UMTS_RNS_I_02_20090530 Node B Equipment Survey Process and Environmental Acceptance ZTE University

UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Embed Size (px)

DESCRIPTION

UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Citation preview

Page 1: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

UMTS_RNS_I_02_20090530Node B Equipment Survey Process and Environmental Acceptance

ZTE University

Page 2: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview

Project Survey Process

Project Environment Survey Guide

Node-B (NB09) Project Survey Guide

Quality Control of Project Survey

Content

Page 3: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview

Project survey is the initial stage of the whole project.

“Well begun is half done.” It has direct influence on every link of the project

afterwards. Introduction

Purpose: To provide normalized instructions on the process, item and method of the project survey; to offer a uniform survey standard to ensure good preparation; and to make sure the project survey plays its due role

Contents: Process, steps, methods, and filling in forms

Page 4: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview Project survey:

Ensures accurate production scheduling and timely delivery according to contract.

Is the original basis for data configuration and debugging of production lines.

Is the basis of project design. Is the original material for the completion report. Is part of normalized project management.

Conducting no project survey, or wrong project survey, will result in: Delay in scheduling and production, and error in data

configuration. Delay in delivery, with excesses, shortages and omissions. Project suspension and material supply delay, so that the

installation personnel can do nothing but wait, and there is no installation solution confirmed by both parties, possibly causing changes of customer requirements, reworking, and refusal of acceptance.

Lack of original materials in the completion report. Lack of links in normalized project management.

Page 5: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview

Project Survey Process

Project Environment Survey Guide

Node-B (NB09) Project Survey Guide

Quality Control of Project Survey

Content

Page 6: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Project Survey Flowchart

Project Survey Plan

Start

Preparing for project survey

Making project survey plan

Conducting field project survey and first environmental acceptance

Producing survey documents

Reviewing the survey

Qualified?

Handling documents

End

Project Survey Guide

Contract Problem Feedback

Project Survey Report

Environmental Acceptance Report

Review Form of Project Survey

ReportGuide for Project

Survey Report ReviewNo

Yes

Page 7: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Description of Project Survey Process

Preparing for Project Survey Purpose: To ensure smooth project survey Person in Charge: Project survey engineer Responsibilities:

1. Accepting tasks, receiving materials, and understanding requirements

2. Taking charge of consultation, understanding, and communication

3. Keeping in touch with the customer to know on-site situations and identify conditions

– Actions to take under poor survey conditions– Actions to take under good survey conditions

4. Drafting a Project Survey Plan 5. Making survey tools and meters ready 6. Carrying survey documents

Page 8: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Project Survey Process

Making Project Survey Plan Purpose: To conduct planned project survey Person in Charge: Project survey engineer Output document: Project Survey Plan Responsibilities:

Holding a project survey briefing Making a Project Survey Plan Being ready for carrying out the project survey

Page 9: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Project Survey Process

Conducting Field Project Survey and First Environmental Acceptance Purpose: To ensure that the field survey meet

specifications Person in Charge: Project survey engineer Input Document: Project Survey Guide Responsibilities:

Conducting field survey, with the customer involved, to record on-site information and data

Conducting first check of equipment operating environment

Defining installation environment requirements Knowing preparations of both parties for the project

Page 10: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Project Survey Process Producing Survey Documents

Purpose: To ensure production debugging and accurate delivery, and to guide project construction and commissioning, serving as the basis of producing project design documents

Person in Charge: Project survey engineer Output document: Project Survey Report (Scheduling & Delivery Data), Project

Survey Report (Project Design Information), Project Survey Report (Commissioning Data), Environmental Acceptance Report, and Contract Problem Feedback

Responsibilities: Collating and filling in survey data according to the requirements specified in

Project Survey Guide; signing in the Project Survey Report and in the First Environmental Acceptance column of the Project Survey Report after both the customer and ZTE reach an agreement on the results of the survey and environment acceptance

Communicating and negotiating with the customer, asking them for advice to reach an agreement, and listing important things into the project survey memorandum

Providing the customer with a copy of the documents Filling in the Contract Problem Feedback to help the business manager and the

customer solve problems upon discussion if the result of the survey does not conform to the contract

Submitting the Project Survey Report

Page 11: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Project Survey Process Reviewing the Survey

