Upload
nancy-phelps
View
220
Download
0
Tags:
Embed Size (px)
Citation preview
WORKSHOP ON EXPERIENCE SHARING AND LESSONS LEARNT DURING
IMPLEMENTATION OF ESMF IN 2013-14
Presented By
SADAT ALI
ASSISTANT DIRECTOR WATER QUALITY
WASA RAWALPINDI
PCGIP 2
CONTENTS•About PCGIP
•About Environmental and Social Management Framework (ESMF)
•Environmental and Social Categorization of Schemes
•ESMF Implementation Steps
•Environmental and Social Management Plans (ESMP)
•Case study of ESMP preparation
•Benefits of ESMF
•Issues faced by WASA
•Conclusion
PCGIP3
PROJECT INTRODUCTION (PCGIP)
•Government of the Punjab, with the financial assistance from World Bank, is implementing Punjab Cities Governance Improvement Project (PCGIP).
•The project is focused at strengthening of systems and governance improvement for enhanced service delivery and being implemented in 05 large cities.
PCGIP4
ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK
(ESMF)
•ESMF has been prepared under the project “Punjab Cities Governance Improvement Project (PCGIP).
•ESMF serves as a guiding document to address the environmental and social issues during projects implementation covering following phases: Planning and design, Construction and rehabilitation, Operation and maintenance, Decommissioning and closure phases.
•ESMF ensure that schemes to be designed and implemented by the Government are environmentally sound, socially acceptable and comply with the national regulatory and WB policy frameworks.
PCGIP5
ENVIRONMENTAL CATEGORIZATION OF SCHEMES
PCGIP 6
E – 1 Schemes wherein major environmental impacts
are foreseen EIA/IEE*
E - 2Schemes that are expected
to have only moderate environmental impacts
ESMPs**
E - 3 Schemes with negligible environmental impacts
no further assessment required
*Environmental Impact Assessment (EIA)./ Initial Environmental Examination (IEE)**Environmental & Social Management Plans (ESMPs)
SOCIAL CATEGORIZATION OF SCHEMES
PCGIP 7
S – 1 schemes that will impact more
than 40 households, and are expected to have significant
negative social consequencesRAP *
S - 2Schemes that will impact less than 40 households and are expected to have significant
social consequences affecting local inhabitants
RAP*
S - 3schemes expected to have no
significant social consequences affecting local inhabitants
* Resettlement Action Plan (RAP)** Social Assessment Report (SAR)
1. Environment and social screening of all
schemes
2. Prepare IEE/EIA/RAP/SAR/ESMP
3. ESMP/EIA/IEE is included in bidding
document along with mitigation plans
4. Environment and Social Monitoring
ESMF IMPLEMENTATION STEPS
PCGIP 8
ENVIRONMENT & SOCIAL MANAGEMENT PLANS (ESMPS)
For each scheme with E2 category, The Environmental and Social Management Plan (ESMP) is prepared according to the World Bank Policy Guidelines; environmental and social laws; and policies of Government of Punjab (GoPb).
ESMPs will be used to identify and mitigate the environmental and social impacts that may emerge during implementation of schemes.
PCGIP9
ESMPs of WASA-R SCHEMES 2013-14
ESMPs have been prepared of following 04 schemes of WASA-R:
1.REPLACEMENT OF OLD LEAKING WATER SUPPLY LINE IN WASA EAST ZONE I2.REPLACEMENT OF OLD LEAKING WATER SUPPLY LINE IN WASA WEST ZONE I
3.REPLACEMENT OF OLD LEAKING WATER SUPPLY LINE IN WASA EAST ZONE II
4.REPLACEMENT OF OLD LEAKING WATER SUPPLY LINE IN WASA WEST ZONE II
PCGIP10
CASESTUDY
ESMP OF REPLACEMENT OF OLD LEAKING WATER SUPPLY LINE IN
WASA WEST ZONE II
PCGIP 11
SCHEME INFORMATION
ESMP implementation cost: 0.0816 million
Total cost of the scheme: 2.26 million (including ESMP cost)
PCGIP12
STEP 1
ENVIRONMENTAL AND SOCIAL
SCREENING OF SCHEME
PCGIP13
STEP 2ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)
PREPARATION
PCGIP14
Scheme
Replacement of old leaking water supply line in WASA West Zone-II
Environment or Social Prospective
Potential Negative Impacts Mitigation Measures Responsibility Entity
Monitoring Agency
A. Development and Design Phase
Public and CulturalProperties
Disturbance to people visiting publicproperties i.e. mosque, schools,shrines, and graveyards etc.
Incorporate technical design features to minimize the scheme construction activities to avoid anyinterference with cultural heritage site and public property as far as possible.
WASA-R & Design consultant
WASA-R
Scheme development & design
Failure of water works and flooding of nearby areas.
Scheme design should consider terrain, soil characteristics, hydrology and geology.
WASA-R & Design consultant
WASA-R
Disturbance to other services
Other infrastructure like electrical cables, telephone poles etc. might disturb
Scheme should be designed to avoid interference with other services.
CDGR& Design consultant
CDGR& Design consultant
ESMP CONT… B. Repair/Rehabilitation/ Construction PhaseSurface & ground water quality
deterioration the surface water quality.
