Upload
akash-nair
View
13
Download
2
Embed Size (px)
Citation preview
1
1. INTRODUCTION
River and coastal related disasters have increased in both frequency and
intensity in recent years. The effect of sea level rising as a result of global
warming has also become a major concern. As a result, the construction of
dikes, river or coastal protection structures, or the rehabilitation of existing
dikes or coastal protection structures has become an important part of disaster
mitigation strategies.
It is a challenge to geotechnical engineers to develop cost-effective
methods or techniques for river or coastal protective structures that can be
constructed speedily and conveniently, in particular suitable for disaster
mitigation. As dikes or other types of coastal protection structures are long, a
small improvement in the design could result in a significant amount of saving.
Three innovative dike construction methods are use of clay filled
geomats for dike construction, the use of prefabricated, semi-circular caissons
for offshore breakwater, and the use of suction caisson for dike construction.
Each method has its own merits and demerits.
2. DIKES OR BREAKWATERS
Dikes and breakwaters are coastal protection structures. The purpose of
offshore breakwater or dike is to prevent storm waves from reaching the beach
and to resist flood, to protect harbour, to avoid beach erosion etc. Now a day the
coastal related disasters are increasing. So these protection structures have to be
constructed in a cost effective manner. The three innovative methods of dike
construction are explained below.
3. GEOSYNTHETIC TUBES AND GEOMATS
As a counter measure against river and coastal related disasters in recent
years, there has been an increasing use of geotextile and geosynthetic materials
for river and coastal construction. Rubber dam, geosynthetic or geotextile tube
and geosynthetic mats (or geomats) are a few examples of geotextile materials.
3.1 GEOTEXTILES
Geotextiles are permeable fabrics which have the ability to separate,
filter, reinforce, protect or drain. It is made from polypropylene or polyester.
There are several methods for using geotextile or geosynthetic materials for the
construction of coastal structures such as breakwater and dikes.
2
3.1.1 USE GEOTEXTILES ACTING AS FORMWORK FOR CEMENT MORTAR
UNITS CAST-IN-SITU
The mortar mix needs only be of sufficient compressive strength to
support the weight above and the moment from the side force of the waves.
Since the subsequent deterioration due to UV rays or other conditions is of little
concern. Thus the method tends to be cheaper than the conventional method.
3.1.2 USE OF WATER OR AIR INFLATED RUBBER BAGS FOR THE
CONSTRUCTION OF SMALL DAMS FOR IRRIGATION OR FLOOD CONTROL
PURPOSE
This method is normally used
only for small dikes up to 6m high.
This method has an advantage of
adjusting the height of the dike
easily by pumping and releasing air
or water in to rubber bags. For this
reason this method has been used
recently for the Ranspot storm
barrier in Netherlands. This rubber
dam in this application is 8.2m
above the base when it is full
inflated.
3.1.3 USE OF SAND OR DEHYDRATED SOIL FILLED GEOSYNTHETIC TUBES
One shortcoming with the use of geotextile tubes for the construction of
dikes is the difficulty to maintain the lateral stability of the dike. To overcome
this problem, sand or sandy soil is filled in the geotextile tube. For near shore or
off shore projects suction dredger is used to pump sand from the seabed or a
sandpit directly in to the geotextile tubes. Silty clay or soft clay has also been
used when sand is not readily available. In this case clayey fill would have to be
in slurry state in order to be pumped and flow in the tube. After pumping the
slurry in the geosynthetic tubes it act as a cheese cloth. Allowing seepage of
liquid out and retaining the solid particle. In this case the selections of the
geotextile used for the tubes or mats become important. The geotextile has to be
chosen to meet both the strength and filter design criteria. The apparent opening
size (AOS) of the geotextile needs to be selected to allow the pore pressure to
dissipate freely and yet retain the soil particles in the geosynthetic tubes or
geosynthetic mats.
Fig.1 water inflated rubber dam used for a river
3
Fig.2 Sand filled geotextile tubes for shoreline protection
3.1.4 USE OF GEOMATS
It is difficult to maintain the lateral stability of the dike when geotubes
are stacked one on the top of another. One innovative idea developed recently is
the use of geotextile mattresses or geomats. In this case, the soil filled geotextile
bag form a mattress with its lateral dimensions much greater than the vertical
one. The use of geomats will overcome the lateral stability problem.
.
3.1.5 USE OF GEOTEXTILE TUBES TO CONTROL BEACH EROSION
The beaches of the Northern coast of Yucatan in Mexico have been in a
permanent erosion process that has dramatically increased in the past 15 years.
Any restoring action did not affect the natural dynamic process that relates wave
climate-bathymetry-sediments. The solution was to generate a sand
accumulation process without interrupting alongshore sediment transport. Also
the solution had to be as flexible as possible, avoiding any rigid structures, so it
would easily absorb any physical media modification. Under these conditions
Fig.3 A picture showing the formation of a
dike using clay slurry filled geotextile
bags
Fig.4 A concrete mattress was cast in-situ with
geotextile as a mould to cover the dike
made of geomats.
