MLA – August 2017
Bathurst Inlet – August 2017
9 person temporary camp established August 2017
Ice Air Strip on Bathurst Inlet: Early-Mar 2018
100 Air freight flights including Hercules, ATR, 737 & Dash 7 aircraft
28 Hercules Air Transport Flights transporting MLA Camp, Temporary fuel Tanks & Construction Equipment
5000 Foot Air strip on Bathurst Inlet
Establishing a “Toe-hold” at MLA: Mar 2018
Unloading supplies on the ice Personnel Transport to MLA
45-Person CampFit for Purpose Dining Facility
Drill & Blast at the MLA Quarry: Apr 2018
Development Earthworks begin to support exploration and future development activities
6
Quarry
A-N storage road
Camp
Road works
Fuel Storage
Quarry
A-N storage
Quarry & Earthworks Construction at MLA – Apr 18
8
Completed Permanent 45 Person Camp at MLA
Completed Temporary Fuel Storage Depot at MLA
Completed Pad for Permanent Fuel Tanks - MLA
10
MLA June 2018 – Approximately mid-way through construction
11
From “pioneering” to finished works in 5 months
Aug 2018
Aug 2017
Staging / Loading Sealift at Hay River – July 2018
13
Equipment Loading at Hay River July 2018
14
Barges Loading at Hay River – July 2018
15
Barge Loading at Hay River – July 2018
16
Barges Loaded and ready for sealift – July 2018
17
First Barges received and unloaded – August 13 & 14, 2018
18
Barge Unloaded and Equipment Stored at MLA – August 2018
19
Equipment At MLA – August 2018
20
21
Equipment Stored at MLA- August 2018
Completed MLA – August 2018
22