40
July 2008 1 USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report Period 1st July 16, 2018 to September 30, 2018 Submission Date: October 15, 2018, revised October 29 & November 4, 2018 USAID Contract Number: AID-OAA-I-15-00047, Order: 72027818F00002 Contract/Agreement Period: July 16, 2018 to September 30, 2022 COR Name: Akram AlQhaiwi Submitted by: Rick Minkwitz, Chief of Party CDM International Inc. 73 Al Mutanabi St, Amman, Jordan Tel: 009626 4642720 Email: [email protected] This document was produced for review and approval by the United States Agency for International Development / Jordan (USAID/Jordan).

USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

July 2008 1

USAID JORDAN WATER INFRASTRUCTURE

Quarterly Progress Report Period 1st – July 16, 2018 to September 30, 2018

Submission Date: October 15, 2018, revised October 29 & November 4, 2018

USAID Contract Number: AID-OAA-I-15-00047, Order: 72027818F00002

Contract/Agreement Period: July 16, 2018 to September 30, 2022

COR Name: Akram AlQhaiwi

Submitted by: Rick Minkwitz, Chief of Party

CDM International Inc.

73 Al Mutanabi St, Amman, Jordan

Tel: 009626 4642720

Email: [email protected]

This document was produced for review and approval by the United States Agency for International

Development / Jordan (USAID/Jordan).

Page 2: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report
Page 3: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 3/31 October 15, 2018, revised October 29 & Nov 4,

2018]

CONTENTS

Contents .................................................................................................................... 3

Acronyms and Abbreviations ................................................................................ 5

1. Background ...................................................................................................... 7

a. Introduction .................................................................................................................. 7

b. Report Period ............................................................................................................... 7

2. Activity Overview .......................................................................................... 7

a. Activity Details ............................................................................................................ 7

b. Executive Summary .................................................................................................... 9

3. Activity Implementation .............................................................................. 11

a. Progress Narrative .................................................................................................... 11

b. Reporting Data and DevResults ............................................................................ 15

c. Implementation Challenges and Modifications Made/Issues Addressed from

Last Quarterly Report .............................................................................................. 15

4. Collaborating and/or Knowledge Sharing ................................................ 16

a. Collaboration and/or knowledge sharing with Other USAID Activities and

Partner Entities in Host Government and other Donor Agencies .................. 16

5. Assessments / Evaluations / Lessons Learned ........................................ 16

a. List Major Assessments / Internal Evaluations and Lessons Learned and

Actions and Way Forward ...................................................................................... 16

6. Planned Activities for Next Quarter .......................................................... 17

a. Proposed Tasks and Activities for the Next Quarter......................................... 17

7. Branding Communications and Dissemination ....................................... 19

a. Key Communication Activities - Specific Activities That Reflect Branding

Awareness for USAID ............................................................................................ 19

b. Branding ..................................................................................................................... 19

Page 4: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 4/31 October 15, 2018, revised October 29 & Nov 4,

2018]

8. Sustainability and Exit Strategy ................................................................. 19

9. ANNEXES ..................................................................................................... 20

Annex I Indicator Performance Tracking Table .......................................................... 20

Annex II Geographic Data Reporting – GIS Template .............................................. 25

Annex III Data Collection ................................................................................................ 26

Annex IV Training Report ................................................................................................ 28

Annex V Deliverables ....................................................................................................... 28

Annex VI Staff .................................................................................................................... 29

Annex VII Meetings .......................................................................................................... 30

Annex VIII Management and Administrative Issues .................................................. 30

Annex IX Sub-Award Details .......................................................................................... 30

Annex X Schedule .............................................................................................................. 30

Page 5: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 5/31 October 15, 2018, revised October 29 & Nov 4, 2018]

ACRONYMS AND ABBREVIATIONS

A&E Architect & Engineer

ADS Automated Directives System

AMELP Activity Monitoring, Evaluation, and Learning Plan

AWC Aqaba Water Company

BEO Bureau Environmental Officer

BOT Build, Operate, and Transfer

CAD Computer-Aided Design

CAPEX Capital Expenditure

CD Compact Disk

CDCS Country Development Cooperation Strategy

CDM Smith CDM International Inc.

CIRS Context Indicator Reference Sheet

CLA Collaborating, Learning and Adapting

CLIN Contract Line Item Number

CMC Construction Management Contract

CMS Construction Management Services

COP Chief of Party

COR Contract Officer Representative

CSO Civil Society Organization

DCOP Deputy Chief of Party

DDL Development Data Library

DEC Development Experience Clearinghouse

DESAL Desalination

DLS Department of Land and Survey

DO Development Objective

DOS Department of Statistics

DQA Data Quality Assessment

EA Environmental Assessment

EDCO Electricity Distribution Company

EIA Environmental Impact Assessments

EIB European Investment Bank

EMMP Environmental Monitoring and Mitigation Plan

ESMP Environmental and Social Management Plan

ESR Environmental Status Report

FARA Fixed Amount Reimbursement Agreement

FIDIC International Federation of Consulting Engineers

GESI Gender Equality and Social Inclusion

GIS Geographic Information System

GOJ Government of Jordan

GUC Grant Under Contract

HO Home Office

IEE Initial Environmental Examination

IM Implementing Mechanism

IPs Implementing Partners

IPS Intake Pump Station

IPTT Indicator Performance Tracking Table

Page 6: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 6/31 October 15, 2018, revised October 29 & Nov 4, 2018]

IR Intermediate Result

JICA Japan International Cooperation Agency

JRSP Jordan Red Sea Project (aka Jordan National Red Sea Water Program)

JVA Jordan Valley Authority

KAC King Abdullah Canal

KaMP Knowledge Management Portal

LF Logical Framework

LOE Level of Effort

MCM Million Cubic Meter

M&E Monitoring and Evaluation

MEL Monitoring, Evaluation and Learning

MEO Mission Environmental Officer

MIS Management Information System

MoEnv Ministry of Environment

MOH Ministry of Health

MPWH Ministry of Public Works and Housing

MWI Ministry of Water and Irrigation

NDA Non-Disclosure Agreement

NEPCO National Electricity Power Company

NGO Non-Governmental Organization

NICRA Negotiated Indirect Cost Rate Agreement

NRW Non-Revenue Water

O&M Operation and Maintenance

OPEX Operational Expenditure

PAD Project Appraisal Document

PDT Performance Data Table

PIRS Performance Indicator Reference Sheet

PMP Performance Management Plan

PMU Programme Management Unit

PPP Public Private Partnership

PPR Performance Plan and Report

PQM Project Quality Management

PRVs Pressure Reducing Valves

RF Results Framework

RFP Request for Proposal

RFTOP Request for Task Order Proposal

RSDS Red Sea Dead Sea Conveyance Project (also known as Jordan Red Sea Project)

RSS Royal Scientific Society

SCADA Supervisory Control and Data Acquisition

SOW Statement of Work

STC Special Tendering Committee

SWRO Seawater Reverse Osmosis Plant

TDY Temporary Duty

ToC Theory of Change

TOR Terms of Reference

USAID United States Agency for International Development

USG United States Government

WAJ Water Authority of Jordan

WMI Water Management Initiative

WWTP Wastewater Treatment Plant

YWC Yarmouk Water Company

Page 7: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 7/31 October 15, 2018, revised October 29 & Nov 4, 2018]

1. BACKGROUND

a. Introduction

USAID Jordan Water Infrastructure (the Project) is an indefinite delivery/indefinite quantity (IDIQ)

contract awarded to CDM International Inc. (CDM Smith) by United States Agency for International

Development (USAID) to cover all architectural and engineering (A&E) infrastructure development tasks

that USAID, in cooperation with the Ministry of Water and Irrigation (MWI)/Water Authority of Jordan

(WAJ), water companies, municipalities and Ministry of Environment (MoE), plans to carry out during

the project life span within selected areas of Jordan. The goal is to achieve USAID and Government of

Jordan (GOJ) strategic goals. USAID supports the water sector activities through improved infrastructure

and management. The objective is to help

USAID partners better plan their resources

to ensure best utilization of limited water

resources, develop strategic planning, build

capacity among their staff and improve

environmental protection through

improvements to the water and wastewater

infrastructure based on the most feasible

options to satisfy future growth. The scope

of work to achieve the goals and objectives

includes but is not limited to engineering

assessments; studies; site investigations;

network modeling; geographic information

system (GIS) development; energy studies;

designs; capacity building; and construction

management in the water, wastewater and

environment sectors.

b. Report Period

Quarterly Report No. 1 covers the USAID

Jordan Water Infrastructure activities from

July 16, 2018 to September 30, 2018, and

reports on activities accomplished during the period and activities anticipated to be accomplished during

the next quarter.

2. ACTIVITY OVERVIEW

a. Activity Details

USAID JORDAN WATER INFRASTRUCTURE

The Project commenced on July 16, 2018 and has an end date of September 30, 2022.The Project consists

of a 4-year 2-month, multiple-site, multiple project infrastructure investment program to deliver specific

improvements throughout Jordan. The Project is divided into the following nine tasks and the task’s

locations are shown on Figure 1-1:

Figure 1-1 Project Locations

Page 8: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 8/31 October 15, 2018, revised October 29 & Nov 4, 2018]

▪ Task 1 (Optional) - Providing services and support for the Red Sea Dead Sea (RSDS)

Conveyance Project – Phase II will consist of the development of a build-operate- transfer (BOT)

contract and designs for RSDS Phase II which will include connections to Phase I, a seawater

reverse osmosis treatment facility in Aqaba, transmission pipelines to Amman and pump stations.

Estimated start date to be exercised by USAID.

▪ Task 2 – Construction supervision – Shedeyyeh – Hasa Water Project Phase I located in central

Jordan will consist of construction management services (CMS) for the well drilling contract, and

precontract and CMS services for the design/build contract (WTP, wellhead completion and

pumps, wellfield pipelines). Estimated start date November 2018.

▪ Task 3 – Detailed engineering design and tender documents for expansion of Zai Water

Treatment Plant Project located at Deir Alla in the Jordan Valley and continues through Balq’a

Governorate to Amman. The task will consist of a feasibility report for the expansion of the Zai

water treatment plant project (WTP, PS, and transmission pipeline), existing conditions

assessments, and design and tender documents for the water supply system expansion. Start date

August 2018.

▪ Task 4 – Feasibility study, design, and tender documents for expansion of Madaba Wastewater

Treatment Plant (WWTP) will consist of a feasibility report for the expansion of the WWTP, a

reuse plan, existing conditions assessments, and design and tender documents for WWTP

expansion. Start date August 2018.

▪ Task 5 - Feasibility study, design, and tender documents for expansion of the Ramtha WWTP

will consist of a feasibility report for the expansion of the WWTP, a reuse plan, existing

conditions assessments, and design and tender documents for WWTP expansion. Start date

August 2018.

▪ Task 6 – Water and wastewater project for Deir Alla and Al Karameh located in the Jordan

Valley will consist of preparing detailed designs and tender documents based on a feasibility

study prepared by others under a European Investment Bank (EIB) funded program. Estimated

start date November 2018.

▪ Task 7 - Water and wastewater project for Bani Kenanah a district of Irbid Governorate will

consist of water and wastewater master planning, a feasibility report for the water/wastewater

infrastructure, and design and tender documents for the immediate and short-term needs

identified and agreed upon. Estimated start date February 2019.

▪ Task 8 (Optional) – Technical assistance to water utilities is to provide technical, financial,

customer service, energy efficiency, operation and maintenance (O&M), and other services as

requested. Estimated start date to be exercised by USAID. Activities under Task 8 could be

country wide and will be located on the project map once identified.

▪ Task 9 (Optional) - Assessment of water/wastewater systems, feasibility studies, designs,

tendering support and construction management services will cover additional A&E services as

identified and requested by USAID and in coordination with WAJ. Estimated start date to be

exercised by USAID. Activities under Task 9 could be country wide and will be located on the

project map once identified.

Page 9: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 9/31 October 15, 2018, revised October 29 & Nov 4, 2018]

b. Executive Summary

(a) Short Introduction

The Project commenced on July 16, 2018 and has an end date of September 30, 2022. The goal is

to achieve USAID and GOJ strategic goals. USAID supports water sector activities through

improved infrastructure and management. The objective is to help USAID partners better plan

their resources to ensure best utilization of limited water resources, develop strategic planning,

build capacity among their staff and improve environmental protection through improvements to

the water and wastewater infrastructure based on the most feasible options to satisfy future

growth.

The Project office has been established, staff levels appropriate for performing the work are in

place, and the collection of data will be ongoing throughout the Project. Significant record data

and reports have already been collected with the assistance of MWI/WAJ, Miyahuna, and

Yarmouk Water Company (YWC). Various coordination meetings and a workshop have been

held to inform all stakeholders of the scope of the work and to learn from the stakeholders of their

interests and priorities.

