Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
Underwater Defence Technology 2020
26-28 May
Rotterdam Ahoy, NL
Conference Theme - The Underwater Golden Triangle: Teamworking in the Underwater Domain.
There are many international aspects to the managing the trade-offs in design, as the Netherlands along with many other countries sees the need to work and collaborate internationally. The Netherlands policy makes clear that international cooperation is at the heart of the Netherlands development of its capabilities and in their future operational employment.
The Netherlands employs a “Golden Triangle” concept in its capability development. This approach encourages regular and institutionalised collaboration between the government, knowledge institutions and industry. UDT is a platform for the exchange of information and ideas between those working in the development and exploitation of undersea defence technology; it is the Underwater Golden Triangle.
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
UDT 2020 - Fast paced spiral development for the UK’s SSN(R),
part of the Royal Navy’s Maritime Underwater Future Capability
Annabelle Ransome-Williams1, Craig Bland 2
1 MUFC / SSN(R) Programme Manager , Submarine Delivery Agency, UK MOD, Bristol, UK 2 MUFC & Strategy Director, BAES SYSTEMS, Barrow-in Furness, UK
The UK’s SSBN deterrent submarines is well underway. In addition, the Maritime Underwater Future
Capability (MUFC) project has been established to assess future capability requirements and develop
options to perform operations and tasks within the underwater environment when the current Astute
Class Submarines leave service. With approval to proceed with the Design Phase achieved the
programme is embarking on the early submarine design phase which takes a fast-paced design spiral
approach to accelerate the submarine procurement. A collaborative approach has been adopted which
combines the complementary capabilities and capacities of the UK Ministry of Defence, BAE
SYSTEMS as the submarine designer and manufacturer, Rolls-Royce as the designer and manufacturer
of the nuclear propulsion plant and drawing on Babcock’s as the through-life support know-how. From
the earliest point, suppliers are to be engaged fully in the design effort, with a focus on optimising the
delivery arrangements alongside availability and sustainment considerations. This paper sets out the
background delivery principles, approach and some of the aspects for leadership and management
attention in the delivery of this programme
NOMENCLATURE
DRE Dreadnaught class
Joint Cost Model (JCM), the Jointly-Owned
Reference Design (JORD), the Design
Specification (JODS), the Joint Risk and
Opportunity Register (JROR)
IMBS Integrated Master Build Schedule
LFE Learning from Experience
MoD Ministry of Defence (United Kingdom)
MSTA Major System Technical Authority
MUOC Maintenance, Upkeep and Operating Cycle
NSRP Nuclear Steam Raising Plant
PDD Programme Definition and Design
SDA Submarine Design Authority
SSN(R) Ship Submersible Nuclear (Replacement)
TLC Through-life Cost
UPC Unit Price Cost
WBI Whole Boat Support Integration
WBTA Whole Boat Technical Authority
1 Background
Pre-concept MUFC work commenced in 2014.
Early wok focussed on development of Operational
Analysis and development of indicative SSN(R)
design solutions, notably the nuclear reactor plant
(NSRP). By 2017 the MUFC strategy recognised
that while SSNs remain the majority capability
solution, emerging technology offered enhanced
capabilities and led to consideration of non-SSN
capability elements. In August 18 MUFC formally
entered the Equipment Procurement Programme
with approval for year-1 of a 3-year initial concept
phase to develop SSN-options leading to the
endorsed Capability Requirement Document (under
Underwater Battlespace Capability Management
Group) in December 18.
2 Initial Concept Phase
The approach sought to involve industry in
exploring new and potentially radical
technological, operational and commercial
solutions to the challenges facing modern-day war-
fighting scenarios. In the face of sometimes rapid
technical, military and environmental changes the
challenges include:
a) Exploitation of the underwater
environment, including the challenges and
opportunities of underwater detection and
communication;
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
b) Improving availability, flexibility,
affordability and supportability of
capability solutions;
c) Optimising the time taken from concept
phase through design and to manufacture
of solution.
