Water Supply Project Specification

Embed Size (px)

Citation preview

  • 8/10/2019 Water Supply Project Specification

    1/33

    TECHNICAL SPECIFICATIONS

    SECTION 6

    WATER SUPPLY SYSTEM

    6.1 General

    These Specifications shall be applied on all water supply system

    works, comprising, but not limited to, the water intake structure,

    conveyance pipeline, transmission pipeline to the elevated tank, water

    elevated tank and distribution network pipeline which shall consist of

    various works that are grouped according to their natures and

    characters as set out below :

    (a) Civil works including earthwork, concrete works, drainage

    works, roadway works, outdoor works and others;

    (b) Piping works, for the conveyance, transmission and

    distribution network pipelines including valves; and

    (c) Architectural and metal works including fencing and gate

    setting, ladders, anchoring and others.

    6.2 Civil Works

    6.2.1 Earthworks

    The working area shall be confined within the lots demarcated

    as shown on the Drawings. The areas shall be cleared, stripped

    and leveled to the lines, grades, formations and dimensions as

    shown on the Drawings.

    The earthworks shall be undertaken and completed for, but not

    be limited to, the following :

    (a) Trench excavation, bedding and backfilling along the

    alignment of the treated water transmission pipeline and

    the treated water distribution network pipelines ;

    (b) The lot assigned to the elevated water tank;

    (c) Preparation for structural foundations of the various

    concrete structures;

    VI -

  • 8/10/2019 Water Supply Project Specification

    2/33

    TECHNICAL SPECIFICATIONS

    (d)Sub-grading for roadways including associated subsidiary

    drainage works and flooring of open space in the lots to be

    occupied by the elevated tank ; and

    (e) Other miscellaneous and ancillary works.

    Each work item shall be governed by the respective relevant

    provisions of the Technical Specifications, such as :

    (a) Open excavation works including pits and trenches

    (b) Cobble or broken stone bedding

    (c) Sand bedding

    (d)Earth or sand backfill works

    6.2.2 Concrete Works

    Concrete works shall include the following items :

    (a) Lean concrete works employing K125 bedding

    materials of concrete structures ;

    (b) Concrete foundations, footings, blocks, saddles, posts,

    etc. to be required for pipes;

    (c) Structural concrete works using K225 for water tower

    to store treated water; and;

    (d)Concrete K250 works for block-out and secondary

    concrete to be made for anchoring the equipment,

    devices and materials.

    All the concrete works shall be executed and completed

    conforming to the lines, grades and dimensions as shown on the

    Drawings and shall be carried out under the respective relevant

    provisions of the Technical Specifications, such as :

    (a) Lean concrete works

    (b) Structural concrete works

    (c) Block-out and second stage concrete works

    The Contractor shall be checked the necessity of thrust concrete

    block at steel pipe bending points or tee setting points, and

    VI -

  • 8/10/2019 Water Supply Project Specification

    3/33

    TECHNICAL SPECIFICATIONS

    concrete block, which has required volume, shall be placed if

    necessary. All cost incurred for this work shall be included in

    the lump sum price for the relevant items in the Bill of

    Quantities.

    6.2.3 Drainage Works

    Drainage works to be undertaken within the premises of the lot

    for the facilities shall include side drain ditches which are to be

    placed at the side of the roadways as shown on the Drawings.

    The drainage works shall also include drainage system to drain

    surface water out of the lot to a drainage outfall.

    The drainage facilities provided within the premises of the lot of

    facilities shall be executed and completed to the lines, gradesand dimensions as shown on the Drawings. Each work item

    shall be carried out in accordance with the respective relevant

    provisions of the Technical Specifications.

    6.2.4 Roadway Works

    Paved roadways shall be installed within the premises of the lot

    of the facilities. The base course and the roadway pavement are

    designed for lighter traffic only and are therefore narrower inwidth and thinner in sections than the normal roads. The

    roadways shall be provided with crushed stone and side drain

    ditch. All works shall be completed according to the lines,

    grades and dimensions as shown on the Drawings and shall

    comply with the respective relevant provisions of the Technical

    Specifications for the following items :

    (a) Sub-grade

    (b) Side drain ditches(c) Shoulder

    (d)Sodding

    6.2.5 Outdoor Works

    Outdoor works shall include all structures and facilities to be

    constructed within the different lots of the water supply system

    complex. The work items are as set out below :

    (a) Fencing and gate setting

    VI -

  • 8/10/2019 Water Supply Project Specification

    4/33

    TECHNICAL SPECIFICATIONS

    (b) Sodding and tree planting on open spaces of the lot

    All the above works shall be completed to the lines, grades and

    dimensions as shown on the Drawings, and shall include,

    except the metal works such as fabrication of fences and gates,the following :

    (a) Excavation of pits, trenches for fences, gates, side

    drain and ditches

    (b) Wet masonry work for side drain ditches

    6.3 Mechanical Works

    6.3.1 General

    Mechanical works for the water supply system shall consist of

    erection, installation, fabrication and assembly of the equipment

    and materials provided for this system. The works shall be

    executed and completed to the lines, positions, places and

    dimensions as shown on the Drawings.

    All the works shall be carried out by the Contractor until the

    system has been certified by the Engineer as fully and

    satisfactorily completed and have passed all requiredperformance tests, whereupon the Contractor shall be issued

    "Mechanical Completion" and "Performance Test" certificates.

    The equipment and materials to be incorporated in the water

    supply system include, but shall not be limited to, the

    following :

    (a) Pipelines for transmission and distribution of treated water

    including fittings and valves

    (b) Elevated water tank

    6.3.2 Standards and Workmanship

    All materials shall be new, the best of their respective kinds and

    of such quality as are usual and suitable for work of like

    character. All materials shall comply with the latest Japanese

    Industrial Standards (JIS) or equivalent.

    VI -

  • 8/10/2019 Water Supply Project Specification

    5/33

    TECHNICAL SPECIFICATIONS

    All workmanship shall be of the highest class throughout to

    ensure smooth and vibration free operation under all possible

    operating conditions, and the design, dimensions and materials

    of all parts shall be such that the stresses to which they may be

    subjected shall not render them liable to distortion, undue wear,or damage under the most severe conditions encountered in

    service.