(b) Summary of Results for the Reporting Period and Key Achievements

Three of the nine tasks (Tasks 3, 4 and 5) were authorized for commencement on 1 August 2018

and two activities under Task 9 were requested by USAID on 13 September 2018. The executive

summary will provide results of the three tasks and the two activities under task 9.

(i) Task 3 –Expansion of Zai Water Treatment Plant Project

This task commenced on 1 August 2018 with the main objective of the task being to evaluate the

different options for increasing the capacity of the Zai water supply scheme which will allow for

the anticipated additional water quantities that will be available as a result of the swap agreement

between Jordan and Israel.

A coordination meeting was held on 17 September 2018 with MWI/WAJ and USAID.

MWI/WAJ advised that the additional anticipated water quantities planned to be available in the

KAC have not fully materialized to the point where additional water quantities would be available

for expanding of the Zai water treatment system. MWI/WAJ advised that additional available

water quantities in the KAC will be used by the Wadi Arab II Project. Therefore, as agreed upon,

there currently are no plans under task 3 to expand the system.

The agreed upon plan under task 3 is to complete the Zai water treatment system evaluation with

the intent to identify potential options to upgrade, rehabilitate and provide reliability to the system

for the future.

(ii) Tasks 4 and 5 –Expansion of Madaba and Ramtha Wastewater Treatment Plants

These two tasks commenced on 1 August 2018. The 2 tasks aim at the expansion of the Madaba

and Ramtha WWTPs to treat the projected wastewater flows until the year 2045. The tasks will

Page 10: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 10/31 October 15, 2018, revised October 29 & Nov 4, 2018]

consider population forecasts, and additional wastewater service areas planned to be connected to

the sewer network for Madaba and for Ramtha including proposed connection of the localities of

Turra, Shajarah and Emmrawah. within the planned horizon.

During the reporting period the planned approach was threefold:

1. Data collection

2. Facility and organizational assessments

3. Sampling program at each WWTP

At the end of the reporting period the Assessment Report was in preparation and a subcontract for

the sampling program was being finalized.

(iii) Task 9 (Optional) - Additional Architectural and Engineering (A&E) services

This optional task will commence when exercised by USAID. Two activities under Task 9 were

requested by USAID on 13 September 2018 as follows:

1. Technical assistance to support the Phase III expansion of the As Samra WWTP.

We met with MWI/WAJ and USAID on 17 September 2018 to discuss this new activity.

MWI/WAJ advised that Fichtner prepared a feasibility study for the Phase III expansion

of the As Samra WWTP.

At the meeting, MWI/WAJ requested the following assistance:

• Technical review: A technical review of the feasibility study

• Cost proposal review: A review of the construction cost proposal prepared by the

SPC for reasonableness

• Legal review: A review the SPC agreement with MWI/WAJ to advise on the

legal aspects of MWI/WAJ options for the expansion; specifically, the clauses

that may provide the SPC with priority over other contractors on the Phase III

expansion.

MWI/WAJ requested a Non-Disclosure Agreement (NDA) from CDM Smith to receive

the relevant documents to perform the review at the end of the reporting period.

2. Technical assistance to analyze and design energy interventions to support the water

sector.

We met with MWI/WAJ and USAID on 17 September 2018 to discuss this new activity.

MWI/WAJ advised that KfW funded a comprehensive study (by Dorsch) on the energy

efficiency in the water sector, including opportunities and projects for renewable energy.

We met with MWI/WAJ, the Dorsch representative and USAID on 23 September 2018

and agreed to follow-on meetings. The planned outcome of this initial review follows:

▪ Provide a GAP analysis to determine what studies and interventions related to

energy efficiency and renewable energy have taken place in the water sector,

Page 11: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 11/31 October 15, 2018, revised October 29 & Nov 4, 2018]

▪ Meet with Dorsch, NEPCO, and RSS, and

▪ Visit the Wadi Shalalah WWTP where it is understood renewable energy on

digestor gas has been implemented.

Other potential activities, discussed at the 17 September 2018 meeting none of which have been

authorized, included:

• East Aqab Basalt Wellfield

• Ain Ghazal to As Samra WW 1500 mm Pipeline – MWI/WAJ sent an email on 12

October 2018 stating the project would be implemented as design/build and CDM Smith

would not be required for this work.

3. ACTIVITY IMPLEMENTATION

The following provides an overview of the issues and activities completed during the reporting period that

are either common to some or all of the Tasks or are required to perform the overall works of the

Contract. Additionally, activities accomplished during the reporting period that are specific to each of the

nine tasks are discussed under each task heading. Three of the nine tasks (Tasks 3, 4 and 5) were

authorized for commencement on 1 August 2018 and two activities under Task 9 were requested by

USAID on 13 September 2018 all of which are discussed below.

a. Progress Narrative

(a) Mobilization

We moved into our new offices on 12 August 2018. The office location is at 73 Al Mutanabi

Street, Amman, Jordan on the 2nd floor. Staff appropriate for the first quarter of the Project are

operating from this location. Long term staff and short term (TDY) staff are listed in Annex VI.

Jeff Dickinson has been approved for a TDY to lead the renewable energy and energy efficiency

activity during the second quarter. John Crippen was mobilized as task 4 and 5 leader. Our M&E

specialist was mobilized during the quarter along with various engineering disciplines from the

home office to carry out evaluations and assessments under tasks 3, 4 and 5. Subcontracts for our

local partners Consolidated Consultants and Arabtech Jardaneh were under development. A

subcontract for the task 4 and 5 sampling programs at the WWTPs was finalized.

Staff approvals and travel approvals have all proceeded well. Residency and work permits where

required are in process. The tax exemption letter from USAID was received for the Project and it

is being used successfully with vendors and hotels.

(b) Data Collection

Requests for data including record drawings, specifications, population census, survey

information, organization charts, condition and age of equipment and tax information were made

to the responsible agencies. The data collection information received is included in Annex III.

(c) Meetings, Collaboration and Site Visits

Page 12: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 12/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Meetings, collaboration and site visits that were conducted during the reporting period are

included in Annex VII.

(d) Monitoring, Evaluation and Learning (MEL) Plan

The development of the draft monitoring, evaluation, and learning (MEL) Plan was ongoing

through the quarter with the assistance of our consultant, monitoring and evaluation (M&E)

Specialist, and meetings with the COR and mission M&E Specialist.

(e) Gender

The development of population projections for the existing and planned areas to be connected to

the Madaba and Ramtha WWTPs to the design year are under development. The projections will

be disaggregated by male and female. We are an equal opportunity employer in our hiring

practices and currently have six males and three females in technical roles and two males and

three females in administrative roles. Our M&E Specialist is female. There were 56 persons in

attendance at the PQM workshop (43 males and 13 females).

(f) Task 1 (Optional) - Red Sea Dead Sea (RSDS) Conveyance Project – Phase II

This optional task will commence when exercised by USAID. This task has not been authorized

by USAID. At a meeting on 17 September 2018, MWI/WAJ explained that the concept design of

the Red Sea- Amman Water Supply project would replace the RSDS Phase II project. The

concept design has been finalized by Dar Al Handasah. Final discussions towards preparation of

BOT bid documents with priority for Component 1 of this new concept between USAID and

MWI/WAJ will take place before this work is authorized.

(g) Task 2 – Construction Supervision – Shedeyyeh–Hasa Water Project Phase I

This task has an estimated November 2018 start date.

(h) Task 3 –Expansion of Zai Water Treatment Plant Project

This task commenced on 1 August 2018 with the main objective of the task being to evaluate the

different options for increasing the capacity of the Zai water supply scheme which will allow for

the anticipated additional water quantities that will be available as a result of the swap agreement

between Jordan and Israel.

Task 3 required direct coordination with MWI/WAJ, to estimate the additional anticipated water

quantities that will be available to be utilized through the Zai water system for the expansion. As

envisioned under Task 3, the additional anticipated water quantities available in the King

Abdullah Canal (KAC) would come from 2 sources:

1. The swap agreement would provide 50 MCM/year to the KAC from Lake Tiberius.

2. The use of treated effluent directly for irrigation in the Jordan Valley would reduce the water

quantities currently taken from the KAC for irrigation purposes.

As a result of a coordination meeting on 17 September 2018 with MWI/WAJ and USAID,

MWI/WAJ advised that the two additional anticipated water quantities planned to be available in

Page 13: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 13/31 October 15, 2018, revised October 29 & Nov 4, 2018]

the KAC have not fully materialized to the point where additional water quantities would be

available for expanding of the Zai water treatment system. MWI/WAJ advised that additional

available water quantities in the KAC will be used by the Wadi Arab II Project. Therefore, as

agreed upon, there are currently no plans under Task 3 to expand the system.

The agreed upon plan under task 3 is to complete the Zai water treatment system evaluation with

the intent to identify potential options to upgrade, rehabilitate and provide reliability to the system

for the future. One such option discussed is to propose a parallel transmission pipeline to the

existing 33-year old pipeline from the Intake Pump Station (IPS) to the Zai WTP for system

reliability. A water quality assessment report will also be prepared. During August, we had the

following disciplines perform site visits for the facility existing conditions–process, mechanical,

hydraulics, electrical and instrumentation.

(i) Tasks 4 and 5 –Expansion of Madaba and Ramtha Wastewater Treatment Plants

These two tasks commenced on 1 August 2018. The 2 tasks aim at the expansion of the Madaba

and Ramtha WWTPs to treat the projected wastewater flows until the year 2045. The tasks will

consider population forecasts, and additional wastewater service areas planned to be connected to

the sewer network for Madaba and for Ramtha including proposed connection of the localities of

Turra, Shajarah and Emmrawah. within the planned horizon.

During the reporting period the planned approach was threefold:

1. Data collection – This has been achieved through requests from MWI/WAJ, Miyahuna (for

Madaba) and YWC (for Ramtha).

2. Facility and organizational assessments – This has been achieved with local staff and an O&M

Specialist visiting each of the sites and working with local facility operators.

3. Sampling program – Based on each facility’s mode of operation, develop a 24/7 sampling and

analysis program to determine and verify existing information on the influent and effluent

quality as well as at locations internal to the facility. A subcontract with the RSS to provide

these services has been developed and signing expected early October 2018. The sampling

program for each WWTP will commence in October 2018. The results will be used in

modeling the facility as part of the feasibility study.

At the end of the reporting period the assessment report was in preparation.

(j) Task 6 – Water and Wastewater Project for Deir Alla and Al Karameh

This task has an estimated November 2018 start date. We expect to receive the EIB funded

feasibility study and other documentation developed under the EIB work in November to

commence the design process for those water and wastewater facilities that were recommended in

the feasibility study and agreed upon with MWI/WAJ.

(k) Task 7 – Water and Wastewater Project for Bani Kenanah in Irbid Governorate

This task has an estimated February 2019 start date. The original scope included preparing water

Page 14: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 14/31 October 15, 2018, revised October 29 & Nov 4, 2018]

and wastewater planning, feasibility and design and tender documents for this district of Irbid

Governorate.

Our understanding, during the period of task order preparation and negotiation, is that MWI/WAJ

contracted with Atkins and Engicon under EIB funding to prepare a feasibility study for water

and wastewater improvements for the district of Bani Kenanah in the Irbid Governorate.

Therefore, this task will use the feasibility study outcomes and other deliverables required under

the EIB funded work to advance design/implementation of new and upgraded water and

wastewater facilities.

We expect to receive the EIB funded feasibility study and other documentation developed under

the EIB work in February 2019 to commence the design process for those water and wastewater

facilities that were recommended in the feasibility study and agreed with MWI/WAJ.

(l) Task 8 (Optional) – Technical Assistance to Water Utilities

This optional task will commence when exercised by USAID. There have been no activities

identified under this task.

(m) Task 9 (Optional) - Additional Architectural and Engineering (A&E) services

This optional task will commence when exercised by USAID. Two activities under Task 9 were

requested by USAID on 13 September 2018 as follows:

1. Technical assistance to support the Phase III expansion of the As Samra WWTP.

We met with MWI/WAJ and USAID on 17 September 2018 to discuss this new activity.

MWI/WAJ advised that Fichtner prepared a feasibility study for the Phase III expansion

of the As Samra WWTP. The feasibility study is understood to include 2 options: 1) the

expansion would be integrated with the existing WWTP and 2) the expansion would be

on the same site as the existing WWTP but would standalone from the existing WWTP.

The existing (original Phase I) WWTP and first expansion (Phase II) were constructed

and are being operated by a Special Purpose Company (SPC) under a BOT contract with

the MWI/WAJ. As part of the feasibility study a cost proposal was provided by the SPC.

At the meeting, MWI/WAJ requested the following assistance:

• Technical review: A technical review of the feasibility study

• Cost proposal review: A review of the construction cost proposal prepared by the

SPC for reasonableness

• Legal review: A review the SPC agreement with MWI/WAJ to advise on the

legal aspects of MWI/WAJ options for the expansion; specifically, the clauses

that may provide the SPC with priority over other contractors on the Phase III

expansion.

