Update on FCPS Construction/Renovation Projects
May 2009
May 2009
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010 Contract Sum: $9,061,000
Change Orders to Date: $0
Current Phase: 1 (On Schedule)
May 2009
Cassidy Elementary – RenovationRendering of Final Façade
May 2009
Cassidy Elementary – RenovationWork Completed in Last 30 Days:
New staff parking lot @ Tates Creek Rd. cut to subgrade. Subgrade for new 2-Story Administration/Classroom Addition
completed and foundations begun. Original Stage and Music Room demolition complete. Miscellaneous interior demolition continued as needed.
Current Work Effort (May): Stone installed in new parking lot for temporary staging area. New Music Room/Mechanical Room Addition foundation and
concrete slab will be complete. New 2-Story Administration/Classroom Addition foundation and
concrete slab will be complete. Masonry to begin with concrete block walls on 2 additions. Underground sanitary and plumbing rough-in work to start under
new additions. Underground electric feeds and below slab rough-in to continue.
May 2009
Cassidy Elementary – RenovationNew 2-Story Admin Addition
foundationNew Staff Parking Lot subgrading,
Tates Creek Rd
May 2009
New Underground Detention System excavation
New Music Rm./Mech. Rm. Addition site
Russell Cave Elementary – Renovation
Architect: Pearson & Peters Architects
General Contractor: Congleton-Hacker Construction
Substantial Completion Date: August, 2010
Contract Sum: $5,001,150
Change Orders to Date: $0
Current Phase: 1
May 2009
Russell Cave Elementary – RenovationRendering of Final Façade
May 2009
Russell Cave Elementary – RenovationWork Completed in Last 30 Days:
Building pad and foundation bearing have been tested and approved.
Footings and foundation walls: 125 feet of footings have been poured and 61 feet of foundation wall have been poured.
Existing sprinkler line has been relocated.Current Work Effort (May):
Additional work on footings and foundation at the new addition will continue.
Installation of the new leach fields for the septic system will begin installation in the front lawn of the building.
New electrical conduits will be installed in the existing crawlspaces to feed wiring to new addition and the existing kitchen.
New cooler/freezer and hood roof curb for kitchen renovation is scheduled for delivery the week of June 8th. Work will begin as soon as school is out.
May 2009
Russell Cave Elementary – RenovationFoundation Work 5.5.09 Foundation Work 5.5.09
May 2009
Foundation Work 5.5.09
Foundation Work 5.5.09
Arlington Elementary – Renovation
Architect: RossTarrant Architects
General Contractor: W/S Construction
Substantial Completion Date: August, 2010
Contract Sum: $9,920,194
Change Orders: $36,900 (#1--Demo)
Current Phase: 1
May 2009
Arlington Elementary – RenovationRendering of Final Façade
May 2009
Arlington Elementary – RenovationWork Completed in Last 30 Days:
Demolition completedWork at Site to begin in mid-May
May 2009
Arlington Elementary – RenovationDemo – Main Bldg. Demo – Main Bldg.
May 2009
Demo – Gym Demo – Gym
Bryan Station Middle – Renovation
Architect: Clotfelter-Samokar Architects
General Contractor: Preston Construction Group
Substantial Completion Date: August, 2010
Contract Sum: $10,769,400
Change Orders to Date: $0
Current Phase: Phase 1 to begin June 1
May 2009
Bryan Station Middle – RenovationRendering of Final Façade
May 2009
Bryan Station Middle – RenovationWork Completed in Last 30 Days:
GC conducting preparatory activitiesWork at Site to Begin June 1
May 2009
Leestown Middle – Renovation
Architect: Lucas/Schwering Architects
General Contractor: D.W. Wilburn, Inc.
Substantial Completion Date: August, 2010
Contract Sum: $11,182,000
Change Orders to Date: $0
Current Phase: Phase 1a, 1b, 1c to begin June 1
May 2009
Leestown Middle – RenovationRendering of Final Façade
May 2009
Leestown Middle – RenovationWork Completed in Last 30 Days:
Pre-construction meeting held on 5/5/2009.Work at Site to Begin June 1
May 2009
Lafayette High Stadium – Replacement
Architect: Strand & Associates
General Contractor: Set to bid July 1
Substantial Completion Date: July, 2010
Contract Sum: TBD
Change Orders to Date: $0
Current Phase: Construction Documents
May 2009
Lafayette High Stadium – Replacement
UPDATED – Existing Campus
May 2009
Lafayette High Stadium – Replacement
UPDATED – Existing Football Stadium
May 2009
Lafayette High Stadium – Replacement
UPDATED – New Football Stadium
May 2009
Central Bus Garage – Adaptive Reuse
Architect: Lucas/Schwering Architects
General Contractor: James R. Leake & Sons, Inc.
Substantial Completion Date: August, 2009
Contract Sum: $2,782,000
Change Orders to Date: $0
Current Phase: Construction
May 2009
Central Bus Garage – Adaptive ReuseFaçade
May 2009
Central Bus Garage – Adaptive ReuseProposed Floor Plan
May 2009
Tonight’s Agenda ItemsProject Agenda Item
Arlington Elementary Approval of BG-4 – Final Payment to Contractor for Demolition Work Superior Demolition: $44,724.30 Total Demolition Cost: $124,148
Lafayette Stadium Approval of Design Development & Construction Documents Total Estimated Cost: $5,795,500
Liberty Elementary Approval of Change Order #5 Total Credit for Unused DPOs: ($17,392.32)
William Wells Brown Elementary
Approval of Change Order #7 Total Credit for Unused DPOs: ($13,041.47) Change to GC Contract: ($439.62)
May 2009