© Wärtsilä Wärtsilä Scrubber Retrofit Wärtsilä Marine Solutions / Environmental Solutions Wärtsilä Scrubber Retrofit 2016 1 4 November 2016

Wärtsilä Scrubber Retrofit 4 November 2016 Wärtsilä Scrubber Retrofit 2016 Installation supervision RETROFITTING ALTERNATIVES –SCOPES OF SUPPLY Vendor selected by the customer

  • Upload
    vanthu

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

© Wärtsilä

Wärtsilä Scrubber RetrofitWärtsilä Marine Solutions / Environmental Solutions

Wärtsilä Scrubber Retrofit 20161 4 November 2016

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 20162

RETROFITTING ALTERNATIVES

EQUIPMENT ONLY INSTALLATION

ENGINEERING

SITE ADVISORY

EPC + POSSIBILITY FOR SCRUBBER INVESTMENT FINANCING

© Wärtsilä

EQ

Ba

sic

EE

Q

Ba

sic

+d

eta

il

EE

Q

Fu

ll

EP

C

EP

C-M

4 November 2016 Wärtsilä Scrubber Retrofit 20163

Installation supervision

RETROFITTING ALTERNATIVES – SCOPES OF SUPPLY

Vendor selected

by the customer

GA drawings, class approval drawings

Installation plan class approval

Equipment

Laser scanning

Fabrication & installation drawings

Optional

Project management for the corresponding delivery scope

Optional

Construction &

installation

Vendor selected

by the customer

Optional

Optional

Optional

FEED

Pre-fabrication

Installation

supervision

Optional

Optional

Optional

Pre-fabrication

FEED

Construction & installation

Project management

Detail design scope

Laser scanning

Installation plan class approval

Basic design scope

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 20164

EPC (TURNKEY) PROJECT DESCRIPTION

Initial phase Front End

Engineering &

Design (FEED)

Basic engineering;

project planning;

contractors’

selection

Detailed

engineering and

procurement

Construction

and installation

Commissioning

and approvals

Warranty

LIFECYCLESUPPORT

EPC PROJECTMANAGEMENT

Review gate with the customer

Benefits for the customer:

• Single point of contact

• Avoid sub-optimisations within suppliers

• Dedicated & experienced scrubber project team

• Minimized economic risks

• Time, cost & resource savings

• Optimised quality and schedule control

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 20165

Technical feasibility report

• Dozens of technical feasibility reports have been done already for various different vessel types

• That with several engineering packages delivered puts Wärtsilä in the forefront of integrating a scrubber system with an existing vessel

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 20166

Layout study

Extended

Layout study

Technical

feasibility study

Economical feasibility study If desired If desired If desired

Technical Data sheet

Technical Specification

Layout arrangement

Ship visit -

Report, including e.g.: - -

Ship data - -

Equipment arrangement and locations - -

Tank arrangement and locations - -

Modifications to existing ship - -

Pipe routing principles - -

Sea water capacity check - -

Electrical evaluation - -

Stability and weight evaluation - -

Conclusion and possible red flags - -

Process flow diagram - -

SCRUBBER RETROFIT STUDY SCOPES

© Wärtsilä

SCRUBBER FINANCING MODEL

4 November 2016 Wärtsilä Scrubber Retrofit 20167

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 20168

STRATEGY TO MEET SECA REGULATIONS

HFOSTRATEGY

MGOSTRATEGY

FUEL

EQUIPMENT

CAPEX

FUEL COST

HFO 3.5% S HFO 3.5% S MGO 0.1 % S

SCRUBBER SCRUBBER FUEL COOLER

HIGH (100%) NO INVESTMENT LOW (3-5%)

LOW ($240/ton)From day one

SAVINGS TO MGODURING CME FINACINGLOW AFTER

HIGH ($450/ton)From day one

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 20169

EXAMPLE CME FINANCING TIMELINE

SHIPOWNER

CME

WÄRTSILÄ

INITIALIZATIONPHASE

YEAR 0 YEAR 1 YEAR 2 YEAR 3 YEAR 4 YEAR 5

€ € € €

TITLE TO EQUIPMENT€

INSTALLATION

© Wärtsilä10

SHARED SAVINGS MODEL: PRE AND DURING ECSA

Fixed Fuel Adder

Add’l OPEX from EGCS system

Savings shared with ship owner

• Ship-owner receives immediate fuel cost savings in Year 1, as well as ECA compliance

• Transition of capex to OPEX for the ship-owner; shared savings = annuity for investors

0 1 2 3 4 5 6Year

HFO

MGO

An

nu

al

Fu

el

Co

st

Insta

llatio

n

ECSA Term

4 November 2016 Wärtsilä Scrubber Retrofit 2016

© Wärtsilä

RETROFIT REFERENCE EXAMPLE

4 November 2016 Wärtsilä Scrubber Retrofit 201611

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 201612

COLOR LINE: SUPERSPEED 2

RoRo / passenger vessel

operating 100% within

SECA

• 4 x 9.45MW Wärtsilä

• Retrofit: space limitations

in funnel

• Wärtsilä inline scrubber

installation in March 2014

at FaYard

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 201613

SUPERSPEED 2 – SCRUBBER SETUP

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 201614

SUPERSPEED 2 – DEMOLITION

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 201615

SUPERSPEED 2 – INSTALLATION ON BOARD

© Wärtsilä 4 November 2016 Wärtsilä Scrubber Retrofit 201616

• Wärtsilä can provide different supply scopes from ”equipment only” (with or without engineering) to full ”retrofit EPC” delivery

• Vessel survey followed by a comprehensive technical feasibility study assures optimal scrubber system integration into the vessel

• Proven track record of successfully delivered turnkey projects guarantees peace of mind and one stop shop for the customer

– Global manufacturing and support capabilities

SUMMARY