05.2014.Transmission charges shall be paid byJPVL only.

200 UPPCL CTU vide Letter drd 30.05.14 (Copyenclosed), indicated no objection foroperationalizing 200MW to UPPCL fromLTA of 704 MW of JPVL, w.e.f 01.06.2014.Transmission charges shall be paid byJPVL only.

ANNEXURE-18/1LTA Status for the month June, 2015

Quantum for target Regions (MW) - for LTA withuntied beneficiaries

176 - - 304 Yes26 Jaiprakash Power Ventures Limited(JPVL) Generator NR 704 128 -

Page 63: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

S. No. Name of LTA Customer (Injecting utility) Generator/Load/Trader

Region Quantumof LTAgranted

LTA withtied upbeneficiaries

Name of thebeneficiaries

Whetherapplicableduring the

month

RemarksQuantum for target Regions (MW) - for LTA withuntied beneficiaries

27 Jaypee Karcham Hydro Power CorporationLimited (JPVL)

Generator NR 176 104 Rajasthan Discoms 72 - - - - 72 Yes CTU vide Letter drd 29.09.2014 (Copyenclosed), indicated no objection foroperationalizing 104MW to RajasthanDiscoms from LTA of JPVL, w.e.f01.10.2014. Transmission charges shallbe paid by JPVL only.

28 JINDAL Generator WR 500 0 NA - - 500 - - 500 Yes29 Lanco Anpara Generator NR 100 0 NA 100 - - - - 100 Yes30 Lanco Green Power Private Limited Generator NR 8.4 8.4 NA - - - - - 0 Yes31 Lanco Kondapalli PPL Generator SR 0 0 NA 0 - 0 - - 0 Yes 250MW relinquished by LKPL w.e.f.

14.08.2012 as per CERC Order dtd21.02.2014 in Pet. 63/MP/2013.

32 Maithon Power Limited (MPL U#1) Generator ER 140.5 0 NA - 140.5 - - - 140.5 Yes33 MPPTC (DVC Power) Trader WR 500 500 MP - - - - - 0 Yes34 NDPL (CLP Jhajjar) Load NR 124 124 NDPL - - - - - 0 Yes35 NDPL (DVC Power) Load NR 67 67 NDPL - - - - - 0 Yes36 NDPL (MPL U#1) Load NR 140.5 140.5 NDPL - - - - - 0 Yes37 NDPL (MPL U#2) Load NR 140.5 140.5 NDPL - - - - - 0 Yes38 NDPL (DVC Power) Load ER 20 20 NDPL - - - - - 0 Yes39 PTC (Budhil) Trader NR 61.6 0 NA 61.6 - - - - 61.6 Yes40 PTC(Lanco Amarkantak) Trader WR 300 0 NA - - 300 - - 300 Yes41 PTC(Malana-II/Everest Power) Trader NR 86 86 PSEB - - - - - 0 Yes42 Punjab (DVC Durgapur U#1) Load NR 100 100 PSPCL - - - - - 0 Yes43 Punjab (PPCL) Load NR 140 140 Punjab - - - - - 0 Yes44 Spectrum Coal & Power Generator WR 60 0 NA - - 60 - - 60 Yes45 Torrent Power Generator WR 300 100 MP - - 200 - - 200 Yes46 WBSEDCL (MPL U #1&2) Load ER 140.5 140.5 WBSEDCL - - - - - 0 Yes47 WBSEDCL (MPL U#1) Load ER 70 70 WBSEDCL - - - - - 0 Yes48 WBSEDCL (MPL U#2) Load ER 70 70 WBSEDCL - - - - - 0 Yes49 Adhunik Power & Natural Resources Ltd Generator ER 100 100 WBSEDCL - - - - - 0 Yes50 Tata Steel Ltd (DVC, Mejia B) Load ER 100 100 Tata Steel - - - - - 0 Yes

51 Tata Steel Ltd (DVC, DSTPS) Load ER 100 100 Tata Steel - - - - - 0 Yes

52 Jindal Power (Chattisgarh) Generator WR 150 150 TANGEDCO - - - - - 0 Yes Transmission charges shall be paid byJPL only

