What You Should Consider Before Paying for Site Material

Embed Size (px)

Citation preview

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    1/15

    {

    What you should

    consider before payingfor Site Material?

    Presented by Mazuan Lin

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    2/15

    DefinitionBuilding Contract Dictionary by Chappell, Marshall, Powell-Smith andCavender

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    3/15

    Contract Clauses

    Brief Description of RelevantContract Clauses

    Contract Clauses

    PAM

    1998

    PAM

    2006

    PWD

    203A

    KLCC

    2012Material delivered shall not beremoved from site

    14.1 14.1

    20.0 46.4

    Contractor shall be responsiblefor loss or damage to materialsand goods

    14.2 &14.4

    14.3

    When material paid it shall become a property of theclient/government

    14.2 &14.3

    14.2

    Warranty of title of goods andmaterials

    - 14.4 - -

    Value of Materials and Good(Default)

    100% 100% 90% ClientDiscretion

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    4/15

    a) Delivered to the Site;

    b) Intended for incorporation into the permanent works;

    c) Reasonably, properly and not prematurely brought to theSite;

    d) Adequately protected against weather and other casualties.

    In practice, i add up some more...

    e) The materials has been approved by relevant consultant (ifany);

    f) Attached with Payment Voucher, Receipt, Purchase Order(PO) and Delivery Order (DO);

    g) Verified by the resident architect/engineer or clerk of work.

    Criteria for Payment

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    5/15

    Clause 14.2 & 14.3 (PAM1998)Clause 14.2 (PAM 2006)Clause 20.0 (PWD 203A)

    All the above clause stated that when the materials paidunder Materials on Site, it shall be a property of theEmployer/Government.

    Question: Does those clauses bound the third party??i.e Supplier

    Reference made to a Legal MaximNEMODAT NON QUAD HABET

    A MAN CANNOT GIVE WHAT HE HAS NOT

    Who is the Owner???

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    6/15

    DAWBER WILLIAMSON V HUMBERSIDE COUNTYCOUNCIL

    Plaintif supplied slates to the site. The Main Contractorthen claimed it as an Unfixed Material. PP hasevaluated and included the Slate into IPC whichsubsequently being paid.

    Later on, the Main Contractor was declared bankruptand unable to made payment to the Plaintif.

    Plaintif came to site and claimed for the material butwas not allowed by the client.

    Court has then decided that the Plaintif have his rightsfor the slates as no payment received by him from theMain Contractor.

    Court Cases

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    7/15

    LIM CHUI LAI V ZENO

    Zeno is a supplier for concrete culvert to a contractornamed Ahmad.

    Later on Ahmads contract was terminated by MPPJ.

    Zeno contacted MPPJ saying that the payment has yetto be made by Ahmad. As such, the materials are still

    owned by Zeno.

    When Zeno went to site, it was found that Ahmad hadsold the materials to Lim.

    Court has decided that Ahmad has no right to sell thematerial to anyone. Ahmad is only a BAILEE underthe law as long as the payment has yet to be made toZeno. In that case, Zeno still hold the rights against thematerials.

    Court Cases

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    8/15

    Contractor needs to supply the material at siteor adjacent to the site. The contractor also need

    to be responsible on the suitableness of thematerial including damage and loss as well.

    TEST VALLEY BOROUGH COUNCIL VGREATER LONDON COUNCIL The court

    has decided that the contractor will providegood and proper materials. The material will beFIT FOR THE PURPOSE so far as that has beenmade known to the contractor.

    Court Cases

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    9/15

    In Young and Martin Ltd - v - MacManus Child Ltd(1969), the Contractor supplied defective roof tiles to

    the Employer under a house building contract. The brand and manufacturer for the tiles had beenspecified, but the Contractor had been allowed tomake his own contractual arrangements for supplyof the tiles from a sub-contractor. The House ofLords held that in the absence of any reliance therewas no room for the implication of a term as toreasonable fitness for purpose. However, theabsence of reliance did not displace the implicationof the term for satisfactory quality.

    Court Cases

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    10/15

    Contractor is required not to supply the material prematurelyfrom site activity. What is the meaning of prematurely?

    Refer case of STANLEY HUGH LEACH Court decided that theactual activity duration to become a basis and not according to

    contractors work program.

    This is crucial as to avoid any damage risk, early payment andshall be in accordance with SALES OF GOODS ACT.

    Court Cases

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    11/15

    What if we wereasked to payMaterial OFF

    Site????

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    12/15

    1. Check whether there is provision in CoC forMaterials off Site.

    2. Materials must be in BONDED store / fullyinsured

    3. Materials must be properly placed in store - awayfrom other materials/equipment

    4. Materials must be properly identified for thatparticular project/client

    5. The supplier/contractor/subcon must show provethat the ownership have been transferred to themfrom the manufacturers or whoever they boughtthose materials from.

    6. Consider asking for a parent company guaranteeor a performance bond in return for payment.

    Before you pay Materials offSite

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    13/15

    What iswrong with

    this MOS?

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    14/15

    1. Pay for MOS without looking at it.2. They just simply take the rates from BQ as a

    basis.3. Using Current Market Price instead of

    Market Price during tender.4. Payment made for premature items.5. Temporary works included.6. Never ask for Transfer of Ownership Proof.

    Dosa-dosa Seorang QS

  • 8/13/2019 What You Should Consider Before Paying for Site Material

    15/15

    With knowledge, certify Material On Site without fear......

    Treat contractor as partner to complete.... Not an enemy tocompete.

    Thank You!