    All parts shall conform to the dimensions on and shall be built

    in accordance with approved drawings. All joints, datum

    surfaces, and mating components shall be machined and all

    castings shall be spot faced for nuts. All machined finishes shall

    be as shown on the Contractor's drawings.

    In all mechanical parts, such as screws, bolts, studs, nuts and

    threads for pipes etc., the unit of measurement should be in

    Metric System.

    Standard to be used

    All materials to be furnished under the Contract shall conform

    to the required standard for materials and test of Japan or

    United States of America, or equivalent. The following

    standards are referred to and abbreviations shown have beenused.

    (a) Japanese Industrial Standard (JIS)

    (b) American Society for Testing and Materials (ASTM)

    Other International standards may be accepted, provided that

    the requirement therein are, in opinion of the Engineer,

    equivalent to the above standards. If the Contractor proposes

    equivalent standard for such materials, the Contractor shall statethe exact nature of the changes, and shall submit complete

    standard, and the information and data on the materials in

    English language for the Engineer's approval.

    If no standard is indicated, then the relevant Japanese Industrial

    Standard, or American Society for Testing and Materials shall

    apply.

    VI -

  • 8/10/2019 Water Supply Project Specification

    6/33

    TECHNICAL SPECIFICATIONS

    All electrical equipment and metal or electrical works shall

    comply with the requirements and latest edition of the

    following codes and standards, where applicable :

    (a) Japanese Electro-Technical Committee's Standard (JEC)

    (b) Japanese Technical Standard for Electrical Facilities

    (c) Japanese Electric Machine Industry Association's Standard

    (JEM)

    (d)Japanese Cable-makers Association Standard (JCS)

    (e) Local codes, other standard, instructed and/or approved

    by the Engineer.

    6.3.3 Piping Work

    6.3.3.1 General

    Steel pipe or PVC pipe shall be used for water lines. All

    necessary studs, bolts, screws, nuts, washers, gaskets,

    packing, supports, etc., required in connection with the

    field assembly of the piping systems shall be supplied by

    the Contractor. All gaskets and packing shall be of

    approved material and of the type that has been proven

    satisfactory for the service to which they will be subjected.

    Where pipe is embedded in concrete, it shall be carefully

    set to the required lines and grades, and securely braced

    and held in place so that no movement shall occur during

    concrete placement. Pipe supports to be embedded in

    concrete shall be made of material which shall not

    deteriorate, weaken or cause damage to the pipe. The

    Contractor shall schedule and arrange his work of

    installing pipes and pipe supports in coordination with the

    Engineer.

    The Contractor shall supply and install all pipe hangers,

    brackets and supports required for the support of the

    piping, including the drilling and caulking for the

    expansion anchors and any work incidental to the setting

    of such embedded anchors or inserts in concrete.

    VI -

  • 8/10/2019 Water Supply Project Specification

    7/33

    TECHNICAL SPECIFICATIONS

    Unless otherwise specified, pipe support shall be spaced at

    7-feet (2.13 m) maximum. Vertical runs shall be supported

    by means of pipe clamps or collars. Hangers and support

    shall be painted.

    6.3.3.2 Mortar Lined and Enamel Coated Steel Pipe

    (a) General

    Mortar lined and enamel coated steel pipe materials,

    and method of manufacture of straight pipe and pipe

    specials shall conform to AWWA-C200 Specifications

    or equivalent, subject to the exceptions and

    supplemental requirements contained herein. The

    pipe, of the diameter and class as specified shall befurnished complete with rubber gaskets, if required,

    and all specials and bends shall be provided as

    shown.

    (b) Cylinder Material

    Cylinders shall be fabricated from hot-rolled carbon,

    sheets or plates, conforming to ASTM A-570 Grades

    C, D, and E, ASTM A-283 Grade D; steel pipeconforming with ASTM A-139, Grade B; or, if

    approved by the Engineer, high strength low-alloy

    steel conforming with ASTM A-572 Grade 42, or

    equivalent JIS standards.

    (c) Rubber Gasket

    The rubber gasket furnished with the pipe shall be

    continuous ring type, made of a special composition

    rubber. The gasket shall be so formed and cured as tobe dense, homogenous, and have a smooth surface,

    free of blisters, pits, and other imperfections. The

    gasket shall be of sufficient volume to fill substantially

    the recess provided, when the joint is assembled, and

    shall be the sole element depended upon to make the

    joint water-tight. The compound shall be of first

    grade natural crude, synthetic rubber, or a suitable

    combination thereto and shall conform with the

    physical requirements listed below :

    VI -

  • 8/10/2019 Water Supply Project Specification

    8/33

    TECHNICAL SPECIFICATIONS

    Physical Requirements Value

    Tensile Strength, min.

    Natural RubberSynthetic and combination

    Ultimate Elongation, % min.

    Natural Rubber

    Synthetic and combination

    Shoredurometer, Type A

    Compression set, percent of

    original deflection, max.

    Tensile strength after aging,

    percent of original tensile

    strength, min. (Oxygen

    pressure test or air heat test)

    160 kg per sq cm150 kg per sq cm

    500%

    425%

    40-65

    20%

    80%

    (d) Welded Joints

    Where welded joints are provided, weld bell type

    joints may be used, or the bell may be cut back or afiller rod added so as to permit a field weld between

    the bell and spigot joint rings.

    (e) Pipe Design

    Design parameter shall be as follows :

    For Cement-Lined Steel Pipes : (Class 150)

    Nominal

    Diameter (mm)

    Steel Cylinders

    Thickness (mm)

    300 and under

    350 - 500

    600 - 700

    750 - 900

    1000 - 1200

    4.70

    6.00

    7.90

    9.50

    11.10

    VI -

  • 8/10/2019 Water Supply Project Specification

    9/33

    TECHNICAL SPECIFICATIONS

    Outside diameters of cement-lined, coal-tar coated

    and surface painted steel pipes

    Nominal

    Diameter (mm)

    Outside

    Diameter (mm)100

    150

    200

    250

    300

    350

    400

    450

    500600

    700

    750

    800

    900

    1000

    1100

    1200

    114.30

    168.30

    219.10

    273.10

    323.90

    391.00

    441.80

    506.60

    557.40661.60

    763.20

    817.80

    868.60

    970.20

    1075.00

    1176.60

    1278.20

    (f) Lining

    The mortar for pipe lining shall consist of one (1) part

    of cement to not more than three (3) parts of sand by

    weight and shall develop a compressive strength of

    not less than 175m kg per sq cm at 28 days. The

    cement mortar lining shall be applied by the results.