Analysis of surface water/ground WASA-R & Contractor
WASA-R & ESSS
Rainwater runoff Alteration in natural flow of rainwater runoff
Riprap (cobbled stone), gravel or concrete will be used as needed to prevent erosion of drainage structures
WASA-R & Contractor
WASA-R & ESSS
Access disruption Reduced pedestrian and vehicle access to residences and businesses
Establish work sequence, provide alternative safe access; temporary crossings and walkways
WASA-R & Contractor
WASA-R & ESSS
Construction materialstorage, handlingand use
Water may be contaminated due to the oil spillages if the water source is nearby the storage yard. Health risk to workers.
Material shall be appropriately secured to ensure safe passage between the destinations during transportation. Loads shall have appropriate cover Contractor is also liable to pay the affectees
Contractor CDGR & ESSS
PCGIP 15
ESMP CONT…Traffic Increased traffic inconvenience Use alternate traffic routing;
ensure coordination with local authorities
WASA-R & Contractor
WASA-R & ESSS
Solid waste Conflicts might arise due to piling of debris material and blockage of channel will be resulted. Dumping into agriculture lead to deteriorate crops.
Immediately transport the debris construction waste Trash should be collected in waste bins. No dumping is allowed into agriculture fields
WASA-R & Contractor
WASA-R & ESSS
Public health & safety
Accidents/injuries can occur during rehabilitation work.
PPE’s should be provided to workforce First Aid facility should be provided to workforce.Safety signs should be displayed.
WASA-R & Contractor
WASA-R & ESSS
Oil/grease spillage Oil/grease leaching into soil strata.
Oil/grease leakage should be avoided and drums should be kept on concrete platforms.
WASA-R & Contractor
WASA-R & ESSS
PCGIP 16
MONITORING PLAN
Sr. #
Identified Environmen
tal& Social issues
Mitigation MeasureMonitoring
Site
Monitoring
Frequency
Reporting Frequency
Responsibility
1. Water quality
Water samples will be taken and will be analyzed in the EPA certified laboratory.
Once during repair/improvement phase
Frequent site visits
Once after completion of project; an environmental compliance report
DO *(Environment) & ESSS**
2. Dust PPE’s, Mask Avoiding construction
activities during nights. Sprinkling of water
Scheme Site
Frequent site visits
Once after completion of project; an environmental compliance report
DO (Environment) & ESSS
PCGIP 17
MONITORING PLAN CONT…3 Waste
management
Immediately transport the accumulated construction waste to a site identified by the implementing CDG****/other concerned authority
Scheme Site
Frequent site visits
Once after completion of project; an environmental compliance report
DO (Environment) & ESSS
4 Provision of first aid in case of any emergency
First aid will be provided immediately to save the life of affectees.
Ambulance will be called up to shift the affectees to the nearest medical facility.
Scheme Site Frequent site visits
Once after completion of project; an environmental compliance report
DO (Environment) & ESSS
5 Health, Safety and Environmental needs
The Contractor should ensure provision of appropriate housing, water supply, and sanitation facilities to labor.
PPEs
Scheme Site Frequent site visits
Once after completion of project; an environmental compliance report
DO (Environment) & ESSS
PCGIP 18
ESMP IMPLEMENTATION COST
PCGIP 19
Item Quantity Cost /Item(Rs) Total Cost
A. Safety
Safety Shoes 22 1200 26400
Gloves 22 500 11000
First Aid Box 02 1000 2000
Safety Signs 05 1000 5000
Sub-Total A 44400
B. Environmental Analysis
Ground Water Analysis(Bacterial analysis, pH, turbidity, TDS, total hardness, Arsenic, chloride, lead, nitrates, sulphates, zinc, mercury)
01 8400 8400
Surface/ Waste Water Analysis(pH, TDS, TSS, oil & greece, cadmium, chromium (trivalent & hexavalent) lead, nickle, mercury, zinc, flouride, cyanide)
01 7800 7800
Sub-Total B 16200
C. Others
Pole hanging waste bins 03 5000 15000
Sub-Total C 15000
D. Field Visits
Environment Specialist 02 3000 6000
Sub-Total D 6000
Grand Total (A+B+C+D) 81600
STEP 3ESMP IMPLEMENTATION
The ESMP cost included in the scheme implementation cost.
The ESMP included in the bidding documents.
Training of Contractors conducted regarding ESMP compliance
Contractor's guideline for environmental and social management prepared by the Urban Unit distributed among the contractors
PCGIP20
STEP 4ENVIRONMENTAL AND SOCIAL
MONITORING
Frequent Site Visits
Environment and social checklist filling
Testing of environmental parameters through EPA certified laboratory
On site training of laborers and contractor
Public consultation
Photographic record
Monitoring report preparation
PCGIP21
BENEFITS OF ESMF IMPLEMENTATION
Environmental protection
Community involvement
Capacity building of contractors, labor and WASA
Environmental and social screening of schemes at identification stage
Environmental and social monitoring during scheme execution
PCGIP 22
ISSUES / HURDLES FACED BY WASA REGARDING ESMF IMPLEMENTATION
• Labor are reluctant to wear PPEs
• People attitude towards cordon off work area
PCGIP 23
Thanks
PCGIP24