Purpose: To ensure the integrity, compliance, and correctness of the project survey data

Person in Charge: Project survey assessment engineer Input Document: Guide for Project Survey Report Review Output document: Review Form of Project Survey Report Responsibilities:

Assessing the integrity, compliance, and correctness of the Project Survey Report

Filling in the Review Form of Project Survey Report Revising the survey documents in any unqualified Project

Survey Report, and repeating field survey if necessary until it meets the requirements

Submitting the qualified Project Survey Report to project survey engineer for filing

Submitting the Review Form of Project Survey Report to project survey engineer for filing

Page 12: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Project Survey Process Handling Documents Purpose: To file the survey results and provide them to the

departments that need them Person in Charge: Project survey engineer/document controller Responsibilities:

SendingProject Survey Tasks,Project Survey Plan,Project Survey Report (Scheduling & Delivery Data), Project Survey Report (Project Design Information), Project Survey Report (Commissioning Data), Environmental Acceptance Report, Survey Problem Feedback,and Review Form of Project Survey Report to document controller for filing

Submitting Project Survey Report (Scheduling & Delivery Data) to the involved Planning Department of the Product Division

Submitting Project Survey Report (Project Design Information) to project design manager

Submitting Project Survey Report (Commissioning Data) to commissioning engineer

Submitting Environmental Acceptance Report to project supervisor for a second environmental acceptance

Page 13: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview

Project Survey Process

Project Environment Survey Guide

Node-B (NB09) Project Survey Guide

Quality Control of Project Survey

Content

Page 14: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Requirements for Equipment Room Environment

Basic Environment of Equipment Room High temperature, heavy dust, harmful gases, explosives, low air pressure,

strong vibration or noise, and high-voltage electrical equipment The equipment room must be built at the location that meet the engineering

design requirements of the communication equipment. A long-term view should be taken before construction. Do not relocate the equipment room unless necessary. Durability should be considered to avoid frequent renovations. The equipment room must be fireproof and shockproof.

Construction, structure, heating, ventilation, power supply, lighting and fire protection are required.

MPT specifications must be followed. The equipment room should be designed for the convenience of the cabling

and daily maintenance of the signal cable and power cable, to reduce cabling cost and communcation failure and improve working efficiency.

General Information of Equipment Room Location of equipment room Type of equipment room Route for equipment to enter the equipment room Equipment unloading area

Page 15: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Working Environment Survey

Temperature, Humidity and Daylighting of Equipment Room Short-term working condition (temperature): -5C~+55C. A

temperature between +15 ~+30 is always ℃ ℃recommended.

Short-term working condition (humidity): 20%~90%. A humidity between 40~65 is always recommended.

Direct sunlight should be avoided. There should be no glare. Generally, the equipment room is lighted by fluorescence lamps. For an equipment room where a power failure frequently occurs, an emergency light should be installed at a proper location.

Survey Description: Generally, Node-B equipment rooms are unattended, so

fluorescence lamps are used for lighting.

Page 16: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Indoor Environment Survey Equipment Room Floor and Fire Protection

The bearing capacity of the equipment room floor should be higher than 450kg/m2.

The equipment room must be equipped with appropriate fire fighting devices, such as several dry powder fire extinguishers.

Antistatic raised floorboards or antistatic terrazzo should be laid in the equipment room. Conductive floorboards should be used instead if raised floorboards are unavailable. Static grounding must be performed for conductive or raised floorboards, which should be connected to a grounding device through a current-limiting resistor and a connecting wire.The resistance of the current-limiting resistor should be 1MΩ.

Survey Description: If antistatic floorboards are used in the equipment room, the floor height should

be checked. Doors/Windows/Walls of Equipment Room

The door should be over 2.0 m high and over 1 m wide. The doors and windows must be sealed with anti-dust rubber strips. It is

recommended to use tightly sealed double-glass windows. The walls and the ceiling should be free from pulverization, dust and peeling.

Decorative materials applied on the walls should be fire-retardant. Survey Description: There should be some space on the walls because wall-mounting DDFs or

ODFs are requied sometimes.

Attention!

