20
Work Category Specification WCS31 Commissioning Operating and Accessing the Network Check this is the latest version before use Page No: 1 of 20 Approved by Work Practices Manager WCS31 Version 20 © Energex Limited 2015 23 July 2015 ABN 40 078 849 055 Table of Contents 1. SCOPE This Work Category Specification (WCS) documents the Service requirements for Commissioning, operating and access to the network. 1.1 GENERAL (a) As part of and in conjunction with this WCS, read WCS133 for the general standards and conditions that are relevant to, and are incorporated into this category of work. (b) For the avoidance of doubt, a breach of a general standard or condition contained in WCS133, and the requirements and conditions of WCS31,is a breach of the category of work specific WCS under which Services are being provided. 1.2 APPLICATION The application of Services includes, but is not limited to, the following functions: (a) Submissions of applications for Commissioning and switching via A4S computer system (including Reclose Block) [wherever practical] or alternatively Form 1056 for voltages up to 33 kV. (b) Acceptance and surrender of supporting control documents for distribution operational practices, for example permits, authorities and notices. (c) High Voltage (HV) live work works which do not energise or de-energise HV distribution electrical apparatus. (d) Undertake auto reclose disable / restore functions on non-telemeted Pole Mounted Reclosers (PMR). (e) Preparation and submission for approval of Low Voltage (LV) Switching Sheets (including Rate 2 street lighting). (f) Conducting approved LV switching (including Rate 2 street lighting). (g) Pre Commissioning Checks and post Commissioning Checks on HV and LV distribution electrical apparatus and connections. (h) Distribution of Interruption Notices. (i) Development of Commissioning programs. (j) Submission of all associated documents and test results. 2. AMENDMENT RECORD Version Change 20 Clause 1.1 – General.

Work Category Specification WCS31 - Energex€¦ · (iv) Energex Manual 00297 – Network Labelling and Signage Manual. (v) Energex Manual 00301 – Operating Practices Manual. (vi)

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 1 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Table of Contents

    1. SCOPE

    This Work Category Specification (WCS) documents the Service requirements for Commissioning, operating and access to the network.

    1.1 GENERAL

    (a) As part of and in conjunction with this WCS, read WCS133 for the general standards and conditions that are relevant to, and are incorporated into this category of work.

    (b) For the avoidance of doubt, a breach of a general standard or condition contained in WCS133, and the requirements and conditions of WCS31,is a breach of the category of work specific WCS under which Services are being provided.

    1.2 APPLICATION

    The application of Services includes, but is not limited to, the following functions:

    (a) Submissions of applications for Commissioning and switching via A4S computer system (including Reclose Block) [wherever practical] or alternatively Form 1056 for voltages up to 33 kV.

    (b) Acceptance and surrender of supporting control documents for distribution operational practices, for example permits, authorities and notices.

    (c) High Voltage (HV) live work works which do not energise or de-energise HV distribution electrical apparatus.

    (d) Undertake auto reclose disable / restore functions on non-telemeted Pole Mounted Reclosers (PMR).

    (e) Preparation and submission for approval of Low Voltage (LV) Switching Sheets (including Rate 2 street lighting).

    (f) Conducting approved LV switching (including Rate 2 street lighting).

    (g) Pre Commissioning Checks and post Commissioning Checks on HV and LV distribution electrical apparatus and connections.

    (h) Distribution of Interruption Notices.

    (i) Development of Commissioning programs.

    (j) Submission of all associated documents and test results.

    2. AMENDMENT RECORD

    Version Change

    20 Clause 1.1 – General.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 2 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    3. AIMS / OBJECTIVES

    The aim of this WCS is to ensure:

    (a) The overall aims and objectives detailed in WCS133, Section 3 - Aims and Objectives, are met by the application of procedures herein.

    (b) The additional category of work specific aims and objectives below are met:

    (i) Switching operations are consistent with Energex requirements and computing systems.

    (ii) Compliance with Queensland Electricity Entity Procedures for Safe Access to High Voltage Electrical Apparatus (SAHV) and Manual 00301.

    (iii) Compliance with the requirements for Customer notification of Planned Interruptions of electricity supply.

    4. COMPETENCIES, TRAINING AND QUALIFICATIONS

    (a) Service Providers / Operators / subcontractors performing Services are suitable licensed and trained in accordance with WCS133, Section 4 - Competencies, Training and Qualifications and Table 1 below.

    (b) Table 1 specifies the Energex Competencies / Authorisations (or combinations thereof) that are Energex requirements to be held by Operators.

    Table 1 – Operator Competencies

    CAMS Code Competency Description Operator Requirements

    Operators hold the following competencies:

    A OILS Oil Spill Management (Note 1) MO

    A VIRO General Environmental Awareness (Note 1) R

    A WEED Declared Plants Management Awareness (Note 1) MO

    U EO Electricity Officer R

    U GCI Generic Contractor Induction R

    U OHAW Overhead Safety Awareness R

    - Authorised Person (as defined in the Electricity Safety Regulation 2013) R

    Operators hold the following competencies when the relevant work activity is being undertaken.

    A A4S Application for Switching R

    A CONN Testing Connections to LV Distribution Network R

    A IWG Individual of Work Group R

    A LVSO Low Voltage Switching Operator R (Note 2)

    A SR Switching Recipient R

    U SSAW Substation Safety Awareness R

    U UGAW Underground Awareness R

    A XR Restricted Operator (Note 3) R

    Legend:

    R Required.

    AR As required.

    MO A minimum of one person on Worksite holds this competency.

    Note 1: Service Providers with their own environmental training system equivalent as a minimum to the Energex environmental training system, may train and assess their own Operators as competent.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 3 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Note 2: Minimum requirement is one Operator with A LVSO Authorisation assisted at all times by a competent assistant as defined in Manual 00301.

    Note 3: Restricted to the operation of auto reclose on non-telemeted PMRs.