The design vision and ambition emerged and fully
embraced the mothership concept [1]: work
packages considered off-board sensors carried
(hosted) by a manned platform, vehicles that are
independent (autonomous) and/or deployed from
manned surface and air platforms.
Presently, we are about starting the follow-on work
- Programme Definition and Design (PDD) Phase.
The purpose of this three-year initial design phase
is to create a compelling, compliant, client-owned
solution for SSN(R) Full Design and succeeding
phases, which meets Customer requirements for: (i)
Warfighting Capability; (ii) Availability on time
and through life; (iii) Whole life cost efficiency;
(iv) Enterprise and boat sustainment; and (v)
Stakeholder confidence. It must do this in a way
which retains compliance with Industry corporate,
MOD and SDA governance requirements.
3 Introduction
The PDD Strategy requires a change in mindset
from previous projects at a similar stage, learning
from experience to meet challenging strategic
objectives to optimise the sustainment of in-service
capability through 2030 and beyond. It must
concurrently: refine a submarine design until
sufficiently mature to enter the Full Design stage
and define much improved delivery arrangements.
Control of the programme must be maintained
throughout, to deliver value-for-money outcomes
which provide a sound basis for the next phase.
4 SSN(R) Delivery Principles
The approach is based on six key agreed principles:
PRINCIPLE 1: SSNR programme is to be
delivered at pace
a. The management arrangements must be
designed to empower the project teams to make
effective and swift decisions, with appropriate
escalation and arbitration mechanisms
b. To enable pace the management arrangements
and establishment (mobilisation) must consider the
hard and soft systems to ensure that custom and
practice is moved on to set new norms of behaviour
c. Supporting processes must be more
innovative especially in understanding the nature of
change, benefits and associated risk.
d. Pace is to be reflected in the design iteration
drumbeat and Whole Boat Integration review
intervals.
e. Learning mechanisms are to be established
to ensure that economies of scale and scope with
Dreadnought (re-use) and knowledge pull-through.
PRINCIPLE 2: SSNR programme decisions are
a balance of schedule, cost, capability and in-
service availability
a. The decision-making arrangements are to be
designed to allow engineering aspects to be traded
against schedule (including build drumbeat), cost
(UPC and TLC), capability and in-service
availability.
b. The management arrangements are to
establish the requisite participants and supporting
systems to ensure an emphasis on design for cost,
and, design for maintainability.
c. Wider ecosystem will need to be considered
in determining good decisions, and making
transparent the full implications - engineering being
a single component of design focus.
d. Maximum re-use and minimal (most
beneficial) change principles should be exploited to
maximum effect in the programme and design
definition. To support effective change control, a
clear integrated baseline (design, build duration
and cost) is maintained throughout.
e. Ways to future-proof components, systems
and interfaces are to be addressed in the availability
and support workstreams.
PRINCIPLE 3: SSNR programme and design
definition is to be fully integrated with the
supply base
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
a. Programme definition is to provide a step-
change in the submarine enterprise supply chain
engagement, both existing and potential suppliers.
In doing so, the design phase is to innovate around
known problem areas.
b. Critical suppliers are to be engaged fully in
the whole boat design effort, from the earliest point
possible. Non-material aspects are to be fully
explored to identify programme benefits.
PRINCIPLE 4: SSNR programme ways of
working are fully collaborative
a. The definition phase is to be collaborative
across MOD, Tier 1s, wider supply base (Tiers 2-4)
and other stakeholders (e.g. users and other
experts), co-located at BAES-S (Barrow).
b. Key people (across the supply base) with the
requisite capability and aptitude for collaborative
working are to be seconded into the programme.
PRINCIPLE 5: SSNR Programme Integration is
a key value-adding capability
a. Programme Integration is a whole enterprise
activity centred around timely MOD decision
making in a controlled design evolution.
b. Common interfaces and standard protocols
are to be used to simplify Whole Boat Integration
and minimise complexity.
c. In-service availability is a key feature of
trade-off decision making, the programme is to
optimise the military capability against
commitments and capability coverage.
d. PDD scope of work is to be made clear
through definition of a plan comprising all
activities to deliver the outcomes and deliverables
against the Strategic Objectives. Whole Boat
Integration and Programme integration approach,
activities, scope and capability is to be defined.