    The process used in the application of the lining shall

    produce a smooth dense durable surface, free frompockets, voids, over-sanded areas, blisters, and

    excessively cracked areas. Except where otherwise

    specified or shown, lining thickness shall be as

    follows, with a tolerance of plus or minus twenty-five

    percent (25%).

    Nominal

    Diameter (mm)

    Steel Cylinders

    Thickness (mm)

    under 300 mm300 - 400

    6 mm13 mm

    VI -

  • 8/10/2019 Water Supply Project Specification

    10/33

    TECHNICAL SPECIFICATIONS

    over 400 mm 20 mm

    (g) Hydrostatic Pressure Test

    All steel cylinders shall be subjected to a hydrostatic

    pressure test which stresses the steel to 1760 kg per sq

    cm. While under pressure test, all welds shall be

    thoroughly inspected, and all parts showing leakage

    shall be marked. Cylinders which show any leakage

    under test shall be rewelded at the point of leakage,

    and subjected to another hydrostatic test.

    (h) Specials

    (1) Definition

    Specials are defined as bends, reducers, wyes,

    tees, crosses, outlets, and manifolds, wherever

    located, and all piping above ground or in

    structures.

    (2) Design

    Except as otherwise provided herein , materials,

    fabrication and shop testing of straight pipe shallconform with the "AWWA Standard for Steel

    Water Pipe, 6 Inches and Larger" (AWWA C-

    200). Minimum plate thickness of specials shall

    be computed using the following formula :

    T =

    where :

    T = plate thickness in inches

    D = outside diameter of steel cylinder

    in inches

    P = design pressure, psi

    S = factor of safety 2.50

    Y = specified yield point of steel in

    psi

    but in case shall the design stress (Y/S) exceed

    930 kg per sq cm nor shall plate thickness be less

    than the following :

    VI - 10

  • 8/10/2019 Water Supply Project Specification

    11/33

    TECHNICAL SPECIFICATIONS

    Nominal PipeDiameter (mm)

    Pipe Manifolds

    Piping Above

    Ground Piping in

    Structures Fittingsabove Ground (mm)

    Fittings

    UndergroundInstallation (mm)

    300 and under

    350 - 500

    600 - 700

    750 - 900

    1000 - 1200

    4.70 mm

    6.00 mm

    7.90 mm

    9.50 mm

    11.10 mm

    4.70 mm

    4.70 mm

    6.00 mm

    7.90 mm

    9.50 mm

    (3) Outlets, Tees, Wyes, and Crosses

    Outlets shall be welded to the steel cylinder of

    the pipe. Following this, all outlets larger than

    50 mm in diameter shall be provided with steel

    reinforcing saddles, wrapper plates, or crotch

    plates, or they shall be fabricated in their

    entirety of steel plates having a thickness equal

    to the sum of the required thickness of the

    saddle or wrapper plate, plus the cylinder to

    which they are attached.

    Such saddles or wrapper plates shall be of steel

    plate, at least 1.25 times the thickness of the pipe

    cylinder to which the outlet is attached. The

    total cross-sectional area of the saddle or

    wrapper plate shall be at least 1.25 times the

    product of the cut-out length and the plate

    thickness of the pipe, as determined in the

    equation above. The overall width of the saddle

    or wrapper plate shall not be more than 2 times,

    and not less than 1.67 times, the maximum

    dimensions of the cut-out. Outlets 300 mm and

    smaller may be fabricated from schedule 30 or

    heavier steel pipe in the standard outside

    diameters, i.e., 324 mm, 273 mm, 219 mm, 169

    mm, and 144 mm.

    Where required, crotch plates shall be provided,

    and designed according to the nomographmethod described in AWWA Manual M-11,

    VI - 11

  • 8/10/2019 Water Supply Project Specification

    12/33

    TECHNICAL SPECIFICATIONS

    Section 19.5, or AWWA Journal, Vol. 47, No. 6,

    June 1955, pp. 617 to 623.

    Tees, wyes, and crosses shall either be fabricated

    of steel plate or provided with wrapper plates orwith crotch plates. The thickness of the plate or

    plates, exclusive of crotch plates. The thickness

    of the plate or plates, exclusive of crotch plates,

    being such that when multiplied by the diameter

    of the opening, shall not be less than 1.25 times

    the cross-sectional area of the cutout. Where

    tees, wyes and crosses are fabricated from steel

    plate with out wrapper plates, the thickness of

    the plate shall not be less than 2.5 times therequired plate thickness as shown in the

    preceding table for such fittings.

    (4) Dimensions

    Unless otherwise shown, dimensions of specials

    shall conform with "AWWA Standard for

    Dimensions for Steel Water Pipe Fittings

    (AWWA C-208) for Service in Transmission and

    Distribution Systems."

    (5) Steel Welding Fittings

    Steel Welding fittings shall conform with ASTM

    A234.

    (6) Ends for Mechanical Type Couplings

    Except as otherwise provided herein, where

    mechanical-type couplings are indicated, theends of the pipe shall be banded with Type C

    collared ends, using double fillet welds. Where

    pipe 300 mm (12 in) and smaller is furnished in

    standard schedule thickness equals or exceeds

    the coupling manufacturer's minimum wall

    thickness, the pipe ends may be grooved.

    (7) Flanges

    VI - 12

  • 8/10/2019 Water Supply Project Specification

    13/33

    TECHNICAL SPECIFICATIONS

    Flanges shall have flat or raised faces. Flanges

    shall be attached with bolt holes straddling the

    vertical axis of the pipe.

