6
Technical Note Using equivalent grade factors to find the optimum cut-off grades of multiple metal deposits M. Osanloo * , M. Ataei Department of Mining, Metallurgy and Petroleum Engineering, Amirkabir University of Technology, Tehran Polytechnic, 424 Hafez Ave., PO Box 15875-4413, Tehran, 15914 Iran Received 11 September 2002; accepted 14 April 2003 Abstract One of the most important aspects of mine design is to determine the optimum cut-off grades. Material grading above and below the cut-off is directed to different destinations. Optimization of cut-off grade is now an accepted principle for open pit planning studies. The most commonly criteria used in cut-off grade optimization is to maximize net present value. Lane formulated the concept of cut-off grade optimization for single metal deposit but this method cannot be use in multiple metal deposits. Because in single metal deposits six points are possible candidates for the optimum cut-off grade, in multiple metal deposits an infinite number of points are possible candidates for the optimum cut-off grades. The objective function evaluation of these infinite points is im- possible. In this paper, the equivalent grade factor is used to find optimum cut-off grade of multiple metal deposits. First, the objective function is defined for multiple metal deposits and then objective function is converted to one variable function by using equivalent factors. The optimum equivalent cut-off grade of main metal can be found by the optimization techniques such as the Lane algorithm or elimination methods. At final step, the optimum cut-off grades will be determined by interpolation of grade- tonnage distribution of deposit. Ó 2003 Elsevier Ltd. All rights reserved. Keywords: Modelling; Optimization 1. Introduction One of the most critical parameters in mining oper- ation is cut-off grade. Taylor presents one of the best definitions of cut-off grade. He defined cut-off grade as ‘‘any grade that, for any specific reason, is used to sep- arate two courses of action, e.g. to mine or to leave, to mill or to dump ...’’ (Taylor, 1972, 1985). Most researchers have used break-even cut-off grade criteria to define ore as a material that just will pay mining and processing costs. These methods are not optimum but the mine planner often seeks to optimize the cut-off grade of ore to maximize the net present value (NPV). The determination of the optimum cut-off grade of single metal deposit can be very complex even when price and cost are assumed constant, but it in- volves the costs and capacities of the several stages of the mining operations, the waste/ore ratios, average grades of different increments of the ore body and so on. Lane (1964, 1988) has developed a comprehensive theory of cut-off grade calculation for a single metal deposit. Whittle and Wharton added the idea of using opportunity cost. They introduced two pseudo costs, which are also important. They are referred to as delay cost and the change cost (Whittle and Wharton, 1995a,b) but this algorithm cannot be use in multiple metal deposits. The reason is due to the fact that, while in single metal deposits six points are possible candi- dates for the optimum cut-off grade (Lane, 1988), in multiple metal deposits an infinite number points are possible candidates for the optimum cut-off grades and the objective function evaluation of these infinite points is impossible. These types of deposits can be evaluated based on a value per ton of ore calculated from the net smelter re- turn (NSR). NSR represented the total value of metals recovered from each ton of ore minus the cost of smelting (Annels, 1991). In this method, it is possible * Corresponding author. Tel.: +98-21-64542929; fax: +98-21- 6413969. E-mail address: [email protected] (M. Osanloo). 0892-6875/03/$ - see front matter Ó 2003 Elsevier Ltd. All rights reserved. doi:10.1016/S0892-6875(03)00163-8 Minerals Engineering 16 (2003) 771–776 This article is also available online at: www.elsevier.com/locate/mineng

Using Equivalent Grade

Embed Size (px)

DESCRIPTION

Um bom trabalho

Citation preview

  • ical

    o me

    o *,

    ring,

    5875-

    2002;

    mine

    f cut

    timiz

    concept of cut-o grade optimization for single metal deposit but this method cannot be use in multiple metal deposits. Because in

    single metal deposits six points are possible candidates for the optimum cut-o grade, in multiple metal deposits an innite number

    any grade that, for any specic reason, is used to sep- deposit. Whittle and Wharton added the idea of using

    is impossible.