    5. VEHICLES AND PLANT

    For vehicles and plant requirements, refer to WCS133, Section 5 – Vehicles and Plant.

    6. MATERIALS, TOOLS AND EQUIPMENT

    (a) Provide materials, tools, equipment and spare parts in accordance with WCS133, Section 6 – Materials Tools and Equipment, and Table 2 below.

    (b) Table 2 specifies the nominated materials, tools and equipment required when providing Services for this category of work.

    Table 2 – Materials, Tools and Equipment

    Description Supplier

    Digital Low Impedance Volt Meters * Service Provider

    Phase Rotation Meters * Service Provider

    Loop Impedance Meters * Service Provider

    Low Voltage Proximity Testers * Service Provider

    Micro-ohm meter Service Provider

    Eye Protection Service Provider

    Correct Class of Insulating Gloves Service Provider

    *WP1202 specification

    7. SAFETY

    For safety requirements, refer to WCS133, Section 7 - Safety.

    8. ENVIRONMENT

    For environmental requirements, refer to WCS133, Section 8 - Environment.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 4 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    9. EXTENT OF WORK

    9.1 GENERAL

    (a) For the general extent of work requirements, refer to WCS133, Section 9 – Extent of Work.

    (b) For extent of work requirements specific to this category of work refer to the below included references and clauses.

    (c) Provide Services in accordance with (but not limited to):

    Work Category Specification WCS31 – Commissioning Operating and Accessing the Network. (i)

    Work Category Specification WCS133 – General Standards and Conditions. (ii)

    Work Category Specification WCS47.1 – Subdivision Design. (iii)

    Energex Manual 00297 – Network Labelling and Signage Manual. (iv)

    Energex Manual 00301 – Operating Practices Manual. (v)

    Queensland Electricity Entity Procedures for Safe Access to High Voltage Electrical Apparatus (SAHV). (vi)

    Energex High Voltage Live Work Manual, Doc. No.10608-A4. (vii)

    Energex Technical Instruction TSD0013 – Ring Main Unit Fuse Selection Guide. (viii)

    Energex Work Practice WP1202 – Low Voltage Connections. (ix)

    Energex Form 1056 – Contractor Application for Switching or Energising. (x)

    Energex Form 1092 – Cable Test Report. (xi)

    Energex Form 1175 – HV Apparatus Commissioning and Maintenance Sheet. (xii)

    Energex Form 1368 – Tree Trimming Field Planning. (xiii)

    Energex Form 1482 – Planned Interruption Notice. (xiv)

    Energex Form 1769 – Isolation LV Sheet. (xv)

    Energex Form 8798 - Variation of Planned Interruption Notice Period. (xvi)

    The requirements of the Energex approved Work Plan and associated drawings and instructions. (xvii)

    9.2 SERVICE PROVIDER RESPONSIBILITIES

    The Service Provider (or their agent) is responsible for:

    (a) Notifying all interested parties (Principal Contractor for the work place and / or the overall Site Project Manager) of works that are programmed to be Commissioned in full or progressively.

    (b) Ensuring WHS management plan is amended (if required) at the time of Commissioning.

    9.3 WORKING ON UNDERGROUND CABLES

    When working on underground cables, ensure the safe system of work is consistent with following as a minimum:

    (a) Isolate underground network in accordance with Manual 00301 and the Queensland Electricity Entity Procedures for Safe Access to High Voltage Electrical Apparatus (SAHV).

    (b) Positively identify target cable(s) prior to any work commencing on underground cables.

    (c) Complete cable jointing or termination and testing in accordance with approved Energex / manufacturer’s instructions.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 5 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    9.4 WORKING ON OVERHEAD ELECTRICAL NETWORK

    When working on overhead conductors and plant, ensure the safe system of work is consistent with following as a minimum:

    (a) Isolate (where required) the overhead network in accordance with Manual 00301 and the Queensland Electricity Entity Procedures for Safe Access to High Voltage Electrical Apparatus (SAHV).

    (b) Treat all conductors including the neutral as energised until proven de-energised.

    (c) Prior to work commencing on overhead structures or equipment, conductors and adjacent structures are visually inspected for damage or deterioration.

    (d) Streetlights mounted on non-conductive poles are tested to determine they are de-energised (not live).

    9.5 GSL PAYMENTS

    (a) Energex as the distribution Authority is required (in accordance with the Electricity Industry Code) to maintain Guaranteed Service Levels (GLS) of electricity supply to Customers.

    (b) Should the action of the Project Manager and or Service Provider result in Energex not meeting its obligations for Planned Interruptions and / or Reliability of Supply GSLs, Energex will recover relevant costs of GSL Payments from Project Manager / Service Provider.

    9.6 GENERATOR SET LOCATION

    The Service Provider is to:

    (a) Locate generators on Site to minimise the impact of noise and odour from exhaust fumes on surrounding Customers. Generator Sites are to be nominated and or approved by Commissioning Coordinator.

    (b) Locate generators to minimise the environmental harm that may be caused by fuel or oil spills.

    9.7 MAXIMUM DEMAND INDICATOR READINGS

    Do not reset the indicator, when Operators reading Maximum Demand Indicators (MDI) to determine load at time of switching application.

    9.8 AS CONSTRUCTED DRAWINGS

    Ensure after Commissioning of the HV and / or LV networks, ‘As Constructed’ drawing for all affected works are:

    (a) Updated.

    (b) All network infrastructure constructed is identified.

    (c) Forwarded to Energex within 5 Business Days from date of Commissioning of affected HV and or LV network.

    9.9 COMMISSIONING PROGRAM

    (a) Where the works form part of a Subdividers Supply Agreement (SSA) the nominated WCS47.1 Design Consultant is responsible for developing a Commissioning Program.

    (b) The Commissioning Program is to be developed in accordance with Planned Outage Standards.