53 JPVL - Nigri STPS (Unit#1) Generator WR 232.65 232.65 MPPMCL - - - - - 0 Yes LTA to MPPMCLto be considered 232.65MW from 21.09.2014 onwards

54 JPVL - Nigri STPS (Unit#2) Generator WR 232.65 232.65 MPPMCL - - - - - 0 Yes LTA to MPPMCLto be considered 232.65MW from 07.05.2015 onwards

55 MB Power Generator WR 197.4 197.4 MPPMCL - - - - - 0 Yes LTA to MPPMCLto be considered 197.4MW from 20.05.2015 onwards

Total 9771.08 7035.98 995.6 140.5 1599 0 0 2735.1

9771.08

Note : 1. The above information is based on LTA intimation/Letter issued by CTU to different applicants. For billing purpose, the same may be verified by RLDCs/RPCs/NLDC and addition / deletion of LTA/MTOA to the above,noticed if any, may please be informed for n.a.

2. The above does not include the MOP allocation. As per Regulations, ISTS Transmission charges are not applicable for Solar Projects, therefore LTA for Solar Projects is not included.

200MW LTA effective from 01.06.2014.

Page 64: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Remarks

Entity / Location ofGenerating Station

Region Entity / Location ofLoads

Region

1 WBSEDCL Baghlihar, Jammu & Kashmir NR 100 01.07.2012 30.06.2015 WBSEDCL, West Bengal ER

2 WBSEDCL Mejia Unit-7&8, DVC ER 200 01.05.2013 31.10.2015 WBSEDCL, West Bengal ER3 National Energy Trading and Service Ltd. Lanco Anpara Power Ltd., Uttar

PradeshNR 100 16.06.2013 31.05.2016 TANGEDCO, Tamil Nadu SR

4 Jindal Power Limited Jindal Power Limited, Chhattisgarh WR 200 16.06.2013 30.11.2015 TANGEDCO, Tamil Nadu SR

5 Adani Enterprises Limited Adani Power Limited Stage -III,Mundra, Gujarat

WR 200 16.06.2013 31.12.2015 TANGEDCO, Tamil Nadu SR

6 KSK Mahanadi Power Company Limited KSK Mahanadi Power Co. Ltd.,Chhattisgarh

WR 400 16.06.2013 15.06.2016 APCPDCL, Andhra Pradesh SR

7 WBSEDCL WBSEDCL ER 250 15.10.2014 31.07.2016 Bangladesh International Refer CTU letter dtd 13.05.2014.

8 Jindal Stainless Ltd Jindal Stainless Ltd, Odisha ER 30 01.01.2015 31.10.2015 Jindal Stainless Ltd, Hissar,Haryana

NR Refer CTU ltr dtd 23.09.2014

9 Jindal Stainless Ltd Jindal Power Limited, Duburi ER 10 01.03.2015 31.10.2015 Jindal Stainless Ltd, Hissar,Haryana

NR Refer CTU ltr dtd 10.12.2014

10 PTC India Ltd Balco, Korba, Chattisgarh WR 100 01.05.2015 28.02.2017 KSEB, Kerala SR Refer CTU Ltr dtd 23.04.2015 (MTOAenhanced from 58 MW to 100MW w.e.f01.05.2015)

11 UT of Daman-Diu NSPCL, Bhilai WR 22 01.04.2015 31.03.2016 UT of Daman-Diu WR Refer CTU Ltr dtd 10.12.2014

1612

ANNEXURE-18/2MTOA Status for the month June, 2015

Sl.No.