PRINCIPLE 6: SSNR programme outputs will
positively support MOD approvals
a. The outcome is increased certainty and more
tightly bounded risk.
b. Options must be underpinned by realism and
developed in a way that makes transparent the full
implications of any choice.
c. Programme pace is to result in a good level
of product maturity to enable an incentivised
detailed design and build contract to maximise
confidence in the customer and approvals
community
Design Tension and Scope
The PDD Phase scope can be considered as two
‘types’ whose outputs must be integrated:
a. the refinement of the Reference Design
and delivery solution to a maturity suitable to
progress to the next phase
b. investigations focussed on improving the
design or delivery solution to be taken forward,
defined in terms of benefits to resilience, pace,
sustainment, cost-efficiency, quality and Submarine
Enterprise capability
Design tension exists between the tasks in that:
a. Challenging Strategic Objectives have
been set requiring overall improvements, a % in
time and cost for platform(s) delivery
b. Need to achieve an optimum balance
between re-use with the changes necessary to
make required improvements
c. Capacity, time and cost to achieve the
definition and design outcomes is constrained
d. With some possible exceptions, the
adoptions of investigation recommendations will
require reworking of the design, hence impacting
the pace of design maturity in exchange for benefit
realisation propositions. Also, many of the benefits
themselves are in tension
These outcomes will be articulated within the key
artefacts, namely the Integrated Master (Build)
Schedule (IMBS), the Joint Cost Model (JCM), the
Jointly-Owned Reference Design (JORD), the
Design Specification (JODS), the Joint Risk and
Opportunity Register (JROR) and the Delivery
Arrangements for the future programme.
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
5 The PDD Operating Model
The design and delivery arrangements taken
forward into the business case will be the result of
MOD decision-making, based on evidence and
proposals developed by collaborative
MOD/Industry design and focussed investigation.
During PDD, Design Authority will be held by
MOD for both the Submarine Design and the
Delivery Arrangements. The Reference Design
provided by MOD at the start of PDD has been
developed by the MOD-led Naval Design
Partnership. During Full Design, the intent is for
MOD to delegate the Technical Authority (TA)
role to Industry and therefore during PDD the 'TA-
in-waiting' will play a vital role in creating
solutions and making recommendations, gaining
deep, progressive experience and ownership of the
Reference Design. It is intended that at the end of
PDD the starting point for the next phase will be a
'Jointly Owned Reference Design' (JORD).
Figure 1: SSN(R)high level operating model
6 PDD Design Spiral Approach
To balance tensions, drive intensity and efficiency,
the approach is to adopt a fast-paced spiral
methodology. In addition, adopting enhanced
supplier engagement with particular focus on
exploring supply chain sustainability, optimisation
and capability.
Design approaches cover a number of key models:
waterfall, spiral, iterative/incremental models. The
Waterfall Model is the oldest and the most well-
known model. This model is widely used in
government projects and in many major companies.
The special feature of this model is its sequential
steps. In software and other industries, waterfall
model works well for projects where quality
control is a major concern because of its intensive,
but for submarine design the multi-functional
nature of the design problem hampers a more direct
design process to develop a design description to
such a level of detail that it can serve as the basis
for the production of a ship [2]. Also, the model is
hard to adapt for ill-defined re-use of previous
design elements and isn’t adaptable enough to
address ambiguity associated with technology
insertion and collaboration and structural aspects
leads to time and cost projection unacceptable to
the UK MOD. Iterative or incremental model
assumed that all customer capability features are
defined and that a core product is stable when
increased functionality is designed-in. The spiral
model is a development process which combines
elements of both design and prototyping in stages,
combining the advantages of top down and bottom
up design.