    (c) The Project Manager is responsible for submitting applications for Commissioning, operating and access in accordance with the Commissioning Program. Energex may request additional network constraints be included, for example operations in areas targeted for Reliability Improvement Programs and overlapping works planned for the area requiring access to network be undertaken during a single outage.

    (d) Any applications received that are not in accordance with the Commissioning Program, are to be approved by Subdivisions Coordinator and or Commissioning Coordinator before operation of network. The WCS47.1 Design Consultant is to ensure all appropriate additional fees are paid.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 6 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    (e) The Project Manager ensures:

    Sufficient of the Service Provider’s Operators and resources (including materials) are available to carry (i)out the works in accordance with the Commissioning Program.

    Completion of all preparation and initial works prior to accessing the distribution network. (ii)

    Identification of any potential for additional works within the program and has a contingency plan in (iii)place to ensure restoration of electricity supply in the event of delays to the works or additional works.

    9.10 CONSTRUCTION / TEST AUTHORITIES

    (a) The Energex Commissioning Coordinator is responsible for issuing Construction Authority (CA) and / or Test Authority (TA) to the Service Provider in accordance with Manual 00301.

    (b) The Service Provider is responsible for the surrender of the above Authorities to the Commissioning Coordinator, or a delegate, prior to the works being Commissioned.

    (c) The Project Manager / Service Provider advises the Commissioning Coordinator as to progress of work to ensure all relevant documentation can be issued, for example CA for work to be carried out in a controlled and safe manner.

    9.11 COMMISSIONING / SWITCHING APPLICATIONS

    (a) The Project Manager / Service Provider are to submit applications for Commissioning / switching to Energex using Energex’s Application for Switching (A4S) computer system [wherever practical] or alternatively Form 1056.

    (b) Form 1056, is only required in the following situations:

    Commissioning of HV / LV network and plant. (i)

    Commissioning by HV live work techniques. (ii)

    Commissioning of Rate 2 Streetlight circuits. (iii)

    (c) Application for isolation and access to the network can be made using A4S computer system [wherever practical] or alternatively Form 1056, in the following situations:

    HV live work construction / maintenance works. (i)

    HV / LV switching for vegetation maintenance works. (ii)

    HV / LV switching for construction / maintenance purposes. (iii)

    (d) The Project Manager / Service Provider is to provide specific job scoping details with each application; for example:

    Construction sequence of works. (i)

    Contact details of Operator managing construction at Site. (ii)

    Contingency plan for restoration of electricity supply should difficulties occur after the “point of no (iii)return” in construction sequence.

    (e) Applications for Commissioning and / or switching will be restricted to Business Days. Energex may approve applications outside of Business Days in special circumstances.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 7 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    (f) The minimum notification for Commissioning and / or switching applications to Network Operations is:

    HV live work 5 Business Days (network re-configuration required)*.

    1 Business Day (NO network re-configuration required)*.

    HV work 10 Business Days*.

    LV work

    LV Commissioning / Switching

    10 Business Days (planned interruption required)*.

    5 Business Days (NO planned interruption required)*.

    *Addition notification will be required where other Energex Departments are involved in the Commissioning / Switching process, for example Subdivisions, Rate 2 Public Lighting or Large Customer Connections.

    (g) The Project Manager / Service Provider is responsible for ensuring all works are complete and are in a safe condition to energise within the approved outage duration.

    (h) Approval of the application will be dependent upon the availability of Energex resources to carry out the work.

    9.12 RATE 2 STREETLIGHT APPLICATIONS

    The Project Manager / Service Provider are to submit a list of Site numbers (pole numbers) with the Form 1056, to clearly identify, which streetlights are to be Commissioned.

    9.13 VEGETATION SWITCHING APPLICATIONS

    (a) Vegetation Service Provider(s) is responsible for scoping individual Worksites that require HV live work and or HV / LV switching resources to safely remove vegetation.

    (b) Scoping details to be recorded on Form 1368.

    (c) The Service Provider is to submit the individual Form 1368, that relate to Form 1056.

    (d) The vegetation Service Provider is responsible for LV switching.

    (e) The Service Provider is to take into consideration the availability of resources and network constraints (for example, operations in areas that have been targeted for Reliability Improvement Programs) when submitting A4S Reclose Block [wherever practical] and / or the Form 1056, and batch of work detailed on Form 1368.

    (f) The vegetation Service Provider where required is responsible for:

    Entering the Reclose Block application into Energex’s Application for Switching (A4S) computer system. (i)

    Disabling and restoring non telemeted auto reclosers or liaising with the nominated Energex Officer to (ii)arrange Energex crews to disable or restore non telemeted auto reclosers.

    Liaising with nominated Energex Officer to arrange crews for LV Switching and HV Isolation and access. (iii)

    Returning all completed Reclose Block documentation to Energex for auditing and filing in accordance (iv)with the requirements of the Manual 00301.

    9.14 HV LIVE WORK CONSTRUCTION

    (a) HV live work construction Service Providers are responsible for submitting applications for switching utilising the Energex’s Application for Switching (A4S) computer system and undertaking auto reclose disabling and restoring functions at PRMs after scoping individual Worksites that require HV live work and or HV / LV switching resources to safely undertake works.

    (b) The construction Service Provider is responsible for LV switching.

    (c) The Service Provider is to take into consideration the availability of resources and network constraints.

    (d) The authorised HV live work construction Service Provider is responsible for:

    Entering the reclose block application into Energex’s Application for Switching (A4S) computer system. (i)

    Disabling and restoring auto recloser functions at non telemetred PMRs in accordance with Manual (ii)00301.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 8 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Returning all completed reclose block disabling and restoring documentation to Energex for auditing (iii)and filing in accordance with the requirements of Manual 00301.

    9.15 LOW VOLTAGE SWITCHING

    (a) The Project Manager / Service Provider submit Form 1769, with all applications for LV Commissioning and Switching in accordance with Manual 00301, and WP1202. Other forms will not be accepted.