    These types of deposits can be evaluated based on a

    value per ton of ore calculated from the net smelter re-

    turn (NSR). NSR represented the total value of metals

    recovered from each ton of ore minus the cost of*

    Minerals Engineering 16 (2Corresponding author. Tel.: +98-21-64542929; fax: +98-21-

    6413969.arate two courses of action, e.g. to mine or to leave, to

    mill or to dump . . . (Taylor, 1972, 1985).Most researchers have used break-even cut-o grade

    criteria to dene ore as a material that just will pay

    mining and processing costs. These methods are not

    optimum but the mine planner often seeks to optimize

    the cut-o grade of ore to maximize the net present

    value (NPV). The determination of the optimum cut-ograde of single metal deposit can be very complex even

    when price and cost are assumed constant, but it in-

    opportunity cost. They introduced two pseudo costs,

    which are also important. They are referred to as delay

    cost and the change cost (Whittle and Wharton,

    1995a,b) but this algorithm cannot be use in multiple

    metal deposits. The reason is due to the fact that, while

    in single metal deposits six points are possible candi-

    dates for the optimum cut-o grade (Lane, 1988), in

    multiple metal deposits an innite number points arepossible candidates for the optimum cut-o grades and

    the objective function evaluation of these innite pointsof points are possible candidates for the optimum cut-o grades. The objective function evaluation of these innite points is im-

    possible. In this paper, the equivalent grade factor is used to nd optimum cut-o grade of multiple metal deposits. First, the

    objective function is dened for multiple metal deposits and then objective function is converted to one variable function by using

    equivalent factors. The optimum equivalent cut-o grade of main metal can be found by the optimization techniques such as the

    Lane algorithm or elimination methods. At nal step, the optimum cut-o grades will be determined by interpolation of grade-

    tonnage distribution of deposit.

    2003 Elsevier Ltd. All rights reserved.

    Keywords: Modelling; Optimization

    1. Introduction

    One of the most critical parameters in mining oper-

    ation is cut-o grade. Taylor presents one of the best

    denitions of cut-o grade. He dened cut-o grade as

    volves the costs and capacities of the several stages of

    the mining operations, the waste/ore ratios, average

    grades of dierent increments of the ore body and so on.

    Lane (1964, 1988) has developed a comprehensive

    theory of cut-o grade calculation for a single metalTechn

    Using equivalent grade factors tof multiple

    M. Osanlo

    Department of Mining, Metallurgy and Petroleum Enginee

    424 Hafez Ave., PO Box 1

    Received 11 September

    Abstract

    One of the most important aspects of mine design is to deter

    the cut-o is directed to dierent destinations. Optimization o

    studies. The most commonly criteria used in cut-o grade opE-mail address: [email protected] (M. Osanloo).

    0892-6875/03/$ - see front matter 2003 Elsevier Ltd. All rights reserved.doi:10.1016/S0892-6875(03)00163-8Note

    nd the optimum cut-o gradestal deposits

    M. Ataei

    Amirkabir University of Technology, Tehran Polytechnic,

    4413, Tehran, 15914 Iran

    accepted 14 April 2003

    the optimum cut-o grades. Material grading above and below

    -o grade is now an accepted principle for open pit planning

    ation is to maximize net present value. Lane formulated the

    003) 771776This article is also available online at:

    www.elsevier.com/locate/minengsmelting (Annels, 1991). In this method, it is possible

  • sent to the concentrator, Qr1: the amount of product 1

    C

    772 M. Osanloo, M. Ataei / Minerals Engineering 16 (2003) 771776actually produced over this production period, Qr2: theamount of product 2 actually produced over this pro-duction period.

    If d is discount rate, the dierence m between thepresent values of the remaining reserves at times t 0and t T is (Hustrulid and Kuchta, 1995)m P VTd 2where V is the present values at time t 0. SubstitutingEq. (1) into Eq. (2) yields

    m s1 r1Qr1 s2 r2Qr2 mQm cQc f VdT 3

    The quantities of rened metals Qr1 and Qr2 are re-lated to that send from the mine to concentrator (Qc),thereforethat to express the grade of one metal in term of another

    (Zhang, 1998; Liimatainen, 1998). Other methods for

    ore/waste discrimination in multiple metal deposits are

    critical level method, single grade cut-o approach,

    dollar value cut-o approach (Annels, 1991; Barid and

    Satchwell, 2001).

