9/9/2014 1 Virginia Beach Transit Extension Study Draft Environmental Impact Statement Town Center Alignment Alternative Briefing Virginia Beach City Council Virginia Beach City Council September 9, 2014 Presentation 1. Project Background 2. Town Center Alternative 3. Town Center Capital Costs, O&M Costs, and Ridership Forecasts 4. Study Schedule Page 2

Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

Embed Size (px)

Citation preview

Page 1: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

1

Virginia Beach Transit Extension StudyDraft Environmental Impact Statement

Town Center Alignment Alternative BriefingVirginia Beach City CouncilVirginia Beach City Council

September 9, 2014

Presentation

1. Project Background

2. Town Center Alternative

3. Town Center Capital Costs, O&M Costs, and Ridership Forecasts

4. Study Schedule

Page 2

Page 2: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

2

VIRGINIA BEACH TRANSIT EXTENSION STUDY

PROJECT BACKGROUND

Page 3

Project Goals• Provide additional mobility opportunities in the east‐west corridor

• Expand multi‐modal transportation system that supports local land use plans and initiatives (Strategic Growth Areas)p ( g )

• Develop transportation infrastructure that supports the regional tourism industry

Page 4Page 4

Page 3: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

3

Virginia Beach Transit Extension StudyThe Virginia Beach Transit Extension Study (VBTES) is examining the best transit options for a former freight rail right of way that runs from Newtown Road to Birdneck Road in Virginia Beach.  The study area extends from Newtown Road to the Oceanfront area on 19th Street. 

• Four Fixed Guideway Alignment Alternatives from Newtown Road

– Alternative 1a: ~3 miles to the Town Center Area

– Alternative 1b: 4.8 miles to the Rosemont Area

– Alternative 2: 12.2 miles to the Oceanfront along the NSRR corridor (with Maintenance Facility)

– Alternative 3: 13.5 miles to the Oceanfront through the Hilltop Area (with Maintenance Facility)

Page 5

Alternative 1b: 

Alternative 1a: Newtown to Town Center (Town Center Alternative)

Newtown to Rosemont (Rosemont Alternative)

Alternative 2: Newtown to Oceanfront via NSRR ROW (NSRR Alternative)

Page 6

Alternative 3: Newtown to Oceanfront via Laskin Road (Hilltop Alternative)

Page 4: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

4

DEIS Technology Alternatives• Light Rail Transit (LRT)

• Bus Rapid Transit (BRT)

7

Feeder Bus Routes

Page 8

Page 5: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

5

VIRGINIA BEACH TRANSIT EXTENSION STUDY

TOWN CENTER ALTERNATIVE

Page 9

Alternatives 1b, 2, and 3: Newtown to Rosemont and theOceanfront

Page 10

Page 6: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

6

Alternative 1a: Newtown to Town Center (Town Center Alternative)

Page 11

Alternative 1a: Newtown to Town Center (Town Center Alternative)

Page 12

Page 7: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

7

Page 13

Page 14

Page 8: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

8

Page 15

Page 16

Page 9: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

9

Page 17

Page 18

Page 10: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

10

Page 19

Page 20

Page 11: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

11

Page 21

Page 22

Page 12: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

12

Page 23

Page 24

Page 13: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

13

Page 25

Alternative 1a: Newtown to Town Center (Town Center Alternative)

Page 26

Page 14: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

14

TOWN CENTER ALIGNMENT ALTERNATIVE

CAPITAL COSTS, O&M COSTS, AND RIDERSHIP FORECASTS

Page 27

Capital Cost Estimating

Costs Contingency Escalation

Page 28

Page 15: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

15

Capital Cost Assumptions 

Assumptions for the Town Center Light Rail Alternative

• Escalation

• Contingencies

• Real Estate

• Vehicle Costs

• Soft Costs

Page 29

Capital Cost Assumptions

• Escalation

Year IHS Global Insight Highway and Street Index

ENR Construction Cost Index VBTES Rate VBTES Cost

Index

2013 BASE Base Cost Plus

2014 1.4% 4.7% 4.70% 4.7%

2015 2.5% 3.4% 3.40% 8.3%

2016 2.9% 2.2% 2.90% 11.4%

2017 2.5% 2.4% 2.50% 14.2%

2018 2.2% 2.4% 2.40% 16.9%

Page 30

% %

2019 2% 2.7% 2.70% 20.1%

2020 2% 2.6% 2.60% 23.2%

Page 16: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

16

Capital Cost Assumptions

• Contingencies by major project element

Major Project Element ContingencyTrack 35%Stations 30%Modifications to Maintenance Facility 30%Site Work 35%Utilities 40%Rail Systems (Traction Power, Signals) 35%Real Estate (excluding NSRR ROW) 50%

Page 31

Vehicles 20%Unallocated 2% of total

• Real Estate Costs– Based on City assessed values for 2013

– Includes 

Capital Cost Assumptions

• Partial property takes

• Whole property takes

• Costs to relocate businesses, where required

• Legal fees and transfer costs

– Does not include• Costs of Kempsville Lumber, NSRR ROW (prorated), and Circuit p , (p ),City (all properties already owned by the City)

• Temporary construction easements

Page 32

Page 17: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

17

• Vehicles– Four Light Rail Vehicles required for service to Town Center

Capital Cost Assumptions

– Twelve additional transit buses are required to support LRT Service to support• Three additional bus routes

• Extended AM and PM hours

• Additional service days (weekends)

• Increased frequency of service

Page 33

Capital Cost Assumptions

• Soft Costs (% of construction)

Soft Costs % of Construction

Project Development (DEIS/Concept Design) 2.5%Engineering 12%Project Management 5%Construction Management 8%Insurance 2%Legal/Permit Fees 2%