    (b) Check LV Switching Sheets prepared from diagrams in the field.

    (c) Except for emergency switching, a LV Sheet is not to be prepared and checked by the same person.

    (d) Undertake the preparation and checking of LV Switching Sheet; and the approval and coordination of LV Switching as detailed:

    LV Switching Applicants are responsible for the correct preparation and field checking of LV Switching (i)Sheets.

    Energex LV Outage Officer is responsible for checking all LV Switching Sheets. (ii)

    Energex LV Outage Officer is responsible for authorising all paper-based LV Switching Sheets. (iii)

    Energex Network Control Centre is responsible for authorising all SMS (A4S) written LV Switching (iv)Sheets.

    Energex Network Control Centre is responsible for the coordination of all LV Switching. (v)

    (e) The LV Switching Operator is to notify the Energex Network Control Centre prior to commencing and on completion of all LV Switching.

    (f) Return all completed LV switching sheets to Energex within 5 Business Days from the date the switching occurred.

    (g) The Project Manager / Service Provider are to obtain approval from the LV Outage Officer to leave the LV network in an abnormal situation.

    (h) The Project Manager / Service Provider is to notify the LV Outage Officer if a LV switching sheet does not proceed on the same day as specified on Form 1056. The rescheduling of date for the LV switching sheet to proceed may be approved by the LV Outage Officer.

    (i) The Project Manager / Service Provider is required to submit a new application (e.g. Form 1056) and re-notify effected Customers (4 Clear Business Days notification), where LV switching is rescheduled to a different date and / or time.

    9.16 CUSTOMER OUTAGES – SWITCHING OF NETWORK

    (a) The Service Provider is responsible for the distribution of Electricity Interruption Notices to Customers affected by an electricity supply interruption including a Wide Spread Outage and advising Customers of potential electricity supply interruption when generators are used to minimise electricity supply interruption. Interruptions occur when connecting / disconnecting generators that cannot be synchronised.

    (b) Distribute interruption notices at least 4 Clear Business Days prior to the planned interruption or mail the interruption notices out at least 6 Clear Business Days prior to the planned interruption, but not more than 10 Business Days prior to the planned interruption.

    (c) Where electricity supply is to be interrupted to special needs Customers (e.g. registered life support Customers), 4 Clear Business Days written notification is to be provided if hand delivered, or mail the written notification out at least 6 Clear Business Days prior to the planned interruption, but not more than 10 Business Days prior to the planned interruption.

    Note: Deliver Electricity Interruption Notices to affected Customers unless agreed otherwise by Commissioning Coordinator.

    Note: Should there be a special needs Customer(s) [e.g. registered life support Customer(s)] that has received less than 4 Clear Business Days’ notice, the planned interruption is NOT to proceed.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 9 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    (d) The Project Manager / Service Provider are to provide on the Electricity Interruption Notices distributed to all Customers affected the following details as a minimum:

    Date of electricity interruption. (i)

    Commencement time for electricity interruption. (ii)

    Planned duration of the electricity interruption. (iii)

    (e) The Project Manager / Service Provider are to provide their own name and contact details on Electricity Interruption Notices distributed unless agreed otherwise by Commissioning Coordinator.

    (f) The Service Provider is to distribute a completed Form 1482 to all effected Customers of the planned interruption to their Premises.

    (g) Send a copy of the relevant electricity interruption notice to Energex with the Form 1056.

    (h) The Service Provider is to also provide specific details (street / suburb / house numbers / approximate number of Customers) associated with all planned Customer outages or potential Customer outages when generators deployed including the date of distribution of forms.

    9.17 CUSTOMER OUTAGE NOTIFICATIONS AND COMPLETION – NO SWITCHING OF NETWORK

    (a) The Service Provider or their nominated Operator manages all outage negotiations and agreed planned outage times with all affected Customers (including domestic, commercial and industrial Customers).

    (b) When work tasks require a planned interruption to electricity supply at Customer’s installations, the Service Provider or Operator is to:

    Provide Energex with as much prior notice as practical of the planned interruption to electricity supply (i)at Customer’s installations with all the details of the installation or installations to be isolated, including where an electricity installation supplies multiple installations (e.g. multi tenancy unit complex).

    For multi tenancy unit complexes each individual tenant / resident is to be provided with notification of (ii)planned interruption to their electricity supply [detailed in Clause 9.17 (b) (iii) below] or the Service Provider or their nominated Operator is to obtain a signed waiver (Form 8798) from the individual tenants /residents [detailed in Clause 9.17 (c) below].

    Advise all effected Customers of the planned interruption to electricity supply at their installation(s) by (iii)the distribution of Form 1482 (or other nominated Energex form). Distribute Form 1482(or other nominated Energex form) at least 4 clear business days to the Customer’s premises (letter box drop) and / or mailed at least 6 clear business days prior to the planned interruption to electricity supply.

    The Service Provider or their nominated Operator is to also establish a system for recording and (iv)reporting, that supports delivery of notice(s) to each individual Premises, maintain details (house numbers / street / suburb / date and time of the distribution of the notification forms) associated with a planned Customer outage(s).

    (c) A waiver (Form 8798), can be used to obtain Customer agreement to forgo the 4 clear business days prior notification of planned interruption to the electricity supply to their installation / premises and is to strictly comply with the below:

    A request to a Customer for the electricity supply outage may occur on the same day as the outage (i)provided the Customer signs the waiver. Advice is to be provided to Energex at the completion of work and the outage in accordance with clause (c) (v) below.

    A request to a Customer for the electricity supply outage, may occur if the Customer agrees before the (ii)day of the planned electricity supply outage and signs the waiver. The Service Provider will notify Energex with full details of the waiver and the agreed electricity supply outage on the Business Day the waiver is signed or if the waiver is signed on a non-Business Day (e.g. weekend) then the next Business Day to occur using the prescribed interfaces with Energex corporate systems (SANS System or EPP System).

