    Project Network Manager Baseline Prep. NM/KD / Mikael Thorgren 2006-01-12 Appr. NM/KD / Erik Hedenblad 2006-01-12 Doc. kind Users Guide Doc. des. Ref. des. WAH334 Title S P L

    Resp. dept NM/KD Status Approved Doc. no. Lang. Rev. ind. Page 1

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39 FILE: Wah334.doc; SAVEDATE: 2006-01-12 12:47; TEMPLATE: Techn_Doc_Deliv_P_FunctionDescription.dot B; SKELETON:

    Network Manager

    S P L

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 2

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Abstract This is a common User's Guide for all functions based on the SPL tool.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 3

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Table of Contents

    1 Overview................................................................................................................... 5 1.1 Introduction .................................................................................................. 5

    1.1.1 Terminology.................................................................................... 5 1.2 Creation and Activation of SPL Sequence.................................................... 6 1.3 SPL Operation.............................................................................................. 7

    1.3.1 Sequences started manually from Operator Dialog......................... 7 1.3.2 Sequence Started on Event ............................................................ 7 1.3.3 Sequence Start on Timer................................................................ 7 1.3.4 Sequence start on Manual Data Entry (MDE) ................................. 7 1.3.5 Interlock Start ................................................................................. 8 1.3.6 Sequences started from a poke point ............................................. 8 1.3.7 Status/Numeric Calculations........................................................... 8 1.3.8 Job Management............................................................................ 8

    1.4 Parameters to SPL programs ....................................................................... 9 2 Installation Guide................................................................................................... 10

    2.1 Procedures and Files ................................................................................. 10 2.2 Example, init_ws400 .................................................................................. 11 2.3 Example, Install_Spl................................................................................... 13 2.4 Security ...................................................................................................... 14

    3 Sequence Control Operation................................................................................. 15 3.1 The Pictures Used for Sequence Control ................................................... 15 3.2 Activating Sequences................................................................................. 16

    3.2.1 Sequence Status .......................................................................... 16 3.2.2 Manual Operation of Sequence .................................................... 16 3.2.3 Manual Start from Sequence Information Picture.......................... 17 3.2.4 Operator Settings ......................................................................... 18

    3.3 Alternative Function Start Methods............................................................. 18 3.4 The Parameters in the Pictures .................................................................. 20

    4 SPL Code Creation ................................................................................................ 21 4.1 Overview .................................................................................................... 21

    4.1.1 Some Hints................................................................................... 21 4.1.2 SPL Sequences and SPL programs ............................................. 21

    4.2 Creating the SPL Code in an Editor............................................................ 21 4.3 Creating the SPL Code in the Interactive Tool............................................ 21

    4.3.1 The Interactive SPL Generation Picture........................................ 21 4.3.2 Start the Interactive SPL Generation Function .............................. 21 4.3.3 Create the Element List ................................................................ 22 4.3.4 Create the SPL Code.................................................................... 22 4.3.5 Some hints and warnings ............................................................. 23

    5 Creation of Point Groups ...................................................................................... 24 5.1 Generate Point Groups in the Data Engineering Tool................................. 24 5.2 Create Point Groups Interactively............................................................... 24

    6 Connect and Delete Sequences............................................................................ 25 6.1 Overview .................................................................................................... 25 6.2 Connect and Delete Picture........................................................................ 25 6.3 Start/Exit Editor .......................................................................................... 25 6.4 Sequence Creation..................................................................................... 26

    6.4.1 Selection of Data to a Sequence................................................... 26 6.4.2 Fill in the Starts............................................................................. 27 6.4.3 Connect (Create) a Sequence ...................................................... 31

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 4

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    6.4.4 Disconnect (Delete) a Sequence .................................................. 31 6.4.5 Show Sequence ........................................................................... 31 6.4.6 Reset data .................................................................................... 31

    6.5 Delete program .......................................................................................... 32 6.6 Rule Creation ............................................................................................. 32 6.7 Warning and Hints...................................................................................... 33

    6.7.1 Object list and Element list............................................................ 33 6.7.2 Names containing special characters ........................................... 33

    7 SPL Monitor............................................................................................................ 34

    8 SPL Debug.............................................................................................................. 36

    9 Hints and Fault Situations..................................................................................... 38

    10 Conventions ........................................................................................................... 39

    11 List of References.................................................................................................. 39

    Table of Figures Figure 1: Creation and activation of the SPL-sequences ................................................... 6 Figure 2: Sequence Control picture structure .................................................................. 15

    Associated Documents WAH328, Implementation manual for SPL. WAB034, Design description for SPL. WAH223, Implementation manual for Interactive SPL Generation. WAB086, Design description for Interactive SPL Generation. WAH331, Implementation manual for Sequence Control. WAB087, Design description for Sequence Control. WAH330, Implementation manual for Table calculations. WAB089, Design description for Table calculations.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 5

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    1 Overview

    1.1 Introduction SPL (Programming Language) is a tool to create new functions in the Network Manager system. Several functions in Network Manager are using SPL as a basic tool, such as Sequence Control, Interlock, status/numeric Calculations and Job management.

    1.1.1 Terminology Function Explanation SPL Programming Language. Object list The SPL declaration of the input/output object(s). It can be

    an object(s) from , , or any other database file. This list is declared in the SPL program.

    Element list A Specification of the objects to be included in an execution of an SPL Program. This list is saved in the database and has to correspond to the object list. Several Element lists can be connected to the same SPL program and several SPL Programs may use the same Element list.

    Point group The element list. Poke point A pushbutton in a picture that will start a specific SPL

    sequence by simply selecting the button and clicking on it. Sequence One SPL program that is connected to one element list. Sequence Status Current status of a sequence. Every sequence can have

    several types of statuses such as executing, waiting, suspended etc.

    Interlock rules A sequence that is connected to the Interlock function. MDE start Sequence start after manual data entry.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 6

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    1.2 Creation and Activation of SPL Sequence

    Network Manager

    SPL Program Code

    Activation type

    Poke point

    Interlock

    Sequence Control

    Calculation

    Job Management

    Return data to function SPL

    Monitor

    SPL Output for updating the database or send a start to other programs in

    Data Base

    SPL Compiler

    Input Data

    Figure 1: Creation and activation of the SPL-sequences

    SPL Program Code The SPL Program Code can be created by source code editing from a maintenance console or by the Interactive SPL Generation from an operator's workstation. Note that in the case of using text editor, the program file name should contain: Only lowercase letters. Max. 20 characters. See also hints and warnings (4.3.5). SPL Compiler All created SPL Programs have to be compiled in the SPL-compiler. When it has been compiled the SPL Program can be used in a Sequence. The compiled program code is saved in the Avanti database.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 7

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Input Data To get the most flexible sequence the SPL program code contains a list of input data references (Object List). This list tells if the object is a MEASURAND, INDICATION, ACCUMULATOR etc. The input data from the element list is connected to the Object list of the SPL program. The connection is specified in the Point Group of the particular Sequence. The same SPL program can be used on several Element Lists. The same Element list can also be used on different SPL programs. The Point Group is created in the Data Engineering tool or interactively on-line and are then stored in the Avanti database. The Sequence is created by connecting a Point Group to a Program, this is done in the SPL Connect and Delete function. SPL Output The output can be at any object(s) in the database or to any other function in Network Manager

    1.3 SPL Operation The SPL are used by the functions Sequence Control, Interlock, Status/Numerical calculations and Job Management.