With express intent to accelerate the capability
timeline, the SSNR design phase has designed- into
the governance a 4-month spiral drumbeat and
builds on agile delivery methods. Empowered
cross-functional teams will work in parallel
workstreams, solving known problem and building
on opportunities using many sources of innovation
and novelty. The design and programme will be
integrated and (re)balanced at regular intervals to a
fixed governance drumbeat. Using a problem and
benefit focused activity, identifying solution
strategies aligned the strategic benefits against the
customer capability requirements. In this way the
approach combines naval architecture and systems
engineering [3] approaches in a complimentary
way, deriving the optimised requirement within the
programme time and cost parameters [4].
To increase programme pace, PDD strategy looks
to break the traditional separation of stages and
Phases to include preliminary design, system
design (functional and spatial). The phase is to be
cost and time constrained, against candidate key
user requirements which will be defined through
the design process, therefore, the only variable is
the maturity of system design.
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
Fig 2: PDD straddles the consecutive phases and
Stages in the submarine design
With significant variables a modern design for all
submarine functions and specifically considering
operational analysis necessitating aspects of
mothership core design [1] a rapid design spiral
with early design choices is essential. Design
decision logic mapped to the timeline will drive
focus and pace throughout the iteration drumbeat.
The staring position is to understand the extent of
previous design re-use to leverage economies of
learning, scale and scope with Dreadnought in
particular. With the input of a MOD owned
reference design the design work will focus on
delivering better value product with minimal
change and where change is benefit led approach
is adopted to understand what risk and reward is
expected. This process is designed to allowed
rapid progress of the design where it matters most,
capitalising on re-use where appropriate – see
Figure 2.
Figure 3: Design The spiral model (adapted for
submarine design)
7 The key aspects for implementation
A number of key aspects for management attention
during the implementation are summarised.
1. Scope of Work and Planning: the core design
development tasks, the re-use of existing design
and technologies, and benefits led assessment of
the areas for innovation and change. Sequencing
the areas for major change upfront allows the
design to be constrained early
2. Benefit and Risk Analysis: a process to identify
areas that matter most for design prototype solution
and design choices and trade-off space. Then to
determine work prioritisation (combination of risk,
investment and benefit trade-off) and order or
sequencing with dependencies identified.
3. Whole Boat Integration: the system and
functional aspects of the product are produced in
stove-piped teams, along with the testing and
recommendations. Every quarter the design is
brought together to look at the whole boat and
programme implications, seeking to balance the
design and find the conflict and trade-space
forming early good quality customer and supplier
decisions to lock down the variables and drive
design maturity.
4. Programme Integration (Evaluation) Phase: This
allows all parties to evaluate the programme
implications, specifically the P (design maturity,
safety and performance against capability
requirements/aspirations), T (time for platform
construction and fleet force projection) and C (unit
cost and whole life costs) parameters. This
understanding drives the focus and planning in the
next spiral.
Fundamentally important to the success of the
approach is collaboration and teamwork.
MOD with the two primary Industry Participants,
BAES – Submarines and Rolls Royce -Submarine
under a commercial Collaboration Agreement. A
tripartite framework commercially ties each party
to working together with the PDD phase
Contract(s) to which it is a party, to deliver the:
PDD Phase Strategic Objectives;
PDD Phase Outcomes;
PDD Phase Deliverables.
In working together to deliver the Collaborating
Parties agreed to:
act openly and in good faith;
make decisions under this Agreement to
achieve what is Best for SSN(R) Project
and the wider Submarine Enterprise;
11
SSN-R Programme Definition Phase Architecture
1 2 3 5 6 74A. Requirements and Targets
B. Programme Design & Definition
C. Approvals and Assurance
D. Procurement and Supply Chain
E. Build and Drumbeat
F. LFE & Capability Improvement
G. WB Design Maturity:
- WB Transversal & Standards
- Ship Systems
- Platform Systems
- NSRP
- Secondary Systems
- Ship Control
- Ocean Interface
- Combat Systems
- Cross Thematic Areas
H. Plat. Availability Improvements
I. Team Devel. & Improvements
Workstreams
12
Overview* 1-3 year duration PDD Phase* Define end-state targets for PDD and each year*Define focus and targets for each workstream; annual and each PI Block* Allocate £ per workstream per block but estimate per W/S total and each year*Define Control Account who holds ring for PCT & risk, and manage within timelines (CAM does not equal W/S)* Each W/S has PC/PM/BS & tech supt for toolsets
Go-live
Year 1Apr 20 Apr 21 Apr 22 Year 2 Year 3
OBC 2 LSD
8 129 10 11
2* Programme
Leadership Board (Q’ly)
1* Programme Management Board (Monthly)
2 * Leadership ALB
AMBSEDR
NED Challenge Function?