    Signed by the Responsible Person who is in control of the premise /tenant and the Service Provider or (iii)their nominated Operator requesting the waiver.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 10 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    For each of the signed waiver(s): (iv)

    Provide the nominated tear out copy to the Responsible Person who signed the waiver.

    The Operator is to retain the Service Provider copy (second nominated tear out copy) and return it to the Service Provider’s office. [The Service Provider is to retain, file and make available to Energex upon request this copy of the signed waiver(s).]

    For work completed after obtaining a waiver, provide full details of waiver obtained and work(s) (v)undertaken within 1 business day of completion in electronic format through the prescribed interface with Energex corporate systems (SANS System or EPP System), unless directed otherwise by the Energex Officer.

    The waiver (Form 8798) is a registered form (with an individual number) issued from a controlled waiver (vi)booklet. The booklet of numbered waivers is to be immediately returned to Energex when fully used. The Service Provider is to maintain a register detailing all the waiver booklet(s) [including the number range] issued to each of its Operators. (Make this register available to Energex upon request).

    (d) The Service Provider or their nominated Operator will provide Energex with full details of all planned interruptions to electricity supply at Customer’s installation, within 1 business day of distribution of notices. This data is provided in an electronic format through the prescribed interfaces with Energex corporate systems (SANS System or EPP System) unless directed otherwise by the Energex Officer. Provide Energex, as a minimum, with the following details (Table 4) pertaining to provision of planned interruption to electricity supply at Customer’s installation notifications to Customers.

    Table 4 – Outage Notification Data

    Data Item Description

    Work Job Number Specific PTJ number (Process Tracking Job number) or Work Order number for work to be undertaken requiring interruption to electricity supply.

    NMI The premise(s) at which the interruption(s) will occur.

    Date Notification Provided The date the notification was either mailed out or placed in the Customer’s letter box.

    Notified by The name of the individual Operator responsible for provision / distribution of the notifications. Should a notification issue arise this person may be contacted to investigate the issue.

    Method of Notification Methods: Mailed Out, Letter Box Drop, Signed Waiver (including waiver identification number).

    Date of the Interruption The day that the interruption is planned to take place.

    Expected Time Work May Commence The earliest time on the day the work will be performed and the interruption to electricity supply is expected to start.

    Expected Time Work May End The latest time on the day the work will be performed and the interruption to electricity supply is expected to end.

    Expected Interruption Duration The expected time period the interruption to electricity supply is expected to last for work to be performed.

    Contact Name Service Provider contact name shown on the notification distributed.

    Contact Organisation Name Service Provider organisation name shown on the notification distributed.

    Contact Phone Number Service Provider contact phone number shown on the notification distributed.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 11 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    (e) The Service Provider or their nominated Operator will provide Energex with full details of all completed works (jobs) and planned interruptions to Customer(s) electricity supply within 3 business day of the planned outage occurring and work being completed. This data is provided in an electronic format through the prescribed interfaces with Energex corporate systems (SANS System or EPP System) unless directed otherwise by the Energex Officer. Provide Energex, as a minimum, with the following details (Table 5) pertaining to all completed works (jobs) and planned interruptions to Customer(s) electricity supply occurring.

    Table 5 – Outage Completion Data

    Data Item Description

    Work Job Number Specific PTJ number (Process Tracking Job number) or Work Order number for work undertaken and the interruption to electricity supply.

    NMI The premise(s) at which the interruption will occur.

    Notification – Waiver Obtained

    Signed Waiver (details including waiver identification number).

    Scheduled Date of the Interruption

    The scheduled day that the interruption is planned to take place.

    Scheduled Time Work To Commence

    The scheduled time on the day the work will be performed and the interruption to electricity supply is expected to start.

    Scheduled Time Work To End The scheduled time on the day the work will be performed and the interruption to electricity supply is expected to end.

    Date of the Interruption The day that the interruption took place.

    Time Work Commenced The time on the day the work was performed and the interruption to electricity commenced.

    Time Work Ended The time on the day the work performed and the interruption to electricity supply ended.

    Interruption Duration The time period the interruption to electricity supply lasted for work to be performed.

    Contact Name Service Provider contact name shown on the notification distributed.

    Contact Organisation Name Service Provider organisation name shown on the notification distributed.

    Contact Phone Number Service Provider contact phone number shown on the notification distributed.

    (f) For special needs Customers (e.g. registered life support Customers) the Service Provider or their nominated Operator is to ensure they have current details of all special needs Customers (e.g. registered life support Customers) impacted by any interruptions to Customer(s) electricity supply. It is the Service Provider’s responsibility to ensure they have current special needs Customer (e.g. registered life support Customer) data by sourcing the data from Energex.

    Note: For all works, if Operator(s) are unsure about whether there is a special needs Customer (e.g. registered life support Customer) on the Premises they are able to Phone 1300SITEID to confirm if a special needs Customer (e.g. registered life support Customer) is at the Premises.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 12 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    9.18 PRE-COMMISSIONING CHECKS

    (a) The Service Provider is to carry out all pre-Commissioning Checks when ground mounted, padmounted and pole mounted plant are in their final resting position and record the results on Form 1175. When completed, the Form 1175 is to be left on Site for the Commissioning crew or as directed by Energex.

    (b) Where neutral connections from or to ground mounted, padmounted and pole plant is broken after initial pre-Commissioning Checks and associated Form 1175 has been completed, the Service Provider / Operator is to repeat all pre-Commissioning Checks and complete and submit a Form 1175.