    (8) Shop Testing

    Upon completion of welding, but before lining

    and coating, each special shall be bulkheaded

    and tested under a hydrostatic pressure of not

    less than one and one-half (1-1/2) times the

    pressure for which the pipe has been designed;

    provided, however, that if straight pipe used in

    fabricating the special has been previously tested

    in accordance with sub-clause (h)(2) herein, the

    circumferential welds may be tested by a dye

    penetration process using Turco-Dy-Check or

    approved equal with no further hydrostatic tests.

    Any pinholes or porous welds, which may be

    reveled by the test, shall be chipped out ad

    rewelded, and the special retested.

    (9) Lining

    All requirements pertaining to thickness,application and curing of lining specified for

    straight pipe shall apply to specials, with the

    following provisions.. If the special cannot be

    lined centrifugally, it shall be lined by hand. In

    such case, the lining shall be reinforced with 50

    mm x 100 mm No. 12 welded wire fabric

    positioned approximately in the centers shall

    extend circumferentially around the pipe with

    the fabric securely fastened to the pipe. Splicesshall be lapped 100 mm, and the free ends tied

    or looped to assure continuity.

    (10)Coating

    All requirements pertaining to coating specified

    for straight pipe shall apply to specials. Unless

    otherwise shown, the coating on the buried

    portion of a pipe section passing through a

    structure wall shall extend 50 mm inside the

    VI - 13

  • 8/10/2019 Water Supply Project Specification

    14/33

    TECHNICAL SPECIFICATIONS

    outer surface of the wall or to the wall flange, if

    one is indicated. Pipe above ground or in

    structure shall be field-painted, as specified in

    Painting and Coatings.

    (11)Marking

    A mark indicating the true vertical axis of the

    special shall be placed on the top and bottom of

    the special.

    (i) Internal Bracing

    (1) General

    Pipe sections 450 mm and larger shall be braced

    internally as soon as practicable after the cement

    mortar lining has been applied.

    (2) 450 mm through 750 mm Diameter Pipe

    Pipe sections shall be braced within 300 mm of

    each end with two 2 x 4s wedged in the pipe at

    right angles to each other.

    (3) Larger than 750 mm through 1200 mm Diameter

    Pipe

    Pipe sections shall be braced within 300 mm of

    each end, and at intervals not exceeding 3 m

    along the pipe length, with two 2 x 4s wedged in

    the pipe at right angles to each other.

    (4) Larger than 1200 mm Diameter Pipe

    Pipe sections shall be braced within 300 mm of

    each and, and at intervals not exceeding 3 m

    along the pipe length, with two 4 x 4s wedged in

    the pipe at right angles.

    (j) Cleanliness of Pipe

    The interior of each pipe sections and special shall be

    clean, and free of foreign materials when they aredelivered to the site of the work.

    VI - 14

  • 8/10/2019 Water Supply Project Specification

    15/33

    TECHNICAL SPECIFICATIONS

    (k) Transport and Handling

    Coal tar enamel coated steel pipe shall be transported

    and handled as specified herein. Any pipe section

    that becomes damaged as a result of impropertransporting, handling or stockpiling shall be

    repaired to the satisfaction of the Engineer. Where

    damaged areas are extensive or where, in the

    Engineer's opinion, field repairs are not practicable,

    the Engineer may order the Contractor to remove the

    damaged pipe section from the site of the work and

    replace it with a new section.

    Transporting and handling of enamel coated pipe

    shall conform with the requirements of AWWA

    Standard C-203. After enamel coated pipe has been

    delivered to the trench site, any section of pipe which,

    in the Engineer's opinion, indicates possible coating

    damage, shall be spark tested by the Contractor, in the

    presence of the Engineer, at the expense of the

    Contractor. Any damaged areas in the enamel

    coating shall be field-repaired using hot coal tar

    enamel or the section of pipe replaced as specified

    above.

    (l) Installation of Piping

    (1) General

    Unless otherwise provided, the Contractor shall

    furnish and install all pipes, specials, fittings,

    closure pieces, valves, supports, bolts, nuts,

    gaskets, jointing materials, and all otherappurtenances as shown and as required to

    provide a complete and workable installation.

    Where pipe support details are shown, supports

    shall conform thereto, and shall be placed as

    indicated; provided, that the support for all

    exposed piping shall be complete and adequate,

    regardless of whether or not supporting devices

    are specifically shown. Concrete thrust blocks,

    anchor blocks, or welded joints shall beprovided at all junctions, changes in direction

    VI - 15

  • 8/10/2019 Water Supply Project Specification

    16/33

    TECHNICAL SPECIFICATIONS

    exceeding 11-1/2 degrees or where otherwise

    shown. At all times when the work of installing

    pipe is not in progress, all openings into the pipe

    and the ends of the pipe in trenches or structures

    shall be kept tightly closed to prevent entrance ofanimals and foreign materials. The Contractor

    shall take all necessary precautions to prevent

    the pipe from floating due to water entering the

    trench from any source, and shall assume full

    responsibility for any damage due to this cause,

    and shall, at his own expense, restore and

    replace the pipe to its specified condition and

    grade, if it is displaced due to floating. The

    Contractor shall maintain the inside of the pipefree from foreign material, and in a clean and

    sanitary condition until its acceptance by the

    Engineer.

    (2) Laying

    Trenches shall be in a reasonably dry condition

    when the pipe is laid. Necessary facilities,

    including slings, shall be provided for lowering

    and properly placing the pipe section in the

    trench without damage. The pipe sections shall

    be laid to the line and grade as shown, and they

    shall be closely jointed to form a smooth flow

    line. Immediately before placing each section of

    pipe in final position for jointing, the bedding

    for the pipe shall be checked for firmness and

    uniformity of surface.

    (3) Rubber and Gasket Joints

    The rubber gasket joints shall be made by

    properly lubricating the rubber gasket with a

    suitable vegetable compound soap before it is

    placed in the groove, with care taken to equalize

    the stress in the gasket around the circumference

    of the joint. The gasket shall not be twisted,

    rolled, cut, crimped,, or otherwise injured or

    forced out of position during the closure of thejoint. A "feeler" gage shall be used to check the

    VI - 16

  • 8/10/2019 Water Supply Project Specification

    17/33

    TECHNICAL SPECIFICATIONS

    position of the rubber gasket after the joint has

    been telescoped.