    1.3.1 Sequences started manually from Operator Dialog A sequence can be connected to an object. To start a sequence that is connected to an object: Select the object. Select Sequence Control under the MB3 menu. If sequences are

    connected to the object a dialog box with the sequences present in a list will be shown. If no sequences are present, the operator will get a warning.

    Select the sequences that shall be started and select "START". The sequence will now be executed.

    Depending on the status different possibilities will be possible on the sequence. The functions that are not possible to use at the moment will not be possible to select.

    1.3.2 Sequence Started on Event A sequence can be connected to start on a status change on an Indication (Breaker or Isolator) or a status change of a measured value. The status change will be done before the sequence is started.

    1.3.3 Sequence Start on Timer The sequence can be started on an exact timer or cyclical.

    1.3.4 Sequence start on Manual Data Entry (MDE) A sequence can be connected to start after an operator's manual data entry on an object(s) which is globally known in the system.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 8

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    1.3.5 Interlock Start Note: There are some interlocks which are implemented as default interlock checks (Reference 3) and not affected from SPL based interlocks which are mentioned in this document. The Interlock function contains rules for the objects in the system. Command, data entry, and tagging on an object(s) are only possible if the rule corresponding to that object(s) in question is fulfilled. Otherwise the Interlock function returns NOT_OK to its caller and prohibits the requested changes. The operator gets a message about what is wrong. All rules are written as SPL programs. An Interlock rule is simply an SPL program with a number of predefined in/out parameters (see 1.4). The Interlock program is terminated by an Interlock termination; the built-in function INTRET should be called and the execution control will consequently return to the caller. Rules may consist of conditional checks on any object value that is stated in the Avanti database, i.e. values within set of ranges, indication status or data flags in defined positions etc. Note that the interlock sequences are not directly executed by the operator. They are created and connected to object(s) in point group(s) (see 6.3.2, Interlock operation). Later on, when a manual change (command or manual data entry) is applied to this object(s), the Interlock function is automatically activated. It can be possible to "Bypass" the Interlock function. A bypass parameter is passed to the Interlock function to serve for this purpose (see 1.4).

    1.3.6 Sequences started from a poke point A sequence can be connected to an object and a poke point. To start a sequence that is connected to an object and a poke point: Select the picture with the poke point. Position the cursor at the poke point. Click at the poke point. The sequence that is connected to the element in that specific poke point will be started automatically.

    1.3.7 Status/Numeric Calculations A Status/Numeric calculation can be treated as a sequence that returns a value in a resulting object.

    1.3.8 Job Management Job management uses the SPL language as a tool but has its own user interface.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 9

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    1.4 Parameters to SPL programs There are four input parameters to the SPL Code. These parameters have different use for different functions. The parameters should always be Integers. They can be of other types but the result can not be guaranteed. No parameters have to be included in the SPL program. Manual start For manual start the parameters can be set by the operator. The parameters can be updated in the Sequence start dialogue or the SPL Sequence information picture. Event start The first parameter will indicate the position in the object list, of the object that has been changed and started the sequence. Interlock start Note: There are some interlocks which are implemented as default interlock checks (Ref. 3) and not affected from SPL based interlocks which are mentioned in this document. The first parameter to an Interlock rule is the index of the object that caused the interlock start in the object list. Every executing Interlock sequence is associated with a job number. This job number is sent to the Interlock function as the second parameter. It is returned to the caller by having it as the first parameter in INTRET at the end of the program. The third parameter to an Interlock rule is the bypass parameter. Zero indicates no bypassing and one indicates the opposite. It is then up to the rule to allow bypassing the condition checks or not. The fourth parameter is the tag level of the object which caused the Interlock start.

    Timer start The parameters will get the sequence parameters from the SPL Sequence information picture. Poke point start The parameters can be updated in the Sequence start dialogue or the SPL Sequence information picture. No dialog for the operator to change the dialogs will occur at poke point startup of a sequence. MDE start The first parameter is the index of the element that caused the sequence start (the element that has been target to manual data entry) in the program's element list. The second parameter is the element's file reference. The second parameter is the element's record reference. The second parameter is the element's item number (the item that has been target to operator's manual data entry).

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 10

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    2 Installation Guide

    2.1 Procedures and Files Procedures The SPL runtime system is installed by the init_ws400 script or by the install_spl script on directory mmx. If init_ws400 is used, the executables and the resource-files will be installed automatically when the WS 400 runtime system is installed. This script uses ftp to transfer the files to the target node. The install_spl script uses cp, (UNIX copy), to transfer the files, and therefore requires that the source files are reachable through an nfs-mounted file system. Install_spl can be used to install all or parts of the SPL runtime system. The default directory in which the SPL runtime system is loaded is xxx/mmi/spl/load, where xxx is the path to the home-directory of user spider. During the installation there are a number of questions to be answered, see 2.2 and 2.3. Files In the host nodes, in directory spimgr there is a file, servers.rmt, which holds information about server names, nodes and socket port numbers. When a new Network Manager-system is added, (ADD chosen from the spider menu), this file will be copied from spicommon and updated with actual node names concerning the current system configuration, but can also be edited manually. The port numbers can be replaced by any other unused port number. The server name consists of 'program name'_'node name'_'database identity'. Node name is the name of the node where this particular server is running. By default, there are three symbols used in servers.rmt, HOSTA, HOSTB and HOSTC, to indicate the identity of the host node. These symbols that are replaced by actual node-names during add of a spider-system described above. In all nodes where the SPL runtime system is installed, two system files have to be edited, /etc/inetd.conf and /etc/services. The following information has to be added to /etc/inetd.conf as one single text line: wabk67 stream tcp nowait spider /usr/users/spider/spi0/spiexe/wabk67 /usr/users/spider/spi0/spiexe/wabk67 The following information has to be added to /etc/services as one single text line: wabk67 2226/tcp # SPL Client start 2226 is the default port number used by wabk67 and can only be replaced by another port number if both file servers.rmt, (in the host nodes), and /etc/services are updated with the same number. If either /etc/inetd.conf or /etc/services is edited, the system has to be rebooted. Example: If SPL runtime is installed in node snem20 and there is two host nodes snem30 and snem31, and the default port for wabk67, 2226, is to be changed to 3456, the following actions has to be done: 1. Login as spider 2. Replace 2226 by 3456 in file servers.rmt, in directory spimgr, in both host

    nodes snem30 and snem31, for server with name wabk67_snem20. 3. Login as root 4. Replace 2226 by 3456 in file /etc/services in node snem20. Reboot node

    snem20, (shutdown -r now).

