6
waste EW - 003 Description of work : Debris Clearance Rate in Zone A Consider Volume 2.26 Activities Unit Qty Rate Rate Analysis abo!r Cost Un skilled Labour Hr 8.00 175.00 = A"" : For mall !" = #ransport Cost Use #ra$tor Hr 6.00 250.00 = #otal %asi$ Cost = A"" : &'er Head ( )ro*t 20" = +ate ,or +emo'in- /sistin- Con$rete aste t ite For 2.26 m!3 = Rate $er % &3 = 'ay Rate per %&3 =

Waste Concrete Removing 1

Embed Size (px)

DESCRIPTION

doc

Citation preview

waste

Description of work :

Debris Clearance Rate in Zone AConsider Volume 2.26

ActivitiesUnitQtyRateAmountRate Analysis

Labour Cost

Un skilled LabourHr8.00175.00=Rs.1,400.001,400.00Add :For Small 3% =Rs.42.00280.00

Transport CostUse TractorHr6.00250.00=Rs.1,500.001,500.00

Total Basic Cost=Rs.3,180.00Add :Over Head & Profit 20% =Rs.636.00Rate for Removing Exsisting Concrete Waste At Site (For 2.26 m3)=Rs.3,816.00Rate Per 1 m3=Rs.1,688.50

Say Rate per 1m3=Rs.1,700.00

&"-,Regular"&8&A&"-,Bold"&8EW - 003

Debris Cleaning45Rate Analysis for Variation Items46Variation No:47Variation :Debris Clearance Rate in Zone A48Assumed Quantity for rate build-up :1.80Cu.mMark-up :20.00%49Norm Ref. :5051Price CodeLabour ComponentUnitQuantityRateAmount52Labour USKDay2.001,200.002,400.0053 0.054 0.055 0.056Total Cost for Labour - A2,400.005758Price CodePlant/Equipment ComponentUnitQuantityRateAmount59TractorDay0.253,500.00875.006061 0.062 0.063Total Cost for Plant/Equipment - B875.006465Price CodeMaterial ComponentUnitQuantityRateAmount66 0.067 0.068 0.069 0.070Total Cost for Material - C0.07172Price CodeMiscellaneous Cost ComponentUnitQuantityRateAmount73Allow for toolsAllow2.50%2,400.0060.0074 0.075 0.076 0.077Total Cost for Miscellaneous - D60.007879Estimated Direct Cost - E ( A + B + C + D )3,335.008081Overheads and Profit - F20.00%of E667.008283( E + F )4,002.008485Rate per unit( G / 2)2,223.338687Say Rate2,224.008846Rate Analysis for Variation ItemsVariation No:47Variation :Tower Crane Cost for Debris cleaning work48Assumed Quantity for rate build-up :12.00hrsMark-up :20.00%49Norm Ref. :5051Price CodeLabour ComponentUnitQuantityRateAmount52OperatorsHrs12.00166.672,000.0060,000.0053Signal MansHrs24.00111.112,666.6740,000.0054 0.055 0.056Total Cost for Labour - A4,666.675758Price CodePlant/Equipment ComponentUnitQuantityRateAmount59Tower CraneHrs12.001,291.6715,500.006061 0.062 0.063Total Cost for Plant/Equipment - B15,500.006465Price CodeMaterial ComponentUnitQuantityRateAmount66 0.067 0.068 0.069 0.070Total Cost for Material - C0.07172Price CodeMiscellaneous Cost ComponentUnitQuantityRateAmount73Allow for toolsAllow2.50%4,666.67116.6774 0.075 0.076 0.077Total Cost for Miscellaneous - D116.677879Estimated Direct Cost - E ( A + B + C + D )20,283.338081Overheads and Profit - F20.00%of E4,056.678283( E + F )24,340.008485Rate per hour( G / 12)2,028.338687Say Rate2,029.0088

&"-,Italic"&10RDA/NRCP/ICB/ADB/CP-10

&"-,Italic"Bill 7 B1 - Rate Analysis - Page &P of &N