    (c) The Service Provider is to record the following pre-Commissioning information:

    TR Number. (i)

    Serial Number. (ii)

    11 kV Fuses (type / size and resistance measurement). (iii)

    Earth Resistance (separate / common). (iv)

    Earth test readings. (v)

    Continuity / Insulation test results. (vi)

    Name and signature of Pre-Commissioning Officer. (vii)

    Date pre-Commissioning Checks completed. (viii)

    (d) The Service Provider is to measure the resistance (in mΩ) of all HV fuses immediately prior to inserting the fuses into HV apparatus and equipment and record the readings on Form 1175. Carry out the resistance measurements using a HV Fuse resistance measuring instrument (Micro-ohm-meter).

    (e) The resistance readings are within the acceptable resistance range specified by the manufacturer.

    (f) The Project Manager / Service Provider is responsible for placing the Substation Numbers (SC numbers) on the transformer after the pre-Commissioning Checks have been performed where appropriate pole / station numbers and correct placement of all cable destination labels required.

    (g) The Project Manager / Service Provider are to undertake all pre-Commissioning testing of HV Cables and record results on Energex HV Cable test forms. When completed, leave a signed copy of HV Cable test forms on Site for the Commissioning Coordinator / Crew or as directed by Energex allowing for Commissioning to proceed as scheduled.

    (h) The Project Manager / Service Provider are responsible for notifying all other interested parties of work that is programmed to be energised in full or progressively. Interested parties include the Principle Contractor for the work place and or the overall Site Project Manager. Complete notification to all parties and amend the Construction Workplace Plan (if required) at the time of Energex confirming switching date confirmation / approval.

    9.19 POST COMMISSIONING CHECKS

    (a) The Project Manager / Service Provider will carry out the following checks immediately after energising:

    (b) LV connections procedures where required etc.

    (c) Phasing-out checks at LV connection / isolation points between energised circuits.

    (d) Phasing rotation when required.

    (e) All labels identify physical cable terminations and destinations.

    9.20 TEST RESULTS

    The Project Manager / Service Provider will submit the following test results relevant to the work being energised:

    (a) Certificate of Test Part 1 – Insulation Test Report for 4 Core LV Cables.

    (b) Certificate of Test Part 2 – LV Continuity, Insulation Resistance, Phasing and records of LV connection tests.

    (c) Form 1092.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 13 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    (d) Earth Resistance Test Report.

    (e) Certificate of test for public lighting rate 2 installations.

    Note: Complete underground cable tests no earlier than 48 hours prior to energising.

    9.21 PART ENERGISING OF WORKS

    (a) Energex may approve the part energising of works provided the Project Manager / Service Provider provides:

    Written confirmation that all associated infrastructure (kerbs, road surfaces, survey pegs, final levels, (i)tree clearing etc.) is complete.

    Other interested parties have been notified. (ii)

    (b) An “As Constructed” drawing(s) and test results are submitted for the area being energised.

    (c) The non–Commissioned section of works is physically isolated and tagged (bridges removed DNOB attached).

    (d) Service Providers construction audit / assessment result records for the area being energised are submitted.

    9.22 RING MAIN UNIT FUSE INSTALLATION

    (a) Fitting of the correctly rated fuses to ring main units is critical.

    (b) All fuses used in a ring main unit to be the same type (including manufacture) and rating.

    (c) Following the operation of a ring main unit fuse; replace all fuses.

    (d) Refer to Technical Instruction TSD0013 for assistance in identify the correct fuse for use with each transformer and switchgear combination along with the acceptable cold resistance values for each fuse.

    (e) Any salvaged fuses following a fault are to be confirmed serviceable by testing with a Micro-ohm-meter. If the fuse resistance is proved to be within the nominated limits, the fuse may be reused and included in an identical set of fuses for future use. (If the fuse resistance is outside the nominated limits, the fuse may have deteriorated and is to be discarded.)

    9.23 PLANNED OUTAGE STANDARD

    (a) General:

    Energex is committed to delivery of high quality uninterrupted supply of electricity to its Customers. (i)The standard of supply is measured by, reliability targets and is guaranteed to Customers through Guaranteed Service Levels (GSL’s) and monitored through level of Customer complaints received.

    In order for Energex to achieve uninterrupted supply of electricity targets, all works requiring access to (ii)the distribution network or Commissioning new infrastructure onto the distribution network, is not to result in an interruption of electricity supply to Customers, unless it is impractical to do otherwise. In cases where planned interruptions are unavoidable to undertake works, initial applications for interruptions to supply will be assessed by the appropriate Energex Officer (e.g. the Low Voltage Outage Officer, Contract Officer or Commissioning Coordinator) to determine whether the interruption can be practically avoided.

    Distribution of network constraints may determine the time when switching can occur. The Energex (iii)Commissioning Coordinator may determine the most suitable time for switching.

    Where an interruption to Customers cannot be avoided by the use of LV ties, live work techniques or (iv)generator deployment; limit planned outages to 1 outage between the hours of 8:00 am and 4:00 pm.

    Note: When generators nominated to be used to avoid a planned outage and minimise Customer inconvenience; this excludes Customers within immediate Worksite.

    Exception from generator deployment at a Worksite is when a situation occurs where it is impractical (v)from an engineering / construction prospective or an unsafe situation will occur.

    (b) Commercial and Industrial:

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 14 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Electricity supply to commercial and industrial Customers cannot be interrupted during their normal (i)hours of business without their prior consent.

    Longer outage duration is acceptable if negotiated with all affected Customers and have their written (ii)agreement.

    9.24 SAFETY TAG AND LOCKOUT

    (a) Ensure the effective safe tagging and lockout of all energy sources where inadvertent activation or deactivation of control mechanisms are to be implemented to reduce the risk to Operators or plant.

    (b) Manual 00301 and the Queensland Electricity Entity Procedures for Safe Access to High Voltage Electrical Apparatus (SAHV) details procedures for working on the de-energised Energex network.