MWI/WAJ advised that they are open for a conventional design/bid/build process where

competitive bids can be procured if the funding is secured based on host country contract

basis. At the meeting, MWI/WAJ agreed to provide CDM Smith with all the relevant

documents so it can start working on this activity.

Page 15: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 15/31 October 15, 2018, revised October 29 & Nov 4, 2018]

MWI/WAJ requested at the end of the reporting period a non-disclosure agreement

(NDA) from CDM Smith to receive the relevant documents to perform the review.

2. Technical assistance to analyze and design energy interventions to support the water

sector.

We met with MWI/WAJ and USAID on 17 September 2018 to discuss this new activity.

MWI/WAJ advised that KfW funded a comprehensive study (by Dorsch) on the energy

efficiency in the water sector, including opportunities and projects for renewable energy.

The attendees agreed that CDM Smith will coordinate with Dorsch to make sure it takes

the intended projects and or recommendations of the KfW study into consideration.

We met with MWI/WAJ, the Dorsch representative and USAID on 23 September 2018

and agreed to follow-on meetings. We requested and received approval from USAID to

have a renewable energy person on TDY status come to Jordan during October 2018 to

assist in scoping out the required technical assistance. Planned activities include:

▪ Provide a GAP analysis to determine what studies and interventions related to

energy efficiency and renewable energy have taken place in the water sector,

▪ Meet with Dorsch, NEPCO, and the RSS, and

▪ Visit the Wadi Shalalah WWTP where it is understood renewable energy on

digestor gas has been implemented.

Other potential activities, discussed at the 17 September 2018 meeting, none of which have been

authorized, included:

• East Aqab Basalt Wellfield

• Ain Ghazal to As Samra WW 1500 mm Pipeline – MWI/WAJ sent an email on 12

October 2018 stating the project would be implemented as a design/build and CDM

Smith would not be required for this work.

b. Reporting Data and DevResults

Geographic information on Tasks 3, 4, and 5 as noted in Annex II are ready to be included in DevResults

once the Project is registered.

Deliverables to date are listed in Annex V.

c. Implementation Challenges and Modifications Made/Issues Addressed from Last

Quarterly Report

The implementation challenges and modifications, both actual and potential, have been discussed above

under paragraph 3.a.

Environmental Status Report: The Programmatic - Initial Environmental Examination (P-IEE) issued

during the RFTOP process provides the umbrella for all activities planned under the task order for USAID

Jordan Water Infrastructure.

Page 16: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 16/31 October 15, 2018, revised October 29 & Nov 4, 2018]

4. COLLABORATING AND/OR KNOWLEDGE SHARING

a. Collaboration and/or knowledge sharing with Other USAID Activities and Partner

Entities in Host Government and other Donor Agencies

Meetings, collaboration and site visits that were conducted during the reporting period are included in

Annex VII. In summary the following significant collaboration and knowledge sharing has taken place:

• Coordination meeting with the implementing partner (IP) on the Water Management Initiative

(WMI) to share scopes of services. CDM Smith requested the report WMI was preparing on the

KAC as part of task 3 expansion of the Zai water system. As it was determined that additional

water in the KAC was unavailable for Zai expansion the need for the report was not required.

WMI indicated they may identify needs that cannot be implemented under WMI and they

potentially could be incorporated into USAID Jordan Water Infrastructure.

• A Project Quality Management (PQM) Workshop was held with attendees from USAID,

MWI/WAJ, and other stakeholders and agencies. The PQM provided all attendees with the scope

of services, the opportunity to identify critical success factors and an action plan to meet those

success factors. The PQM also provided insight into other projects ongoing or planned in Jordan.

• A Post Award Orientation meeting was held with USAID. The meeting allowed CDM Smith to

meet with the USAID personnel within the mission offices that we would have contact with

during the project life and to understand the requirements of the task order contract.

• A coordination meeting with MWI/WAJ, Miyahuna and USAID to discuss the USAID Jordan

Water Infrastructure status, scope of services and to receive input from MWI/WAJ on their

priorities for the Project going forward.

• We coordinated with the USAID M&E staff and our M&E consultant to ensure the MEL Plan

under development would meet the data collection needs of the Mission’s Performance

Management Plan (PMP), and the Mission’s annual Performance Plan and Report (PPR).

5. ASSESSMENTS / EVALUATIONS / LESSONS LEARNED

a. List Major Assessments / Internal Evaluations and Lessons Learned and Actions and

Way Forward

• Task 3 Expansion of the Zai Water Treatment Plant Project: Due to the unavailability of

additional expected source water in the KAC the expansion of this facility will not move forward.

What will move forward is defining and recommending potential upgrades and rehabilitation to

provide system reliability improvements to portions of the system that are as much as 33 years

old.

• The MWI/WAJ has a list of priority projects that are being considered by USAID and

MWI/WAJ.

Page 17: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 17/31 October 15, 2018, revised October 29 & Nov 4, 2018]

6. PLANNED ACTIVITIES FOR NEXT QUARTER

The following provides an overview of the activities expected to be worked on during the next quarter

that are either common to some or all of the Tasks or are required to perform the overall works of the

Contract. Additionally, engineering activities to be worked on during the reporting period that is specific

to each of the nine tasks are discussed under each Task heading.

a. Proposed Tasks and Activities for the Next Quarter

(a) Mobilization

Staff mobilization will continue during the second quarter of the Project to meet the ongoing

activities and task requirements. Subcontract development for our local partners is ongoing and

where required USAID consent to subcontract will be requested. The need for procuring the

project vehicles will be reviewed – currently we have two project vehicles that were turned over

to this Project from WIP II. The renewable energy and energy efficiency lead will arrive in

October 2018. We will be proposing a task leader for tasks 3, 6 and 7 since task 6 is expected to

commence in November 2018.

(b) Data Collection

Data collection will be an ongoing activity for those tasks authorized and expected to commence

in the second quarter.

(c) Meetings, Collaboration and Site Visits

Meetings, collaboration and site visits will continue to further define scopes and to coordinate our

work with others and to ensure that our performance is in line with USAID and our local client’s

expectations. We are expecting a USAID IP meeting will be scheduled. With the change of

Minister at the MWI, we could expect meetings to define the scope of services and/or receive

MWI/WAJ priority projects planned for implementation.

(d) Monitoring, Evaluation and Learning (MEL) Plan

The draft MEL Plan will be submitted for USAID review. We expect comments and discussions

with USAID to finalize the submittal during the second quarter.

(e) Task 1 (Optional) - Red Sea Dead Sea (RSDS) Conveyance Project–Phase II

This optional task will commence when exercised by USAID.

(f) Task 2 – Construction Supervision – Shedeyyeh–Hasa Water Project Phase II

This task has an estimated November 2018 start date.

Page 18: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 18/31 October 15, 2018, revised October 29 & Nov 4, 2018]

(g) Task 3 –Expansion of Zai Water Treatment Plant Project

The draft and final submittals of the existing conditions and water quantity report, and the water

quality assessment will be delivered. The options report will be under development during the

quarter based on the findings from the existing conditions report.

(h) Tasks 4 and 5 –Expansion of Madaba and Ramtha Wastewater Treatment Plants

The RSS will complete the sampling programs for the Ramtha and Madaba WWTPs and the test

results will be reported. The assessment report for the two WWTPs will be submitted as draft and

finalized during the second quarter. The preliminary development of the feasibility study will be

started.

(i) Task 6 – Water and Wastewater Project for Deir Alla and Al Karameh

With the estimated November 2018 start date, we expect to receive the EIB funded feasibility

study and other documentation developed under the EIB work in November to commence the

design process for those water and wastewater facilities that were recommended in the feasibility

study and agreed upon with MWI/WAJ.

(j) Task 7 – Water and Wastewater Project for Bani Kenanah in Irbid Governorate

This task has an estimated February 2019 start date.

(k) Task 8 (Optional) – Technical Assistance to Water Utilities

This optional task will commence when exercised by USAID. There have been no activities

identified under this task.

(l) Task 9 (Optional) - Additional Architectural and Engineering (A&E) services

This optional task will commence when exercised by USAID. Two activities under Task 9 were

requested by USAID on 13 September 2018 as follows:

1. Technical assistance to support the Phase III expansion of the As Samra WWTP.

Pending a final signed non-disclosure agreement (NDA), we will receive the Fichtner

prepared feasibility study for the Phase III expansion of the As Samra WWTP and the

construction cost proposal prepared by the SPC. With that information we will

commence the following reviews:

• Technical review: A technical review of the feasibility study

• Cost proposal review: A review of the construction cost proposal prepared by the

SPC for reasonableness

2. Technical assistance to analyze and design energy interventions to support the water sector.

We will continue our meetings and site visits with MWI/WAJ, Dorsch, Gesellschaft fur

Internationale Zusammenarbeit (GIZ), NEPCO, Wadi Shalalah WWTP, the RSS and others

Page 19: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 19/31 October 15, 2018, revised October 29 & Nov 4, 2018]

to determine what studies and interventions related to energy efficiency and renewable

energy have taken place in the water sector.

7. BRANDING COMMUNICATIONS AND DISSEMINATION

a. Key Communication Activities - Specific Activities That Reflect Branding Awareness

for USAID

CDM Smith’s communication specialist has been in contact with USAID’s Senior Development Outreach

Specialist regarding publicity protocol, messaging, specific dos and don’ts and the importance of

coordinating our efforts. She also provided information regarding quality information versus quantity and

the importance of a consistent USAID topline message.

b. Branding

The mobilization of our new office has included locating two USAID signs reflecting the appropriate logo

with the words “from the American people”. Additionally, we have worked with the USAID Office of

Outreach and Communications to develop an acceptable poster that is portable for locating at workshops

and other events to show the USAID brand.

8. SUSTAINABILITY AND EXIT STRATEGY

Nothing to Report

Page 20: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 20/31 October 15, 2018, revised October 29 & Nov 4, 2018]

9. ANNEXES

Annex I Indicator Performance Tracking Table

As part of our draft MEL Plan this table is under development and will be finalized in the second quarterly report.

PROJECT

INDICATORS

TASK NUMBER,

INFRASTRUCTURE

TYPE, STAGE, ETC

BASELINE

& YEAR

2018-2019

TARGET

2018-2019

ACTUAL

2019-2020

TARGET

2020-2021

TARGET

2021- 2022

TARGET

COMMENTS

DO3

DO3d: Number of

people gaining

access to safely

managed sanitation

services as a result

of USG assistance

(Enter target only

in year of expected

completion of

construction; Task

9 TBD)

T4- Madaba Wastewater

Treatment Plant

Total Total Total Total Total Geographic locations:

Madaba Governorate Female Female Female Female Female

Male Male Male Male Male

T5- Ramtha Wastewater

Treatment Plan

Total Total Total Total Total Geographic locations:

Ramtha District in Irbid

Governorate Female Female Female Female Female

Male Male Male Male Male

T6- Deir Alla Water and

Wastewater Project

Total Total Total Total Total Geographic locations:

Deir Alla and Al Karameh in the

Jordan Valley Female Female Female Female Female

Male Male Male Male Male

T7- Bani Kenanah/Irbid

Governorate Water and

Wastewater Project

Total Total Total Total Total Geographic locations:

Bani Kenanah District in Irbid

Governorate Female Female Female Female Female

Male Male Male Male Male

DO3

DO3e: Number of

people gaining

access to safely

managed drinking

water services as a

result of USG

assistance

T1- Red Sea/Dea Sea

Conveyance Project Phase

II

Total Total Total Total Total Geographic locations:

Agaba to Amman Governorates Female Female Female Female Female

Male Male Male Male Male

T2- Shedeyyeh-Hasa

Water Project, Phase I

Total Total Total Total Total Geographic locations:

Central Jordan along the Amman-

Aqaba Highway Female Female Female Female Female

Male Male Male Male Male

Total Total Total Total Total Geographic locations:

Female Female Female Female Female

Page 21: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 21/31 October 15, 2018, revised October 29 & Nov 4, 2018]

(Enter target only

in year of expected

completion of

construction; Task

9 TBD)

T3- Zai Water Treatment

Plant

Male Male Male Male Male Deir Alla in the Jordan valley

(Balqa Governorate) to Amman

Governorate

T6- Deir Alla Water and

Wastewater Project

Total Total Total Total Total Geographic locations:

Deir Alla and Al Karameh in the

Jordan Valley Female Female Female Female Female

Male Male Male Male Male

T7- Bani Kenanah/Irbid

Governorate Water and

Wastewater Project

Total Total Total Total Total Geographic locations:

Bani Kenanah District in Irbid

Governorate Female Female Female Female Female

Male Male Male Male Male

IR 3.3

IR3.3c: Cubic

meters of water

provided or saved

as a result of USG

assistance

(Task 9 TBD)

T1- Red Sea/Dea Sea

Conveyance Project Phase

II

0

TBD

Geographic locations:

Agaba to Amman Governorates

T2- Shedeyyeh-Hasa

Water Project, Phase I 0

TBD

Geographic locations:

Central Jordan along the Amman-

Aqaba Highway

T3- Zai Water Treatment

Plant 0

TBD

Geographic locations:

Deir Alla in the Jordan valley

(Balqa Governorate) to Amman

Governorate

T4- Madaba Wastewater

Treatment Plant 0

TBD

Geographic locations:

Madaba Governorate

T5- Ramtha Wastewater

Treatment Plan 0

TBD

Geographic locations:

Ramtha District in Irbid

Governorate

T6- Deir Alla Water and

Wastewater Project 0

TBD

Geographic locations:

Deir Alla in the Jordan valley

(Balqa Governorate) to Amman

Governorate

T7- Bani Kenanah/Irbid

Governorate Water and

Wastewater Project

0

TBD

Geographic locations:

Bani Kenanah District in Irbid

Governorate

Sub Sub-IR 3.3.2.1

Training courses

ArcGIS 1

0

Total Total Total Total Total Facilities of participants:

Page 22: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 22/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Sub Sub-

IR3.3.2.1b: Number

of water and

wastewater staff

trained

ArcGIS 2

Building GeoDatabase

Geometric Network for

Utilities

Editing Data ArcGIS

Desktop

Modeling Software Bently

Other - TBD

TBD

Female Female Female Female Female Location provided by the vendor

of the software

Male Male Male Male Male

Seconded staff

T1 – 1/Aqaba

T3 – 2/Miyahuna

T7 – 3/Yarmouk, 1/WAJ

Staff assigned to multiple

tasks:

Tasks 3, 4, 5, 6, 7 –

4/WAJ

Other - TBD

0

TBD

Total Total Total Total Total

Female Female Female Female Female

Male Male Male Male Male

IR 3.3.3

IR3.3.3a: Percent of

construction

completion of water

and wastewater

infrastructure

systems by facility

T2- Shedeyyeh-Hasa

Water Project, Phase I 0

2018

TBD

TBD

100

Geographic locations:

Expected construction completion

2021

T4- Madaba Wastewater

Treatment Plant 0

2021

TBD

TBD

Geographic locations:

Expected construction start 2021

T5- Ramtha Wastewater

Treatment Plan 0

2021

TBD

TBD

Geographic locations:

Expected construction start 2021

T9 - TBD Geographic locations:

IR 3.3.3

IR3.3.3b: Number

of approved

T1- Red Sea/Dea Sea

Conveyance Project

Phase II

Stage 1 Pre-Design

Stage 2 Design

Stage 3 Pre-Contract TBD

S1 = 0

year TBD Reports will be prepared in CDM

Smith Amman office

S2 = 0

year TBD

S3 = TBD

T2- Shedeyyeh-Hasa

Water Project, Phase I

Stage 2 Design

Stage 3 Pre-Contract

S2 = 0

2018

1

S3, P1&3 = 0

2019

Page 23: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 23/31 October 15, 2018, revised October 29 & Nov 4, 2018]

engineering reports

and/or studies

(Phases 1 & 3 combined

total) 4

T3- Zai Water Treatment

Plant

Stage 1 Pre-Design

Stage 2 Design

(Phases 1-3)

S1 = 0

2018

4

S2/P1 = 0,

2018

S2/P3 = 0,

2019

2 (total S2)

4 (S2, P3)

T4- Madaba Wastewater

Treatment Plant

Stage 1 Pre-Design

Stage 2 Design

(Phases 1 – 3)

Stage 3 Pre-Contract TBD

S1 = 0

2018

3

S2 = 0

2019

7 (S2,P1+3)

S3 = TBD

T5- Ramtha Wastewater

Treatment Plan

Stage 1 Pre-Design

Stage 2 Design

(Phases 1 – 3)

Stage 3 Pre-Contract TBD

S1 = 0

2018

3

S2 = 0

2019

7 (S2,P1+3)

S3 = TBD

T6- Deir Alla Water and

Wastewater Project

Stage 2 Design

(Phases 1 – 3)

S2/P1 = 0

2018

S2/P3 = 0

2019

2

(S2,P1+P3)

4

(S2, P3)

T7- Bani Kenanah/Irbid

Governorate Water &

Wastewater Project

Stage 2 Design

(Phases 1 – 3)

S2/P1 = 0

2019

S2/P3 = 0

2019

2

(S2,P1+P3)

4

(S2, P3)

T9 – A&E services TBD

2018-2019: X task

reports

TBD

TBD

Potential data -

context, gender, etc.

related to learning

agenda

Page 24: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 24/31 October 15, 2018, revised October 29 & Nov 4, 2018]

PROJECT TASKS & START DATES Task 1 – Red Sea/Dea Sea Conveyance Project, Phase II (optional, by USAID request)

Task 2 – Shedeyyeh-Hasa Water Project, Phase I (Nov 2018)

Task 3 – Expansion of Zai Water Treatment Plant Project (Aug 2018)

Task 4 – Expansion of Madaba Wastewater Treatment Plant (Aug 2018)

Task 5 – Expansion of Ramtha Wastewater Treatment Plan (Aug 2018)

Task 6 – Deir Alla Water and Wastewater Project (Nov 2018)

Task 7 – Bani Kenanah/Irbid Governorate Water and Wastewater Project (Feb 2019)

Task 8 – Technical Assistance and Training – water utilities (optional, by USAID request)

Task 9 – A&E Services (optional, by USAID request)

Page 25: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 25/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Annex II Geographic Data Reporting – GIS Template

The following table shows the activity location data for Tasks 3, 4 and 5.

The coordinates for Task 3 are the location of the WTP. This task includes an area from the intake

structure in Deir Alla in the Jordan Valley, a transmission system from Deir Alla to the WTP, and a

transmission system from the WTP to the Dabouq reservoir in Amman.

The coordinates for Tasks 4 and 5 are the WWTP location.

Activity Sector Governorate Y X Note

USAID Jordan

Water

Infrastructure

Task 3

Expansion of Zai Water

Treatment Plant Project Balqa 32.104975 35.715224

Expansion of Zai water

supply system which

includes the WTP,

pumping stations and

the transmission

pipelines

USAID Jordan

Water

Infrastructure

Task 4

Expansion of Madaba

WWTP Madaba 31.697554 35.806146

Madaba WWTP

Expansion Project

USAID Jordan

Water

Infrastructure

Task-5

Expansion of Ramtha

WWTP Irbid 32.593664 35.988541

Ramtha WWTP

Expansion Project

Page 26: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 26/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Annex III Data Collection

Task 1 – Red Sea Dead Sea Conveyance Project Phase II

Item # Received Data

1 Consulting Services for Environmental and Social Impact Assessment Study (ESIA)

2 Revised Concept Design Report

Task 3 – Expansion of Zai Water Treatment Plant Project

Item # Received Data

1 Zai WTP as-built Drawings (1985)

2 Zai As-built Drawings (1997)

3 Zai Expansion as-built Drawings (2000)

4 Zai WTP_Expansion 2001

5 New Intake Station - modification completed in 2018

6 UV Installation Project

7 Abu Al Zeigan Wells

8 Intake_Topography_Intrance and Streets

9 Water Quality

10 Water Quantities

11 Site Visits Photos and Multimedia

Task 4 – Expansion of Madaba WWTP

Item # Received Data

1 Madaba Upgrade Record Drawings 1998

2 WWTP flow (in- Out) (quality and quantity)

(2015, 2016, 2017, 2018)

3 Madaba new PS and FM design (drawings and tender documents)

4 Organization Structure

5 Vehicle List

6 JICA Master Plan

7 Madaba WWTP O&M Manual

8 Report by RSS Treated Effluent & Biosolids Maize

9 Madaba Wastewater Collection System - GIS

10 Report by RSS Treated Effluent & Biosolids Maize

11 Meeting with employees & flow direction

12 Al-Dar Study report for Madaba transmission system

13 Madaba WWTP Daily Operation record data 2015 up to 2018 from site

14 FINAL DESIGN REPORT MADABA 1996-WAJ Library

15 Miyahuna Labs tests results/external lab 2015-2017

16 Madaba Local Lab test results

17 Madaba operation and service manual 1989-WAJ library

18 Madaba operation and maintenance volumes; Mechanical, Process part1/2, Process part 2/2

19 Madaba operation and maintenance manual 1989-WAJ library

20 Meteorological Data for Madaba and Queen Alia Airport Stations

Page 27: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 27/31 October 15, 2018, revised October 29 & Nov 4, 2018]

21 DOS (2015 Data) Population Projection, year book, population based on nationality

population based on gender and DOS growth rates for Madaba governorate up to 2050.

22 Madaba Contour and google Image from Al Mehwar

Task 5 – Expansion of Ramtha WWTP

Item # Received Data

1 Ramtha upgrade As-Built Drawings 2005

2 WWTP flow (quality and quantity)

(2015, 2016, 2017, 2018)

3 JICA Master Plan

4 Ramtha WWTP O&M Manual

5 Effects of the Upgrading of Al-Ramtha WWTP on Quality of the Effluent and Environment

6 Report by RSS Treated Effluent & Biosolids Maize Final w Akrum's Edits

7 Sahel Horan Record Drawings

8 National Strategic Wastewater Master Plan Prepared by USAID/Jordan (ISSP)

9 Ramtha meeting with employees & flow direction

10 Ramtha Vehicles

11 organization chart & list of employees and qualifications

12 Expansion of Ramtha WWTP O&M manual 1999 from WAJ library

13 Monthly WWTP site reports: operation and lab tests 2015 up to 2018

14 Ramtha final design report 1996-WAJ Library

15 The only available lab tests for local lab in the plant

16 Complete scanned As-Built drawing from eng. Hisham Obidate/manager of the plant

17 EPG speed Control 1983 manual

18 National Strategic Wastewater Master Plan Report 2014

19 Meteorological Data for Ramtha and Irbid Stations

20 DOS (2015 Data) Population Projection, year book, population based on nationality

population based on gender and DOS growth rates for Ramtha governorate up to 2050.

21 Ramtha Contour and google Image from Al Mehwar

Task 6 – Water and Wastewater Project for Deir Alla

Item # Received Data

1 Deir Alla Draft Feasibility Study Draft Report July 2018

Task 7 – Water and Wastewater Project for Bani Kenanah/Irbid Governorate

Item # Received Data

1 Bani Kenanah Feasibilty Study Report

Task 9 – Additional A&E Services

Item # Received Data

1 Aqeb Wells / Basalt Report

2 Hallabat, Dullail and Khaldiya Detailed Design Drawings and Tender Documents

3 Energy Report

Page 28: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 28/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Annex IV Training Report

Project Quality Management Workshop – 30 August

2018

The PQM provided all attendees with the scope of

services and the opportunity to identify critical

success factors and an action plan to meet those

success factors. The PQM also provided insight into

other projects ongoing or planned in Jordan. The sign-

up sheet for the workshop identified 12 organizations

including subcontractors, USAID, MWI/WAJ, water

companies and Electricity Distribution Company

(EDCO). There were 56 persons in attendance (43

males and 13 females).

Annex V Deliverables

Deliverable Draft

Submittal To

Final Submittal

To

Work Plan 1st Year 19 August

2018 USAID

1st Quarterly Reports Due 15

October 2018 USAID

Accruals 13 Sept 2018 USAID 4th Quarter 2018

Draft MEL Plan Due 16

October 2018

Technical Memorandum-Availability of Additional Source Water in the KAC

20 September

2018 USAID, MWI/WAJ

PQM Workshop

Page 29: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 29/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Annex VI Staff

Long Term and Local Staff Assignments

Name Function Start Date End Date

Rick Minkwitz COP/Project Manager 17-Jul-18

Mehran Meserlian Deputy COP/Project Manager 17-Jul-18

Neveen Abdulghani Assistant Project Manager 17-Jul-18

John Crippen Task Manager 25-Aug-18 14-Sep-18

John Crippen Task Manager 1-Oct-18

Bashar Al Hammouri Civil Engineer 17-Jul-18

Sawsan Bataineh Senior Civil Engineer/Deputy Task Manager 22-Jul-18

Luba Hamdi Senior Civil Engineer/Deputy Task Manager 22-Jul-18

Ali Yousef Civil Engineer 12-Aug-18

Muhannad Al Masri CAD Operator 17-Jul-18

Lana Masannat Administrative Manager 17-Jul-18

Siham Shaban Receptionist 13-Aug-18

Hala Mawajdeh Financial Manager 17-Jul-18

Emad Basal Accountant 2-Sep-18

Saif Ababseh Computer & Network Specialist 17-Jul-18

Maher Mezher Driver 17-Jul-18

Mohammed Shalan Office Helper 17-Jul-18

Temporary Duty Assignments

Name Function Start Date End Date

Mark White WTP Process Engineer – Task 3 6-Aug-18 17-Aug-18

Richard Lof Mechanical Engineer – Task 3 24-Aug-18 31-Aug-18

Stephen Fontneau Electrical Engineer – Task 3 24-Aug-18 31-Aug-18

Saed Hussain Instrumentation Engineer – Task 3 24-Aug-18 31-Aug-18

Christopher Oot Officer in Charge – PQM & PA Orientation 28-Aug-18 31-Aug-18

Ammar Daoud Contract Sales Leader PQM & PA Orientation 28-Aug-18 31-Aug-18

Charles Tellis Subcontract Manager PQM & PA Orientation 27-Aug-18 31-Aug-18

Jeffrey Montera

Development Assistance Manager PQM & PA

Orientation 27-Aug-18 31-Aug-18

Harold Gillam PQM Facilitator 25-Aug-18 31-Aug-18

Salem Ali Contract Administrator 8-Sep-18 13-Sep-18

Matt Antill O&M Specialist – Task 4 and 5 2-Sep-18 17-Sep-18

Margaret Harritt M&E Specialist – Consultant 19-Sep-18

PA – Post Award

Page 30: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 30/31 October 15, 2018, revised October 29 & Nov 4, 2018]