Page 34

Survey/Testing/Inspection 2%System Startup 1.5%

Page 18: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

18

Capital Costs

Opinion of Probable Capital Cost Current Year*(2013)

YOE* (2018)

Construction Cost $ 161 $ 188Other Project Costsj

Existing Tide System Improvements $ 5 $ 6

Light Rail Vehicles (4) $ 21 $ 25

Bus Vehicles (12) $ 9 $ 11

“New” Real Estate Required** $ 19 $ 24

Project Development and Engineering $ 24 $ 27

Other Soft Costs (PM/CM/Legal/Startup) $ 34 $ 39

Unallocated Contingencies $ 6 $ 7

Total Probable Capital Cost $ 279 $ 327

Page 35

Reflects Constitution Station End of Line Option – 3.1 Miles* In Millions of Dollars** Does not include real estate purchased to date of $28M

OCC Modifications

Page 36

Page 19: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

19

Capital Cost Comparison

Project Length Capital Cost Cost per MileVBTES LRT to Constitution Drive 3.1 $279 million* $90 million*

VBTES compared to significant LRT projects under construction in FY13

Virginia Beach, VA$ $

Central Corridor LRTMinneapolis, MN

9.8 $956 million $97 million

North Corridor LRTHouston, TX

5.28 $756 million $143 million

Southeast Corridor LRTHouston, TX

6.56 $822 million $125 million

Dulles Metrorail Extension Northern Virginia**

11.7 $3.1 billion $269 million

Page 37

* FY 13 Dollars** Heavy Rail Project in VA

Local Share of O&M Costs*

Comparison of Bus and LRT Service CostsO&M Costs

in 2012 Service Levels and Dollars

Virginia Beach Projected Bus and LRT Service $ 11.0 MVirginia Beach Bus Service Costs in 2012** $ 3.0 M

Expanded Bus Service for LRT $ 6.0 M

Light Rail Service in Virginia Beach to Town Center $ 2.0 M

Norfolk Bus and LRT Service $ 14.2 MNorfolk Bus Service Costs in 2012 $ 8.5 M

Light Rail Service in Norfolk in 2012 $ 5.7 M

Page 38

* Not Including Paratransit Costs** FY14 Virginia Beach local share for bus service costs is $4.4 M

Page 20: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

20

Ridership Forecast

Ridership Forecasting for Light Rail to Town Center

• Results of FTA approved ridership model• Home-Based Work Model produces conservative ridership numbers

Tide Forecast(FY 2011)

Actual Tide(FY 2014)

Projected Norfolk (2034)

Projected Virginia Beach

(2034)

Total ProjectedTide LRT(2034)

AverageWeekday

2,900 5,300 7,050 2, 250 9,300

• Does not include Tourism or Special Events

Page 39

Annual Trips

870,000 1.4 million 2.8 million

Tide Ridership

Tide Average Monthly Ridership Since Opening

140,000

160,000

40,000

60,000

80,000

100,000

120,000

Page 40

-

20,000

FY12 FY13 FY14 FY15

Page 21: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

21

VIRGINIA BEACH TRANSIT EXTENSION STUDY

STUDY SCHEDULE

Page 41

September Public Meetings ‐ Town Center Alternative

• September 22, 2014Renaissance AcademyWit hd k R dWitchduck Road6:00 to 7:30 PM

• September 24, 2014Westin HotelTown Center

Page 42

o Ce te6:00 to 7:30 PM

Page 22: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

22

Public Comment

• Comments are welcome at any time during the VBTES process.

• You are encouraged to participate throughout the entire study g p p g yprocess.

• Formal Comments on the DEIS will be accepted after the release of the document (the beginning of 2015) during the Formal Public Comment Period at the Formal DEIS Public Hearings.

HRT ill dd ll “ b t ti ” itt t• HRT will address all “substantive” written comments.

Page 43

VBTES DEIS Remaining Milestones

• Early Submittal of DEIS Chapters to FTA (September 2014)

• Full Submittal of DEIS to FTA (October 2014)Full Submittal of DEIS to FTA (October 2014)

• Formal DEIS Public Comment Period and Formal DEIS Public Hearings (Early 2015)

• Locally Preferred Alternative Selected by City Council (Early 2015)

Page 44

Page 23: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

23

2014 2015 2016J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

DEIS  Completion

Update DEIS ‐ New Alternative

FTA Review/Approval of DEIS

Town Center Schedule under State – City Funding

pp

DEIS Circulation and Public Hearings

Locally Preferred Alternative (LPA)

LPA to HRTPO Fiscally Constrained LRTPHRT Request to Enter  FTA "Project Development"

Preparation of Final EIS/ROD 

HRT Request to Enter FTAHRT  Request to Enter FTA “Engineering"

Design Build

FFGA/ Final Engineering /Construction

Operations

Page 45

Thank You

Page 46

Page 24: Virginia Beach Transit Extension Study - WAVY-TV · PDF file · 2014-09-092014-09-09 · The Virginia Beach Transit Extension Study ... •Real Estate • Vehicle Costs •Soft Costs

9/9/2014

24

Public Comment

Visit the VBTES Website or leave a message on the VBTES project hotline

• Website:  www.gohrt.com/about/development/vbtes

• Study Hotline: 757‐222‐6098• Study Hotline: 757 222 6098

Share your comments directly with HRT and the City of Virginia Beach

HAMPTON ROADS TRANSITJulie Timm

Transit Development OfficerDepartment of Planning and Development

CITY OF VIRGINIA BEACHBrian Solis

Transportation and Transit ManagerStrategic Growth Area Office

47

509 East 18th StreetNorfolk, VA 23504

757‐222‐6000 ext. [email protected]

4525 Main Street, Suite 710Virginia Beach, VA 23462

757‐385‐[email protected]