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 11

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    2.2 Example, init_ws400 Answers that have to be typed are underlined. CR means that just the return key is pressed. init_ws400 Which parts of the WS400 software should be loaded / configured? KIT WS400 Kit-File of your choice RUN WS400 Runtime System: Sources, EXEs and Data DEV WS400 Runtime System + Editor: Sources, EXEs and Data SUB WS400 Subsystem, Part of your choice REL WS400 Release, only Sources and Data CON WS400 System Files, Configuration Parameters Please enter your choice or enter q to quit: KIT 1 WS400 Runtime Kit-File 2 WS400 Picture Editor Kit-File 3 WS400 Runtime and Picture Editor Kit-File Which Kit-File? 1

    Give the path to the files to store: Return if path = /usr/users/spider/mmi/ws400 CR Please enter host login node: snev02 Please enter login user: .

    . (Installation of WS500 runtime system) .

    Please enter node to get SPL runtime (UNIX node): snem32 Give directory where to put SPL: Return if path = /usr/users/spider/mmi CR Please enter login user: 'username' The password is to be given later when prompted for. Enter project root: 'project_root'/spiroot' Enter remote user project root: /rel/7b0/spiroot Checking directory spl ... CREATED Checking directory spl/load ... CREATED Connected to snem32. 220 snem32 FTP server ready. Name (snem32:'username'): 331 Password required for spladm.

    Password: 'password' 230 User spladm logged in. Remote system type is UNIX. Using binary mode

    to transfer files. 250 CWD command successful. 200 Type set to A. 200 PORT command successful. 550 k54: No such file or directory. 200 PORT command successful. 150 Opening ASCII mode data connection for k68 (138.221.106.212,3072)

    (268 bytes). 226 Transfer complete. 265 bytes received in 0.051 seconds (5.1 Kbytes/s) 200 PORT command successful. 150 Opening ASCII mode data connection for spldebug

    (138.221.106.212,3073) (92 bytes).

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 12

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    226 Transfer complete. 91 bytes received in 0.042 seconds (2.1 Kbytes/s)

    250 CWD command successful. 200 Type set to I. 200 PORT command successful. 150 Opening BINARY mode data connection for wabk54

    (138.221.106.212,3074) (10676792 bytes). 226 Transfer complete. 10676792 bytes received in 10 seconds (1e+03

    Kbytes/s) 200 PORT command successful. 150 Opening BINARY mode data connection for wabk65

    (138.221.106.212,3075) (4089587 bytes). 226 Transfer complete. 4089587 bytes received in 3.5 seconds (1.1e+03

    Kbytes/s) 200 PORT command successful. 150 Opening BINARY mode data connection for wabk67

    (138.221.106.212,3076) (45664 bytes). 226 Transfer complete. 45664 bytes received in 0.096 seconds (4.7e+02

    Kbytes/s) 200 PORT command successful. 150 Opening BINARY mode data connection for wabk68

    (138.221.106.212,3077) (4720728 bytes). 226 Transfer complete. 4720728 bytes received in 4.1 seconds (1.1e+03

    Kbytes/s) 221 Goodbye. >>>>>> After the installation of SPL is completed: >>>>>> >>>>>> Login as root >>>>>> Add the following line to /etc/inetd.conf: wabk67 stream tcp nowait spider /usr/users/spider/mmi/spl/load/wabk67 /usr/users/spider/mmi/spl/load/wabk67 >>>>>> Add the following line to /etc/services: wabk67 2226/tcp # SPL Client start >>>>>> Reboot the system >>>>>> Login as spider and add the following line to file >>>>>> servers.rmt in directory spimgr on all spider hosts: wabk67_snem32 snem32 2226 SPL installation... Done Press return to continue... And - Done ...

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 13

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    2.3 Example, Install_Spl Answer that has to be typed is underlined. CR means that just the return key is pressed. install_spl Which parts of the SPL software should be loaded? 1. SPL Debugger 2. Job Management 3. Sequence start Please enter your choice or enter q to quit: 1 2 3 Give directory where to put SPL: Return if path = /usr/users/spider/mmi CR Are the files to be fetched from the release? (y/n): n Enter project root (e.g. /proj/'proj name'/'projadm'/spiroot): /proj/spl/spladm/spiroot Checking directories... Checking directory spl ... CREATED Checking directory spl/load ... CREATED copying Client start wabk67 end Client start copying SPL Debugger wabk65 SPLDEBUG end SPL Debugger copying Job Management wabk54 K54 Management copying Sequence start wabk68 K68 end Sequence start >>>>>> After the installation of SPL is completed: >>>>>> >>>>>> Login as root >>>>>> Add the following line to /etc/inetd.conf: wabk67 stream tcp nowait spider /usr/users/spider/mmi/spl/load/wabk67 /usr/users/spider/mmi/spl/load/wabk67 >>>>>> Add the following line to /etc/services: wabk67 2226/tcp # SPL Client start >>>>>> Reboot the system SPL installation... Done Press return to continue...

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 14

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    2.4 Security The security has to be set up to allow the SPL client processes to open new windows on the screen. Current node name has to be added to the list of authorized hosts. 1. Choose Security... from Session Manager's Options menu. 2. Type current node name. 3. Click on the Add button. The node name is added to the list of authorized

    host list. 4. Click on OK. 5. Choose Save Current Settings from Session Manager's Options menu to

    save the new settings.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 15

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    3 Sequence Control Operation

    3.1 The Pictures Used for Sequence Control Below you can see the pictures that are used for the Sequence Control function. The Status/Numeric calculation and the Interlock functions are not accessible for the operator.

    INFO

    Sequence startdialog

    SequenceInformation

    Point GroupInformation

    ElementInformation

    Figure 2: Sequence Control picture structure Sequence Information The Sequence Information picture is the main picture. It contains the information about the sequence and the operator input parameters. From this picture is it possible to start the same actions as in the Sequence dialog. It is also possible to start the sequence with debug and go to the Interactive part of the sequences. Point Group Information picture The Point Group Information picture holds the element list. Element Information The Element Information picture shows, what file and record the element is connected to.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 16

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    3.2 Activating Sequences

    3.2.1 Sequence Status The sequence can have one status out of the following Status Explanation Free The sequence is not used at the moment. Active The sequence is sent and included in the "SPL monitor" but not

    executing in the monitor. Executing The sequence is now executing in the "SPL monitor". Pause The sequence is paused by the SPL Program. It will be started

    after a Time out or if the operator resumes the sequence. Waiting The sequence is waiting for a return value from the Network

    Manager Process. Stepwise The sequence is in stepwise mode Suspended The operator has set the sequence in suspension mode. Canceled The operator has canceled the sequence. Interrupted The Sequence has been interrupted by the process. This happens

    when the Sequence gets some not accepted data, for example one command is not possible to perform. The SPL-code writer can also enter aborts in the program. The abort reason will be stated in the operator message line in the Sequence Information picture and the SPL program line where it is aborted will be shown in the line counter.