    All of these methods are associated with some aws:none of these methods consider the grade distribution of

    the deposits and do not take into account time value of

    money. Furthermore, they completely ignore the ca-

    pacities of the mining system, so the cut-o grades cal-

    culated by these methods are not optimum.

    This paper describes the use of equivalent grade fac-

    tors to optimum the cut-o grades of multiple metal

    deposits.

    2. Objective function

    In large open pit mines, there are typically three

    stages of operations: (i) the mining stage, where units of

    various grade are mined up to some capacity, (ii) the

    treatment stage, where ore is milled and concentrated,again up to some capacity constraint and (ii) the rening

    stage, where the concentrate is smelted and rened to a

    nal product which is shipped and sold; the latest stage

    is also subject to capacity constraints. Each stage has its

    own associated costs and a limiting capacity.

    By considering costs and revenues in this operation,

    the prot is determined by using the following equation:

    P s1 r1Qr1 s2 r2Qr2 mQm cQc fT 1where P : prot ($), m: mining cost ($/ton of materialmoved), c: concentrating cost ($/ton of material con-centrated), r1: renery cost ($/unit of product 1), r2: re-nery cost ($/unit of product 2), f : xed cost ($), s1:selling price ($/unit of product 1), s2: selling price ($/unitof product 2), T : the length of the production period,Qm: quantity of material to be mined, Qc: quantity of oreQr1 gg1y1Qc 4Qr2 gg2y2Qc 5where gg1: average grade of metal 1 sent for concentra-tion, gg2: average grade of metal 2 sent for concentration,y1: recovery of metal 1 from the ore, y2: recovery ofmetal 2 from the ore.

    Substituting Eqs. (4) and (5) into Eq. (3) yields

    m s1 r1gg1y1 s2 r2gg2y2 cQc mQm f VdT 6

    One would now like to schedule the mining operation

    in such a way that the depreciation in the present value

    takes place sooner rather than later. This is because later

    prots are discounted more than those captured earlier.

    In examining Eq. (6), this means that m has to be max-imized. m is a function of two variables: grade of metal 1and grade of metal 2.

    In Eq. (6), the grade of metal 2 is converting to grade

    of metal 1 by using equivalent factor. Therefore m will befunction of grade of metal 1 and Eq. (6) yields

    m s1

    r1y1 gg1

    s2 r2y2s1 r1y1 gg2 c

    Qc

    mQm f VdT 7Equivalent factor is equal to

    Feq s2 r2y2s1 r1y1 8

    Substituting Eq. (8) into Eq. (7) yields

    m s1 r1y1gg1 Feqgg2 cQc mQm f VdT9

    To calculate the average equivalent grade of ore based

    upon equivalent factor and average grade of each metal,

    the following equation can be used:

    ggeq gg1 Feqgg2 10Substituting Eq. (10) into Eq. (9) yields

    m s1 r1y1ggeq cQc mQm f VdT 11Eq. (11) is the fundamental formula for calculation of

    optimum cut-o grades of ore. The time taken T is re-lated to the constrain capacity. Three cases arise de-pending upon which of the three capacities is actually

    limiting factor.

    If the mining capacity (M) is the limiting factor thenthe time T is given by

    T QmM

    12 If the concentrating capacity (C) is the limiting factor

    then the time T is controlled by the concentrator

    T Qc 13

  • o grades. These methods require only objective func-

    tion evaluations and do not use the derivative of the

    function to nd the optimum point (Rardin, 1998). In

    these methods at rst step, the uncertainty space of theproblem is estimated. In next step by selecting test points

    in uncertainty space and evaluating and comparing ob-

    jective function at these test points, a part of uncertainty

    space will be eliminated. This procedure is repeated until

    uncertainty interval in each direction is less than a small-

    specied positive value e. Where e is desirable accuracyto determine the optimum cut-o grades. Ratio of re-

    mained length after elimination process to initial lengthin each dimension is called reduction ratio. Among of

    these methods, the reduction ratio of golden section

    search method is optimum and equal to 0.618 (this

    number called the golden number). In this method, ratio

    of eliminated length to initial length will be equal 0.382.