Final
Workstream Rules
- Within Sprint box, full autonomy
- No deviation outside box
- If < Target Maturity, allow 1 month
after WB/Prog Review to mend
- PM /PCE can redirect W/S if they
signal divergence from overall direction
Termly/4 monthly Month long Cross-W/S Integration
Programme Increment
(PI)
Pro
gra
mm
e /
P C
on
tro
ls (
Dri
vin
g th
ing
s in
rig
ht
way
)
Monthly
Sprint Cycles
PI and Sprint Cycle sets formal governance rules:
- Whole Prog Annual 2* review
- Termly 2*/1*
- Monthly 1*/
PM/PCE
Inte
grat
ive
Spri
nt
– P
rogr
amm
e w
ide
reba
lan
cing
, inc
l WB
Re
view
. Upd
ate
MD
AL,
Ris
ks,
Cos
t M
odel
. R
etro
spec
tive
an
d r
edir
ect.
Sta
rt e
ach
PI B
lock
afr
esh!
Ou
tco
me:
PC
T a
nd
Ris
k
Ou
tco
me:
PC
T a
nd
Ris
k d
efi
ne
d f
or
wh
ole
pro
gra
mm
e
1098
Inte
grat
ive
reba
lanc
ing
– P
rogr
amm
e W
ide
incl
udin
g W
hol
e B
oat
Rev
iew
. R
etro
spec
tive
, an
d re
dire
ct.
Star
t ea
ch P
I Blo
ck a
fres
h!
Incentives
Align incentive proposal around
hitting target maturity at end of
each year. If not, allow 3
months to recover, but then
incentive falls away quickly
Plat
form
Inte
grat
ion
Programme Increment
(PI)
Programme Increment
(PI)
PDD
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
work on an Open Team basis;
encourage co-operative behaviour between
themselves and their suppliers;
operate in accordance with the PDD Phase
Values and Delivery Principles.
All parties agree to carry out the following
activities:
fulfil their roles under the Collaboration
Agreement, and actively participate in the
Governance and Design Management
Arrangements;
work with the wider supply chain to help
sustain key skills, support innovation and
promote collaborative working where
necessary or conducive in the supply chain
and in accordance with law;
work together to make available such
facilities as may reasonably be required
develop the Project processes on an
ongoing basis to optimise scarce resources
8 Challenges
Designing future military capabilities including
submarine programmes requires increased
teamwork between platforms, industry participants
and inclusion of wider sector / non-sector expertise
to stimulate new ways of doing in a traditional
design and delivery environment with the
introduction of increasingly unmanned systems, the
programme approach to stimulate development of
technology and concepts to advance man/machine
teaming will be key to operational success. To this
end, programme approaches need to adapt to be
inclusive, adaptable and agile in how they employ
the best people in design and delivery and maintain
underwater military capability.
It is still early days for the programme; progress
made so far is extremely encouraging but not
without effort in some key areas:
Leadership and Culture. Developing a business
case and contract that in many ways goes against
the learnt behaviours is challenging. Seniors Leader
change leadership and advocacy on internal
approvals process and governance is required.
Strong leadership and middle management is
required to champion the aspects of a time-boxed
working enhanced collaboration and tolerance with
ambiguity, whilst ensuring the core competence of
submarine design is safeguarded and nurtured to
stretch capabilities.
