Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Please sign in at the front desk and provide your contact
information if you would like to receive project updates.
We invite you to walk around and look at the displays.
If you have questions or comments, please ask one of our
representatives or fill out a comment form and we’ll be in touch.
Thank you for attending!
Welcome to our Open House!
Background
• BluEarth acquired the Hand Hills Wind Project from Joss Wind Power Inc. in the fall of 2012.
•On August 31, 2012 after several years of study, including wind resource analysis,
environmental and heritage studies and assessments, public and agency consultation
and turbine siting, the Hand Hills Wind Project received Alberta Utilities Commission
approval to construct and operate.
• Since receiving the approval, BluEarth has been consulting with stakeholders, meeting
with the involved municipalities and completing technical and environmental studies.
• Technical studies and major advancements in wind turbine technology have led us to
select a new turbine for the project.
• BluEarth will be filing an amendment to our approved Alberta Utilities Commission
application in June 2017 to reflect the changes to the turbines.
Development work on the Hand Hills Wind Project has been underway since 2007.
Hand Hills Wind Project
Delia
Township Road 304
Highway 9
Hanna
Starland County
Special AreasNo. 2
Township Road 300
High
way
851
Rang
e Ro
ad 16
4
Proposed TurbineProposed Project LandsRoadHighwayRailroadProperty LineMunicipal Boundary
LEGEND
Project Description • Facility size: up to 78.2 MW capacity of
renewable power
•Number of turbines: up to 34 turbines
• 34.5-kilovolt electrical collector system and
fibre-optic cable
•New ATCO transmission line will connect
the new Highland 572S substation to the
Alberta electricity grid at Coyote Lake 963S
substation, 13 km south of the project
• Access roads, temporary construction roads,
and an operations and maintenance building
Preliminary layout
Located approximately 28 km northeast of Drumheller, Alberta and 3 km south of Delia, Alberta
Hand Hills Wind Project
Hand Hills Wind Project
Environmental Considerations
Studies planned or underway during 2017 will assess:
• Spring and Fall Bird Migration
• Spring and Fall Bat Migration
• Breeding Birds
•Nesting Raptors
• Sensitive Species (e.g., Sharp-tailed Grouse,
Burrowing Owl and Amphibians)
•Wetlands
• Listed Plants
• Habitat Mapping
Results of the 2017 environmental surveys will be
provided to Alberta Environment and Parks for their
review and comment.
The AUC Power Plant application will also consist of:
• An Environmental Evaluation to outline the site
conditions and potential Project impacts on the
environment
• Environmental Protection Plan to provide
mitigations to reduce potential environmental
impacts
•Noise Impact Assessment to assess predicted
noise levels at residences to ensure that the
Project does not cause noise level limits to be
exceeded
As a condition of the Alberta Utilities Commission (AUC) permit, and to update our knowledge of the environmental conditions at the site, BluEarth has consulted with Alberta Environment and Parks and is conducting various environmental studies in 2017.
Hand Hills Wind Project
SoundWind energy projects must meet the detailed Alberta Utilities Commission (AUC) regulatory requirements for noise control
Detailed noise modelling
is undertaken to ensure
the AUC sound level
requirements of 40 dBA
(night time) are met at
all residences. The noise
modelling considers:
• Topography (hills and
slopes);
• Ground cover (trees, water,
grass); and
• Existing noise sources
(oil & gas infrastructure,
highways).
Studies of the noise
conditions within the Hand
Hills Wind Project area are an
important factor in selecting
the final turbines for the
Project.
* Permissible Sound Level (PSL) includes sound contribution from ambient (i.e., background) noise, other regulated facilities (e.g., oil
and gas infrastructure, power/utilities infrastructure), and any newly proposed regulated facilities (i.e., the Project). Nighttime PSL at
receptors in rural environments is 40 dBA (AUC – Rule 012 Noise Control)
Project Benefits
• Employment – temporary jobs during construction (approximately 100,000 person
hours) and permanent jobs associated with the operations and maintenance of the
Project (4 to 5 full-time positions).
•New Investment – in the form of local services and supplies such as infrastructure
improvements, fuel, accommodation, meals and supplies for employees, construction
personnel, and contractors who will spend time in the local communities.
• Landowners and Community – wind turbines are compatible with other land uses,
such as farming, and can serve as a financial boost for rural economic development.
•Municipal Tax Revenues – municipal taxes paid by wind companies to rural
communities can be important, and the project does not increase demand on municipal
services or public works such as sewer and water upgrades.