    9.25 PERSONAL PROTECTIVE EQUIPMENT – WORKING ON ENERGISED ELECTRICAL EQUIPMENT

    (a) While performing any work on energised electrical equipment or working in Proximity to exposed live parts of the Energex network, ensure the safe system of work includes the following:

    Eye protection is worn (Non-metallic). (i)

    Correct class of insulating gloves also worn when: (ii)

    Performing any HV manual switching work.

    Operating ground controlled plant (for example, GP trucks).

    (b) At all other times the wearing of insulating gloves is to be determined by the Service Providers safe system of work, excluding the situations outlined above.

    9.26 EWPS USED IN HV LIVE WORK

    (a) For cleaning and testing of EWPs used for HV live work, ensure compliance with the cleaning and testing requirements detailed in the Energex High Voltage Live Work Manual.

    10. RECORDS

    For records requirements, refer to WCS133, Section 10 - Records.

    11. WORK VERIFICATION

    (a) For work verification requirements, refer to WCS133, Section 11 – Work Verification.

    (b) For work verification requirements specific to this category of work, refer to the below included references and clauses.

    11.1 SPECIFIC REQUIREMENTS

    Provide Energex with the option of attending Site to witness testing of cables.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 15 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    12. GLOSSARY

    (a) For standard definition of words, acronyms and abbreviations used in this WCS, refer to WCS133, Section 12 - Glossary.

    (b) For addition definition of words, acronyms and abbreviations specific to this category of work, refer below.

    Term Definition

    EPP System The Energex electrical partners’ portal system that records work undertaken and confirms notification obligations are met for individual planned interruptions to Customers’ electricity supply which are being managed by the Energex Service Providers. The system is provided externally via the Internet (web portal).

    Clear Business Day This is a full Business Day occurring between the completion of all Customer notifications and the commencement of the planned interruption. In this instance, a local Authority public holiday is considered to be a Business Day should it occur on a Monday to Friday inclusive. (A Queensland state wide statutory holiday is not a Business Day).

    Responsible Person An effected Customer (resident /tenant) over the age of 18 years.

    SANS System Energex system for the management and recording of planned interruptions to small areas of Customers that do not require switching of the electricity network (Small Area Non-Switched). The system is provided externally via the Internet.

    13. REFERENCES

    (a) For reference requirements, refer to WCS133, Section 13 – References.

    (b) For additional reference requirements specific to this category of work, refer to Section 13 references and clauses.

    13.1 AVAILABLE DOCUMENTS

    Make available (at all times) to infield Operators the relevant documents / forms listed in Table 3 below for verifying Service requirements.

    Table 3 – Available Documents

    Document Reference Detail / Description

    Work Category Specification WCS31 Commissioning, Operating and Accessing the Network.

    Energex Manual 00297 Network Labelling and Signage Manual.

    Energex Manual 00301 Operating Practices Manual.

    Energex Technical Instruction TSD0013 Ring Main Unit Fuse Selection Guide.

    Document No. 10608-A4 Energex High Voltage Live Work Manual.

    Energex Work Practice WP1202 Low Voltage Connections.

    Energex Form 1056 Contractor Application for Switching or Energising.

    Energex Form 1092 Cable Test Report.

    Energex Form 1175 HV Apparatus Commissioning and Maintenance Sheet.

    Energex Form1368 Tree Trimming Field Planning.

    Energex Form 1482 Planned Interruption to Your Premise.

    Energex Form 1769 Isolation LV Sheet.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 16 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Document Reference Detail / Description

    Energex Form 8798 Variation of Planned Interruption Notice Period.

    Energex approved Work Plan and associated drawings and instructions.

    13.2 RECOMMENDED DOCUMENTS

    Refer below for the additional recommended documents that are of relevance.

    13.2.1 Energex Documents

    Table 4 – Energex Document

    Document Reference Detail / Description

    Work Category Specification WCS31A Assessment - Commissioning Operating and Accessing the Network.

    Work Category Specification WCS133 General Standards and Conditions.

    Work Category Specification WCS47.1 Subdivision Design.

    Work Category Specification WCS47.2 Subdivisions Project Management.

    SAHV Queensland Electricity Entity Procedures for Safe Access to High Voltage Electrical Apparatus

    13.2.2 Queensland Acts and Regulations

    For Queensland Act and Regulation requirements, refer to WCS133, Section 13.2.2 – Queensland Acts and Regulations and the additional Queensland Act and Regulation below.

    National Energy Retail Law (Queensland) Act 2014.

    National Energy Retail Law (Queensland) Regulation 2014.

    13.2.3 Australian Standards and Other Documents

    For Australian Standard and other documents, refer to WCS133, Section 13.2.3 – Australian Standards and Other Documents.

    14. APPENDICES

    Appendix A Declared Non-Live Tasks.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 17 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Appendix A – Declared Non-Live Tasks

    Declared Non-Live Tasks A1

    The Electrical Safety Regulation 2013 places restrictions on the performance of live work and only allows it where it is not practicable to perform the work de-energised and the work can be done safely. These tasks have been assessed to have an intolerable risk when performed live. Energex has declared that due to this intolerable risk the following activities will only be performed de-energised.

    S.E.A.Q. Concrete Pillar

    Declared Non-Live Task. Not to be worked on live by any person

    NGK LV ABC bundle box to which restrictions apply.

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 18 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    Table 5 – Declared Non-Live Tasks

    Ref No. Description of Task

    1 Replace / install LV surge arresters.

    2 Maintenance or repair work on pole mounted distribution transformers unless Live Line techniques are used. (E.g. repair oil leaks; apply possum proofing; replace bridging and LV leads; repair burnt terminal on transformer bushing or repair burnt neutral connection to transformer tank).

    3 Making or breaking electrical connections at consumer’s terminals in overhead network supplied areas.

    4 Working from concrete poles when performing LV tasks other than testing. Replacing a burnt fuse base, burnt link or faulty connection may be performed with conductors energised if carried out from the basket of a EWP or if appropriate barriers / mats are in place. (Refer to safe system of work for working on concrete poles.)