Name of the Applicant MTOAGranted for

(MW)

Date from whichMTOA is Granted

Date upto whichMTOA Granted

Injection of Power Drawl of Power

Page 1 of 1

Page 65: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

ANNEXURE-20

Status of Deviation Charges Payable/Receivable to WR Deviation Pool Fund Account

Last updated on 07/07/15

Total dues Payments overdue

Principal Principal

CSPDCL 1,09,03,746

MP Power Management Co. Ltd. -58,82,682

GETCO LTD. -1,06,07,487

MSLDC UI Settlement account 1,05,71,175

Goa -23,70,853

D&D 1,53,45,919 1,24,60,771

D&NH -3,62,090

NTPC -1,53,94,309

NR 78,47,37,354 38,56,09,221

SR 2,29,10,316

ER -29,31,19,206

JINDAL POWER LIMITED 80,97,072

HVDC Vin. -1,15,572

HVDC Bha. -1,05,453

Lanco Amarkantak Power Ltd 2,77,171

NSPCL -6,11,939

ACBIL 3,12,37,338 4,07,09,084

RGPPL -1

BALCO 90,94,649 12,88,260

CGPL UMPP MUNDRA -15,51,500

Page 66: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

DCPP JSPL 53,24,010

Essar Power MP Ltd 22,08,96,949 22,00,94,934

SASAN Power limited -60,47,100

KSK Mahanadi -20,84,856

Vandana Vidyut Ltd 8,46,74,245 8,45,79,936

EMCO Energy ltd. 35,59,410 42,88,659

KORBA WEST POWER Corp. LTD 2,04,54,581 1,91,87,624

D. B.Power 6,96,189 1,67,005

JAYPEE NIGRI TPP 3,43,71,678

Essar Steel India Ltd 1,04,21,803 81,87,693

DGEN (Torrent Energy Limited) 8,68,866 6,35,628

GMR Chhattisgarh Energy ltd 27,26,257 8,19,562

Dhariwal Infrastructure Ltd. 14,16,984 11,31,564

RKM Powergen Pvt Ltd. -1,294

MB Power (Madhya Pradesh) Ltd. 15,13,323 3,81,769

Jhabua Power Ltd 1,81,89,810 1,58,43,650

SKS POWER GENERATION(CHHATTISGARH) LTD 1,38,701 66,532

Note : This includes :

1. DSM Accounts issued upto 12th week of 2015-16 ie., 15.06.15 TO 21.06.15.

2. DSM Payments received and distributed upto 06.07.15

Page 67: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

ANNEXURE 20A

Status of Reactive Energy Charges Payable to REC Pool Account

Last updated on 07/07/15

(+) Payable / (-) Receivable from Pool

Amount in Rs.

Total dues Total overdues

Principal Principal

GETCO -2,61,399

MPMPCL 0

CSPDCL 46,372

MSEDCL 0

Goa 0

DD 0

DNH 2,15,027

TOTAL 0 0

*When Receivables are more than payable, total of all receivables made equal to payable.

*When all are receivable, all receivables made zero .

Note : This includes :

1. REC Accounts issued upto 12th week of 2015-16 ie.,15.06.2015 to 21.06.2015

2. REC Payments received up to 6.07.15

Page 68: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Sr.No. PARTICULARS Feb-15 Mar-15 Apr-15 May-15 Jun-15

1 MAXIMUM FREQUENCY (Hz)

1.1 Integrated over an hour 50.22 50.37 50.23 50.32 50.31

1.2 Instantaneous 50.55 50.54 50.55 50.55 50.55

2 MINIMUM FREQUENCY (Hz)

2.1 Integrated over an hour 49.73 49.77 49.74 49.75 49.75

2.2 Instantaneous 49.58 49.52 49.50 49.55 49.60

3 AVERAGE FREQUENCY (Hz) 50.00 49.98 49.99 49.98 50.00

4.1 48.6 Hz 0 0 0 0 0

4.2 48.8 Hz 0 0 0 0 0

4.3 51.0 Hz 0 0 0 0 0

5.1 Above 50.05 Hz 27.55 23.76 24.86 19.44 25.70

5.2 Between 49.9 Hz & 50.05 Hz 60.15 58.47 60.20 64.74 65.01

5.3 Below 49.9 Hz 12.30 17.77 14.94 15.82 9.29

5

PERCENTAGE TIME WHENFREQUENCY WAS

FEBRUARY 2015 TO JUNE 2015

ANNEXURE 21.1(a)FREQUENCY PARTICULARS OF WESTERN REGION FOR THE PERIOD

4

NUMBER OF TIMESFREQUENCY TOUCHED

Page 69: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15Availability (MW) 3468 3638 3677 3466 3209 12273 12719 13178 13188 13063 9033 6815 6984 7158 7121 18816 19804 19714 19722 19145