Page 17: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Indoor Environment Survey Cabling Routes and Reserved Holes The amount, location and size of hidden pipes, troughs and

holes reserved in the equipment room should fit various cables and follow the engineering design. Damp-proof measures should be taken for all troughs, with edges and corners well trimmed. Lighting and power cables should be laid in a hidden way.

Check to see if there is a hole for the antenna feeder system to enter the equipment room. If no, check whether such a hole can be made. The position and size of the hole must be marked.

Construction Power Supply Requirements All equipment rooms should be equipped with 220V/2000W

power supply for construction. Multifunctional sockets with both two-pin and three-pin jacks should be provided.

Survey Description: An AC power supply is required during construction. Check

the voltage and frequency of the power supply, and note the socket type (in the form of picture).

Page 18: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Indoor Environment Survey Equipment Room Air Conditioning

An air conditioning system should be installed in the equipment room. The heat radiation in the equipment room and the refrigerating output of the air

conditioning can be calculated as follows: 1. Heat radiation of the equipment: Q1=0.82VA (kcal/h)

– Where:– Q1 is the head radiation of the equipment.– V is the DC power supply voltage (V).– A is the average power consumption current (A).– The value 0.82 is the product of 0.86 (the scaling factor for converting every

watt of electrical energy into heat energy) and 0.95 (the scaling factor for converting electrical energy to heat energy in the equipment room).

2. The refrigerating output of the equipment room: Q2=S×150 (kcal/h)– Q2: The refrigerating output of the switching room– S: The area of the switching room (M2)– 150: The parameter for converting room area to refrigerating output

(Kcal/h×M2) 3. The refrigerating output of the air conditioning (actual capacity): Q=Q1+Q2

Survey Description: Different models of equipment has different requirements on ambient temperature and

humidity. For detailed information, refer to the corresponding equipment technical manuals. Generally, it is required to install an air conditioning system in the equipment room. If an air conditioning system exists, the power of the air conditioning and the heat radiation of the existing equipment should be noted during survey. If the existing air conditioning system cannot meet the requirements of the new equipment, additional air conditioners are required. The air conditioners should run automatically once powered.

Page 19: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

General Information of Antenna Feeder Plane

Antenna feeder plane: the surface on which the outdoor antenna feeder system is installed

Survey Items: Rooftop Bearing capacity of the antenna feeder plane Ways to reach the antenna feeder plane Pole-mounted mode Tower-mounted mode Maximum wind speed Weather conditions Height of the antenna feeder plane Electromagnetic Environment

Page 20: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Auxiliary Facilities Lightning-Protection Grounding

Joint lightning-protection grounding is used, with a grounding resistance of no higher than 5Ω.

Outdoor cabling racks, poles, and towers Lightning-Protection grounding principle, length of the

grounding cable, grounding mode, and rust prevention Grounding bar of lightning-Protection Ground

Functions and installation position Survey Description: The principle for BS equipment grounding is to make indoor

grounding and outdoor grounding separately. If the customer cannot provide outdoor grounding bars, a note should be written during the survey to say that the grounding bars will be provided by ZTE. Generally, one site provides one outdoor grounding bar. Outdoor grounding bars are directly connected to outdoor cabling racks or lightning-protection networks.

Page 21: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Auxiliary Facilities Tower

Requirements: A tower is required if a tower-mounted

antenna is used. Tower provider The design and instillation should

meet the telecommunication system specifications.

160KM/H Professional tower provider The tower must be grounded and

lightning-protected according to technical specifications.

The grounding resistance of the tower must meet the requirements.

The installation height of the lightning arrester must meet the requirements.

Survey items: Tower space Isolation from the existing antennas Spatial separation used Feeder routing Weight bearing and height

The antenna must be within the 45-degree protection range of the lightning arrester.

Attention!

Page 22: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Auxiliary Facilities

Pole A pole is used for rooftop antenna installation. The pole height should meet wind and ightning

protection requirements. Each pole should be connected to the lightning belt

separately, and should be rust-proof and corrosion-proof.

Survey Description: Pole diameter: 60 mm or above Accessory: lightning arrester Protective angle of the lightning arrester The length and specification of the pole's grounding

cable should be checked during the survey.

Page 23: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview

Project Survey Process

Project Environment Survey Guide

Node-B (NB09) Project Survey Guide

Quality Control of Project Survey

Content

Page 24: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Equipment Installation Information

Node B (B8200, BS8800) supports back-to-wall installation.

