Project Report May 2012
Current Projects
Recently Completed Projects
CAMLS
Sun Dome Renovation
Engineering II Building Renovation
Intercollegiate Golf Team Practice Facility
Music – Visual and Performing Arts Facility
Campus Recreation Center Expansion and Southeast Dining Facility
Interdisciplinary Science Teaching and Research Facility
USF Athletic Facilities
Dr. Kiran C. Patel Center for Global Solutions
Project No.: Architect/Engineer: Construction Manager: Project Budget: Status: Projected Completion Date: Source of Funds:
518 Beck Group Beck Group $26,076,701 Construction February 2012 USF Financing Corporation
Description: This project is being constructed as a 90,000 square foot World- Class Education, Training and Research facility that provides a portfolio of activities to meet the needs of health professionals from students and residents to practicing clinicians, to continuing education.
Recently Completed Projects
CAMLS – Center for Advanced Learning & Simulation
Project No.: Architect/Engineer: Construction Manager: Project Budget: Status: Projected Completion Date: Source of Funds:
593 Populous Skanska $30,230,000 Construction April 2012 USF Financing Corporation
Description: Extend Life Expectancy of Existing Facilities, Upgrade Existing Building Systems – improving efficiency, Enhance User Experiences, Provide for Additional Events & Activities.
Recently Completed Projects
Sun Dome Arena & Convocation Center - Renovation
Project No.: Architect/Engineer: Construction Manager: Project Budget: Status: Partial Occupancy Projected Completion Date: Source of Funds:
- Williamson & Dacar Architects Williams Company $1,300,000 Construction August 2011 November 2011 USF / Engineering Department
Description: Renovation of the First Floor Lecture Hall, Hall of Flags, Conference Room, Interdisciplinary Lab, Corridors and Restrooms
Recently Completed Projects
Engineering II Building Renovation
Project No.: Architect/Engineer: Construction Manager: Project Budget: Status: Projected Completion Date: Source of Funds:
- TBD TBD $1,300,000 Request for Proposals June 2012 -
Description: A free-standing 1-story facility to house the practice, meeting, locker, changing rooms and equipment storage for the USF intercollegiate athletic Women and Men’s golf team and coaching staff.
Recently Completed Projects
Intercollegiate Golf Team Practice Facility
Project No.: Architect/Engineer: Construction Manager: Total Project Cost: Status: Occupancy: Source of Funds:
550 Hanbury Evans Wright+Vlattas I Performance Architecture Skanska $46,605,935 Completed February 2011 PECO
Description: The project includes facilities for educating approximately 400 music majors, as well as adequate specialized space to facilitate the unique performance needs in educating artists/musicians. The building includes a 500 seat concert hall, 100 seat student recital hall and practice rooms for small and large groups.
Recently Completed Projects
Music – Visual & Performing Arts Facility
Description: The project includes recreational and dining facilities between the campus recreational building and the USF Sun Dome.
Recently Completed Projects
Campus Recreation Center Expansion and Southeast Dining Facility
Project No.: Architect/Engineer: Construction Manager: Total Project Cost: Status: Occupancy: Source of Funds:
577 Canerday, Belfsky + Arroyo (Design/Build) Biltmore Construction (Design/Build) $17,101,507 Completed July 2011 CITF/Infrastructure/Student Funds/Business Services
Description: The space in this building is designed to promote interdisciplinary research and teaching. The project will support the Physics, Chemistry, and Biology programs, and will provide large multi-user interdisciplinary shared core facilities.
Recently Completed Projects
Interdisciplinary Science Teaching and Research Facility
Project No.: Architect/Engineer: Construction Manager: Total Project Cost: Status: Occupancy: Source of Funds:
534 HOK Skanska $80,232,583 Completed August 2011 PECO/USF Loan
Description: The project consists of the design, construction, and furnishings of the USF Athletics Complex project on the University of South Florida, Tampa Campus. The project includes improvements and facilities for intercollegiate basketball, baseball, softball, football and intramural recreation. The USF Athletics Complex project will include a Basketball Practice Facility, Baseball Stadium Improvements, a Softball Stadium, Soccer Stadium, Football Practice Fields and relocation of existing Recreation Fields.
Recently Completed Projects
USF Athletics Complex
Project No.: Architect/Engineer: Construction Manager: Total Project Cost: Status: Occupancy: Source of Funds:
579 Populous (Design/Build) R.R. Simmons Construction Corporation (Design/Build) $33,739,750 Construction May 2011 Loan
Recently Completed Projects
USF Athletics Complex
MUMA – Basketball Practice Facility
Baseball/Softball Stadium
Recently Completed Projects
USF Athletics Complex
Morsani Football Practice Fields
Soccer Stadium
Description: This project is established to promote sustainable, healthy communities. This facility will provide for USF World programs to develop research of the natural, social, and economic environments which have local, national, and global applications and guide future solutions and education in Florida and around the world; and contribute to improving the human condition.
Recently Completed Projects
Dr. Kiran C. Patel Center For Global Solutions
Project No.: Architect/Engineer: Construction Manager: Total Project Cost: Status: Occupancy: Source of Funds:
512 Ponikvar Associates (Design/Build) Charles Perry Construction (Design/Build) $23,751,995 Completed December 2010 Private Funding, State Match