Unrestricted demand (MW) 3619 3817 3788 3748 3394 12277 12724 13207 13314 13177 9033 6815 6984 7159 7121 19146 19936 19933 19886 19290

Deficit(-)/Surplus(+) in MW -151 -179 -111 -282 -185 -4 -5 -29 -126 -114 0 0 0 -1 0 -330 -132 -219 -164 -145

Deficit(-)/Surplus(+) in % -4.17 -4.69 -2.93 -7.52 -5.45 -0.03 -0.04 -0.22 -0.95 -0.87 0.00 0.00 0.00 -0.01 0.00 -1.72 -0.66 -1.10 -0.82 -0.75

Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15Availability (MW) 433 465 552 467 449 297 301 301 278 281 679 714 740 720 725 42750 43145 42690 43240 41884

Unrestricted demand (MW) 435 466 583 467 450 297 301 301 278 281 679 714 740 720 725 42966 43580 43135 43538 42608

Deficit(-)/Surplus(+) in MW -2 -1 -31 0 -1 0 0 0 0 0 0 0 0 0 0 -216 -435 -445 -298 -724

Deficit(-)/Surplus(+) in % -0.46 -0.21 -5.32 0.00 -0.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 -0.50 -1.00 -1.03 -0.68 -1.70

Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15Availability (MUs) 1677 2128 2081 2097 1988 7378 8184 8775 9192 8088 3821 3481 3550 3722 4359 9672 10238 11599 12426 10883

Unrestricted Requirement (MUs) 1696 2160 2109 2128 2011 7378 8184 8775 9193 8088 3821 3481 3550 3722 4359 9841 10281 11649 12473 10915

Deficit(-)/Surplus(+) in MUs -18.81 -32.27 -28.03 -30.42 -23 0 -0.07 -0.21 -0.82 0 0 0 0 -0.09 0 -169.09 -43.28 -50.52 -46.91 -32

Deficit(-)/Surplus(+) in % -1.11 -1.49 -1.33 -1.43 -1.14 0.00 0.00 0.00 -0.01 0.00 0.00 0.00 0.00 0.00 0.00 -1.72 -0.42 -0.43 -0.38 -0.29

Details 

Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15Availability (MUs) 242 396 426 432 432 136 181 166 191 189 343 447 447 492 472 23269 25055 27045 28196 26411

Unrestricted Requirement (MUs) 242 396 427 432 432 136 181 166 191 189 343 448 447 492 472 23456 25130 27124 28275 26466

Deficit(-)/Surplus(+) : in MUs 0 -0.01 -0.73 0 -0.05 0 0.01 -0.01 -0.01 0 0 -0.02 0 -0.01 0 -187.9 -75.65 -79.48 -78.25 -55

Deficit(-)/Surplus(+) : in % 0.00 0.00 -0.17 0.00 -0.01 0.00 0.01 -0.01 -0.01 0.00 0.00 0.00 0.00 0.00 0.00 -0.80 -0.30 -0.29 -0.28 -0.21

ANNEXURE - 21.1(B)

Goa Daman & Diu Dadra & Nagar Haveli Western Region

Goa Daman & Diu

POWER SUPPLY POSITION IN WR FOR PERIOD FROM FEBRUARY 2015 TO JUNE 2015 (IN MUs) EX-BUS

POWER SUPPLY POSITION IN WR FOR PERIOD FROM FEBRUARY 2015 TO JUNE 2015 (IN EX-BUS MW)