    5 Fitting LV switch fuse unit on an existing LV Panel. Replacement or addition of a LV switch fuse unit on existing LV panel on all switchboards, for example in padmount transformers and GT enclosure LV cubicles etc.

    6 Consac Cable. All work on consac cable is to be carried out de-energised other than the following tasks:

    Electrical testing in pillars.

    Fuse replacement in pillars.

    Fuse base replacement in pillars.

    Work on plastic insulated cable tails of consac terminations.

    Disconnection and reconnection of looped cable terminations by unbolting of lugged terminations to separate like phases in order to provide a temporary isolation point to limit the number of de-energised customers.

    7 SEAQ Type Concrete Pillars – Looping Pillars. All work on SEAQ type concrete pillars is to be carried out de-energised other than the following tasks:

    Electrical testing;

    Fuse replacement;

    Note: This does not apply to “BCC” type concrete pillars commonly referred to as “Tombstones” which are able to be worked on while energised.

    8 Operating Krone RMU’s and padmount transformer load break elbows.

    9 Connection of generator leads onto LV boards. Connection of generator leads onto LV boards in PMT’s and GT’s where there is no provision for temporary connection.

    10 Working in live pillars with un-insulated tools. All work in pillars, where any parts are energised, is not permitted with un-insulated tools (e.g. vice-grip pliers). Note: Insulated tool kits are available for this purpose

    11 Changing poly phase metering equipment.

    12 Wilson Padmount Transformer Lid removal. Prior to the lid being removed the transformer and associated equipment is to be de-energised.

    13 Replacement of MDI and / or associated current transformers on energised Transformers.

    14 Operation of all Stemar / JUNG DTL RF 250 CFS (combined fuse switch) units. These units can only be operated after they are tested and proved de-energised.

    15 Making or breaking of connections to the NGK bundle box (identifiable by being all black) are only to be performed in a de-energised environment. Operation of the bundle box while energised (open close) is permitted.

    16 Replacing a low voltage transposition cross arm and or insulators on transposition cross arms

    17 All work to be performed on LV cast iron pole terminations are to be carried out de-energised other than the following tasks:

    Electrical Testing

    Making or breaking the connections to the overhead apparatus where the bridging can be supported, under switching conditions.

    Workers are not to perform the above tasks live (energised)

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 19 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    CONTENTS

    1. SCOPE ............................................................................................................................................. 1 1.1 General ............................................................................................................................................. 1 1.2 Application ....................................................................................................................................... 1

    2. AMENDMENT RECORD .................................................................................................................... 1

    3. AIMS / OBJECTIVES ......................................................................................................................... 2

    4. COMPETENCIES, TRAINING AND QUALIFICATIONS ........................................................................... 2

    5. VEHICLES AND PLANT ...................................................................................................................... 3

    6. MATERIALS, TOOLS AND EQUIPMENT .............................................................................................. 3

    7. SAFETY ........................................................................................................................................... 3

    8. ENVIRONMENT ............................................................................................................................... 3

    9. EXTENT OF WORK ........................................................................................................................... 4 9.1 General ............................................................................................................................................. 4 9.2 Service Provider Responsibilities ..................................................................................................... 4 9.3 Working on Underground Cables ..................................................................................................... 4 9.4 Working on Overhead Electrical Network ....................................................................................... 5 9.5 GSL Payments ................................................................................................................................... 5 9.6 Generator Set Location .................................................................................................................... 5 9.7 Maximum Demand Indicator Readings ............................................................................................ 5 9.8 As Constructed Drawings ................................................................................................................. 5 9.9 Commissioning Program .................................................................................................................. 5 9.10 Construction / Test Authorities ........................................................................................................ 6 9.11 Commissioning / Switching Applications ......................................................................................... 6 9.12 Rate 2 Streetlight Applications......................................................................................................... 7 9.13 Vegetation Switching Applications .................................................................................................. 7 9.14 HV Live Work Construction .............................................................................................................. 7 9.15 Low Voltage Switching ..................................................................................................................... 8 9.16 Customer Outages – switching of Network ..................................................................................... 8 9.17 customer Outage Notifications and completion – no switching of Network .................................. 9 9.18 Pre-Commissioning Checks ............................................................................................................ 12 9.19 Post Commissioning Checks ........................................................................................................... 12 9.20 Test Results .................................................................................................................................... 12 9.21 Part Energising of Works ................................................................................................................ 13 9.22 Ring Main Unit Fuse Installation .................................................................................................... 13 9.23 Planned Outage Standard .............................................................................................................. 13 9.24 SAfety Tag and Lockout .................................................................................................................. 14 9.25 Personal Protective Equipment – Working on Energised Electrical Equipment ............................ 14 9.26 EWPs Used in HV Live Work ........................................................................................................... 14

    10. RECORDS ...................................................................................................................................... 14

    11. WORK VERIFICATION .................................................................................................................... 14 11.1 Specific Requirements.................................................................................................................... 14

  • Work Category Specification WCS31 Commissioning Operating and Accessing the Network

    Check this is the latest version before use Page No: 20 of 20 Approved by Work Practices Manager

    WCS31 Version 20 © Energex Limited 2015 23 July 2015

    ABN 40 078 849 055

    12. GLOSSARY .................................................................................................................................... 15

    13. REFERENCES ................................................................................................................................. 15 13.1 Available Documents ..................................................................................................................... 15 13.2 Recommended Documents ............................................................................................................ 16

    13.2.1 . Energex Documents .......................................................................................................... 16 13.2.2 . Queensland Acts and Regulations ..................................................................................... 16 13.2.3 . Australian Standards and Other Documents .................................................................... 16

    14. APPENDICES ................................................................................................................................. 16 Appendix A – Declared Non-Live Tasks ................................................................................................... 17