Annex VII Meetings

Representatives Date Purpose

CDM and USAID 22 July 2018 Preliminary discussions following TO signing

CDM, MWI/WAJ, USAID 5 August 2018 Scope of work Tasks 4 and 5

CDM, Miyahuna,

MWI/WAJ, USAID

6 August 2018 Scope of work Task 3

CDM, Miyahuna,

MWI/WAJ, USAID, JVA

9 August 2018 Availability of additional water in KAC

H.E. MWI SG, CDM,

MWI/WAJ, USAID

12 August 2018 Scope of work for the Project

CDM, USAID, WMI 16 August 2018 IP Meeting to compare scopes for potential collaboration

CDM and USAID 16 August 2018 MEL Plan

CDM and USAID 29 August 2018 Post Award Orientation

CDM and Subcontractors 29 August 2018 Project Planning and Scope Review Meeting

All Stakeholders 30 August 2018 Project Quality Management Workshop

H.E. Minister, H.E. MWI

SG, H.E. WAJ SG, CDM,

USAID, MWI/WAJ

4 September 2018 Meeting to provide Minister with information on the scope of

the Project

H.E. WAJ SG, CDM,

USAID, MWI/WAJ

17 September

2018

Project scope of work and priorities of MWI/WAJ

CDM and USAID 18 September

2018

Project scope of work and priorities of MWI/WAJ

CDM, USAID,

MWI/WAJ, Dorsch

23 September

2018

Dorsch contract and renewable energy/energy efficiency in

the water sector

CDM, USAID, M&E

Consultant

25 September

2018

MEL Plan collaboration with USAID

The above represents key meetings during the quarter. However, there were many more meetings by staff

in the process of data collection from MWI/WAJ, the water companies, Department of Statistics (DOS)

and site visits to the Zai water system and the Ramtha and Madaba WWTPs during August and

September 2018.

Annex VIII Management and Administrative Issues

Nothing to Report

Annex IX Sub-Award Details

Subcontractor Description Date Value

Royal Scientific Society

(RSS)

Wastewater Sampling and Testing Programs at

Madaba and Ramtha WWTPs

Early

October

signing

US$

104,022

Annex X Schedule

Page 31: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

1 MANAGEMENT 1584 days 15/07/18 14/11/222 Task Order Signed 0 days 15/07/18 15/07/183 2‐Day PQM Workshop 2 days 29/08/18 30/08/184 Prepare Annual Workplan 1462 days 15/07/18 15/07/2210 Submit Annual Work Plan (for all project activities) 1403 days 13/09/18 16/07/2216 Prepare Monitoring, Evaluation and Learning Plan 90 days 15/07/18 12/10/1817 Submit Monitoring, Evaluation and Learning Plan 0 days 12/10/18 12/10/1818 Manage Resources in Terms of Work plan 1522 days 01/08/18 30/09/2219 Coordinate with USAID, MWI, WAJ, Miyahuna, JVA, AWC, YWC ‐ Track &

Report Progress1538 days 16/07/18 30/09/22

20 Quarterly Report (for Activities undertaken during the quarter Compared with the Approved work Plan)

850 days 15/10/18 16/01/22

32 Annual Progress Reports (for all activities) 735 days 27/12/18 31/12/2036 Annual Financial Reports 1111 days 16/07/19 30/07/2241 Quarterly Accruals Report 1384 days 01/10/18 15/07/2258 Annual Non‐Expendable Property Report 1096 days 30/07/19 30/07/2263 Initial Environmental Examination (IEE) 1 day 15/07/18 15/07/1864 Geographic Data Reporting 0 days 12/09/18 12/09/1865 Draft Final Project Report 1 day 31/08/22 31/08/2266 Final Project Report  1 day 14/11/22 14/11/2267 Close‐Out Plan & Equipment Disposition 1 day 31/03/22 31/03/2268 TASK 1 ‐ RED SEA DEAD SEA CONVEYANCE PROJECT / PHASE II 1071 days 01/12/18 05/11/2169 Suggested USAID/MWI/WAJ Notice to Proceed 1 day 01/12/18 01/12/1870  Task 1 PQM Workshop 1 day 01/01/19 01/01/1971 Component I: Preliminary Services  517 days 01/01/19 01/06/2072 Component I: Preliminary Services  0 days 01/01/19 01/01/1973 Collect, Review and Analyze Data 60 days 02/01/19 02/03/1974 Establish Electronic Project Library on a GOJ website 1 day 01/02/19 01/02/1975 Assess and Evaluate Different Scenarios & Options 210 days 02/02/19 30/08/1976 Evaluate Hydropower Production Potentials 120 days 03/04/19 31/07/1977 Evaluate, Recommend & Select Best Scenario 90 days 02/06/19 30/08/1978 Evaluate Different Technical, Legal and Financial Options 90 days 02/06/19 30/08/1979  Draft Evaluation and Recommendation Memo 1 day 31/08/19 31/08/1980  USAID/MWI/WAJ Review and Approval 15 days 01/09/19 15/09/1981 Final Evaluation and Recommendation Memo 1 day 01/10/19 01/10/1982  Environmental Impact Assessment 275 days 01/09/19 01/06/2083 Review Previous Relevant ESIA Reports 120 days 02/09/19 30/12/1984 Perform Additional Environmental and Social Studies 200 days 02/09/19 19/03/2085 Prepare Environmental and Social Management Plan 120 days 21/11/19 19/03/2086  Conduct Scoping Sessions 173 days 01/09/19 20/02/2093  Draft Scoping Statement 1 day 21/02/20 21/02/2094  USAID/MWI/WAJ Review and Approval 15 days 22/02/20 07/03/2095  Final Scoping Statement 1 day 23/03/20 23/03/2096  Draft Environmental and Social Impact  Assessment (ESIA) 1 day 23/04/20 23/04/2097  USAID/MWI/WAJ Review and Approval 15 days 24/04/20 08/05/2098  Final Environmental and Social Impact Assessment (ESIA) 24 days 09/05/20 01/06/2099  Financial and Legal Frameworks 122 days 18/08/19 17/12/19100  Evaluate Possible Legal Frameworks 90 days 18/08/19 15/11/19101  Prepare BOT Procurement Requirements 90 days 18/08/19 15/11/19102  Conduct Financial Affordability Analysis 90 days 18/08/19 15/11/19103  Prepare Financial Model for Debt & Equity Investment Analysis 90 days 18/08/19 15/11/19104  Draft Financial and Legal Memo 1 day 16/11/19 16/11/19105  USAID/MWI/WAJ Review and Approval 15 days 17/11/19 01/12/19106  Final Financial and Legal Memo 1 day 17/12/19 17/12/19107  Preliminary Design 272 days 02/02/19 31/10/19108  Prepare Design Criteria 60 days 02/02/19 02/04/19109  Define, Alignments  Locations & Land Requirements 90 days 17/02/19 17/05/19110 Prepare Suvey Requirements & Carry out Topo Surveys  90 days 19/03/19 16/06/19111 Prepare Requirements & Conduct Geothechnical Studies & Surveys 120 days 03/04/19 31/07/19112  Assist MWI/WAJ Prepare Land Acquisition Documents 90 days 03/05/19 31/07/19

15/07/18 Task Order Signed30/08/18 2‐Day PQM Workshop

12/10/18 Submit Monitoring, Evaluation and Learning Plan

                IEE For Tasks to be Identified           Provide Activity location Data                                   Update Location Data For Task to be Identified

Draft Final Project Report 31/08/22Final Project Report  14/11/22

Close‐Out Plan & Equipment Disposition 31/03/22

01/12/18 Suggested USAID/MWI/WAJ Notice to Proceed01/01/19 Task 1 PQM Workshop

01/01/19 Component I: Preliminary Services 

01/02/19 Establish Electronic Project Library on a GOJ website

31/08/19 Draft Evaluation and Recommendation Memo

01/10/19 Final Evaluation and Recommendation Memo

21/02/20 Draft Scoping Statement

23/03/20 Final Scoping Statement23/04/20 Draft Environmental and Social Impact  Assessment (ESIA)

01/06/20 Final Environmental and Social Impact Assessment (ESIA)

16/11/19 Draft Financial and Legal Memo

17/12/19 Final Financial and Legal Memo

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 1

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 32: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

113  Conduct Concept Designs for Diffent Alignment Scenarios  180 days 04/03/19 30/08/19114 Provide Project Capital & Operating Expenditure Cost Estimates 60 days 17/07/19 14/09/19115 Conduct Comparative Analysis & Prioritize Scenarios  30 days 31/08/19 29/09/19116  Preliminary Design TRC  1 day 16/08/19 16/08/19117  Draft Preliminary Design Report for Least Cost Scenario 1 day 30/09/19 30/09/19118  Preliminary Design Stage Workshop 1 day 08/10/19 08/10/19119  USAID/MWI/WAJ Review and Approval 15 days 01/10/19 15/10/19120  Final Preliminary Design Report 1 day 31/10/19 31/10/19121 Component II: Procurement Services 558 days 02/05/19 09/11/20122  Prepare Pre‐Qualifications Documents  60 days 02/05/19 30/06/19123 Obtain Pre‐Qualification Proposals 90 days 01/07/19 28/09/19124  Assist USAID/MWI/WAJ with Evaluation of Prequalification Proposals 60 days 29/09/19 27/11/19

125 Draft Prequalification Evaluation Report 1 day 28/11/19 28/11/19126  USAID/MWI/WAJ Review and approval 15 days 29/11/19 13/12/19127 Final Prequalification Evaluation Report 1 day 29/12/19 29/12/19128 Develop BOT Tender Documents for the Approved Option 210 days 31/05/19 26/12/19129 BOT Tender Documents TRC 1 day 16/11/19 16/11/19130 Draft BOT Tender Documents 1 day 27/12/19 27/12/19131  USAID/MWI/WAJ Review and approval 15 days 28/12/19 11/01/20132 Final BOT Tender Documents 1 day 11/02/20 11/02/20133 Pre‐Bid Meeting & Site Visits  114 days 01/03/20 22/06/20138 Obtain Bids 150 days 12/02/20 10/07/20139  Assist USAID/MWI/WAJ With the Bids Evaluation 90 days 11/07/20 08/10/20140  Draft Tender Evaluation Report 1 day 09/10/20 09/10/20141  USAID/MWI/WAJ Review and approval 15 days 10/10/20 24/10/20142  Final Tender Evaluation Report 1 day 09/11/20 09/11/20143 Component III: Negotiation Support 150 days 10/11/20 08/04/21144 Provide Technical, Legal & Financial Support To MWI/WAJ During 

Contract Negotiations120 days 10/11/20 09/03/21

145 Execute Final Contract Documents 30 days 10/03/21 08/04/21146 Component IV: Transaction Support (if the project is 

implemented during the contract period of performance)241 days 10/03/21 05/11/21

147 Provide Technical, Legal & Financial Support To MWI/WAJ During The Implementation Of The Project Through Financial Close

180 days 09/04/21 05/10/21

148  Prepare and Implement Project Execution Plan 180 days 09/04/21 05/10/21149  Provide General Project Coordination 175 days 10/03/21 31/08/21156  Provide Supplemental Services  175 days 10/03/21 31/08/21163  Monthly Progress Reports 154 days 15/03/21 15/08/21170 Annual Progress Reports 1 day 05/11/21 05/11/21171  Task 1 Executive Summary & Summary Report 1 day 05/11/21 05/11/21172 TASK 2 ‐ SHEDEYYEH ‐ HASA WATER PROJECT / PHASE I 1053 days 28/10/18 14/09/21173 Submit Annual Work Plan to USAID 769 days 01/12/18 07/01/21177 Pre‐Contract Services (For Hasa DBO Contract) 316 days 01/11/18 12/09/19178 Prepare Invitations, Advertisements & Pre‐qualification Questionnaire30 days 01/11/18 30/11/18