Gujarat

Dadra & Nagar Haveli Western Region

Details 

Madhya Pradesh

POWER SUPPLY POSITION IN WR FOR PERIOD FROM FEBRUARY 2015 TO JUNE 2015 (IN MUs) EX-BUS

Details Chhatisgarh

POWER SUPPLY POSITION IN WR FOR PERIOD FROM FEBRUARY 2015 TO JUNE 2015 (IN EX-BUS MW)Maharashtra

Maharashtra

Details Chhatisgarh Gujarat Madhya Pradesh

Page 70: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

400 kV S/S KasorMonth Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min

Feb-15 424 394 419 389 440 400 435 383 422 397 422 405 421 403 414 391

Mar-15 423 397 418 394 440 400 439 382 424 398 424 400 424 400 418 391

Apr-15 421 390 419 388 438 397 436 386 421 394 423 405 424 401 412 389

May-15 420 393 419 386 437 394 434 391 417 393 422 400 422 400 412 388

Jun-15 427 392 424 393 438 402 438 395 427 396 430 400 429 401 415 392

400 kV S/S Bina Gwalior NagdaMonth Max Min Max Min Max Min Max Min Max Min Max Min Max Min Max Min

Feb-15 422 394 416 389 426 394 430 394 773 744 790 749 795 748 795 753

Mar-15 421 400 416 388 425 398 429 399 772 746 793 747 798 751 792 754

Apr-15 420 395 411 386 424 393 433 397 777 742 789 742 792 727 795 749

May-15 423 396 417 386 424 396 430 398 768 748 789 746 794 740 797 745

Jun-15 422 396 413 385 429 391 430 402 793 746 796 750 792 746 793 750

Dhule

Voltages at the important 400 and 765 kV substations during the period February 2015 TO JUNE 2015

Asoj Bhilai

GWALIOR (765 kV) BINA (765 kV)Khandwa Sipat (765 kV) Seoni (765 kV)

ANNEXURE - 21.2

JetpurIndore Itarsi Karad

Page 71: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

1 01-Feb-15 0 0 0 0 0 0 0 02 02-Feb-15 0 0 0 0 0 0 0 03 03-Feb-15 0 0 0 0 0 0 0 04 04-Feb-15 0 0 0 0 0 0 0 05 05-Feb-15 0 0 0 0 0 0 0 06 06-Feb-15 0 0 0 0 0 0 0 07 07-Feb-15 0 0 0 0 0 0 0 08 08-Feb-15 0 0 0 0 0 0 0 09 09-Feb-15 0 0 0 0 0 0 0 0

10 10-Feb-15 0 0 0 0 0 0 0 011 11-Feb-15 0 0 0 0 0 0 0 012 12-Feb-15 0 0 0 0 0 0 0 013 13-Feb-15 0 0 0 0 0 0 0 014 14-Feb-15 0 0 0 0 0 0 0 015 15-Feb-15 0 0 0 0 0 0 0 016 16-Feb-15 0 017 17-Feb-15 0 0 0 0 0 0 0 018 18-Feb-15 0 0 0 0 0 0 0 019 19-Feb-15 0 0 0 0 0 0 0 020 20-Feb-15 0 0 0 0 0 0 0 021 21-Feb-15 0 0 0 0 0 0 0 022 22-Feb-15 0 0 0 0 0 0 0 023 23-Feb-15 0 0 0 0 0 0 0 024 24-Feb-15 0 0 0 0 0 0 0 025 25-Feb-15 0 0 0 0 0 0 0 026 26-Feb-15 0 0 0 0 0 0 0 027 27-Feb-15 0 0 0 0 0 0 0 028 28-Feb-15 0 0 0 0 0 0 0 0

Max 0 0 0 0 0 0.0 0 0Total 0 0 0 0 0 0 0 0

1025 91 490 851

ANNEXURE -21.3/1Under Frequency Operation in various Constituent System of Western Region during the month FEBRUARY 2015

NIL NIL NIL

( Compiled from the data received from the constituents)Sl. No Date Gujarat Chhattisgarh

