Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Wall Acquisition Executive Steering Committee (ESC)
May 3, 2017
PREDECISIONAL/FOR OFFICIAL USE ONLY
BW8 FOIA CBP 000278
Presenter’s Name June 17, 2003
Agenda
Wall Acquisition ESC Overview
Border Wall System Overview
Status of the ADM for ADE-1
Status & Schedule for ADE-2A/B documentation
Prototype Schedule
RFI Status & Schedule
22
(b) (7)(E)
BW8 FOIA CBP 000279
Presenter’s Name June 17, 2003 3
Wall Acquisition ESC
PREDECISIONAL/FOR OFFICIAL USE ONLY
Purpose of the Wall ESC: The ESC provides a recurring, formalized opportunity for the Chief Acquisition Executive (CAE) and appropriate DHS and CBP leadership and technical experts to engage in appropriate oversight of the proposed Wall investment, in accordance with Department policies and procedures, to ensure sound management, review, support and oversight of Wall-related activities.
Facilitator/Owner: i, Chief Acquisition Executive (Wall Acquisition ESC Facilitator), Wall Program Manager
Frequency: Monthly (to be reevaluated as program matures)
Attendees: CBP, CRSO, S&T, Policy, DOT&E, OCPO, JRC, CFO, CTO, PARM
(b)(6);(b)(7)(C)(b) (6)
BW8 FOIA CBP 000280
Presenter’s Name June 17, 2003
Fulfill the President’s mandate to “secure the nation’s southern border through the immediate construction of a physical wall, monitored and supported by adequate personnel so as to prevent illegal immigration, drug and human trafficking and acts of terrorism.”
4
Executive Order
PREDECISIONAL/FOR OFFICIAL USE ONLY
Obtain and maintain complete operational control of the southern border through infrastructure investment, enforcement resources, technology and enhanced operational tactics and strategy
Plan, design and construct a physical wall using materials and technology along approximately 1,200 miles of the United States border with Mexico
(b) (7)(E)
BW8 FOIA CBP 000281
Presenter’s Name June 17, 2003 5
Southwest Border Operational Requirements
PREDECISIONAL/FOR OFFICIAL USE ONLY
USBP Capabilities
1. Domain Awareness (technology/intelligence)
2. Impedance and Denial (wall)
3. Mobility and Access (roads)
4. Mission Readiness (agents/equipment)
Requirement for impedance and denial has increased- Evolution of threat- More demanding definition of operational control
BW8 FOIA CBP 000282
Presenter’s Name June 17, 2003
Analysis of Border Wall Alternatives
6
Prototype Existing ToolkitOptimal
Wall Solution for Each Segment of Border
Analysis of Operational
Factors
Range of Wall Options
(b) (7)(E)
BW8 FOIA CBP 000283
Presenter’s Name June 17, 2003
I&D Summary: SWB Chief Patrol Agents’ Requests for Total Miles of Barrier
The table below summarizes the TOTAL Barrier Requests from the SWB CPAs. The complete submittal from the CPAs is currently ongoing additional analysis.
PRE
Types of Barrier
Primary Fence
Secondary Fence
Replace (Primary or Secondary)
Vehicle to Primary
Total Miles for All Barrier Types
Sector Primary Secondary ReplacementVehicle‐to‐Primary Total
RGVLRTDRTEPTBBTTCAYUMELCSDCTotal
7
(b) (7)(E)
BW8 FOIA CBP 000284
Presenter’s Name June 17, 2003
Acquisition Status
84
• CBP is following the DHS Acquisition process for each segment of the wall, to validate the need and cost of the project, and ensure fair and open competition.
• On March 14, the Acquisition Review Board (ARB) reviewed the CBP Wall program. The purpose of the ARB was to assess the Wall program’s Acquisition Decision Event 1 (ADE-1) readiness.
• On April 14, the CBP Wall program was granted an ADE-1. The program was added to the Master Acquisition Oversight List (MAOL).
BW8 FOIA CBP 000285
Presenter’s Name June 17, 2003
Initial Program Priorities
Will slide
9
BW8 FOIA CBP 000286
Presenter’s Name June 17, 2003
Prototype
10
WALLPROTOTYPE ACQUISITION
MARCH TO JULY
CONSTRUCTIONJULY TOAUGUST
MAR 17 Solicitation to
Industry
JUN 06Designs due
from selected Vendors
APR 04Concepts due from Vendors; Evaluation
begins
JUL 18-25Contract awarded;
Construction begins AUG 22
Prototype Construction
complete
INSERT DEF of PROTOTYPE and MB LANGUAGE
(b) (5)
BW8 FOIA CBP 000287
Presenter’s Name June 17, 2003 11
Prototype Schedule
PREDECISIONAL/FOR OFFICIAL USE ONLY Dates subject to change
3/1/2017 8/31/2017
4/1/2017 5/1/2017 6/1/2017 7/1/2017/
3/17/2017Solicitation to Industry
5/8/2017Down Select to up to 20 Vendors Notified
4/4/2017Concept Papers Due
5/30/ 2017Design Proposals
Due FromDown Selected
Vendors
7/12/2017Source Selection
Best Value Determination
7/18/2017Contracts Awarded
8/22/2017Prototype
Construction Completes
7/25/2017Prototype
Construction BeginsDown Select
Contractors Site Visits
5/16 to 18/2017
BW8 FOIA CBP 000288
Presenter’s Name June 17, 2003
12
WALL (b) (5)(b) (7)(E)
(b) (7)(E)
BW8 FOIA CBP 000289
Presenter’s Name June 17, 2003 13
APR 13USACE Wall IAA
Awarded
MID-MAYContract for Design
Awarded
WALLDESIGN
APRIL TO JUNE
FY18FY17
Draft initial Project schedule in Primavera (April 25) Communication milestone chart (April 25) (May 4) (May 5) (May 15) (3 projects) (May 25) (May 30)
(b) (7)(E)
(b) (5)(b) (5)
(b) (7)(E)
(b) (7)(E)
(b) (7)(E)
(b) (7)(E)
(b) (5)
(b) (5)
(b) (5)
(b) (5)
(b) (5)
(b) (5)
BW8 FOIA CBP 000290
Presenter’s Name June 17, 2003
ADE-1& ADE-2A/B: Status & Schedule Currently, efforts are focused on the ADE-2A/B schedule completion.
Kick off meeting scheduled for Tuesday, May 2 with CBP (OA and OFAM), Johns Hopkins University Applied Physics Laboratory (APL), USACE/ERDC (Engineering Research and Development Center) to support the Wall AA.
The purpose of this meeting is to define roles and responsibilities, and discuss the methodology and approach for AA completion.
Pre kick off meeting regarding CBP cost estimate baseline and Independent Cost Estimate with DHS PARM, CAD, OA and BPAM PMO
Provided CAD the LCCE for the current TI and the draft CEBD
145
BW8 FOIA CBP 000291
Presenter’s Name June 17, 2003
Next Steps
The scope of the Wall Program will continue to evolve over time
CBP will continue to work closely with our DHS counterparts to continue to share information, including a Integrated Master Schedule that coalesces all aspects of the Wall Program
15
BW8 FOIA CBP 000292
BW8 FOIA CBP 000293
Presenter’s Name June 17, 2003 17
: Status & Schedule - DRAFT
6
(b) (5)(b) (7)(E)
BW8 FOIA CBP 000294