    Using the golden section rule means that for every stage

    of the uncertainty range reduction (except the rst one),

    M. Osanloo, M. Ataei / Minerals Engineering 16 (2003) 771776 7733. Determination of optimum cut-o grades

    As previously mentioned, using equivalent factor, the

    objective function must be converted to one variable

    function. Then optimization techniques such as Lane

    algorithm or elimination methods can be use to nd

    optimum cut-o grades.

    According to Lane algorithm, there are three limiting

    cut-o grades and three balancing cut-o grades. If only

    the capacity of one operation is limited factor then thebreak-even cut-o grade for that stage will be the opti-

    mum cut-o grade. To nd the grades that maximize the

    NPV under dierent constraints, one rst takes the de-

    rivative of Eqs. (15)(17) with respect to grade. In next

    step, setting derivative of Eqs. (15)(17) equal zero, it

    will obtain three economic optimum cut-o grades.

    When mining operations are constrained by more

    than one capacity, the optimum cut-o grade calculatedby conventional method may not necessarily be a break-

    even cut-o grade. In such a case, the balancing cut-o

    grade for each pair of stage needs to be considered as

    well. A balancing grade is one that which allows both

    stages of the pair being considered to achieve maximum

    capacities jointly. Therefore, the balancing cut-o

    grades are independent of economics and being deter-

    mined by using the grade distribution and the capacitiesof each of the dierent system. Based on these consid- If the renery output of main metal (Rm) is the limit-ing factor then the time T is controlled by the reningof main metal

    T Qr1Rm

    gg1y1QcRm

    14

    Substituting Eqs. (12)(14) into Eq. (11) yields the fol-

    lowing equations:

    mm s1 r1ggeqy1 cQc m

    f VdM

    Qm 15

    mc s1

    r1ggeqy1 c

    f VdC

    Qc mQm 16

    mr s1

    r1 f VdRm

    ggeqy1 c

    Qc mQm 17

    Now for any pair of cut-o grades, it is possible to

    calculate the corresponding mm, mc and mr. The control-ling capacity is always the one corresponding to the leastof these three equations. Therefore

    max me maxminmm; mc; mr 18In Eqs. (15)(17), V is unknown value because it

    depends upon the cut-o grade. Since the unknown Vappears in the equation thus iterative process must be

    used.erations, now six cut-o grades are candidate for overall

    optimum cut o grade. The optimum cut-o grade will

    be one of the six cut-o grades consisting of the three

    limiting economic cut-o grades and the three balancing

    cut-o grades. Fig. 1 shows six candidate cut-o grades.

    Lane has presented a graphical method to determine

    overall optimum cut-o of ore among of these six cut-ogrades.

    The optimum cut-o grade for a particular pair of

    stages is the balancing grade limited by both stages. If

    only one of the stages in the pair is a bottleneck then the

    optimum cut-o grade for the pair is the breakeven cut-

    o grade for the limiting stage. The overall optimum

    cut-o grade is the middle value of the optimum cut-os

    for the three stages.In this case, objective function is a unimodal func-

    tion. So elimination methods such as dichotomous

    search method, Fibonacci search method and Golden

    section search method will be used to nd optimum cut-

    Fig. 1. mm, mc mr and me curves and six candidate cut-o grades.

  • rst step, assume L;U be the initial interval of uncer-tainty and note that the initial interval included the

    optimum point. Then, select two test points, g1 and g2.Locations of these points are

    g1 L U L 0:382 19g2 L U L 0:618 20In next step, the objective function of points g1 and g2will be calculated. Depending on the objective function

    value of these points, the length of the new interval of

    uncertainty successively is reduced. By placing a new

    observation, the process is repeated until the optimum

    point with desirable accuracy is found.