Cabinet Placement The commissioning side of the equipment should be

no less than 1.2 m away from other objects in front. Survey Description:

Enough space in all directions should be considered in cabinet positioning (depending on cabinet model). If the cabinet supports back-to-wall installation, small space or no space should be reserved in the back.

For cabinets that support back-to-wall installation: If there is enough space in the equipment room, a distance of 40-50 cm from the wall is recommended in the back.

Attention!

Page 25: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Equipment Installation Information

0.4-0.5m

1m

1m1.2m

Page 26: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Equipment Installation Information

Area of Equipment Room There should be enough space in the equipment room

for cabinet installation. The area of the equipment room should be larger than the base area of the cabinet, being equal to the sum of the base area and the required space in the front/back of the cabinet.

Enough space should be reserved for the main equipment, auxiliary equipment, and capacity exapnsion.

Page 27: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Equipment Installation Information

Equipment Room Size Measurement Measure the size and net height of the equipment room. Measure the positions and dimensions of the existing

equipment.

The net height refers to the vertical distance from the beam and air duct to the antistatic floor surface.

The net height should be no less than 2.5 m for upward cabling.

The net height should be no less than 2.2 m for downward cabling if antistatic floor is used.

The Node B equipment room has less demanding requirements than the central equipment room in terms of net height.

Attention!

Page 28: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Auxiliary Facilities

Cabling Rack The equipment room should be equipped with upward

cabling racks if upward cabling is used. Generally, the customer should provide cabling racks and finish installing them before rack (cabinet) installation.

The cabling racks should be about 2 m high and 300 mm~600 mm wide. The capacity planned for terminal offices should be considered when determining the rack width.

Survey Description: If the customer cannot provide indoor cabling racks,

the length and installation mode (ceiling-mounted or bracket-mounted) of the required cabling racks, as well as the length and specification of the grounding cables, should be surveyed.

Page 29: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Auxiliary Facilities DC Power Supply Equipment

Generally, a -48V DC power supply system should be provided by the customer. The power supply must meet the power requirement of the equipment, and provide surplus power for capacity expansion.

Batteries should be provided in the places where a power failure often occurs. The battery capacity should be selected according to the duration of power supply. Generally, a battery should have a capacity of four hours' power supply.

Survey Description: The power consumption of ZXWR NB09 in full configuration is

2,700 W. If the DC power supply equipment is provided by ZTE, a power supply survey is required.

The survey report template is provided by the Mobile Business Department. The survey should focus on the placement of the power supply equipment and the batteries, and the specification and length of the AC power cable from the AC power supply system to the DC power supply system.

ZXWR NB09 requires a DC voltage range of -57V~ -40V.

Page 30: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Auxiliary Facilities AC Power Supply System

Single-phase 220V or 3-phase 380V AC power supply should be used. Preferably, two separate mains should be used to ensure reliable power supply.

Generators should be provided in the places where a power failure often occurs. An AC power distribution box or a switch box should be provided. The AC power

supply system should be safe and reliable. Other Requirements of Power Supply System: The primary power supply system should have an alarm device, which will gives

visible and audible alarm signals if the power supply system is in abnormal condition.

Power cables should be kept intact, and any joint is unacceptable. Check to see if protective tubes should be used, and if signal cables will be laid

nearby. An appropriate surplus length should be reserved for the power cables between

the AC power distribution box and the equipment. Survey Description: Special attention should be paid to the voltage, frequency, and capacity of the

AC power supply during the survey to see if they can meet the requirements. The length of the AC power cable should also be measured.

If the customer asks ZTE to provide the AC power distribution box or the AC air switch, such a requirement should be noted in the survey report, with specifications and models specified.

ZXWR requires an AC voltage range of: 380 V±10% (3-phase power supply), or 220 V±10% (single-phase power supply).

Page 31: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Auxiliary Facilities AC Power Supply System

Single-phase 220V or 3-phase 380V AC power supply should be used. Preferably, two separate mains should be used to ensure reliable power supply.