    Crashed If the sequence is wrong in some way, for example the element list does not match the Object list, the sequence will crash. The reason will be stated on the operator message line in the sequence information picture, the code line where it is crashed will be shown in the operator information line.

    Debug The sequence is executing with debug.

    3.2.2 Manual Operation of Sequence Get the sequence dialog A sequence is controlled from the sequence dialog. The dialog holds all sequences that are connected to one object. To start the dialog select an object, then select Sequence control with MB3. Starting a sequence A sequence is started in the sequence dialog by selecting the "Start" button. Status for this sequence will now be changed to activated or executing. When the sequence is completed the status will be Free. The sequence can only be started if the status is Free, Canceled, Interrupted or Crashed. When a sequence is started and completed (or canceled) an event is included in the event list. This will show the sequence that is started, which Point Group, which SPL Program Code and the operator identity. This event can be omitted by setting the event handling flag off in the Sequence Information picture. When a sequence crash an event will always be generated.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 17

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Suspend a sequence The sequence can only be suspended when the sequence has some kind of break, for example is waiting for back indication, is paused, is delayed etc. If the sequence status is active, executing, waiting or pause, the poke-point suspend can be selected. The suspend function sets the sequence in a suspension mode. The sequence will be waiting until the Start or Cancel is selected. The sequence will now continue from the position that it was suspended. After a suspend, the status will be Suspend. Resume a sequence If the sequence is in a pause or in suspension mode the Start button activates (resumes) the sequence again. Resume will continue at the next statement in the sequence. The status after a resume will be active or executing. Cancel a sequence If the Sequence status is active, executing, stepwise, waiting, suspend or pause the button Cancel can be selected. The cancel function will cancel the Sequence in the next break, as pause, waiting, delay etc. The status after cancel will be canceled. This action will result in an event in the event list. This will show which sequence that was canceled and which point group it was executing on. Information select If the information is selected the sequence information picture will appear on the output window.

    3.2.3 Manual Start from Sequence Information Picture All sequences can be started from the sequence Information picture, also sequences that is not connected to a sequence start object. Start sequence Start sequence can be done by selecting DF key Start sequence. Cancel sequence Cancel sequence is done by selecting DF key cancel sequence. Suspend sequence Suspend sequence is done by selecting DF key suspend sequence. Stepwise execution With the stepwise execution it is possible to run the sequence statement by statement.

    To set the Sequence in stepwise mode the "stepwise parameter" is set to YES. For every start/resume the sequence will execute one statement (one SPL code line). Current code line in the SPL source code will be stated in the "Line counter" parameter. The stepwise mode can be set before the operator starts the sequence or during a break before the operator resumes the Sequence. The stepwise mode can be reset at any time. The sequence will take the pause status.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 18

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    The stepwise activation results in an event when the sequence is activated at the first time and when it is completed. No event is generated if the event log flag is set to NO. Do never leave the stepwise flag to YES when the work with the sequence is completed. Debug start The sequence is started with debug when selecting the DF key Debug.

    3.2.4 Operator Settings There are some input parameters that the operator can set before starting a Sequence. Parameter 1-4 These parameters are the operator input to the sequence. The SPL program has to be coded to take care of the parameters as input. An explanation to these parameters is found in the Sequence Information Picture. Stepwise If the stepwise flag is set to YES the sequence will be executed step by step with one statement for each start/resume. This flag can only be set in the Sequence information picture. Sequence Event log If the Sequence Event logged flag is YES all start and compilations of Sequences are stated in the event list. This is normally used for Sequences that are started by the operator. This flag can be changed in the sequence information picture.

    3.3 Alternative Function Start Methods Apart from the operator activation above (start and resume) the sequence can be started in the following alternative ways. Event start For an indication status change or a measurand limit violation, it is possible to start one or several Sequences. Event start is often used in status calculations. Interlock start Note: There are some interlocks which are implemented as default interlock checks (Ref. 3) and not affected from SPL based interlocks which are mentioned in this document. If Interlock rules are stated for one object, the Interlock Sequence connected to that object will be started upon manual changes. Every type of manual change, such as command or data entry, on one Interlock object result in one start of a rule (specified as a sequence) that gives the result if the input is OK or not. This means that the execution of an interlock sequence is not handled by the operator, but automatically controlled and ordered by a process that is associated with manual changes on objects. Certain conditions are checked by the sequence and the caller process is notified with the result.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 19

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    The following activator types (types of manual changes) are available in SPL Connect and Delete picture page 2: Command ON Command OFF Manual data entry ON Manual data entry OFF Issue tag Set tag Command and Manual data entry ON Command and Manual data entry OFF Timer start It is possible to define a timer to start a sequence. Then the sequence will be activated cyclical. This is a normal start of numeric calculation. Poke point start If a sequence is connected to a poke point, it can be started by pressing the poke point. The poke point is connected to an element that has to do a poke point start. MDE start If a sequence is connected with this type of start, it will be activated when the objects in its object list that are sat with this option will become target to an operator's manual data entry. The MDE start option can be defined for the single object as well as the whole file containing that object. In that case, any object of that type can initiate the sequence start after operator's manual data entry. Sequences start from SPL or from a Network Manager function Other Network Manager functions can be started from Sequences. It is also possible to start a Sequence from another Sequence. This can be done in two ways. In both cases it is done in the SPL-code, out of the control from the operator. By sending a Sequence starts which will be queued and started after the

    executed Sequence. By an "Execute" function internally in the SPL code. The new Sequence

    runs as a subroutine to the calling Sequence. In both cases will the calling program have the possibility to get a return parameter from the SPL program.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 20

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    3.4 The Parameters in the Pictures Parameters included in the SPL pictures. Parameter In picture Comment Priority Sequence Info With this parameter it is possible to

    determine the order the sequences will be activated from the "SPL monitor". A sequence with a higher priority will be executed before one with lower priority.

    Event log Sequence Info If this flag is set, an event will be included in the event list every time a Sequence is started and completed.

    Elements Point Group Info The element list in this Point Group. Program identity Sequence Info The SPL program Status Sequence Info The current status of the sequence

    right now. Stepwise Sequence Info If the sequence shall be executed in

    stepwise mode. Line counter Sequence Info Current line in the SPL-code that is

    executed. This is only shown if it is executed in stepwise mode or if the sequence crash or been Interrupted.

    Parameter 1-4 Sequence Info Operator input parameters.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 21

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    4 SPL Code Creation

    4.1 Overview The SPL code for new sequences can be created either in an ordinary editor or in the Interactive SPL creation function. It is recommended to use an ordinary editor.

    4.1.1 Some Hints When a new sequence is created, the designer should very carefully describe what the sequence shall be used for. A lot of work can be saved later if for example all element lists are specified in the beginning and some type definitions are created.

    4.1.2 SPL Sequences and SPL programs If a program, that is included in a sequence, is re-compiled will the sequence still be intact. The sequence will point out the new compiled version of the program. The old compiled version of the program is removed.