    (4) Field-Welded Joints

    Field welding of pipe joints shall conform with

    the requirements of the "AWWA Standards for

    Field Welding of Steel Water Pipe Joints"

    (AWWA C206). Prior to welding, the joint shall

    be made up in accordance with Subsection (l)(3)

    and(l)(5) herein. Such joints shall be inspected

    and approved by the Engineer before any

    protective coating is placed around the outside

    of the joint.

    (5) Protective Coatings

    With pipe smaller than 450 mm in diameter,

    before the spigot is inserted into the bell, the bell

    shall be daubed with mortar containing one (1)

    part of cement to three (3) parts of sand by

    weight. The spigot end then shall be forced to

    the bottom of the bell, and excess mortar on the

    inside of joint hall be swabbed out. With pipe450 mm in diameter and larger, joints shall be

    pointed on the inside with mortar, as specified

    for field joints in AWWA Standard C205, after

    the backfill has been placed. After coated pipe

    section have been joined, the coating shall be

    made continuous across the joints, forming a

    coating equivalent to the factory-applied coating

    of adjacent pipe sections. Coating and spark

    testing of coal tar enamel field joints shall be asspecified in AWWA Standard C203, and shall be

    performed at the expenses of the Contractor.

    The use of coal tar tape to provide the required

    protection shall not be permitted.

    After the pipe sections on cement mortar coated

    pipe have been joined, but before backfilling has

    been completed, the outside annular space

    between pipe sections shall be completely filledwith grout. The grout shall be poured in such a

    VI - 17

  • 8/10/2019 Water Supply Project Specification

    18/33

    TECHNICAL SPECIFICATIONS

    manner that all exposed portions of metal joints

    shall be completely protected with cement

    mortar. Grout shall consist of one (1) part of

    cement to three (3) parts of sand, by weight, and

    shall be sufficiently fluid to permit it to bepoured into the joint space. Exterior field joints

    shall be coated with cement mortar, retained by

    suitable forms so as to bridge the joint. The

    mortar shall be compacted within the form to

    produce dense coating without voids. The joint

    coating shall be kept moist until the backfill is

    placed.

    (6) Butt-straps

    Where a butt-strap is used, both the interior and

    exterior surfaces of the but-strap shall be given a

    coating equivalent to the factory-applied coating

    of the adjoining pipe sections. Mortar coating

    shall be reinforced with wire mesh. The mortar

    lining shall be reinforced with wire mesh,

    where the exposed length of the butt-strap, as

    measured between the ends of the connected

    pipe section, exceeds 100 mm. Butt-straps used

    as closure pieces shall be provided with hand

    holes for repair of the lining.

    6.3.3.3 Small Steel Pipe

    Unless otherwise shown, galvanized steel pipe, sizes less

    than 100 mm in diameter and smaller, shall conform with

    the requirements of the "Specifications for Black and Hot-

    Dipped Zinc Coated (Galvanized) Welded and SeamlessSteel Pipe for Ordinary Uses" (ASTM A-120), and shall be

    Schedule 40. Galvanized steel pipe shall not be cement

    mortar-lined, unless otherwise specified. Fittings for

    galvanized steel pipe shall be of galvanized malleable iron,

    Galvanized and black steel pipe shall not be used for

    buried service, except where shown on the Drawings.

    Galvanized steel pipe for service connections shall be

    allowed only as specifically shown on the Drawings. Thepipe shall be wrapped with a 500 micron thick PVC tape to

    VI - 18

  • 8/10/2019 Water Supply Project Specification

    19/33

    TECHNICAL SPECIFICATIONS

    a total thickness of 1000 microns, with half width

    overlapping. PVC tape shall be applied in accordance with

    the manufacturer 's recommendations.

    6.3.3.4 PVC Pipes

    Polyvinyl chloride pipes shall conform to JIS K6742 and/or

    K6741, and be laid and jointed in accordance with the

    manufacturer's instructions and to the Engineer's

    satisfaction.

    After the pipes have been laid, they shall be left exposed,

    haunched or surrounded in concrete or covered with spoil

    as required on the Drawings. Where covering with spoil is

    done, care shall be taken to prevent damage due to largestone striking the pipe by removing large stones from the

    layer of spoil immediately against the pipe or by other

    means.

    6.3.3.5 Pressure and Leakage Testing

    (a) General

    The Contractor shall furnish all equipment, labor and

    material, including taps, valves, and bulkheads, as

    required, exclusive of water and water meter testing.

    The water and any water meter used for testing shall

    be furnished by the Employer, but the Contractor

    shall provide the facilities necessary to convey the

    water from the designated source to the points of use.

    All testing shall be done in the presence of the

    Engineer.

    (b) Pipeline Testing

    All pipelines shall be thoroughly flushed out with

    water prior to testing. The Contractor shall test the

    pipeline in section prior to permanent resurfacing

    after the trench is backfilled, but with joints exposed

    for examination, except in heavily traveled roadways.

    Maximum length of test sections shall be 500 metres

    for distribution mains and 1, 000 metres for

    transmission mains, unless otherwise approved by theEngineer. Where test sections are approved which

    VI - 19

  • 8/10/2019 Water Supply Project Specification

    20/33

    TECHNICAL SPECIFICATIONS

    exceed the above maximum lengths, the allowable

    leakage for the lengths in excess of the maximum

    allowable shall be reduced by fifty percent (50%).

    The pipeline shall not be filled with water until the

    following curing period have elapsed.

    Description

    Minimum

    Allowable Time

    1.

    2.

    3.