Recommonded Load relief at49.2 Hz / 49.0/48.8/48.6 Hz

Madhya Pradesh Maharashtra

Page 72: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

1 01-Mar-15 0 0 0 0 0 0 0 02 02-Mar-15 0 0 0 0 0 0 0 03 03-Mar-15 0 0 0 0 0 0 0 04 04-Mar-15 0 0 0 0 0 0 0 05 05-Mar-15 0 0 0 0 0 0 0 06 06-Mar-15 0 0 0 0 0 0 0 07 07-Mar-15 0 0 0 0 0 0 0 08 08-Mar-15 0 0 0 0 0 0 0 09 09-Mar-15 0 0 0 0 0 0 0 0

10 10-Mar-15 0 0 0 0 0 0 0 011 11-Mar-15 0 0 0 0 0 0 0 012 12-Mar-15 0 0 0 0 0 0 0 013 13-Mar-15 0 0 0 0 0 0 0 014 14-Mar-15 0 0 0 0 0 0 0 015 15-Mar-15 0 0 0 0 0 0 0 016 16-Mar-15 0 0 0 0 0 0 017 17-Mar-15 0 0 NIL NIL NIL 018 18-Mar-15 0 0 0 0 0 0 0 019 19-Mar-15 0 0 0 0 0 0 0 020 20-Mar-15 0 0 0 0 0 0 0 021 21-Mar-15 0 0 0 0 0 0 0 022 22-Mar-15 0 0 0 0 0 0 0 023 23-Mar-15 0 0 0 0 0 0 0 024 24-Mar-15 0 0 0 0 0 0 0 025 25-Mar-15 0 0 0 0 0 0 0 026 26-Mar-15 0 0 0 0 0 0 0 027 27-Mar-15 0 0 0 0 0 0 0 028 28-Mar-15 0 0 0 0 0 0 0 029 29-Mar-15 0 0 0 0 0 0 0 030 30-Mar-15 0 0 0 0 0 0 0 031 31-Mar-15 0 0 0 0 0 0 0 0

Max 0 0 0 0 0 0.0 0 0Total 0 0 0 0 0 0 0 0

1025 91 490 851

Maharashtra

ANNEXURE -21.3/2

5Under Frequency Operation in various Constituent System of Western Region during the month MARCH 2014

Gujarat ChhattisgarhSl. No Date Madhya Pradesh

Recommonded Load relief at49.2 Hz / 49.0/48.8/48.6 Hz

Page 73: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

1 01-Apr-15 0 0 0 0 0 0 0 02 02-Apr-15 0 0 0 0 0 0 0 03 03-Apr-15 0 0 0 0 0 0 0 04 04-Apr-15 0 0 0 0 0 0 0 05 05-Apr-15 0 0 0 0 0 0 0 06 06-Apr-15 0 0 0 0 0 0 0 07 07-Apr-15 0 0 0 0 0 0 0 08 08-Apr-15 0 0 0 0 0 0 0 09 09-Apr-15 0 0 0 0 0 0 0 0

10 10-Apr-15 0 0 0 0 0 0 0 011 11-Apr-15 0 0 0 0 0 0 0 012 12-Apr-15 0 0 0 0 0 0 0 013 13-Apr-15 0 0 0 0 0 0 0 014 14-Apr-15 0 0 0 0 0 0 0 015 15-Apr-15 0 0 0 0 0 0 0 016 16-Apr-15 0 0 0 0 0 0 017 17-Apr-15 0 0 NIL NIL NIL 018 18-Apr-15 0 0 0 0 0 0 0 019 19-Apr-15 0 0 0 0 0 0 0 020 20-Apr-15 0 0 0 0 0 0 0 021 21-Apr-15 0 0 0 0 0 0 0 022 22-Apr-15 0 0 0 0 0 0 0 023 23-Apr-15 0 0 0 0 0 0 0 024 24-Apr-15 0 0 0 0 0 0 0 025 25-Apr-15 0 0 0 0 0 0 0 026 26-Apr-15 0 0 0 0 0 0 0 027 27-Apr-15 0 0 0 0 0 0 0 028 28-Apr-15 0 0 0 0 0 0 0 029 29-Apr-15 0 0 0 0 0 0 0 030 30-Apr-15 0 0 0 0 0 0 0 0