179 Assist WAJ in Responding to Bidders' Questions  30 days 01/12/18 30/12/18180 Participate in the Evaluation of Qualification Applications 30 days 31/12/18 29/01/19181 Draft Evaluation Report with Recommendations 1 day 30/01/19 30/01/19182 USAID/MWI/WAJ Review and Approval 15 days 31/01/19 14/02/19183 Final Evaluation Report 1 day 19/02/19 19/02/19184 Assist WAJ in Preparing Invitation Letters 15 days 20/02/19 06/03/19185 Pre‐bid Meeting & Site Visit 1 day 14/03/19 14/03/19186 Assist WAJ in Preparing Addenda 60 days 15/03/19 13/05/19187 Bids Evaluation 60 days 14/05/19 12/07/19188 Draft Evaluation Reports 1 day 13/07/19 13/07/19189 USAID/MWI/WAJ Review and Approval 15 days 14/07/19 28/07/19190 Final Evaluation Reports 1 day 05/08/19 05/08/19191 Assist WAJ in Preparing Letters and Reports for Approval 21 days 06/08/19 26/08/19192 Draft Documents for Contract Signing 1 day 27/08/19 27/08/19

16/08/19 Preliminary Design TRC 30/09/19 Draft Preliminary Design Report for Least Cost Scenario08/10/19 Preliminary Design Stage Workshop

31/10/19 Final Preliminary Design Report

28/11/19 Draft Prequalification Evaluation Report

29/12/19 Final Prequalification Evaluation Report

16/11/19 BOT Tender Documents TRC27/12/19 Draft BOT Tender Documents

11/02/20 Final BOT Tender Documents

09/10/20 Draft Tender Evaluation Report

09/11/20 Final Tender Evaluation Report

05/11/21 Annual Progress Reports05/11/21  Task 1 Executive Summary & Summary Report

30/01/19 Draft Evaluation Report with Recommendations

19/02/19 Final Evaluation Report

14/03/19 Pre‐bid Meeting & Site Visit

13/07/19 Draft Evaluation Reports

05/08/19 Final Evaluation Reports

27/08/19 Draft Documents for Contract Signing

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 2

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 33: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

193 USAID/MWI/WAJ Review and Approval 15 days 28/08/19 11/09/19194 Final Documents for Contract Signing 1 day 12/09/19 12/09/19195 Construction Supervision (FIDIC Base Contract) 1037 days 01/11/18 02/09/21196 Assist USAID/WAJ to Issue the Notice to Proceed for DBO Contract 1 day 13/09/19 13/09/19197  Provide Field Staff & Home Office Support 1006 days 01/11/18 02/08/21198  Advise & Provide Assistance to USAID/WAJ 1006 days 01/11/18 02/08/21199  Reviews and Monitoring 1006 days 01/11/18 02/08/21200  Review, Provide Comments & Approve Contractor's Submittals 1006 days 01/11/18 02/08/21201 Verify Contractor's Shop & As‐Built Drawings 1006 days 01/11/18 02/08/21202  Verify Contractor Quality Control / Assurance Plan 1006 days 01/11/18 02/08/21203  Monitor the Contractor's Progress & Performance 1006 days 01/11/18 02/08/21204  Review Contractor's Subcontracting Plans  1006 days 01/11/18 02/08/21205  Monitor Contractor's Firm for Special Investigations 1006 days 01/11/18 02/08/21206 Conduct and Lead the Monthly Progress Meetings 973 days 01/11/18 01/07/21240  Construction Supervision 1006 days 01/11/18 02/08/21241  Monitor the Construction Work 1006 days 01/11/18 02/08/21242  Review & Approve Construction Field & Laboratory Test Results 1006 days 01/11/18 02/08/21243  Provide Instructions to the Contractor 1006 days 01/11/18 02/08/21244 Advise & Assist USAID/WAJ on Need for Inspection of Equipment 

Manufacturing617 days 01/11/18 09/07/20

252 Practice in Material Acceptance Committee 1006 days 01/11/18 02/08/21253  Certification, Reporting, and Compliance 1006 days 01/11/18 02/08/21254 Tax Exemption Certification 435 days 01/11/18 09/01/20260 Ensure Implementation of EA Mitigation Measures 1006 days 01/11/18 02/08/21261 Conduct/Attend Inspections & Acceptance Operation, Testing & 

Warranty Initiation1006 days 01/11/18 02/08/21

262 Verify Warranties of Equipment & System Guarantees 1002 days 01/11/18 29/07/21274  Quarterly Progress Report 821 days 01/02/19 01/05/21285  Quarterly accruals 821 days 01/02/19 01/05/21296 Submittal of Technical Memoranda as Necessary 982 days 01/11/18 09/07/21308  Final Project Report 1 day 02/09/21 02/09/21309  Measurements, Payments and Modifications 1006 days 01/11/18 02/08/21310 Conduct Detailed Measurment & Quantity Surveying 1006 days 01/11/18 02/08/21311  Review & Approve/Disapprove Contractor's Payment Vouchers 1005 days 01/11/18 01/08/21312  Examine Contractor's Claims & Make Recommendations  982 days 01/11/18 09/07/21324 Study & Assisst USAID/WAJ in Variation Oreders 982 days 01/11/18 09/07/21336  Start‐Up and Commissioning of the Constructed Facilities 180 days 01/02/21 30/07/21337  Review & Approve Contractor's Start‐up & Operating Plans 60 days 01/02/21 01/04/21338  Conduct Final Inspection on Completed Work 150 days 01/02/21 30/06/21339 Project Taking Over  90 days 02/05/21 30/07/21340 Testing & Commissioning 30 days 01/07/21 30/07/21341 Verify Contractor As‐Built Documents & Coordinate Requisite 

Submittals to WAJ120 days 02/04/21 30/07/21

342  Task 2 Summary Report 1 day 14/09/21 14/09/21343 Well Drilling Contract Duration 732 days 28/10/18 28/10/20347 Hasa DBO (Pre‐contract Services & Construction Supervision) Contract 

Duration1003 days 01/11/18 30/07/21

353 TASK 3 – ZAI WATER TREATMENT PLANT  EXPANSION 577 days 01/08/18 28/02/20354 Preliminary Design 301 days 01/08/18 28/05/19355 Collect and Analyze Data 86 days 01/08/18 28/11/18356 Estimate Zai Water System Anticipated Water Quantities  86 days 01/08/18 28/11/18357 Review Previous Studies 120 days 01/08/18 28/11/18358 Draft Existing Conditions & Water Quantities Assessment Report 1 day 29/11/18 29/11/18359 USAID/MWI/WAJ Review and Approval 15 days 30/11/18 14/12/18360 Final Existing Conditions & Water Quantities Assessment Report 1 day 30/12/18 30/12/18361 Study, Analyze & Test (if needed) KAC Water Quality 120 days 01/08/18 28/11/18362 Draft Water Quality Assessment Report 1 day 29/11/18 29/11/18363 USAID/MWI/WAJ Review and Approval 15 days 30/11/18 14/12/18364 Final Water Quality Assessment Report 1 day 29/12/18 29/12/18365 Zai Water System Components Evaluation 120 days 01/08/18 28/11/18

12/09/19 Final Documents for Contract Signing

13/09/19 Assist USAID/WAJ to Issue the Notice to Proceed for DBO Contract

02/09/21  Final Project Report

14/09/21  Task 2 Summary Report

29/11/18 Draft Existing Conditions & Water Quantities Assessment Report

30/12/18 Final Existing Conditions & Water Quantities Assessment Report

29/11/18 Draft Water Quality Assessment Report

29/12/18 Final Water Quality Assessment Report

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 3

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

ABDULGHANINM
Text Box
Well Drilling - Construction Contract
ABDULGHANINM
Text Box
Hasa DBO Pre-Contract Services
ABDULGHANINM
Text Box
Hasa DBO - Construction Contract
Page 34: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

366 Zai Water System Options 120 days 01/08/18 28/11/18367 Draft Evaluation & Options Report 1 day 29/11/18 29/11/18368 USAID/MWI/WAJ Review and Approval 15 days 30/11/18 14/12/18369 Final Evaluation & Options Report 1 day 29/12/18 29/12/18370  Environmental Impact Assessment 270 days 01/09/18 28/05/19371 Perform  Environmental Impact Assessment 270 days 01/09/18 28/05/19372 Review Previous Environmental & Social Impact Assessment 

Reports90 days 01/09/18 29/11/18

373 Conduct Scoping Session 1 day 30/11/18 30/11/18374 Draft Scoping Statement 1 day 31/12/18 31/12/18375 USAID/MWI/WAJ Review and Approval 15 days 01/01/19 15/01/19376 Final Scoping Statement 1 day 30/01/19 30/01/19377 Draft EIA Report 1 day 12/04/19 12/04/19378 USAID/MWI/WAJ Review and Approval 15 days 13/04/19 27/04/19379 Final EIA Report 1 day 28/05/19 28/05/19380 Preliminary Engineering Designs & Cost Estimate 271 days 01/08/18 28/04/19381 Existing System Energy Efficiency Evaluation 120 days 01/08/18 28/11/18382 Draft Energy Efficiency Report 1 day 29/11/18 29/11/18383 USAID/MWI/WAJ Review and Approval 15 days 30/11/18 14/12/18384 Final Energy Efficiency Report 1 day 30/12/18 30/12/18385 Preliminary Design (30%) TRC 1 day 13/02/19 13/02/19386 Draft Preliminary Design Report (BODR) 150 days 31/10/18 29/03/19387 USAID/WAJ Review and Approval 15 days 30/03/19 13/04/19388 Final Preliminary Design Report (BODR) 1 day 28/04/19 28/04/19389 Detailed Design 336 days 30/03/19 28/02/20390 Topo Survey, Soil Investigation & Field Verifications  120 days 30/03/19 27/07/19391 Geotechnical Investigation Report 1 day 12/08/19 12/08/19392 Zai Transmission Hydraulic Analysis 180 days 29/04/19 25/10/19393 Assist WAJ in Prepare Land Acquisition Documents 120 days 29/05/19 25/09/19394 Detailed Designs & Tender Documents 198 days 01/05/19 14/11/19395 60% Design TRC  1 day 15/07/19 15/07/19396 90% Design TRC  1 day 14/10/19 14/10/19397 Confidential Cost Estimate  60 days 30/09/19 28/11/19398 Packaging Evaluation 30 days 30/10/19 28/11/19399 Draft Tender Documents 1 day 29/11/19 29/11/19400 USAID/WAJ Review and Approval 30 days 30/11/19 29/12/19401 Final Zai WTP & Transmission System Tender Documents 1 day 28/01/20 28/01/20402 Task 3 Summary Report 1 day 28/02/20 28/02/20403 TASK 4 – EXPANSION OF MADABA WASTEWATER TREATMENT 

PLANT1692 days 01/08/18 19/03/23

404 Feasibility Study & Environmental Impact Assessment 421 days 01/08/18 25/09/19405  Collect, Review and Analyze All Available Data 120 days 01/08/18 28/11/18406  Conduct Tests of Wastewater Quality  90 days 31/08/18 28/11/18407 Conduct Survey Work for Critical Locations needed to Conduct the Fea60 days 31/08/18 29/10/18408  Assess & Evaluate Conditions, Serviceability & Capacity of the Existing120 days 31/08/18 28/12/18409  Assess Staff and Equipment & Recommend improvements 120 days 31/08/18 28/12/18410  Assess & Describe the Operational Aspects of the WWTP 120 days 31/08/18 28/12/18411  Establish Appropriate O&M Procedures 120 days 31/08/18 28/12/18412 Evaluation of Existing Facilities Rehabilitation, Upgrading & Expansion 120 days 31/08/18 28/12/18413 Draft Madaba WWTP Assessment Report 1 day 29/12/18 29/12/18414  USAID/MWI/WAJ Review and Approval 15 days 30/12/18 13/01/19415 Final Madaba WWTP Assessment Report 1 day 29/01/19 29/01/19416  Study Agricultural Practices, Determine the Suitable Crops & Identify 

Effluent Reuse Areas & Sludge Disposal Facilities120 days 30/01/19 29/05/19

417 Perform Feasibility Study, Analysis & Cost Estimates 150 days 30/01/19 28/06/19418 Perform Energy Efficiency Study 120 days 01/03/19 28/06/19419 Perform Economic, Financial, & Socio Economic Analysis 120 days 01/03/19 28/06/19420  Draft Feasibility Study & Analysis Report 1 day 29/06/19 29/06/19421  USAID/MWI/WAJ Review and Approval 15 days 30/06/19 14/07/19422  Final Feasibility Study & Analysis Report 1 day 30/07/19 30/07/19

29/11/18 Draft Evaluation & Options Report

29/12/18 Final Evaluation & Options Report

30/11/18 Conduct Scoping Session31/12/18 Draft Scoping Statement

30/01/19 Final Scoping Statement12/04/19 Draft EIA Report

28/05/19 Final EIA Report

29/11/18 Draft Energy Efficiency Report

30/12/18 Final Energy Efficiency Report13/02/19 Preliminary Design (30%) TRC

Draft Preliminary Design Report (BODR)