    Cement Mortar Linings

    Cement Mortar at Joints

    Concrete Thrust Block

    14 days

    8 hours

    a. Standard Cement

    b. High Early Strength Cement

    7 days

    39 hours

    The pipeline shall be prepared for testing by closing

    valves, when available, or by placing temporary

    bulkheads in the pipe and filling the line slowly with

    water. During the filling of the pipe, and before the

    application of the specified test pressure, all air shall

    be expelled from the pipeline. To accomplish this,

    taps shall be made, if necessary, at profits of highest

    elevation, and after completion of the test; and taps

    shall be tightly plugged, unless otherwise specified.After the line or section thereof has been completely

    filled, it shall be allowed to stand under a slight

    pressure for a minimum of forty-eight (48) hours, to

    allow the escape of air from any air pockets, and to

    allow the pipe or mortar to absorb as much water as

    possible.

    During this period, all exposed pipes, fittings, valves,

    hydrants, joints, coupling shall be examined for leaks.if found to be cracked or defective, they shall be

    removed and replaced by the Contractor with sound

    material at his own expense. The pipeline shall then

    be refilled, and all bulkheads, joints, and connections

    shall be examined for leaks. If any are found, these

    shall then be refilled, and all bulkheads, joints, and

    connections shall be examined for leaks. If any are

    found, these shall be stopped. The test shall consist of

    holding the test pressure on each section of the linefor a period of two (2) hours. The test pressure at the

    VI - 20

  • 8/10/2019 Water Supply Project Specification

    21/33

    TECHNICAL SPECIFICATIONS

    lowest point shall be 690 KPa (100 psi) or 1.0 MPa (150

    psi) according to the class of pipe installed, class 100

    or class 150, and as approved by the Engineer.

    Pressure gauges shall also be provided at all ends of

    the section tested. The water necessary to maintainthe pressure shall be measured through a meter or by

    other means satisfactory to the Engineer. The leakage

    shall consider the amount of water entering the

    pipeline during the two-hour test period. The

    allowable leakage for asbestos cement pipe shall not

    exceed the values listed in Table 1 of the "AWWA

    Standard for Installation of Asbestos Cement Pipe"

    (AWWA C-603), The allowable leakage for cast iron

    pipe or ductile iron pipe shall not exceed the valueslisted in Table 3 of the AWWA Standard for

    Installation of Cast Iron Water Main (AWWA C-600).

    All other types of pipes shall have an allowable

    leakage not exceeding 1.85 L/mm, (20 gal/in) of

    diameter of pipe per kilometer per day. Should any

    test of a section of pipeline disclose joint leakage

    greater than that permitted, the Contractor shall, at

    his own expense, locate and repair or replace the

    defective pipe, fitting, joint coupling, or otherappurtenance. The test shall then be repeated until

    the leakage is within the permitted allowance.

    Closure pieces between newly installed and existing

    mains shall be tested after the pipe has passed the

    pressure and leakage test specified above. The test

    shall include subjecting the joint to a pressure of 345

    KPa (50 psi) for a period of five (5) minutes, and

    visually checking for leakage. All visible leaks shallbe repaired by the Contractor at no expense to the

    Employer.

    6.3.4 Valves

    6.3.4.1 General

    The Contractor shall furnish and install all valves as

    specified herein, and as shown on the Drawings. All

    valves shall be new and of current manufacture.

    VI - 21

  • 8/10/2019 Water Supply Project Specification

    22/33

    TECHNICAL SPECIFICATIONS

    Flanged valves may be plain faced with serrated gasket

    surface or raised. Flanges of valves for water working

    pressure of 1.2 MPa (175 psi) or less shall be faced and

    drilled of 125-lb American Standard dimensions; flanges of

    valves for water working pressures greater than 1.2 MPa(175 psi) shall be faced and drilled to 250-lb American

    Standard dimensions.

    Each valve body shall be tested under a test pressure equal

    to twice its design water working pressure.

    All valves shall be provided with a exterior protective

    coating in accordance with the pertinent provisions of the

    Specifications.

    When the operating nut of a buried valve is located more

    than 1.5 metres below the ground surface, the Contractor

    shall provide and install in the valve box a steam

    extension. The bottom of the extension shall be securely

    fastened to the operating nut of the valve, and the top of

    the extension shall be centered in the valve box.

    The Contractor shall furnish a minimum of six (6) tee-

    handle valve keys of variable lengths, sufficient to permitoperation of all buried valves regardless of depth, by

    operators of average height working in normal position.

    Where the number of valves to be provided exceeds thirty

    (30) units, the Contractor shall provide one (1) valve key

    for every five (5) additional valves or a fraction thereof.

    Operating nut shall turn counter-clockwise to open.

    6.3.4.2 Gate Valves

    (a) Valves

    All valves shall conform with the "Standard Systems"

    (AWWA C509). Gate Valves, where the pipeline

    design pressure is 1.0 MPa (150 psi) or less, shall be

    designed for a minimum water working pressure of

    1.0 MPa (150 psi), and shall be cast iron bodied, with

    resilient seats applied to the body and gate. Disksshall be cast iron with bronze disc rings, and the seat

    VI - 22

  • 8/10/2019 Water Supply Project Specification

    23/33

  • 8/10/2019 Water Supply Project Specification

    24/33

    TECHNICAL SPECIFICATIONS

    tested with twice the specified rated pressure

    applied to one side of the gate and zero pressure

    on the other side. The test shall be made in each

    direct across the gate. Under this hydrostatic

    test, the Contractor may make special provisionsto prevent leakage past the seats. No part of the

    valve or gate shall be permanently deformed by

    the test.

    (5) Torque Test

    A prototype of each size shall be overtorqued in

    the closed and open positions, to demonstrate no

    direction of the valve stem or damage to the

    resilient seat as evidenced by failure to seal at

    rated pressure. The applied torque shall be 250

    ft-lb for 3 and 4 NRS valves, and 350 ft-lb for 6,

    8, 10, and 12 NRS valves (1.0 ft-lb = 0.736

    Newton-meter = 0.66 kg-m).

    (6) Leakage Test

    Two prototype valves of each size chosen by the

    Engineer to represent the extremes of seatcompression shall be fully opened and closed to

    a seal for 500 complete cycles with sufficient flow

    that the valve is at 200 psi pressure differential at

    the point of opening and closing. The valves

    shall be drop-tight under rated pressure

    differential applied alternately to each side of the

    gate after completion of the tests.