    4.2 Creating the SPL Code in an Editor For programming see the manual SPL Reference Manual Reference 1. The program file name should contain lower-case letters and be extended

    with "sc".

    The program should be saved in/copied to "spidb3" and then compiled by: ../spiupd/trans filename or ../spiexe/wabk60 filename

    4.3 Creating the SPL Code in the Interactive Tool

    4.3.1 The Interactive SPL Generation Picture Select the ISG (Interactive SPL generation) editor DF key from the Sequence Info picture, the SPL Monitor picture or the SPL Connect and Delete picture. The ISG Editor will now appear. In the ISC Editor is it possible to interactively create code. Only one user at a time can use the editor.

    4.3.2 Start the Interactive SPL Generation Function To start the ISG Editor; select the DF-key "Start". The used flag will now be set to YES. The ISG editor can not be started if somebody else is using the function for the moment. Neither can the function be started in the on-line computer if a hot stand-by computer is present. When the function is selected it is only possible to use the function on the VDU where the function was started.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 22

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    4.3.3 Create the Element List Create Element List The elements in the Element List are selected by selection of an object in a Single line diagram or Information picture see creation of Point Groups chapter 5.

    4.3.4 Create the SPL Code Every SPL program code-line in the sequence is created with one function (i.e. Set_Pause, Regulate_Breaker, Abort_Sequence etc.) and one or several parameters. Functions are selected from the function list. Information about functions

    parameters can be accessed by selection of any function by MB1 and selection of INFO under MB3. To scroll the info pages, use Page forward/backward.

    Objects are selected from the element list or directly from other pictures. If it is selected from other pictures it will be added to the object list.

    A number of fixed parameters are found below the function list. Only fixed parameters that are possible to select are shown in the fixed parameter list.

    Operator parameters can be set by the operator. The Operator parameters can be numerical values or text of max. 20 characters. The parameter should be inserted into the parameter's field before the corresponding function is selected.

    The next parameter type that should be selected is written on the info line. The list will not be updated if a wrong parameter is selected. This type of programs can have up to 100 lines. Warning: The VDU is still in action. An ordinary Command from the keyboard will give a Command!! New line To add a new line, set the cursor at the position where the new line shall be included and select a function, then add the parameters in a normal way. The Editor operates in Insert mode only. Copy This function will copy one or several code lines and save it in an internal memory. Select the Copy mode. Then select the lines that shall be copied. The lines will be copied when the Copy is selected again. Cut This function will cut out one or several code lines and store it in an internal memory. Select the Cut mode. Then select the code lines that shall be cut out. The lines will be cut when the Cut function is selected again. Paste This function will paste the code lines that are stored in the internal memory. Select the paste function. Then select position where the code will be pasted. Every time that a code line is selected the code in the memory will be pasted. The paste function is ended when the paste is selected again. Delete all code All code can be deleted if the DF-key "Delete code" is selected. The element list will still be present.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 23

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    4.3.5 Some hints and warnings The saved and/or compiled SPL program will directly be available in the hot-standby computer. Even if there was saved in the Study database. Warning: It is possible to work on the same code at the same time in the RDB and SDB. The latest update will be the one that remains. If save is done at the same time to the same saving the saved code will be destroyed. No capital letters are allowed in file names of the source code, when using an ordinary editor, to be able to use the SPL debugger. This is not valid for name of include files, which can consist of both small and capital letters. When using ISG editor, the source file name will be saved on ../spidb3 with lower-case letters. But from operator's point of view, the ISG editor is not case sensitive.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 24

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    5 Creation of Point Groups New Point Groups and element lists are created in the data Engineering tool or interactively on-line.

    5.1 Generate Point Groups in the Data Engineering Tool How to fill in the data engineering tool will be described in Reference 2. Point Groups created in the Data Engineering tool can not be changed interactively.

    5.2 Create Point Groups Interactively Creation of a Point group can be created interactively. The picture Go to the Create Point Group Picture. This picture is reachable from the Connect and deletes picture and the Interactive SPL generation picture. Start the interactive generation. Select ISG start. Select the objects The object is selected by selection on single line diagram or by selection of its external identity in its corresponding information picture. The selection has to be done on the same VDU by mouse click. Only objects that have an external identity can be selected. When an object is selected it will be shown in the list. To change an object or select another position, select the object or position in the list. Delete a selected object Objects are deleted by selecting the function "Delete selected object". Only objects that not are used in the ISG Editor code can be deleted. Save the Point Group To save/create a new Point Group, the new Point Group name has to be entered on the Point group name line. The Point Group classification has also to be entered. Note: the point group- and point group classification name will automatically be compressed and capitalized before saving. Select the Save Point group DF-key. A new Point Group is now created. If an old Point Group is entered and it is changeable, the old Point Group will be overwritten. It is not possible to store the result in a Point Group that is not changeable The new Point Group can now be used. Delete the Point Group Write the point group name in the point group name field and select the DF-key "Delete Point Group". The point group is deleted if: The given point group name is correct. The given point group is not used in a sequence. The system is running in RDB. The point group is changeable. End the editor session. The edit session shall be ended with Exit ISG DF key.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 25

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    6 Connect and Delete Sequences

    6.1 Overview With connect and delete function it is possible to: Create new sequences Delete sequences Show sequences Create rules Updates rules Show rules Delete rules

    Delete programs Redo connections Redo all rules This is the main function for creating sequences for all functions that use SPL. No other way is possible.

    6.2 Connect and Delete Picture The "Connect and delete" function consists of two pictures. In the main picture you can see what sequences that shall be created and picture two shows what type of starts that the sequences shall be connected to. The "Connect and Delete" picture is reached from the SPL Monitor picture, the Sequence information picture and the Interactive SPL Generation Editor picture. Observe that there is not any limit on the number of users in this picture, i.e. it can be the same data they are changing. However, the operator can inform others that he's currently modifying the pictures (see 6.3.)

    6.3 Start/Exit Editor To reduce the risk that several operators will be editing the Connect & Delete pictures at the same time, a Start/Exit Editor function is provided in these pictures as a DF-key. When an operator selects the Start Editor option, his Network Manager Username will appear in the operator-id field. This way the other operators will be notified and hopefully avoid doing any modifications until the first operator exit the Edit mode. Note, however, that the Edit mode does not prohibit any operator to modify the picture. If the Edit mode is already activated, the Exit Editor option can always be selected by any operator. The name Editor is only to give a sense of exclusive use privilege. No real editor or further advantage is involved.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 26

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    6.4 Sequence Creation Overview Every new sequence is a connection between one program and one Point Group. When a sequence is connected the program is one and only one but it is possible to connect that program to one or several point groups at one time, either to use wild-cards in the Point Group identity or to connect it to all Point groups in a Point Group class. To every Sequence a start can be connected. The starts that are possible in the connect tool are:

    Sequence start: Manual start from an object. Event start: The sequence will be started on a status change on an

    INDICATION or a MEASURAND. Timer start: The sequence will be started by timers. Interlock start: This is an Interlock rule sequence. Poke point start: The sequence will be started by a poke point. MDE start: The sequence will be started after a manual data entry. The sequence creation can be set so it will not refer to any of these start types. It is also possible to set any number of start types for a sequence. The Connect and delete function is not case sensitive except for Sequence Class names.

