EMCal Meeting Nantes – July 15-17 2008 1 J-F Muraz

Grenoble Status

Assembly and test Hall.

Page 2: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 2 J-F Muraz

Grenoble Status

Trigger support structure.

- Done for Yale and Grenoble assembly sites.

Page 3: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 3 J-F Muraz

Grenoble Status

Trigger light guides.

- delivered.

- Ready to be glued to scintillators produced by Yale

Page 4: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 4 J-F Muraz

Grenoble Status

Test bench electronic setup.

PMT DFC

x32

Delay

ADC TDC

VME

NIM

CAMAC

EMCal FEE

…Trigger module

Transl.

CCUSB DAQ/PC

Delay

Analog

splitter

To be delivered

Page 5: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 5 J-F Muraz

Grenoble Status

DAQ.

- DAQ installed by Terry and David last week

Page 6: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 6 J-F Muraz

Grenoble Status

4 SM Platforms:

- Done.

- Successfully load tested and certified.

- Delivery expected next week. (after painting!)

Page 7: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 7 J-F Muraz

Grenoble Status

Strip handling tools.

- By the end of July, I will send to YALE:

- 1 Strip handling tool fully equipped.

- 1 Strip handling tool support frame.

- all trigger scintillator support and positioning structure.

Page 8: Assembly and test Hall

EMCal Meeting Nantes – July 15-17 2008 8 J-F Muraz

Grenoble Status

Strap Foils.

- 3600 precutted (Full EU production : 3 SM)

- 1200 machined and cleaned (1 SM)

Hand precutting station Final cleaning

Wire cutting operation(80 straps stack)