Generators should be provided in the places where a power failure often occurs. An AC power distribution box or a switch box should be provided. The AC power

supply system should be safe and reliable. Other Requirements of Power Supply System: The primary power supply system should have an alarm device, which will gives

visible and audible alarm signals if the power supply system is in abnormal condition.

Power cables should be kept intact, and any joint is unacceptable. Check to see if protective tubes should be used, and if signal cables will be laid

nearby. An appropriate surplus length should be reserved for the power cables between

the AC power distribution box and the equipment. Survey Description: Special attention should be paid to the voltage, frequency, and capacity of the

AC power supply during the survey to see if they can meet the requirements. The length of the AC power cable should also be measured.

If the customer asks ZTE to provide the AC power distribution box or the AC air switch, such a requirement should be noted in the survey report, with specifications and models specified.

ZXWR requires an AC voltage range of: 380 V±10% (3-phase power supply), or 220 V±10% (single-phase power supply).

Page 32: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Auxiliary Facilities Digital Distribution Frame (DDF) and Optical Distribution

Frame (ODF) If the DDF is provided by ZTE according to the project

interface, ZTE should survey the DDF. Placement DDF specifications - ZTE specially provides a reference list

for model selection. Generally, rack-type or cabinet-type is selected.

The length of the grounding cable of the DDF 75 ohms or 120 ohms. If the ODF is provided by ZTE according to the project

interface, ZTE should survey the ODF. Placement ODF specifications - ZTE specially provides a reference list

for model selection. Generally, rack-type or cabinet-type is selected.

The length of the grounding cable of the ODF Type of the Optical connector (optical ring flange)

Page 33: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Auxiliary Facilities

Transmission Equipment ZXWR Node B supports multiple transmission modes: Direct optical fiber connection Direct 2M cable connection SDH transmission-based connection ZXWR Node B provides two transmission interfaces:

STM-1 and E1. ZXWR Node B supports 75-ohm and 120-ohm

interfaces.

Page 34: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Cables and Materials

– Make sure the installation positions and cabling routes of the related equipment.

– General principles for cabling routes:» It should facilitate the wiring of signal cables and

power cables and routine maintenance.» It should make the lines as short as possible to avoid

detours.» It should help reduce wiring costs and

communication failures.– All cables must be kept intact, and any joint or transition

point is unacceptable.– A 10% surplus length should be reserved for all cables.

Attention!

注意!

Page 35: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Cables and Materials Grounding Cables Generally, the indoor grounding bar is installed on the lower part of the wall in the

equipment room. The protective grounding cable of the rack: 35 mm2 multi-strand soft copper wire; the cable

length should be the focus during the survey.

The protective grounding cable of the indoor cabling rack: 35 mm2 multi-strand soft copper wire; the cable length should be the focus during the survey.

The protective grounding cable of the DDF/ODF: 35 mm2 multi-strand soft copper wire; the cable length should be the focus during the survey.

The protective grounding cable of the power supply equipment: 35 mm2 multi-strand soft copper wire; the cable length should be the focus during the survey.

The protective grounding cable of the transmission equipment: 35 mm2 multi-strand soft copper wire; the cable length should be the focus during the survey.

The grounding downlead from the indoor grounding bar to the grounding body in the equipment room: 95 mm2 multi-strand soft copper wire, or 40 mm × 4 mm zinc-plated flat steel; the cable length should be the focus during the survey.

Note: Whether the grounding cables described in points 2, 3, 4, 5, and 6 is provided by ZTE or other companies should be made clear.

Page 36: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Cables and Materials Transmission Cables

Different transmission modes require different transmission cables, which should be selected during survey according to the applications.

The selection of transmission cables is specified in the Technical Proposal . Optical fiber connection: Single-mode tail fibers

BII board: SC connector; opposite end: Being determined according to actual applications, generally being FC connector

The number and length of tail fibers, as well as connector types, should be the focus during the survey.

2M cables: Node B mostly uses 2M cables for transmission. If Node B and RNC are in the same equipment room, direct connection is used

through 2M cables. If Node B and RNC are not in the same equipment room, indirect connection is

used through 2M cables from Node B to transmission equipment, and then to RNC.