    6.4.1 Selection of Data to a Sequence Selection of a program The program is selected by writing in the program name in the Program field. Wild card * can be used to find the right program. To scroll to the next, use the push button at the right, to scroll to previous use the push button at the left. The name can be given in either upper- or lower-case letters. When the sequence is created the program line has to match exactly one program that is compiled. Selection of a Point Group The Point Group is selected by writing in the Point group name in the Point Group field. Wild card * can be used to find the right Point Group. To scroll to the next, use the push button at the right, to scroll to previous use the push button at the left. The name can be given in either upper- or lower-case letters. When the sequence is created the Point Group with wild cards shall match at least one real Point Group. If no match is found, this parameter will not be used. All point groups that match the Point Group Identity parameter will be connected to the program and create a sequence. Selection of a Point Group Class The Point Group Class is selected by writing in the Point Group Class in the Point Group Class field. Wild card * can be used to find the right Point Group Class. To scroll to the next, use the push button at the right, to scroll to previous use the push button at the left. The name can be given in either upper- or lower-case letters. This parameter will only be used if no match is found on the Point Group parameter. When the sequence is created the Point Group Class with wild cards shall match at least one real Point Group Class. If no match is found, this parameter will not be used. All Point Groups that the classification matches the "Point Group Class Identity" parameter will be connected to the program and create a sequence.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 27

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Selection of a Sequence Class The Sequence Class is selected by writing in the Sequence Class in the Sequence Class field. Wild card * can be used to find the right Sequence Class. To scroll to the next, use the push button at the right, to scroll to previous use the push button at the left. Note that this function is case sensitive. When the sequence is created and no sequence class matches it will use the first Sequence class. The first sequence class is the first one shown in the SPL Monitor picture. It is not possible to connect a job to several sequence classes. Sequence priority In the priority field the sequence priority is filled in. Priority is from 0 to 99 where 0 is the lowest and 99 the highest. Event log If the sequence shall have an event in the event list every time it is started and completed, select Yes. Parameter explanation If the program parameters shall be updated by the operator, an explanation shall be written in this field.

    6.4.2 Fill in the Starts Sequence start operation The sequence start is the manual start of the sequence. The ready sequence will be connected to one or several objects in the system. It is only possible to connect the sequence to objects that are present in the Point Group in the sequence. To set the sequence start: Select the Connect and delete picture page 2. Set the sequence start flag to yes. It is possible to get a type Point Group (one point group that match the

    point groups at page 1) by selection of the push bottom of the Show Point Group field. The objects and their positions will be shown in the list below.

    Set the flags for the object to yes if the object shall start a sequence. The object in this position that now is created will have a sequence start. If the flag is set to yes and no object exist in that position, the flag will be ignored.

    Only 400 sequences for sequence start can be connected for every object. Event start operation The Event start will start the sequence if a status change on one INDICATION or limit violation on a MEASURAND value. It is possible to connect other type of objects to the start but it will not be used, since no status change is specified for these starts. The ready sequence will be connected to one or several objects in the system. It is only possible to connect the sequence to objects that are present in the Point Group in the sequence. To set an Event start: Select the Connect and delete picture page 2. Set the Event start flag to yes. It is possible to get a type Point Group (one point group that match the

    point groups at page 1) by selection of the push button in the front of the Show Point Group field. The objects and their positions will be shown in the list below.

    Set the flags for the objects to yes if the objects shall start a sequence on event. The object in this position that now is created will have an event start. If the flag is set to yes and no object exist in that position, the flag will be ignored.

    Only 400 sequences for event start can be connected for every object.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 28

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Interlock start operation Note: There are some interlocks which are implemented as default interlock checks (Reference 3) and not affected from SPL based interlocks which are mentioned in this document. The Interlock will check if there is a rule to control that a command, data entry or tagging is possible or not, see Reference 3, to start the interlock rule if a change of a breaker is done manually or if a tag is set or reset. The ready sequence will be connected to one or several objects in the system. It is only possible to connect the sequence to objects that do not have this rule connected. Set the Interlock start flag to yes in SPL Connect and Delete picture page

    1.

    Select the Connect and Delete picture page 2. Set the Interlock start flag to yes. Set what interlock rule that this sequence is connected to. It is possible to get a type Point Group (one point group that match the

    point groups at page 1) by selection of the push button in the front of the Show Point Group field. The objects and their positions will be shown in the list below.

    Set the flags for the objects to yes if the object shall start a sequence on an interlock rule. The object in this position that now is created will have an interlock start. If the flag is set to yes and no object exist in that position, the flag will be ignored.

    For each object it is only possible to connect one of each type of Interlock rule. Poke point start operation The poke point start is the instant start of the sequence from a poke point. The ready sequence will be connected to one or several objects in the system. The sequence and object will also be connected to the poke point in the picture. It is only possible to connect the sequence to objects that are present in the Point Group in the sequence. To set the sequence start: Set the Poke point start flag to Yes in SPL Connect and Delete picture

    page 1 or 2. Select the Connect and delete picture page 2. Set the Poke point start flag to Yes. Set the Poke point number to a value, 0-99. 0 means no poke point

    connection. If there are more than one poke point start that should be connected to one element in any point group, this has to be a unique number for each poke point. The number will also be used when defining the poke point in the Picture editor. One element could only be connected to poke point number 1 in one sequence, number 2 in another and so on, i.e. each element could be connected to 99 different poke points.

    It is possible to get a type Point Group (one point group that match the point groups at page 1) by selection of the push bottom of the Show Point Group field. The objects and their positions will be shown in the list below.

    Set the Poke point flag for the object to Yes if the object shall have a poke point start. The object in this position that now is created will have a poke point start. If the flag is set to Yes and no object exists in that position, the flag will be ignored. Should be an object that is presented in the picture.

    Each element in a point group can be connected to 99 different poke points. Each element can be connected to poke point "1" for 4 different point groups.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 29

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    When the poke point should be defined in the Picture Editor, add a poke point (see PED manual) and as parameters add: Function table key 108 (start a function) Parameters 76,1 (where 76 is the number of the function startup

    and 1 is the poke point number, see above) Connected element Should be connected to the object that has a poke

    point start. Timer start operation The Timer start of sequences will start the sequence on a defined timer. The timer start can be set with wild cards (i.e. when the flag is set to 'No'). Then the timer will start every time the real time matches the sequence time. On this timer an offset can be put that will start the sequence on the normal timer plus a start(s) on the offset time(s). The timer is recalculated each expiration time and taking into account any specified offset time. It is also possible to include how many times the offset time shall be used. Select the Connect and delete picture page 2. Set the Timer activation on. Set the time flags to yes on the times that shall be valid. Then set the times,

    if the computer denies doing it the other way around. Set the offset times on the real start time if any, then turn the offset time on. Set the number of offset times if needed then turn the number of offset

    times on. The number of offset times is only regarded as long as the normal time is reached. E.g. Normal time set to 12.00 each day. Offset time is set to 7.00 hours and number of offset times is set to 10. The following will happen if the sequence is created at 11:00:

    Sequence start: 1st. 12:00 2nd. 19:00 3rd. 02.00 4th. 09.00 5th. 12.00 6th. 19.00 7th. 02:00 ....

