Upload
eugene-murphy
View
215
Download
1
Embed Size (px)
Citation preview
DESALINATION
ELSEVIER Desalination 106 (1996) 361-370
Wastewater disposal option in Mundaring: A practical case study
Eugene Murphy Water Authority of WA, 629 Newcastle Street, Leederville 6007, Western Australia
Tel. +61 (9) 420-2420; Fax +6/ (9) 420-3200
Received 19 May 1995; Accepted 5 August 1995
Abstract
Urban development in the Hills areas of Perth is difficult to provide with local or regional wastewater systems due to the remoteness and isolation as well as the sensitive environment. Development to date has therefore mainly been on the basis of large-sized lots with individual on-site systems. This in turn puts limitations on f&her development or re-development of these areas. In some locations such as Kalamunda, a connection to one of the Authority’s major schemes has recently been possible. In other areas such as Mundaring, a local scheme would be required. This paper describes the development of such a scheme to the concept stage for the development of the Mundaring town centre.
Ke_~word.s: Small community wastewater treatment plant; Health; Environmental and social issues; Economics- user pays; Community consultation; Advanced wastewater treatment
l.Introduction
The Perth region consists of a relatively flat
coastal plain some 20 km wide, extending to the foot of the Darling Scarp. Urban development has occurred in corridors extending outwards from the major central business districts of Perth and Fremantle (see Fig. I).
The Shire of Mundaring covers a number of urban cells in rural settings located in the eastern corridor. The population of the region is some 30,000. The main business area of Mundaring is located approximately 30 km from the city of Perth.
Mundaring is not connected to the Authority’s sewerage system (see Fig. 1), and consequently the whole Shire is served by individual on-site septic tank systems. It has been general govern- ment policy that residential lots of 2000 m2 or greater as used in this region, are suitable for on- site systems. These facilities must meet the re- quirements of the controlling authority, the Health Department of WA.
The Hills Area of the Darling Scarp drains naturally into the Swan and Canning Rivers, which like most river systems in WA, Australia and the world, are sensitive to excessive nutrient loads from urban development and agricultural/
CO1 l-9164/%/$15.00 Copyright 0 1996 Elsevier Science B.V. Ail rights reserved.
PII SO01 l-9164(96)00131-2
362 E. Murphy / Desalination 106 (1996) 361-370
~ n INFLL AREAS
--I : i IISEWERED A.AEAS
SCARBOROUGH
FREMANTLE
Garden Island
Fig. 1. Urban development in the Perth area.
E. Murphy /Desalination IO6 {I9961 361-370 363
SURF&E WATER \
CAKHUENT tit3 [EXISTING k flliURE) -_-___ b )
”
CnURCHUAN BROOK-
horticultural activities in the catchment. The principal authorities involved in controlling the condition of these rivers are the Department of Envjronment, the Swan River Trust, the Water- ways Commission and the Health Department.
Additionally, the Hills area east and south of Perth currently provides the bulk of the potable water supply for the Perth region and for the Goldfields and Agricultural Water Supply scheme (see Fig. 2). This water is only chlori- nated and fluoridated prior to supply to the consumer.
Consequently, it has been the policy of the Water Authority to pursue acceptable wastewater schemes for any new development or re-develop- ment in this region. This is done to protect pres- ent and future surface water supplies. as well as to reduce the impact on the sensitive river sys- tems. Since the mid-1980s the Authority has actively pursued providing a wastewater scheme in this area. This has resulted in the current pro- posal of a limited wastewater scheme to serve the Mundaring town centre and two primary schools.
This facility is planned for commissioning in 1995/96.
WOOROLCO BROOK
INDIAN OCEAN
n
ROlTN EST FREMANTLE
ISLAND 9
Fig. 2. Sources of potable water supply for the Perth region.
2. Criteria for a wastewater scheme
Any wastewater scheme must be capable of dealing with the flow produced on a continuous basis each day of the year. The system must also meet four essential criteria:
l protection of the health of the community . safeguarding the environment l social (community) needs . economic considerations
These criteria vary to some extent depending on the specific application and location of the scheme, and most importantly, on the type of effluent disposal system, either with or without reuse applications.