    4. Example

    Consider a hypothetical situation wherein nal pit

    limits of Cu/Mo deposit has been superimposed on a

    mineral inventory. The pit outline contains 14.4 million

    tons of materials. The gradetonnage distribution and

    average grades of ore for each metal are shown in Tables

    13 and associated costs, prices, capacities, quantities

    and recoveries are given in Table 4.According to Eq. (8), equivalent factor for this situ-

    Fig. 2. Flowchart for nding the optimum cut-o grade by the golden

    section search method.

    774 M. Osanloo, M. Ataei / Minerals Engineering 16 (2003) 771776the objective function will be evaluated at one new point

    (Chong and Zak, 1996; Rao, 1996).

    Fig. 2 shows owchart to calculate the optimum cut-o grade of ore by the golden section search method. InTable 1

    Gradetonnage distribution of copper and molybdenum

    Copper (%) Molybdenum (%)

    00.025 0.0250.05 0

    00.1 1,320,000 900,000 2

    0.10.2 360,000 300,000 2

    0.20.3 735,000 525,000 3

    0.30.4 1,110,000 570,000 3

    0.40.5 525,000 255,000

    0.50.6 510,000 300,000 210,000 105,000 30,000

    0.60.7 375,000 270,000 210,000 90,000 90,000

    >0.7 645,000 690,000 5

    Table 2

    Average grade of copper of dierent copper and molybdenum intervals

    Copper (%) Molybdenum (%)

    00.025 0.0250.05 0

    00.1 0.02 0.03 0

    0.10.2 0.12 0.17 0

    0.20.3 0.25 0.27 0

    0.30.4 0.33 0.32 0

    0.40.5 0.44 0.47 0

    0.50.6 0.53 0.55 0

    0.60.7 0.67 0.63 0

    >0.7 0.98 1.04 170,000 495,000 360,000

    .050.075 0.0750.1 >0.1

    .02 0.03 0.05

    .16 0.19 0.14

    .25 0.22 0.26

    .35 0.34 0.37

    .45 0.48 0.46

    .57 0.54 0.55

    .65 0.64 0.66

    .02 1.09 1.01ation is

    Feq 6797:15 190 0:81674:5 63 0:82 4

    1

    .050.075 0.0750.1 >0.1

    85,000 315,000 510,000

    40,000 135,000 60,000

    00,000 210,000 30,000

    75,000 135,000 30,000

    75,000 60,000 90,000

  • Table 3

    Average grade of molybdenum of dierent copper and molybdenum intervals

    Copper (%) Molybdenum (%)

    00.025 0.0250.05 0.050.075 0.0750.1 >0.1

    00.1 0.002 0.026 0.052 0.076 0.113

    0.10.2 0.017 0.031 0.06 0.085 0.114

    0.20.3 0.011 0.028 0.066 0.091 0.137

    0.30.4 0.031 0.042 0.058 0.094 0.138

    0.40.5 0.006 0.035 0.054 0.091 0.119

    0.50.6 0.012 0.039 0.07 0.082 0.152

    0.60.7 0.014 0.029 0.062 0.085 0.12

    >0.7 0.009 0.038 0.063 0.086 0.128

    M. Osanloo, M. Ataei / Minerals Engineering 16 (2003) 771776 775Table 4

    Economic parameters for a manual example

    Parameter Unit Quantity

    Mine capacity Tons per year 2,500,000

    Mill capacity Tons per year 750,000

    Rening capacity (copper) Tons per year 5000

    Rening capacity (molybde-

    num)

    Tons per year 1000

    Mining cost Dollars per ton 1.06

    Milling cost Dollars per ton 3.52

    Rening cost (copper) Dollars per ton 63

    Rening cost (molybdenum) Dollars per ton 190

    Fixed costs Dollars per 790,000Now using the equivalent factor and average grade of

    each metal, the equivalent copper grade of dierent

    copper grade is calculated (Table 5).