    This means that the offset will be disregarded if the normal time is reached. If the sequence is created at 13.00: Sequence start: 1st. 19:00 2nd. 02.00 3rd. 09.00 4th. 12.00 5th. 19.00 6th. 02:00 ....

    For each sequence it is possible to have one start time with wild-cards, with corresponding offset times.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 30

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Set the "Event, on no timer start" flag to 'Yes' if an event shall be generated every time the sequence should have been started in a certain way but was not able to. This flag can be used to tune the SPL function when setting timers on a certain period. When traps starts to come then you should not run the SPL sequence faster. Cases when a sequence could not started as planned are: - the classification is not possible to fulfill. In this case an event is always

    generated but the sequence will start in the first monitor as default. If the sequence is not classified the first classification will be used (seen in the SPL-monitor picture as the first classification) as default.

    - if the sequence is already executing no further startup will be made. An event will be generated.

    Flag evaluation. The evaluation is done in the following order: 1. "Timer"; is a timer connected or not. 'Yes' means a timer is connected to

    this sequence. 2. "Offset time"; the flag tells if an offset is used. 'No' means no offset is

    regarded. 3. the flag "Number of offset times" ; If this flag is 'Yes' the offset values are

    regarded. A special case is if the flag "Number of offset times" = 'Yes' and the "Number of offset times" = 0. The offset is calculated forever. If "Number of offset times" = 'No' then you will get a one shot (to be compared with the "Number of offset times" = 1) timer.

    MDE start operation The sequence connected with this type of start is triggered after a change in status, value, or flags of an object(s). Furthermore, you can specify all objects of a certain type to start the sequence. This means that the sequence is connected to the whole file containing objects of that particular type. If the same object is defined several times to start the same sequence, or the whole-file option is selected for several different objects of the same type, only one start is fired. Note that in similarity with other types of sequence start, only those objects that can be presented in a point group, can be defined for this type of start. To set the MDE start:

    Set MDE start to yes in the Connect and Delete picture page 1 or 2 Select Connect and Delete picture page 2 Press the Show Point Group push button, so the point group identity that

    you have selected in page 1 will appear in the corresponding field and its containing elements will appear in the element list below this field.

    Set MDE Start Buffer flags to yes for the objects that should start the sequence. This flag should be sat even for the next option.

    Set also MDE All Elements flags to yes if you want all objects of a file to start the sequence. Not that the MDE Start Buffer flag should also be sat, otherwise this selected option is ignored.

    If a flag is set to yes where no object exist in that position, the flag is ignored.

    Up to 400 sequences can be connected to an object or to a file.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 31

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    6.4.3 Connect (Create) a Sequence With the Connect function one or several sequences are created. To connect a program the operator has to: Select a Program Select a Point Group or a Point Group Class Select a sequence class Fill in the Sequence priority Fill in if the sequence shall have event log or not Fill in the different starts a sequences shall have. To create the sequence select the DF key Connect Sequence. The number of connections done and the connections can be shown in the picture. From the connection list is it possible to do INFO and come to the Sequence Information picture. If one of the connections already exists an Ill-text will inform the user and no connections will be done.

    6.4.4 Disconnect (Delete) a Sequence With the disconnect sequence one or several sequences are deleted. Sequences are disconnected by selecting one Program in the Program field and one Point Group or Point Group Class in the corresponding field. Point Groups and Point Group Class can have wild card. The Point Group Class will only be used if no match is found in the Point Group field. To disconnect the sequence select the DF key Disconnect Sequence.

    6.4.5 Show Sequence With the Show Sequence function, the number of and the sequences that match the input data will be shown in the sequence list. Sequences are shown by selecting one Program in the Program field and one Point Group or Point Group Class in the corresponding field. Wild card(s) can be used. The Point Group Class will only be used if no match is found in the Point Group field. To show the sequence select the DF key Show Sequence. List Paging UP/Down, Scroll Up/Down, or First/Last Page can be used by selection of MB3 to scroll up/down the information.

    6.4.6 Reset data If the reset function is selected all shown data for the SPL Connect Delete function will be reset.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 32

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    6.5 Delete program The delete program function will delete the compiled version of the program. It will also take away the possibility to take the SPL program up in the ISG editor. The code on DB3 will remain unchanged. It will not be possible to delete a program that is included in a sequence. It is not possible to use this function in SDB. Warning: If the program is deleted in RDB and a sequence in SDB is connected to this program, will it crash in SDB when trying to execute the sequence.

    6.6 Rule Creation Sequence creation that shall survive a DE generation shall be saved as a rule. The rule function will save the rule for the Connect sequences and when the system is regenerated the sequences will be added as the rule says. Sequences that are not specified as a rule will be deleted. If new point groups have been added, this will automatically be added to the programs that they are connected to. With the rule function it is possible to: Show rule Update rule Save rule Delete rule

    Redo all connections Select a rule A rule is selected by writing its name in the rule text field. It is also possible to scroll in the rule list with extract wild cards. The name can be given in either upper- or lower-case letters. Show rule The show rule function requires that a rule exists. The rule information will be shown on connect and delete picture. Update rule The update rule function will update one rule with the current data in the Connect and delete functions. The rule must exist. Create rule Create rule function creates a new rule with the data from the Connect and delete function. If the rule already exists then no rule will be created and no data will be updated. Delete rule The delete rule function deletes one rule from the rule function. The data in the rule is deleted but the created sequences will remain until new data is integrated with DE. Redo all connections This function will redo all connections done with the Connect and delete function. All sequences will be deleted and redone with the current rules in the system. Sequences that are not saved as a rule will be deleted. Warnings and hints When a rule is created or be updated it will not automatically redo the connection. The rule is saved for execution the next time the "Redo all connections" function is done.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 33

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    6.7 Warning and Hints

    6.7.1 Object list and Element list The object list and element list has to be coordinated in a way that the object list only have pointers to elements, that are at the same concept type as the element. They can also point at zero elements, but then they can not be used in the Program code. If it will be an object mismatch, the sequence will crash when it is started and the reason will be shown in the Sequence Information picture.