For the Mundaring region, due to its remote- ness from existing Authority schemes, a local treatment and disposal/reuse scheme is required. The scheme would provide an effluent which ultimately would reach local water courses (Jane Brook) and eventually the Swan River. During the drier months, the effluent could be used for irrigation of ovals or parklands, with storage or the alternative disposal system being provided in
364 E. Murphy / Desalination 106 (1996) 361-370
case of non-use or failure of the irrigation plant.
For such a scheme the following aspects need to
be considered with regard to the four criteria.
sources. It was also observed that public health
and protecting the environment are the most
important issues for the community.
2.1. Impact on human health 2.3. Economic considerations
The critical issue here would be to control the
level of pathogens in the effluent to meet the
relevant quality requirement. Disinfection of the
effluent would be essential. For irrigation appli-
cations special conditions need to be adopted,
such as the Guidelines for Use of Re-claimed
Water in Australia produced by NHMRC and
AWRC in 1987, currently under review.
The Authority is a self-funding organization
and operates generally on the “user pays” princi-
ple. Consequently, the overall community served
by any wastewater scheme must bear the cost.
This applies both to the cost of constructing the
facility and to the annual cost of operating and
maintaining the system. These costs are recouped
from the community through the annual sewerage
rating system. Essentially this scheme will ser-
vice developed land which will make the provi-
sion of sewerage uneconomic to the Water Au-
thority.
2.2. Environmenta issues
As previously mentioned, the most important
issue is the residual levels of nutrients (N and P)
in the effluent, and their impact on the receiving
wraters. Conventional wastewater treatment as
practised at the Authority’s three major Perth
plants would not be sufficient. The technology
exists to provide an advanced treatment plant
which produces an effluent with the acceptable
level of nutrients. Such a plant is currently being installed by the Authority for the town of Pem-
berton in the southwest of the State.
2.3. Communify needs
At the present time the Authority is undertak-
ing a major review of its long-term wastewater
treatment and disposal strategy for the Perth-
Bunbury coastal region, known as the Waste-
water 2040 project. This involves a community
consultation program to seek input from the
wider community. The Authority recently pub-
lished its Wastewater 2040 Discussion Papers as
the initial Authority response to the issues and
concerns raised from the community consultation
program to date.
In summary, the community generally has a
strong conviction that wastewater is a valuable
resource and that treated wastewater should be
reused to conserve scarce potable water re-
In summary, a number of authorities and
groups are involved in providing a wastewater
scheme and these are as follows:
9 Dept of Environmental Protection - sets con-
ditions for and issues discharge licences
l WA Health Department - defines public
health standards
l Local Authority - ensures planning by-laws
are met
l Local Community - ensures that it addresses
their needs l Operating Authority (Water Authority) -
must meet all requirements including the
financial implication
3. The proposed scheme
3.1. Development of scheme
Detailed investigations of a wastewater
scheme for Mundaring were commenced by the
Authority in 1986. At that time development
proposals of two remaining large landholdings
were initiated. The Shire of Mundaring, as part of
their review of their town planning scheme, held
a workshop in 1987 on the issues of wastewater
treatment ‘and disposal. This was attended by
E. Murphy / Desalination 106 (1996) 361-370 365
Table 1 Mundaring limited wastewater scheme
Source Equivalent population (EP for WWTP)
Primary school: assume 300 students/staff
Areas as defined by Shire of Mundaring letter of 16/4/l 991: A. Central business area at 5000 m2 and 10 m’!ha!d = 5 m3/d = 25 persons over
8 h day, EP=75 B. 3 x (9 residences + 8 units) = 51 persons plus others, say 19 EP
C. 3 x (16 units -t 7 residences) = 69 persons plus others, say 11 EP
D. 3 x (32 units + 7 residences) = 117 persons plus others, say 63 EP
E. 3 x (10 residences + 24 units) = 102 persons plus others, say 28 EP
F. 3 x (11 residences + 24 units) = 105 persons plus aged hostal = 40 EP plus aged units 0 72 x 2 = 144 persons
Possible future private school - as for above
representatives from Shire of Swan, Health De- partment, EPA, the Waterways Commission and
the Water Authority. In 1988 several development proposals were
given conditional approval by the DEP to pro- ceed without a wastewater scheme in the short term [EPA Bulletins 333 (6/88), 357 (S/85)]. In the longer term, a connection to a “reticulated sewerage service” was recommended.