4
and for critical points geosynthetics were considered optimal for the beach
restoration project. Woven polypropylene geotextile tubes were designed to
work as low crested submerged structures. Their main function was to reduce
the incident wave energy on the beach, by controlling the wave breaking
process to the required level that maintains the dynamic balance on the
shoreline.
4. PREFABRICATED CAISSONS
The geotextile tube or mattress method may only be feasible
when dikes are to be constructed in relative shallow or quiet water. When water
is too deep or the wave is rough, gravity retaining structures using prefabricated
reinforced concrete segments or caissons may be a better option.
These concrete segments or caissons
have to be tall enough to match the
water depth and heavy enough to
provide stability against the waves.
When the concrete segments or
caissons are too heavy, the caissons
will cause settlement or bearing
capacity problems. This is particularly
the case when the foundation soil is
soft. The weak foundation soil can be
improved. However, it is difficult and
costly to treat soil offshore and over a
large area or distance. large area or distance.
Fig.5 Geotextile tube inducing wave
breaking for energy attenuation
Fig.6 View after sand accumulation
shoreward of geotextile tubes
Fig.7 Prefabricated caisson supported by
rubble mound and scour protection cover
5
The concrete would provide a noncorrosive structure. The caisson would
be cast on the shore and floated into position. If the seabed is of soft soil it has
to be treated by using prefabricated vertical drains (PVDs) before the caisson
was installed. The semi-circular shaped caissons are more preferable.
Advantages of semi-circular shaped caissons are
1. The water pressure acting on the semi-circular shaped surface pass
through the centre of the circle. Thus the overturning moment
becomes much smaller and the vertical pressure distributions at the
base of the caisson become more uniform.
2. The lateral wave force acting on a semi-circular shaped breakwater is
smaller than that on a vertical breakwater of same height and thus the
cost for the construction of breakwater can be reduced.
In Yangtze Estuary coastal protection project, some dikes for navigation
purposes needed to be constructed. It was constructed at 40 km away from the
coast. The water depth ranged from 5.0 to 8.5 m. The design wave height was
3.32-5.90 m with a return period of 25 years. The total length of the dike was
about 17 km. The typical soil profile below the dike consisted of a 1.5-3.5 m
thick silt sand followed by 2-4m thick muddy clay and a layer of soft clay of
roughly 30 m thick underlying the muddy clay. The seabed soil was treated by
preloading using prefabricated vertical drains (PVDs) before the caissons were
installed. The caisson used was prefabricated reinforced concrete hollow
segment. It was semicircle shaped. The radius of the semicircle was 5.7m. The
advantage of using a semi-circular cross-section is that the direction of the
resultant wave force on the semi-circular shaped structure will always pass
through the centre of the circle, which will greatly improve the loading
condition of the structure. The hollow caisson would be filled with sand after
installation through a 600 mm diameter hole on top of the caisson. In order to
prevent the foundation soil from scouring, a geotextile sheet was used to cover
the seabed. A cushion which acted as the foundation bed was placed on top of
the geotextile. The cushion was 1-2m high. It was made of crushed stones of 1-
100 kg for the centre and 200-400 kg for the edge. After the caisson was placed,
berms were placed on two sides of the caisson. The berms were made of 400-
600 kg crushed stones.
5. SUCTION CAISSONS (Skirted foundation/buckets/suction anchors)
One of the disadvantages of the prefabricated concrete caisson method as
described above is the need to treat the soft seabed soil and the construction of
rubble mound which can be time consuming. Thus, the gravity caisson method
is not suitable for disaster mitigation purposes. Another method of building
breakwater or seawalls is the use of cylindrical steel or concrete suction
6
Piles or caissons developed by the Tianjin Port Corporation, China. This
method is particularly suitable for the construction of breakwater on soft seabed
or in deep water. It takes less time to install than piles and being easier to
remove during decommissioning. So suction caissons are used extensively for
anchoring large offshore installations to the seafloor at great depths.
Suction caissons are a better alternative to driven piles in deep water
because of technical challenges and costs associated with the installation
equipment for driven piles. Heavy lift vessels can be avoided, simplifying and
shortening the installation procedure. Another advantage is that there is more
control over the installation process. Therefore, the location of the anchors on
the seabed is fixed and known with accuracy. Suction caissons also provide a
greater resistance to vertical and lateral loads than driven piles and drag anchors
because of the larger diameters typically used. Initial penetration of the suction
caisson into the seabed occurs due to the self-weight. Subsequent penetration is
by the “suction” created by pumping water out from the inside of the caisson. A
submersible pump attached to the top of the sealed caisson applies suction
pressure. By evacuating water from the inside, a pressure differential is created.