28/04/19 Final Preliminary Design Report (BODR)

12/08/19 Geotechnical Investigation Report

15/07/19 60% Design TRC 14/10/19 90% Design TRC 

29/11/19 Draft Tender Documents

28/01/20 Final Zai WTP & Transmission System Tender Documents28/02/20 Task 3 Summary Report

29/12/18 Draft Madaba WWTP Assessment Report

29/01/19 Final Madaba WWTP Assessment Report

29/06/19 Draft Feasibility Study & Analysis Report

30/07/19 Final Feasibility Study & Analysis Report

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 4

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 35: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

423 Feasibility Study Workshop 1 day 15/08/19 15/08/19424 Environmental Impact Assessment 270 days 30/12/18 25/09/19425 Perform Comprehensive Environmental Impact Assessment 270 days 30/12/18 25/09/19426 Review Previous Environmental & Social Impact Assessment Reports90 days 30/12/18 29/03/19427 Conduct Scoping Session 1 day 28/02/19 28/02/19428 Draft Scoping Statement 1 day 14/03/19 14/03/19429 USAID/MWI/WAJ Review and Approval 10 days 15/03/19 24/03/19430 Final Scoping Statement 1 day 03/04/19 03/04/19431 Draft EIA Report 1 day 11/08/19 11/08/19432 USAID/MWI/WAJ Review and Approval 30 days 12/08/19 10/09/19433 Final EIA Report 1 day 25/09/19 25/09/19434  Detailed Design and Preparation of Tender Documents 394 days 17/07/19 13/08/20435  Conduct Topo survey and soil investigation 90 days 16/08/19 13/11/19436  Soil Investigation Tender Documents 1 day 17/07/19 17/07/19437  Soil Investigation Report 1 day 14/12/19 14/12/19438  Prepare Basis of Design Report 120 days 31/07/19 27/11/19439 Basis of Design (30%) TRC 1 day 28/11/19 28/11/19440  Draft Basis of Design Report (BODR) 1 day 14/12/19 14/12/19441  USAID/MWI/WAJ Review and Approval 15 days 15/12/19 29/12/19442  Final Basis of Design Report (BODR) 1 day 14/01/20 14/01/20443 Preparation of Detailed Designs, Tender Documents & BOQ 180 days 15/01/20 12/07/20444  60% TRC 1 day 15/03/20 15/03/20445  90% TRC 1 day 13/06/20 13/06/20446  Define Locations and Land Requirements 30 days 14/05/20 12/06/20447  Assist MWI/WAJ Prepare Land Acquisition Documents 90 days 14/05/20 11/08/20448  Prepare Confidential Cost Estimate 60 days 14/05/20 12/07/20449 Draft Madaba WWTP Construction Tender Documents 1 day 13/07/20 13/07/20450  USAID/MWI/WAJ Review and Approval 15 days 14/07/20 28/07/20451 Final Madaba WWTP Construction Tender Documents 1 day 13/08/20 13/08/20452  Pre‐contract Services & Construction Supervision (if WAJ Secures 1084 days 29/02/20 16/02/23453 Pre‐Contract Services 364 days 29/02/20 26/02/21454  Assist in prequalification 150 days 29/02/20 27/07/20455  Draft Prequalification Evaluation Report 1 day 28/07/20 28/07/20456  USAID/MWI/WAJ Review & Approval 15 days 29/07/20 12/08/20457  Final Prequalification Evaluation Report 1 day 28/08/20 28/08/20458  Assist in Tendering 150 days 29/08/20 25/01/21459  Draft Tender Evaluation Report 1 day 26/01/21 26/01/21460  USAID/MWI/WAJ Review & Approval 15 days 27/01/21 10/02/21461  Final Tender Evaluation Report 1 day 26/02/21 26/02/21462 Construction Supervision (The Construction Period Ends Beyond the 

End of the Project)720 days 27/02/21 16/02/23

463  Act as the Engineer under the contract 720 days 27/02/21 16/02/23464  Post Contract Closeout Activities 150 days 20/09/22 16/02/23465  Certified As‐Built & Substantial Completion Certificate 150 days 20/09/22 16/02/23466 Task 4 Summary Report 1 day 19/03/23 19/03/23467 TASK 5 – EXPANSION OF RAMTHA WASTEWATER TREATMENT 

PLANT1692 days 01/08/18 19/03/23

468 Feasibility Study & Environmental Impact Assessment 421 days 01/08/18 25/09/19469  Collect, Review and Analyze All Available Data 120 days 01/08/18 28/11/18470  Conduct Tests of Wastewater Quality  90 days 31/08/18 28/11/18471 Conduct Survey Work for Critical Locations needed to Conduct the 

Feasibility Study60 days 31/08/18 29/10/18

472  Assess & Evaluate Conditions, Serviceability & Capacity of the Existing Systems

120 days 31/08/18 28/12/18

473  Assess Staff and Equipment & Recommend improvements 120 days 31/08/18 28/12/18474  Assess & Describe the Operational Aspects of the WWTP 120 days 31/08/18 28/12/18475  Establish Appropriate O&M Procedures 120 days 31/08/18 28/12/18476 Evaluation of Existing Facilities Rehabilitation, Upgrading & Expansion 120 days 31/08/18 28/12/18

477 Draft Ramtha WWTP Assessment Report 1 day 29/12/18 29/12/18

15/08/19 Feasibility Study Workshop

28/02/19 Conduct Scoping Session14/03/19 Draft Scoping Statement

03/04/19 Final Scoping Statement11/08/19 Draft EIA Report

25/09/19 Final EIA Report

17/07/19 Soil Investigation Tender Documents14/12/19 Soil Investigation Report

28/11/19 Basis of Design (30%) TRC14/12/19 Draft Basis of Design Report (BODR)

14/01/20 Final Basis of Design Report (BODR)

15/03/20 60% TRC13/06/20 90% TRC

13/07/20 Draft Madaba WWTP Construction Tender Documents

13/08/20 Final Madaba WWTP Construction Tender Documents

28/07/20 Draft Prequalification Evaluation Report

28/08/20 Final Prequalification Evaluation Report

26/01/21  Draft Tender Evaluation Report

26/02/21  Final Tender Evaluation Report

19/03/23 T

29/12/18 Draft Ramtha WWTP Assessment Report

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 5

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 36: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

478  USAID/MWI/WAJ Review and Approval 15 days 30/12/18 13/01/19479 Final Ramtha WWTP Assessment Report 1 day 29/01/19 29/01/19480  Study Agricultural Practices, Determine the Suitable Crops & Identify 

Effluent Reuse Areas & Sludge Disposal Facilities120 days 30/01/19 29/05/19

481 Perform Feasibility Study, Analysis & Cost Estimates 150 days 30/01/19 28/06/19482 Perform Energy Efficiency Study 120 days 01/03/19 28/06/19483 Perform Economic, Financial, & Socio Economic Analysis 120 days 01/03/19 28/06/19484  Draft Feasibility Study & Analysis Report 1 day 29/06/19 29/06/19485  USAID/MWI/WAJ Review and Approval 15 days 30/06/19 14/07/19486  Final Feasibility Study & Analysis Report 1 day 30/07/19 30/07/19487 Feasibility Study Workshop 1 day 15/08/19 15/08/19488 Environmental Impact Assessment 270 days 30/12/18 25/09/19489 Perform Comprehensive Environmental Impact Assessment 270 days 30/12/18 25/09/19490 Review Previous Environmental & Social Impact Assessment 

Reports90 days 30/12/18 29/03/19

491 Conduct Scoping Session 1 day 28/02/19 28/02/19492 Draft Scoping Statement 1 day 14/03/19 14/03/19493 USAID/MWI/WAJ Review and Approval 10 days 15/03/19 24/03/19494 Final Scoping Statement 0 days 03/04/19 03/04/19495 Draft EIA Report 1 day 11/08/19 11/08/19496 USAID/MWI/WAJ Review and Approval 30 days 12/08/19 10/09/19497 Final EIA Report 1 day 25/09/19 25/09/19498  Detailed Design and Preparation of Tender Documents 394 days 17/07/19 13/08/20499  Conduct Topo survey and soil investigation 90 days 16/08/19 13/11/19500  Soil Investigation Tender Documents 1 day 17/07/19 17/07/19501  Soil Investigation Report 1 day 14/12/19 14/12/19502  Prepare Basis of Design Report (BODR) 120 days 31/07/19 27/11/19503  Basis of Design (30%) TRC 1 day 28/11/19 28/11/19504  Draft Basis of Design Report (BODR) 1 day 14/12/19 14/12/19505  USAID/MWI/WAJ Review and Approval 15 days 15/12/19 29/12/19506  Final Basis of Design Report (BODR) 1 day 14/01/20 14/01/20507 Preparation of Detailed Designs, Tender Documents & BOQ 180 days 15/01/20 12/07/20508  60% TRC 1 day 15/03/20 15/03/20509  90% TRC 1 day 13/06/20 13/06/20510  Define Locations and Land Requirements 30 days 14/05/20 12/06/20511  Assist MWI/WAJ Prepare Land Acquisition Documents 90 days 14/05/20 11/08/20512  Prepare Confidential Cost Estimate 60 days 14/05/20 12/07/20513 Draft Ramtha WWTP Construction Tender Documents 1 day 13/07/20 13/07/20514  USAID/MWI/WAJ Review and Approval 15 days 14/07/20 28/07/20515 Final Ramtha WWTP Construction Tender Documents 1 day 13/08/20 13/08/20516  Pre‐contract Services & Construction Supervision (if WAJ Secures 

funds)1084 days 29/02/20 16/02/23

517 Pre‐Contract Services 364 days 29/02/20 26/02/21518  Assist in prequalification 150 days 29/02/20 27/07/20519  Draft Prequalification Evaluation Report 1 day 28/07/20 28/07/20520  USAID/MWI/WAJ Review & Approval 15 days 29/07/20 12/08/20521  Final Prequalification Evaluation Report 1 day 28/08/20 28/08/20522  Assist in Tendering 150 days 29/08/20 25/01/21523  Draft Tender Evaluation Report 1 day 26/01/21 26/01/21524  USAID/MWI/WAJ Review & Approval 15 days 27/01/21 10/02/21525  Final Tender Evaluation Report 1 day 26/02/21 26/02/21526 Construction Supervision (The Construction Period Ends Beyond the 

End of the Project)720 days 27/02/21 16/02/23

527  Act as the Engineer under the contract 720 days 27/02/21 16/02/23528  Post Contract Closeout Activities 150 days 20/09/22 16/02/23529  Certified As‐Built & Substantial Completion Certificate 150 days 20/09/22 16/02/23530 Task 5 Summary Report 1 day 19/03/23 19/03/23531 TASK 6 ‐ DEIR ALLA WATER & WASTEWATER SYSTEMS 665 days 01/11/18 26/08/20532 Collect, Review and Analyze All Available Data 90 days 01/11/18 29/01/19

29/01/19 Final Ramtha WWTP Assessment Report

29/06/19 Draft Feasibility Study & Analysis Report

30/07/19 Final Feasibility Study & Analysis Report15/08/19 Feasibility Study Workshop

28/02/19 Conduct Scoping Session14/03/19 Draft Scoping Statement

03/04/19 Final Scoping Statement11/08/19 Draft EIA Report

25/09/19 Final EIA Report

17/07/19 Soil Investigation Tender Documents14/12/19 Soil Investigation Report

28/11/19 Basis of Design (30%) TRC14/12/19 Draft Basis of Design Report (BODR)

14/01/20 Final Basis of Design Report (BODR)

15/03/20 60% TRC13/06/20 90% TRC

13/07/20 Draft Ramtha WWTP Construction Tender Documents

13/08/20 Final Ramtha WWTP Construction Tender Documents

28/07/20 Draft Prequalification Evaluation Report

28/08/20 Final Prequalification Evaluation Report

26/01/21  Draft Tender Evaluation Report

26/02/21  Final Tender Evaluation Report

19/03/23 T

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 6

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 37: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

533 Assess & Evaluate Feasibility Study Documents to Proceed with the BODR

90 days 01/11/18 29/01/19

534 Evaluate Existing Systems Adequacy 90 days 01/12/18 28/02/19535 Conduct Topo Surveys & Soil Investigations 90 days 01/12/18 28/02/19536 Soil Investigation Tender Documents 1 day 15/01/19 15/01/19537 Soil Investigation Report 1 day 01/03/19 01/03/19538 Water System Modeling & Design 559 days 31/12/18 11/07/20539 Prepare Basis of Design Report (BODR)  150 days 31/12/18 29/05/19540 Basis of Design (30%) TRC 1 day 30/05/19 30/05/19541 Draft Basis of Design Report (BODR) 1 day 14/06/19 14/06/19542  USAID/MWI/WAJ Review and Approval 15 days 15/06/19 29/06/19543  Final Basis of Design Report (BODR) 1 day 15/07/19 15/07/19544 Prepare Detailed Design & Tender Documents 330 days 16/07/19 09/06/20545 60% TRC 1 day 24/10/19 24/10/19546 90% TRC 1 day 12/03/20 12/03/20547 Define Locations and Land Requirements 60 days 13/01/20 12/03/20548 Assist MWI/WAJ Prepare Land Acquisition Documents 120 days 11/02/20 09/06/20549 Prepare Confidential Cost Estimate 120 days 11/02/20 09/06/20550 Packaging Evaluation 90 days 12/03/20 09/06/20551 Draft Deir Allah & Al‐Karameh Water System Pre‐Contract & Tender 