In 1988 a wastewater scheme for development of the Mundaring town centre was proposed by the Authority and received favourable consider- ation by the Council of the Shire. It was consid- ered that a larger scale regional wastewater scheme could not be economically justified, while lot sizes remain at 2000 m* or larger. A limited scheme for 1000 EP was therefore con- ceived as detailed in Table 1.
In 1990 the Authority commenced studies on a pilot plant employing advanced treatment tech- nology for application to the Mundaring scheme.
100
75
(175) 70
(245)
(3;:) 180
(505) 130
(635) 289
(924)
100
1024 ___. -~ - -.~
The basic processes used were as follows:
Chcmid Feed (aalum, caustic)
I
wastewater ---_, lntetmitent ------> glow -----> Sand ------a Disinfection
extended balancing filtration
aeration ‘“”
I process I
, , 1 Effluent I
Waste sludge
Typical test results from this pilot plant are given in Table 2.
3.2. Current status qf project
Over the last 3 years discussions held with relevant authorities to bring
have been the project
to fruition. The main issues were what treat- ment/disposal/reuse system was to be provided in what location, and how the project was to be funded. The Shire has held a public meeting on
E. Murphy / Desalination 106 (1996) 361-370
Table 2 Pilot plant test results
pH SS mg/l
SVI” DO BODj COD COD (sol) ml/g mgil mg/lS mgil mg/l
lnfluent 6.7 270 340 710 Mixed liquor 6.5 6400 85 1.2 Effluent 6.9 10 10 Final effluent after Dynasand and UV 7.0 < 5 <5 55 45
(225)
Total N NH,-N NO,-N NO -N 3
Total P Sol P mgil ml/g mglL mg /l mg/l mg/l
Influent 6.7 45 10 4.6 Effluent 6.9 3.0 0.15 0.80 1.2 0.45 Final effluent after Dynasand and UV 7.1 3.1 0.15 0.85 0.80 0.25
% UV transmittance Faecal coliforms at 254 nm no./100 ml
Salmonella
Effluent Final effluent after Dynasand and UV
100,000&450,000 51-55 median iOb
Present Seldom isolated
aBased on nine tests only. Values were within the range ~10 - 420. bUV transmittance of >55% is required for reliable disinfection.
the issue, and petitions for and against this pro- A further major hurdle to overcome was find- ject have been submitted to the Council and the ing an acceptable site for the treatment plant. government.
The estimated cost for stage 1 of the scheme is $2.6 million. Of this $2.0 million will be pro- vided by the Authority under the advanced infill sewerage program announced by the State Gov- ernment earlier this year. Additionally, funding was sought and granted from the Commonwealth Government under the One Nation Program to assist with this scheme. Due to on-going delays with the project, this funding has now been di- verted to the Denmark WWTP. However, assis- tance with funding for the treatment plant has been obtained under the National Landcare Pro- gram ($0.48 million). The Shire of Mundaring will also contribute to the scheme ($0.12 mil- lion).
Fig. 3 indicates the alternative sites considered by the Authority in liaison with the Shire and au- thorities such as the DEP and CALM. It needs to be appreciated that this region covers three dif- ferent water supply catchment areas, as shown in the Table 3.
On the basis of these and other factors, in- cluding a present value cost analysis, the current preferred site was selected. Needless to say, the proposed treatment plant site is not favoured by the community living in close proximity. This is a common problem with such facilities. Although the community needs and desires the benefit of the wastewater service, location of the treatment plant often receives the NIMBY response. The Authority for the current proposal has made the
E. Murphy /Desalination 106 (1996) 361-370 367
FUTURE JANE BROOK CATCHMENT
WATER CATCHMENT BOUNDARY - I - I
ALTERNATIVE EXAMINED WWTP SITES
MUNDARING WEIR CATCl-iMENT AREA
/LOWER HELENA PIPEHEAD DAM I
CATCHMENT AREA
Fig. 3. Water catchment areas and alternative sites for water treatment plant.