The limiting value of this pressure differential, such that cavitation does not
occur, is the sum of the atmospheric pressure and hydrostatic pressure outside
the caisson. In very deep waters, large penetration or suction pressures can be
created, which is only limited by the capacity of the pump. Once the required
depths are reached, the pumps can be disconnected and retrieved.
Fig.8 Layout of the suction caissons: (a)
viewing from the bottom of the suction
Caissons; (b) viewing from the top of the
concrete suction caissons with the top
Cylinders used as part of the breakwater
Fig.9 Installation of concrete suction
caissons.
7
This method has been used recently in the Tianjin Port, China for an offshore
breakwater project.
The soil profile at the site consisted of up to 25 m soft soils where the
water content of the soil was generally higher than the liquid limit of the soil.
Four 12m in diameter prefabricated reinforced concrete cylinders were
connected together using 4 concrete walls to form one unit as shown in Fig 8a.
The top opening of the four cylinders was sealed by a precast concrete plate as
shown in Fig 8a. The unit formed by the four cylinders was towed to the
required position and sunk onto the seabed by ballasting. Suction was then
applied simultaneously to the inner chambers of the four cylinders which were
sealed at the bottom by the seabed clay. Under the suction and the hydrostatic
pressure, the four cylinders were dragged down to penetrate into the seabed soil.
The suction was removed after the penetration depth of the cylinder was
sufficient. The amount of penetration required was calculated in accordance
with the bearing capacity that had to be provided by the shaft friction. After the
4 cylinder units were installed, another row of prefabricated concrete cylinders
of the same diameter was installed on top of the bottom units as shown in Fig
8b. The operations for the installation of the lower 4 cylinder unit and the upper
cylinders are presented in Figs. 9 and 10 respectively. The breakwater after
installation is shown in Fig. 11.
Although a new development, the use of suction caissons for offshore
dike or breakwater construction has shown a number of advantages over the
existing methods. In addition to avoiding the treatment of the seabed soil, it also
seems to be more economical as compared with the semi-circular concrete
caisson method. The settlement of the caisson is also much smaller. However,
this method may only be applicable to sites with a relatively thick layer of soft
soil. Furthermore, it required special machines to cast, transport, and install the
suction caissons. More study on the design and analysis aspects is also required
before this new approach can be developed into an established technology.
Fig 11. Breakwater after installation. Fig. 10. Installation of upper cylinders to
form breakwater.
8
6. CONCLUSION
The main features of each method are
1) The geotextile mattress or geomat method is suitable for the construction of
breakwater or dikes in shallow water. In this method, the dike is constructed by
stacking several layers of flat geotextile mattresses that are formed by pumping
either sandy or clayey slurry into pre-sewed geotextile bags. The main
advantage of this method is that it can provide much better lateral stability as
compared to the geotextile tube method.
2) The prefabricated concrete caisson method is suitable for the construction of
seawall or sea dike in relatively rough water. However, when the seabed is
relatively weak, the soil has to be improved.
3) The suction caisson method is new, but promising. It is particularly suitable
for dikes constructed in relatively deep water. With the use of suction skirt, the
treatment of soft seabed soil is no longer required. However, more field
experience needs to be established. More theoretical studies are also required to
guide the design and construction.
9
7. REFERENCES
J.chu,S.W.Yan,W.Li, “Innovative methods for dike construction - An
overview”, Geotextiles and Geomembranes, science direct,30(2012)35-
42,1 st
February 2011,<http://www.sciencedirect .com >,(5th
July 2012)
Ing E.Alvarez,Ramiro Rubio, Herbert Ricalde, “Beach restoration with
geotextile tubes as submerged breakwaters in Yucatan, Mexico”,
Geotextiles and Geomembranes, 25(2007)233-241,10th
May
2007,<http:// www.sciencedirect .com >, (5th
July 2012)
Leshchinsky.D,Leshchinsky.O,Ling.H.I,Gilbert.P.A, “Geosynthetic
Confined pressurised slurry(GeoCoPs):Supplemental notes for
Version1.0”,Report TR CPAR-GL-96-1,September 1996, (8th
July 2012)
Ashutosh Sutra Dhar, Abu Siddique, Syed Fakrul Ameen, “Ground
Improvement using Pre-loading with Prefabricated Vertical Drains”,
International Journal of Geoengineering Case Histories ©, Vol. 2, Issue 2,
p. 86,<http://casehistories.geoengineer.org>, 28th
March 2011, (28th July
2012)
Jia, Donghua (1999), “Study on the Interaction of Water Waves with
Semi-Circular Breakwater”, China Ocean Engineering, Vol.13, No.1,
pp.73-80, (28th July 2012)
Charles Aubeny and Don Murff, “Suction Caissons & Vertically Loaded
Anchors: Design Analysis Methods”, A National Science Foundation
Graduated Engineering Research Centre , December 2005(28th
July 2012)