    Converting molybdenum grade into copper grade, the

    gradetonnage distribution of two metal deposits is

    converted into one-dimensional grade tonnage distri-

    bution and cut-o grade optimization method of single

    metal deposit such as Lane method or eliminationmethod was used to calculate the optimum cut-o

    grades in year by year. Then the gradetonnage curve of

    deposit is adjusted for each year of mine life. To do this,

    tonnage of ore in rst year of mine life from the grade

    of copper: Tonnage of ore 10779464.65, Tonnage ofwaste 3620536.45,Waste: ore 0.3358, Average equiv-

    Table 5

    Equivalent copper grade of dierent copper grade

    Copper grade (%) Average grade

    Copper (%) Molybdenum (

    00.1 0.0282 0.0368

    0.10.2 0.1522 0.044

    0.20.3 0.2525 0.0364

    0.30.4 0.332 0.0437

    0.40.5 0.4521 0.0266

    0.50.6 0.5442 0.0451

    0.60.7 0.652 0.043

    0.72 1.0269 0.0567

    year

    Price (copper) Dollars per ton 1674.5

    Price (molybdenum) Dollars per ton 6797.15

    Recovery (copper) % 82

    Recovery (molybdenum) % 80

    Discount rate % 20alent grade 0.6238%.If concentrator capacity is controlling factor, then the

    mine life is equal to

    10779463:65

    750; 000 14:37 yeardistribution intervals above optimum cut-o grades and

    tonnage of waste in rst year of mine life from the grade

    distribution intervals below optimum cut-o grades was

    subtracted. These calculations are repeated until the end

    of mine life. Table 6 shows the optimum cut-o grades

    of ore for dierent years of mine life.

    5. Justication of the proposed method

    To justify proposed method, the NPV of break-even

    equivalent cut-o grade was calculated and compared

    with NPV calculated by proposed method. By deni-

    tion, the break-even equivalent cut-o grade is grade

    that revenue is equal to costs. So

    1674:5 63 geq100

    0:82 1:06 3:52) geq 0:3466

    Thus, break-even equivalent cut-o grade of copper is

    0.3466%. Using interpolation technique and Table 5, thecopper grade is calculated to be 0.1263%. For this gradeYearly revenue will be equal to

    Equivalent

    copper grade (%)Tonnage

    %)

    0.1754 3,330,000

    0.3282 1,095,000

    0.3981 1,800,000

    0.5068 2,220,000

    0.5585 945,000

    0.7246 1,215,000

    0.824 1,035,000

    1.2537 3,760,000

  • 6182964:363

    Hustrulid, W., Kuchta, M., 1995. Open-pit Mine Planning and Design,

    n)

    776 M. Osanloo, M. Ataei / Minerals Engineering 16 (2003) 771776Moreover, yearly cost will be equal to

    Yearly cost 750; 000 1 0:3358 1:06 750; 000 3:52

    4492019:035Yearly cash ow and NPV of mining operation under

    break-even equivalent cut-o grade found to be

    6182964:363 4492019:035 1690945:325 $

    NPV 1690945:3251 0:214:37 1

    0:2 1 0:214:37 7839174:188

    Therefore, NPV of mining operation under break-

    even equivalent cut-o grade is $ 7839174.188 and NPV

    of mining operation under proposed method according

    to Table 6 is $ 16,355,000. Thus, if mining operation is

    operated under proposed method, NPV is more than

    twice of NPV of mining operation under break-even

    equivalent cut-o grade.

    6. Conclusion

    One of the important aspects of mining is decidingYearly revenue 1674:5 63 0:6238100

    0:82 750; 000

    Table 6

    The optimum cut-o grades of dierent years of mine life

    Year Copper cut-o grade (%) Qm (Ton) Qc (To

    1 0.4617 2,010,300 750,000

    2 0.3725 1,345,100 750,000

    3 0.3645 1,601,700 750,000

    4 0.3555 1,555,600 750,000

    5 0.3455 1,507,300 750,000

    6 0.3355 1,462,000 750,000

    7 0.3255 1,419,200 750,000

    8 0.2634 1,222,500 750,000

    9 0.2464 1,181,500 750,000

    10 0.2293 794,700 521,330what material in a deposit is worth mining and pro-

    cessing, and on the contrary, what material is waste.