    (7) Pressure Test

    One prototype of each valve size shall be tested

    to 500 psi with the closure member in the open

    position. There shall be no rupture or cracking

    of the valve body, valve bonnet, or seal plate.

    Leakage at pressure-containing joints shall not

    be cause for failure of the test.

    6.3.4.3 Butterfly Valves

    (a) Valves

    VI - 24

  • 8/10/2019 Water Supply Project Specification

    25/33

    TECHNICAL SPECIFICATIONS

    Butterfly valves shall conform with the "AWWA

    Standard for Rubber -Seated Butterfly Valves"

    (AWWA C504) subject to the following requirements.

    Valves shall be of Class 150B and, unless otherwise

    specified, may either be short-bodied to long-bodied.Shaft seals shall be designed for use with standard

    split V-type packing or "O" ring seals. The valve ends

    shall be either flanged or of the wafer type, except

    where otherwise shown on the Drawings.

    (b) Operators

    Operators shall conform with the above-referenced

    AWWA Standard, subject to the following

    requirements: Valves shall be equipped with 50 mm

    square operating nuts or with handwheels 600 mm

    maximum diameter, as specified, and shall be

    provided with watertight gear housings.

    The Contractor shall furnish a written certification

    stating that the operator torque has been computed,

    and the operators have been sized to meet the full

    AWWA Class specified in Subsection (a) herein.

    (c) Testing Requirements

    (1) Performance Tests

    Each valve that has the operator directly on the

    valve shall be shop-operated three times from

    the fully closed to the fully opened position, and

    the reverse, under a no-flow condition, to

    demonstrate that the complete assembly is

    workable.

    (2) Leakage Tests

    Each valve shall be shop-tested for leaks in the

    closed position. The test shall be conducted

    with the body flanges in a horizontal plane.

    With the disc in the closed position, air pressure

    shall be supplied to the lower face of the disc for

    the full test duration as follows :

    VI - 25

  • 8/10/2019 Water Supply Project Specification

    26/33

  • 8/10/2019 Water Supply Project Specification

    27/33

  • 8/10/2019 Water Supply Project Specification

    28/33

    TECHNICAL SPECIFICATIONS

    6.3.4.5 Air Vacuum and Air Release Valves

    Air vacuum and air release valves shall have threaded

    connections. The bodies shall be of high-strength cast iron,

    and the float shall be of stainless steel. Float guidesbushings, lever pens and all other internal parts shall be

    constructed of stainless steel or bronze. Seat washers and

    gasket shall be of a material insuring water-tightness with

    a minimum of maintenance. Valves shall be designed for a

    water working pressure of not less than 1.0 MPa (150 psi).

    All valves shall be designed to automatically operate so

    that they will : (a) positively open under atmospheric

    pressure (as water drains from the body of the valve, it will

    allow air to flow into the pipe while it is being emptied);(b) positively close as water, under low head, fills the body

    of the valve ; (c) not blow-shut under high velocity air

    discharge; and (d) permit the escape of accumulated air

    under pressure while the pipe is in operation. The valves

    shall be either direct or lever operating.

    6.3.4.6 Air Vacuum Valves

    Air vacuum valves, of sizes up to and including 100 mm (4

    in) in diameter, shall have threaded connections except

    where otherwise shown on the Drawings. The bodies shall

    be of high strength cast iron, and the float shall be of

    stainless steel. All internal parts such as float guides,

    bushings, and baffle retaining screws, etc., shall be either

    stainless steel or bronze. Seat washers and gaskets shall be

    of a material insuring water tightness with a minimum of

    maintenance. Valves shall be designed for a water working

    pressure of not less than 1.0 MPa (150 psi). All valves shall

    be designed to automatically operate so that they will : (a)

    positively open under atmospheric pressure (as water

    drains from the body of the valve, it will allow air to flow

    into the pipe while it is being emptied; and (b) positively

    close as water, under low head, fills the body of the valve;

    (c) not blow shut under high velocity discharge.

    6.3.4.7 Air Release Valves

    Air release valves, up to an including 100 mm (4 in.) indiameter, shall have threaded connections, except where

    VI - 28

  • 8/10/2019 Water Supply Project Specification

    29/33

    TECHNICAL SPECIFICATIONS

    otherwise shown on the Drawings, and shall be designed

    for a water working pressure of 1.0 MPa (150 psi). The

    body shall be of high strength cast iron, and the float shall

    be of stainless steel. All internal parts, except the seat,

    shall be of stainless steel or bronze. The seat shall be ofmaterial insuring water tightness with a minimum of

    maintenance. The valves shall be designed to

    automatically permit the escape of accumulated air under

    pressure while the pipe is in operation. The valves shall be

    either direct or lever operating.

    6.3.4.8 Float Valves

    Float valves shall be as shown on the Drawings.

    6.3.4.9 Miscellaneous Small Valves

    Valves 50 mm and smaller, unless otherwise specified shall

    be all bronze or brass with threaded connections designed

    for a water working pressure not less than 1.0 MPa (150

    psi).

    6.3.4.10 Plug Valves

    Plug valves shall be lubricated 50 mm semi-steel

    straightway valves with a working pressure of 175 lb. The

    valves shall be wrench-operated, two-bolt cover type with

    screwed ends. A complete locking device assembly shall

    be provided for each valve, where indicated on the

    Drawings.

    6.3.4.11 Pressure Reducing Valves

    The pressure reducing valve shall be of the diaphragmtype, equipped with a pilot spring to provide a range of

    downstream pressure settings. the pressure reducing

    valve shall be designed for a minimum water working

    pressure of 1.0 MPa (150 psi), and shall be factory tested

    under a hydrostatic pressure of at least 2.0 MPa (300 psi).

    The valve body and cover shall be cast iron, meeting the

    requirements of ASTM A48. The valve shall have flanged

    ends, and the valve disc shall be non-metallic and

    renewable. The main valve trim shall be of bronze, asspecified in ASTM Specification B62, and the valve seat

    VI - 29

  • 8/10/2019 Water Supply Project Specification

    30/33

    TECHNICAL SPECIFICATIONS

    shall be of brass, with type 18-8 stainless steel trim. The

    diaphragm shall be of heavily reinforced synthetic rubber,

    and shall be fully supported by the valve body. The valve

    shall be coated in accordance with the pertinent provisions

    of the Specifications.