Documents1 day 10/06/20 10/06/20

552  USAID/MWI/WAJ Review and Approval 15 days 11/06/20 25/06/20553 Final Deir Allah & Al‐Karameh Water System Pre‐Contract & Tender 

Documents1 day 11/07/20 11/07/20

554 Wastewater System Modeling & Design 559 days 31/12/18 11/07/20555 Prepare Basis of Design Report (BODR) 150 days 31/12/18 29/05/19556 Basis of Design (30%) TRC 1 day 30/05/19 30/05/19557 Draft  Basis of Design Report (BODR) 1 day 14/06/19 14/06/19558 USAID/MWI/WAJ Review and Approval 15 days 15/06/19 29/06/19559 Final Basis of Design Report (BODR) 1 day 15/07/19 15/07/19560 Prepare Detailed Design & Tender Documents 330 days 16/07/19 09/06/20561  60% TRC 1 day 24/10/19 24/10/19562  90% TRC 1 day 12/03/20 12/03/20563  Define Locations and Land Requirements 60 days 13/01/20 12/03/20564 Assist MWI/WAJ Prepare Land Acquisition Documents 120 days 11/02/20 09/06/20565 Prepare Confidential Cost Estimate 120 days 11/02/20 09/06/20566 Packaging Evaluation 90 days 12/03/20 09/06/20567 Draft Deir Allah & Al‐Karameh Wastewater System Pre‐Contract & 

Tender Documents1 day 10/06/20 10/06/20

568  USAID/MWI/WAJ Review and Approval 15 days 11/06/20 25/06/20569 Final Deir Allah & Al‐Karameh Wastewater System Pre‐Contract & 

Tender Documents1 day 11/07/20 11/07/20

570 Task 6 Summary Report 1 day 26/08/20 26/08/20571 Task 6 Executive Summary Report 1 day 26/08/20 26/08/20572 TASK 7 ‐ BANI KENANAH WATER & WASTEWATER SYSTEMS 1014 days 01/02/19 10/11/21573 Assessment of Water/Wastewater Systems & Preparation of 

Master Plan428 days 01/02/19 03/04/20

574 Collect, Review and Analyze All Available Data 150 days 01/02/19 30/06/19575 Collect & Update Information about Existing & Future Water 

Resources 150 days 01/02/19 30/06/19

576 Conduct Tests of Water & Wastewater Quality  90 days 02/04/19 30/06/19577 Assess & Evaluate Conditions, Serviceability & Capacity of the Existing

Systems120 days 03/03/19 30/06/19

578 Evaluate Existing Systems Adequacy 150 days 03/03/19 30/07/19579  Assess Staff and Equipment & Recommend improvements 150 days 03/03/19 30/07/19580  Establish Appropriate O&M Procedures 120 days 02/04/19 30/07/19581 Draft Water & Wastewater Systems Assessment Report 1 day 31/07/19 31/07/19582 USAID/MWI/WAJ Review and Approval 15 days 01/08/19 15/08/19583 Final Water & Wastewater Systems Assessment Report 1 day 31/08/19 31/08/19584 Prepare & Apply W/WW Hydraulic Models 270 days 02/04/19 27/12/19585 W/WW Systems Hydraulic Models & User's Manuals 1 day 28/12/19 28/12/19

15/01/19 Soil Investigation Tender Documents01/03/19 Soil Investigation Report

30/05/19 Basis of Design (30%) TRC14/06/19 Draft Basis of Design Report (BODR)

15/07/19 Final Basis of Design Report (BODR)

24/10/19 60% TRC12/03/20 90% TRC

10/06/20 Draft Deir Allah & Al‐Karameh Water System Pre‐Contract & Tender Documents

11/07/20 Final Deir Allah & Al‐Karameh Water System Pre‐Contract & Tender Documents

30/05/19 Basis of Design (30%) TRC14/06/19 Draft  Basis of Design Report (BODR)

15/07/19 Final Basis of Design Report (BODR)

24/10/19 60% TRC12/03/20 90% TRC

10/06/20 Draft Deir Allah & Al‐Karameh Wastewater System Pre‐Contract & Tender Documents

11/07/20 Final Deir Allah & Al‐Karameh Wastewater System Pre‐Contract & Tender Documents

26/08/20 Task 6 Summary Report26/08/20 Task 6 Executive Summary Report

31/07/19 Draft Water & Wastewater Systems Assessment Report

31/08/19 Final Water & Wastewater Systems Assessment Report

28/12/19 W/WW Systems Hydraulic Models & User's Manuals

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 7

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 38: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

586 Conduct Flow & Pressure Measurements 120 days 01/06/19 28/09/19587 Land Use, Population, Water Demand & Wastewater Generation 

Projections 180 days 02/04/19 28/09/19

588 Prepare Analysis, Rehabilitation & Restructuring 180 days 02/04/19 28/09/19589 Prepare Prioritization & Cost Estimate  180 days 02/04/19 28/09/19590 Draft Water & Wastewater Master Plan 1 day 28/12/19 28/12/19591 USAID/MWI/WAJ Review and Approval 15 days 29/12/19 12/01/20592 Final Water & Wastewater Master Plan 1 day 28/01/20 28/01/20593 Develop/Update GIS Database 428 days 01/02/19 03/04/20594 Assess Conditions, Prepare Work & Staffing Plan & Collect Data  120 days 01/02/19 31/05/19595 Draft GIS Work & Staffing Plan 1 day 03/03/19 03/03/19596 USAID/MWI/WAJ Review and Approval 15 days 04/03/19 18/03/19597 Final GIS Work & Staffing Plan 1 day 03/04/19 03/04/19598 GIS Database Preparation 365 days 04/04/19 02/04/20599 GIS Database Submittal 1 day 03/04/20 03/04/20600 GIS Training & Support 365 days 04/04/19 02/04/20601 Assist MWI/WAJ Staff to Develop & Apply GIS System 365 days 04/04/19 02/04/20602 Water & Wastewater Feasibility Study & Environmental Impact 

Assessment270 days 05/10/19 30/06/20

603 Identify, Evaluate & Recommend the Rehabilitation, Upgrading & Expansion of Water & Wastewater systems

120 days 29/01/20 27/05/20

604 Conduct Survey Work for Critical Locations needed to Conduct the Feasibility Study

60 days 29/01/20 28/03/20

605  Study Agricultural Practices, Determine the Suitable Crops & Identify Effluent Reuse Areas & Sludge Disposal Facilities

120 days 29/01/20 27/05/20

606 Perform Feasibility Study, Analysis & Cost Estimates 120 days 29/01/20 27/05/20607 Perform Energy Efficiency Study & Recommend Solutions 120 days 29/01/20 27/05/20608 Perform Economic, Financial, & Socio Economic Analysis 120 days 29/01/20 27/05/20609 10% TRC 1 day 13/04/20 13/04/20610  Draft Feasibility Study & Analysis Report 1 day 28/05/20 28/05/20611 Feasibility Study Workshop 1 day 05/06/20 05/06/20612  USAID/MWI/WAJ Review and Approval 15 days 29/05/20 12/06/20613  Final Feasibility Study & Analysis Report 1 day 28/06/20 28/06/20614 Environmental Impact Assessment 270 days 05/10/19 30/06/20615 Perform Comprehensive Environmental Impact Assessment 270 days 05/10/19 30/06/20616 Review Previous Environmental & Social Impact Assessment 

Reports90 days 05/10/19 02/01/20

617 Conduct Scoping Session 1 day 03/01/20 03/01/20618 Draft Scoping Statement 1 day 03/02/20 03/02/20619 USAID/MWI/WAJ Review and Approval 15 days 04/02/20 18/02/20620 Final Scoping Statement 1 day 04/03/20 04/03/20621 Draft EIA Report 1 day 02/05/20 02/05/20622 USAID/MWI/WAJ Review and Approval 30 days 03/05/20 01/06/20623 Final EIA Report 1 day 30/06/20 30/06/20624 Water & Wastewater Systems Detailed Design & Tender Documen469 days 29/06/20 10/10/21625 Conduct Topo Surveys & Soil Investigations 120 days 29/06/20 26/10/20626 Soil Investigation Tender Documents 1 day 29/07/20 29/07/20627 Soil Investigation Report 1 day 27/10/20 27/10/20628 Prepare Basis of Design Report (BODR)  120 days 29/06/20 26/10/20629 Prepare Basis of Design (30%) TRC 1 day 27/10/20 27/10/20630 Draft Basis of Design Report (BODR)  1 day 11/11/20 11/11/20631  USAID/MWI/WAJ Review and Approval 15 days 12/11/20 26/11/20632  Final Basis of Design Report (BODR)  1 day 12/12/20 12/12/20633 Prepare Detailed Design & Tender Documents 270 days 13/12/20 08/09/21634 60% TRC 1 day 23/03/21 23/03/21635 90% TRC 1 day 10/08/21 10/08/21636 Define Locations and Land Requirements 60 days 12/06/21 10/08/21637 Assist MWI/WAJ Prepare Land Acquisition Documents 120 days 12/05/21 08/09/21638 Prepare Confidential Cost Estimate 120 days 12/05/21 08/09/21639 Packaging Evaluation 90 days 11/06/21 08/09/21640 Draft Water & Wastewater Systems Pre‐Contract & Tender Documents1 day 09/09/21 09/09/21

28/12/19 Draft Water & Wastewater Master Plan

28/01/20 Final Water & Wastewater Master Plan

03/03/19 Draft GIS Work & Staffing Plan

03/04/19 Final GIS Work & Staffing Plan

03/04/20 GIS Database Submittal

13/04/20 10% TRC28/05/20 Draft Feasibility Study & Analysis Report05/06/20 Feasibility Study Workshop

28/06/20 Final Feasibility Study & Analysis Report

03/01/20 Conduct Scoping Session03/02/20 Draft Scoping Statement

04/03/20 Final Scoping Statement02/05/20 Draft EIA Report

30/06/20 Final EIA Report

29/07/20 Soil Investigation Tender Documents27/10/20 Soil Investigation Report

27/10/20 Prepare Basis of Design (30%) TRC11/11/20 Draft Basis of Design Report (BODR) 

12/12/20 Final Basis of Design Report (BODR) 

23/03/21 60% TRC10/08/21 90% TRC

09/09/21 Draft Water & Wastewater Systems Pre‐Contract & Tender Docum

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 8

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 39: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

ID Task Name Duration Start Finish

641  USAID/MWI/WAJ Review and Approval 15 days 10/09/21 24/09/21642 Final Water & Wastewater Systems Pre‐Contract & Tender Documents1 day 10/10/21 10/10/21643 Task 7 Summary Report 1 day 10/11/21 10/11/21644 Task 7 Executive Summary Report 1 day 10/11/21 10/11/21645 TASK 8 ‐ TECHNICAL ASSISTANCE TO WATER UTILITIES 1429 days 14/10/18 11/09/22646 Review all Previous Related Studies, Reports, and Data 1429 days 14/10/18 11/09/22663 Identify Entities that Need Technical Support 1429 days 14/10/18 11/09/22680 Evaluate the Entities Situation & Prepare Findings & Solutions Report 1429 days 14/10/18 11/09/22697 TASK 9 ‐ W/WW SYSTEMS ASSESSMENT, FEASIBILITY STUDIES, 

DESIGNS, TENDER’G, & CMS 1448 days 13/10/18 29/09/22

10/10/21 Final Water & Wastewater Systems Pre‐Contract & Tender Do10/11/21 Task 7 Summary Report10/11/21 Task 7 Executive Summary Report

S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M7 Q4 '17 Q1 '18 Q2 '18 Q3 '18 Q4 '18 Q1 '19 Q2 '19 Q3 '19 Q4 '19 Q1 '20 Q2 '20 Q3 '20 Q4 '20 Q1 '21 Q2 '21 Q3 '21 Q4 '21 Q1 '22 Q2 '22 Q3 '22 Q4 '22 Q1 '23

Jordan Water Infrastructure (JWI) Draft Workplan Schedule

Legend:TRC: Technical Review Committee PQM: Project Quality Management Page 9

Task Order Signed: July. 15 2018Tasks 3, 4 & 5 Start Date: Aug. 1 2018

Project End Date: Sep. 30 2022

Page 40: USAID JORDAN WATER INFRASTRUCTURE Quarterly Progress Report

1st Quarterly Report: USAID Jordan Water Infrastructure P 31/31 October 15, 2018, revised October 29 & Nov 4, 2018]