New ways of working need to be enshrined through
new process development, new people are required
to bring forward wider experience and galvanise
development. a
Balance of Investment across Re-Use and
Change. The balance of re-use and change is
fundamentally important. Moreover, the ability to
make the most important change decision upfront
and in a well-informed way is imperative to drive
tight spiral of submarine design maturity to achieve
pace and efficiency. Re-use or pull through from
existing programmes is imperative to exploit Non-
reoccurring costs, optimise the economies of scale
and scope for consistency at a component level
(supply chain), training and operator knowledge
(operator and operations benefits) The change
needs to be minimal and focussed where it matters
most to enhance military capability whilst
optimising the cost of ownership. Early and robust
challenge panel on appropriate methods of
constraining change from the outset and
maintenance of position is an intrinsic part of the
process.
Balance of focus between Product and Delivery
Arrangements. Our submarine products are
complex – a great deal of systems, suppliers and
interfaces. The focus on delivery and the key areas
of tension, including critical dependencies needs as
much, maybe more, attention as the product design
– these are the areas that are sometimes left later in
the design cycle and can cause delay. They are
inherently difficult to identify and manage without
concerted effort and a wider variety of skills to
understand the interrelations, and, develop ways of
minimising and overcome. The team stricture was
developed to create dedicated teams outside main
system teams to maintain focus on key areas of
build strategy, cost of ownership, acceptance,
supply chain value etc, and multifunctional teams
executed beneficial activities
Decision making. In PDD programme decisions
are a balance of schedule, cost, capability and in-
service availability. The decision-making
arrangements are to be designed to allow
engineering aspects to be traded against schedule
(including build drumbeat), cost (NRE, UPC and
TLC), capability and in-service availability. The
management arrangements are to establish the
requisite players and supporting systems to ensure
an emphasis on design for cost, and, design for
maintainability – a healthy tension in this stage of
the lifecycle. To support effective change control,
UDT 2020
Fast paced spiral development for the UK’s
SSN(R) Presentation/Panel
a clear integrated baseline has been established and
will be used from the start of PDD to build a
mature jointly owned design, cost model and
master Design and Build (D&B) schedule. PDD
will analysed potential opportunities for build
duration and drumbeat compression to deliver the
full scope of the customer requirements at an
affordable cost. To this end, the phase outputs
including Platform and NSRP design maturity,
Build Strategies, a fully resourced Integrated
Performance Management Baseline (IPMB)
including cost assurance, and coherent and
effective management arrangements including
those to deliver design, acceptance and support
arrangements. Ways to future-proof components,
systems and interfaces are to be addressed in the
availability and supportability.
9 Concluding Remarks
Identifying the range of supply chain parties to be
involved and specific delivery and design
challenges is fundamental. Alignment of strategic
intent and programme and objectives needs to
follow, alongside the understanding of the focus of
design iteration and extent of re-use. The vision
must we set and believed to stretching but
achievable. Also, a benefit led approach is
essential to galvanise the collective will to
overcome inevitable points of tension. Pragmatic
delivery principles need to be flowed down
throughout the organisation to set the climate for
success. Fostering positive relationships,
encouraging open communication and embedding
supportive behaviours means project members and
parent organisations can change and flex to meet
inherent challenges without breaking down
In summary, the combination of vision, design and
planning and collaboration behaviours across non-
traditional and diverse skills establish a powerful
force for capability generation.
References
[1] R G Pawling and D J Andrews, A SUBMARINE CONCEPT DESIGN – THE SUBMARINE AS AN UXV
MOTHERSHIP Warship 2011 - Naval Submarines and UUVs. Royal Institution of Naval Architects, 2011. 1.
Web.
[2] Nordin, Mats. "A Novel Submarine Design Method - Based on Technical, Economical and Operational
Factors of Influence." (2014): 2014. Web
[3] Van Griethuysen, W. J., Marine design – can systems engineering cope? CMDC, 2000.
[4] Andrews, D. J., Marine Requirements Elucidation and the Nature of Preliminary Ship Design, pp. A23-A39,
Transaction of RINA 153, Part A1, London, 2011
Biographies
Craig Bland
Annabelle Ransome-Williams Annabelle is an established and experienced delivery lead and P3M
professional, with experience of private, public and third sectors. Annabelle has a track record delivering
strategically important programmes and projects, closing the gap between strategy, capability and capacity
through transformational results.