Matching impedance: 75 ohms in China, 120 ohms abroad Opposite connectors and connector types: Being provided by the DDF supplier

or transmission equipment supplier Survey Focuses: Matching impedance of 2M cables, number and length of 2M cables, and

opposite connector types

Page 37: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Cables and Materials DC Power Cables

- 48VDC racks There are two types of DC power cables: - 48V working grounding cable (GND) and - 48V power

cable (- 48V). Focus during survey: diameter, specification, and length of power cables. The cable diameter can be calculated as follows: S=∑I×2L/ ( × U△ )

S: Cross section of power cables (mm2) ∑I: Total current L: Effective length of the feeder (M) △U: Permissible voltage of the feeder (v) : Conductivity of the feeder For copper core cables, =54.4, For aluminum core cables, =34 Value range of U:△ From battery to DC power supply: U≤0.2V△ DC power supply: U≤0.2V△ From DC power supply to DC power distribution cabinet: U≤0.8V△ From DC power distribution cabinet to switch rack: U≤0.4V△

Power cable specifications: 1, 1.5, 2.5, 4, 6, 10, 16, 25, 35, 50, 70, 95, 120, and 185 (unit: mm2)

Generally, 25 mm2 cables are used as DC power cables for the racks; 35mm2 cables are used as protective grounding cables for the equipment. Fire-retardant cables should be used.

A back-up power supply should be provided if there are two ways of separate DC power inputs. -48V power cable: 25 mm2 multi-strand soft copper core power cable; fire-retardant; blue -48V working grounding cable: 25 mm2 multi-strand soft copper core power cable; fire-retardant;

black The length of the power cables should be the focus during the survey. If the length exceeds 100 m, 35 mm2 fire-retardant, multi-strand soft copper core power cables

should be used instead.

Page 38: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Survey of Indoor Cables and Materials

AC Power Cables If ZTE provides the primary power supply equipment, it

should also provide the AC power cable from the primary power supply equipment to the AC power distribution box.

The length of the AC power cable from the primary power supply equipment to the AC power distribution box should be measured during the survey. Generally, a 16 mm2 four-core fire-retardant cable is used. For more details, refer to the survey report sumbitted by the primary power supply equipment supplier.

It is required to lay the AC power cable and other cables separately, with a distance of over 150 mm away from each other. If separate cabling is impossible, a shielding tube must be used. The length of the shielding tube should be noted during the survey.

Page 39: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Installation Survey

Installation Position of Antenna Installation height, position, and orientation

Main Feeder Routing Check to see if the feeder routing is reasonable, if any

hidden danger exists, and if the installation is difficult. Outdoor Cabling Rack

Measure the length of the required cabling racks according to the cabling rack routing.

Check the length and Specifications of the grounding cable of the cabling racks.

Page 40: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Material Survey

Outdoor Materials: Antenna, tower amplifier, feeder, jumper, and

grounding clip Feeder clip and outdoor grounding bar

Page 41: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61
Page 42: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Material Survey Tower Amplifier A jumper from the antenna to the tower amplifier, as well as a

jumper from the tower amplifier to the main feeder, should be provided when configuring the tower amplifier. Currently, ZXWR NB09 (V3) has no tower amplifier.

If a tower amplifier is planned, it should be noted during the survey.

Jumper The 1/2”super-flexible jumper has fixed length. By default, the

rack-top jumper is 2 m long, and tower-top jumper is 3 m. Distribute the jumpers according to the site configurations

during survey. Feeder Measure the feeder length along the designed feeder routing. Generally, the main feeder is 7/8'' feeder cable, or 5/4'' feeder

cable if the length exceeds 60 m.

Page 43: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Material Survey Grounding Cables

Outdoor grounding bar: Check the number of the outdoor grounding bars.

– Generally, ZTE distributes one outdoor grounding bar to each site.

Grounding downlead of the outdoor grounding bar: 95 mm2 multi-strand soft copper wire, or 40 mm × 4 mm zinc-plated flat steel

– The cable length should be the focus during the survey. Outdoor equipment grounding cable: the grounding cable

from the lightning arrester busbar to the outdoor grounding bar

– 25 mm2 multi-strand soft copper wire; the cable length should be the focus during the survey.

Grounding cable of pole or tower lightning arrester: 40×4 mm zinc-plated flat steel

– Check the cable length, which should be the total length. The nearest grounding should always be made.