Max 0 0 0 0 0 0.0 0 0Total 0 0 0 0 0 0 0 0

1025 91 490 851

( Compiled from the data received from the constituents)Sl. No Date Gujarat Chhattisgarh

Recommonded Load relief at49.2 Hz / 49.0/48.8/48.6 Hz

Madhya Pradesh Maharashtra

ANNEXURE -21.3/3Under Frequency Operation in various Constituent System of Western Region during the month APRIL 15

Page 74: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

1 01-May-15 0 0 0 0 0 0 0 02 02-May-15 0 0 0 0 0 0 0 03 03-May-15 0 0 0 0 0 0 0 04 04-May-15 0 0 0 0 0 0 0 05 05-May-15 0 0 0 0 0 0 0 06 06-May-15 0 0 0 0 0 0 0 07 07-May-15 0 0 0 0 0 0 0 08 08-May-15 0 0 0 0 0 0 0 09 09-May-15 0 0 0 0 0 0 0 0

10 10-May-15 0 0 0 0 0 0 0 011 11-May-15 0 0 0 0 0 0 0 012 12-May-15 0 0 0 0 0 0 0 013 13-May-15 0 0 0 0 0 0 0 014 14-May-15 0 0 0 0 0 0 0 015 15-May-15 0 0 0 0 0 0 0 016 16-May-15 0 0 0 0 0 0 017 17-May-15 NIL 0 NIL NIL NIL 018 18-May-15 0 0 0 0 0 0 0 019 19-May-15 0 0 0 0 0 0 0 020 20-May-15 0 0 0 0 0 0 0 021 21-May-15 0 0 0 0 0 0 0 022 22-May-15 0 0 0 0 0 0 0 023 23-May-15 0 0 0 0 0 0 0 024 24-May-15 0 0 0 0 0 0 0 025 25-May-15 0 0 0 0 0 0 0 026 26-May-15 0 0 0 0 0 0 0 027 27-May-15 0 0 0 0 0 0 0 028 28-May-15 0 0 0 0 0 0 0 029 29-May-15 0 0 0 0 0 0 0 030 30-May-15 0 0 0 0 0 0 0 031 31-May-15 0 0 0 0 0 0 0 0

Max 0 0 0 0 0 0.0 0 0Total 0 0 0 0 0 0 0 0

1025 91 490 851Recommonded Load relief at

49.2 Hz / 49.0/48.8/48.6 Hz

( Compiled from the data received from the constituents)Sl. No Date Gujarat Chhattisgarh Madhya Pradesh Maharashtra

ANNEXURE -21.3/4Under Frequency Operation in various Constituent System of Western Region during the month MAY 15

Page 75: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

No. ofOccasions

Max Load Reliefat 49.2 Hz

1 01-Jun-15 0 0 0 0 0 0 0 02 02-Jun-15 0 0 0 0 0 0 0 03 03-Jun-15 1 3.2 0 0 0 0 0 04 04-Jun-15 1 2.7 0 0 0 0 0 05 05-Jun-15 0 0 0 0 0 0 0 06 06-Jun-15 0 0 0 0 0 0 0 07 07-Jun-15 0 0 0 0 0 0 0 08 08-Jun-15 0 0 0 0 0 0 0 09 09-Jun-15 0 0 0 0 0 0 0 0