Table 3 Water supply catchment areas
Catchment area
Mundaring Weir
Protection objectives ----..._ -.. -I
Priority 1 : Non-degradation by strict limitation on land use
Lower Helena pipehead dam Priority 2: Restrictions on land use to ensure level and risk of pol- lution is not increased
Ian Brook catchment (future) Priority 3 Protection through management with less emphasis on restrictions
368 E. Murphy / Desalination 106 (1996) 361-370
ARFA 10 BE SERVED (S IAGt 1)
lii_TIMAT- SCHEMt
W/‘&II WitI t: I’liMI’ l;lA ION
WASTrW.4T’R PRESURE MAlN
Fig. 4. Layout of the treatment plant.
guarantee to the Shire Council that the plant would not exhibit odour nuisance or unacceptable noise levels at 200 m from the facility under normal operating conditions. This buffer distance would be provided by the existing bushland of the current proposal.
3.3. C’oncept design
The current proposal provides for the staged installation of the plant in two 500 EP modules. The possible layout of the plant is shown in Figs. 4 and 5, and the treatment units require an area of 30 m by 2.0 m. The effluent from this plant would flow through a storage/reed bed
system prior to reuse for irrigation or discharge to a creek via a leach drain system for further effluent polishing. It may be necessary in the final design to use the storage/reed bed for flow balancing, and then filter and disinfect the bed effluent. A regular monitoring program would be set up for the performance of the total system. The treatment plant would be designed to pro- duce the following effluent quality:
l Suspended solids - 5 mg/l l BODS - 10 mgil l Total nitrogen - 15 mg/l l Total phosphorus - 1 mg/l l Faecal coliforms - 10 per 100 ml
E. Murphy / Desalination 106 (1996) 361-370 369
EFFLUENT TO REED BEDS-P
AIR COMPRCSSORS A L-DUAL MOUNTED COMPRESSORS
TO UYNASAND FILTER
Fig. 5. Details of the treatment plant.
Table 4 Major activities still to be undertaken
_
Activity
Acceptance by community DEP works approval Statutory approval Funding approvals Design and construct:
Sewerage reticulation Pump station/pressure main Treatment plant Effluent system
Commissioning of system
3.4. Work stiIl to be undertaken
Table 4 summarises the major activities still
to be executed before the scheme is put into
operation.
Government
Comments
WAWA - in liaison with Shire WAWA - under EP Act 1986 WAWA - under WA Act 1984 WAWA - with Commonwealth
Design ~ WAWA; const. - contract Design - WAWA; const. - contract Design and construct contract Design - WAWA; const. - contract WAWA and contractors
4. Conclusions
On the basis of the Authority’s experience
with the development of the limited wastewater scheme for Mundaring, the following conclusions
can be made.
370 E. Murphy / Desalination 106 (1996) 361-370
1. The underiying concept of small communi- ty plants with local effluent disposal, with or without reuse applications, is generally supported but difficult to implement due to the many as- pects that need to be addressed, and due to the different groups involved with their specific interests which have to be considered.
2. The most critical issue to be addressed is the disposal of the effluent from the treatment plant, with or without reuse applications.
3. When a local treatment plant is envisaged, provisions have to be made in the town planning schemes for suitable sites with buffer areas.
4. Cooperation between all groups involved including the community, is essential for the success of the scheme.
5. Discussions between these groups should take place as early as possible in the planning and concept development phases, and this should occur at least 5 years before the system is to be become operational.
6. At the outset an environmental impact as- sessment should be undertaken of both the exist- ing facilities and of the proposed facilities for the future development.
7. There must be an on-going community education process and program.
8. Research into new technology and moni- toring of existing similar plants, both here in Australia and elsewhere, should be on-going.