Page 44: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Material Survey

Number of Main Feeder Grounding Clips The number of the grounding clips depends on the

feeder length and routing. Feeder length: 5 m, 20 m, 60 m, and〈 60 m Installation modes: On-tower, rooftop, and horizontal

cabling

Page 45: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Outdoor Material Survey

Feeder Clips Triple feeder clip Double feeder clip The number of the feeder clips depends on the

feeder length.

Page 46: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms

Purposes To identify the environmental conditions, equipment

installation, cabling, and project tasks & responsibilities; to know all related details; to make preparations for scheduling, delivery and field installation.

Tasks Completing the survey on environmental conditions, floor plan

of the equipment room, cabling, original debugging data, and hardware installation interface.

Requirements The environment conditions should be fully described. The

installation position of each equipment should be identified. The number, length, and cabling route of every kind of cable should be checked. The installation interfaces for both parties should be identified.

Page 47: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-First Environmental Condition Survey

1.Conduct the first environmental acceptance according to the items specified in the Environmental Acceptance Report

2. For compulsory items, specified conditions must be provided by the customer. For the conditions that are currently not provided, a deadline should be negotiated by both parties.

3. For general items, it is unnecessary to "force" the customer to meet the environmental conditions, but it is necessary to explain the advantages/disadvantages to the customer. A deadline should be negotiated by both parties if the customer is capable of meeting such requirements.

Page 48: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-General Project Information

The project survey personnel should collect the following basic information and fill in the cover pages of all Project Survey Reports:

Contract No. Party A's name Party A's contact person Tel/fax Survey personnel Tel/fax The project survey personnel should collect the following basic

information and fill in the Site Information Forms of all Project Survey Reports:

Site name Equipmeng configurations Project types (including new construction, capacity expansion,

and reconstruction) Survey results and notes

Page 49: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Scheduling and Delivery Data

Collect scheduling and delivery data; fill in the Project Survey Report (Scheduling & Delivery Data)

The report should include such information as site name, configuration, floor height, number of racks, and length of digital trunk cable, fire-retardant power cable, grounding cable, optical fiber, and cabling rack.

Where: There are two types of optical fiber interfaces: LC/PC - LC/PC and LC/PC -

FC/PC. Fill the selected type(s) in the report according to the survey results. A 10% surplus length should be reserved for all cables. All power cables must be fire-retardant, with 25 mm2 (for power cables) and 35

mm2 (for protective grounding cables) in cross section. If the length of a power cable exceeds 100 m, a 35 mm2 power cable should be used instead. The length of the grounding cable should be the total length of all grounding cables.

The Project Survey Report (Scheduling & Delivery Data) must be sent back to the Planning Department of the Mobile Division.

Helping the Planning Department complete material clarification.

Attention!

Page 50: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Commissioning Data Collect information about equipment installation & commissioning;

fill in the Project Survey Report (Commissioning Data) Description of Networking Structure Diagram Drawing

Actual logic networking topology The networking structure diagram should be drawn according to the

technical agreement. Network topology should be confirmed by signature. Any possible changes must be noted in the diagram.

Drawing requirements: The networking modes among all NEs and networks, number of trunks, trunk type, signaling type, and number of links should be drawn in the diagram.

Visio or AUTOCAD should be used for drawing. Sometimes the diagram can be obtained from the pre-sales

support personnel or the technical proposal. Filling in the information about software installation and debugging

Some data is only available from the customer through negotiation. Some data is only available from RNC through negotiation. Some data is only available from network planning.

Such information should be filled in according to the actual situations.

Page 51: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Project Design Information

Collect information about equipment installation & commissioning; fill in the Project Survey Report (Project Design Information)

Page 52: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Project Design Information

– Description of Equipment Layout Drawing The layout describes the planimetric position of the equipment in all equipment

rooms. The dimensions and positions of all equipment, the distances between them,

and the reserved positions should be measured, marked and recorded carefully and accurately.

Unnecessary changes must not be made once the equipment positions are confirmed by both parties!

The customer must send a prior written notice to ZTE for any necessary changes.

Drawing Requirements: The size of the equipment should be marked in the layout.

The positions of ODF, DDF, transmission equipment, switching equipment and access equipment should be provided in the layout.