    6.7.2 Names containing special characters When choosing names to create user defined parts of SPL Connect and Delete components (programs, point groups, etc.), the reserved AQL characters should be considered with care. Characters like underscore (_) and percent (%) in strings are interpreted as wild cards by SPL due to its internal embedded AQL search queries, see Reference 4. Otherwise, these characters can be freely used in Connect and Delete picture, in order to restrict your selections when using SPL Connect and Delete function.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 34

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    7 SPL Monitor The SPL function can be executing on different monitors. Every sequence is scheduled on a monitor and sorted by sequence classification and priority. If the sequence is to be debugged, then it will run in one of the monitors which is allowed to run SPL-debugger and the priority is ignored. The SPL function calculates what monitors the sequence is allowed to be executed in. Then the monitor with for the moment lowest load is selected. The monitors' priority and debug-possible flag can be changed in the monitor picture. This way the operator can schedule its sequences to run on desired monitors or block some monitors to be used without changing the sequences priority; if a monitor has higher priority than a sequence, then the sequence is blocked to run on that monitor. Likewise, the sequences to be debugged can only run on monitors that have their debug flag set. Note that the above discussion is of interest only for systems with more than one monitor. If the sequence is not possible to start on any monitor the sequence will start on the first monitor anyway. The monitor picture From the monitor picture it is possible to: See the sequence monitors and the starts scheduled to the different

    monitors.

    Change the priority for different monitors. Decide what monitors that the debug function shall be possible to execute

    in.

    See the total load and the peek load of number of sequences executing in the monitors.

    Reset the statistics Reach the monitor picture The monitor picture is reached from: Control system maintenance menu Sequence Information picture SPL Connect and delete picture Interactive SPL Generation editor picture. Changing the priorities When the monitor priority is changed it will directly affect the priorities in the system. The priority can be changed from 0 that is the lowest priority to 99 that is the highest. Once again, SPL schedules sequences on monitors that have equal or lower priorities than the sequences. Debug function ON/OFF When a sequence is executing with debug, only the monitor(s) that is marked with debug-possible flag is used. It will not have any effect on the sequence priority or classification. The debug is changed by switching the debug flag with manual data entry. If no monitor is specified with debug possible, sequences that are executing with debug will be executed in the first monitor. Statistics function In the statistics function it is possible to see the number of sequences that have been started on each monitor and the peek load.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 35

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    Reset statistics With the reset statistics function the statistics can be set to zero. If any sequences are executing at the moment the current peek load can be larger than the total started for a moment.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 36

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    8 SPL Debug By the SPL Debug function the sequence can be executing in a debugger. With the debugger it is possible to: See the code Follow the path of execution Suspend the executing code Execute the code stepwise Set breakpoints in the code Set a new start-point See the variables Examine variables Update variables Follow the updates of the variables in a watch list Cancel the program When the debug is executing on a sequence the sequence will be blocked from other usage. Find the SPL Debug function The SPL Debug function is started by the DF key Debug in the Sequence Information picture. The debug function will start on that sequence. Debug window explanation In the debug window it is possible to see The code in the code menu The valid variables on this program level in the variable menu A watch list over variables History of the instructions that the operator has given Run With the run function the sequence will be executed. No variables in the variable list will be updated until the program ends, or until suspend is made. During the execution it is possible to see the path of execution. Step Step one line. If a function, procedure or an Execute statement is stepped it will step into that. Step forward Step one line to the next higher line on this program level or higher level. It will execute all code in between. No step into subroutines, procedures or execute. Suspend This will stop the code and complete the line the code is executing at the moment. This is working when the run and step forward function is executing. Break points Set a breakpoint in the code. The execution will stop at this line. To set the breakpoint, Select the line then select the break function. To remove the breakpoint select the line with the breakpoint then select the break function.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 37

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    New Start Line With the new line function is it possible to skip some code or execute the code again. To select a new start line: select the line and then select the New line function. It is not possible to select a line on another level e.g. in a procedure. All data that is set before remains. Examine Examine variables is done by selection of the variable and then select the examine function. The result will be shown in the show history list. For arrays the specific indices have to be included. Character strings are accepted. For SREAL and SINTEGER will the value and the flags are presented. The flags are presented as a hexadecimal value, (0x'value'). Possible flags and values: Flag Decimal value Hexadecimal value INVALID 1 0x1 MANUAL_ENTRY 2 0x2 UPDATED 4 0x4 ALARM 8 0x8 IMPLEMENTED 16 0x10 DEACTIVATED 32 0x20 MEASUR_PROCESS 64 0x40 INVALID_IN_TTD 128 0x100 CORRECTED 256 0x200 BLANK_VALUE 512 0x400 NORMAL_STATUS 20 0x14 A number of combinations of these flags are possible. Assign Assign a new value to a variable. With the assign function it will be possible to add a new variable. For an array the specific index must be selected before the assign works. Character strings are accepted. For SREAL and SINTEGER will the value and the flags are presented. The flags are presented as a hexadecimal value, (see Examine above). Add watch Values that are included in the watch list are shown all the time and updated when the value is updated. To add a value to the watch function select the value in the function list and then select the add watch function Delete watch The delete watch function will delete a value from the watch list. To delete the value, select the value in the watch list and select the delete watch function. Cancel The cancel function will stop the debug execution. The program will be reset and next time it starts it will start from the beginning.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 38

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    9 Hints and Fault Situations Heavy changes of the file sizes It is recommended to make a re-population of the SPL-files after heavy changes of the file sizes. Otherwise SPL can get into trouble and crash. The dialogs as Sequence start and Debug is not started The Console has no authority to open new windows. Set security. A trap occurs and no dialog is started The SPL tool is not installed on the system. Read the installation chapter 2. Sequence included in the system but not started The sequence is not connected to any object, event or timer to be started from. Read the Users Guide to SPL Reference 5. No sequence is still started Check that the monitors are included. On picture SPL Monitor (ISCM0201) will show the monitors included in the system. At least one monitor has to be filled in form IPM and one classification on form IPA. The sequence disappears after the DE tool was executed The description of how the Sequence was created was not saved as a rule. See chapter 6.4. The program is compiled but you get a message that the program does not exist or the SPL debugger crashes The program file name contains capital letters or more than 20 characters. WARNING: There is a limited size of the stack. On the stack, variables are put as well as the context when a new level is called in the hierarchy of routines. Large arrays used in the program will hasten this problem. This limit is not calculated when compiling the programs. It occurs when executing the program.

  • Doc. kind Users Guide Project Network Manager Baseline

    Title S P L

    Doc. no. Lang. Rev. ind. Page 39

    ABB Power Systems 1KSE 000 591-A en A No. of p. 39

    10 Conventions SPL Programming Language

    11 List of References R1: WAH493, SPL Reference Manual. R2: WAH236 - 240, Data Engineering - Common Process data. R3: WAB093, Design description for Interlock. R4: WAC068, Avanti Reference Manual - Avanti Query Language R5: WAH327, Users Guide to Calculation in Network Manager

    REVISION Rev. ind. SPR No. Description Date A SOM050464 New document. All contents from 3AST 001 998 moved to TTT-

    template without any changes of the functions. Trade Mark SPIDERTM replaced by Network Manager.

    2006-01-12