10 10-Jun-15 0 0 0 0 0 0 0 011 11-Jun-15 0 0 0 0 0 0 0 012 12-Jun-15 0 0 0 0 0 0 0 013 13-Jun-15 0 0 0 0 0 0 0 014 14-Jun-15 0 0 0 0 0 0 0 015 15-Jun-15 0 0 0 0 0 0 0 016 16-Jun-15 0 0 0 0 0 0 017 17-Jun-15 1 100.6 NIL NIL NIL 018 18-Jun-15 0 0 0 0 0 0 0 019 19-Jun-15 0 0 0 0 0 0 0 020 20-Jun-15 0 0 0 0 0 0 0 021 21-Jun-15 0 0 0 0 0 0 0 022 22-Jun-15 0 0 0 0 0 0 0 023 23-Jun-15 0 0 0 0 0 0 0 024 24-Jun-15 0 0 0 0 0 0 0 025 25-Jun-15 0 0 0 0 0 0 0 026 26-Jun-15 0 0 0 0 0 0 0 027 27-Jun-15 0 0 0 0 0 0 0 028 28-Jun-15 0 0 0 0 0 0 0 029 29-Jun-15 0 0 0 0 0 0 0 030 30-Jun-15 0 0 0 0 0 0 0 0

Max 1 100.6 0 0 0 0.0 0 0Total 3 106.5 0 0 0 0 0 0

1025 91 490 851

ANNEXURE -2.3/5Under Frequency Operation in various Constituent System of Western Region during the month JUNE 15

( Compiled from the data received from the constituents)Sl. No Date Gujarat Chhattisgarh Madhya Pradesh Maharashtra

Recommonded Load relief at49.2 Hz / 49.0/48.8/48.6 Hz

Page 76: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy

Details Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15

Unrestricted demand(MW) 3417 3472 3489 12100 12137 12555 6555 6853 7593 19200 19100 19540Availability (MW) 3556 3576 3656 12513 12257 12829 8755 9292 9750 18961 19220 19960Deficit(-)/Surplus(+)

(i) MW 138 104 167 413 121 274 2200 2439 2157 -239 120 420 ( ii) % 3.89 2.91 4.58 3.30 0.98 2.13 25.13 26.24 22.13 -1.26 0.63 2.10

Details Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15

Unrestricted demand(MW) 490 490 495 310 300 295 725 735 745 43497 43787 45412Availability (MW) 490 484 501 310 299 301 724 736 746 46009 46563 48443Deficit(-)/Surplus(+)

(i) MW 0 -6 6 0 -1 6 -1 1 1 2512 2777 3031 (ii) % 0.04 -1.32 1.17 0.05 -0.45 1.84 -0.19 0.11 0.15 5.46 5.96 6.26

Details Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15

UnrestrictedRequirement (MUs) 2040 1986 2050 7650 7257 7276 4370 4559 4944 11679 11981 11503Availability (MUs) 2103 2050 2140 7757 7235 7317 5084 5041 5201 12349 12460 11748Deficit(-)/Surplus(+)

(i) MUs 63 64 90 107 -22 41 714 482 257 671 479 244 (ii) % 2.98 3.11 4.21 1.38 -0.30 0.57 14.04 9.56 4.94 5.43 3.84 2.08

Details Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15 Jul-15 Aug-15 Sep-15

UnrestrictedRequirement (MUs) 290 285 290 195 187 186 478 480 480 27223 27255 27233Availability (MUs) 294 276 285 203 190 189 481 484 484 28791 28256 27867Deficit(-)/Surplus(+)

(i) MUs 4 -9 -5 8 3 3 3 4 4 1568 1001 635 (ii) % 1.23 -3.33 -1.74 3.93 1.54 1.83 0.60 0.82 0.73 5.45 3.54 2.28

WESTERN REGIONGOA DD DNH

MAHARASHTRA

ANNEXURE -22ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JULY 2015 TO SEPTEMBER 2015 (IN MW)(EX-BUS)

DD

CHATTISHGARH

CHATTISHGARH

GOA WESTERN REGION

MADHYA PRADESH

GUJARAT

GUJARAT

DNH

MADHYA PRADESH MAHARASHTRA

ANTICIPATED POWER SCENARIO IN WR FOR PERIOD FROM JULY 2015 TO SEPTEMBER 2015 (IN MUs)(EX-BUS)

Page 77: u - wrpc32 Chief Operating Officer(O&M), Adani Power Ltd Ahmedabad 079-25557176 33 Joint Managing Director, ACB(India)Ltd., Gurgaon. 0124-2719185 34 Director, Adani Enterprises.Ltd(Energy