• Clean Energy – wind energy provides societal benefits by offsetting harmful emissions
such as carbon dioxide, oxides of nitrogen, and sulphur dioxides that are created
through conventional, thermal power generation.
What are the benefits of wind development?
Hand Hills Wind Project
Hand Hills Wind Project
Project Schedule
Application for Amendment Approval to Alberta
Utilities Commission (AUC)June 2017
AUC & Municipal Development Permit Approvals September 2017
Alberta Electric System Operator Renewable
Energy Program Contract AwardedDecember 2017
Project Financing & Procurement Commencement January 2018
Earliest Start of Project Construction June 2018
Expected Commercial Operation December 2019
Hand Hills Wind Project
Headquartered in Calgary, BluEarth Renewables is a private independent renewable
power producer, focused on the acquisition, development, construction and
operation of wind, water, and solar projects. BluEarth’s mission is to be the Canadian
renewable energy leader by developing, building, and operating a portfolio that
optimizes people, planet, and profit. BluEarth believes it has the power to change the futureTM by demonstrating how to be sustainable and profitable, leaving the world a
better place. For more information, visit bluearth.ca.
BluEarth Renewables
234
6
Bull Creek Wind FacilityNE of Provost, AlbertaConstructed in 2015
Bow Lake Wind FacilityNW of Sault Ste Marie, OntarioOperational in 2015
Solar
Hydro
Development
Pending Acquisition
Wind
BluEarth has 18 operating power generation facilities
Alberta Climate Leadership PlanElectricity generation is the second
largest source of emissions in
Alberta, responsible for 17%, or
45 megatonnes of greenhouse
gas emissions in 2014. Coal fired
generation represents 85% of
total emissions from the electricity
sector.
The Alberta government is
currently looking for opportunities
to reduce emissions. They
have committed to increasing
renewable energy generation to
30% by 2030 through investments
in wind, solar and hydroelectric
technologies.
BluEarth intends to bid the project
into the Renewable Energy
Program (REP) process, which
would award long-term generation
contracts for wind energy projects.
The REP is a competitive process
based on power price, so it will
encourage competition among
developers that will ultimately
result in lower power prices from
renewable energy projects.
Hand Hills Wind Project
!b
Township Road 304
Township Road 300
Highway 9
Hig
hway
851
Map17-0242 - Hand Hills - Vantage Point 1 V2
0 2 4 6Kilometres
±
±
Original Photograph
Photomontage
Delia
Hand HillsWind Project
Note: This photomontage is a general visualsimulation of the proposed wind turbines. Thefinal layout and design is subject to change.Date: May 31, 2017Photo Taken: May 25, 2017Projection: NAD 1983 UTM Zone 12NSources: AltaLIS, Natural Resources Canada.
Photograph and Site Location
Index Map
0 500 1,000 1,500Metres
PHOTOMONTAGE OFPROPOSED
WIND TURBINES FROMVANTAGE POINT 1
SOUTHEAST OF SITE
Distance to NearestInfrastructure: 3.8km
Township Road 300
Ran
ge R
oad
164
Close-up of Turbine Location
Legend
Wooded Area
Waterbody
Road
Project Location
Photograph Viewshed
Proposed Wind Turbine
b Camera Location
!b
Hig
hway
851
Highway 9
Township Road 300
Township Road 304
Map17-0242 - Hand Hills - Vantage Point 2 V2
0 2 4 6Kilometres
±
±
Original Photograph
Photomontage
Delia
Hand HillsWind Project
Note: This photomontage is a general visualsimulation of the proposed wind turbines. Thefinal layout and design is subject to change.Date: May 31, 2017Photo Taken: May 25, 2017Projection: NAD 1983 UTM Zone 12NSources: AltaLIS, Natural Resources Canada.
Photograph and Site Location
Index Map
0 500 1,000 1,500Metres
PHOTOMONTAGE OFPROPOSED
WIND TURBINES FROMVANTAGE POINT 2
NORTHEAST OF SITE
Distance to NearestInfrastructure: 3.7km
Craigmyle
Close-up of Turbine Location
Highway 9
Ran
ge R
oad
164
Legend
Wooded Area
Waterbody
Road
Project Location
Photograph Viewshed
Proposed Wind Turbine
b Camera Location
!b
Township Road 300
Township Road 304
Highway 9
Hig
hway
851
Map17-0242 - Hand Hills - Vantage Point 3 V2
0 2 4 6Kilometres
±
±
Original Photograph
Photomontage
Delia
Hand HillsWind Project
Note: This photomontage is a general visualsimulation of the proposed wind turbines. Thefinal layout and design is subject to change.Date: May 31, 2017Photo Taken: May 25, 2017Projection: NAD 1983 UTM Zone 12NSources: AltaLIS, Natural Resources Canada.