    This decision-making is summarized by the cut-o gradepolicy. Cut-o grades of multiple metal deposits are

    evaluated by several methods such as NSR method,

    critical level method, single grade cut-o approach,

    dollar value cut-o approach. None of these methods is

    optimum. In this paper, proposed that minable ore is

    ranked based on metals contribution of the mine reve-

    nue and equivalent grade of main metal is determined

    using equivalent factors. Objective function is expressedto one variable function. Then optimization techniques

    such as Lane algorithm or elimination methods must bevol. 1. A.A. Balkema, Rotterdam, Brookled (pp. 512544).

    Lane, K.F., 1964. Choosing the optimum cut-o grade. Quarterly of

    the Colorado School of Mines 59 (4), 811829.

    Lane, K.F., 1988. The Economic Denition of Ore-cut-o Grades in

    Theory and Practice. Mining Journal Books Limited, London.

    p. 145.

    Liimatainen, J., 1998. Valuation model and equivalence factors for

    base metal ores. In: Singhal, J. (Ed.), Proceeding of Mine Planning

    and Equipment Selection. A.A. Balkema, Rotterdam, Brookled,

    pp. 317322.

    Rao, S.S., 1996. Engineering optimization (Theory and Practice), third

    ed. A Wiley-Interscience Publication, John Wiley and Sons Inc,use to nd optimum equivalent cut-o grade for main

    metal (caused more revenue). Optimum cut-o grades

    are determined by interpolation of gradestonnage dis-

    tribution. A verication example is presenting for con-

    rming the approach proposed in this study. The

    comparison of results are shown the NPV of mining

    operation under proposed method is more than twice of

    NPV of mining operation under break-even equivalentcut-o grade.

    References

    Annels, A.E., 1991. Mineral Deposit EvaluationA Partial Approach.

    Chapman and Hall, London (pp. 114117).

    Barid, B.K., Satchwell, P.C., 2001. Application of economic para-

    meters and cut-os during and after pit optimization. Mining

    Engineering, 3340.

    Chong, E.K.P., Zak, S.H., 1996. An Introduction to Optimization. A

    Wiley-Interscience Publication, John Wiley and Sons Inc, New

    York (p. 409).

    Qr1 (Ton) Prot ($) NPV ($)

    4976.9 4,425,600 16,355,000

    4546.2 4,013,100 15,201,000

    4487.3 3,961,200 14,228,000

    4421 3,899,900 13,112,000

    4347.4 3,828,700 11,834,000

    4273.8 3,754,300 10,373,000

    4200.2 3,677,200 8,693,000

    3850.5 3,286,600 6,754,000

    3774.9 3,196,200 4,818,000

    2571.4 3,103,000 2,586,000New York (p. 903).

    Rardin, R.L., 1998. Optimization in Operations Research. Prentice-

    Hall International Inc. (p. 919).

    Taylor, H.K., 1972. General background theory of cut-o grades.

    Institution of Mining and Metallurgy Transactions, A160179.

    Taylor, H.K., 1985. Cut-o gradessome further reections. Institu-

    tion of Mining and Metallurgy Transactions, A204216.

    Whittle, J., Wharton, C., 1995a. Optimizing cut-o grades. Mining

    Magazine, 287289.

    Whittle, J., Wharton, C., 1995b. Optimizing cut-os over time, 25th

    international symposium application of computers and mathemat-

    ics in the mineral industries, 1995b, Australia, pp. 261265.

    Zhang, S., 1998. Multimetal recoverable reserve estimation and its

    impact on the cove ultimate pit design. Mining Engineering, 73

    77.

    Using equivalent grade factors to find the optimum cut-off grades of multiple metal depositsIntroductionObjective functionDetermination of optimum cut-off gradesExampleJustification of the proposed methodConclusionReferences