Old and new equipment should be drawn differently (described by text, or marked by bold or fine line).

The rack front, storey height, ceiling, and floor height should be marked. The position and size of holes, doors and windows should be marked. If the description is not clear by using a planar top view, a detail view can be

used instead. Both sketch and formal VISIO diagram should be produced. Copying this diagram is permitted.

Page 53: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Project Design Information

– Description of Cable Route Drawing It describes all cabling routes in the equipment room. It shows all cabling routes and modes, as well as detailed

cabling facilities. Unnecessary changes must not be made once the cabling

routes are confirmed by both parties! If cabling facilities are not in position, their installation locations

should be identified, and then marked and noted in a sketch. Drawing Requirements:

The cabling route from the digital trunk cable to the DDF should be marked.

Different types of cables should be marked differently. Both sketch and formal VISIO diagram should be produced. Copying this diagram is permitted.

Page 54: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Project Design Information

Installation and Cabling of Antenna Feeder System It is the schematic diagram of antenna feeder installation. Drawing Requirements:

The tower position, antenna (including GPS antenna) installation position, and parameters (such as tower height, platform height, pole height, and lightning arrester height) should be marked in the diagram.

The installation mode of the omnidirectional antenna, as well as the position and height of the lightning arrester, must be indicated.

The outdoor cabling rack routes should be drawn, with the length of all feeder segments being marked.

If the tower has not been installed yet, the customer should provide the tower blueprint and the cabling design.

All kinds of information can be marked in the diagram by text.

Sketch, and formal AUTOCAD or VISIO diagram should be produced.

Page 55: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Project Design Information

Construction Difficulty Description It describes the construction for which ZTE is responsible. The purpose is to

provide a brief explanation for the convenience of the construction afterwards. The outdoor cabling rack, feeder cabling, feeder window installation, and how

difficult it is to make a hole, should be described. Equipment securing and indoor cabling rack positioning should be explained. Equipment handling (including the route to reach the equipment room from the

ground, the highest floor that the cargo lift can reach, the distance for manual handling, width limit of the handling route, and precautions) should be described in detail.

Equipment Capacity Expansion Information The capacity expansion information includes a basic information form and a

board slot layout. Fill in the form with the basic configurations of the unexpanded equipment, making good preparations for the capacity expansion.

The cabinet type, height, color, shelf type, and wiring capacity of the equipment specified in the current contract should be marked.

The existing board positions should be marked. The required new cables and sub-shelves should be described in detail.

Page 56: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Filling in Survey Forms-Project Memorandum

Every report includes a memorandum. Communication engineering is rather complicated,

with many issues being involved. Extra, special, or unexpected problems or situations

will possibly happen. All these issues should be recorded into the Project

Survey Memorandum. Any special installation materials that are not

recorded in the Project Survey Report (Scheduling & Delivery Data) should be included into the memorandum.

The memorandum is very important. Forgetting to fill in it will probably result in serious consequences.

Page 57: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Overview

Project Survey Process

Project Environment Survey Guide

Node-B (NB09) Project Survey Guide

Quality Control of Project Survey

Content

Page 58: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Quality Control of Project Survey

Quality is the center of any work. The quality of the survey must be ensured. The quality of the project survey should be ensured

in two ways: Process quality Document quality

Page 59: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Process Quality Control Every step must be carried out according to the project survey

process. Project-related information should be collected carefully.

Project requirements, including general and key tasks, should be understood thoroughly.

The project survey process must be strictly followed. The survey should be scheduled and planned reasonably to ensure high efficiency.

The survey should be conducted together with the customer to obtain accurate original information about the site and understand special requirements and situations. Countermeasures should be planned to avoid emergencies during the survey.

Every possible resource should be fully used during the survey based on a good cooperation with the local ZTE office.

Site-related data should be measured and reorded accurately. All sites should be designed accurately to avoid delay or waiting due to unconformity during construction.

Page 60: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61

Document Quality Control

Document reflects the quality of your work.

» Integrity: Ensure the integrity of the documents.

» Accuracy: Ensuer the accuracy of the documents.

» Timeliness: Ensure the timeliness of the documents.

Page 61: UMTS_RNS_I_02_20090530-Node B Equipment Survey Process and Environmental Acceptance-61