Photograph and Site Location
Index Map
0 500 1,000 1,500Metres
PHOTOMONTAGE OFPROPOSED
WIND TURBINES FROMVANTAGE POINT 3
NORTHWEST OF SITE
Distance to NearestInfrastructure: 3.9km
Craigmyle
Close-up of Turbine Location
Hig
hway
851
Township Road 310Mai
n St
S
Legend
Wooded Area
Waterbody
Road
Project Location
Photograph Viewshed
Proposed Wind Turbine
b Camera Location
!b
Township Road 300
Township Road 304
Highway 9
Hig
hway
851
Map17-0242 - Hand Hills - Vantage Point 4 V2
0 2 4 6Kilometres
±
±
Original Photograph
Photomontage
Delia
Hand HillsWind Project
Note: This photomontage is a general visualsimulation of the proposed wind turbines. Thefinal layout and design is subject to change.Date: May 31, 2017Photo Taken: May 25, 2017Projection: NAD 1983 UTM Zone 12NSources: AltaLIS, Natural Resources Canada.
Photograph and Site Location
Index Map
0 500 1,000 1,500Metres
PHOTOMONTAGE OFPROPOSED
WIND TURBINES FROMVANTAGE POINT 4
WEST OF SITE
Distance to NearestInfrastructure: 2.2km
Craigmyle
Ran
ge R
oad
172
Township Road 304
Legend
Wooded Area
Waterbody
Road
Project Location
Photograph Viewshed
Proposed Wind Turbine
b Camera Location
!b
Township Road 304
Township Road 300
Highway 9
Hig
hway
851
Map17-0242 - Hand Hills - Vantage Point 5 V2
0 2 4 6Kilometres
±
±
Original Photograph
Photomontage
Delia
Hand HillsWind Project
Note: This photomontage is a general visualsimulation of the proposed wind turbines. Thefinal layout and design is subject to change.Date: May 31, 2017Photo Taken: May 25, 2017Projection: NAD 1983 UTM Zone 12NSources: AltaLIS, Natural Resources Canada.
Photograph and Site Location
Index Map
0 500 1,000 1,500Metres
PHOTOMONTAGE OFPROPOSED
WIND TURBINES FROMVANTAGE POINT 5
WEST OF SITE
Distance to NearestInfrastructure: 367 m
Craigmyle
Ran
ge R
oad
173
Township Road 304
Legend
Wooded Area
Waterbody
Road
Project Location
Photograph Viewshed
Proposed Wind Turbine
b Camera Location
!b
Township Road 304
Township Road 300
Highway 9
Hig
hway
851
Map17-0242 - Hand Hills - Vantage Point 6 V2
0 2 4 6Kilometres
±
±
Original Photograph
Photomontage
Delia
Hand HillsWind Project
Note: This photomontage is a general visualsimulation of the proposed wind turbines. Thefinal layout and design is subject to change.Date: May 31, 2017Photo Taken: May 25, 2017Projection: NAD 1983 UTM Zone 12NSources: AltaLIS, Natural Resources Canada.
Photograph and Site Location
Index Map
0 500 1,000 1,500Metres
PHOTOMONTAGE OFPROPOSED
WIND TURBINES FROMVANTAGE POINT 6
EAST OF SITE
Distance to nearestinfrastructure in FOV: 2.7km
Craigmyle
Close-up of Turbine Location
Township Road 304
Ran
ge R
oad
162
Legend
Wooded Area
Waterbody
Road
Project Location
Photograph Viewshed
Proposed Wind Turbine
b Camera Location
Hand Hills Wind Project
Thank you for attending!Please take the time to fill out a comment form and tell us what you think about
the project changes.
If you have any additional questions that were not answered, or if you have
further comments or feedback, please include it on the comment form and
provide us with your name and contact information.
Questions and comments can also be sent to the contact information provided
on the comment form.
Comments must be received by June 16, 2017 for consideration in our decision-
making process and for inclusion in any amendments filed with the Alberta
Utilities Commission.
For more information on BluEarth and the Hand Hills Wind Project, visit:
www.bluearth.ca/handhills
1-844-214-2578