    6.3.4.12 Pressure Relief Valves

    The pressure relief valve shall be of the diaphragm type.

    The disc shall be non-metallic and renewable, and the

    valve seat shall be replaceable. The main valve trim shall

    be of bronze, conforming with ASTM Specification B62.

    The pilot control shall be fully supported by the valve

    body. The valve shall be coated in accordance with the

    pertinent provisions of the Specifications.

    6.3.4.13 Fire Protection System

    (a) Fire Hydrant Heads

    Fire hydrant heads shall be designed for a minimum

    pressure of 1.0 MPa (150 psi) and have a 150 mm (6

    in) flanged inlet, a 100 mm (4 in) streamer hose

    outlets shall have hose caps and chains. Fire hydrantheads shall have a heavy duty body of bronze

    conforming with ASTM Specification B-62 and shall

    be cast-iron body in accordance with AWWA

    Standard for Wet-Barrel Fire Hydrants (AWWA C503)

    with bronze working parts. The stem shall be

    provided with at least two (2) O-rings. Hydrant

    valves shall open counter-clockwise. Burys for the

    hydrants may be a commercial product or locally

    fabricated.

    (b) Wrenches

    The Contractor shall provide three (3) sets of

    pentagon spanner wrenches that will operate all

    valves specified.

    VI - 30

  • 8/10/2019 Water Supply Project Specification

    31/33

    TECHNICAL SPECIFICATIONS

    6.3.5 Welding

    All welding shall be done either manually by the shielded

    metallic arc process or automatically by the shielded arc or

    submerged arc method.

    The Contractor shall submit a welding procedure for the

    approval of the Engineer in the same manner as the drawings.

    After the welding procedure has been approved, the Contractor

    shall record it on a special drawing, which shall thereupon

    become one of the drawings of the Contract. Weld sizes and

    types shall be shown on all Contractor's drawings where

    welding is required.

    Plates to be joined be welding shall be accurately cut to size androlled by pressure to the proper curvature, which shall be

    continuous from the edge. Flattening the curvature along the

    edges with correction by blows shall not be allowed. The

    dimensions and shape of the edges to be joined shall be such as

    to allow thorough fusion and complete penetration, as

    necessary, and the edges of plates shall be properly formed to

    accommodate the various welding conditions. The surfaces of

    the plates for a distance of 25 mm from the edge to be welded

    shall be thoroughly cleaned of all rust, grease and scale, tobright metal.

    Qualification of Welding Procedure

    The technique of welding employed, the appearance and

    quality of the welds made, and the methods used in correcting

    defective work, shall conform to the American Welding Society

    (AWS) Standard D.I.I., or other approved equivalent standard.

    Qualification of Welders and Welding Operators

    All welders and welding operators to be assigned to the works

    shall have passed a qualification test, within the preceding six

    months, for Welders and Welding Operators, in accordance

    with JIS Z 3801 or equivalent. The Contractor shall furnish the

    Engineer with three (3) certified copies of report of the results of

    physical test of specimens welded in the qualification tests. If,

    in the opinion of the Engineer, the work of any welder at any

    time appears questionable he shall be required to pass the

    VI - 31

  • 8/10/2019 Water Supply Project Specification

    32/33

    TECHNICAL SPECIFICATIONS

    appropriate re-qualification test. All costs of qualification tests

    shall be borne by the Contractor.

    Welding Electrodes

    The welding electrodes shall conform to JIS Z 3211 or 3212, low

    hydrogen type covering or equivalent.

    Stainless type weld metal, where used in the water passages for

    protection against pitting, shall be of chromium nickel steel.

    The type, chemical composition for this purpose shall be

    subject to approval of the Engineer.

    6.3.6 Protection, Cleaning and Painting

    The following surfaces shall not be painted ;

    (a) Surface which will be buried in concrete.

    (b) Parts made of stainless steel, bronze or brass.

    (c) Surfaces in rolling or sliding contact.

    (d)Surfaces such as gear teeth.

    (e) Wire ropes.

    All machined parts of bearing surfaces shall be cleaned and

    protected from corrosion before leaving the manufacturer's

    shop, by the application of an approved rust preventive

    compound or a peelable plastic film. Where the latter is

    impracticable, such parts shall be heavily covered with high

    melting point grease or other approved materials. Before

    commencement of erection such parts shall be cleaned with

    solvent and lapped or polished bright. The Contractor shall

    supply the materials necessary for each cleaning.

    All parts, other than machined parts, which shall be exposed

    after erection shall be thoroughly cleaned and given at least

    three (3) coats of best quality approved primer and at least two

    (2) coats of best quality approved finish paint before leaving the

    manufacturer's shop. The Contractor shall perform to the

    equipment touch-up painting at the site after erection, except

    such apparatus as panels and instruments, which shall be finish

    painted under approved procedures before shipment. The

    Contractor shall supply paint materials and necessary tools,

    which are used at the Site, for the Plant.

    VI - 32

  • 8/10/2019 Water Supply Project Specification

    33/33

    TECHNICAL SPECIFICATIONS

    Primer shall be applied to surfaces in accordance with the paint

    manufacturer's instructions. The surfaces shall be wiped clean

    immediately prior to applying the paint. The primer and finish

    coats of paint shall be applied using the methods and

    equipment recommended by the manufacturer. The paintsystem selected shall have a proven life expectancy of not less

    than five (5) years in the atmosphere prevailing at the Site.

    The internal surface of all pipes shall be cleaned out by

    approved methods before installation and again prior to

    commissioning, to ensure freedom from dirt, rust, scale,

    welding slag, etc. All exposed pipes shall be colour coded for

    identification after erection is completed. The code system

    shall be approved by the Engineer.

    The final colour of all equipment shall be approved by the

    Engineer but the Contractor shall propose a colour scheme for

    the equipment and shall submit colour chips or paint samples.

    A colour chip shall be included with the approved colour

    schedule, for each type of finish to be applied at the Site.